S No Concession Covenant

10 Construction Period
Important
11 Nullifying Positive Change of
Scope Order
Important

12 Negative Change of Scope


Important
Details
910 days for most of the projects

§ Concessionaire can nullify change of scope orders if their sum in


any 3 consecutive years exceeds 10% of bid cost and 25% overall at
any times
§ These numbers were 5% and 20% respectively in earlier
concessions
§ Reduction in Change of Scope would reduce the bid project cost
by the % reduction in the civil cost
§ O&M payments will also be reduced or increased proportionate
to the length reduced or increased
§ Earlier obligations for works under negative change of scope
were deemed to be fulfilled by paying 80% of the cost savings from
such reduction