Professional Documents
Culture Documents
p261 PDF
p261 PDF
1. INTRODUCTION
Metropolitan areas in rapidly developing regions feature for indoor & outdoor application alike due
are faced with special problems in augmentation to very short erection and commissioning time.
of their power supply system due to uncontrolled Reduced requirement of maintenance make them
growth, uncertainty of development plans, suitable option for most reliable operation. In fact,
extreme congestion and very high load densities. quality consciousness of equipment alone make
GIS as favoured equipment choice for remote
The continuous growth of large metropolitan cities operation. All these factors in totality make GIS
and industries, which results in concentration of most attractive equipment options to adopt.
the demand for electricity, necessitates installation Though initial cost of equipment is higher than
of distribution equipment upto highest voltage. that of AIS, the choice of GIS with respect to AIS
Use of large size transformers to achieve economy is a techno economic decision to be made taking
of scale and space results in high fault levels into account technical economical &
within these areas. environmental factors.
The population in Mumbai has been growing at a Considering all the above factors Tata Power had
very rapid rate and today , it is around 15 to 16 therefore decided to adapt GIS at 245 kV and 145
million resulting in total congestion of the existing kV and commissioned in 1988 India’s first such
land and leaving no Right Of Way for any substation at Carnac Receiving Station (R/s)
additional HV overhead line input into the city. In situated in the heart of Mumbai city. Since then
fact, finding a suitable route for underground Tata Power has experience of operating more than
cables is also becoming almost impossible due to 600 bay years of 245 kV GIS and 284 bay years of
narrow carriageways, large number of 145 kV GIS respectively.
underground utilities and non co-ordinated
development of underground services. 2. EXPERIENCE OF TATA POWER
In addition, land in South Mumbai is at very high The performance of GIS in Tata Power has been
premium, which makes it practically impossible to quite good as compared to conventional AIS.
plan conventional indoor or outdoor EHV However, some problems faced with GIS are
Receiving Stations economically with high briefly described below:
reliability.
• 245 kV SF6 gas to oil transformer bushings at one
To meet the above constraints, installation of Gas of Tata Power’s substation failed which resulted in
Insulated Switchgear (GIS) was the only a flashover in the power transformer exit bus duct
alternative to conventional outdoor/ indoor compartment. Impending failure of a similar
switchgear to ensure economical supply of power bushing was detected in incipient stage by
with a high degree of reliability. monitoring of dissolved gases in bushing oil. This
bushing was dismantled and stripped which
GIS has excellent adaptability in meeting most indicated Very Fast Transient Over Voltage
difficult terrain or space constraints. Low space (VFTO) as a possible cause of failure of the
requirements on account of high dielectric strength bushing. The computer simulation of GIS model
of gas leads to flexibility of application. Entire was carried out by using the Electro Magnetic
switchgear being in a sealed environment does not Transiemnt Programme (EMTP) for analysis of
get impacted by polluting conditions like dust, transients generated by closing and opening of 245
impurities and deteriorating lubricants used in kV breaker of 315 MVA auto transformers. EMTP
disconnectors. There has been besides above, studies indicated that the maximum rise in voltage
other factors such as safety, longevity and during switching operation of breaker was 2 pu in
adaptability which make GIS an attractive 530 nano secs. The computer model of 245 kV
proposition as compared to Air Insulated GIS and corresponding theoretical voltage wave
Substation (AIS). It is upto 220 kV level, form obtained using EMTP simulation is indicated
transportation conditions permit factory assembled in Figure 1 and 2 respectively. Tests were
bay which is most attractive and favourable conducted at site to correlate and validate the
427
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
Time→
428
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
to two and thickness of connecting wire was also Fig 4 : GIS Enclosure Connection to Copper Screen of
increased. XLPE
iv) The new bushing was satisfactorily tested at • 245 kV GIS high speed earth switch bushings used
bushing manufacturer’s works to simulate VFTO. to crack during the operation of high speed earth
The torque withstand capability of the bushing cap switch. It was observed that due to solid
was improved from 120 Nm to 190 Nm, as connection and inadequate dampner, the shock
required by GIS manufacturer, to prevent rotation was getting transferred to the porcelain bushing of
of bushing top cap which was the interface point the high speed earth switch. Subsequently the
with the GIS. Earlier lesser top cap torque solid connection was replaced by the manufacturer
capability had led to snapping grading lead and there were no subsequent failures of the high
connections. speed earth switch bushings.
v) Thus the results of these studies helped the • In 145 kV GIS circuit breaker compartment one
manufacturer to modify the design & adopt correct safety disc ruptured. The sequence of events
interface between GIS, bushing & transformer. logged by SCADA indicated initially Low
pressure alarm and LOLO pressure trip within 715
• The earthing system of the GIS requires greater mseconds. The bay was carrying current of 270
care as compared to that for a conventional amps prior to tripping. No other relay operated
outdoor substation. During initial charging of 145 and the breaker tripped on LO-LO SF6 pressure.
kV GIS when 110 kV XLPE cable was earthed The internal inspection of the breaker
through high speed earth switch, a flash over was compartment did not reveal flash over marks or
observed from 145 kV GIS cable compartment to any other abnormality. The ruptured disc was
the metallic gland on which the copper screen of replaced by a new safety disc. After reinstalling
XLPE cable was terminated. The flash over was the top cover of the circuit breaker and evacuation,
caused due to non provision of shorting strips SF6 gas was filled and breaker taken into load
which were meant to directly connect GIS service after carrying out timing, contact
enclosure to copper screen of XLPE cables. This resistance and insulation resistance checks.
had resulted in discontinuity in the GIS earthing Broken pieces of the safety disc were sent to the
system. The case of the flash over was attributed manufacturer. After studying the pieces of the
Transient Ground Potential Rise (TGPR). When faulty disc no defect was found. Carbon matter
the cable was switched off, it retained a trapped also did not show any micro cracks. The
DC charge between the conductor and the screen manufacturer opined that the defective disc was
of the cable. When the earth switch was closed, probably knocked during the transport or handling
this caused a discharge at the shortest path across of the circuit breaker, which induced stressed
the sealing end enclosure to the cable screen, due inside the carbon matter until the disc burst
to high inductance of the GIS earthing system in suddenly. After the replacement of the safety disc
the absence of the shorting strips. After provision the GIS has been operating satisfactorily.
of shorting strips, there was no incidence of flash
over during abovementioned operation. Figure 4 • Gas leak from gaskets particularly from the
indicates connection for GIS enclosure to copper outdoor flanges of GIS is frequently experienced.
screen of XLPE cable. The ultra violet radiations causes faster
deterioration of gaskets. The gradual corrosion of
the aluminium metal enclosure was also observed
due to moisture ingress in outdoor GIS gaskets.
429
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
Achieving and maintaining high level of Dielectric tests are carried out on complete
availability of equipment requires integrated installation (except surge arrestors, Cables,
approach to quality control by both users and Voltage Transformers and Power Transformers) to
manufacturers. Tata power has standerdised confirm dielectric integrity of GIS and detect
quality assurance programme to be carried out at presence of foreign particles and verify
the time of purchase of GIS, as well as it follows correctness of connections. The dielectric tests are
standardised (internally) operation and carried out through special test set with bushings
maintenance philosophy for GIS. or backcharged VTs which are specially
strengthened. Once GIS is commissioned it
As a part of quality assurance program during requires no or very little maintenance. The
initial purchase stage and commissioning stage of maintenance and inspection philosophy for GIS
GIS, cleanliness during assembly and erection is followed by Tata Power consists of following.
very vital since any contamination causes
deterioration in the properties of SF6 gas. Access 1. Visual Inspection – To be carried out on
to current carrying parts during services is not periodic internals i.e. every month.
possible as all the live parts of GIS are enclosed in
metal enclosure. Opening of the enclosure for 2. Detailed Inspection – To be carried out every
inspection at site can lead to introduction of 6 years or 1000 times of no-load switching
impurities which can deteriorate dielectric operation.
properties. This necessitates stress on diagnostic
measurement in case of GIS instead of usual 3. Disassembling Inspection – Every 18 years
maintenance practices for outdoor switchyard or the initial stage and afterward carrying out
equipment. The values measured during initial referring to the initial stage inspection results
commissioning are very useful as a reference in as per manufacturer’s standards and as per
future. Following tests are performed after Tata Power, follow trends of various
completion of erection of GIS at site : inspection & testing results.
1. Checking the moisture content of SF6 gas of 4. Special Inspection – (i) In case of any
various gas compartments. abnormality. (ii) For GCBs : After 10 times of
breaking at rated breaking current. (iii) After
2. Measurement of contact resistance, operating 1000 times of breaking at rated normal
time of circuit breakers, isolators etc. by using current. (iv) After 2000 times of no-load or
insulated bushings of the earthing switches. small current switching
3. Caliberation of gas density monitors. The brief procedures for visual, detailed and
4. Partial discharge test. disassembling inspection (special inspection) are
indicated below :
.
430
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
Special Inspection To be carried out under To be carried out as and when the conditions indicated
supervision of above are observed. The inspection content is same in
manufacturer’s case of an detailed and disassembling inspections.
representative During O&M, parts may be exchanged, greasing,
cleaning of all ports done.
Besides the above, certain novel modifications in GIS GIS substations. The advantages and disadvantages of
architecture, incorporated due to operating experience modifications in GIS architecture are indicated below:
were carried out by Tata Power while procuring new
4. INNOVATIVE SOLUTIONS
In today’s changing market, the substation is of available space. Hybrid GIS bay consists of
becoming more and more a key element to breaker, isolator, earthing switch enclosed in
meet end users requirements successfully and an enclosure filled up with SF6 gas. The
economically. Many existing substations have interface with the existing switchyard can be
outlived their operational life and a one-to-one through air bushings if it is to be connected to
replacement of conventional AIS components busbars or through cable if the bay is located
like circuit breakers and disconnectors is not away from busbars. Sometimes, based on the
economically advisable. Completely new customer’s requirement, the hybrid GIS bay
substations have to meet tough requirements of can be equipped with conventional current
in terms of occupied space, environment and transformers.
availability. Also, extension of existing
substations require high availability of primary In one of Tata Power’s Generating Station at
circuit components, to cope with already Lodhivli, three 110 kV outdoor bays were to
existing control systems, lack of availability of be created for Generator Transformer and two
space, limited down time. outgoing lines in a very limited space
(Trapezoidal plot 10M x 23M x 20M x 25M)
Taking into consideration all the above factors, for evacuation of power. It was not possible to
to expand existing substation, Tata Power has install conventional outdoor bay within space
introduced new concept of “Hybrid available. Also, it was not economically
Switchgear” in HV/EHV switchyards. Hybrid advisable for installation of complete GIS.
Switchgear is a combination of AIS and GIS Hence a midway solution of installation of
and it can be thought as “Performance and Hybrid GIS was considered and
Save Space” and it can meet any substation commissioned. Figure 5 shows Hybrid GIS by
layout requirement while making efficient use installed at Tata Power’s Lodhivli Station.
431
Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008
5. CONCLUSION
References :
432