You are on page 1of 14

Eng. & Technology, Vol.25, No.

1, 2007

Early Manufacturing Cost Estimate For Mechanical Parts

Khalid Karam Abd*


Received on: 29/ 1/2006
Accepted on: 23/11/2006
Abstract
In manufacturing environment cost estimates process is made in all stages of
product development from research to final product. Good estimating
techniques and procedures are necessary for each manufacturing stage. When
properly implemented, these techniques produce acceptable operational
estimates that are useful to management for decision-making.
In this research, an algorithm is developed to build system is called
FBMCE (Feature-Based Manufacturing Cost Estimate) to incorporate making
decisions integrating design, process planning and manufacturing for cost
estimate purposes. The FBMCE system has been tested on product (Shaft 8E -
200) in State Company for Electrical Industries and showed promising results.

Keywords: cost estimation, feature-based, process planning


‫ﺍﻟﺨﻼﺼﺔ‬
‫ﻋﻤﻠﻴﺔ ﺘﺨﻤﻴﻥ ﺍﻟﻜﻠﻔﺔ ﻓﻲ ﺍﻟﺒﻴﺌﺔ ﺍﻟﺘﺼﻨﻴﻌﻴﺔ ﺘﻤﺭ ﻓﻲ ﻜل ﻤﺭﺍﺤل ﺘﻁﻭﻴﺭ ﺍﻟﻤﻨﺘﺞ ﻤﻥ ﻤﺭﺤﻠﺔ ﺍﻟﺒﺤﺙ ﺍﻟﻰ‬
.‫ ﺍﻥ ﺘﻘﻨﻴﺎﺕ ﻭﺨﻁﻭﺍﺕ ﺍﻟﺘﺨﻤﻴﻥ ﺍﻟﺠﻴﺩﺓ ﻀﺭﻭﺭﻴﺔ ﻓﻲ ﻜل ﻤﺭﺍﺤل ﺍﻟﺘﺼﻨﻴﻊ‬.‫ﻤﺭﺤﻠﺔ ﺍﻟﻤﻨﺘﺞ ﺍﻟﻨﻬﺎﺌﻲ‬
‫ ﻓﺎﻨﻬﺎ ﺘﺅﺩﻱ ﺍﻟﻰ ﺘﺨﻤﻴﻥ ﻤﻘﺒﻭل ﻟﻤﺼﺎﺭﻴﻑ ﺍﻟﺘﺸﻐﻴل‬،‫ﻭﻫﺫﻩ ﺍﻟﺘﻘﻨﻴﺎﺕ ﻋﻨﺩ ﺘﻨﻔﻴﺫﻫﺎ ﺒﺸﻜل ﻤﻨﺎﺴﺏ‬
.‫ﻭﺍﻟﺘﻲ ﺘﻔﻴﺩ ﺒﺎﺘﺨﺎﺫ ﺍﻟﻘﺭﺍﺭﺍﺕ‬
‫ )ﺘﺨﻤﻴﻥ ﻜﻠﻔﺔ ﺍﻟﺘﺼﻨﻴﻊ ﺒﺎﻻﺴﺘﻨﺎﺩ‬FBMCE ‫ﻓﻲ ﻫﺫﺍ ﺍﻟﺒﺤﺙ ﺘﻡ ﺘﻁﻭﻴﺭ ﺨﻭﺍﺭﺯﻤﻴﺔ ﻟﺒﻨﺎﺀ ﻨﻅﺎﻡ ﻴﺩﻋﻲ‬
‫ﺍﻟﻰ ﺍﻟﺴﻤﺔ( ﻭﺍﻟﺫﻱ ﻁﻭﺭ ﻻﺘﺨﺎﺫ ﺍﻟﻘﺭﺍﺭﺍﺕ ﺤﻭل ﺍﻟﺘﻜﺎﻤل ﺒﻴﻥ ﺍﻟﺘﺼﻤﻴﻡ ﻭﺘﺨﻁﻴﻁ ﺍﻟﻌﻤﻠﻴﺔ ﻭﺍﻟﺘﺼﻨﻴﻊ‬
‫( ﻓﻲ ﺍﻟﺸﺭﻜﺔ ﺍﻟﻌﺎﻤﺔ‬Shaft 8E - 200) ‫ ﺘﻡ ﺍﺨﺘﺒﺎﺭ ﺍﻟﻨﻅﺎﻡ ﻋﻠﻰ ﺍﻟﻤﻨﺘﺞ‬.‫ﻟﻐﺭﺽ ﺘﺨﻤﻴﻥ ﺍﻟﻜﻠﻔﺔ‬
.‫ﻟﻠﺼﻨﺎﻋﺎﺕ ﺍﻟﻜﻬﺭﺒﺎﺌﻴﺔ ﺤﻴﺙ ﺍﻅﻬﺭ ﺍﻟﻨﺘﺎﺌﺞ ﺍﻟﻤﺭﺠﻭﺓ ﻤﻨﻪ‬

1- Introduction process selection, and basic


Most Computer-Aided Design manufacturing engineering processes
(CAD) and Computer-Aided and technology. Nevertheless,
Manufacturing (CAM) tools are computer-aided tools for integrated
applied to improve detailed design conceptual design and process
and detailed manufacturing planning, planning are still far from being
but not conceptual design, which satisfactory in real-world applications
usually does not include functions, [2]. The reason is a lack of theoretical
behaviours, form, structure, foundations to characterize the
tolerances, and surface conditions that process of early product design and
determine manufacturing methods and the integration of various functions
cost [1]. and technologies for effective product
In design engineering research, design[1,2]
some researchers have proposed
methods for cost estimation, material
Dept. of Production Eng. & Metallurgy, UOT., Baghdad, IRAQ.

103
Eng. & Technology, Vol.25, No.1, 2007 Early Manufacturing Cost Estimate
For Mechanical Parts

Figure (1) illustrates many Simpson proposed a production cost


stages of communication that can model based on a production cost
exist when establishing framework associated with the
interoperability between design and manufacturing activities. The
process planning. In cost estimation, production cost model can be easily
some of the recent researches are the integrated within optimization
following: - Mark Alan described a frameworks to support a Decision-
methodology whereby companies can Based Design approach for product
improve product cost estimation at the family design. As an example, the
conceptual design phase, using production cost model is utilized to
intelligent searching and arrangement estimate the production costs of a
of existing accounting data to enable family of cordless power screwdrivers
designers to access the activity cost [8].
information more readily. The design
decision support framework is The main goal of this research
illustrated by applying it to a typical is to design a system which describes
problem in aerospace composites the integration of design, process
manufacturing [3]. Azhar et al planning and manufacturing for cost
developed a system which could estimation purposes using a feature-
integrate the cost estimation and cost based costing technique (FBC) Such
control processes. Such integration system includes the determination of
enables the transfer of cost estimation manufacturing process.
data automatically to the cost control
process. Therefore, complete 2- Cost Estimating Methodologies
information regarding the cost status Cost model for a
of the project can be accessed at any manufacturing component or system
time [4]. Weustink et al presented a can have several purposes. The
generic framework for cost estimation required output of a cost estimating
and cost control in product design and method depends on the purpose for
illustrated with a sheet metal example which it is to be used. There are
[5]. Roy et al described a various cost estimating methodologies
methodology for developing Cost used throughout industry. These
Estimating Relationship (CER) that include: Traditional method,
explicitly consider and capture both Parametric method, Feature-based
quantitive and qualitative design times costing method, Case-based reasoning
during the (CER) development method and Neural-network-based
process [6]. Narcyz Roztocki method [9].
described that the Integrated Activity-
based costing (ABC) and Economic There is no available research
Value Added (EVA) System. It is on how the integration of design,
useful not only for manufacturing process planning and manufacturing
companies, but also for companies for cost estimation purposes is made
from the service sector. The ABC using a feature-based costing
component of this integrated system technique (FBC).
will help the companies to trace
overhead cost, while the Economic 3- Feature-Based Costing (FBC)
Value Added component will help The integration of design,
them trace capital cost [7]. Park and process planning and manufacturing

104
Eng. & Technology, Vol.25, No.1, 2007 Early Manufacturing Cost Estimate
For Mechanical Parts

for cost estimating purposes using a 4-1 Feature Description Module.


feature-based modeling approach can In this phase the part is
be possible, although it is not yet fully described as rotational or prismatic
developed with respect to cost and all features are classified into
engineering. Through the use of holes, slots, pockets…etc. Each
features, products can be described as feature is classified into sub-classes
a number of associated features, such and the user identifies the dimensions
as holes, flat faces, groove, slot… etc and tolerances for each feature, and
[10], as shown in Figure(2). output results are geometrical
information in other applications.
Each product feature has cost
implications during production, the 4-2 Process Selection Module.
more features a product has the more This module starts with
manufacturing and planning required. geometrical information that is driven
Therefore, choices regarding the from the feature description form to
inclusion or omission of a feature select the suitable processes for each
impact the downstream costs of a part feature and the system selects the
and eventually the life cycle costs of specific process with capabilities of
the product. Other reasons for using tolerance.
FBC are that the same features appear
in many different parts and products, 4-3 Machining Parameter Selection
so the basic cost information prepared Module.
for a class of features can be reused. The selection of process
Manufacturers should have numerous parameter depends on the tool
past geometric data that can be related material, work piece material, tool
to features [10]. diameter. Since there are a wide
number of material, diameter and
4- Methodology depth of cut combination, the storage
Design and Development of of process parameter requires a large
Automated Feature-Based database.
Manufacturing Cost Estimate System
(FBMCE) is developed as an 4-4 Tooling Cost Module.
approach to computer aided process The cost of the tooling is the
planning to link design phase with cost of the cutting tools and the
manufacturing phase. This helps the prorated cost of any special jigs and
designer to explore alternatives at fixtures used to hold the workpiece.
early design stage. Feature-Based The cost of the cutting tool per unit
costing techniques are used from depend on both of the cost and life of
development to production to the tool.
determine the manufacturing cost for
mechanical parts. Although there have 4-5 Material Cost Module.
been several reported researches on This module starts with
cost estimation for mechanical specifying the type of the parts shape
products. (rotational, prismatic) for the purpose
The architecture of the of calculating material cost which can
developed FBMCE system consists of be defined as the value of the material
six modules, shown in figure (3). necessary for producing a piece of
product.

105
Eng. & Technology, Vol.25, No.1, 2007 Early Manufacturing Cost Estimate
For Mechanical Parts

material is entered to the design


4-6 Cost Estimation Module. model through selection from user. In
This module starts with this case the material type of the test
calculation of production time, cost part is steel, this is illustrated in
rate, machining cost and cost of a Figure (7).
machined unit, which depends on
calculation of tooling cost and 3- The output results of the system in
material cost. Finally, the the feature description stage include
manufacturing cost of product can be representation of all information
calculated. required in other stages in FBMCE
system. The output results through the
The estimate selling price per system window include feature type,
unit is established by adding a sub-feature, feature dimension such as
markup/profit to the total cost per (length, diameter, radius, etc),
unit. The percent markup must cover topological information (tolerance,
all operating expenses (wages, rent, surface finish). By feeding the system
advertising, etc.) and provide some with the required information it
margin of profit. The block diagram becomes possible to select the process
explain estimate selling price per unit and machining parameters. The output
is shown in Figure (4). results are illustrated in Figure (8)
through the system window.
5- The FBMCE System Testing
To examine and test the 4- After generating all manufacturing
capabilities of the developed system information about the select design
are carried out through selecting model and generating a plan sheet, the
mechanical part, which is considered user enters the machine number. In
as an example for testing the system. this case the part needs multi machine
The part design models selected are to manufacture, this is illustrated in
taken from the real world problem Figure (9). Then calculate the tooling
chosen from the manufacturing cost and machining cost, this is
environments of State Company for illustrated in Figure (10).
electrical Industries, which are shown
in Figure (5). The interaction with the 5- Calculate total cost of machined
system and the results output will be unit, manufacturing cost estimation
given as follows: - and selling price. The final outputs of
the FBMCE system as shown in
1- Providing the needed table(1).
information, which is considered
essential data to feed the system
mechanism, the system contains three
types of database: Machine-Operator,
Customer-Parameter and Tools
database this is illustrated in
Figures(6).

2- Selection of the type of part shape


and entering the major dimension of
part parameters, after that the type of

106
Eng. & Technology, Vol.25, No.1, 2007 Early Manufacturing Cost Estimate
For Mechanical Parts

Table (1): The final outputs The FBMCE database system


through FBMCE system can provide refinements that would
not be possible for an engineer to
Material Cost 0.427 $ handle. For example, tool type, tool
Tooling Cost 0.343 $ materials, and materials conditions
can easily and quickly be factored into
Machining Cost 0.556 $ cost, thus making the estimate more
Total Cost of Machined accurate and reliable.
1.327 $
Unit Computer estimates are very
Manufacturing Cost Per consistent and therefore more
1.605 $ accurate. Estimates can be adjusted
Unit higher or lower, as needed, or
observed from previous cost
Estimate Selling Price $
2.07 $ estimates. More details can be
Per Unit incorporated into an estimate because
of computer-details that might be
tedious and time-consuming if done
6- Conclusions
by hand can be done quickly and
Cost has become a major
accurately on computer.
business driver in many industries. It
is observed that there is a lack of
understanding about the process to References
cost estimate in the design stage of a
product. This research presents a 1. Shaw,C.F. & Eugene,Y.S.,
business case to understand the “Information Modeling of
principles of ‘Cost Estimating’ within Conceptual Process Planning
the manufacturing industries. The Integrated with Conceptual Design”,
main goal of this research is focused The ASME Design Engineering
on the development and Technical Conferences, (2000).
implementation of the integration
between design, process planning and 2. Shaw,C.F. & Zhang,Y.,
manufacturing for cost estimate “Conceptual Process Planning -A
purpose using feature-based costing. definition and functional
decomposition”, Manufacturing
This paper describes FBMCE Science and Engineering,
system is developed to face the need Proceeding of the International
to improve the linkage between CAD Mechanical Engineering Congress
and CAM through applying and Exposition, Vol.10, P.97-106,
automated process planning technique (1999).
and automated cost estimate
techniques. The FBMCE system to 3. Eaglesham,A.M., “A Decision
help planner and manufacturing Support System for Advanced
engineering to select manufacturing Composites Manufacturing Cost
process, determine machining Estimation” Ph.D., T hesis,
parameters, and estimate Faulty of the Virginia Polytechnic
manufacturing cost for products. Institute and State University, (1998).

107
Eng. & Technology, Vol.25, No.1, 2007 Early Manufacturing Cost Estimate
For Mechanical Parts

4. Azhar,S. et al., “Development of an 9. Esawi,A.M. & Ashby,M.F., “Cost


Integrated Cost Estimation and Cost Estimates to Guide Pre-Selection of
Control System for Construction Processes”, Mechanical
Projects” Florida International Engineering Department, The
University, (2000). American University In Cairo,
(2003).
5. Weustink,I.F. et al., “ A generic
framework for cost estimation and 10. Roy,R., “Cost Engineering: Why,
cost control in product What and How”, Decision
design”,Proc. of the 6th Int. Conf. Engineering Report Series,
on Sheet Metal, Vol.2, P.231-242, Caranfield University, (2003).
(2000).
11. Wage,H.W., “Manufacturing
6. Roy,R. & Kelvesjo,S., Engineering” Taylor and Francis
“Quantitative and Qualitative Cost Inc, (1996).
Estimation for Engineering
Design”, Department of Enterprise 12. Salvendy,G., “Hand Book of
integration, Caranfield University, Industrial Engineering”, John Wiley
(2001). and Sons, (2001).

7. Roztoki,N., “ The Integrated


Activity-Based Costing and
Economic Value Added System for
the Service Sector”, State
University of New York at New
Paitz, School of Business, (2001).

8. Park,J. & Simpson,T.W.,


“Prodution Cost Modelling To
Support Product Family Design
Optimization”, Department of
Industrail and Manufacturing
Engineering, The Pennsylvania
State University, (2003).

108
Eng. & Technology, Vol.25, No.1, 2007 Early Manufacturing Cost Estimate
For Mechanical Parts

Conceptual Design Conceptual


Process Planning

Form/Structure Process
Requirement & property Process Selection
•Fabrication
Functional •Assembly
Design •Inspection
Function Resource
Behavioral Selection
Specificatio n
Estimated Equipment/Skill
Behavior Time & Cost
Time & Cost
Embodiment
Estimation
Des ign
Form/Structure Time & Cost

Detailed Detailed Process


Design Planning
•Geometry
•Operation sequen ces
•Topology
•Process parameters
•Tolerances
•Setup/Fixture
•Dimensions
•Accurate time& cost
•Surface Conditions
•Manufacturing resource
•Materials

Figure (1): Design and process planning message


exchange for integration [1].

Groove
Hole Face

Step slot
Square groove Slot
Hole

Straight

Figure (2): Examples of different views on features

109
Eng. & Technology, Vol.25, No.1, 2007 Early Manufacturing Cost Estimate
For Mechanical Parts

USER Design
Information

Feature Description
Phase I
(F.D.) Module

FBMCE system Manufacturing Processes Selection


Database (M.P.S.) Module
Phase
II Manufacturing Parameter Selection
(M.R.S.) Module
Machine--Operator
Database

Tooling Cost (T.C.) Module

Customer-- Phase
Parameter Database III Material Cost (M.C.) Module

Machining parameter
Database Phase Manufacturing Cost Estimation
VI (C.E.) Module

Final Manufacturing Cost Estimate

Figure (3): FBMCE system architecture.

110
Eng. & Technology, Vol.25, No.1, 2007 Early Manufacturing Cost Estimate
For Mechanical Parts

Markup/Profit

Sales
Estimate
Selling Price
Per Unit
Administration

Manufacturing
Total Cost Per
Overhead Unit

Material Cost
Manufacturing
Cost Per Unit
Total cost of
Tooling Cost machined part

Machining Cost

Figure (4): Block diagram explain estimate selling price per unit

111
Eng. & Technology, Vol.25, No.1, 2007 Early Manufacturing Cost Estimate
For Mechanical Parts

Figure (5): Shift (8E-200)

Figure (6): The machine-operator, tools and customer-parameter database Screen

112
Eng. & Technology, Vol.25, No.1, 2007 Early Manufacturing Cost Estimate
For Mechanical Parts

Figure (7): The output results by material cost module screen.

OD

Figure (8): The output results by process and machining determined screen.
113
Eng. & Technology, Vol.25, No.1, 2007 Early Manufacturing Cost Estimate
For Mechanical Parts

Figure (9): The output results by multi-machines screen.

Figure (10): The output results by tooling cost and machining cost screen.

114
Eng. & Technology, Vol.25, No.1, 2007 Early Manufacturing Cost Estimate
For Mechanical Parts

Appendix
Production time formula [11].
T unit = Tm + Ti …………………………..……….. ( 1 )
where:
T= machining time …………..…min
Ti = idle time ……………………min

Machining time formula [11].

For drilling: H + 0.3D , H + 0.3D ..…...….. ( 2 )


Blind hole
T = Through hole T =
F * N F * N
L …………………………………….……….. ( 3 )
For milling: T = F N No
* *
For turning: L ………………………….....………………..….. ( 4 )
T
F *
= N
where:
T = machining time…….…….…(min)
L = length of cut……….……..…(mm)
H = hole depth…………………..(mm)
F = Feed per revolution……..…(mm/rev)
N = rpm………………….……...(rev/min)
D = drill diameter……………....(mm)
No = number of gear teeth.

Revolution per minute formula [12].


1000 * S ……………..………..……….. ( 5 )
N=
where: 3.14 * D
N = RPM.…………………….…(rev/min)
D = Diameter of work, cutter….(mm)
S = cutting speed………………..(mm/min)
Idle time formula [13].

Ti = t set + t hand + t down + t change ……..…..……….. ( 6 )


+
where:
tset = total time for job setup divided by number of parts in the batch.
thand = time the machine operator spends loading and unloading the work on the machine.
tdown = downtime lost because of machine or tool failure, waiting for material or tools.
tchange = prorated time for changing the cutting tool. It can be calculated by using the
following formula:-

115
Eng. & Technology, Vol.25, No.1, 2007 Early Manufacturing Cost Estimate
For Mechanical Parts

t Cutting
T Changing = Tool change time * …………….…………(7)
Tool life
Material Cost formula [12].

M.C. = V D P …………………………….. ( 8 )
where:
* *
M.C. = Material Cost….….…..($)
V = Volume of workpiece…….(mm³)
D = Density…………….…...…(Kg/mm³)
P = Price…………...……….....($/Kg)

Tooling Cost formula [12].


Tm ....……..…………….. ( 9 )
T.C. = C t *
where: TL
T.C.=Tooling Cost…………..…..($)
Ct = Cost of a cutting tool……...($)
Tm = machining time …………..(min)
TL = Tool life…………………….(min)

Machining Cost formula [13].

Cm = Cr .………………………. ( 10 )
where: * T unit
Cm=machining Cost………..…($)
Cr = cost rate……………….… ($/min)
T unit = production time…..…(min)

Cost rate formula [13].

1  M (1 + OHm) W (1 + OHop ) 
Cr = +
60   ……………………………(11)
100 100 
where:
M = machine cost…………………. ..($/hour)
OH m = machine overhead rate…….. (%)
W = labor rate for operator……….. ($/hour)
OH op = operator overhead………... (%)

Total cost of machined part [13].

C= M.C. + T.C. + Cm ………………………..(12)

116

You might also like