Final Cost Summary

ACTIVITY SUBTOTAL

I. STRUCTURAL-CIVIL WORKS
1.00 Earth / Site Works
Subtotal for item 1.00 ₱ 2,209,725.99
2.00 Reinforcing Bars
Subtotal for item 2.00 ₱ 17,989,519.07
3.00 Formworks
Subtotal for item 3.00 ₱ 19,428,231.57
4.00 Concreting
Subtotal for item 5.00 ₱ 82,236.34
6.00 Thermal & Moisture Protection (Waterproofing)
Subtotal for item 6.00 ₱ 721,504.62
7.00 Masonry Works
Subtotal for item 7.00 ₱ 2,831,087.67
8.00 Stair and Finishes
Subtotal for item 8.00 ₱ 437,874.48

TOTAL FOR ITEM II STRUCTURAL ₱ 63,948,230.75

II. ARCHITECTURAL - FINISHING WORKS


1.00 Finishing
Subtotal For Item No.1 ₱ 23,775,568.21
2.00 Painting Works
Subtotal For Item No. 2 ₱ 1,289,690.50
3.00 Doors & Hardwares
Subtotal For Item No. 3 ₱ 481,872.44
4.00 Windows
Subtotal For Item No. 4 ₱ 79,108.36

TOTAL FOR ITEM II. ARCHITECTURAL ₱ 25,626,239.50

TOTAL FOR ARCHITECTURAL AND STRUCTURAL ₱ 89,574,470.25