Project Name : INSTRUMENT AIR 7,5K

Originated by : Date :

NO DESCRIPTION SPEC UNIT QTY U/PRICE AMOUNT REMARK


I MATERIAL COST
1 PIPE CARBON STEEL 4" Mtr 90,0 180.000 16.200.000
2 FLANGE CLAS #150 4" Mtr 20,0 71.000 1.420.000
3 GASKET TEPLON 4" Mtr 10,0 71.000 710.000
4 BOLT AND NUTS 20M X 100 Pcs 72,0 4.150 298.800
5 GATE VALVE 4" Pcs 1,0 71.000 71.000
6 CON REDUCER 6 "X 4" Pcs 1,0 106.500 106.500
7 PAINTING SUPPORT Lot 1,0 695.000 695.000

SUB TOTAL I 19.501.300

II CONSUMABLE COST
1 Material Consumable Lot 1 2.925.195 2.925.195
SUB TOTAL II 2.925.195

III EXPENSE
1 TOOL LOOSE FEE 585.039
2 EXPENDITURE 3.588.239
SUB TOTAL III 4.173.278

GRAND TOTAL 26.599.773