tee No: TCD)
B.EJ/B.Téch. DEGREE EXAMINATION, APRIL/MAY 2017.
Seventh Semester
Computer Science and Engineering
CS 6704 - RESOURCE MANAGEMENT TECHNIQUES
Regulations 2013)
‘Time : Three hours Maximum : 100 marks
Answer ALL questions.
PART A — (10 x 2 = 20 marka)
1. Explain slack variables of LP problem.
2. Whats sonsitivity analysis?
3. Define primal and dual problem?
4. Write the difference between the transportation problem and the assignment
problem. :
5. List different types of Integer programming problems.
6. Write the Gomory’s constraint for the all integer programming problem whose
simplex table (with non intoger solution) given below :
C,>2 2 -10 0
a
7. Write down the necessary condition for general non linear programming
problem by Lagrange's multiplier method for equal constraints.Define the Jacobian matrix J and the control matrix C.
Draw the network for the project whose activities and their precedence
relationship are as given below :
Activities: ABCDE F GH I
Precedence: - A A - D B,C,E F E G,H
State the rules for network construction.
PART B —(6 x 16 = 80 marks)
(a) Solve the following LP problem using graphical method.
Maximize z=6z, +8x,
‘Subject to
5x, +10x, <60
4x, +4x, <60
x and x,20. : = a6)
_ Or
(b) Solve the LPP by simplex method
Min 2=x,-9x,+2x5
Subject to
8x, x, +2x, 7
2x, r4x, $12
~ 4x, +9x, + 8x, $10
4. %q.%520. e
a6)
C J)
(0) Using dual simplex method solve the LPP
Minimize 2=2x,+2,
Subject to
8x, 47,23.)
4x, +3x, 26°
4, +2x,23
and x;,x,20. a6)
2 7169313.
ua
®
(a)
@)
Solve the transportation problem : as)
1 2 3 4 Supply
I 216 25 13
n wisw 2 2B
I 82 27 18 41 «19
Demand 6 10 12 15
Find the optimum integer solution to the following 7 programming
problem =
Maximize 2=3, +22;
Subject to
2x, 37
*+%,$7
2x, =11
and x,.x;20 and are integers. (a6)
and x,,x,20 and mse a6)
y
Maximize f(z) =27 (a0 nn
Subject to E a
m(a)=x, +22} +825) -5=0
e(x)= hr; 42} 7500
Apply te Jacobian method to find f(x) in the feasible neighbourhood of
the feasibla point (1,1,1). Assume that the feasible neighbourhood is
specified by Og, =-0.1, ég, =.02 and @r, =.01. a6)
me
3 71693(&) Solve the nonlinear programming problem by Lagrangian multiplier
method.
!
Minimize. z «x? + 3x3 +5x}
Subject to the constraints
wy +x, 43x, =2
Gx, 42x, 4x, =5 (16)
%, Xp,%y 20.
15. (a) The following indicates the details of a project. The durations are in days.
‘ad’ refers to optimistic tine, ‘m' refers to most likely time and 't’ refers to
- pessimistic time duration.
Activity: 1-2 1-3 1-4 2-4 2-5: 3-4 4-6
a: z 3 48 6 SS#
m: 4 4 6 8 8 (a )6
b: 6 6 6..41).3. 7
@® Draw the network
(i). Find the critical path
(ii) Determine the expected standard deviation of the completion time,
Or
b) Aproject schedule has the following characteristics :
Activity: 1-2 1-4 1-7 23 36 45 48 56 69 78 89
Destin: 2 2: UDXeXy 5 8 4 38 3. 5
@ Construct a PERT Network and find the critical path and the
project duration.
(ii) Activities 2-3, 4-5, 6 ~9 each requires one unit of the same key
equipment to complete it. Do you think availability of one unit of
the equipment in the organization is sufficient for completing the
project without delaying it; if 90 what is the schedule of these
activities?
4 71693