Work Plan for The Towing Bridle Assembly

Tasks Responsible Start End Days Status


11/26/2018
Review of Documents relating to
fabrication of Flounder Plate MPN 11/22 11/26 4 Complete
Availability of materials
including mill certificates & Inspection of
Materials HNL/WAOS/MPN 11/09 11/26 17 Complete
Flounder Plate Fabrication
Marking out of Sheet Plates HNL/WAOS 11/26 11/26 4 Hrs In progress

Dimensional checks of
marked out materials before cutting. HNL/WAOS 11/26 11/26 1 Hr
Cut to Size HNL/WAOS 11/26 11/26 3Hrs
Mark out Cheek Plate, Cut and Tack
Weld HNL/WAOS 11/27 11/27 1
Dimensional Checks before Welding &
Welding HNL/WAOS 11/28 11/29 2
Visual Inspection of Welds HNL/WAOS 11/29 11/29 1 Hr
NDT for welds after visual examination HNL/WAOS 11/29 11/29 1 Hr
Blasting / Painting of Flounder Plate HNL/WAOS 11/29 11/29 2 Hrs
Transfer of Flounder Plate to Towing Bridle
Testing Site (Location TBD by Bureau
Veritas) HNL/WAOS 11/30 11/30 2
Delivery of Towing Bridle Ancillaries (Shackle,
Master Link & Stud Chain Links)
Receipt of Materials & Issue of OEM Test
Certificates and Proof Load Certificate Nigerian Ropes 11/28 11/28 1 Not started

Transport of Towing Bridle Ancillaries to Port


Harcourt HNL. 11/29 11/30 1 Not started
Third Party Certification
Design review of construction drawing and
details, material specification and
calculation note at SWL. Bureau Veritas 11/02 12/02 30 In Progress

Testing Bureau Veritas 12/3 12/4 1 Not started

Delivery to FOT Onne HNL 12/5 12/5 1 Not started