,..), thea, by Bayes’ theorem, the updated
probability of crown collapse due to the presence of a fault
zone would be 65%:
0.18 x0.85
0.2350
= 06511 as)
here the updated probability of failure due to a fault zon
(current probability of failure due to poor rock—eg. fault
zone) x (probability of intersecting poor-quality rock if fat
exists) + (Current probability of encountering poor-quality
rock). I however, the core drilling proved that rock com-
petence was high throughout the pillar, the updated proba-bility oF failure due toa faule would be only about 2%:
018x010
0235 an
0.7650
where the updated probability of failure due 10 a fault
(current probability of future due to poor rock—e.g. a faut
zone) x (prababilty of not intersecting poor-quality rock as
no fault zone exists) « (current probability of not imersecting
‘poor-quality rock),
Ifthe mine did dlecide to undertake the core driling and it
showed that the rock quality was indeed poor (a 24%
chance), what would be the most cost-effective decision?
Using the updated probability of failure for collapse of the
crown pillar, dhe expected costs for the two options that are
being considered would be calculated as follows,
Fencing Fencing costs $100 000 to install and has @ (1 ~
0.6511 = 0.3489) chance of success with @ 25% of 65.11%
chance that a collapse could break through and affect the
highway, thereby incurring additional expenditure of
'$8 000 000. Thus, the total weighted cost is $100 000 +
(0.25 x 0.6511 > $8 000 000) = $1 402 200.
Backfill Backilling costs $1 000 000 and provides 100%
security, giving arora weighted cost of $1 000 000,
Obviously, with poor rock conditions proved by the drilling,
‘backfling becomes the more cost-effective approach
senso POF
ITEROALLNG
swat POF
Fae T vEsTCaTON
PROBABLTY OF FLRE 1,1
ace ouALiTy
Arevsen a
maak
Fig 11 Conceprus) changes in probability distbusion with
‘improved undemanding of rock “quality as consequence of
addiuona investigation. PDF, probably density function
If, on the other hand, as suggested by the original proba-
Dility distribution (shown diagrammatically in Figs. 6 and
11), the drilling did not find poor rock within the pillar (a
76.5% likelinood—P,.4) the updated decision analysis
would suggest the following.
Fencing Cost, $100 000, with (1 ~ 0.0235 = 98%) chance
fof success and only 25% of 2.35% chance of incurring
Additional expenditure of $8 000 000. Thus, total weighted
‘ost = $109 000 + (0,25 x 0.0235 x $8 000 000) = $147 200.
Backfill Cost, $1 000 000; security, 100%; giving total
weighted cost of $1 000 000.
Clearly, proof that good rock existed in the crown pillar
would considerably reduce the weighted risk-based cost. The
rine would therefore be even more justified in opting simply
to fence off the area ofthe hazard.
Is the driling information worth che expendinure? The
previous analysis showed that ifthe drilling were not cazried
fut, the optimal decision would be to fence the site at an
expected cost of $460 000. If drilling is undertaken, the
optimal decision depends on the outcome: ifthe rock quality
is poor, the best choice isto backfill if tis good, a fence i
the most sensible option, The overall expected cost if the
Grilling were to be carried out would be: weighted cost of|
Alling = (cost of investigation) ++ (weighted cost of poor
ground) + (weighted cost of good ground)—i.
'$50 000 + (0.2350 x $1 000 000) +
(0.7650 x $147 200) = $397 608
‘Thus, the drilling program would be a good investment as it
‘would reduce the overall expected cost from $460 000 to
$397 608.
Assessment of uncertainties
‘The approach presented above, while straightforward in
concept, makes assumptions of representativencss that the
[parameters truly reflect actual conditions. However, as is
‘evident from the example, a large degree of uncertainty
results simply ffom lack of detailed knowledge of crown
‘conditions. Only by gaining improved information from
detailed field investigation is it possible to reduce this type
fof uncertainty. In such critical situations enough data
‘must be collected that the uncertainty is reduced 10 that
arising from the true variability in rock mass conditions
Gig. 12),
wn
SITE INVESTIGATION
EXPENDITURE
wweemTany
Fig. 12. Relationship between uncerninses due to natural
vatabilty and data inadequacies as function of data accuracy and
cost of site investigations. J, Uncertainty due wo ignorance and eos
and insecraces in data; 2, uneerainy due to wue variation in rock
sass and geomewe factors
‘As can be seen, formal techniques of decision analysis are
‘merely aid to the making of explicic decisions on the basis of
4 careful analysis of the problem at hand.*! In principle, all
ASSsuch decisions are simple: the real difficulties lie in ensuring
that the initial database is valid and in developing a full
‘understanding ofthe ramifications ofthe decision. Once that
understanding is reached and the reliability of the database
has been verified the decision may be readily apparent. In
fac, the general techniques illustrated here merely formalize
jn mathematical terms the judgments that go into making
any reasonable decision. Bayes" theorem and the principles
of decision analysis are the mathematical expressions of
‘common sense and judgment.
Decision analysis can be of great value in reducing
apparently very complex decisions to more manageable parts
and in providing a more balanced perspective on. the
advantages and disadvantages of @ decision. However, it
rust be appreciated that itis easy to be misled by a decision
analysis that embodies false premises, In considering stopes,
like those in the example, that were directly adjacent to
hhighway one would want to think Jong and hard before
committing expenditure to a fencing-only option unless
driling had been undertaken that had proved good-quality
rock in the pillar area. Where decisions affect lives other
prions always need to be explored. In such cases not only
should the cos alternatives be verified but 0, 190, should the
jeomechanical factors thet form the basis for the decision-
‘making. Any of these issues could, if overlooked, invalidate
the analysis—with catastrophic consequences, as actually
‘occurred in the case example, where one particularly weak
zone controlled che overall behaviour characteristics,
Another complication for effective decision-making—
although usually of a more minor narure—is inaccuracy in
the estimating. Although the associated uncertainties can
usually be ignored in deriving overall cost estimates for pre-
liminary decision-making, it should be appreciated that at
times wrong decisions can be made as a resule of such un-
certainties or because of wide error margins in the costings
‘Typically for the level of costing required for the ‘ype of
decision analysis that has been discussed i is rare that there
is a nced 0 extend the accuracy beyond @ Class C estimate
(ie. 425% accuracy). Costs can therefore usually be based
fon previous practice and experience. This issue, however,
‘becomes significant when lite cost differential separates the
various alternatives. In these cases itis worth undertaking
‘more detailed estimating since costs developed from base-
case information (derived from applicable labour and
‘material rates) usually allow the error band of uncertainty to
be reduced significantly, as indicated in Table 4.
Table 4 Usual levels of acceptable accuracy for cost.
estimating purposes
Class Accuracy, % Estimate
"Binal construction tender
Deign-evel engineering
Feasibility or prefeastbity level
ome
Nevertheless, even with these provisos, for crown-pillar
work all estimating of costs should be considered very
tentative as actual remediation costs can vary dramatically
‘owing to the unforeseen cor “cations that can atise when
the work is in progress.2® In ny eases where itis evident
that remediation will be difficult it is wise to consider
undertaking detailed contingency costing as well as base-case
costing when preparing final decsion-matsix tabulations,
56
Conclusions
Establishing the stability and deciding whether remediation
is required to ensure the long-term integrity of surface crown,
pillars over active or abandoned near-surface mine workings
ccan be a complex task. However, the application of risk:
bbased decision-making procedures can assist significantly in
the rational costing and selection of remediation alternatives
s0 that a beer evaluation can be made of options for