Professional Documents
Culture Documents
February 2020
Progress up to Jan 31th
CODE: EECL-1-WCA-PM-INC-005
Check Control
Rev Date Elaborated by Reviewed Approval by
A 31-01-20 Jesús Farías José Luis Rojas Marco Herrera
B 06-02-20 José Luis Rojas Marco Herrera Carlos Regolf
0 07-02-20 José Luis Rojas Marco Herrera Carlos Regolf
ii
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
Índex
0
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
1
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
1. Project Information
a. Project Description
Wind Calama is a 151.2 MWac wind farm (36 WTGs x 4.2 MWac) located 15 km Southeast of Calama
city, in the Antofagasta Region, aside of the B-165 route, on a very flat and barren desert land. The site
is divided by the route, creating two lots with a total of 1,761 Ha (the upper lot of 999 Ha and 22 WTGs
and the lower lot of 762 Ha and 14 WTGs).
The contractor for WTG´s supply and installation is Siemens – Gamesa. The BOP Contractor is GES
and its scope includes the step-up substation and grid interconnection through a Tap-off.
Interconnection to the national transmission grid is granted through a Tap Off SS on the Calama – Jama
220 kV TL, owned by RJIN Capital. Connection point and tap off solution are already approved by the
grid administrator “CEN” (Coordinador Eléctrico Nacional).
2
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
There are two international ports in a less than 300 km, Antofagasta port and Puerto Angamos
(Mejillones) port. Big parts as blades, towers and WTGs will be imported through Angamos port, most
suitable for that kind of equipment. Distance to the site is 275 km by a national route.
3
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
The project team has been organized regarding the following structure:
Sponsor Carlos Regolf GCIP 20
Renewable Projects Manager Marco Herrera GCIP 40
Project Manager Calama Wind José Luis Rojas GCIP 100
Site Manager Calama Wind Cristián Carrasco GCIP 100
Civil Supervisor Calama Wind 100
Hector Navarrete GCIP
EECL
Electrical Supervisor Calama Américo Villarroel 100
GCIP
Wind EECL (February 2020)
Commissioning Supervisor EECL Start in July 2020 GCIP 100
Renewable Engineering Manager Karen Rückoldt GCIP 50
C&P, SCADA and Grid 50
Carlos Calderon GCIP
Connection
PMO Manager Jesús Farías GCIP 50
Planning and Control Heilyn Maraima GCIP 50
50
Customs & Logistics Renewables Paula Jara External
50
Material Control Renewables Leonardo Gonzalez External - CyD
H&S Specialist for Calama Wind Francisco Fredes H&S Unit 100
4
Managing Directors IT Unit Controlling Unit Legal Unit Finance Unit
Matías Bernales Roberto Pumarino
Custom & Procurement Management
Sustainability & Permits Human Human
Logistics Unit HSE Unit O&M Unit
Unit Control Unit Resources Resources
Carlos Regolf
Corporative Implementation
Project Team Project´s Manager (Sponsor)
20%
Office
Marco Herrera
Eduardo Fuentealba Pedro Portela Jesús Farias
Renewable Projects
HSE Manager Contract Manager PMO Manager
Manager
50% 40% 50% 50%
José Luis Rojas
Project Manager
100%
Construction Site
100% Staffed Cristian Carrasco
Site Manager
the “EECL´s Culture” be applied) supported by and external team.
Francisco Fredes
Specialist H&S
Joseph Órdenes
QAQC (TBD)
Technical Project Office
René Videla
H&S Supervisor (CyD)
Functional Dependency
Head of Support Unit (Director)
Hector Navarrete Américo Villaroel
Support Unit Appointed Civil Supervisor Electrical Supervisor Commissioning (TBD)
provide Safety Supervisors, an Environmental Supervisor and a Technical Officer at Site.
5
José Garrido (TBD) (TBD) Commissioning
ENGIE Project Team Member
Civil Inspector Electrical Supervisor Supervisor
(TBD) SCADA/P&C
CyD: Technical Inspection and Supervisor
Management Support Service
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
provided by O4U Chile, and Construction Inspection on site, provided by CyD. This last company, also
The appointed EECL’s Project Team, is supported by external services such as Owner Engineer,
The main areas of project and construction will be managed by an EECL´s representative (to ensure
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
d. Project CAPEX
Servitude provision (Codelco, Raúl Araya and Andes Wind Park) EECL USD 4.000.000
NOTE: According with Compliance Memo, project won’t be financed through a project finance, then not Financial Cost has
been included into the CAPEX.
Table 2 – Project Budget Base Line (Source: Compliance Memo)
6
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
e. Project Milestones
Milestone Plan
COD 30-06-2021
2. Highlights of the Month
a. General
7
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
As attention point there is a potential impact to GES contractual milestones (2 and 3) due the delay
on delivery of Previous Studies and Technical specification for MV Equipment for Interconnection
Process to CEN. Being monitored weekly in a specific meeting.
e. Engineering
- Engineering for Civil Works of substation completed. Electrical is ongoing and planned to be
finished at end of February.
- Concern about the possible impact of delay in vendor information of electrical equipment to attend
the schedule of interconnection process with CEN. GES is being supported by an expert consultant
“ESTUDIOS ELECTRICOS” (recent good experience in TEN and IEM connection).
8
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
g. Construction
3. Health, Safety and Environment
a. Main activities, Manpower and Indicators
Target Site
Frequenc
Frequenc
Severity
Severity
y Rate
y Rate
Rate
Rate
9
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
- 41
18
232
The contractual ratio established for the project related to quantity of H&S supervisors and Direct
personnel correspond to 1/40. The following table shows the H&S supervisors and Direct personnel on
site. The current monthly Rate is 7/59
10
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
Site Personnel
11
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
- During January national social contingencies have decreased, which mean that construction
activities have been re-taken with normality. Anyway, the HSE Team continuous realizing a daily
monitoring of site area and access routes, in order to identify and avoid any kind of
inconveniences of construction personnel.
4. Project Schedule and Progress Management
a. Monthly Summary Status
PROGRES BY SUB CONTRACTOR COMPANY PROJECT PROGRESS
MONTHLY PROGRESS ACUM. PROGRESS MONTHLY PROGRESS ACUM. PROGRESS
GLOBAL ACTUAL
WEIGTH CONTRACTOR ACTIVITY WEIGTH STATUS COMENTARIOS
ACTUAL PLAN STATUS PROGRES ACTUAL PLAN GLOBAL ACTUAL PLAN ACTUAL PLAN
ACTUAL PROGRES
ENG 1.40% 36% 43% 54.40% 79.0%
18% GES SUM 20.55% 12% 7% 1.38% 18.20% 19.0% 2.10%
CONS 78.07% 6% 5% 9.10% 16.7% 1.65% 1.61% 4.23% 6.47%
SUM 65% 1% 1% 4.00% 6.0%
82% SGRE 0.27% 2.14%
CONS 35% 0% 0% 0.00% 0.0%
Note: Plan Progress as per Recovery Plan of GES and Contractual Schedule of SGRE.
150%
Project Status ‐ Calama Wind
100%
50%
6,47%
4,23%
0%
Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Plan Actual
12
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
100%
80%
60%
40% 16,70%
20%
9,10%
0%
Sept Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
Plan Actual
13
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
14
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
September
September
November
November
December
December
February
February
October
October
January
January
WIND CALAMA
August
August
March
March
April
April
June
May
May
July
Jun
Contract signature 26/08/201
Anchor Bolts Cages
Tower section T1‐T3
Siemens Gamesa
Nacelles and Hubs
Blades
Elevator SS
OOCC
GES
Assembly
Energization SS 31/08/2020
WF CALAMA
Access roads
GES Foundations
Plattform
Assembly of equipment
Siemens Gamesa Commissioning
Reliability Run 26/04/2021
COD request 01/06/2021
COD CEN 30/06/2021
15
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
c. Interphase management
The project interphase management between GES, SIEMENS-GAMESA and EECL, was establish
contractually by the Division of Responsibilities (DoR), which is being monitored and controlled by
EECL´s Project Team through weekly coordination meetings directly with contractors.
16
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
Since December, due the delay presented by GES, the critical activities and paths, start with the
Engineering of Civil Works for Calama Substation, what is directly affecting to Control building
construction and its activities related to Control room and auxiliary facilities. The control building delay
could affect the commissioning activities of Calama Substation.
That engineering is already finished and is being checked by Engie. First week of January GES
mobilized an Engineering Coordinator to Chile to improve the execution.
17
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
5. Project Budget and Cost Control
a. Monthly Payments of Main Contracts
18
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
19
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
Agreement between ENGIE and Community of Chiu Chiu was signed during December. The agreement
establish payment commitment related mainly with compensations to the community, and promote the
continuous development of farming and renewable energy at the zone. The agreement has a cost of
110 KUSD. Currently is being formalized into the project cost management system.
See Annex 3 – Project Payment Milestones for BOP (GES) and WTG Supplier (Siemens-Gamesa)
updated to January 31th.
6. Project Risk Management Status
a. Monthly Risks Status
The Risk Management analysis is carried out in base to the Governance of PRM regarding to EECL
Standards. The monthly status for risk management is represented regarding the following Heat Map.
20
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
The Project Risk Heat Map represents the risk status of November as shown below:
Short
Risk N° Risk Description Description Action Plan Monthly Update or Actions
or Entity
RJIN Capital: Owner of TL Calama ‐ Jama where the park is
connected. Despite of connection is granted by Law; TL’s Discussion on technical issues of contract. RJIN
Sign toll agreement, Get
owner could delay the process. A Connection and Toll rejects to talk about economics up today. During
R‐1 RJIN Capital technical information about
Agreement are required and still not reach. To obtain contact February it expects to maintain the contact with
the protections setup
to RIJN Capital has not been successful, due there is a RIJN Capital.
potential sell of transmission line.
Andes Wind Park (AWP): AWP has developed a wind farm
next to Wind Calama. He is asking for a part of EECL land
rights whit not WTG’s projected and also EECL to move 2
WTGs. AWP have not enough rights to start legal actions Andes Wind Legal unit in charge to follow
R‐2 No activities during January
against EECL, but have some Mining Concessions (and said Park (AWP) up this issue.
that can influence another mining concessions’ owner) under
project site that could affect the project execution. Case is
managed by Legal Department of EECL.
21
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
Raul Araya (Local Miner): Part of project area on Mining
According to legal and technical analysis of the
Concession of Araya. Araya explodes Travertine marble. He
documentation provided by the stakeholder of the
asks to confirm the coexistence of both projects or to be Under evaluation the
mining project, Engie propose them the possibility
compensated for the affectation on his project (11 turbines relocation of 5 WTGs to
that both projects coexist, and reach an economic
are affected, but 5 are the most exposed). He left folder with Raul Araya minimize Raul Araya´s area
agreement by paying only for the areas of mining
R‐3 his project developed and more backups. According with the (Local and also a cost study of the
concessions really impacted and not for the total.
Legal evaluation, he has not enough rights to start legal Miner): compensation to negotiate,
The proposal was rejected by Raul Araya, indicating
actions against EECL or affect the project construction. A Faith considering the probable
that they should start legal complaint actions.
of Facts was made with the Notary to leave evidence that production of the mine.
Currently the Engie legal area, are preparing the
there are no mining works on the area at the moment. Case is
strategy to manage the possible legal complaint.
managed by Legal Department of EECL.
During December, the agreement with Chiu‐Chiu
Community was signed. With this agreement, the
Community of Chiu‐Chiu: Native Community who has tried to
Community community desisted about their demands to
stop the environmental permits obtained by EECL. Under
R‐4 of Chiu‐ Agreement signed. Environmental Court, and ENGIE must ensure the
negotiation an agreement between Engie and Chiu‐Chiu to
Chiu: community will have free access during construction
avoid any impact to the project.
phase, to access the mud extraction points located
beside project area (access are within project area).
Social Contingencies: Due the national social contingencies
started on October, it has been necessary and mandatory to
keep a daily monitoring of Calama access point, routes to To avoid risks and unsafe
project area, and local situation, in order to avoid any kind of Social situations to project
Daily monitoring by HSE Team of local situation
R‐5 unsafe situation and/or risks to project personnel. The risk is Contingenci personnel during
about mobilizations to/from site, barricades, etc.
mainly related to barricades (blocking accesses) and potential es transportation to / from
attacks to private property. During November the intensity of project site.
manifestations has been decreasing, but the supervision by
HSE team is alert to any event.
Direct archeological supervision service on site
(Archeologist) during civil works. During the month
Archeology: Avoid any kind of intervention or damage over
of January, the National Monuments Council visited
archeological findings. An archeological supervision service is Protection of archeological
R‐6 Archeology the project, performing a paleontological inspection.
appointed to site in order to verify the correct fulfilment of findings in project area.
Three samples of possible findings was found and a
archeological protection measures declared.
final report will be send in at least 25 days,
indicating the actions to be taken.
In order to mitigate the Until this moment no explosives have been used for
Soil Hardness affecting productivity during excavation of Constructio
R‐7 productivity of excavation excavation, however it is still analyzed for a number
WTG´s foundations. n/Permit
works (WTG foundations) of smaller foundations (under analysis).
b. Opportunity Analysis
7. Stakeholders Management Monthly Status
a. Stakeholder Engagement Status (Heat Map)
The Stakeholders Management analysis is monitored and tracked through the Stakeholder Mapping
and Engagement Framework (SMEF), regarding the EECL´s Governance for project management.
22
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
The list of total Stakeholders identified and managed are shown in Annex 1
8. Supply and Delivery Plan Status
a. Delivery Plan Status
September
November
November
December
December
February
October
January
August
WIND CALAMA
March
Start
June
April
May
End
July
Anchor Bolts Exworks 04‐nov 25‐ene
Tower Exworks 13‐ene 28‐mar
Manufacturing Nacelle Exworks 06‐ene 27‐jun
Hubs Exworks 06‐ene 27‐jun
Blades Exworks 20‐ene 27‐jun
Tower Inspection 13‐abr 18‐jul
23
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
All Chinese suppliers are suffering some kind of impact due to the Corona Virus epidemic (plant closed,
sub-suppliers affected, ports and airports closed). Some Force Majeure letters have been received.
Also FAT tests schedule could be affected and not Owner representatives could attend them. Only
Chinese inspection companies could be contracted. Engie China with some capacity problems to attend
the demand.
During February PMO will organize a site reinforcement respect to supply receipts process on site, in
order to clarify responsibilities during download and handling of material, equipment and components.
This is a support activity in order to prepare the site team for the massive supplies arrival to site, mainly
regarding to anchor cage and WTG components, avoiding any contractual issue due a wrong
understanding of supply handling on site.
9. Quality Management
a. Project General Quality Status and activities
- Project documentation reviewed: Site procedures, protocols and ITPs. Topography and Site
Management (load and upload of charges, tool’s colors) procedures.
- Monthly meetings with contractor counterparts: Procedure status, FAT test coordination.
- Engineering support, during the definition phase and supply management for transformer and lay-
out of plants.
- SIEMENS-GAMESA has sent the plan and quality control types for WTG components to EECL.
With this information an inspection service for FAT will be activated by EECL. FAT test will start
on March 2020 in China.
- Diffusion on site on Quality standards and requirements for construction quality management to
ENGIE and Contractor Team (GES). The activity was help and lead by PMO.
- Quality Control Plans (QCP) of BOP Contractor (GES) under review with the support of Inspection
Service (CyD).
24
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
c. Document Control
All project documentation is being managed through SIGEDO, the documental control Platform.
No activities.
e. Lesson Learned and Good Practices
No activities.
10. Deviation and Change Management
a. Deviation and Change Management Monthly Status
Impact Estimated
(Order of
Magnitude
Deviation/Change Short
N° Area Description Cost Time Status Observation
C-001 Sustainability Payment for The 110 KUSD - Already paid This Change is being
(Community Agreement formalized into cost
Management) between EECL management
and Chiu-Chiu system.
Community.
25
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
11. Photographic Report
26
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
27
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
Pic. 26 – Anchor bolts arrived and stored Pic. 28 –Weekly Safety Diffusion
Pic. 29 – WTG Platform Excavation works Pic. 30 – WTG Foundation excavation with rock-breaker
28
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
12. Annexes
- Annex 1 – Heat Maps Stakeholders Engagement Analysis
- Annex 2 – Stakeholders List
- Annex 3 – Project Payment Milestones
- Annex 4 – Project Division of Responsibilities (DoR)
- Annex 5 – HSE Indicators
29
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
30
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
The Heat Map analysis for Stakeholder´s Influence Level corresponding to December is shown below:
31
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
The Heat Map analysis for Stakeholder´s Engagement Level corresponding to December is shown
below:
32
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
33
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
34
Monthly Report – Calama Wind - CODE: EECL-1-WCA-PM-INC-005
Frequency Rate: Number of occupational accidents (work stopped more than one day) arisen during
a period of 12 months by one million hours worked.
𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑎𝑐𝑐𝑖𝑑𝑒𝑛𝑡𝑠 𝑥 1.000.000
𝐹𝑟𝑒𝑐𝑢𝑒𝑛𝑐𝑦 𝑅𝑎𝑡𝑒 𝐹𝑅
𝑇𝑜𝑡𝑎𝑙 𝑚𝑎𝑛 ℎ𝑜𝑢𝑟𝑠 𝑜𝑓 𝑤𝑜𝑟𝑘 𝑝𝑒𝑟𝑓𝑜𝑟𝑚𝑒𝑑
35