M6 Furnace Repair Work Tentative Schedule

Duration Aug-19
# Activity Days 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
1 Cooling Off 5
2 Billet Removal 1
3 Mobilization 1
4 Set-up 1
5 Demolition
5.1 Bullnose 2
5.2 Side Wall (M.S.- S.Z.) 1
6 Formwork Prefabrication 2
7 Install Anchor Bricks 1
8 Install Formworks 1
9 Casting 1
10 Curing 1
11 Formwork Removal 0.5
12 Clearing/Housekeeping 0.5
13 Demobilization 1
14 Preheating/ Sintering 5
Furnace Repair Works Monitoring Sheet

Item Started Completed


# Activity Date Time Date Time Remarks