You are on page 1of 13

Transport Proceedings of the Institution of Civil Engineers

http://dx.doi.org/10.1680/jtran.16.00031
Operational readiness for climate change Paper 1600031
Received 02/02/2016 Accepted 05/07/2016
of Malaysia high-speed rail
Keywords: infrastructure planning/rail track design/
Binti Sa’adin, Kaewunruen and Jaroszweski railway systems

ICE Publishing: All rights reserved

Operational readiness
for climate change of
Malaysia high-speed rail
Sazrul Leena Binti Sa’adin BEng, MSc David Jaroszweski BSc, MSc, PhD
Civil Engineer, Public Work Department of Malaysia, Kuala Lumpur, Research Fellow, Birmingham Centre for Railway Research and Education,
Malaysia The University of Birmingham, Birmingham, UK
Sakdirat Kaewunruen BE, MEng, PhD, MBA, MIEAust, CPEng,
NER, RPEQ, FHEA
Senior Lecturer in Railway and Civil Engineering, Birmingham Centre for
Railway Research and Education, The University of Birmingham,
Birmingham, UK (corresponding author: s.kaewunruen@bham.ac.uk)

The Paris Agreement of December 2015 signifies global unity to limit global warming to well below 2°C (above
pre-industrial levels) and to pursue efforts to limit the increase to 1·5°C. The global community now agrees that
anthropogenic climate change is unequivocal. According to the Intergovernmental Panel on Climate Change, the
global average combined land and surface temperature has increased by 0·78°C. Although the magnitude of change
in mean temperatures is relatively small, attendant extreme weather events have been shown to have increased in
frequency, and are projected to increase in the future. The potential impacts of climate change on railway
infrastructure and operations have not been fully assessed in the literature. The projected urban growth in Kuala
Lumpur and Singapore has led to the necessity to establish a high-speed rail (HSR) system between the two.
However, the existing railway network in the region has been significantly affected by severe weather conditions
such as rainfall, lightning, wind and very high temperatures. This research addresses a knowledge gap regarding the
potential impacts of climate change on future rail projects in the region, and points out the vulnerabilities that may
lead to impaired operations and system failures. These insights are intended to inform the holistic consideration of
climate change impacts in the design stage of HSR systems in Malaysia and beyond.

1. Introduction to infrastructure projects, little research has been conducted


High-speed rail (HSR) is increasingly being viewed as an in Malaysia into how vulnerable the proposed system will
important measure for improving national productivity and be, especially in terms of the physical infrastructure and the
mobility, and has resulted in significant infrastructure develop- planned operations on the network. It has been widely recog-
ment around the world. Malaysia is a developing country nised that there is a need to integrate considerations of climate
which is seeking to develop new transport infrastructure to change and its impacts into development policies and projects
realise both short-term (by way of internal investment) and (Kramer et al., 2010; New Straits Times, 2013; Victorian
long-term economic benefits (by way of employment, improved Government, 2005).
productivity and increased business capability). As a result, the
Malaysian government has proposed building a new high- The Kuala Lumpur–Singapore HSR line is currently in the
speed rail line between Singapore and Malaysia, a route which planning stages, and the aim is for it to be fully operational
currently ranks in the top ten in terms of passenger air traffic. by 2020. The conceptual design of the HSR was produced by
With the projected increase in meteorological hazards associ- the Malaysia Land Public Transport Commission (SPAD) and
ated with climate change, any new infrastructure will need will include seven stations. These consist of two terminus
to cope with potentially significantly different conditions to stations, in Kuala Lumpur and Singapore, and five transit
those of today. These projected changes introduce a new stations, one each in Negeri Sembilan and Malacca and three
source of uncertainty for railroad operators (Remennikov and in Johor. The HSR will have two modes of operation: non-stop
Kaewunruen, 2008; Remennikov et al., 2012). from Kuala Lumpur to Singapore with an estimated journey
time of 90 min, and transit operation including seven stops
Extreme weather has many well-established impacts on railway with an estimated total journey time of 120 min. The trains
operations and safety, and can cause property damage, injuries are expected to have a maximum operational speed of
and fatalities. Despite climate change posing serious challenges 300 km/h or faster, although the average speed will be lower

1
Downloaded by [ Syracuse University] on [16/09/16]. Copyright © ICE Publishing, all rights reserved.
Transport Operational readiness for climate change
of Malaysia high-speed rail
Binti Sa’adin, Kaewunruen and Jaroszweski

Quick facts on the KL–Singapore high-speed


rail project
– to run along the western side of the
North–South expressway
– will cut across three states and feature
six transit stations
– feeder buses will connect the stations
to the nearest cities and towns Proposed HSR transit station
– will run across the Johor Straits Proposed HSR route
through the Second Link before ending Current KTM route
in Singapore North–South expressway 50 km

Figure 1. Proposed high-speed rail route from Malaysia to


Singapore

due to slower speeds when approaching stations. The con- such as topography, geology and climate. This study aims
ceptual alignment has been developed by SPAD as shown to assess the vulnerability of the planned infrastructure and the
in Figure 1. However, the detailed alignments remain con- potential ramifications of this for climate adaptation strategies
fidential at the time of writing. The HSR will have a dedicated (Pachauri and Meyer, 2014). In the course of this study, a
line, which is proposed to be double track on a standard critical review of the relevant literature has been carried out.
gauge. The HSR project is expected to impact the way of life Data for the Malaysian HSR are derived from SPAD, with
for Malaysians and Singaporeans in terms of society, politics weather data being supplied by the Malaysian Meteorological
and the economy. According to SPAD, the main objective Department. These are used to examine how projected climate
of the HSR project is to reduce travel time between change, alongside the stated operational requirements, may
Kuala Lumpur and Singapore to 90 min, which will in turn affect the design of the infrastructure. Potential actions to miti-
strengthen the link between two of South-east Asia’s most gate climate-related risks are then evaluated.
vibrant and fast-growing economic engines. The proposed
journey time compares to the current journey time of 5–6 h 2. Local climate and geography
by road or 8 h by conventional train. Although the travel As illustrated in Figure 3, Malaysia is divided into two main
time between the two cities by plane is approximately 90 min, regions: peninsular Malaysia and east Malaysia, which are sep-
total journey time (including security and boarding) is closer arated by the South China Sea. The climate in Malaysia is
to 2·5 h. Figure 2 gives a summary of current and expected dominated by two monsoon regimes, namely the north-east
travel times for different modes of transport (UIC, 2011, 2015). and south-west monsoons. The north-east monsoon circulates
during the months of December, January and February, which
At this initial stage of planning, the opportunity exists is Malaysia’s wettest season and the period when most flooding
for HSR in Malaysia to include climate change impacts occurs. The south-west monsoon occurs between the months
and adaptation strategies in the detailed design stage of the of May and September, the driest period for the country as
proposed HSR system. The ultimate goal is to manage better a whole, often resulting in droughts. Being an equatorial
the weather and climate-related risks to the planned operations country, the average temperature throughout the year is con-
of the HSR system. These risks are determined by the stantly high (26°C) and the humidity is very high. Malaysia
HSR system design in conjunction with local conditions also has very high rainfall, totalling more than 2500 mm/year

2
Downloaded by [ Syracuse University] on [16/09/16]. Copyright © ICE Publishing, all rights reserved.
Transport Operational readiness for climate change
of Malaysia high-speed rail
Binti Sa’adin, Kaewunruen and Jaroszweski

Total journey
Mode of time
transport Kuala Lumpur Singapore

KL CBD to Waiting Travel time in train Immigration RTS


KL Central time for system to
train Singapore 9·5 h
SBD
15 min 15 min 320 min 15 min 15 min

Travel time in bus from KL CBD by North–South Immigration Expressway to


Expressway assuming speed 85 km/h SG CBD
6·5 h

300 min 15 min 30 min

KL CBD to Departure Travel time in Arrival Airport


KL Central process and waiting plane and taxi process to SG
and Immigration CBD 4h

40 min 60 min 90 min 30 min 20 min

KL CBD to Departure Travel time in Arrival HSR to


KL Central process and waiting HSR process SG SBD
and Immigration 2·5 h

15 min 15 min 90 min 15 min 15 min

Figure 2. Travel time from Kuala Lumpur (KL) to Singapore (SG)


comparison between KTM, bus, plane and HSR. CBD, central
business district; RTS, rapid transit services; SBD, Singapore
business district

200 km N

Figure 3. Geography of Malaysia

(MMD, 2009). The Malaysian Metereological Department concentration of greenhouse gases (GHGs) in the atmosphere.
(MMD, 2009) reported that the climate of the earth is It is projected that in the next 50 years, Malaysia will experi-
warming, with the rise being due to the increasing ence higher temperatures, changing rainfall patterns, rising sea

3
Downloaded by [ Syracuse University] on [16/09/16]. Copyright © ICE Publishing, all rights reserved.
Transport Operational readiness for climate change
of Malaysia high-speed rail
Binti Sa’adin, Kaewunruen and Jaroszweski

are grouped according to four types of belt, namely the


Western Belt, Bentong–Raub Suture, Central Belt and the
Easter Belt zones. Overall, granitoids occupy nearly half of
peninsular Malaysia.

In eastern peninsular Malaysia, the geology consists of sedimen-


tary basins from Gunung Gagau in the north to Gunung
Panti in the south. The sediments, comprising sandstone, con-
glomerate and shales with minor coal seams and volcanos, show
fluvial, lacustrine and deltaic conditions of deposition. It is
noted that Malaysia’s coastal area consists of mostly quaternary
deposits. Only in the straits of Malacca is the coastal geology in
the form of Ordovician phyllites, schists and limestone. Kinta
and Klang Valley contain valuable tin ore (a historic factor in
the location of Kuala Lumpur, Malaysia’s capital).
Figure 4. Malaysia east coast line railway bridge, crossing
Nenggiri River in Kemubu during the flood of December 2014
As shown in Figure 5, the proposed HSR route, starting
from Kuala Lumpur, will pass through a carboniferous area,
levels and more frequent extreme weather events, including which predominantly consists of limestone. The route then will
droughts and floods (TheSundaily, 2015). cross granite geology in the Seremban area. Towards the south,
the alignment will pass through limestone and sandstone
An important case study which demonstrates the impact of regions. In the southern part of the route, the HSR line from
weather on rail operations occurred on the famous Malaysian Melaka to Nusajaya lies on a coastal area with a geological
jungle railway (east coast line, Figure 4), which is operated by profile of marine and continental deposits. The soil conditions
National Malaysia Railway (KTM). The line was disrupted are mostly in the form of clay, silt and peat. According to
for almost 6 months due to a major flood in December 2014. Bakhshipour et al. (2013), approximately 40% (236·827 km2)
The damage included the railway quarters, signalling, tracks, of the Kuala Lumpur area is underlain by limestone and karst,
locomotives, machinery and rolling stock. The disruption which are extensively developed and classified as extreme karst
affected thousands of workers, traders and children going to class Kv. The process of karst formation commences as rainfall
school. One stretch of line remains closed due to the collapse (water (H2O)) falls from the atmosphere onto the surface,
of the railway bridge in Kemubu, Kelantan (Badrul Hisham where it then infiltrates the ground. Mixed with carbon dioxide
et al., 2009; Bakhshipouri et al., 2009). Construction of a new (CO2) from the air and soil, this water produces a weak car-
250 m long bridge across the Nenggiri River is expected to bonic acid (H2CO3), which seeps further into the ground
cost RM30 million (RM, Malaysian ringgit; equivalent to and makes contact with the limestone (calcium carbonate
£4 million). This incident should serve as a lesson to the railway (CaCO3)) and/or dolomite (CaMg(CO3)3) (Azam, 1996; Milne
industry and policy makers that extreme weather can have severe et al., 2014; Tan, 2001; Waltham and Fookes, 2003).
impacts on transportation infrastructure and operations. Rebuild-
ing railway infrastructure is often difficult and very costly; thus, 4. Climate change projections
to provide a reliable railway system for the future, studies of the
4.1 Climate and weather
potential impact of climate change are needed. Such studies
The American Meteorological Society, quoted by Dessler
would better inform the adaptation of railway infrastructure
(2012: p. 1), defines climate as ‘The slowly varying aspects of
and rolling stock to a changing climate (Krezo et al., 2016).
the atmosphere–hydrosphere–land surface system. It is typi-
cally characterised in terms of suitable averages of the climate
3. Topographical and geological challenges
system over periods of a month or more, taking into consider-
in Malaysia
ation the variability in time of these averaged quantities’.
The route of the planned Malaysian HSR, designed by SPAD,
According to Dessler (2012), weather refers to the actual state
will run along the coastal area. It is important to note that
of the atmosphere at a particular time. Climate, in contrast, is
Malaysia comprises a wide range of rock types, from the sands
used for statistical descriptions of the weather over a period of
and silts of the coastal plains to the granite of the main range.
time, usually several decades.
In peninsular Malaysia, the geology ranges from Cambrian
to Quaternary, that is from 570 million years before present,
to around 10 000 years ago. Sedimentation was unremitting 4.2 Climate change in Malaysia
throughout the Palaezoic and Mesozoic eras and, owing to the Malaysia is located near the equator, and is characterised as a
basin instability, there were major faults within and between tropical country with a monsoon climate. It experiences heavy
the Palaezoic, Mesozoic and Cenozoic groups of rocks. These precipitation all year round. The weather is strongly influenced

4
Downloaded by [ Syracuse University] on [16/09/16]. Copyright © ICE Publishing, all rights reserved.
Transport Operational readiness for climate change
of Malaysia high-speed rail
Binti Sa’adin, Kaewunruen and Jaroszweski

North–South expressway
N
Proposed HSR KL–Singapore
40 km line

(a)

Quartenary Marine and continental deposits; clay, silt, sand, peat with minor gravel.
Basal of early Pleistocene age in Kuantan area.

Tertiary Isolated continental basin deposits of late Tertiary age, shale sandstone,
conglomerate and minor coal seams. Volcanics are in the Segamat area.

Jurassic– Continental deposits of thick, cross-bedded sandstone with subordinate


Cretaceous conglomerate and shale/mudstone. Volcanics are locally present.

Triassic Interbedded sandstone, siltstone and shale; widespread volcanics, mainly tuffs
of rhyolitic to dacitic composition in Central Peninsular. Limestone is prominent
in the lower part of the succession. Conglomerate and chert are locally prominent.

Permian Phyllite, slate and shale with subordinate sandstone and schist. Prominent
development of limestone throughout the succession. Volcanics, mainly rhyolitic
to andesitic in composition, are widespread.

Carboniferous Phyllite, slate, shale and sandstone; argillaceous rock are commonly carbonaceous.
Locally prominent development of limestone. Volcanics of acid to intermediate
composition are locally present.

Devonian Phyllite, schist and slate; limestone and sandstone are locally prominent. Some
interbeds of conglomerate chert and rare volcanics.

Ordovician– Schist, phyllite slate and limestone. Minor interlocations of sandstone and volcanics.
Silurian

Cambrian Sandstone with subordinate siltstone, shale and minor conglomerate.

Permian–Jurassic Intrusive rocks, mainly granite with minor granodiorite.

(b)

Figure 5. Geological map of the Malaysian stretch of the


HSR route (a full-colour version can be found in the online edition
of this paper)

by topographical features, particularly the mountain and sea– September, and the winter north-east monsoon from
land configuration. Two monsoons dominate the Malaysia December to February. Tropical storms and depressions form
climate; the summer south-west monsoon from May to in the South China Sea and the Indian Ocean.

5
Downloaded by [ Syracuse University] on [16/09/16]. Copyright © ICE Publishing, all rights reserved.
Transport Operational readiness for climate change
of Malaysia high-speed rail
Binti Sa’adin, Kaewunruen and Jaroszweski

South-east Asia is currently experiencing increasing surface

Drainage design must cater for ARI plus climate change projections
Platform level needs to cater for sea level rise and drainage design

Need to study rail designs resilient to high temperature or provide


Need to monitor the ground movement and the relationship with
air temperatures. The El Niño–southern oscillation (ENSO), a

rainfall intensity, especially in the karst area in Kuala Lumpur.


time-scale-based oscillation of the Indian Ocean dipole (IOD)
must cater for average recurrence interval (ARI) plus climate

and the intraseasonal Madden–Julian oscillation (MJO), influ-


ence the observed interannual and intraseasonal rainfall distri-
bution in South-east Asia. There are several studies that
demonstrate the increase in tropical cyclones originating in the
Pacific. These events cause major impacts to the Philippines
and Vietnam, including the floods in peninsular Malaysia in
2006 and 2007 (IPCC, 2014; MMD, 2009). The increasing
temperature and decreasing rainfall have both significantly
increased the intensity and spread of forest fires in South-east
Asia. Fires in peat regions in Indonesia during the El Niño
dry season are now common every year and have caused haze
in most ASEAN (Association of Southeast Asian Nations)
Adaptation measures

countries. The countries that are badly affected by this haze are
change projections

Indonesia, Malaysia and Singapore. In 2005, the prime minister


of Malaysia declared a state of emergency in Port Klang,
watchmen

Selangor, 40 km from Kuala Lumpur, after the air pollutant


index (API) reached 500 (the index’s pollutant components com-
bine carbon monoxide, ozone, nitrogen dioxide and sulfur dioxide
and it is reported in ppmv; PM10 particulate matter is reported
in μg/m3) (Joshi, 2005; Mukhlisin et al., 2015). According to the
short term

Malaysian Metereological Department (MMD, 2009), an


Long or

average temperature increase of 0·5°C to 1·5°C has been recorded


Long
Long
Long

Long

in peninsular Malaysia, with the September–October–November


period recording the highest increase in temperature, followed by
from climate change

December–January–February.
Likely negative

Malaysian rainfall distribution patterns are determined by


seasonal wind flow patterns and local topographic features. The
east coast of peninsular Malaysia experiences more heavy rain as
impact

High
High

High

the area is exposed to the South China Sea. Conversely, the west
Low

coast area of peninsular Malaysia is likely to be sheltered from


heavy rains due to its topographical location. Thus, the east
Performance

coast experiences more flooding during the monsoon season com-


pared to the west coast. It was also found that the south coast
impact

High
High
High

High

Table 1. Overview of risks of the Malaysia–Singapore HSR

will experience more rainfall during April, and that the east
coast is also likely to see increased rainfall during this period.
Medium
impact
Safety

5. Extreme weather and its potential impact


High
High

High

on railway infrastructure
Natural hazards due to extreme weather events have occurred
Increased flooding

frequently in Malaysia during the past decade. The most


Track buckling

devastating natural disasters experienced in Malaysia have


generally

Settlement

been due to floods and landslides. The risks and consequences


Landslide

associated with these events can affect railway infrastructure


Risks

and operations, as explained in Table 1.

5.1 Floods
Increased rainfall
Increased rainfall
Climate impact

Severe and destructive floods in the southern peninsular of


Sea level rise

Malaysia occurred in two events back to back in December


2006 and January 2007, which are known as Typhoon Utor.
group

The massive flood in Kota Tinggi Johor started when the


Heat

north-east monsoon brought heavy rain through a series of

6
Downloaded by [ Syracuse University] on [16/09/16]. Copyright © ICE Publishing, all rights reserved.
Transport Operational readiness for climate change
of Malaysia high-speed rail
Binti Sa’adin, Kaewunruen and Jaroszweski

storms. The series of floods were unusual as the 2006 average Malaysia when designing the platform level for bridges
rainfall return period was 50 years, whereas 2007 was equival- (Ahmad Radzi and Ismail, 2013).
ent to a 100-year return period. Extreme localised weather
events are among the natural causes that triggered the flash 5.4 Heat
floods (Sani and Diya, 2014). Significant consequences from There are many impacts of hot and dry weather to railway
such severe floods were evident in the shutdown of transpor- infrastructure, the most obvious being the risk of track buckling.
tation, logistics and railway systems. The impacts caused The definition of buckling is a track deformation constituting a
shortages of medicines, food, clean water and consumables. reportable misalignment, which would render the line unfit for
the passage of trains at line speed and/or would necessitate
5.2 Landslide emergency remedial work to a running line under either a tem-
South-east Asia suffers more landslides compared to other porary speed restriction or closure of the line. Track buckling is
parts of the world owing to its climate and geography. extremely dangerous as it can cause catastrophic derailment of
According to the United Nations university (UNU, 2005), trains and disruption to operations. Figure 7 shows a Singapore-
among natural disasters, landslides are ranked seventh in terms bound train which was derailed on 26 January 2013 due to
of fatalities, after windstorms, floods, droughts, earthquakes, rail buckling (New Straits Times, 2013). The wagons landed on
volcanos and extreme temperatures. On average, 940 people their sides, trapping the crew and injuring five passengers. Train
annually were killed by landslides in the decade from 1993 to services in the southern part of Malaysia were disrupted for
2002. Most of these victims were from Asia. It is important to several days owing to the difficulties rescuers and maintenance
note that there are many factors that can trigger landslides, crews had in reaching the remote location of the incident.
including changes in slope geometry, changes in water level,
rainfall intensity and changes in loading. However, in 6. Infrastructure design requirements for
Malaysia, the major cause of landslides is high precipitation operational readiness to climate change
(Zakaria and Ahmad Jamalluddin Shaaban, 2007). As well as examining the impact of climate change on rail
operational readiness, it is important to ensure infrastructure
Figure 6 shows the impact of an extreme rainfall event. In the resilience to emerging risks from climate change (Harris and
case of rock falls and landslides, road vehicles can often swerve to Ramsey, 1994).
avoid the hazard. Trains do not have this option, and as a result
even a minor landslide can cause a derailment risk (Jaroszweski 6.1 Horizontal and vertical alignment
et al., 2015; Petley, 2012). It is important for the infrastructure SPAD has developed a baseline alignment for HSR Malaysia,
manager to design the slope and track embankment with the con- but the detailed alignment remains confidential at the time of
sideration of extreme rainfall due to climate change. writing. Thus, this paper will discuss the conceptual alignment
of the HSR line in Malaysia. According to the International
5.3 Sea level rise Union of Railways (UIC, 2011, 2015) the typical parameters
A rise in the sea level has the potential to affect the 100-year for new high-speed lines include the following measures.
return period flood level, which is usually the standard used in
& The maximum gradient (depending on geographic charac-
teristic and operating conditions) for dedicated passenger
traffic is 35 mm/40 mm per metre run subject to suitable
rolling stock.
& Track centre distances for 200 km/h and 300 km/h speeds
are 4 m and 4·5–5 m, respectively.
& Maximum cants are between 150 mm and 170 mm.
& Minimum curve radius is shown in Table 2.

To reduce the use of structures in uneven terrain, the maximum


design of gradient is always implemented. SNCF adopted a
maximum gradient of 35 mm/m for its Paris–South East line,
which made it possible to reduce drastically the number of
bridges and tunnels on moderately uneven terrain, and reduce
the cost of construction to about 65% of a two-lane motorway
on the same terrain. However, powerful rolling stock and
massive earthworks are needed if these concepts are to be
Figure 6. The Bukit Lanjan rockfall along the New Klang Valley accomplished. The climate change risk associated with this
expressway, in November 2003, resulting in a 6-month closure approach will be very high, because high rainfall or droughts
will affect the degree of soil moisture in earthworks.

7
Downloaded by [ Syracuse University] on [16/09/16]. Copyright © ICE Publishing, all rights reserved.
Transport Operational readiness for climate change
of Malaysia high-speed rail
Binti Sa’adin, Kaewunruen and Jaroszweski

Figure 7. KTM train derailed due to rail buckling near the Figure 8. The Batu Tiga KTM Komuter station during a flash
Kempas, Johor station in southern Malaysia flood

from the construction area, thus floods frequently occur in the


Minimum speed: Ideal curve Recommended
immediate vicinity of build sites. This also applies to building
km/h radius: m curve radius: m
construction when run-off affects rail operations, as happened
to the two railway lines in Serdang (which is 15 km from
200 2500 3500
Kuala Lumpur). The floods put a halt to two important rail
300 5500 7000
services, the commuter and express rail lines, in 2005. Not only
Table 2. Minimum curve radius for HSR do the tracks become slippery, but the water poses a danger
to trains and passengers because high-voltage electricity (e.g.
1500 V DC/AC, 25 kV AC) is commonly used for train oper-
ations and signalling. The solution to this problem implemen-
Tunnelling in the Kuala Lumpur area will be the best method
of construction as it would be extremely difficult to construct ted by the drainage and irrigation department was to upgrade
the infrastructure without significant and long-lasting disrup- a 1 km stretch of a drain located just a few metres away from
the station. This work cost the Malaysian government
tion to surface transport. Previous light rapid transit and mass
rapid transit projects in Kuala Lumpur have demonstrated that £450 000, which could have been avoided if such measures had
tunnelling can be successful. However, Kuala Lumpur is a been taken beforehand (Zakaria and Ahmad Jamalluddin
Shaaban, 2007).
limestone area. Sink holes will most likely be the greatest risk
during the construction phase. Studies need to be carried out
to mitigate this problem. The flash flood that hit Klang Valley on 12 May 2015 affected
KTM Batu Tiga station, as shown in Figure 8. Passengers
were refunded 30 pence and were informed by KTM to alight
6.2 Earthwork
and find their own transportation from the station. This
The nature of earthworks will very much depend on the topo- passenger measure cannot be implemented when it comes to
graphy of the route. They will be governed by the rules set out HSR, as the fares and operations are more costly compared
by the government, which will include environmental protec-
to other rail services. Therefore, it is important for the develo-
tion. The government of Malaysia, by way of the Malaysia pers and policy makers involved in the HSR project to inte-
public work department, has set the guidelines to ensure that grate climate change considerations into their track vertical
each project should comply with these rules. Sections which
profile.
are constructed in cuttings and tunnels will make the align-
ment lower than the surrounding area, causing these sections
to be prone to flooding. Therefore, the point of discharge and 6.3 Soil stabilisation
flood level of these sections needs to be measured during the The proposed route of the Malaysian HSR line transverses
early stages. undulating ground including several limestone areas, swampy
areas and low-lying areas where floods occur annually. There
Other climate risks that must be assessed include the extreme were several design concepts for HSR Malaysia. These con-
rainfall events that Malaysia experiences during the monsoon cepts, however, are merely guidelines and can only be con-
season. Drainage is a common problem during the construc- firmed once soil investigations are carried out. However, based
tion phase. Most developers in Malaysia ignore the run-off on the risk analysis, geotechnical design and ground

8
Downloaded by [ Syracuse University] on [16/09/16]. Copyright © ICE Publishing, all rights reserved.
Transport Operational readiness for climate change
of Malaysia high-speed rail
Binti Sa’adin, Kaewunruen and Jaroszweski

improvement methodologies have been proposed, including 6.3.2 Option 2: partial removal and replacement
the following. with surcharge
In contrast to option 1, only partial removal of soft material
(a) Cut slope: maximum height of cut slope is expected to be is carried out and replaced with sand and/or suitable earth
up to four benches with the height of each typical bench fill. If the water table is present, sand is used as replacement
at 5 m and gradient of 1(V):1·5(H). Each bench is material and placed 300 mm above the water table. A geo-
separated with a 2 m wide berm for maintenance access textile separator is placed along the base of the excavation
and berm drainage. For this typical configuration the to avoid mixing of replacement fill with the original soft
slope is stable and does not normally need stabilisation ground. The maximum depth of removal is about 3 m.
work. Turfing by hydroseeding is necessary to minimise
erosion. Surcharge, between 1 m and 1·5 m thick above the finished
(b) Fill slope: the fill slope is proposed to be constructed at road level, is required to accelerate the consolidation of the
1(V):2(H) gradient with a bench height of 5 m and berm remaining soft soils. This treatment is suitable for relatively low
width of 2 m. Based on plans provided by the Malaysian embankments and soft soils less than 5 m thick.
public works department (JKR), it is anticipated that the
maximum height of fill slope will be about 15 m. 6.3.3 Option 3: replacement with surcharge and
Fill materials shall be compacted to 90% of maximum high-strength geotextile reinforcement
dry density (MDD) based on modified Proctor This option is similar to option 2 but with the addition
compaction, except within 1 m of road subgrade where of high-strength geotextile reinforcement along the base of the
the fill shall be compacted to 95% of MDD. excavation to increase the factor of safety against slope stability
(c) Bridge foundations: it is very likely that piers and failure. In addition, surcharge as per option 1 is required to
abutments of the bridge will need to be supported on accelerate the consolidation of soft soil. This treatment is suit-
piles. The use of prestressed concrete spun piles enables able for a high embankment with relatively thick soft soil.
piling works to be completed in a short time and is
economical compared to bored piles or micro piles. If it
is found that spun piles are not suitable, this may be due 6.3.4 Option 4: surcharge and vertical wick drains
to the shallow bedrock or hard/very dense ground. In In this particular treatment, there is no removal and replace-
that case, bored piles or micro piles shall be used. ment. A geotextile separator is placed on the original ground
(d) Bridge approaches: bridge approaches will be designed (after clearing the ground) and followed by a sand blanket
to comply with settlement criteria as specified by the about 1 m thick. Vertical wick drains are installed at triangular
authority. If the existing ground is not capable of spacing of 1·0 m to 1·5 m centre to centre to accelerate the
supporting the fill approach, the ground shall be treated consolidation of soft soil. This treatment is suitable for
or the fill shall be supported on piles – that is, piled embankments on very thick, soft soil for which the consolida-
embankment. tion period will be long – that is, more than 12 months if only
(e) Vehicular box culvert (VBC) foundation: VBC can be the treatment with surcharge is adopted.
founded on the original ground if the ground is capable
of supporting the load imposed by the VBC, traffic and If necessary, geotextile reinforcements shall be placed along
fill above the VBC. Otherwise, the ground will need to be the base of the fill to increase the safety factor against slope
treated or the VBC will need to be supported on piles. failure (Milne et al., 2014).
Type, size, length, capacity and spacing of piles shall be
determined based on soil investigation data. 6.3.5 Option 5: stone column
( f ) Proposed ground treatments: for embankments over This is a method where columns of soft ground are replaced by
soft ground, the treatments described in the following compacted stone columns, forming stone/soil composite. The
subsections can be considered (options 1 to 6). The use stone columns act as vertical drains, accelerating the consolida-
of such treatment will be based on the merits and tion of soft ground which is compressed by fill load, strength-
demerits of each treatment. ening the soft soils against shear failure and reducing the
magnitude of settlement of the soft soils.
6.3.1 Option 1: total removal and replacement
In this treatment, the whole layer of soft soil is removed and Similar to the vertical wick drain, geotextile separators and a
replaced either with suitable earth or sand if the groundwater 1 m layer of sand blankets are required. Normal sizes of stone
table is present within the excavation. The sand is placed up to columns range from 600 mm to 1000 mm in diameter and are
300 mm higher than the groundwater table. Earth/sand can be installed at a spacing of 1·5–2 times the diameter of the
placed above the sand fill. No surcharge treatment is required columns. As the size of the columns is much greater than the
for this treatment as the compressible layer is removed. This vertical drain, the consolidation period is normally less than
treatment is suitable for soft ground less than 3 m thick. 3 months.

9
Downloaded by [ Syracuse University] on [16/09/16]. Copyright © ICE Publishing, all rights reserved.
Transport Operational readiness for climate change
of Malaysia high-speed rail
Binti Sa’adin, Kaewunruen and Jaroszweski

Type of treatment Merits Demerits

Option 1 (a) No stability and settlement (a) For shallow soft soil only
(total removal and replacement) problem (b) Disposal of unsuitable materials
(b) Easy construction
(c) Cost effective
(d) No surcharge required
Option 2 (a) Suitable for low embankment (a) Not suitable for high embankment and
(replacement with surcharge) and shallow, soft soil thick, soft soil
(b) Easy construction (b) Stability problem for high embankment
(c) Cost effective (c) Long surcharge period as limited
(d) No surcharge required surcharge thickness due to stability
problem
(d ) Disposal of unsuitable materials
Option 3 (a) Suitable for high embankment (a) Long surcharge period for high
(replacement with surcharge and and thick soft soil embankment and thick soft soil
high-tensile reinforcement) (b) Easy construction (b) Disposal of unsuitable materials
(c) Cost effective
Option 4 (a) Suitable for high embankment (a) Slightly more costly compared to option 3
(surcharge and vertical wick drains) and thick soft soil (b) Specialist contractor for vertical drain
(b) Faster surcharge period required
(c) Overcome stability problem with
high-tensile reinforcement
Option 5 (a) Short surcharging period (a) More costly compared to option 4
(stone column) (b) Less settlement (b) Specialist contractor for stone column
Option 6 (a) Can solve all geotechnical (a) More costly compared to option 5
(piled slab embankment) problems
(b) Easy construction
(c) No surcharge period
Option 7 (a) Suitable to replace high (a ) Most costly option
(elevated structure) embankment over swampy/thick,
soft soil
(b) Narrow right of way compared to
embankment option

Table 3. Merits and demerits of each ground treatment option

As the consolidation period is shorter and settlement In civil engineering, the engineers can only be sure of the exact
magnitude is reduced, this method is suitable at bridge ground condition (especially deep below the ground) once the
approaches. tunnelling or excavation has started. Even though soil investi-
gations (such as taking a soil sample) and testing are performed,
these only act as a guide, and will never be fully accurate
6.3.6 Option 6: piled slab embankment
because underground conditions vary greatly with the amount
In this treatment, geotechnical problems such as settlement,
of water present. Malaysia’s major problem during construction
bearing capacity and slope stability can be solved/minimised.
is groundwater. A high proportion of the claims and litigation
The only disadvantage using this treatment is the cost. This
in construction contracts arise from groundwater problems.
treatment is proposed for embankments at bridge approaches
to overcome the differential settlement between a pile-founded
6.4 Structures and tunnelling
structure and a normal embankment.
Design structures such as viaducts and elevated structures
for railway tracks will eliminate the possibility of flooding to
6.3.6.1 MERITS AND DEMERITS OF EACH GROUND the HSR tracks in low-lying areas. According to the UK
TREATMENT OPTION Environment Agency (2009), pier scouring will be a risk to the
Table 3 shows the merits and demerits of each ground treat- UK based on the 2008 tidal Thames extreme water levels. This
ment option for comparison. analogy estimates that all tunnel portals are at risk of fluvial

10
Downloaded by [ Syracuse University] on [16/09/16]. Copyright © ICE Publishing, all rights reserved.
Transport Operational readiness for climate change
of Malaysia high-speed rail
Binti Sa’adin, Kaewunruen and Jaroszweski

No. Type of subgrade material Drainage properties

1 Non-cohesive materials like gravel Drains well and normally makes good subgrades
and sand
2 Cohesive clays and slits Very low permeability due to the small pores between the particles. In this case
rainwater falling on the track needs to be collected in the ballast and channelled
to drains before it gets to the subgrade. If not, over the long term the track
settlement will begin to show itself
3 Organic peats and silts The most difficult subgrade to build on and should be designed by specialists. It has a
variety of textures, and will usually shrink if drained or if subjected to repeated
loading
4 Sedimentary rocks such as Often permeable by water and also contain springs and lenses or layers of other
sandstone or limestone materials. Provided suitable means of drainage, this subgrade material will offer
a satisfactory subgrade even if waterlogged
5 Igneous rocks such as granite Impermeable and are unlikely to give any problems to the subgrade

Table 4. Type of subgrade material and their drainage properties

flooding against a best estimate peak flood level of a 1 in the HSR developer or policy-maker accept the failure of oper-
200-year return period ations once a year, or should they build to withstand a high
return period event? The answer will depend on many factors
6.5 Drainage including financial and economic viability, as well as the
One failure system that could paralyse the whole railway oper- climate projections for the given area.
ation is drainage. Weakness of drainage design often leads
to flooding. Usually the selection of rainfall intensity will be 6.6 Track structure and substructure
based on the return period or average recurrence interval (ARI) Continuous welded rail with continuous ballast is frequently
selection. Rainfall intensity is not a measure of how often it adopted by designers for most high-speed railway tracks. It is
rains; rather it is about heavy downpours that only occur once in important that the rail be designed to accommodate projected
100 years, for example. Normally rainfall intensity is measured changes in climate such as extremely hot weather to prevent
in millimetres per hour over a given duration. The heaviest rain- buckling occurring, as Malaysia will experience higher temp-
fall deluges are likely to be experienced for a short period. Most eratures in the future. Continuous ballasts are favoured as
rainfall intensity measurements use 5 min durations. The ARI they allow automated maintenance, meaning it is often
describes how often a particular rainfall event can be expected specified where there is a discontinuity in the track support,
to occur. The ARI is normally expressed in years. such as transitions on or off fixed structures or over structural
movement/expansion joints (Remennikov et al., 2012).
As discussed earlier, the heaviest rainfall will occur during However, according to Kwon and Park (2006), since the begin-
the monsoon season. As previously mentioned, there were two ning of the high-speed train operations in Korea in April 2001,
major events back to back in Johor in December 2006 and several unfavourable impacts have been observed on the oper-
January 2007. This area coincides with the planned route of ating ballast-track lines, including the flying ballast phenom-
the Malaysian HSR. The massive flood in Kota Tinggi Johor enon. This in turn caused damaged wheels, broken glass at
started when the north-east monsoon brought heavy rain stations and damaged acoustic screens. It has also been noted
through a series of continuous storms. As highlighted earlier, that the track design of HSR Malaysia could incorporate these
the series of floods were unusual as the 2006 average rainfall findings, as follows.
return period was 50 years and the return period of the 2007
event was 100 years. Localised extreme weather events are one & At wind velocities of 20 m/s, ballast laid on the wind
of the major natural causes that trigger flash floods (Harris tunnel will start to move and will completely blow out at
and Ramsey, 1994; Kwon and Park, 2006; Lane and Dora, a wind velocity between 25 m/s and 45 m/s. Furthermore,
2011). Thus, selection of ARI should accommodate climate for ballasts stacked between ties, at wind velocities of
change and should not be based just on historical data but only 33 m/s, flying ballast is observed.
also future projections of rainfall intensity. However, the cost & As the mass of ballast becomes smaller, the ballast starts to
will be excessive if a return period of 100 years is used as a move at lower wind velocities.
design standard. As such, the return period used in the design & Flatter ballast (high flakiness ratio) has a higher critical
of the HSR platform level should be well considered. Should wind velocity compared to rounded ballast.

11
Downloaded by [ Syracuse University] on [16/09/16]. Copyright © ICE Publishing, all rights reserved.
Transport Operational readiness for climate change
of Malaysia high-speed rail
Binti Sa’adin, Kaewunruen and Jaroszweski

& Higher ties or a lower ballast surface will prevent ballast Research Fellowship (long term) at the Railway Technical
flying. Research Institute and The University of Tokyo, Tokyo, Japan.
& Countermeasures should be focused at the centre of the Financial support from the European Commission is gratefully
track because the strongest airflow is observed in this region. acknowledged for H2020-MSCA-RISE Project No. 691135
& The probability of ballast flying at a train speed of ‘RISEN: Rail infrastructure systems engineering network’,
350 km/h is about double that at 300 km/h. which enables a global research network that tackles the grand
challenge of railway infrastructure resilience and advanced
There is also a new form of railhead damage known as ballast sensing under extreme events.
pitting that often occurs on high-speed lines because of the
speed and energy of the vehicle, which is thought to generate an
explosive crushing of the ballast particles. This in turn damages REFERENCES
the railhead. This mechanism is also thought to be associated Ahmad Radzi A and Ismail H (2013) Trend analysis of sea
with the nose region of vehicles (Quinn and Hayward, 2008). level rise for Kukup (Johor), west coast of peninsular
Malaysia. Proceedings of the International Conference
The track bed is the ground base onto which a railway track is on Emerging Trends in Engineering and Technology, Phuket,
laid. Normally the track bed is laid on natural ground with the Thailand, pp. 113–115.
removal of 100 mm or 50 mm thickness of topsoil. According Azam T (1996) Project KLCC: geology, soils and foundations.
to Bonnet (2005) the control of water in the track bed is a Newsletter, Geology Society Malaysia: 73–74.
major factor in designing the construction layers in relation to Badrul Hisham A, Marzukhi M and Daud A (2009) The worst
the subgrade material, which is shown in Table 4. flood in 100 years: Johore experience. Malaysian Journal of
Community Health 15: 1–14.
Bakhshipouri Z, Omar H, Yousof ZBM and Ghiasi V (2009)
7. Concluding remarks
An overview of subsurface karst features associated with
Although international communities have agreed to set a
geological studies in Malaysia. Electronic Journal of
common goal for reduction in global warming, climate change
Geotechnical Engineering (EJGE) 14(P): 1–15.
is still a natural threat to critical infrastructure. Malaysia is
Bakhshipour Z, Huat BBK, Ibrahim S, Asadi A and Umar Kura N
still far behind in terms of assessing the risks and vulnerability
(2013) Application of geophysical techniques for
of railway operations to climate change. There is a lack of
3D geohazard mapping to delineate cavities and potential
studies on the potential regional and local impacts of climate
sinkholes in the Northern part of Kuala Lumpur,
change on Malaysian railway infrastructure and operations.
Malaysia. The Scientific World Journal 2013: 629476.
Now that Malaysia is planning to build a new HSR line
Bonnet CF (2005) Practical Railway Engineering. Imperial
between Singapore and Malaysia, the mitigation and adaption
College Press, London, UK.
measures to the risk of climate change are crucial in assuring
Dessler AE (2012) Introduction to Modern Climate Change.
Cambridge University Press, New York, NY, USA.
& railway safety
Environment Agency (2009) Assessment and Measurement of
& reliability
Asset Deterioration Including Whole Life Costing.
& capacity for the future
Environment Agency, Bristol, UK, Science Report
& value for money
No. SC060078/SR2.
& prevention and recovery of assets from natural disaster.
Harris NG and Ramsey JB (1994) Assessing the effects of
railway infrastructure failure. The Journal of the
The impact of climate change on the operational readiness
Operational Research Society 45(6): 635–640.
of HSR in Malaysia is thus highlighted in this paper. The vul-
IPCC (Intergovernmental Panel on Climate Change) (2014)
nerability of rail infrastructure has been evaluated with the use
IPCC, 2014: Climate Change 2014: Synthesis Report.
of local geographical information. Mitigation and risk man-
Contribution of Working Groups I, II and III to the Fifth
agement measures have been proposed to help track engineers
Assessment Report of the Intergovernmental Panel of the
and designers better manage the risks, which should in turn
Intergovernmental Panel on Climate Change. IPCC,
improve infrastructural and operational resilience.
Geneva, Switzerland.
Jaroszweski D, Hooper E, Baker C, Chapman L and Quinn A
Acknowledgements (2015) The impacts of the 28 June 2012 storms on UK
The authors are grateful to Malaysia Land Public Transport road and rail transport. Meteorological Applications 22(3):
Commission (SPAD) for information and financial support 470–476.
throughout this study. They would also like to thank Joshi V (2005) Malaysia haze prompts state of emergency.
Kritditorn Chamniprasart for assistance in the reproduction Mongabay, 11 August. See https://news.mongabay.com/
of infographics. The second author wishes to thank the Japan 2005/08/indonesian-forest-fires-again-cause-haze-in-
Society for the Promotion of Sciences for his Invitation malaysia/ (accessed 01/12/2015).

12
Downloaded by [ Syracuse University] on [16/09/16]. Copyright © ICE Publishing, all rights reserved.
Transport Operational readiness for climate change
of Malaysia high-speed rail
Binti Sa’adin, Kaewunruen and Jaroszweski

Kramer SA, Prudent-Richard AG and Sainsbury M (2010) Sani G and Diya MB (2014) Floods in Malaysia: historical
Incorporating Climate Change Impacts and Adaption in reviews, causes, effects and mitigations approach.
Environmental Impact Assessments: Opportunities and International Journal of Interdisciplinary Research and
Challenges. The Organisation for Economic Co-operation Innovations 2(4): 59–65.
and Development (OECD), Paris, France, OECD Tan BK (2001) Engineering geology of limestone in Malaysia.
Environmental Working Paper no. 24. Acta Geologica Sinica 75(3): 316–324.
Krezo S, Mirza O, He Y, Makim P and Kaewunruen S (2016) TheSundaily (2015) Construction of railway bridge in
Field investigation and parametric study of greenhouse gas Kemubu ready next year: KTMB. theSundaily, 14 July.
emissions from railway plain-line renewals. Transportation See http://www.thesundaily.my/news/1489643 (accessed
Research Part D: Transport and Environment 42(1): 77–90. 03/08/2016).
Kwon H and Park C (2006) An Experimental Study on the UIC (International Union of Railways) (2011) High Speed Rail
Relationship between Ballast-Flying Phenomenon and and Sustainability. International Union of Railways, Paris,
Strong Wind under High-Speed Train. Korea Railroad France. See http://www.uic.org (accessed 15/06/2015).
Research Institute, Gyeonggi, Republic of Korea. UIC (2015) High Speed Rail: Fast Track to Sustainable
Lane J and Dora J (2011) Tomorrow’s railway and climate Mobility. International Union of Railways, Paris, France.
change adaptation (TraCCA). Proceedings of the World See http://www.uic.org (accessed 01/09/2015).
Congress on Railway Research, WCRR, Lille, France UNU (United Nations University) (2005) Climate Change Will
(CD-ROM). Mean More Landslides, Experts Warn. United Nations
Milne D, Le Pen L, Powrie W et al. (2014) The influence of University, Shibuya, Tokyo, Japan. See http://update.unu.
structural response on ballast performance on a high edu:archive.unu.edu/update/issue40_10.htm (accessed
speed railway viaduct. Proceedings of the International 22/10/2015).
Conference on High Speed Rail, Birmingham, UK. Victorian Government (2005) Victorian Greenhouse Strategy
MMD (Malaysia Metereological Department) (2009) Climate Action Plane Update. Victorian Government, Melbourne,
Change Scenarios for Malaysia 2001–2099. Malaysian Victoria, Australia.
Metereological Department, Selangor, Malaysia. Waltham A and Fookes P (2003) Engineering classification of
See http://www.met.gov.my (accessed 01/05/2015). karst ground conditions. Speleogenesis and evolution of
Mukhlisin M, Matlan SJ, Ahlan MJ and Taha MR (2015) karst aquifers. Quarterly Journal of Engineering Geology
Analysis of rainfall effect to slope stability in Ulu Klang, and Hydrogeology 36(2): 101–118.
Malaysia. Jurnal Teknologi (Sciences and Engineering) Zakaria S and Ahmad Jamalluddin Shaaban CY (2007) National
72(3): 15–21. Policy Responses to Climate Change: Malaysia Experience.
New Straits Times (2013) Singapore-bound train derails, National Hydraulic Research Institute of Malaysia
worker trapped, 8 injured. New Straits Times, 26 January. (NAHRIM), Kuala Lumpur, Malaysia.
Pachauri R and Meyer L (eds) (2014) IPCC, 2014: Climate
Change 2014: Synthesis Report. Contribution of
Working Groups I, II and III to the Fifth Assessment
Intergovernmental Panel of Climate Change. IPCC, Geneva,
Switzerland.
Petley D (2012) The national slope masterplan in Malaysia.
AGU Blogosphere – The Landslide Blog. American
Geophysical Union, Washington, DC, USA. See http://
blogs.agu.org/landslideblog/2012/11/07/the-national-
slope-masterplan-in-malaysia/ (accessed 01/06/2015).
Quinn A and Hayward M (2008) Full scale aerodynamic
measurements underneath a high speed train. Proceedings
of the BBAA VI International Colloquium on Bluff Bodies, HOW CAN YOU CONTRIBUTE?

Aerodynamics and Applications, Milan, Italy. To discuss this paper, please email up to 500 words to the
Remennikov AM and Kaewunruen S (2008) A review of loading editor at journals@ice.org.uk. Your contribution will be
conditions for railway track structures due to train and forwarded to the author(s) for a reply and, if considered
track vertical interaction. Structural Control and Health appropriate by the editorial board, it will be published as
Monitoring 15(2): 207–234. discussion in a future issue of the journal.
Remennikov AM, Murray MH and Kaewunruen S (2012) Proceedings journals rely entirely on contributions from
Reliability based conversion of a structural design code the civil engineering profession (and allied disciplines).
for prestressed concrete sleepers. Proceedings of the Information about how to submit your paper online
Institution of Mechanical Engineers, Part F: Journal of Rail is available at www.icevirtuallibrary.com/page/authors,
and Rapid Transit 226(2): 155–173. where you will also find detailed author guidelines.

13
Downloaded by [ Syracuse University] on [16/09/16]. Copyright © ICE Publishing, all rights reserved.

You might also like