3. Company has a plant for meat processing. The factory can produce 4,700 packs per
day. The effective capacity is 4,300. The actual output is 4,076 packs. The factory has 5
production lines which operate 6 days per week (6 th day is half-day), with one 8-hour shift per
day. Compute for the following: (12 points)