How To Obtain Building Completion Certi cate And Occupancy Certi cate
Features Real Estate News by admin - May 27, 2015 8 1519
Procedure to Obtain Building Completion Certi cate / Occupancy Certi cate in MCGM limits for all structures, redevelopment,
fresh and other buildings.
1. Submit application and design plans at Building Proposal of ce of BMC and pay scrutiny fee
Applicant submits application form with plans and all required documents, as prescribed by Section 373 of the BMC Act, at the Andhuri Building Proposal
Of ce of the BMC. If all documents are in order and the le is complete, Builder can proceed to payment of the scrutiny fees. Fees are paid in the same
building by cash or bank draft. Once the fees have been paid, the application le is forwarded to the concerned of cer in the Building Proposal
Department. Then the le is forwarded to the Survey Of ce, which will place their remarks on the application le and check the remarks from the
Development Plan of ce (obtained during the design stage of the project). If the Survey Of ce is satis ed with their review, they will send back the
application le to the Building Proposal Department with one week.
The cost for this procedure is INR 28 per square meter of the built up area/plot area, whichever is the maximum.
Agency: Building Proposal Of ce, Mumbai Municipal Corporation 1 day INR 36,417
3 Obtain Intimation of Disapproval from the Building Proposal Of ce and pay fees
After the site inspection, the application le returns to the Building Proposal Of ce to receive an intimation of disapproval (authorization). The concerned
Sub Engineer scrutinizes the proposal and forwards the report to the Assistant Engineer and Executive Engineer. The proposal is approved at the
Executive Engineer’s level if no concessions are involved. There are 3 executive engineers in the main BMC of ce and 2 in the Andhuri of ce (the latter is
the of ce considered for the purposes of this study).
Complete applications that do not require concessions (i.e. claiming of areas free of FSI as per provision in DCR 1991, de ciency in open spaces etc.) can be
approved within a week. However, the majority of applications require some concessions and further scrutiny so must be forwarded to the competent
authorities. This latter process may take 30 – 90 days to complete.
The intimation of disapproval is issued with a list of NOC’s which the applicant must obtain separately from various departments and government
authorities. Final clearance to build will only be given once BuildCo obtains all NOC’s. The NOC’s assigned to the intimation of disapproval are case speci c.
For the purpose of this study, Doing Business has determined 7 basic NOC’s that are required of almost all projects:
1. Tree Authority
2. Storm Water and Drain Department
3. Sewerage Department
4. Hydraulic Department
5. Environmental Department (concerned with debris management) TOP
https://accommodationtimes.com/how-to-obtain-building-completion-certificate-and-occupancy-certificate/ 1/12
7/2/2018 How to obtain Building Completion Certificate and Occupancy Certificate -
BuildCo’s architect must take the Intimation of Disapproval and the design plans to each clearance of ce separately. NOCs can be applied for
simultaneously, but NOC of ces are spread out so the submission for these 7 NOC’s is likely to take some time.
The cost for this procedure is INR 1 per square meter for Intimation of Disapproval + INR 2 per square meter (or a maximum of INR 45,000) as a deposit for
debris clearance. The latter is returned after the completion of construction if the BMC has deemed all debris cleared.
Agency: Building Proposal Of ce, Mumbai Municipal Corporation 60 days INR 1,301
* 8 Request and obtain NOC from Storm Water and Drain Department
Agency: Storm Water and Drain Department, Mumbai Municipal Corporation 7 days no charge
Agency: Chief Fire Of cer, Bombay Municipal Corporation 7 days INR 13,006
14 Obtain Commencement Certi cate from Building Proposal Of ce and pay Development Charges
On submission of all required NOCs mentioned in the IOD and on compliance of the IOD conditions, the applicant may submit request for the
Commencement Certi cate. The documents and NOC submitted by the applicants are veri ed by the staff and the necessary Commencement Certi cate
is approved. After payment of development charges and other applicable premium the Commencement Certi cate is issued within 7 to 15 days.
The Cost for the CC is INR 200 per square meter of land + INR 500 per square meter of building area.
Agency: Building Proposal Of ce, Bombay Municipal Corporation 10 days INR 836,100
https://accommodationtimes.com/how-to-obtain-building-completion-certificate-and-occupancy-certificate/ 2/12
7/2/2018 How to obtain Building Completion Certificate and Occupancy Certificate -
16 Submit letter stating completion of building works to obtain an Occupancy Certi cate and Certi cate of Completion
BuildCo’s architect must submit a formal letter stating that construction has been completed according to the standards set forth in the IOD and CC.
Agency: Building Proposal Of ce, Bombay Municipal Corporation 1 day no charge
* 18 Request and obtain completion NOC from Storm Water and Drain Department
Agency: Storm Water and Drain Department, Bombay Municipal Corporation 3 days no charge
* 22 Request and obtain completion NOC from Traf c & Coordination Department
Agency: Traf c & Coordination Department 3 days no charge
* 28 Receive on-site inspection for connection to water by the Water Supply Department
An application for water connection is made to the Assistant Engineer of the Municipal Corporation. The Assistant Engineer of the Municipal Corporation
makes the inspection. There are two inspections: one before the water connection is completed, and another after completion. The inspection would not
take more than a day. An of cer of the water department of the Municipal Corporation inspects the premises and prepares a report on the connection.
Agency: Water Department, Bombay Municipal Corporation 1 day no charge
https://accommodationtimes.com/how-to-obtain-building-completion-certificate-and-occupancy-certificate/ 3/12
7/2/2018 How to obtain Building Completion Certificate and Occupancy Certificate -
Admin
Previous article
Property Rights of Women
Next article
Arun Muchhala Group invests Rs.500 crore in affordable housing project at Boisar
SIMILAR ARTICLES
https://accommodationtimes.com/how-to-obtain-building-completion-certificate-and-occupancy-certificate/ 4/12
7/2/2018 How to obtain Building Completion Certificate and Occupancy Certificate -
June 1, 2015 0 72
EXPERT’S NOOK
ILLEGAL CONSTRUCTION OF INFORMATION TECHNOLOGY PARKS IN MUMBAI AHMEDABAD DEVELOPERS SET TO PROVIDE AFFORDABLE HOUSING
Regards,
Hemant Vashta.
Reply
Admin
Yes. OC have nothing to do with conveyance.
Reply
Dear Sir,
Hemant Vashta
Thanks for the reply, Sir.
Regards,
Hemant Vashta
Reply
Sundeep
Sir,
Deemed conveyance is stuck because our building does not have OC.
How can the society obtain OC? Can we apply to BMC for the same?
Reply
Reply
Reply
Reply
Akshay Chandratre
hello sir.
i required the building completion certi cate for medical licence and i dont have it. so i wants to ask that, how can i issue the partial
completion certi cate.
and is it option for tax receipt of municipal corporation?
Reply
LEAVE A REPLY
Comment *
Name *
Email Address *
Website
https://accommodationtimes.com/how-to-obtain-building-completion-certificate-and-occupancy-certificate/ 6/12
7/2/2018 How to obtain Building Completion Certificate and Occupancy Certificate -
Post Comment
Name
Enter Email Id
Captcha
3 + 6 = Enter Sum
Subscribe Me
https://accommodationtimes.com/how-to-obtain-building-completion-certificate-and-occupancy-certificate/ 7/12
7/2/2018 How to obtain Building Completion Certificate and Occupancy Certificate -
NEWS BY DATE
July 2018
M T W T F S S
1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 31
« Jun
FOLLOW US
Recent Popular
https://accommodationtimes.com/how-to-obtain-building-completion-certificate-and-occupancy-certificate/ 8/12
7/2/2018 How to obtain Building Completion Certificate and Occupancy Certificate -
GREEN BUILDINGS PROVIDES THERMAL COMFORTS, VISUAL COMFORTS & MORE: SANJAY SETH
June 30, 2018 0 51
https://accommodationtimes.com/how-to-obtain-building-completion-certificate-and-occupancy-certificate/ 9/12
7/2/2018 How to obtain Building Completion Certificate and Occupancy Certificate -
GREEN BUILDINGS IN 2007 USE TO BE 20% MORE EXPENSIVE, BUT NOT NOW: DR. AJAY MATHUR
June 30, 2018 0 25
https://accommodationtimes.com/how-to-obtain-building-completion-certificate-and-occupancy-certificate/ 10/12
7/2/2018 How to obtain Building Completion Certificate and Occupancy Certificate -
DECLARATION IN RERA
June 30, 2018 0 20
https://accommodationtimes.com/how-to-obtain-building-completion-certificate-and-occupancy-certificate/ 11/12
7/2/2018 How to obtain Building Completion Certificate and Occupancy Certificate -
https://accommodationtimes.com/how-to-obtain-building-completion-certificate-and-occupancy-certificate/ 12/12