You are on page 1of 3

0309-216Mep 4/01/07 15:43 Page 46

COLLOQUIA SC B3

THE SUBSTATION DESIGN PROCESS


AN OVER VIEW
This report was presented at the CIGRE B3 Colloquium
in Venezuela (22-23 October 2001)
Preferential Subject 1
B Y G A R Y E N G M A N N , PA U L F L E T C H E R , L U I G I G I A N U Z Z I , B . N K I S H O R E , J I R I K U N T ,

ERIC LEBOULANGER, JORGE ROIG, ANNE-MARIE SAHAZIZIAN.

1. Summary characteristics (such as short-time current ➤ The need for a new substation has
level, maximum current carrying capac- been identified.
This paper provides an overview of ity, characteristics of transformers, insu- ➤ The system requirements (includ-
the process by which a substation is estab- lation level and compensating devices). ing performance requirements).have been
lished. It considers the system require- The location of a substation at a par- defined.
ments, site selection, and community ticular site will give rise to specific system
acceptance. requirements, some will however be stan- Given this information a suitable site
The attached figure shows the various dardised within the network of the Util- can be selected for the substation consid-
stages necessary in the establishment of ity. Examples of system requirements are ering the following:
a new substation. It gives a typical exam- general location requirement, extent of
ple where a «step by step» approach to the the substation, required availability of
planning and design process is considered. circuits, busbar schemes, current rating, 3.1 Site selection
However, in practice iterative actions may fault current levels, neutral point earth-
often be involved. ing, fault clearance time with respect to For the location of a new substation
This process is described in greater system stability, future extensions, con- in the network, several alternatives often
detail in a CIGRE Technical Brochure [1]. trol and needs of personnel and equip- exist. The total costs of each option
ment characteristics. should be calculated. The cost of build-
ing new transmission lines and the rein-
forcement of existing circuits are often in
2. System require- 2.2 Busbar Scheme the same order as that of the substation.
ments It is thus worth examining various alter-
The selection of a busbar scheme and natives with system planners to limit
2.1 Technical Parameters its possible extensions for a particular sub- transmission line costs.
The design of a substation depends on station is an important initial step of the The choice of a site for a substation
the functions it has to fulfil, these are design. Among the matters that affect this is a compromise between technical, eco-
defined by system planners decision are operational flexibility, system nomic, environmental and administrative
Technical parameters are established safety, reliability and availability, ability to factors.
in consultation with asset managers, sys- facilitate system control and costs. The area available for the substation,
tem operators and system users transmis- the number of outgoing feeders of differ-
sion departments. They are defined by ent voltage levels, the number of main
means of system studies and economic transformers, the busbar schemes and the
considerations. Economic benefits may 3. Design procedure possibility of extension as well as com-
be derived from specifying the technical pensating equipment options should take
requirements to allow the use of stan- The starting point for the substation into consideration future needs and life
dardised HV equipment with identical design procedure is as follows : expectancy of the substation.

46 E L E C T R A N°210 - Octobre 2003


0309-216Mep 4/01/07 15:43 Page 47

COLLOQUIA SC B3

No. 210 - October 2003 E L E C T R A 47


0309-216Mep 4/01/07 15:43 Page 48

COLLOQUIA SC B3 C O N T I N U E D

The first step is to locate possible sites, ➤ Protected areas : The site should be the choice of a substation layout. Diffi-
which are as level as possible, with enough chosen so as to avoid any areas or spots culties in the establishment of line corri-
available area, at reasonable costs, with listed as protected areas due to the impor- dors may be overcome by the use of multi-
easy access, within the general location and tance of their plant or animal communi- circuit pylons or, in extreme cases,
without important restrictions on line cor- ties or their cultural heritage. changing from overhead line to under-
ridors, where the substation can be erected ground cables.
with minimum environmental impacts. It ➤ Community Planning : The local
is advantageous to locate sites near to exist- town planning policy needs to be taken ➤ Pollution : The risk of failure and the
ing line corridors or even at crossing into account when siting the substation to equipment maintenance costs will gener-
points. Sometimes such places simply do avoid urban areas, development land or ally increase with the pollution level. Such
not exist and the choice will be confined land held in reserve for possible future risks are however minimised with GIS.
to places that have only some of the above development. Landscaping may be cov-
characteristics. ered by local regulations and should be
Once the possible sites have been considered in detail.
located, an analysis is then made for all the 4. Implementation
technical and environmental aspects of Other environmental considerations
each one, including costs, potential envi- to be taken into account in the design, such Having selected the site location, the
ronmental impacts and the preventive or as aesthetics, noise, oil leakage /spills, waste design and construction process would
corrective measures that can be taken to management, etc., are described in [2]. broadly follow the steps shown in Fig1.
avoid or reduce them. It is also worthwhile Recent trends in Utilities have been
to assess the community acceptance of towards sourcing design and construction
project. 3.3 Technical Aspects of substations through competitive bid-
This analysis then furnishes the cri- ding processes to ensure capital efficien-
teria for deciding on the most suitable sub- Technical aspects to be considered in cies and labour productivity.
station site, bearing in mind the degree the site selection process include:
of feasibility and the project cost of each
alternative. If no suitable site is found, the ➤ Topography : The area of the sub-
process may be reinitiated with another station site should preferably be flat but
general area. not prone to flood or water stagnation. 5. References
➤ Geological characteristics : The soil [1] General guidelines for the Design
3.2 Environmental Aspects must allow the construction of roads and of Outdoor AC Substations: CIGRE
foundations. A low value of soil resistivity Brochure 161, Aug 2000.
The possible impacts on the natural or is desirable to facilitate earthing system [2] Sahazizian, A.M., Kertesz, T.,
social environment should be considered, design. The seismic characteristics of the Boehme, H., Roehsler, H., Elovaara, J.,
such as: area should also be considered. Blackbourn, R., Stachon, J., Aoshima, Y.,
Fletcher, P. On behalf of WG 23.11: Envi-
➤ Land : The site should be chosen ➤ Access : The most difficult equip- ronmental aspects in Substations; CIGRE
such that the need for earth movement ment, as far as access is concerned, are 1998; 23-201. ■
and spoil disposal are minimised. power transformers and large reactors, the
other equipment being of shape compat-
➤ Water : The site should be chosen ible with any common transportation net-
so as to avoid any damage to the natural work. The transport procedure must be
drainage network, especially to permanent checked both ways (to and from substa-
surface watercourses. tion site) and measures taken to maintain
it during the substation lifetime. Access of
➤ Vegetation : Where possible the operators and maintenance teams must
substation should be sited in low-produc- also be considered.
tivity farming areas or uncultivated land,
avoiding areas in which the existing plant ➤ Line entries : Line corridors have
formations have a high ecological or eco- great influence on the geographical ori-
nomic value. entation of the substation and may impose

48 E L E C T R A N°210 - Octobre 2003

You might also like