Date 06/12/2019.

Field Name: ABIGBORODO


PETINENT DATA: JACKET: 01 BARGE: SIRPI FJORD./CO/NAME : BENEK
TEL(FAX) CAPT/CO-MAN: FOLARIN

SINGLE DUAL
WELL NAME INITIAL FINAL FINAL INITIAL
PRESS

TREE SIZE 3-1/8 mod B


FTHP/FLP

TREE TYPE Vetco Gray 1500psi 1500psi 1700psi 1700psi


SITHP

BASE MANAGER Clifford Odia CHP:A/B 0psi /0psi


BENEK TEAM DIGA PHILIP/ not ok ok
ONWUFUJU C LMV

WV ok not tested
FLOWLINE PLUG VALVE UMV ok ok
CONTROL PILOT SETTING SV ok ok

POB 2 SCSSV
TEST
SDV ok not tested

START FINISH DESCRIPTION : Zonal Isolation


0600hrs 0630hrs Attended Safety meeting with focus on OE Tenent 6 , Topic - Water Pollution
0700hrs 0735hrs Recording of initial CHP =0psi and initial SITHP for Short String = 1700psi , and Long String= 1500psi ,

1030hrs 1120hrs
Load out of Side door lubricator (Equip ID:SDLUB 002) into Jascon 7 for onward movement to
escravos for servicing. ( Note: Side door lubricator was placed inside Zukus Wireline unit.)

1330hrs 1750hrs Wireline Operation Support


1750hrs 1820hrs Recording of Final CHP = 0psi Final SITHP for Short String = 1700psi , and Long String= 1500psi
1830hrs Shutdown for the days activity
BENEK

Remarks
FINAL

Otis

ution
nd Long String= 1500psi ,

onward movement to
us Wireline unit.)

ng String= 1500psi