A PERT chart presents a graphic illustration of a project as a network diagram consisting of numbered nodes (either circles or rectangles)
representing events, or milestones in the project linked by labelled vectors (directional lines) representing tasks in the project. The direction of the
arrows on the lines indicates the sequence of tasks. In the diagram, for example, the tasks between nodes 1, 2, 4, 8, and 10 must be completed in
sequence. These are called dependent or serial tasks. The tasks between nodes 1 and 2, and nodes 1 and 3 are not dependent on the completion of
one to start the other and can be undertaken simultaneously. These tasks are called parallel or concurrent tasks. Tasks that must be completed in
sequence but that don't require resources or completion time are considered to have event dependency. These are represented by dotted lines
with arrows and are called dummy activities. For example, the dashed arrow linking nodes 6 and 9 indicates that the system files must be converted
before the user test can take place, but that the resources and time required to prepare for the user test (writing the user manual and user training)
are on another path. Numbers on the opposite sides of the vectors indicate the time allotted for the task.
The PERT chart is sometimes preferred over the Gantt chart, another popular project management charting method, because it clearly illustrates
task dependencies. On the other hand, the PERT chart can be much more difficult to interpret, especially on complex projects. Frequently, project
managers use both techniques.
PRO+
Content
E-Handbook
E-Handbook
E-Handbook
Here are some additional resources for learning about how PERT charts and other project management tools are used in the enterprise:
Project management tools and strategies: The Gantt chart and the PERT chart are probably the two best known charts in project management.
Each of these can be used for scheduling, but because Gantt charts don't illustrate task dependencies and PERT charts can be confusing, PMs
often use both.
Project management charts: Beyond Gantt: Gantt charts are good for certain purposes, explains project management expert David Christiansen,
but there are other charts PMs have at their disposal.
This was last updated in May 2007
∙
m Continue Reading About PERT chart (Program Evaluation Review Technique)
Critical Tools provides a PERT chart product.
Related Terms
Gray box testing, also called gray box analysis, is a strategy for software debugging based on limited knowledge of the internal ... See complete definitionq
Load More
z 2 comments Oldest 5
Register or Login
email@techtarget.com
Username / Password
Username
Password
Comment
By submitting you agree to receive email from TechTarget and its partners. If you reside outside of the United States, you consent to having your personal data transferred to and processed in the
United States. Privacy
t
Doesn't seem to be compatible with Agile methods. No iterations. Unclear how a feedback is propagated, if there's any.
t
-ADS BY GOOGLE
SOA JAVA CLOUD APPLICATIONS AWS BUSINESS ANALYTICS FINANCIAL APPLICATIONS HEALTH IT
5
SearchSOA
A hackathon can do more than showcase cool apps. It can teach us about the developer community. This Q&A examines a ...
At no time in the evolving and accelerating world of applications development is there a greater need for enterprises to employ ...
About Us Contact Us Privacy Policy Advertisers Business Partners Media Kit Corporate Site Experts