Professional Documents
Culture Documents
PUMP Manual Erection Kalwakur
PUMP Manual Erection Kalwakur
KALWAKUR, C-01-987226-085
Personal The following protective equipment must be worn when carrying out
protective apparel installation and transport work:
• Hard hat
• Protective gloves
• Safety shoes
• Eye protection
5.3 Transportation
5.4 Storage
The following instructions must be observed if the system is not to be
installed immediately:
• Please inform the ANDRITZ shipping department.
• Provide weather protection for stored machine components. In
particular, avoid wide variations in temperature and ensure that the
equipment is kept clean.
• Small items should be protected against damage and unauthorized
withdrawal by storing in a lockable room.
• Packaging should not be removed until field installation work begins.
5.5 General
General
Preparations Foundation
Foundation prepared according to the ANDRITZ foundation plan.
The following preparations have to be made to the foundation prior to
erecting the equipment:
• Mark axes and elevations on the foundation.
• Check the workmanship of the foundation before beginning erection
work.
Preservation
Corrodible machine parts are protected with "Cortec VCI 369"
preservative grease.
The preservative grease need not be removed.
Welding
5.6.1 Drawings
5.6.3 Weights
Weights:
Draft tube liner . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4,600 kg
The draft tube liner is to be erected according to the following table:
Step Activity
1 Attach supporting spindles (27a) to the draft tube liner (27).
2 Suspend draft tube liner from the crane with suitable ropes at
the suspension lugs (27.b).
3 Raise draft tube liner into the mounting position and place on
the foundation plates (27c).
4 Attach turnbuckles (27d) between anchor plates (27e) and
draft tube liner and weld on.
5 Align draft tube with the supporting spindles (27a) and the
turnbuckles (27d) according to the drawings mentioned.
6 Mount drainage pipe (27f).
7 Weld on supports (27g) to secure in mounting position.
8 Inspect and record mounting position and shape of flange
(27h).
9 Mount the shuttering as shown in the foundation drawing.
10 Mount the foundation plates for the spiral casing.
11 Cast draft tube liner in concrete according to the foundation
drawings and Section 5.6.2.
Tab. 5-1 Erection of the draft tube liner
27h X 27
27b
27d
27e
27b
27a
27g 27c
27f
1
27e 27g 27c
View X
27g
27d
27d
27g
Relevant drawings:
Spiral casing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 0HP 108932
Weights:
Spiral casing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19,200 kg
Welding of the The spiral casing is delivered in two parts and welded together on site.
spiral casing
Attached document:
Inspection plan . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4HP 108314
Erection work The spiral casing is to be mounted according to the following table:
Step Activity
1 Insert threaded bolt (1a) and levelling spindles (1b).
2 Attach supporting spindles(1c) to the spiral casing (1).
3 Raise spiral casing into the mounting position and place on
the foundation plates (1d).
4 Align spiral casing with the supporting spindles (12) and the
levelling spindles (1b) according to the drawings mentioned
and bolt together (1a).
5 Inspect and record the installation position of the spiral casing.
Tab. 5-2 Erection of the spiral casing
1b
1c 1c
1a
1d 1d
Relevant drawings:
Pressure test - spiral casing . . . . . . . . . . . . . . . . . . . . . . 1HP 109142
Press-on cover . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3HP 109144
The pressure test for the spiral casing is to be conducted according to the
following table:
Step Activity
1 Mount pressure testing device (1e) and test head (1f) with the
required seals.
2 Remove screw plug from the vent hole (1g) and connect up
pressure source to the connection (1h) at the test head.
3 Fill spiral casing with water and close vent hole (17).
4 Apply the necessary test pressure and pressure-test the spiral
casing against the test data.
5 The pressure testing device remains mounted during
subsequent casting of the spiral casing in concrete and the
spiral casing is filled with water without pressure.
Tab. 5-3 Pressure test - spiral casing
1e 1g
1f
1h
Weights:
Pit liner . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5,300 kg
The pit liner is to be erected according to the following table:
Step Activity
1 Suspend pit liner (4) from the crane using appropriate lifting
gear and ropes.
2 Raise pit liner into the mounting position and place on the
spiral casing (1).
3 Align pit liner according to the drawings mentioned and weld
to the spiral casing (4a).
4 Mounting the shuttering and pipework and making the cutouts.
5 Cast spiral casing (1) in concrete according to the foundation
drawings and Section 5.6.2.
Tab. 5-4 Erection of the pit liner
4a
27
Fig. 5-5 Mounting the pit liner and concreting the spiral casing
27
Fig. 5-6 Concreting the pit liner and the motor foundations
Relevant drawings:
Guide vane mechanism. . . . . . . . . . . . . . . . . . . . . . .0HP 109186, 1-3
Sequence of erection work . . . . . . . . . . . . . . . . . . . . . . . . 701624041
Bottom guide vane ring (6) . . . . . . . . . . . . . . . . . . . . . . . OHP 109125
Top guide vane ring (7) . . . . . . . . . . . . . . . . . . . . . . . . . . OHP 109131
Guide vane (5). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OHP 108278
Operating ring (18) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . OHP 108980
Clamping ring . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2HP 109135
Straps for the operating ring . . . . . . . . . . . . . . . . . . . . . . 2HP 109071
Weights:
Bottom guide vane ring (6) . . . . . . . . . . . . . . . . . . . . . . . . . . 4,200 kg
Top guide vane ring (7) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4,040 kg
Guide vanes (5) . . . . . . . . . . . . . . . . . . 24 vanes weighing 90 kg each
Operating ring (19) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2,650 kg
Clamping ring (28) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 130 kg
Straps for the operating ring . . . . . . . . . 2 rings each weighing 108 kg
Inspection of the Before mounting the guide vane mechanism, the contact surfaces for the
spiral casing guide vane rings and the position of the draft tube liner, Fig. 5-7, must be
inspected and recorded.
Tolerances according to drawing:
Spiral casing. . . . . . . . . . . . . . . . . . . . . 0HP 108932, page 1, detail Z
5 5
6a
6
27
29,30
30
29
Fig. 5-9 Erection of guide vane mechanism - connection to draft tube liner
Step Activity
4 Suspend top guide vane ring (7) from the crane and lift into the
mounting position.
5 Centre the two guide vane rings using the guide vane bores
and bolt to the spiral casing.
17 18
Step Activity
7 Mount guide vane bearing assemblies according to Fig. 5-11.
8 Check gap between the guide vanes (5) and the protective
walls (1a) of the spiral casing.
9 Check mobility of the guide vanes and bearing play at the
guide vane bearing assembly.
10 Suspend operating ring (18) from the crane and lift into the
mounting position.
11 Place the balls in the bearing (19) and fill with mineral
oil-based roller bearing grease. (e.g. Mobilux EP2)
12 Mount clamping ring (17).
18 19 17 17a
1a
Fig. 5-11 Erection of guide vane mechanism - guide vane bearing assembly
Step Activity
13 Install split ring (4) in the bottom guide vane ring (6).
14 Lift the impeller (2) into position and place on the spacer
plates.
S1 = 1mm
Tab. 5-9 Split ring and impeller
4 6
2
4
s1
Pump cover
Step Activity
16 Install pump cover (37).
17 Check the gap between the impeller and the pump cover.
S2 = 1mm
Tab. 5-10 Pump cover
s2
37 2
Step Activity
18 Mount guide vane levers (12) and guide vane links (15,16).
15,16 12 12a
Fig. 5-14 Installation of guide vane mechanism - guide vane levers and guide vane links
Servo-cylinder
Step Activity
21 Mount servo-cylinder (12).
22 Set open and closed position of the guide vane mechanism by
machining the fitting plate (33) and the stop ring (36)
accordingly.
Tab. 5-12 Installation of guide vane mechanism - servo-cylinder
36 31 33
33
36
Fig. 5-15 Installation of guide vane mechanism - servo-cylinder
Guide vane
locking plate
Step Activity
23 Adjust guide vane locking plate (21) to the operating ring.
Tab. 5-13 Mounting of guide vane mechanism - locking plate
21b
21
21a
Adapt to fit
Sensors
Step Activity
24 Mount and set sensors for guide vane locking plate.
21d
21c
Fig. 5-17 Mounting of guide vane mechanism - sensors
23a
23
25
26
Fig. 5-18 Guide vane mechanism - scale and angle of rotation transmitter
Relevant drawings:
Guide bearing and shaft seal . . . . . . . . . . . . . . . . . . . . . . 0HP 109357
Pump shaft . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 0HP 109537
Lifting device for the shaft . . . . . . . . . . . . . . . . . . . . . . . . . 701665894
Mounting the impeller and the shaft . . . . . . . . . . . . . . . . . . 701624042
Weights:
Pump shaft (50) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7,830 kg
Lifting device for the shaft . . . . . . . . . . . . . . . . . . . . . . . . . . . . 100 kg
Corundum coating The torque is transferred from the impeller to the shaft by adherence and
on the pump shaft pre-tensioned bolts. In order to increase the friction coefficient, the contact
surface on the flange of the pump shaft is coated with corundum.
Step Activity
1 Clean and degrease contact surfaces at the impeller and the
shaft
2 Use a spray gun with a nozzle diameter of 1.8 - 2 mm to apply
the corundum coating.
3 Prepare a mixture of three parts zapon varnish (nitrocellulose
lacquer) to one part corundum powder (silicon carbide, grain
size 160 - 180 microns) suitable for spraying.
4 Test the mixture by spraying it very thinly onto an upright,
bright-finish metal plate.
c
a x
Bolted connection The shaft (50) and the impeller (2) are bolted together using anti-fatigue
betweens shaft bolts and SUPERBOLT mechanical tensioners.
and impeller
Step Activity
1 Screw in anti-fatigue bolts (55).
2 Suspend shaft (50) from the crane using the lifting device and
lift into the mounting position.
3 Mount SUPERBOLT mechanical tensioners (55a).
4 Tighten mechanical tensioners according to SUPERBOLT
instructions and the pre-tensioning values stated.
50
55a
55 2
Shaft components
Step Activity
1 Secure cover (59) with cheese head screws and sealing rings.
2 Lift 2-part shaft protection sleeve (56) into the mounting
position and clamp onto the shaft using using the clamping
rings (57,58).
Tab. 5-17 Erection of shaft components
57 58 56
59
50
Relevant drawings:
Guide bearing and shaft seal . . . . . . . . . . . . . . . . . . . . . . 0HP 109357
Step Activity
1 Lower sealing ring 1 (61) and sealing ring 2 (60) onto the top
guide vane ring (7) with the maintenance seal (63) in place
and bolt together (60a).
2 Lower support ring (62) onto the sealing ring 2 (60) and bolt
together (62a).
Tab. 5-18 Mounting the maintenance seal
62a 56
62
60a
63
60
61
Relevant drawings:
Guide bearing and shaft seal. . . . . . . . . . . . . . . . . . . . . . 0HP 109357
Bearing support (66) . . . . . . . . . . . . . . . . . . . . . . . . . . . . OHP 109270
Guide bearing . . . . . . . . . . . . . . . . . . . . . . . . .V/0/231135 (MICHELL)
Weights:
Bearing support (66) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 700 kg
Guide bearing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1780 kg
Bearing support
Step Activity
1 Lower the bearing support (66) onto the spiral casing (1) and
bolt together.
Tab. 5-19 Mounting the bearing support
66
Guide bearing
Step Activity
1 Lower the bearing housing (66a) onto the bearing support (66)
and bolt together.
2 A description of further steps for installation of the guide
bearing (67) can be found in the drawings and installation
instructions provided by the bearing manufacturer.
see .../SUPPLIER DOCUMENTATION/MICHELL
Tab. 5-20 Mounting the guide bearing
66a
67
Relevant drawings:
Bearing and brake . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 0HP 109358
Bearing support . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 0HP 109124
Thrust bearing . . . . . . . . . . . . . . . . . . . . . . .MV/0/231151 (MICHELL)
Weights:
Bearing support (73). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3,890 kg
Bearing support
Step Activity
1 Screw in adjusting screws (73a) and lift the bearing support
(73) onto the pit liner (4).
2 Set the vertical spacing to the shaft (50) according to the
assembly drawings using the adjusting screws (73a).
3 Measure spacing between bearing support (73) and pit liner
(4) and machine the fitting plates (74).
4 Raise bearing support, insert fitting plates (74), and lower the
bearing support onto the fitting plates.
5 Remove adjusting screws (73a) and centre the bearing
support in line with the impeller axis.
6 Secure the bearing support in position with taper pins (73b).
50 73
73
74
4 74
Fig. 5-29 Mounting the bearing support
Step Activity
1 A description of how to install the bearing (75) can be
found in the drawings and installation instructions
provided by the bearing manufacturer.
see .../SUPPLIER DOCUMENTATION/MICHELL
Tab. 5-22 Mounting the thrust and guide bearing
75
Relevant drawings:
Bearing and brake . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 0HP 109358
Lapped flange . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2HP 109286
Connection between motor shaft and pump shaft . . . . . . 2HP 108998
Lifting device ( . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .701665894)
Weights:
Lapped flange (86) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1,164 kg
Mounting the
lapped flange
Step Activity
1 Insert fitting key (86a) into the shaft (50) and bolt together.
2 Lower lapped flange (86) onto the shaft.
Tab. 5-23 Mounting the lapped flange
50
86
86a
50
Corundum coating The torque is transferred from the motor to the lapped flange by
of lapped flange adherence and pre-tensioned bolts. In order to increase the friction
coefficient, the contact surface on the lapped flange of the pump shaft is
coated with corundum.
Step Activity
1 Clean and degrease contact surfaces at the lapped flange and
the motor.
2 Use a spray gun with a nozzle diameter of 1.8 - 2 mm to apply
the corundum coating.
3 Prepare a mixture of three parts zapon varnish (nitrocellulose
lacquer) to one part corundum powder (silicon carbide, grain
size 160 - 180 microns) suitable for spraying.
4 Test the mixture by spraying it very thinly onto an upright,
bright-finish metal plate.
Step Activity
1 Measure and record space (x) between shaft surface (50) and
surface of loose flange (86).
2 Use a lathe to turn the shoulder (Y) on the plate (87)
according to the drawing.
Y = X +0.15/+0.05
3 Bolt the plate (87) to the pump shaft (87a).
87a
87
86
50
Mounting the A description of how to install the motor can be found in the
motor drawings and installation instructions provided by the motor
manufacturer.
see .../SUPPLIER DOCUMENTATION/ABB
Bolted connection The shaft (50) and the motor (90) are bolted together using anti-fatigue
between shaft and bolts and SUPERBOLT mechanical tensioners.
motor
Step Activity
1 Mount anti-fatigue bolts (88) with nuts (89) and mechanical
tensioners (88a).
2 Tighten mechanical tensioners according to SUPERBOLT
instructions and the pre-tensioning values stated.
(M48x5)
Bolt pre-tensioning force . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .700 kN
Tensioning torque . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 131 Nm
90 89
88
88a
50
Brake
Step Activity
1 Mount brake (94), mounting plate (93) and brake disc (95),
then set in position.
95 95a 94 93
93b
95b
93a
94a
Fig. 5-35 Brake - Step 1
95 94 93
93b
Relevant drawings:
Guide bearing and shaft seal . . . . . . . . . . . . . . . . . . . . . . 0HP 109357
Mechanical seal, 510mm . . . . . . . . . . . . . D/65388.01B (John Crane)
Erection work The mechanical seal is mounted after installation and setting of the shaft
bearings.
5.13 Connections
Pipework All connections and connecting dimensions at the pump are shown in the
diagrams and assembly drawings.
• Cooling water pipes for the bearings
• Sealing water lines for the shaft seals
• Jacking station for the thrust bearing
• Relieving line from the pump cover to the suction pipe
• Seepage water pipes from the shaft seal
• Compressed air line for the maintenance seal
Hydraulics
• First filling of the hydraulic plant
Cold test The cold test is to be carried out in the presence of an authorized
representative of the customer.
Final inspection The customer and the site manager shall conduct a final inspection of the
installation after completion of the cold tests.
Certificates The following certificates are issued after completion of the ISO cold test:
• Cold test certificate
• Certificate of completion of erection work