National Highway = 42 (New NH 55) Length = ~ 112 Kms NHAI Cost = Rs. 1535.82 Crores Bid Cost = Rs. 1421.25 Crores Bid Security = 1% of NHAI Cost Construction Period = 910 days or 30 months Operations Period = 15 years from COD Bid Variable NPV of Bid Project Cost + NPV of O&M Cost NPV @ [Bank Rate + 3%] As per specified XL format Performance Security = 5% of Bid Cost Additional Performance Security 10% of [NHAI Cost (–) Bid Cost] Payable if Bid Cost is lower than 10% of NHAI Cost Equity Restriction = 51% upto 2 years from COD Conditions Precedent Cl 4.1.2 = NHAI to fulfill in 120 days