Professional Documents
Culture Documents
METRO LIGERO wjt542
METRO LIGERO wjt542
success which stem from the fact that it has been able to
phase have been built into the plans for future lines.
transport policies.
1. BACKGROUND
Metrolink is the name given to Greater Manchester's light rail system which - when it
was opened in 1992 - was the first modern light railway to incorporate both street and
1
1
segregated track running. By taking over the routes of two suburban railway lines
and linking them with on-street track in central Manchester it was developed as the
network. The route of the first phase is shown in Figure 1. The planning and
development of the project has already been the subject of a paper to the Institution
(1)
.
Since its opening, the first phase has been highly successful in attracting patronage.
This very quickly established a "virtuous circle" of higher service levels leading to
even higher patronage levels. This is in stark contrast to the "vicious circle" of
declining service levels and higher fares leading to even lower patronage levels which
has characterised much of public transport in the United Kingdom since the mid
1950s. As a result, Metrolink has also enjoyed considerable financial success - with
agreement under which the contractor obtained the rights to run the service for a 15
year period. As a result of the payment for the concession, the private sector
The system is owned by the public sector in its entirety - track, structures, rolling
stock. It is operated by the private sector under a concession agreement. This gives
minimum levels of service and performance standards but gives the operator the right
to run higher levels of service and the freedom to set fares. The operator takes both
2
2
the cost and the revenue risks on the operation of the system but has some protection
against the consequences of major legislative change affecting the operation of the
system. The contract could be terminated in the event of GMPTE obtaining powers
and funding to expand the system. This provision was used as part of the process
leading to the first extension and will be used again in the forthcoming network
expansion.
Since its opening the service has evolved in response to passenger demand. The first
section to open was the former rail line between Manchester Victoria and Bury which
replicated the former rail service. After four weeks this was extended across the
centre of Manchester and a few weeks later a through service to Altrincham was
In July 1992 the branch to Piccadilly Station opened and the service pattern changed
to one in which there was a tram every 12 minutes from both Bury and Altrincham to
Piccadilly Station and, during the peaks, this was supplemented by a service from
Bury to Altrincham direct which did not call at Piccadilly. This provided a through,
cross-Manchester connection.
From this time, passengers in the off-peak who wanted to make cross-Manchester
journeys had to change in Manchester. This gave rise to considerable complaint and
over the course of the next few months a revised timetable was devised. In effect,
this involved running the peak service throughout the day, so that besides a 12 minute
through service between the two lines, each line got a 6 minute service to Manchester
3
3
from 0700 to 1830 hours on weekdays and from 0800 to 1800 hours on Saturdays.
The extent of Metrolink's success can be judged from the figures in Table 1. These
figures compare with a patronage level on the two rail lines which it replaced of 7.5
million trips per year. There are many reasons for this continuing growth in
patronage. First, Metrolink started from a sound patronage base built up over the
years by the rail services. Both rail lines - to Altrincham and to Bury - were built as
consequence, access to the system at the home end of the journey is good – the
system as a whole over 60% of passengers live within walking distance of the station.
Monitoring Study(3) found that, at most stations, over 60% of passengers walked to
Metrolink.
given to the major shopping and employment areas in the city. As well as this,
4
4
Metrolink has three interchanges with the national rail network at Piccadilly (which is
the main station for inter-regional and long-distance trains), Victoria and at Deansgate
Third, the service has created a new link across central Manchester which does not
year - travel across the city centre. Very few of these journeys would have been
made on public transport before Metrolink as they would have involved two train
Fourth, it offers journey times which are competitive with the car and much faster
than the bus, as Table 2 shows, for journeys between Altrincham - Manchester and
Bury - Manchester. Thus, in the peak, Metrolink is quicker than the car and the bus.
In the off-peak it is at least competitive with the car and is again faster than the bus.
There are many journeys between other pairs of stops for which these conclusions
apply.
Fifth, the operation has been extremely reliable with very few initial teething troubles
and, since then, operating over 99% of scheduled mileage. This has helped to retain
Sixth, the service is very frequent and can run on a 'no need to know the timetable'
basis. Throughout most of the day there is a tram every 6 minutes to and from
central Manchester. Even in the evenings the service runs every 12 minutes. The
service runs between 0600 and 2330 on weekdays, and even later on Friday and
Saturday nights.
Seventh, the line links three major traffic ‘sources’, central Manchester, Bury and
5
5
Altrincham. There are high traffic flows to both Bury and Altrincham as well as to
central Manchester. Even in the peaks, there is a good balance of loads in both
directions and load factors are maintained throughout the length of the line. On a
tram travelling from Manchester to Bury, passengers getting off at intermediate stops
en route are replaced by those travelling from these shops to Bury. Again, as they get
off they are replaced by others travelling from the intermediate stations into Bury.
This has had a beneficial impact on the good financial performance of the system and
Finally, whilst fares are not cheap, they are related to market demand with many off-
peak return fares at the same level, or lower than, bus fares.
In summary, Metrolink has been a success as a public transport system. It has met
passenger demand for many journeys more effectively than other modes. As a result,
it has captured a high market share of trips to central Manchester from areas within
the catchment of its stations. This is illustrated by the figures in Table 3 which
compares the situation before and after Metrolink opened. They are based on
household surveys carried out as part of the monitoring exercise(3). This shows
clearly that public transport is capable of capturing a high market share for trips for
which it has a competitive advantage over other modes. The challenge for transport
6
6
3. ATTRACTING CAR JOURNEYS
During the time when the government funding for Metrolink was being justified and
negotiated, the criteria for funding changed. Emphasis switched towards basing
grants on the extent to which public transport investments could benefit non-users in
• environmental improvements.
Of these, reduced traffic congestion was the most important in quantitative terms
although all are important objectives of transport policy. These benefits will only be
achieved, clearly, if public transport attracts trips which would otherwise have been
made by car.
In this respect, Metrolink has also been a success. However, measurement of the
extent to which trips have switched from car to Metrolink is far from straightforward.
Two monitoring studies of Metrolink have been carried out by the University of
Salford (2) and Oscar Faber TPA (3) . They adopted different methods of approach to
this question and came up with a range of results which probably represent the upper
and lower limits of the true figure. Taking the mean of these studies gives an
estimate that about 19 % of Metrolink trips would otherwise have been made by car.
Applying this to a patronage of 13.5 million gives a total of 2.6 million trips saved per
year.
7
7
The studies also estimated how much traffic had reduced on the corridors most
affected by Metrolink. Because traffic levels fluctuate in any case, estimating the
impact of Metrolink was subject to even more uncertainty. The best estimates were
that:
4.5% and 6.2% and off-peak flows by between 0.9% and 1.4%;
• on the Bury corridor the reductions were between 2.5% and 5.1% and
Whilst these reductions were relatively small, they reflect the diverse use of these
corridors which reduces the proportion of traffic making journeys that could be
switched to Metrolink.
8
8
The net result is that Metrolink has delivered a wide range of benefits to the
• reduced pollution.
This success reinforced the policy of the Passenger Transport Authority and GMPTE
The original plans for Metrolink, reported later, always envisaged that there would be
a network of six lines. The Bury and Altrincham lines were the first phase. They
• they had the most acute problems of the old electric rolling stock which
• the power supply system and much of the signalling on the Bury line was
• they carried the highest volumes of passengers and would therefore have
the highest benefits on which to justify the cost of the central area section.
9
9
• three existing suburban rail lines (from Manchester to Rochdale (via
However, even before it was built, the potential of flexibility of Metrolink to operate
10
10
In particular it was appreciated that there could be considerable benefit in extending
Metrolink into areas which had not, hitherto, been served by rail. In doing so,
however, it was appreciated that potential extensions would have to have at least
some of the characteristics which have made the first phase successful.
The original six line network was planned in the mid 1980s. Since then there have
been major changes in the economy and land-use of Greater Manchester which have
had implications for transport. Manufacturing has declined and been replaced with a
more dispersed employment pattern. The result is that many areas of the conurbation
declined and have been the subject of regeneration initiatives. At the same time new
employment centres, like Manchester Airport, have developed and many of the towns
in the conurbation which surround Manchester have developed their shopping and
leisure facilities.
Another factor which shaped the direction of the Metrolink extensions programme
was the development of the local rail network. In 1987 two new short rail links
opened which enabled trains from the north and west of Manchester to reach
Piccadilly station and beyond to lines to the east and south. As a result of this and
other developments within the rail network Manchester has developed as a hub for a
networks. This development was helped by the opening of Metrolink which released
some track capacity in central Manchester which formerly used the Altrincham rail
line.
Partly as a result of this, the conversion of the Glossop and Marple lines to Metrolink,
whilst still feasible, would be much more expensive. The costs of segregating the
11
11
lines from the rest of the rail network (which, at that time, was necessary to meet
British Rail requirements as well as to provide the capacity needed for both services)
would be much greater because of the much larger number of other services which
At the same time the potential of Metrolink to serve new areas by a combination of
on-highway and segregated running became more important and powers were sought
for lines which were not in the original programme. The first group of powers were
railway station in Rochdale to the town centre and the bus station. The
existing rail line fails to serve either of these town centres, but by
thus applying the lessons from Phase 1's success. The line would link
• Conversion of the former rail line to Didsbury - again from the original
programme.
12
12
• A new line to serve the regeneration area of Salford Quays. This was
the site of the Manchester Docks which had declined in the 1970s and
develop both housing and offices on the former quays, which have
minutes drive from central Manchester and employers there have had
transport network.
• A new line to serve the Trafford Park industrial estate, which had also
Centre.
Powers for the above were obtained in the late 1980s and early 1990s using the
Parliamentary Private Bill Procedure which has now been replaced by the 1992
The second set of extensions has been granted powers much more recently. These are
This is largely on highway and will provide links between Eccles and
Salford Quays and central Manchester. It will also help to reduce traffic
with a major park and ride site being to be provided just outside Eccles
13
13
bus network.
entirely new public transport route in the area. It would also create a
new crossing of the river Mersey and provide a route between areas
which are not easily linked on the road network. Besides the Airport, it
public transport access for staff. The latter is a key component of the
Relief Road and Intermediate Relief Road. The line would serve the
14
14
These lines were granted powers under the Transport and Works Act, following
which can be related back to the factors which have contributed to Metrolink's
• serve centres other than Manchester itself which will generate demand for
the service - replicating the impact of Bury and Altrincham in this respect;
existing modes;
waiting times;
Section 6 of the paper explains the strategy for funding and building these lines whilst
the next section discusses some of the issues relating to the new procedure for getting
powers for public transport schemes under the Transport and Works Act.
15
15
The second set of extensions described above were authorised under the Transport
and Works Act procedures. This replaced the Parliamentary Private Bills, with
Orders made by Secretary of State for the Environment Transport and the Regions.
The main difference affecting the promoters of a scheme is that, instead of a narrowly
defined group of people affected by the proposals having the right to petition
Parliament with their objections, objections are made to the Secretary of State. This
means that almost any person or organisation can object to the proposals.
Having considered the objections the Secretary of State has to decide if the issues can
inquiry should be held. All three of GMPTE's extensions authorised under the TWA
In many ways the public inquiry is a more appropriate forum than Parliament for
dealing with what can be specific local issues. However, GMPTE experience has
been that the process is more complex than the Parliamentary procedures were. In
16
16
particular, it has proved necessary to have carried out a lot more of the detailed
planning, engineering, economic and financial analyses for the proposals than was the
Inquiries involve Counsel and a wide range of professional and expert witnesses. All
of this adds to the time and cost involved in promoting Metrolink extension or other
Light Rapid Transit schemes. There is also considerably more uncertainty and
variation in the time between the inquiry Inspector reporting and a decision being
made. Overall, from initial planing to decision takes longer under the TWA than it
Metrolink extensions. It has been argued that there is little point in getting powers to
build the whole network of extensions, as it is unlikely that there would ever be
funding to build them all. GMPTE's policy has been based on the principles that:
involvement in funding.
The policy has therefore been that if there is a line which can be justified in policy
and financial terms, then powers which are initially granted for 5 or 10 years should
be obtained and maintained. In this way maximum advantage can be taken of any
17
17
funding opportunities which arise. The fact that the TWA procedures involve such a
lot of preparatory work and can involve a public inquiry emphasises the point that
This is illustrated by the events which led to the building of the Salford Quays and
Eccles line as the first extension of the Metrolink system. In 1995 the Passenger
received over £40 million from this sale and resolved to allocate £25 million to
funding Metrolink extensions. However, this would not have been sufficient in
itself to build any of the extensions and partnership funding was needed.
Of the extensions for which powers were available, the Salford Quays extension was
assessed as most likely to attract private sector and European Regional Development
Fund funding. Private sector property interests in the area had expressed willingness
Discussions with potential private sector operators identified that a short (3 kilometre)
extension to Eccles would improve the attractiveness of the line to them ,by providing
18
18
A combination of the Authority's resources, contributions from the private sector and
ERDF was sufficient to reduce the funding gap on the line to the point where it could
It is not possible, in this paper, to relate the details of the funding process. However,
the end result was that a new tendering process was entered into for:
comprise the Bury and Altrincham lines and the Eccles extension when it
was completed).
This was made possible by the provision in the original contract which provided for
expansion of the system and, if necessary to bring this about, the termination of the
After a competitive bidding process the contract was awarded to Altram (Manchester)
Investors in Industry. The payment for the operating concession has been sufficient
to fund over half of the £160 million cost of building the Eccles extension. The
remainder was funded from property interests, the PTA, ERDF and Capital Challenge
The new consortium took over the operation of the existing network in May 1997.
19
19
Construction of the Eccles line is now well under way and the Salford Quays section
was opened by the Prime Minister in December 1999 and the full line to Eccles in
Spring 2000. Six new trams have been acquired for the extension. They are similar
to the existing fleet but incorporate a number of modifications and improvements and
When fully opened the line will bring Salford Quays within 10 to 15 minutes of
central Manchester and will be served by a tram with at least a 12 minute frequency.
Having got the construction of the first extension underway the PTA's next priority is
to build the extension to Oldham and Rochdale. However, in the Provisional Local
Transport Plan which was submitted to Government in July 1999, the Authority and
the ten District Councils submitted a proposal for a single contract to build the
£520 million, of which almost £160 million would come from the private sector. To
20
20
help fund the public sector contribution, the Passenger Transport Authority and the
explore the implications of becoming a pilot area for road user and/or workplace
parking charges.
• First, it will eliminate the need to terminate the operating concession every
example in vehicle purchase) and give the operator a longer term revenue
stream. This will result in a higher contribution from the private sector
• Third it will bring the benefits of a full network much sooner at a time
This was accepted by Government. Following the opening of the Salford Quays line,
intensive discussions to validate the economic appraisal of the single contract, and to
finalise the funding arrangements, took place. This involved GMPTE, DETR and the
Treasury. In March 2000 the Deputy Prime Minister announced that the case for
accepted and that funding would be made available from the extra transport resources
21
21
announced in the Budget. An immediate allocation of £15m was made to enable
take place.
Meanwhile, a separate agreement has been reached between GMPTE and Peel
Holdings – the owners of the Trafford Centre. This will mean that the Trafford park
line will be included as an option within the single contract and would be built if the
private sector, including peel Holdings, were prepared to cover the funding gap.
integrated transport network. Even in competition with other modes, Metrolink has
been a success for the reasons outlined in this paper. The other major public
22
22
improve the quality of the whole of the public transport network and to promote it as
hoped that it can become an acceptable alternative to the car for many journeys.
A major effort is being made to upgrade the quality of bus services, by bus priority,
investment in new vehicles and infrastructure, and attracting more journeys to the
network as a whole, through better quality passenger information and better facilities
Metrolink has a key role to play in this. It has already demonstrated that high quality
public transport can attract trips from the car. As the backbone of a congestion free
high frequency network it will have a major role to play in the integrated transport
network of the future. The Integration Project is already removing some of the
barriers faced by passengers who want to use bus for part of their journey and
Metrolink for the rest of the trip. Integration will increase the whole public transport
market and in this way help to underpin the future expansion of the Metrolink
network.
23
23
24
24
TABLE 1
Year Patronage
(million trips)
1992 3.75*
1993 10.36
1994 12.29
1995 12.58
1996 13.41
1997 13.87
1998 13.20
1999 12.62
TABLE 2
Altrincham To Manchester
Source: GMPTE
25
25
TABLE 3
Before After
Metrolink Metrolink
TABLE 4
FULL METROLINK NETWORK
Length 98km
Source: GMPTE
26
26
REFERENCES
12.6.00
WJT542
27
27