Professional Documents
Culture Documents
Project
3D METHODOLOGY
TABLE OF CONTENTS
1. INTRODUCTION...................................................................................................................................................1
1.1 NATIONAL SCENARIO.....................................................................................................................................................1
1.1.1 Water Resources of Nepal.............................................................................................................................................. 1
1.1.2 Power Demand and Supply............................................................................................................................................ 1
1.1.3 Power Transmission System.......................................................................................................................................... 2
1.2 INSTITUTIONAL SET UP..................................................................................................................................................3
1.2.1 Ministry of Energy........................................................................................................................................................... 3
1.2.2 Department of Electricity Development........................................................................................................................... 3
1.2.3 Hydropower Development and the Private Sector.......................................................................................................... 4
1.3 PROJECT APPRECIATION...............................................................................................................................................4
1.4 THE CONSULTING SERVICES..........................................................................................................................................6
1.4.1 The Consultant............................................................................................................................................................... 6
1.4.2 Objectives of Consulting Services.................................................................................................................................. 6
1.4.3 Scope of Work................................................................................................................................................................ 6
2. CONSULTANT'S APPROACH.............................................................................................................................8
2.1 GENERAL APPROACH....................................................................................................................................................8
2.2 MANAGEMENT APPROACH.............................................................................................................................................8
2.3 INNOVATIVE THINKING APPROACH................................................................................................................................10
2.4 RISK MANAGEMENT.....................................................................................................................................................10
3. METHODOLOGY AND WORK PLAN FOR FEASIBILITY STUDY...................................................................10
3.1 PHASE 1: INCEPTION PHASE........................................................................................................................................11
3.1.1 Mobilization Activities.................................................................................................................................................... 11
3.1.2 National Policy, Strategy, Manuals and Guidelines Review..........................................................................................12
3.1.3 Review of Previous Study Reports and Data Collection............................................................................................... 14
3.1.4 Reconnaissance Field Visit........................................................................................................................................... 15
3.1.5 Preparation and Submission of Inception Report.......................................................................................................... 16
3.2 PHASE 2: FIELD SURVEY AND INVESTIGATIONS............................................................................................................16
3.2.1 Topographical Survey and Mapping............................................................................................................................. 16
3.2.2 Hydrological, Sedimentation and GLOF Study............................................................................................................. 17
3.2.3 Geological and Geotechnical Investigations................................................................................................................. 21
3.2.4 Seismological/Seismicity Study.................................................................................................................................... 29
3.2.5 Construction Material Survey........................................................................................................................................ 30
3.2.6 Laboratory Test............................................................................................................................................................. 30
3.2.7 Logistic Survey............................................................................................................................................................. 31
3.3 PHASE 3: PROJECT LAYOUT AND ENGINEERING DESIGN...............................................................................................32
3.3.1 Finalization of Design Base Memorandum................................................................................................................... 32
3.3.2 Selection of Project Configuration................................................................................................................................. 32
3.3.3 Project Optimization Studies......................................................................................................................................... 33
List of Figures
Figure 1: Status of Existing and Under-construction Projects in Nepal (Source: NEA report, a year in review 2015/2016).......2
Figure 2: New Organogram of DoED (Source: www.doed.gov.np).............................................................................................3
Figure 3: Location Map of Project area.......................................................................................................................................5
Figure 4: General Approach of the Consultant............................................................................................................................9
Figure 5: Outline of Methodology..............................................................................................................................................11
Figure 6: Project area on protected area map of Nepal............................................................................................................15
Figure 7: Hydrological and Meteorological Stations of Nepal...................................................................................................18
Figure 8: Typical HEC-HMS Interface.......................................................................................................................................19
Figure: 9 Particle Size distribution (PSD) curve........................................................................................................................20
Figure 10: Mineralogical Analysis..............................................................................................................................................20
Figure 11: Regional Geological Map of the Project Area (Source: Dhital, 2015)......................................................................22
Figure 12: Electrical Resistivity Tomogram...............................................................................................................................24
Figure 13: Interpretative cross section......................................................................................................................................24
Figure 14: Sample Core Hole Logging......................................................................................................................................26
Figure 15: Lugeon test arrangement.........................................................................................................................................28
Figure 16: Hydropower projects in Arun valley..........................................................................................................................33
Figure 17: Results of SEEP/W program....................................................................................................................................34
Figure 18: Design profile of spillway and stilling basin..............................................................................................................35
Figure 19: Sample Procedure for Design of Tunnel Supports Based on Tunnelling Quality Index ‘Q’.....................................36
Figure 20: Example of Examining Phase 2 Output...................................................................................................................36
Figure 21: Tunnel Support Design Example.............................................................................................................................37
Figure 22: Methodology for EIA.................................................................................................................................................46
Figure 23: Consultants Organization Chart...............................................................................................................................67
List of Table
Table 1: Existing Transmission Lines (Source: NEA report, a year in review 2015/2016)..........................................................3
Table 2: Salient features of the Project.......................................................................................................................................5
Table 3: Consolidated Objectives of Consulting Services and Scope of Work...........................................................................6
Table 4: Lugeon Test Interpretation..........................................................................................................................................28
Table 5: Laboratory Tests to be performed...............................................................................................................................30
Table 6: List of Contract Packages...........................................................................................................................................42
Table 7: Feasibility Level Reports and Deliverables.................................................................................................................43
Table 8: Proposed Chapters details for ToR.............................................................................................................................50
Table 9: Study Methods and Responsibility, Physical Environmental Aspects.........................................................................53
Table 10: Primary data to be collected in Physical Environment..............................................................................................54
Table 11: Study Methods and Responsibility, Biological Environmental Aspects.....................................................................56
1. INTRODUCTION
The climate of Nepal is influenced by the South West Monsoon in summer and Mediterranean wind in winter
with an annual average precipitation of 1530 mm. 80% of the total annual rainfall occurs in wet period (June to
September) and the remaining 20% occurs during the dry period from October to May.
The perennial nature of rivers and land topography of the country with steep gradients provide excellent
conditions for hydropower development, the theoretical potential of which has been put at 83,000 MW and
technical capacity of around 42,000MW. Out of this large potential, Nepal has developed less around 2% of the
technically feasible power potential only.
The annual peak power demand of the Integrated Nepal Power System (INPS) in fiscal year 2015/16 is
estimated to be 1,385.30 MW, with 554.55 MW power estimated to have been shed. Out of the 855.89 MW of
power actually supplied, 477.93 MW was contributed by NEA hydro, 53.41 MW by NEA thermal, 324.45 MW by
IPP hydro and the rest 116.2 MW was import. Compared to the preceding fiscal year’s figure of 1,094.6 MW, the
annual peak power demand of the INPS registered a growth rate of 9.7 %.
NEA Annual report 2015/16 further reports that total energy used within Nepal in the fiscal year 2015/16 was
approximately 5,910GWh, out of which only 4,631.51 GWh (78.4%) was supplied. The rest 1,278.45 GWh
(21.6%) was resorted to load shedding. Of the total supplied energy volume, 3,559.28 GWh (76.8%) was
contributed by domestic generation and 1,072.23 GWh (23.2%) by import from India. Domestic supply included
1,258.94 GWh (35.4%) from IPPs and the rest 2,300.34 GWh (64.6%) was from NEA owned power stations with
a share of 2,290.78 GWh from hydro and 9.56 GWh from thermal. This energy comprised 57% from NEA's
NEA Annual Report 2015/16 states that the total installed capacity (NEA and IPP) is 851 MW while as projects
of 1,047 MW are under construction. Figure 1 shows the status of existing and under construction project in
Nepal.
Table 1: Existing Transmission Lines (Source: NEA report, a year in review 2015/2016)
Types Lengths (km)
33 kV, Transmission line 1,096
66 kV, Transmission Line 511.16
132 kV, Transmission Line 2,416.7
400 kV, Transmission Line 78
Ministry of Energy is responsible for development of policy, plan and implementation of rules for production,
utilization, regulation and conservation of energy. Besides, it is also liable to conduct survey, research and
feasibility study of energy and its utilization. Frame working policies that promotes the participation of private
parties in the development of electricity is another aspect of the responsibility under the Ministry.
The Department is responsible for assisting the Ministry of Energy in implementation of overall government
policies related to power/electricity sector. The major functions of the Department are to ensure transparency of
regulatory framework, accommodate, promote and facilitate private sector's participation in power sector by
providing "One Window" service and different forms of licenses to power projects. It lists the applicants for
licenses, evaluates and prioritizes them; check the development status for those who are issued the license and
monitors the power plants under generation phase. Further, it encourages the study of hydro power projects at
several phases ranging from the identification, investigations, feasibility and environmental assessment to detail
design.
Under this package of Consulting Services (Job No. 20172/73-13), the DoED has asked for technical and
financial proposal from the shortlisted consulting firms for providing consulting services for Feasibility and EIA
Study of Kimathanka Arun Hydropower Project, Sankhuwasabha District.
This project draws its water from Aun River which is major tributary to Koshi River. It is understood that the
project is upstream (approx. 8 km North) of Upper Arun Hydropower Project. The project is located in Chepuwa
VDC and from the previous study and preliminary layout, all the project components are located in the right bank
of the river. The geographic location of the project (license area) lies within:
Longitude : 27° 46’ 00” - 27° 50’ 00”
Latitude : 87° 23’ 00” – 87° 28’ 00”
From the RFP document, it is understood that the right bank of the river of the proposed layout of KAHP lies
within the buffer zone of Makalu Barun National Park. So, there is necessity of greater co-ordination and scoping
for EIA study.
Kimathanka Arun Hydropower Project (KAHP) is dependent of Arun River which is a snow fed river that
originates from Mt. Xixabangma Feng in the Tibetan Highland region. So, most of the catchment area of KAHP
(25,300 sq. km) lies in Tibet. This project is the most upstream project in the Arun River that has been studied.
The previous studies have identified the capacity of KAHP to be 434 MW. Other projects studied in Arun River
are Upper Arun Hydropower Project (335 MW), Arun III (900 MW) and Lower Arun Project (300 MW).
The salient layout features of the Kimathanka Arun Hydropower project are illustrated below in Table 2.
The project is not accessible by motor way. The nearest location accessible by road ways is Numbazzar which is
in the proximity of Arun III HEP. The accessibility of Numbazaar from is illustrated below.
15 km 40 km
Presently, Upper Arun Access Road and Numbazaar- Kimathanka Access Road are planned for accessibility to
the site. Considering the Upper Arun Access Road, there is necessity of construction of 12 km roads from
headwork of UAHP to provide road accessibility to headwork of KAHP. And the Num-Kimathanka Access road
passes close to the proposed KAHP powerhouse.
The tentative location as extracted form Google Earth and GIS are presented in Figure 3.
In order to meet the prescribed objectives, the consultant will carry out necessary field survey and investigation,
prepare design, drawings and cost estimate and conduct environmental studies. The environmental study (EIA)
will be conformity with the environment legislation of Nepal. So, broadly the objectives of the study can be
identified as:
Feasibility Study
Environmental Impact Assessment (EIA) Study
In addition to above, effective knowledge transfer and training to DoED/GoN personnel for which the selected
personnel (as nominated by DoED) will be integrated with the Consultant’s tem during the feasibility studies,
environment studies and other activities.
2. CONSULTANT'S APPROACH
An effective delivery of the project output will also be based on integrated planning, scheduling and
controlling approach. We are aware of our duties and responsibilities and all our duties are sequentially
tailored and they match the requirements of the TOR in every aspect. Periodic review of the schedule will ensure
optimum use of the resources and time, and will also give an insight of the development of the project. The Work
Breakdown Structure, WBS will ensure that project is simplified into task, work-package, activity and operational
level. So our approach is basically focused on making the task as simple through clearly defined deliverables
and optimum resource management. The Consultant intends to embark upon the services with the following
general approaches:
Selection of those methods and technologies, which have been tested and proven to be optimum in
successful on-going and past projects of similar nature;
Application of an optimal combination of the methods and technologies based on practicality, Client's
requirements, site-specific requirements, strategic importance and sound professional judgment;
Close contact and effective co-ordination with the Client and with all concerned personnel and
authorities
Regular briefing to the Client and concerned personnel and authorities on the progress of the Project
and problems connected thereto;
Strict adherence to the applicable standards, guidelines, reports, drawings, specification, testing
schedule etc.;
Full use of the technical and environmental standards formulated by the Department;
Enhancement of environmental qualities and environmental protection;
Selection and mobilization of appropriate project personnel;
Full use of available and applicable reports, standards, maps/drawings, specification, other information
for execution and completion of the proposed services in accordance with accepted professional
standards and sound engineering and economic practices;
Completion of the proposed services within the stipulated time and budget.
Understanding of TOR
- Study Objectives
- Scope of Services
WHAT TO DO? - Tasks to be performed
- Specific Requirements
TEAM
- Deploy Competent Personnels
WHO WILL DO? - Assign roles and
responsibilities for every
member
METHODOLOGY
- Project Management
- Time Control
HOW TO DO?
- Quality Control
- Cost Control
After the commencement of the services, immediately, the Consultant will organize an internal orientation
program for its team. In order to achieve the goal of the project with the desired quality and within the stipulated
The general approach for the works is divided into two groups i.e. Feasibility Studies and Initial Environment
Examination Studies which are present in subsequent chapters:
Our methodology has been designed after detailed appreciation of the project in such a way to meet all the
objectives following the specified scope of works. So, it constitutes series of interconnected tasks whose
individual outputs will integrate to deliver all the project objectives. The consultant is experienced in more
sophisticated scheduling and project management methodologies and will introduce those as appropriate when
the contract is awarded. For the clarity in methodology and smooth run of feasibility study, total tasks are divided
into numbers of different phases. The outline of methodology is presented in Figure 5.
3.1.2.4 ELECTRICITY REGULATIONS 2050 (1993) AND (AS AMENDMENT) 2007 (2064)
The Government of Nepal has enacted Electricity Regulations 1993, which along with other provisions have also
elaborated the procedure of obtaining license for survey, generation, transmission and distribution. The
following are the provisions related to the promotion of private sector participation in the utilization, conservation,
development and management of hydropower:
Any hydropower project up to 1000 kW requires to inform to the Electricity Development Board about the
detail of project i.e. project description, map of project area, sources of water and quantity of water to be
used, electricity distribution area and number of customers to be benefited, description of claim if any
other has utilized it before and other necessary things.
Separate procedures are prescribed to get the license of survey, generation, transmission and
distribution.
Feasibility Study Report accompanying with EIA is necessary to get the license for production,
transmission and distribution of electricity.
No double survey license is issued to conduct survey in the same area and at the same time.
The license has been guaranteed the right of water use for the certain period of time in accordance with
the terms and conditions stipulated in the license.
The licensee is required to get permission of the government before importation of electricity.
Facility of grid use is provided. If technically possible, the licensee may supply the electricity produced
by the developer in any part of Nepal to the other part of the country through the existing grid system.
3.1.2.5 WATER RESOURCES ACT 2049 (1992) / WATER RESOURCES REGULATIONS 2050 (1993)
The Water Resources Act and its Regulations are key legislation formulated to develop the hydropower
resources of the country. The Act and Regulations have made arrangements for rational utilization,
conservation, management and development of the water resources available on the country. Likewise legal
provisions have been made for the beneficial use of water resources and for the prevention of environmental
and hazardous impact on the sources of water.
3.1.2.9 ENVIRONMENT PROTECTION ACT, 2053 (1997) & ENVIRONMENTAL PROTECTION REGULATIONS (AS AMENDED) 2055
(1999)
Environment Protection Act, 1997, has been enacted by the Parliament to make legal provisions for the
protection of environment so as to maintain clean & healthy environment by minimizing, as far as possible,
adverse impacts likely to be caused from environmental degradation on human beings, wildlife, plants, nature or
physical objects. Basic features of Environment Protection Act and the Environmental Protection Regulations (as
amended) are as follows:
An Initial Environmental Examination (IEE) and Environmental Impact Assessment (EIA) should be
prepared for industries and activities of varying nature in accordance with the Act
Section 4 stipulates that without getting the proposal approved from the concerned agency or ministry,
no person will implement a proposal that could have an impact on the environment.
A proponent who is desirous of implementing any proposal will have to submit such a proposal
accompanied by the report on Initial Environmental Examination or Environmental Impact Assessment
of the proposal, to the concerned agency for the approval of such a proposal.
Provisions are clearly made in Environment Protection Regulation for the development of hydropower
projects. Schedule 1 & 2 concerned with Rule 3 of Environment Protection Regulation 1999, stipulates
that to build hydropower projects of 1 to 5 MW, an IEE should be prepared. For hydropower
projects of more than 5 MW capacity a full-fledged EIA is required. EIA reports are subject to the
approval from the Ministry of Population and Environment.
As per schedule 1 of EPR 1997, and its second amendment 2007, any hydroelectric project with
capacity of 1MW to 10 MW needs to carry out IEE and above 10 MW EIA needs to be carried out.
As per the EPR 1997, third amendment 2009, any hydroelectric project with capacity of 1MW to 50 MW
needs to carry out IEE and above 50 MW EIA needs to be carried out.
We expect the client to provide the prefeasibility report or identification study report of the project. Besides, the
consultant will also collect geological and topographical maps of the area. Available hydrological study reports
and raw data from the DHM will also be collected and studies during the desk study period. After the study
materials are collected, a thorough review of these guidelines and data will be carried out by the team of experts
at the consultant’s head office. In general prefeasibility report, geological maps and hazard zones, hydrological
and meteorological data and information, river basin study report, topographical maps and aerial photographs
will be reviewed to derive a tentative scenario of the proposed project.
For generating a tentative idea on the environmental and socio-economic aspects of the region, reports
pertaining to project area, environmental studies socio-economic reports of the region will be collected from
various sources like Ministry of Women, Children and Social Welfare, Ministry of Population and Environment,
Ministry of Land Reform and Management and other related ministries. From the preliminary study it is found
that project lies within Makalu Barun Buffer zone, therefore the policies and norms related to buffer zones will be
studied so that the environmental studies are carried out as per the statutory requirement. The project location
on protected area map is depicted in Figure 6:
Project Area
The inception report will also include other field findings like evidence of installed staff gauge, requirements of
establishment of automatic hydrological station and the report including the available hydrological and
meteorological data collected from DHM. The report will also include the coloured photographs showing the
location of major structures of Hydropower Projects and copy of Benchmark or Trig Points Sheets collected from
Department of Survey. On environmental aspects, the report will cover the preliminary findings from field
reconnaissance. Besides, the report will include the preliminary and conceptual project configuration and
preliminary cost estimate based on the cost applied to similar other projects. Based on the preliminary cost
estimate a primitive financial analysis will be carried out and included in the report.
After the verification process is completed, the detailed survey of the component sites will follow above scales.
This will enable the Consultant to prepare a more precise and accurate design, cost estimate and drawings. The
survey works will be connected with the national geodetic points. In order to prepare the topographic maps,
following survey will also have to be carried out:
The kind and name of natural or man-made features will be recorded and included in the topographic maps.
After the completion of field survey the consultant will prepare following maps with appropriate scales and
accuracy.
4 Map of headwork site (intake, weir, river diversion, desanding basin, spillway site), penstock alignment and
powerhouse site, switch yard site, tailrace site, sub-station site in 1:1000 with contour interval of 1 m
4 Topographic map of water conveyance alignment cannel / tunnel and project road in 1:2500 scale with
contour interval of 5m covering at least 100 m corridor on each side from the centerline
4 Map of quarry site and borrow areas in appropriate scale
4 Map of office, residential colony and base camp area of the projects in scale 1:1000 with contour interval of
1m
4 Drawings of L-section of river starting from 250 m upstream to 250 m downstream of dam axis covering a
stretch of 500m
4 Drawings of x-section of river from 300 m both upstream and downstream of dam axis at 50 m interval and
along the dam axis
4 Drawing of L-section and x-section at gauging stations with minimum coverage of 500 m upstream and
downstream of the gauge site
4 Drawings showing details of cross-drainage from 200 m both upstream and downstream
4 Drawing of L-profile and cross-sections of access road in suitable interval from the existing road to
necessary areas like Headworks and powerhouse, surge shafts, etc.
The Consultant will submit Topographic Survey and Mapping Report describing the activities undertaken
including all necessary basic data and records relating to the topographic surveys. The details of reference
points will be submitted in separate sheet. Also, a separate BM reference sheet will be prepared and
submitted. All the surveyed data and topographic map will be handed to DoED in workable format
(AutoCAD/Land Development) along with the report.
The hydrological investigations will focus on assessment of the stream flow and on aspects relevant to the
construction operation such as length of the season, rainfall characteristics, number and duration of rainfall
event, dry interval between rainfall event, temperature etc.
The Consultant will carry out hydrological and meteorological studies, consisting of field measurement &
updating the data in order to estimate the firm flow, daily and mean monthly flows and flood flows for the design
of the diversion works and spillway. Additional requirements include confirmation of stage-discharge relationship
and generation of an extended mean monthly and dry flow series for power and energy computation. The flows
of the river will be computed from the routine gauge readings applying the rating curve of the cross section of
river at the gauged site. If required, the Consultant will perform the following activities for collection of
Hydrological and Metrological data.
Collection of long term historical rainfall data and climatological data pertinent to the study
Collection of long term historical flow data and sediment data of the river under study, if available; if not,
collect the data from other river with similar hydrological characteristics in the vicinity.
Checking flow data with rainfall data and generate long series of flow data
Estimation of the design floods for the structures for the return periods of 50, 100, 500 and 1000 years.
Conducting flood frequency analysis for the period October to May for ascertaining diversion flood. The
frequency of diversion flood will be 1 in 20 years
Checking these observed data with the data collected from secondary sources and modify the long term
data accordingly
Direct field measurements of low flow (November – May) will be conducted. For this purpose, a staff
gauge will be established near the headwork site, and daily water level data will be collected. This data
will be substantiated by frequent direct flow measurements to develop rating curves at headwork and
tailrace sites.
Carrying out the water quality analysis to determine the corrosive effectiveness
After the collection of available data, the consultant will perform basin rainfall estimation using Thiessen Ploygon
iso-heytal using long term annual and monsoon rainfall data. The available data will also be checked for any
missing data with appropriate method of estimation. Further, the consultant will conduct consistency test and
study before calculating lagging term basin aerial monthly rainfall data for the study basin and referred basin.
The basin rainfall will be used to estimate and validate hydrological estimation for hydropower project. Based on
the available and derived hydrological data, the consultant will generate extended mean daily, monthly, yearly
flow data including extreme instantaneous maximum and minimum flood, dry flood series for the dam site and
powerhouse / tail race outlet. Flow Duration Curve will also be generated using daily discharge data.
Collection of all Meteorological and Hydrological data recorded on nearby stations in the vicinity of the
catchment
Model Preparation
Hydrological Simulation
Parameter estimation
Analyzing simulation Runs and Storing of data.
The consultant will validate the estimated flow and confirm the flow duration curve with the help of HEC-HMS.
The consultant will submit the results /output of the modeling in separate volume and together with the reports.
The typical interface of HEC-HMS is presented below in Figure 8.
Sediment Study
The sediment study will be conducted concurrently with the hydrological studies. Immediately after signing the
contract, the consultant will install sediment sampling station at the at the intake site. We will refer Guidelines for
Study of Hydropower Projects (December 2003) while conducting the studies and other if any. In order to
conduct sediment studies adequate bed load data will be collected in different seasons. In addition, the available
data from DHM will also be referred. Specifically the consultant will conduct following studies under sediment
condition assessment.
Establish sediment testing laboratory along with required equipment like sediment sampler, sieve of
different size, decicator, filter paper, digital weighting machine drying pan, oven/stove, conical flask,
beaker as well as other articles and chemicals per the requirement,
collect the historical suspended and bed load sediment data/information on reservoir sedimentation at
local, regional, national level and of neighbor countries,
study the catchment characteristics from sediment point of view,
Single sediment sample per day during four wet months (June – September) and two samples per
month during remaining dry months are to be collected on annual basis by suitable method. That means
Figure 9 And Figure 10 shows the particle size distribution (PSD) curve and mineralogical analysis result
carried out by consultant during Detailed Project Report (DPR) study of Likhu 1 HEP 77MW.
GLOF Study
The objective of this activity is to identify and investigate the risk and consequences associated with the possible
occurrence of Glacier Lake Outburst Flood (GLOF). Consultant will incorporate the recommendations from this
task into the Project design to minimize risk and the potentially adverse consequences resulting from an
occurrence of GLOF.
Consultant’s approach will involve establishment of a database of potential GLOF sources, evaluating possible
consequences of floods, and formulating preliminary recommendations for design. The assessment will be
coordinated with hydrologic evaluations and design of project structures, and if the recommendations are
accepted upon review and discussion with DoED, Consultant will provide a general scope of an early warning
system to be incorporated into the design of the Project. Additional recommendations will address long-term
monitoring activities to be followed by DoED.
Collection of relevant documents, maps and information from all possible sources;
Communication with DoED and other concerned organizations that have conducted field or office
studies on GLOF problems within or in the vicinity of the Project catchment basin;
Review and study of documents, maps, aerial photos, satellite imagery, etc.;
Determination of availability of satellite imagery and aerial photography of the Project area, select
appropriate resolution, wavelength and scale for imagery. Recommend acquisition of imagery, if not
already available;
collect the historical GLOF data,
identify and locate the existing and potential Glacier Lake Outburst Flood GLOF) sites in the Arun
catchment
Preliminary assessment of the magnitude and damage potential due to GLOF incidents;
Identify general characteristics of sediments likely to be transported by a GLOF;
If necessary, during the development of the Project, GLOF is determined to be a concern of the Project, the
following additional activities might include:
Generate hypothetical GLOFs of selected peaks at the potential sources, and routing of these floods to
the Project site to evaluate their effects. This will require the use of preparation of a dam break.
Prepare the basic design and specifications for an Early Warning System (EWS), based on satellite
imagery or other sources.
Prepare initial cost and operational cost estimates for EWS.
Prepare guidelines and procedures to be adopted by the Project operational staff during a GLOF
incident.
Review of geological and geotechnical literature and maps relevant to the prospective development
sites, including collection and review of available geological and geotechnical reports nearby study area,
as well as examination and interpretation of stereo pair aerial photographs.
Assessment of regional geological setting and hence preparation of the regional geological map for the
project area in 1:25,000 scale with standard practices of geological mapping.
Assessment of regional seismic setting.
Location of the regional faults.
According to the geological division of Nepal, the project structures lies in Higher Himalayan unit which is
occupied by mainly schist, quartzite, gneiss and migmatite. In the priliminary observation, it is seen that the
project area is influneced by lesser himalyan gneises as well. Since there seems two different type of rock in the
project boundary, it is suspected that there might be some local shear zone or MBT. The consultat is fully aware
of this situation and will give high care during geological mapping. The location of project area has been shown
in the regional map Figure 11.
Figure 11: Regional Geological Map of the Project Area (Source: Dhital, 2015)
Detailed engineering geological mapping will be done, the mapping will cover all locations of the project
components. The geological mapping of the project will include the geological information such as major joint
sets, trends of rock formations, types of surface deposits, faults, folds, shear zones, slide zones, water seepage
zones etc. The map will be useable to establish suitability of the site for intended purposed dam (type and
height), power house (surface and underground), tunnel alignment etc. the map will be basic map for further
detailed study.
The detailed engineering geological mapping will be prepared for the area around major hydraulic structures
(dam site, tunnel alignment, power house site). The mapping will include details of geological conditions of
various rock units, degree of weathering, attitude of rock, prominent and random joint systems and their
persistency, slides, major and minor faults, shear and fracture zones, types of surface deposits or overburden,
tracing of rock outcrops and overburden boundary, slope stability & ground water situation.
The state-of-art trend in rock mass classification is the so called Geological Strength Index (GSI) based
classification after Hoek and Brown (1996), which are demonstrated to yield the engineering properties of rock
more accurately. The Consultant has hands on experience on using this classification system and intends to use
the system extensively in combination with the conventional RMR and Q values. As the GSI classification is
proposed to be used in the project as an innovative tool, the Consultant also proposes to carry out rock triaxial
tests which can validate the output engineering properties from the GSI approach.
The mapping will identify and indicate the geological distributions of bedrock and soil, overburden deposits,
ground water condition, slope stability, degree of weathering, discontinuities (fault, fold, shear/weak zone,
joints/foliation) and properties of rock, soil, joints, faults and weak/shear zones. Samples of different rock types
during the mapping process will be collected, clearly labelled and transported to a laboratory for analysis. Rock
and soil types will be classified according to BS 5930 or ASTM. Properties of rock and soils will be identified for
design purpose.
In defining saturated and unsaturated material, different material type of overburden, underlying rock strata and
their respective strength, weak zones shear zones in bedrock identifying gravitationally deformed slopes, shear
planes in slopes, paleo valleys, collapsed rock mass zones and rock slides. Data acquisition can be carried out
accurately up to 200 m depth by suitably placing the electrodes in between 7 m to 30 m and will be marked with
wooden pegs. The whole survey will be controlled with a laptop computer by programming a sequence of
resistivity measurements. Electrode arrangement (e.g. Wenner, Schlumberger, dipole-dipole, pole- dipole) will
be selected by the consultant depending upon the depth of investigation required and the geological condition of
the site.
Figure 12 And Figure 13 shows results of ERT survey carried out by consultant during Detailed Project Report
(DPR) study of Likhu 2 HEP 55 MW.
Figure 12: Electrical Resistivity Tomogram Figure 13: Interpretative cross section
Pseudo section will be displayed by plotting apparent resistivity value at a distance along a profile that
corresponds to the middle of the array and at a depth proportional to the electrode spacing. This pseudo section
will be processed by using inversion scheme to estimate the subsurface resistivity properties. Once an image of
the subsurface is obtained, interpretation will be carried out using prior knowledge about the geology/ hydrology.
The resistivity and thickness of different layers may be computed manually or by the use of standard software.
The result of the Electrical Resistivity Tomography (ERT) survey will be interpreted in terms of thickness of
different strata and the physical properties of the strata. Surface geological observation and other evidence of
sub-surface condition will support this interpretation. The final report of the survey will also contain limitations &
pitfalls of the survey.
Core drilling will be conducted so as to obtain continuous cores with the maximum practicable amount of core
recovery. Core barrels will be double tube or triple tube, equipped with inner tubes and diamond bits sized to
produce "NQ size core.
The Geologist after the approval of DoED will determine the borehole location, drilling procedures, total depth,
sample intervals and document the requirements in the Drilling Plan and Sampling Plan prior to the start of field
activities. The basis for this prospecting is the proper recovery of core from earth crust obtained in cylindrical
form by annular cutting action of bit and can be regarded as true and unaltered specimen of rock with hard
mineral deposit. These cores are then tested for various chemical, mechanical and physical properties.
The Geologist will be present at the drill site while coring is in progress. The Geologist will observe all handling
of the core by the drill crew, will prepare a lithology log. The Geologist will collect core samples at specific
intervals for purposes of chemical analyses and physical testing.
Core recovery is defined as % of core length recovered w.r.t drilled length of run.
Core recovery (%) = (Length of core/Length of run) x100
100% core recovery is difficult to attain when drilling soft rocks/fragmented formation. Standard core recovery in
medium to hard formation is between 80-100%.
ITECO – AFC – TMS JV P a g e | 25
Consulting Services: Feasibility and EIA Study of Kimathanka Arun Hydropower
Project
3D METHODOLOGY
However, it may be emphasized that that core recovery depends on nature of strata, condition of drill
accessories and type of drilling. It is largely independent of human intervention. The drilling crew takes absolute
care for enhanced core recovery but it can be achieved only when better accessories and technology is used.
Apart from nature of formation, there can be various reasons for low core recovery. There are broadly three main
factors that affect core recovery.
Type of formation encountered- For loose formation there is chances of poor recovery.
Set of Equipment selected excessive washing of core in barrel-bit assembly, improper selection of bit
speed and feed, excessive vibration of string, improper drilling fluid etc.
The diameter of core is determined by I.D of drill bit under use.
Three types of colored photographs: (a) photographs showing the site before investigation, (b) photographs
showing the drilling operation at site and (c) photographs showing the stake after the completion of the
investigation will be included in the report. In addition to photographs, drilling work completion report from
responsible site staff will also be submitted in the field investigation report.
Core sample taken from each borehole will be placed in order in core box. After placement in core box, the core
will be photographed in color prints. NQ size core box will be provided by the firm. All boxes will be uniform in
size. Each core box will be capable of holding approximately 5 meters of core in parallel rows not exceeding one
meter in length. Each core box will contain partitions, which will be arranged to allow for convenient marking and
interpretation of core. Wooden core loose blocks and end of run blocks having a cross-section of 5 cm inside
dimension will be provided. Core losses will be replaced in each run by the core loss blocks equal in length to
The Consultant will prepare the geological logs of each of the bore hole simultaneously with drilling. The bore
hole logs will be prepared by engineering geologist/geological engineer/geo-technical engineer in a standard
format as shown below or with minor modification after consultation with client and consultant after approval.
Work progress and all findings for each drilling unit shall be submitted in the Standard format. The bore hole log
shall contain at least the following information.
4 Date (start and finish)
4 Drill hole number.
4 Location.
4 Site coordinates.
4 Elevation.
4 Drill Machine.
4 Drilling method.
4 Casing.
4 Depth of the hole.
4 Driller.
4 Logged by.
4 Core recovery %.
4 RQD.
4 Lugeon value.
4 Discontinuity characteristic.
4 Remarks
For Bore Hole Location, the pre-cast concrete pillar of size 10cm x 10cm x 200 cm long and marked with
borehole number and elevation will be driven at the location of borehole drilled. The height of the concrete pillar
will not be less than 1m, if any deviation seems to be incorporated during implementation, it will be discussed
and finalize accordingly.
Permeability test
The Consultant will measure the groundwater level and perform permeability tests to determine the water
bearing characteristics of the overburden. The Consultant will provide an adequate source of clear water, a
means of measuring the rate of flow of water, added to the top of the hole and a means of measuring the depth
of water in the hole.
Lugeon Test
The extents of grouting and cut-off depths required in a dam foundation are directly related to the hydraulic
conductivity (permeability) of the rock masses involved. Selecting a representative value of hydraulic
conductivity becomes of the outmost importance during design; especially, since under such a wide variation
range, averaging the measured values will not suffice. Unlike soils, where seepage takes place through a series
of small, closely spaced, interconnected pore spaces, seepage through rock masses occurs mostly along
discrete planar discontinuities (e.g., joints, foliations, shears, etc.).
Lugeon tests are carried out to assess the variability of a borehole as it intersects various hydrogeological units.
Open hole water levels and pumping tests can give misleading results in such environments. Therefore, packer
testing is often utilized to help understand the detailed hydrogeological properties of the various horizons. This
knowledge can often be essential to the proper design of the hydrogeological program.
As required, the Consultant will measure the ground water level and perform water pressure tests (Lugeon tests)
using suitable mechanical or pneumatic packers to determine the water bearing characteristics and rock mass
condition of the rock. Use of drilling mud or other substances that may affect the permeability of the rock will not
be permitted. The packer used will be of double type.
The Consultant will arrange an adequate source of clear water, pumps capable of delivering water at rates up to
130 liters/minute at pressures up to 10 kg/cm 2, packers capable of sealing off portions of the hole under
pressures of up to 10 kg/cm2, water meter (s) reading to the nearest 0.5 liters per minute with an accuracy
within 10 percent, gauge(s) for reading water pressures up to 10 kg/cm 2 with an accuracy of 10 percent, a
stopwatch, valves to allow regulation of flow pressure, and other equipment necessary to conduct the tests.
The hole will be flushed with clear water prior to pressure tests. Tests will be conducted either progressively from
the bottom of the hole upward for the entire portion of the hole in rock, or for isolated segments of the hole.
Water pressure tests will be carried out in each borehole at 3 m intervals in general. Adequate reasons &
evidences will be provided if the no of such test has to be reduced due to some site specific conditions such as
hole collapse. The test pressures for each section will be changed at five steps. Prior to starting the test, three
gauge pressures will be selected, minimum, maximum and intermediate. Flow rate of injecting water will be
observed under each step of the pressure for 10 minutes after the flow rate becomes stable and will be recorded
at every minute.
The Consultant will submit the daily report of the field permeability test for each test stages in suitable format.
The report will include, but not be limited to the following information.
4 Date, hole no, test no, location
4 Packer type, hole diameter
4 Depth of packer setting and the bottom of borehole
4 Test length
4 Gauge height above the ground
4 Depth of water table
4 Pressure of water supply
4 Test period 10 minutes
4 Time of test
4 Name and signature of person conducting the test
4 Depth of casing
4 Pressure test results
For seismicity study, Consultant will review the pertinent and available geological and seismological data, make
a determination of the seismic exposure of the project, and recommend seismic design parameters for the
various major elements of the project. The Consultant will identify and locate the major regional and local
tectonic belts in the vicinity of the projects site and will assess the effect of those tectonic activities on the
hydropower component. For the analysis of seismicity in the region as available from the DMG Nepal and World
ITECO – AFC – TMS JV P a g e | 30
Consulting Services: Feasibility and EIA Study of Kimathanka Arun Hydropower
Project
3D METHODOLOGY
Seismicity Network along with discrete fault effects will be studied and appropriate seismic loads will be
proposed in terms of seismic acceleration coefficient, design accelerograms etc. Apart from this, the Consultant
will focus on the following parameters:
Detailed investigation of fault structure in the project area and its surrounding.
Assessment of magnitudes and locations of past earthquake events. The program should include
determination of fault plane and focal depth for some of the larger events near the dam site. Information
available from Department of Mines, Government of Nepal may be used for this purpose. Determination
of dynamic response profiles for accelerations and velocities applicable at different elevations on the
dam for the Design Basis Earthquake (DBE) and Maximum Credible Earthquake (MCE) including likely
damage to structures for each case.
Investigation on possibility of reservoir induced seismicity after the impoundment of reservoir.
Recommendation on the needs for establishment of the seismic network in the project area and
preparation of the technical specification of the equipment (seismographs, accelerometers etc.) for
procurement and installation by NEA.
Review the pertinent and available geological and seismological data.
History of earthquakes in project site with epicenter(s) and date(s) of occurrence etc. and details of
seismological data collected from the seismological observatories installed by National seismological
center /Department of mines and geology/ GON and other available sources and evaluation of seismic
status of faults, thrusts and other weak features etc.
Need assessment for establishment of new seismic observatories considering the location of seismic
observatories station established earlier
Seismic activity in the project area will be analyzed using history of earthquake that secured in and
around Nepal.
The result will be supplemented by examination of the study of satellite images and aerial photos.
Seismic risk will be specified in term of value and kinematic of co-seismic displacement and the return
period in case of earthquake due to cross cutting of the active fault in the project structure.
Based on the available information and assessment of local and regional seismicity, the seismic design
criteria of structures will be calculated
1990
Shrinkage limits test ASTM D-427; AASHTO T- 92.
Grain size analysis BS 1377:PART 2:1990
Standard Proctor compaction BS 1377: 1975 TEST 12
Specific gravity test ASTM D5550 -06
Triaxial tests if necessary BS 1377:PART 8:1990
The consultant will also conduct preliminary study for development of small hydropower project nearby the
project area and conduct the preliminary level of study of selected proposed hydropower project in order to
identify/set the parameters/features of the project for further investigation/study.
In addition, the consultant will conduct socio-economic baseline survey of the families whose land will be
acquired by the project and/or that will be directly affected by the project. The intent of this survey will be to
provide a basic data for acquisition of land and baseline socio-economic condition of the direct project affected
families.
The Consultant will provide to the Client a Design Criteria Report defining all the parameters, standards,
assumptions to be used and followed during the design activities for the seismicity, geology, hydrology,
hydraulics, stability, structural and materials. In this report the international experience of our consortium will be
used widely to allow the Client for having a reliable and safe project.
The Design Criteria Report will include the following items;
The Consultant will propose the intake and tailrace sites to best utilize the available head. If possible, the intake
site will be shifted upstream while tailrace site will be shifted further downstream to increase the gross head.
Efforts will be made to reduce the head loss between various component structures such as headwork,
desander, tunnel inlet, powerhouse and tailrace. For the purpose, the rating curves of the intake and tailrace will
be carefully developed with the most likely roughness parameters.
The installed capacity in hydropower projects is optimized considering the range of installed capacities and
correspondingly with the range of design discharge. The capacity optimization will be constrained by fixed
design discharge. However, the consultant will make efforts to optimize the capacity with other parameters as
much as possible. As a quick check, the capacity and cost of the hydropower component was estimated using
Hydrohelp1 software. The result shows that the capacity of the plant may increase. This will be carefully
assessed during the design stage.
The Consultant will conduct a constructability analysis of the various project components to ensure that the
proposed structures can be erected at the specific site with the available construction technologies, equipment
and manpower.
While carrying out the designs, the Consultant will carefully consider the appropriateness and applicability of the
designs, techniques and solutions to the project site conditions. For example, underground surge tank may be
more promising where rock conditions are good and the possibility of surface surge tank is not appropriate for
the site condition. Similar will be the case of underground versus surface powerhouse. The Consultant will
prepare comparative analysis of the surface versus underground facilities and through consultation with the
Client, will finalize the finally chosen options.
Similarly, there exist options for various types of desanders, tunnel supports, penstock shafts, gates, valves as
well as hydraulic turbines. Where such alternatives exist, the Consultant will prepare comparative analysis and
present to the Client prior to the actual design. Some design methodologies for the key structures and facilities
are presented in the following section.
The methodology of tunnel excavation and support design will be based on the rock mass characteristics. The
prevailing practice is to make use of the Beniaski’s Rock Mass Rating (RMR) and Barton’s Tunneling Quality
Index (‘Q’) system of rock classification. As an initial design, the Consultant will adopt these systems for rock
classification and tunnel support design. These will provide guidelines for the rock support types and stand up
time. The convergence measurements will be required during the construction period to adjust / modify the
support application and timing.
The Consultant will formulate design base memoranda for each of the structure partly or wholly and seek prior
approval before using it in engineering design and calculations. Where the design memoranda is approved in
parts, engineering design and calculation will be done only for that portion and the structure revisited after the
remaining criteria is approved. Also, the Consultants will use standard software like PHASE 2 or equivalent for
the determination of tunnel support and other works. If such software is used the report should contain
information on basic methodology of the analysis/design.
Figure 19: Sample Procedure for Design of Tunnel Supports Based on Tunnelling Quality
Index ‘Q’
The latest advances on the tunnel design and analysis have come up from Hoek and Brown (1996), which use
separate rock mass classification called Geological Strength Index (GSI) which are demonstrated to correlate
better to the engineering parameters such as Young’s modulus, deformation modulus, tensile strength,
compressive strength etc. The Consultant will apply these state-of-art solutions to the best benefit of the project.
For the application of the solutions, available software such as ROCLAB and EXAMINE2D will be used
extensively.
v) Surge Shaft
The requirement of surge shaft is dependent on the topographic and geotechnical conditions of the project site.
Because of the need of wider underground opening, the surge tank will require more extensive support
requirements including shotcrete / fibercrete, concrete, rock bolts and steel liner. For low depth below the static /
dynamic head, concrete lining may suffice, while for larger depth, steel liner will be required to withstand the
large internal pressure resulting from hydrostatic and hydrodynamic reasons.
The Consultant will carry out transient analysis of the surge shaft operation following the prevailing guidelines.
Apart from the specified guidelines, the references of E. Mosonyi will be extensively followed. For the purpose,
customized worksheet computations will be made, from in house spread sheets.
vi) Penstock
The penstock is the most important element of the hydropower system. The penstock needs to withstand large
hoop stresses caused by the hydrostatic and hydrodynamic reasons. The water hammer effect also needs to be
considered adequately for the design of the penstock. The penstock can be surface type (saddle supported or
partly buried) or alternatively it may be completely underground (inclined shaft or a combination of vertical and
horizontal shaft). While slope stability aspects will be crucial for surface type penstock, rock stress / stability
problems will encountered for underground shafts. As a conservative measure, the entire hoop stresses
resulting from internal hydrodynamic pressure needs to be resisted safely by the steel liner. In this case, the
steel liner thickness will be same in surface and subsurface types of penstocks. However, for underground
vii) Powerhouse
The design of the powerhouse is the most complex one and need coordination of different disciplines. The
starting point will be the sizing of mechanical and electrical equipment to be accommodated within the
powerhouse premise. The number of sets of the generating equipment and setting (vertical / horizontal) will have
major effect on the sizing of the powerhouse. At this point of time, it is anticipated that the turbines and
generators will be set vertically; however, the implications of alternative setting will also be assessed and
recommended accordingly.
The Consultant will be study the variants of vertical versus horizontal setting of turbine-generator units and will
adopt the most optimal variant for further detailed engineering design of the powerhouse foundation and
superstructure.
The number of floors within the powerhouse will be dependent on the functional requirement of the various
electrical and mechanical equipment. The appurtenances such as cooling system, governing system, spiral
casing, nozzles / wicket gates, excitation arrangement, lifting gantry crane arrangement, cable ducts, assembly
hall requirements, control room requirements etc. will dictate the levels and sizes of the rooms / floors.
Facilities such as transformers and switchyards can be either integral with the powerhouse (indoor type) or
separate (outdoor switchyard). The decision on these options will depend on the space availability at the site. It
is notable that Gas Insulated Switchgear (GIS) system is highly compact and can be accommodated safely
within a small room while the conventional outdoor switchgear needs a large area depending on the number of
machines, double bus requirement, single / double circuit etc. The possibility of using gas insulated switchgear
(GIS) will be discussed with the Client on the basis of preliminary costing of the two alternative systems and the
final design will be based on the agreed option.
Similarly, the design of electrical equipment will include design of the following:
Generator; including its excitation system and neutral grounding equipment;
Main circuit equipment, including cable bus, unit circuit breaker, etc.;
Main power transformer;
A project schedule will be prepared which will highlight the key events and major milestones. The critical
activities and the critical path of activities in the schedule will be illustrated. Based on the finalized scheme
layout, a detailed construction program will be prepared using the critical path approach with the help of an
appropriate computer program. The minimum economic construction time will be determined and critical
activities identified. The number and location of construction sites, access requirements, and infrastructure and
spoil tip locations will be determined. This work will be carried out in parallel with the design.
Regarding electromechanical equipment and hydro mechanical equipment, the time and periods required for the
design, raw material supply, manufacturing, shipping and erecting will be considered. The schedule will be
prepared taking into consideration the construction of the temporary facilities, the construction methods,
construction equipment, quantities of works etc.
The Consultant will make use of standard project management tools such as Primavera or MS Project to
develop and later monitor construction and implementation schedule.
Based on the cost estimate and project schedule, a detailed cash flow statement will be prepared. The cost
estimate will be prepared in accordance with international practice. The cost for civil works will be based on
quantities taken from the design of the various structures, and unit costs established with reference with regional
costs of materials and labor.
The cost of equipment will be based on investigations of international market prices. The cost of operation and
maintenance will be estimated on an annual basis and expressed as a percentage of the investment costs for
the project components. The Consultant is able to draw upon its experience of costing various hydropower
projects and other construction works in Nepal.
The cost estimate will take into account access, site infrastructure, all temporary works and services, footbridges
and water supplies. Consideration will be given to the likely construction methods. Contingency sums will be
included which will allow for items, which cannot be adequately defined at Detail Design stage.
The cost of mitigating environmental and social effects will be included as a cost to the project. The construction
management costs for the construction and engineering will be included as a separate items in the estimate.
The Consultant will carry out load flow and transient studies and determine transmission requirements to
transmit power to the load centres in Nepal and northern India. The Consultant will also determine substation
requirements at interconnection points to the regional electricity network.
The study will calculate the Net Present Value (NPV), Benefit Cost ratio and Economic Internal Rate of Return
for the Kimanthanka Arun Hydropower Project. In such calculations, the benefit stream will be derived from the
annual consumer willingness to pay for incremental power consumption from the Kimanthanka Arun Hydropower
Project, any displacement of existing more expensive electricity generation, plus any environmental benefits
associated with avoided carbon emissions. The costs will include all the incremental economic generation,
transmission, distribution, and environmental/ social costs and losses associated with electricity production from
the Project.
The analysis will be an economic evaluation excluding taxes, duties, currency exchange fluctuations, and other
influences that affect the value of the cost and benefits. A constant currency basis will be selected and all costs
and benefits will be valued with a common base. The resulting analysis will be acceptable to the multilateral
lending institutions as a basis for economic evaluation of Kimanthanka Arun Hydropower Project.
Sensitivity analyses will be prepared to assess the importance of the key factors that may be uncertain. This
may include uncertainty in the estimated construction and operation cost due to foreign exchange valuations,
variation in the discount rate, fuel cost escalation, project capital cost, construction schedule, and energy
demand forecast.
The economic analyses will be presented in sufficient detail to satisfy the requirements of the major lending
agencies. In addition, the Consultant will discuss how Clean Development Mechanism (Carbon dioxide Emission
Reduction) credits can be included in the Projects. The consultant will also calculate the quantum of Co2
emission reduction by the development of this project.
Other benefits identified in earlier tasks will be investigated and quantified for inclusion in the economic
analyses, if appropriate.
Costs.
o Construction and equipment supply costs (including import duties).
o Development costs. (Developer, lenders’ legal and financial advisory, land acquisition,
environmental studies and mitigation, working capital, O&M training and set-up, etc.).
o O&M costs.
o Fees for water use.
o Fees for administration and regulatory charge.
Financial Parameters.
o Debt/equity ratio.
o Loan conditions (repayment term, interest rate, and grace period).
o Period of analysis.
Tax Considerations.
o Only taxes associated with construction and equipment supply are to be considered. Tax
considerations related to DoED’s tax position could be included in the analysis if such criteria
are provided.
The financial analysis will include projections in current prices and in fixed prices of the base year of calculation.
By applying an international rate of inflation, calculations will be made in current prices. The financial model
results will include key performance indicators for the next 10 years to assess the Project and its institutional
financial viability.
Sensitivity analyses will be prepared to assess the importance of the key factors that may be uncertain. This
may include uncertainty in the estimated construction and operation cost due to foreign exchange valuations,
variation in the inflation rate, project capital cost, construction schedule, and energy demand forecast.
Financing options will be investigated during this phase since the results will affect the tariff outlook for the
Kimathanka Arun Hydropower Project. The review will include discussions with DoED, as well as with
prospective financing sources internationally. The possible framework for financing will be established along with
the likely cost of debt and its associated charges for guarantees.
3.3.10 Analysis and Modality Finalization of Institutional Arrangement for Project Implementation
Institutional arrangement is a crucial aspect for any project implementation. The project if viable can be
implemented under various modules like Government Agencies and BOOT module. The advantages and
challenges relating to each of the implementation modules will be thoroughly analysed based on the experience
from similar projects. The findings will be explicitly listed in the report. We will analyse the capacity of existing
institution for project implementation and propose a suitable modality for the project. Also, we will assess the
improvements required in the existing institutional arrangement for the project implementation. While doing so,
the consultant will critically analyse alternative institutional set ups to smoothly carryout the project. The
consultant will also clearly identify the resources including but not limited to capacity building measures
(trainings, workshops etc.) physical infrastructures, requirement of software, equipment etc.
The Power
Market, Power Within 18 Describe the power market in Nepal and
System and months of India and include results of the power
5 20 As stipulated in RFP
Power signing of system studies and power evacuation
Evacuation Study contract studies.
Report
6 The Interim 20 Within 20 Include the findings of project layout and As stipulated in RFP
Design Report months of opt1m1zation, hydraulic design, hydro-
signing of mechanical design, electro-mechanical
3.4.5 The Power Market, Power System and Power Evacuation Study Report
ITECO – AFC – TMS JV P a g e | 45
Consulting Services: Feasibility and EIA Study of Kimathanka Arun Hydropower
Project
3D METHODOLOGY
The report will describe the power market in Nepal and India, will present the results of the power system studies
and power evacuation studies.
Progress made in field survey and investigation works carried out up to this period.
Finding, analysis and interpretation of data of different field survey and investigation carried including
hydraulic design, hydro-mechanical design, electro-mechanical design and electrical design.
Preliminary layout, preliminary design and outcome of optimization study.
Design, optimization, calculations, test results, quantity estimate, cost estimate ,drawings, construction
planning, power evacuation plan, economic and financial analysis, sensitivity analysis.
Entire design calculation sheet including the complete draft report in electronics form.
Land and property inventory report and socio-economic report.
Construction Planning
Appropriate contract module
Project Implementation arrangement
Draft tender documents and tender drawings as separate volume
Entire draft final report in electronic form
Design, project optimization, drawings, quantity and cost estimates, construction planning, power
evacuation plan, economic and financial analysis.
Updated Version of draft final report incorporating comments of DoED.
Two copies of the electronic form of entire final report including the complete report, drawings and all
calculations in actual working format as xls, dwg, doc, etc. as well in pdf format.
The Consultant will conduct EIA Study of Hydropower Project in accordance with the requirements of EPA and
EPR and safeguard policies with regard to environmental protection and resettlement. The EIA study will be
carried out in conjunction with the technical team of experts for feasibility study.
4.1 Approach
With the understating of the proposal objectives and scope of works, the consultant intends to embark upon the
services with the following management approaches:
In fact the consultant has looked this project as an opportunity for enhancing professional development in the
sector and would like to assure for providing services, which will meet the intended objectives and expectations
of the client. Besides, for the quality assurance of the Project works, the consultant will establish a Backstopping
support for technical and administration support to the consulting team. The objective of such “Backstopping
Support” with “Backstopping Staff” is to assist in maintaining quality assurance system, provide required facilities
and support to the team, and establish expert problem solving mechanism besides auditing the performance and
taking preventive and corrective measures aimed for quality performance.
4.2 Methodology
The Environmental Impact and Social Safeguard Studies of Kimathanka Arun Project will be carried out in
conformance to guidelines and regulatory requirements as per the terms of reference specified in RFP
document.
As per the Government of Nepal’s requirement, the Environmental Impact Assessment (EIA) process for the
proposed project would primarily involve two stages:
The methodology that will be adapted to complete different phases of the EIA study is briefly presented in the
following section. As per the Government of Nepal’s Environmental Protection Act 1996 and Environmental
Protection Regulations 1997, the general steps involved in proposed EIA is presented in Figure 22, through
schematic representation:
Available literature pertaining to the following areas will be collected and reviewed from various organizations:
4 Secondary available baseline (physical, biological, and socio-economic – cultural archaeological) of the
Project location, reservoir areas, including adjoining areas from different sources;
4.2.1.3 MAKING A PLAN FOR PUBLIC INVOLVEMENT AT KIMATHANKA ARUN HYDROPOWER PROJECT
This task Objective involves:
Concomitant to this activity, a plan will be prepared in consultation with DoED for initial public interaction through
scoping session, interaction programs, talk programs, etc. which will be announced to the stakeholder in
advance.
The Environmental engineer, Sociologist, Public Outreach Expert, Resettlement Expert in co-ordination of the
study team members will undertake the job. The deliverable of the task is the preparation of Public Information
Brochure for Dissemination and to Plan Initial Public Interaction with regard to the Project impacts and benefits
so as to get maximum Input from the Stakeholders to Flag the Environmental Issues for detailed study.
Environment and Social Safeguard team will prepare the notice in consultation and approval of DoED and give it
for publication in the National Daily Newspaper. The Deliverable of the task is to inform all the stakeholders on
the proposal and give time to give their reaction, comments and suggestion if any on the Project particularly
focusing to environmental and social issues.
4.2.1.5 WALKOVER SURVEY OF PROJECT AREAS AND KEY KIMATHANKA HYDROPOWER PROJECT STRUCTURE SITES
Environment expert, environment engineer, sociologist, botanist, aquatic life expert, wetland expert, zoologist,
public outreach expert, forest expert, land use planner, archaeologist will visit the Project for walkover survey.
The deliverable of the task is to provide more people an opportunity to know about the Project and raise
pertinent issues.
4 present the findings of literature review and field walkover survey on the various aspects of the
environment to the stakeholders affected by the Kimathanka Arun Hydropower Project;
4 gather additional information from the stakeholders on the environmental issues in reference to the
project;
4 gather and document stakeholders environmental concerns of the project that need serious
consideration for EIA including SIA;
4 prepare a reference material for the preparation of scoping document and TOR for EIA study.
Environment expert, resettlement expert, environment engineer, botanist, zoologist will accomplish the job as
per the agreed upon plan at the local and central level. Several interaction sessions will be planned at site in
consultation with DoED. The deliverables expected from the task is the feedback from the stakeholders on the
various environmental and social issues that need consideration in Environmental impacts and safeguard
studies of the project.
The environmental expert, sociologists, resettlement expert, forest expert, public outreach and other proposed
team members will accomplish the task. Depending upon the local conditions and the information available,
technical experts will devise and use matrix tools to screen out the potential environmental impacts (adverse or
beneficial) from the Projects based on the existing baseline conditions and experiences from other projects
implemented elsewhere implemented in similar geographical terrain. The deliverables expected from the task is
a list of potential environmental and social issues of the Projects development in the area.
The proposed environmental and social experts, and the scoping workshop participants during scoping, based
on Delphi technique will assign the significance to the issues raised by stakeholders and identified by the
technical team. The expected Deliverable of the task is to list out the insignificant and irrelevant issues for further
considerations.
The proposed team of environmental and social experts will evaluate each of the identified significant
environmental issues for the purpose of prioritization for environmental and social considerations. The
issues will be prioritized in the context of the proposed project and its activities in different phases of
project construction and operation.
The method for prioritization for EIA , and social impact consideration will be based on:
The task deliverables is the list of priority primary and secondary issues for the construction and operation
periods with justification for further environmental and social impact studies. The task also provide details of the
types of assessment and level of study to be conducted with regard to each of the issues prioritized as primary
and secondary in various environmental sector.
All this will culminate into preparation of the scoping document, the structure of which is described below. The
detailed timeline for undertaking these activities, including other tasks commensurate to the suggested approach
and methodology is presented in work schedule.
4.2.2 Preparation of Scoping Document (SD) and Subsequent Terms of Reference (ToR)
Preparing the Scoping Document (SD) and subsequent Terms of Reference (ToR) as per the Environment
Protection Act-2054 and Environment Protection Rules-2054. Before proceeding with the EIA, the ToR and
Scoping documents need to be approved by the Ministry of Science, Technology, and Environment (MoSTE) of
Government of Nepal (GoN).
Suggested chapter and the broad content of a scoping study proposed for the Project is detailed below in Box-2.
Box-2: Chapters of scoping document (SD) for EIA (including SIA) study
Chapter Introduction, will present a brief background of the Project, introduce proponent, present
One: brief description of the Project, list and discuss briefly the relevant legislation, guidelines,
standards, and international convention that attracts the proposal, objective of scoping and
finally delineate the Project area.
Chapter Existing Environmental Condition will present the baseline environmental
Two: conditions of the Project, particularly focusing various aspects of physical,
biological, socio-economic and cultural environments.
Chapter Scoping Methodology will describe in brief the different methodological tools utilized such as
Three: literature review, public notice, walkover survey, scoping workshops, focus group
discussions and methods of issues identification and prioritization.
Chapter Issues Identified and Raised, will list with brief discussion the environmental issues raised at
Four: various platforms and forums by the stakeholders and those identified by the team of
experts.
Chapter Issues Prioritized for EIA Study, will present the list of issues prioritized by the team of
Five: expert with justification. It will also present a short account of the level of study requirements
for the full evaluation of the identified environmental issues. Prioritized issues will be
presented in five broad categories as suggested in TOR such as Physical, Biological, and
Socio-economic and Cultural.
Chapter Work Schedule for EIA Study, will present a Work Schedules for the study based on the list
Six: of issues prioritized and the level of study required.
As demanded by ministry of energy and MoSTE, the document will be presented to the review committee on
behalf of DoED. Upon receipt of comment and suggestions, final Scoping document will be prepared and
presented to DoED for final approval from the MoSTE. The environment and social team from consultant site
and team leader will be responsible for the review presentation.
The Deliverable of the task will be to prepare and present an Interim scoping report for comments from DoED, to
prepare a draft final scoping document for review and approval from the concerned authorities and preparation
of final scoping document for final approval incorporating the comments and suggestion of Department of
Electricity Development (DOED), Ministry of Energy (MoE) and MoSTE.
The objective of the ToR is to frame clear and concise guideline for the EIA Study. As stipulated in the schedule
4 of EPR and Manual for ToR preparation (DoED). The terms of references document will cover the following
sub task as detailed in Table 8.
Guideline for Based on the available information of Scoping Document and the nature of the
Monitoring proposed project, a methodological guideline framework for the identification,
Requirements selection and preparation monitoring indicators in the different phases of project
development will be provided. This will broadly indicate the monitoring
frequencies for identified indicators, monitoring methods, responsible
monitoring agency, and cost of monitoring. A format of Environmental Monitoring
Management Plan will be indicated for the presentation. The team of experts in
consultation with DoED will prepare this section.
Guidelines for Relevant Based on the scoping document and the review of the schedule 4 of the EPR,
Information guideline for the incorporation of other relevant information such as cited
references, maps, designs, tables, chart, graphs, questionnaires, list of persons
Though the scope and methods of study will be more precisely defined by the approved ToR of the Project in a
later phase, the major tasks and the methodologies that will be applied for the study have been identified based
on past experiences in similar projects.
The objective of field survey and data collection is to verify the data collected from different sources and to fill
data gaps that helps prepare detail baseline and to objectively analyze and predict environmental impact on
issues that are likely to emerge due to the implementation of the project. The following key steps will be involved
at this stage (Box-3):
The tools proposed to apply for the field data collection on different aspects of environment will be as follows:
Different methods and tools to be adopted and responsible personnel for the study on physical environment
aspects are depicted the in the Table 9.
No. of
S. N Environmental Attribute Frequency Remarks
Locations
nitrogen, phosphorus, power house etc)
potassium (NPK), calcium, magnesium,
chloride, sulphate, carbonate, iron, copper,
zinc, boron, sodium, cation
exchange capacity, alkali metals, Sodium
Absorption Ratio(SAR), permeability,
water holding capacity.
4 Noise
. Levels 6 Once during the Noise levels will be
study period monitored on hourly basis
for 24 hours using
continuous noise monitoring
equipment. (Submergence,
reservoir, power house etc)
6. Traffic 2 Once during the Traffic movement will be
study period monitored on hourly basis for
24 hours (to and from
directions).
4 Type of vegetation and forest will be identified based on the species composition.
4 Forest sampling (random sampling, systematic sampling, stratified sampling or selective sampling as
appropriate) will be done to collect quantitative baseline information on the forest structure, composition,
density and dominance. Canopy cover of tree species will be measured by visual observation.
4 The data from forest sampling will be quantitatively analyzed for frequency, density, basal area, relative
basal area, crown coverage, important value and estimated wood volume. Based on this information, the
loss of wood and volume will be calculated using Quarter Girth formula.
4 Biodiversity value will be estimated as low, moderate and high applying standard tools. Ethno-botanical
information will be obtained by conducting Rapid Rural Appraisal method. Wildlife survey will be carried
out by direct and indirect evidences for identification purpose.
4 For identification of birds the standard key developed by Fleming et. al., will be followed. Rare,
threatened and protected plants including medicinal plants and wildlife species will be grouped into
different categories and focus will be given for such species on the basis of their present and
distribution, their decline in numbers over the course of time, their abundance and their potential
biological value.
Aquatic Environment: Based on the information collected from published reports, research articles, information
available from public domains, through consultations etc. on aquatic flora and fauna a database of information
on aquatic environment will be developed. Zoologist/ Aquatic Life expert in association with environmental expert
will conduct the survey and collect the samples for identification and assessment of fish and other forms aquatic
lives, threatened and endangered species of aquatic flora and fauna etc. will be identified and listed. A detail fish
sampling will be performed in U/S dam and in dewatered zone. Different methods and tools to be adopted on
biological environmental aspects during the baseline study in Kimathanka Hydropower Project are depicted in
Table 11.
Table 11: Study Methods and Responsibility, Biological Environmental Aspects
Methods and Tools for No of Frequency and
SN Sub-tasks Responsibility
Study locations locations
1 Terrestrial Use aerial photographs and About 25 During Botanist/ Forest
Flora Study delineate the different quadrats (as summer and Expert
forest/vegetation types and status suitable Winter
and transfer it to depending Seasons at
topographic maps for field survey upon the Submergence,
Identify vegetation samplings
terrain of the Reservoir,
plots (20mx50m) in the
topographic plots for all forest area and as Power house,
types and status for direct impact recommended Office/Staff
zones and representative sites for by MoSTE) quarters,
Deliverable of the above field studies is the preparation of sound baseline database of the three components of
the proposals. The collected data will be compiled, collated and processed by using different computer software
packages, as appropriate, for the socio-economic and resettlement/rehabilitation assessment including
vulnerable community development plans in the subsequent tasks as per the requirement of environmental and
social assessments.
Few of the identified sources for collecting secondary data include the following:
The stakeholder consultation and analysis would follow the following approach:
Besides, the consultants would assess the needs of public consultations and meetings at different times and
places as stipulated in the ToR with a view to increase interactions among all parties concerned. Such
consultations and meetings would allow effective communications between project personnel and local people
and help promote effective understanding and minimize potential conflicts. The consultants would design such
The consultant will also give due consideration to the following activities while predicting and evaluating the
impacts:
4 Cut and fill during construction of the proposed project components
4 Maintenance of top soil that may be disturbed and displaced due to cut and fill
4 Reinstatement of all infrastructures disturbed and other quarry and burrow pits used during the
The environmental and social team of experts under the EIA (including SIA) team leader will be collectively
responsible for the above task. Identification of critical environmental areas and the measures to protect them
will be deduced from physical environment assessment on different parameters.
The prime responsibility of these tasks is of the wildlife expert, Zoologist, Aquatic Life Expert, Botanist, and
Forest Expert. From the assessment composition of fish in the river, migratory fish species, fish spawning,
seasonal and lateral migration of fishes, management system of fish population in the changing environment will
be deduced. Likewise composition and status of wildlife terrestrial fauna, identification of endangered fauna, and
effect of the dam, power house and irrigation canal will also be predicted. Composition and status of forest and
watershed in the area, impacts of the Project to these resources, identification of sensitive ecological zones and
endangered flora will be ascertained, which will help to propose mitigation measures in the subsequent task.
Further, each of the benefit augmentation and /or adverse impact mitigation measures will be prescribed in time
line for pre-construction, construction, and operation period with details of responsible authority for
implementation and costs, if required for mitigation. (Box-6)
Identify permanent and temporary socioeconomic impacts arising from land acquisition, changes in land use,
and restrictions of access as a result of construction of the Project facilities, including measures to minimize the
number of affected land users within the river catchments including upstream and downstream areas. The
consultant will identify and evaluate social and economic impacts resulting from project implementation,
including but not limited to, the types of social impacts, the extent and severity of these impacts.
The social impact assessment will take into consideration the aspects related to construction areas; quarry
areas, spoil disposal areas construction camps, community resettlement areas, access roads, power
transmission line/corridors. Also the impacts both upstream and downstream will be taken into consideration.
Based on available information issues on socio-economic and cultural environment will be analyzed and impacts
will predicted in terms of their magnitude, extent, duration and significance. On the methodology aspect it will be
more or less similar to the impact assessment methodology suggested for environmental impacts (Refer to Box
detailing Impact assessment methodology).Major socio-economic and cultural issues to be considered, but will
not be limited to the following:
The sociologist, financial analyst/ environmental economist and other social safeguard support team will be
responsible for the identification and prediction of the socio-economic and cultural environmental impacts.
Mitigation measures for adverse social impacts will follow the same methodology as for addressing the adverse
environmental impacts. However, the same would be based on a dedicated qualitative consideration too.
The social and environmental criteria for analysis of alternatives will be based on examining alternatives in
terms of:
· Minimum disturbance to ecology,
· Minimization of land acquisition.
· Institutional training and monitoring requirements
· Suitability under local conditions
· Capital and operating cost
· The extent of social impact
· The extent of environmental impact
4 Prepare Environmental Management Plan (EMP) covering, but not limited to, the following:
4 Erosion and sedimentation control, spoil disposal and management, quarry management, water quality,
reservoir clearance, chemical and used oils and lubricant waste management, hazardous materials,
emission and dust control, noise control, physical cultural resources, vegetation clearing, landscaping
and re-vegetation, solid waste management, use of explosive materials, and any other construction
related issue.
4 The measures for management of social impacts will include, but not limited to, management required to
mitigate the impact due to change in land use patterns, employments, compensations, water quality,
seasonal flooding, soil degradation, and bank soil stability/erosion and land use changes, fire hazards,
river transportation, inundated forests, impediments to movements of animals, cattle, people, and
disruption of communication between communities, loss of land, land disputes, increased flooding, water
borne diseases, loss of social fabrics, negative impacts on fishing activities, inability to afford new
technologies and impact on ritual sites.
4 Management of operation related impacts which will include reservoir inundation, water quality, riparian
release and management of other identified impacts relevant to the operation and maintenance stages.
Based on the findings of EIA, comprehensive Environment and Social Management Plan (ESMP) will be
prepared. The ESMP will be covering some of the issues, but not limited to:
4 erosion and sedimentation control, spoil disposal and management, quarry management, water quality,
reservoir clearance, chemical and used oils and lubricant waste management, hazardous materials,
emission and dust control, noise control, physical cultural resources, vegetation clearing, landscaping
and re-vegetation, solid waste management, use of explosive materials, and any other construction
related issue.
4 The ESMP will also identify different stakeholders and will delineate roles and responsibilities with the
provision of budget and other resources required for the effective implementation of the plan.
The objective of the plan is to ensure that the mitigation, monitoring and environmental enhancement measures
are timely implemented and the degree, extent and magnitude of environmental impacts due to the Project
implementation are within the threshold limits, which do not cause to disturb the naturally balanced environment.
The prime responsibility of formulating the plan lies with the team leader. However, he will be assisted by other
sector specialists to formulate the plans.
The ESMP besides the generalized Mitigation Management Plan and Monitoring Management Plan, will
incorporate, Acquisition, Compensation, Resettlement and Rehabilitation Plan (RAP), Social Management Plan
(SMP), and other as appropriate and as per requirement with the consent from the client. Resettlement Action
Plan, has been identified as a separate task owing to the complexity of the task involved (kindly refer to the
respective task)
4 Assess the pre-project baseline information in conjunction with the Project current baseline information
4 Assess predicted impacts in the EIA report for defined activity in the Project development in relation to
the actual impacts;
4 Assess provided mitigation measures in the EIA report to minimize the impacts of defined activity in the
Project cycle and their effectiveness;
4 Assess of implementation status of the mitigation measure in the Project cycle as specified in the EIA
report;
4 Assess the effectiveness of the monitoring works for the implementation of mitigation measures and to
evaluate the effectiveness of the mitigation measures;
4 Assess any corrective action suggested or undertaken to mitigate the impacts of the defined activity and
their effectiveness;
4 Assess compliance and non-compliance with the mitigation and monitoring provisions
4 Assess compliance and non-compliance with the national environmental standards in the Project
development and operational cycle and
4 Provide conclusion and recommendations from the experience learned to strengthen impact prediction
in future projects for the defined activities.
4 Generally, the impact indicators are concerned to population growth due to immigration, pressure on
local resources (land, forest, drinking water etc.), health, hygiene and sanitation condition of the people,
education of children, marginalization effects on local poor, ethnic minorities and women, social and
cultural disintegration in the society, conflicts in the use and sharing of resources etc.
4 The magnitude of effects of each indicator will be assessed in order to examine the seriousness of the
problem to the affected population.
4 Based on the nature and extent of the effects, probable mitigation measures would be suggested. The
mitigation measures to minimize the adverse impacts include awareness development among local
communities, development of social infrastructures (schools, health facilities, drinking water), health,
hygiene and sanitation awareness program, skill development and income generation of local people,
particularly the ethnic minorities and women, development and promotion of alternative energy devices,
linkage development of local production and marketing, relocation, conservation or protection of sites
having religious, cultural and historical importance.
4 The social management plan will also assess the impacts related to following, and
depending upon the risk ranking, will include it in the management plan if required:
4 management required to mitigate the impact due to change in land use patterns, seasonal flooding, soil
degradation, and bank soil stability/erosion and land use changes, fire hazards, river transportation,
inundated forests, impediments to movements of animals, cattle, people, and disruption of
communication between communities, loss of land, land disputes, increased flooding, water borne
diseases, negative impacts on fishing activities.
4 Management of operation related impacts which will include reservoir inundation, water quality, riparian
release and management of other identified impacts relevant to the operation and maintenance stages
The sociologist, anthropologist, public outreach expert, public health expert will be responsible for the
preparation of SIA and subsequent Social Management Plan (SMP). The necessary budget to implement the
plan would be estimated based on the details of the programs and activities. A schedule of implementing these
plan measures, manpower requirements, lead agencies and collaborating organizations including NGOs will be
provided.
Preparation of the RAP will also take into consideration the best practices/ guidelines suggested by IFC & World
Bank, which in most of the cases are the international benchmarks. The host country guidelines will also be
taken into consideration.
The steps for the preparation of the RAP will primarily include the following:
4 The consultants, based on their baseline surveys, would first assess the level of impact related to land,
assets, livelihood, and vulnerability
4 Depending upon the loss assessment, the PAFs would be divided into various categories and
entitlement matrix would be prepared for the various categories of losses and
4 policies and package of resettlement and rehabilitation to the Project Affected Families (PAF) will be
recommended
4 Existing legal provisions will be reviewed thoroughly to make recommendations regarding resettlement,
compensation, and rehabilitation arrangements.
4 In addition, resettlement, compensation and rehabilitation measures undertaken in similar projects in the
past (such as Kali Gandaki 'A HEP, MMHEP, Chilime HEP, Kulekhani HEP), Upper Tamakoshi,
Rasuwagadhi and other will be examined to see practical relevance.
4 Livelihood restoration option for the PAPs/ PAFs with special emphasis on the vulnerable population
(including disabled, elderly etc.);
4 Stakeholder consultation and proposed grievance redress mechanism for PAFs.
4 Institutional mechanism for resettlement action plan implementation;
4 The consultants would identify suitable lands for relocation/resettlement according to the preference of
the people to be resettled. The potential sites will be visited and the host people will be consulted in this
context. The potential resettlers would also be involved in finding such areas. Detailed account of the
host population, ethnicity, their attitude towards the resettlers, the available resources, land prices, other
resources including forest, pastures, drinking water, schools, will be made to ensure that the relocation
of the people does not make any significant adverse impacts to both resettles and the host people;
4 Details of the budget provisions for the specific R&R action plan and specific timeline with designated
responsibility for the R&R plan implementation.
4 Only after a thorough understanding of the situation a comprehensive acquisition, compensation,
resettlement and rehabilitation plan will be developed for implementation.
A team of experts includes anthropologist, land use planner, GIS expert, Resettlement Expert, Sociologist, and
an Environmental Economist would accomplish this task. The necessary budget to implement the plan would be
estimated based on the details of the programs and activities. A schedule of implementing these plan measures,
manpower requirements, lead agencies and collaborating organizations including NGOs will be provided.
Institutional strengthening and monitoring framework will be suggested as required. The ESMP/RAP will identify
arrangement for co-ordination between various governmental departments that may help in strengthening the
capacity to implement environmental and resource management policies.
The Consultant will submit 2 copies of the electronic versions of the approved Scoping, Terms of Reference,
Environmental Baseline and EIA Reports in addition to the hard copies of the reports in requisite number as
mentioned above.
The Consultant will submit the Inception Report after completion of desk study, literature review and field
reconnaissance. Based on information collected, the project work plan will be updated and presented in the
Inception Report. The Environmental Baseline report will provide a description and presentation of
environmental and socio-economic Baseline conditions.
The Consultant will prepare a table of contents for the Environmental Impact Assessment report and submit it to
the Client for comments and approval. The Environmental Impact Assessment Report will clearly recommend
the measures required should the project be developed so that decision makers can use it as a document on
which to base their decision whether to proceed with the Project.
The executing agency of the project is DOED. The Project Manager of project will carry out coordination with
DOED, the Consultant, and other concerned stakeholders. The Consultant's Team Leader will be responsible for
the activities in connection with the consulting services for the project. He will manage and control overall
performance of the Consultant's personnel and will ensure close co-ordination with the Project Manager. Under
the direction of the Team Leader, the Consultant's personnel will carry out the various activities in their own
specialties, with due co-operation of the project staff.
In order to maintain the quality of to a specified level of standard as per specification, the Consultant will have
suitable organization wherein the concerned technical and administrative professionals of all the levels of the
respective organization i.e., Client, Consultant and Contractors, are suitably placed and responsibilities are firmly
defined so that all office and field works can be accomplished as scheduled without compromising in quality.
The overall goal of the quality management is to ensure that all the activities which are necessary to design
services in an effective and efficient way. The four main components of the quality management are listed in the
following steps.
Quality Cycle
Quality planning specifies the main attribute which should be the basis for the quality control (e.g. time,
budget, etc.).
Quality control is performed to ensure that products or services are designed and produced to meet or
exceed customer requirements.
Quality assurance is a more accurate standard for meeting customer requirements.
Quality improvements are implemented by means of a continuous improvement process based upon the
appropriate application of concepts as ISO 9001:2008.
6. WORK PLAN
The work schedule, presented in Form 3H, has been prepared based on the instruction given in the RFP. The
proposed schedule presents logical sequence of tasks on which the inputs of the proposed professional staffs
are based, and their respective task responsibilities. In order to optimize use of the Consultant's inputs, the
reporting schedule is also shown in the work schedule.
7. STAFFING SCHEDULE
To execute the services in line with the proposed work schedule, the Consultant has proposed key professional
staffs to the project according to the staffing schedule shown in Form 3G, Manning Schedule. The allocated time
for each staff has been logically distributed as per the RfP document. However, the Consultant also presumes
that there might be changes on the schedule during the project execution. If such situation arises, the Consultant
will refine its staff schedule accordingly in consultation with the Project Manager. The schedule of the
professionals is so arranged that their assignment is not overlapped.
We understand that the transfer of knowledge in the present context is basically a three way process, between
the client, the Consultant and the Contractor. It is also clear from the data sheet that training is not the main
component of the present assignment. Hence the transfer of knowledge from one party to another by formal
training sessions is not envisaged. However, the most effective transfer of knowledge takes place on the basis of
personal or interpersonal dissemination. This aspect will be carefully considered during the project
implementation, whereby, the knowledge inherent in DoED staff can be transferred to Consultant and to the
Contractor's and vice versa for the benefit of all parties.
To be more specific, we purpose to create an environment conducive to the transfer of knowledge from one
party to another by working together as a team to achieve the specific goal of project completion within the
specific time, within resources allocated, and within the specified quality standard. The transfer of knowledge
from one party to another is likely to take place in the following fields.
DoED personnel may be more knowledgeable with regards to the strategic planning of the projects, the
requirements of the donor agencies, the budgetary provisions from the government, financial regulations etc.
apart from the regular engineering know how. Similarly the Consultants may have better knowledge of the latest
software available for engineering design and constructions management and their actual application in the
Construction. As an example, the Client will be able to formulate a better ToR for the consultants and the
Consultants will be able to prepare better documents in future. So, for the effective transfer of technology to
DoED personnel, nominated DoED engineers will be provided with trainings that include, but not limited to the
following:
The number of participants in the training will be approximately 5 to 10 engineers as nominated by DoED.
Nominated DoED engineers will be provided with a daily allowance for the days present in the training as per the
rate decided with DoED. DoED will be informed a week prior to the start of every training. Training will be based
on the subject aforementioned as well as it will incorporate the problems and conditions encountered at the site
and the necessary solution envisaged and applied during study, analysis and design.
Together with above information, the consultant will prepare training need assessment report and submit to
the project for comments and approval. The proposed trainings presented in above section is indicative only, it
will be finalized with consultation of client.
The mechanism of transfer of knowledge is summarized in the following paragraphs based on limited scope of
the work:
4 Collaborating together
4 Regular discussions on various aspects of project implementation
4 Regular discussions in the progress review and coordination meetings
4 Monitoring and evaluation of the construction activities
4 Site visits to interesting works sites
4 On-the-job training
8.3.1 On-the-job-training
Additionally, the telemetric hydrological station will be handed to DoED in proper working condition after the
completion of study.
The consultant will submit the detail inventory & VAT bills of purchased equipment and articles for making
payment.
* Items to be purchased according to DoED specification and after the completion of the assignment, these
equipment and articles must be handed over to DoED. However among them, one laptop, two computers, one
multifunctional colour printer (print, scan and copy) and one wireless laser printer (A3 size printable) will be
handed in advance to DoED at the time of submission of inception report.