Dear All,

Please find the Installation Plan for Dehradun Installation

 Manikandan and Prabir Paul will be reaching Dehradun on Sunday.


 Machine is expected to be delivered on Sunday.
 Unloading of the Machine Planned on Monday - Manikandan & Prabir.
 Paul & Ram will be joining on Monday.
 Since UPS and Computer is supplied by us, need the UPS & Computer Engineer on
Monday at site.

By Tuesday we need to complete the following (MM/PD/PP/PMR)


 Unloding
 Box Inspection
 Positioning of the Machine
 Transit Locks removals.
 Power on

From Our Vendors we need to get the following done.


(Sufficient Man power is required from our Vendors)
 UPS Installation
 Power Cabling from UPS (If not Done by Customer)
 Network Cabling (If not Done by Customer)
 Computer Installation

Puran will be reaching on Monday afternoon and Anit on Tuesday.

Dear Sanjib,
Please let us know if there is any change in the Despatch.
Hotel details at Dehradun, Mani & Prabir is reaching tomorrow.

Availability of the Following at site


Plates, Dev, Repl, Gum, Plate reader

Please add if I have missed out anything

Thanks & Regards


Ramkumar