JOB DATE ORDER RECEIVED PROD. DAYS NEEDED DATE ORDER DUE C.R.

B 120 30 200 2.33


A 110 20 180 2.50
E 130 18 210 4.44
C 122 10 175 4.50
D 125 16 230 6.25

JOB DATE ORDER RECEIVED PROD. DAYS NEEDED DATE ORDER DUE C.R.
A 110 20 180 1.00
E 130 18 210 2.78
C 122 10 175 1.50
D 125 16 230 4.38

JOB DATE ORDER RECEIVED PROD. DAYS NEEDED DATE ORDER DUE C.R.
C 122 10 175 - 0.50
E 130 18 210 1.67
D 125 16 230 3.13

JOB DATE ORDER RECEIVED PROD. DAYS NEEDED DATE ORDER DUE C.R.
E 130 18 210 1.11
D 125 16 230 2.50

JOB PROC. TIME FLOW TIME COMPLETION TIME DUE DATE


B 30 30 160 200
A 20 50 180 180
C 10 60 190 175
E 18 78 208 210
D 16 94 224 230
94 312 962

Job PROJECT COST ‘000 Penalty Cost / Day


ORDER
CUSTO
MER
ADO $4,250,000.00 5% 212,500.00
BATU $1,350,000.00 2% 27,000.00
CUTA $250,000.00 10% 25,000.00
DINO $7,780,000.00 7% 544,600.00
ENTRO $100,000.00 20% 20,000.00
P.O. AVE. COMPLETION TIME 192.4
1 UTILIZATION 30.13%
2 AVE. NO. OF JOBS 3.32
3 AVE. JOB LATENESS 3
4 PENALTY COST $375,000.00
5

P.O. SEQUENCE
1 1 B
3 2 A
2 3 C
4 4 E
5 D
P.O.
1
2
3

P.O.
1
2

LATENESS PENALTY COST


0 0
0 0
15 375000
0 0
0 0
15 375000