You are on page 1of 8

Engineers Australia Design Guidelines: Develop a design usually covered by civil law »very important to resolve Batch processes

Batch processes flowsheets: Very important in pharmaceutical working practices/ Unexpected increase in cost of supplies
solution to meet the project objectives conflicting requirements early and officially in writing industry/Batch processes are time dependent, not steady (Raw materials, Energy, Spare parts, unfavourable exchange
state/ Process flowsheet shows: Line diagram of equipment rate changes)/Increases in tax and insurance charges/New low
Reduce as far as reasonable: Waste production/Energy What do Standards Cover? Fuels/Raw materials/Products/ Sequence of operation with: Step sequence number, time of cost plant opens and competes in market
consumption/Maintenance/Unreliability /Cost Materials of construction (Cement, concrete, steel, plastics, the step, Action undertaken and quantities involved.
glass, electrical wiring, piping cabling, etc)/Electric motors/ Plant sizing Optimum sizing crucial for success
Design requires you to: Make the process choices /Select and Controls/Instruments/Painting, ect/Design: Documentation Process and Instrument Diagram (P&ID):Shows all process
size the equipment/Design the equipment items/Draw the (Reporting, drawings, mass and energy balance presentation, equipment identified by number/Equipment is roughly drawn Oversized plantspoor economic performance/Poor
various flow sheets and plant layout/Undertake the etc. ), Foundation design, Structures, Pressure vessel design, in proportion with location of nozzles shown/All pipes technical efficiency (equipment operating at turndown rather
HAZOP/Undertake the economic analysis/Undertake the piping (inc. support), storage tanks and sheds, Instrumentation identified by line number (Pipe size and material should be than optimum condition)/Overcapitalisation (high interest &
environmental and sustainability analysis/Write the report systems & safety protective systems identified, Flanges are shown )/All valves (both block & depreciation charges)
control) with an identification number( Type & size should be
Teamwork: Most projects (even small ones) are too large for Project Specification: Applies only to the current project/ identified : Valve types are usually identified by use of a Undersized plantLoss of revenue because production
one person/Design requires a wide range of skills (process, Typically covers: Product quality specification, Raw materials symbol, Failure modes are also identified where relevant)/ targets are not achieved/Poor technical efficiency (equipment
mechanical, civil, electrical, architectural skills)/ Few engineers to be used and their availability and location, Production Shows all ancillary fittings that are part of the piping system pushed to the limit, high maintenance costs)
have all the skills required to undertake even a small design capacity in tonne/year, Plant location with site and access (Sight glasses, filters, steam traps, etc, Identified by number)/
requirements, The overarching and company standards that Optimum sizing: to achieve least cost over entire life cycle
All instruments with Pressure gauges, temperature sensors,
Working in teams: cannot choose team members, must work apply (Energy costs are unpredictableEasier to determine
flow meters, etc.( Identified by number, All control loops )/
with all team members, working together is critical for design, optimum vessel size than optimum pumping costs)
Identifying the sensor and control action, Control loops are
disagreements need to be resolved quickly/plan the project as Design Project Requirements also identified by number Feasibility studies: undertaken to assess: Market for proposed
a group/divide the work equally between team members/
Communicate well: Hold weekly meetings, don’t withhold All design is undertaken to a specification divided into two product/ Technical feasibility of proposed process/ Economic
information, especially important when developing the mass parts: An overall specification applying to all projects /A feasibility/ Likely environmental impact // Demand for
Importance of P&ID: Diagrammatic record of the design/ products generally increases with time
and energy balance. process specification applying only to your specific project
Foundation for Hazard Analysis/Used to preparing: Equipment
Purpose of Meetings: Review progress/Identify difficulties/ Overarching specification specifies: Scope of design project List (a list & data sheet of all major items), Bill of Materials (all Typical feasibility study consists of: Conceptual design with:
Plan resolution of difficulties/Allocate priorities (tasks to be including: The objectives of the design of the project allotted other items not on equipment list, some Bills of Materials also Block flow diagram/Preliminary mass & energy balances/
completed prior to the next meeting) to each group/Timescale allowed/Format of report/Plant include items on the equipment list)/ Operating and Preliminary cost estimates (cost of plant (typically + 30%), fixed
layout and site development/Plant operability & safety maintenance instructions costs, direct production costs, administration, distribution
Structure of Meetings: Choose chairperson to prepare the assessment/Environmental impact and sustainability costs, etc..)/More detailed assessment of any proposed new
agenda and manage the meeting/Choose a secretary to record Industrial Context of Projects & Plant Sizing Methods technology/Preliminary environmental impact assessment.
assessment /Capital and operating cost estimates/Work
the minutes/ The chairperson and secretary roles must rotate schedule format/Conclusions and recommendations/Minutes Intent: Produce useful products/Make a profit for its Typical Process Plant Items: Size changing plant (Size
between all group members. of group meetings owners/Be safe in operation/Minimise environmental damage reduction: Crushers/ Size increasing: sintering)/ Separation
Minutes of Meetings: Members in attendance/Members Project specific specification specifies: Scope of project, plant (dryers, centrifuges, gravity settlers, filters, distillation
Risk: The process might fail owing to design errors/Cost over
absent and the reason for the absence/Progress since last the project number and title: Project background/Product or columns, thickeners, electrical and magnetic separators)/
runs may eliminate profit/There may be major safety &
meeting and comparison with the project plan/Problems that products to be manufactured/Annual capacity/Plant Combining plant (Mixers - undertake physical mixing of more
environmental problems  minimise risk
have been resolved/ New problems that have arisen and the availability and design life required/Feedstock than one feed stream)/ Reactors – undertake chemical
plans to resolve them /Work allocation for the coming week. specification/Location may also be specified or left to the Commercial risk Major object of any plant is to: Produce reactions: Separation, Synthesis, Many reactors undertake
group to choose useful products that are in demand (Sell those products for a more than one process.
Specifications: Detail of the design and materials/ A set of
profit, maximise the return for shareholders)/ The investors
instructions governing the design, construction and Process Flowsheets: Flowsheets are key documents in the Typical Reactors: Gas-solid (Fixed bed: Used where the solid is
seek a rate of return on their investment while their money is
commissioning of a plant/ a very large document or series of development of designs/Four basic types: not consumed, Moving bed: Used where the solid is consumed,
being used /Any investment involves a risk arising from factors
documents/Typically 2 groups: Overarching standards that Fluidised bed: used where the bed is catalyst or where the bed
such as: Failure of the process, Change in market demand,
apply to all projects, Project specific standards/Specifications Block Flow Diagram: Diagrammatic description of the is consumed, Rolling bed: Used for solid-solid & gas-solid
New, low cost competition, New, replacement product.
can be a legal requirement of the government or based on process/Shows the major process operations in block or reactions)/Gas liquid (Bubble column: Co-current, counter-
national or client requirements symbolic form/Does not show: Control or ancillary items, Mass Financial risk: The higher the risk the greater the rate of return current, fixed, plug-flow, Used for solid-solid & gas-solid
flows, temperatures or pressures, Utility requirements/ Only required to justify that risk, Difficult to quantify risk to capital reactions)/Three phase (Suspension, slurry, fluidised bed,
Statutory specifications: Specifications that are legal the major operations - essential for a basic understanding of Bubble column, Flash smelter)
authority/must be complied with non-compliance is a criminal the process are incorporated Capital costs include: Design costs, Cost of land occupied,
offence/ replaced by legally endorsed National Standards Construction costs, Interest charges on expenditure to date, Plant Sizing Methods
Process flowsheet or diagram (PFD) show: Tanks, vessels, Commissioning costs, Fees for licences, permits, etc..
Overarching Standards mixers, etc. Major pumps, fans, & compressors, Heat Capacity terminology
exchangers, reactors, Separators, filters, etc, Major pipes and Major risk: Delayed completion & extended
National & International Standards: Compliance is not ducts, Major valves/Only those necessary for process Annual production capacity (tonne/annum)
commissioningIncreased interest charges, increased capital
compulsory but failure to do so without good reason may be understanding, As the design is developed, mass and energy investment Mean daily design rate (MDDR) (tonne/day): The basis of
considered legal negligence/ Some national standards are balance information is added
legally endorsed and effectively become statutory most equipment sizing /Takes into account: Normal variation
Operating costs include: Interest payments on capital
specifications Process flowsheet Index MUST have and shows: All lines in production between different days caused by various
invested, Insurance, Taxes, Depreciation, Operating costs (Raw
identified by number (For simplicity line numbers should only factors; Equipment downtime required for: Scheduled
materials, Energy, Labour costs, Maintenance)
Industry Codes: Codes developed by industry funded change when: Line enters a vessel (except for a cooling or maintenance, Catalyst regeneration, Breakdown; Usually
associations: Provide guidance for industry specific problems, heating coil), Line exits vessel, A line divides or joins)/ Size of Risks to profitability: Over-capitalised plant (Interest charges quoted in tonnes/day
Principally construction or safety related line/Material flowing in line/Mass flow rate of material in too high, Depreciation too high)/ Undercapitalised plant
Calculation of mean daily design rate:
consistent units /Pressure and temperature of material (Poorly designed: High energy costs, Low yields /Poor
Company Standards: Company-wide standards and
equipment: High maintenance costs)/Long construction
specifications/Failure to comply with a company standard is
and/or commissioning times/High labour charges and/or poor
Pannual x IF Traditional sizing method used constant volume/tonne the more popular processes /other processes calculations internal diameter of tube or cylinder (mm), t = thickness of wall
MDDR = production, Failed badly when scale up because increase in have to be done by hand or with Excel (mm))
(365−S)
secondary air velocity above upper limit with existing burner
designs resulted in severe deterioration in fuel/air mixing Optimum Equipment Sizing Determining shell thickness: The longitudinal stress is given
MDDR = mean daily design rate /Pannual = Annual production
scaled up on constant velocitynot feasible (Mechanical by: σL = pd/4t (σL = longitudinal stress (MPa), p = internal
requirement/ S = scheduled shutdown days/ IF= Integration
limits on shell diameter, maximum tyre size achievable) Oversized equipment is expensive: Leads to over pressure (MPa),d = internal diameter of tube or cylinder (mm),
factor capitalization/ Results in poor performance owing to: t = thickness of wall (mm))
Basic scaling techniques: Constant Velocity Scaling (Maintains Operation at non-optimal rate, Poor utilisation of available
The greater the plant integration the higher the MDDR needs
similar inlet velocities for the small scale and large scale turndown ratio The thicker the wall the lower the stress But increases the
to be for the same annual production
systems, Sometimes maintains the velocity ratios similar, weight and cost of the vessel
rather than the absolute velocities), Constant Residence Time Undersized equipment results in: Failure to reach production
Optimum equipment sizing
Scaling (Maintains the gas or particle residence times in the targets/ Poor efficiency with equipment “pushed to the limit”/ • Allowable working stresses are typically 25% of the yield
MDDR: the production that the overall plant must be capable reactor similar), Constant Reaction Intensity Scaling High maintenance costs stress of the material– Stresses caused by other factors must
of sustaining over a 24 hour periodIdeally all equipment (Maintains the specific concentration of species of the small also be allowed.
Design margins (safety factors): the allowance above and
should be sized to achieve the same production over the 24 scale and large scale systems similar)
beyond the design MCR that is used to allow for factors of Determining shell thickness
hour periodselecting installed capacities for individual items
Each method has its advantages and disadvantagesMust ignorance in the design process It ensures that MCR can be
of equipment based on a shorter timescale Usually known as
achieved despite this design sizing in-exactitude/ Design For material except plate: to = t + c + TA + MA + X (mm)
Maximum Continuous Rating (MCR) choose the appropriate technique for the system being scale
(requires a fundamental understanding of the limiting factors) margins should be minimized to avoid risk of equipment over-
sizing For plate material where design thickness is 5mm or less: t o =
Maximum Continuous Rating (MCR) maximum rate that a Need to assess all the factors and decide the limiting factors 0.94(t + c) + TA + MA + X (mm)
plant item can operate over a continuous period of many 24 (there may be more than one) prior to choosing a scale up
Process and economic risks: Too small a design marginPlant
hour days without overload or severe wear & tear/Applies to techniqueWe can’t scale nature! For plate material where design thickness is greater than
does not achieve required output, Energy consumption is
the equipment when in normal well maintained condition/ 5mm: to = t + c - 0.3 + TA + MA + X (mm)
Rules of “thumb”: Procedure based on experience and excessive, Poor product quality/ Too large a design
Production rate usually falls off as wear sets in and
practice rather than theory (Often enshrined in National marginPlant achieves required output but usually with:
maintenance becomes due. Real plant does not operate in c = corrosion allowance /MA = manufacturing allowance
Standards & company design procedures)/ Shortcuts Excessive energy consumption, Possible poor product quality,
steady-state, normally there are continuous variations around (forming & machining) /TA = under-tolerance allowance (from
compared with rigorous calculation/ Usually based on: Unstable operation, Poor turndown performance, Excessive
MCR (MCRconst>MDDR) material specification) /t = minimum calculated thickness for
Empirical observations, Economic practice, “Common sense” capital cost/Accumulation of design marginsover-sizing of
pressure and applied loads /X = any extra thickness to round
Process excursions Around and above MCR, can occur for Widely used in all branches of engineering sub items of equipment, Is a very bad feature, Inconsistent
up to commercially available material
short periods without harm, large or fast excursions may result Can give good results especially where the new system is very plant capacities lead to many problems with process operation
in process instability & damage, Specification of the overload similar to an existing one (Less reliable where there are Design conditions allow for process excursions – Pressure:
Pressure Vessel Design
capacity can be important for some critical plant items/ significant differences between the systems)/ Limits: Can Typically10% or 0.69 to 1.7 bar (10 to 25 psi) above the
Cannot be prevented (Tolerated excursion limits time and rate provide false confidence especially where big changes are maximum operating pressure, whichever is greater/
Pressure Vessel: vessel intended to contain liquids or gases at
interdependent)/Control systems are used to minimize made (Poor plant performance is then a common problem) elevated pressure, Usually any pressure greater than 200 kPa Temperature: For operating conditions 30oC to 345oC, typically
excessive load excursions (absolute). 25oC above the maximum operating temperature; For
Why use “Rules of Thumb”? Design is results based (Need to operating conditions 0oC to -30oC, typically 25oC below the
Turndown ratio: a minimum throughput below which plant produce a functioning process)/Many conflicts exist in the minimum operating temperature; Margins increase below
Pressure vessels are potentially hazardous, There were many
cannot operate effectively/Typical limits on minimum design process (Design vs. analysis, System vs. component, -30oC and above 345oC/ Vacuum: Typically 100 kPa to full
failures of early boilers, Often with catastrophic results.
throughput: Difficulties in maintaining stable flows, Excessive Inter-relationships vs. rules of thumb: are regarded as vacuum/ Structural integrity requirements Minimum shell
heat loss relative to heat utilized, Poor product caused by poor academically inferior , still indispensable, Some become so Development of Standards thicknesses for structural integrity •6.4 mm (1/4 in) for up to
reactant mixing, Poor product separation, etc. entrenched that they are regarded as laws of nature, Practical 1.07 m (42 in) diameter•8.1 mm (5/16 in) for 1.07–1.52 m to
vs. theoretical, Computer literacy vs. numeracy, Cost vs. ASME VIII: "Standards for Specifications and Construction of (42-60 in) diameter•9.7 mm (3/8 in) over 1.52 m (60 in)
Minimum throughput elegance) Boilers and Other Containing Vessels in Which High Pressure is diameter
– Turndown ratio =
Maximumthroughput Contained”, in Imperial units, Provided guidance on the design
Rules of thumb – Cautionary note: Must be used with care and construction of boilers, used extensively throughout the Other aspects of pressure vessel design: Location of welded
Plant equipment items must be sized to achieve MCR (Do not use indiscriminately, Do a “sanity check”, Do not use world especially in the petroleum and gas industries. joints, Vertical vessel support, Horizontal vessel support,
where better methods are available), National standards, ISO Flanges, Nozzle connections, Jacket vessels
Difficult to size: Reactors, furnaces, burners (kinetic data is not standards, should be used where applicable. Divided in to 3 divisions: Division 1: Rules for Construction of
available, May need to scale from lab tests or existing plant, Pressure Vessels/Division 2: Requirements on materials, AS1210 – 2010 is very comprehensive•Specifies acceptable
Can be complex to size correctly) Standard Design Methods used for repetitive equipment items design, and nondestructive examination/Division 3 materials of construction•Gives calculation methods for
/based on a combination of theory, rules of thumb and Requirements applicable to pressure vessels operating at almost all stressed areas•Specifies: Tubeplate design,
Easy to size: Pumps, pipes, valves, flow-meters, Heat experience /Ensures consistency of decision making / either internal or external pressures generally above 10,000 thicknesses, hole diameter & pitch, fixing to shell, etc,
exchangers, surge vessels, tanks, Fans, dampers (Use standard Predicable performance /Predicable cost /Reduces risk psi. (68 MPa) Acceptable gasket materials, bolts, nuts, etc., Inspection
text book techniques) opening requirements & design
Other scaling methods Process Modelling: Increasingly used Australia’s Standard: Covers: Fired (boilers & pressurised
Plant usually has to be scaled from one or more of the design and scaling technique (Based on representing the furnaces) and unfired vessels/Construction using: Ferrous & Design Constraints & Sustainability
systems: Scale up from lab tests/ Scale up from small scale pertinent features of the full size system in the model, When non-ferrous metals, Non-metallic vessels & metallic vessels
industrial tests/ Scale up from pilot plant/ Scale up existing used by suitably qualified and experienced engineers gives with non-metallic linings Design objectives: Production of final specifications for a
plant to larger capacities reliable prediction of the operation of a full sized plant) /Most system capable of being: •Safely operated and maintained
reliable technique for the when fundamental data is Pressure Vessel Design (Including the avoidance of environmental damage)•Efficiently
Scaling is very difficult because not all the pertinent features unavailable but a usable mathematical or physical model exists managed •Efficiently operated from the point of economic
scale similarly/Relevant scaling parameters have to be chosen Determining shell thickness: Based on the allowable stress in performance
very carefully Note on use of Computers for Design: Computers are a useful, vessel wall for a thin walled (diameter is more than 5 x wall
but not essential, design tool/ Process modelling allows more thickness) cylindrical vessel the hoop stress is given by: σh = Design failures: Often associated with:• Failure to choose the
Rotary kiln producing cement detailed calculations computer packages are only available for pd/2t (σh = hoop stress (MPa),p = internal pressure (MPa), d = best technical concept in the early stages• Poor design
information• Construction in the wrong geographical location• Conceptual or Preliminary Design: Work performed in the first Minimising packaging (A major source of preventable waste Photochemical ozone burden (tonne/y of ethylene equiv.)• To
Poor attention to the right kind of detail during the final stages stage of engineering activities: Develop the basic process, but not so much that product deteriorates in transport and Water: Aquatic acidification added (tonne/y of H+ ions equiv.),
of design and construction, chosen on price rather than Study any (confidential) technology transfer information, storage) Aquatic oxygen demand added (tonne/y of O2 equiv.), Eco-
performance• Failure to anticipate and address potential Preliminary capital & running cost estimates, Consideration of toxicity to aquatic life for metals (tonne/y of Cu equiv.), Other
hazards/ Includes very prolonged commissioning times / Local Conditions, Consideration of Environmental Energy conservation: (Benefits: Fuel resource conservation, eco-toxicity to aquatic life for metals (tonne/y of formaldehyde
Economic failure can result from poor timing/ Failure always Requirements, Describe in a preliminary form on paper (or slows the increase in global warming) Strategies By designing: equiv.), Eutrophication added to aquatic systems (tonne/y of
reduces the owners net worth electronic format), Develop a Block Flow Diagram (BFD), also More inherently efficient processes (Avoid repeated heating phosphate equiv.)• To Land: Total non-hazardous solid waste
consider: Design Capacity, mass and energy balances, Yields, and cooling, Process at lower temperatures (where practical), to land (t/y), Total hazardous solid waste to land (t/y).
Avoidance of failure requires: Qualified and trained Preliminary evaluation of the economics and market, Produce Avoid unnecessary size reduction, Lower pressure drops in
engineering staff with recent relevant experience for their role case to management to proceed pipework and equipment), Replace energy intensive thermal L6. Poorly designed plant • Difficult to operate •
and responsibilities/A system approach to design/An adequate processes with alternative non-thermal, Process integration Inefficient • Difficult to maintain • Downright dangerous
budget to fulfill the engineering requirements/Excellent Basic Engineering: Description of plant & process with basic (Combined heat and power, Use the waste energy from one Good plant layout can minimize the effects of • Fires &
project management layout»  Raw material & product specifications» Process process to provide all or some of the energy for another explosions •Toxic leaks
flowsheets (PFD) with M & E balances » Performance data process), Heat recovery (Recover waste heat from flue gases
Safety: Safety is critically important nowadays: increased sheets» Utility consumption & power requirements» Basic and/or product and waste streams), Operational strategies: Human error and design: Many chemical process systems
awareness of the real costs and trauma of accidentsSociety’s equipment list, motor list & data sheets» Basic control & Maximize stable operation of plant (Plant running at constant are extremely complex • Great scope for human error– In
general condemnation of industrial accidents, Widespread instrumentation scheme» Basic engineering flow sheets (P&ID) rate minimizes energy use, Minimize steam use and hot water the design stage – While the plant is being constructed » i.e.
legislation to regulate industry and prevent accidents and hold and specifications washing, Minimize compressed air use), Minimize waste (it not built to specification (relatively common) – During
management accountable contains process energy), Maintain plant in good condition process operation – During maintenance operations » major
Detailed Engineering: Develop detail drawings and (Minimize steam leaks from valve glands, Maintain lagging and cause of serious accidents  Faulty decisions made in the
What is an accident? Any unwanted event that causes death, specifications for procurement, construction and erection from design & construction stage may remain hidden as latent
insulation in good condition)
injury or damage the Basic Engineering Package. Multi-disciplinary task errors for many years before causing a problem
involving: » Mechanical engineering» Materials handling Raw material conservation: Minimize use of high value raw
Accidents, incidents and dangerous occurrences• For every engineering» Tankage and piping engineering» Civil, structural materials by Reuse and recycle Strategies Waste minimization Causes leading to unsafe conditions – Faults in the design
catastrophic and critical accident there are hundreds of minor & architectural engineering» Electrical in production, Recycling of high value used materials (high process • Can be minimized by the application of HAZOP
incidents•Safety is improved by: Analysing & reducing the studies during the design process – Usually undertaken at
engineering» Instrumentation and control systems engineering value means: Those whose known deposits are small, Those
marginal & negligible incidents, Identifying hazard (condition least twice» preliminary process flow diagram » final
with high embedded energy, Those that would be toxic in the
that could lead to an accident), Analysing dangerous Project Management:•Principle engineering activities: engineering flowsheet (P&ID) – Faults in the construction
environment) (There is no value in recycling some items, the
occurrences (an incident that could have been an accident) Definition of Scope of Project, Definition of Project process • Can be minimized by proper supervision of
cost (financial & environmental) is greater than their value)
Organization, Project Procedure Manual, Co-ordination and contractors – Faults in the operation of the plant• Should
Reuse of used materials (Use combustible waste materials as try and anticipate potential operating errors – Need to
Continuous process: Operates 24 h/day for 7 days/week Control of Project implementation, Progress reporting, substitute fuelReduces fossil fuel use, reduce greenhouse specify suitable protective systems
throughout the year• Only downtime is for maintenance and Problem resolution, Close out Reports, Evaluation of Project gas emissions) » relief valves, safety interlock systems,…• Faults in
maybe catalyst regeneration• Generally the choice were: and feed back to Management• Project Management is a
Large scale production required, Continuous operation is maintenance of the plant– Ensure that the plant is readily
critical task to ensure a successful project• Organization of Effectiveness of recycling: --Metals industry is already a very
technically feasible• Plant availability is a very important maintainable – Provision of suitable manuals for plant
tasks: Project manager is critical to the whole process effective recycler especially, aluminium, steel, lead and management • Faults in the design process – Incorrect valve
factor: Must be high for a successful project, Plant availability copper. However the recycling rate (as % of raw materials
(%) = hours producing x 100/8760 sizing• Faults in the construction – Pipe failure • Duty
Societal pressure to improve: Environmental performance and used) is falling not rising, the increasing complexity of products •Correct material specified – Incorrect material used »
Sustainable performance• Related but not necessarily makes them more difficult to recycle--Quality of most metals
Continuous process are normally chosen where: Single creep failure • Faults in the operation – Operational error –
convergent• What does sustainable mean? Means to industry is degraded during recycling, Especially steel, Lead
product• No severe fouling or controllable fouling• Good Flare stack • Used to burn flammable gases in an emergency
maintain effort for a long period• Plant sustainability and copper are not degraded– Quality of plastics is also or process upset • Purge gas (N 2) flow reduced – To below
catalyst life• Proven process design• Established market•  requires: Minimizing the input of raw materials, Minimizing degraded, Cross linked thermo-set plastics cannot be recycled the safe level – “Flash back” occurred » initiated explosion –
Production rate is above 50 to 100 t/h energy consumption, Maximizing product output. Maintenance • Temporary modification • Human
Measuring Sustainability contributions to breakdown of complex systems • Unsafe
Batch process: Operates intermittently• Generally the choice Difference between sustainability and environmental impact
were: – Small scale production required – A range of products Acts • Management pressures – Resource allocation •
(time and location related)• Environmental impact Environmental & Sustainability Reporting Analyzing failures Failure types - deficiencies in
or product specifications are required– Severe fouling considerations tend to short term and local • Sustainability
occurs– Short catalyst life– New product– Uncertain management/organization Failure tokens - individual
tends to be longer term and more global •Significant Inputs: • Raw materials (excluding water): Total consumption
conditions & unsafe acts
design– Continuous operation is not technically feasible ambiguity: Much environmental degradation reduces long- of each raw material (tonnes/year), Specific consumption of
term sustainability each raw material (kg/kg product) •  Recycled materials
All designs are subject to constraints– External: Imposed by: Plant layout • General principles– Goals of the layout design
utilised (if any): Total consumption of each recycled material process • Determination of the relative location of the
Reality, Society – Internal: Imposed by: Client, Project team Current production is very wasteful: Emphasis is on: • (tonnes/year), Specific consumption of each recycled material individual plant items • Specifications of the distance
Maximising output (At the expense of energy efficiency, (kg/kg product) •  Energy: Total consumption of each fossil fuel between plant items • Assess alternative acceptable layouts
The design process: A series of stages with feedback loops,
Regardless of raw material use)significant proportion may (GJ/year), Specific consumption of all fossil fuel (kJ/kg to obtain the optimum for: – Efficient safe and reliable
Ideally plant construction commences on completion of
be unconverted in the process and wasted• Minimising capital product), Total consumption of bought in electricity operation – Minimum hazard and nuisance » to the public »
design, Increasingly plant construction starts before design is
and labour costs/ Energy & material costs have been (MWh/year), Specific consumption of bought in electricity to the environment – Minimum life cycle cost • General
complete especially civil works.
lowlargely ignored in the quest for higher outputs and lower (kWh/kg product) •  Water: Main’s (town’s) water consumed principles - Context of plant layout • General principles -
Stages in Design & Construction of a Plant: Conceptual or overall costs (GL/year), Specific consumption of main’s (town’s) water Constraints – Topography, geology and climatic •
Preliminary Design– Basic Engineering– Detailed (L/kgproduct), Rain water collected and used (GL/year), Surrounding hills, valleys, rivers, coastal, etc.. –
Waste minimization: In all parts of the supply and consumer Specific rain water consumption (L/kgproduct), Waste water Environmental • Emissions and effect on neighbours, … –
Engineering– Project Management– Construction
cycle Strategies By designing: Maximum yield rather than recycled (GL/year), Waste water recycled (L/kgproduct) Access & service• Roads, pipelines, rail, sea, canal, airstrip,
Management– Plant Completion
maximum throughput• Maximum selectivity in multiple … • Power and water supply • Storm water, sewage and
Fast Track Engineering & Construction: Several stages run reaction processes• Recycling discharge streams to extract Discharges:•To Air: Atmospheric acidification burden (tonne/y effluent handling – Legal requirements • Development
concurrently - risky strategy additional product Operational strategies Minimizing reject of SO2 equiv.), Global warming burden emissions (tonne/y of approval, process licensing, … • General principles - Site
product (Optimizing process stability, Quality assurance CO2 equiv.), Human health burden (tonne/y of benzene standards – Road width – Service corridors – Safety
procedures for early detection of off-specification product) equiv.), Ozone depletion (tonne/y of CFC-11 equiv.), requirements – Clearances • Pipe bridge heights • Vehicle
turning circles & lengths • Crane access – Amenities block considered so far »  determine consequences for impose significant loads on the supporting structure and Design development, contingency and risk •  Estimate
– Building lines (car parking) – Architectural finishes, etc. layout of hazardous block interactions - make notes in must be adequately supported »  pipes carrying hot fluids Check and Approval • Bankable feasibility - Estimating
record sheet »  modify proposed layout if appropriate – and solvent should be kept away from electric cables » Elements – Total Installed Cost (TIC) • Direct cost – Labour
• Site layout • Site location plan - Location is Factors to be considered when analyzing block interactions utility pipes (i.e. steam & compressed air) should run above » Standard work hours » Productivity» Labour costs EBA*
superimposed on a map of the area • Typical plant unit plot • Release of material – Frequency –Quantity – Likely process pipes »  large bore pipes are heavy and should be and contractor indirect costs – Subcontract – Equipment
plan • Plant elevation • Criteria for layout development– consequences » fire / explosion » toxic / asphyxiate » other, located close to the vertical supports »  pipes requiring and bulk materials pricing – Freight – Estimating Factors–
Objective is best performance for life cycle • Effective and e.g. flooding – Fire Zone - Typical Fire zone around leak is continuous falls should be mounted externally on separate Design Development *Enterprise Bargaining Agreement –
economical use of space – Land is expensive – Future 5000 ft2 – Factors to be considered when analyzing block supports Work Breakdown Structure (WBS) – Organisational
developments may be allowed for • Access for safe and interactions • Effects of explosion – Damage to human Breakdown Structure (OBS) – Spares • Commissioning •
convenient maintenance – Insitu or removal to workshop • body / equipment » blast pressure » thrown against solid L7. Capital Cost Estimating • Estimating the cost of a plant Capital • Operating – Escalation – Contingency – Risk
Efficient, reliable and safe operation – Economical material barrier (e.g. ground or structure) » hit / buried by falling – Difficult exercise • Can be very time consuming and hence allowances • Commercial risks • Extraordinary risks –
flows • Access for emergencies – Isolation of dangerous debris » struck by missile (e.g. glass or metal fragment) » expensive • Price and cost information can be difficult to Accuracy – Cash Flow – Tax Categories • Operating – labour
items, leak control, etc. – Fire fighting, evacuation of asphyxiated by combustion products – Types of fire and obtain – Little reliable information in the public domain – – Power costs – Fuel costs – Expendable supplies –
casualties • Criteria for layout development – Remember explosion • Liquid pool fire • Jet fire at point of release • Types of estimate • Proposal • Capital • Operating • Trend • Reagents, etc. – Spares • Trend
the need for construction access! – Equipment should be Ignition of large cloud of dispersed vapour /droplets – – Forecasting the project changes • Potential Trend - Order
grouped and numbered logically • Allow adequate Fireball - produces high thermal radiation hazard • Proposal estimating– Type of estimate prepared when of Magnitude – Sign-off by Client to proceed » Produce a
maintenance access – e.g. end access to heat exchangers BLEVE - Boiling Liquid Expanding Vapour Explosion – bidding for a job • Need to get it right – Price too high - bid scope change (Trend) – Trend - Detail Estimate • Budget
allow tube bundle removal • Provide logical identification – Usually a very destructive fireball & deflagration occurs • is over priced compared with the competition » job is lost change • Design change  Concluding Remarks •
Labels become difficult to read as plant gets older » UCVE - UnConfined Vapour-cloud Explosion – Causes and bidding effort wasted – Price too low – job is under- Estimating is a labour intensive process •  Increased
corrosion » dirt» painting deflagration (pressure wave sub-sonic) • Aerial detonation - priced » job will be won but a loss will be made on the accuracy dramatically increases the hours required •
extreme case of UCVE – Pressure wave supersonic – Fire resulting contract • Proposal estimating requires sufficient Proposal estimates need to be as accurate as possible under
• Stages in plant layout development – Stage 1 Layout - prevention • Consider the frequency and potential size of detail to get it right – Proposal estimating is detailed and the circumstances – Too high a cost – job is lost– Too low a
concept of plant defined • Preliminary design showing flammable releases – Estimate the volume where a expensive • Often done against a tight Tender Schedule – cost job is won but becomes loss making – No prizes for
relative positions of units and buildings – Economic factors flammable mixture may occur – Classify the zone (0, 1 or 2) Key parameters to be costed• People and general expenses second place! •  Capital cost estimates are of three types –
– Safety, environmental and nuisance factors • Stage 2 – Use AS/NZS 2430.3.1:2004 Classification of hazardous • Equipment, installation and commissioning – People Order of magnitude + 30% accuracy – Pre-feasibility study
Layout – Further development of design » comprehensive areas for guidance – Eliminate / minimize ignition sources hours • Project management• Engineering • Construction + 20 to 25% accuracy – Bankable feasibility for funding + 10
environmental and social assessments » development within this area – No burners and fired heaters (easier said management – Expenses • General – printing, computing, to 15% accuracy • Trend estimate– Predicting the tends a
planning approval» capital expenditure approval • Stage 3 than done) –Select appropriate electrical equipment for the communications, etc • Travel • Accommodation & living project will take during execution
Layout – Final details and specifications for construction • zone expenses (daily basis) – Equipment • Cost of fabrication and
Stage 1 Layout and integration with general design ex-works price • Shipping and insurance – Installation • L8. Quality Assurance in the Design Process – What is
• Stage 1 Layout - Main themes – Safety - Isolation of • Area Classification – Zone 0 • Flammable/explosive gas Cost of site labour, crane & equipment hire, workers Quality Assurance (QA)? • System of working that ensures
hazardous plant – Environmental and planning regulations air mixture continuously present or present for long accommodation, etc. •  Cost of sundry installation materials that the design, product, service, … meets the standard
• Effluents - including odours and noise emissions – Utilities periods – Zone 1• Flammable/explosive gas air mixture is •  Cost of engineering supervision – Commissioning • Cost required by the customer/user • It is not the detection of
• Electricity, fuel gas, water supplies – General access and likely to occur in normal operation but only for short of supervision, additional site labour, workers errors by inspection but a system to prevent errors occurring
plant arrangement • Relative positions of units and periods – Zone 2 • Flammable/explosive gas air mixture is accommodation, etc. – Overheads – Expenses– Profit – in the first place – Why do we need Quality Assurance (QA)?
buildings including – Control rooms, workshops and not likely to occur in normal operation - if it occurs it will Contingency • Quality Assurance Procedure – Estimates • Designing and building process plant is a complex process
amenities– Access for emergencies & fire fighting– Product only last for a short time • These classifications can also be should be checked and approved by senior experienced – Design errors introduce safety risks • Two types of fault
and raw material storage • Stage 1 & 2 Safety used for toxic/asphyxiant and odour release occurrences • engineers prior to submission can be introduced by design errors – Revealed faults –
considerations – Identification of the hazard/nuisance Protection of Pressure Vessels – e.g. LPG storage sphere - Latent faults • Revealed faults – Cause an observable event
properties of each individual substance • Occurring Critically important Vessel failure is usually catastrophic • Capital cost estimates – Three types • Order of magnitude with or without associated loss – Remedial action can be
normally in the process • That could occur under upset or and results in great damage and many casualties. Note: + 30% accuracy– Owing to lack of readily available data and taken to rectify these errors – Generally remedial action has
failure conditions – The use of this information in a critical These requirements do not apply to vessels storing liquids at rapidly changing costs these tolerances are difficult to a very high financial cost » cost of plant shutdown » cost of
examination of the layout • Minimizing risk by: atmospheric pressure achieve • Pre-feasibility study + 20 to 25% accuracy – remedial work – Failure to rectify errors that subsequently
– Location of hazardous plant with due consideration of: » Requires budget quotations for this accuracy • Bankable lead to an accident has the highest cost of all – Latent faults
adjacent population » location of control, first aid and • Flammable and explosible dusts – Many carbonaceous and feasibility for funding + 10 to 15% accuracy – Requires » un-revealed, therefore very difficult to detect » a certain
amenity buildings • Critical analysis of layout proposal – metallic dusts are flammable and explosible e.g. • more detailed quotations – Based on:• Historical data • combination of events may result in an accident • All efforts
Procedure for stage 1 & 2 analysis Aluminium, magnesium and iron powder • Cornflour, wheat Factored for inflation & foreign exchange movements – should therefore be directed to minimizing errors and the
dust, sugar and starch • Coal dust – Dust clouds are often Method •  Prepare flowsheet & plant layout •  Size and cost subsequent need for changes – HAZOP & HAZAN »
created in the processing and handling of these substances equipment •  Installation work hours •  Percentage factors techniques used to reveal errors and defects in design at the
• Special precautions need to be taken to prevent: – Ignition for other disciplines including engineering – Owing to lack preliminary design stage • Designing and building process
of dust clouds – Spontaneous ignition of dust piles • of readily available data and rapidly changing costs difficult plant is expensive – Doing it 2 or 3 times is even more
Pipework and Services – Pipework enables material flows to achieve + 30% accuracy • Pre-feasibility study – Detailed expensive! – Every change in the design costs time and
within a unit and between blocks • Piping failures are a and factor estimate • Defining options – to select “go money » the bigger the change the more it costs » the later
significant contribution to loss of containment occurrences forward” option – Method• Flowsheet/Preliminary P&IDs • the change the more it costs – All efforts should therefore
– Piping must be suitably supported and protected • Plant layout with some cross-sections • Equipment sizing be directed to minimizing errors and the subsequent need
Especially from vehicle impact – Piping may be located • and costing • Some quantities which significantly effect the for changes • Late design changes are one of the major
Below ground in trenches • At ground level (grade) • On cost – i.e. piping • Installation work hours for equipment• causes of cost “blow outs” on projects • Cost of
– Check plant layout related to surroundings – Refer to overhead racks – Grade level piping • Cheapest Other disciplines, including engineering, factored • manufacturing and construction errors • Cost of
location plan – Examine layout of plant units – Examine arrangement but limits access to plant areas –  Pipe Bankable feasibility study for funding – Detailed estimate replacement – Engineer on site for 3 weeks sorting good
block plan of unit to make product – Substance analysis normally supported slightly above grade - typically 300 mm undertaken – Method • Agreed scope of work for the bricks from bad » $25,000 – Air freighting replacements
table • Start with a block– Select substance in the block » » to allow access for cleaning and painting » to provide facilities to be constructed • Flow sheets & P&IDs • Layout cost $200,000 • Purpose of QA in design – Minimize the risk
consider in sequence all hazards associated with each clearance for trapping and draining – Must dip down into and cross sections of plant • Electrical single line diagrams • of human error • Three broad mechanisms – Planning
substance and the consequences for layout determination - roofed trench to cross under roadways – Elevated Instrument list• Equipment sizing •  Quantity take off for all errors » caused by intended but inadequate action plans –
make notes in record sheet »  modify proposed layout if walkways required for pedestrian access to plant areas – other construction disciplines •  Installation work hours for Slips » attention failures, calculation errors, omissions, etc. –
appropriate • Select next block – Repeat as above – Then Overhead piping • Commonly used method to support equipment and bulk materials •  Engineering procurement Lapses » memory failures such as forgetting the intention,
consider the effect of individual block hazards on each other pipework – Design is a complex 3-D process »  pipes can and contract management cost •  Estimating Factors – losing one’s place, etc.. • These errors can be present at any
stage of design, construction, operation and dismantling • Computational Fluid dynamic modelling (CFD) •  All variation – Not control of the chemical process • Uses Plant can’t be made perfectly safe because: Toxic and
QA Systems – Quality Assurance systems • Are specified in computer calculations and simulations must be validated to techniques such as – Physical inspections, documentation flammable substances are very useful and needed for modern
national and international standards: – AS/NZS ISO minimize the risk of: – Programming errors– Latent checks, – Statistical methods (for mass production) • Non- lifeRisk is therefore inherent
9001:2000 Quality management systems - requirements • software faults corrupting the result •  Input data and compliance with design or specification is investigated–
Organizations wishing to register their QA systems must: – answers should be checked and approved as for hand Results fed back to improve quality system • Cost of and Plant is subject to failure for many reasons: Design errors»
Have their system audited before they can be registered– calculations – Standards design methods •  Wherever potential cost of non-compliance is an important factor • Maintenance errors» Equipment and materials failures
Subject their systems to regular internal and external audits possible standard design methods should be adopted • Training for competency – It is a requirement of most •Human operators make mistakes: Careless or
These would include: – Description of the function of the safety legislation that work be undertaken by “competent inattentive» Interpret information incorrectly» Take
• QA in design – Four major aspects of QA in the design process or unit operation – Design description – A general persons” • Competence is normally established by inappropriate “short cuts”» Fall asleep» Occasionally wilfully
process • Design control • Document control • Process drawing – Sizing and calculation methodology – A worked appropriate training – An engineering degree is just the disregard correct procedures including by senior management
control • Training – We will look at each of these in turn example – References to source information •  Standard start • Design engineers need further training in topics such
methods must be validated by checking and approval – as: – Company design procedures – QA systems» document Process Safety accidents are of low frequency but often have
• Design control – Method of ensuring that: – Reliable Preparation of engineering drawings • Process flow sheets control » interpreting codes and standards » software usage very severe effects
information – Appropriate decisions • Are an integral part (PFDs) • Process and instrument diagrams (P&IDs) • – The design process includes • Preparation of operating
of the design process – Reliable information sources • Engineering flow sheets – These are the most important manuals • Determining the training requirements for: – Company directors have a duty to consider the full effects of a
National and industry standards •  Standard text and drawings produced for a process plant • Must be prepared Process engineers– Operators & supervisors – Maintenance potential process safety accident Can be catastrophic for
reference books (up to a point) •  Company standards that by competent engineers– P&IDs must be subjected to staff • Recognition of competency – Chartered Engineer & both company and community
have been approved and checked •  A carefully planned and HAZOP and HAZAN studies to minimize the risk of latent Chartered Professional Engineer • Recognition of
defects competency in your field – Chartered Engineer (CEng) » Types of incident: Fire, Flash fire, Vapour cloud explosion,
controlled test – Unreliable information sources • Old
drawings, out of date standards and textbooks • Hearsay, Institution of Chemical Engineers (Engineering Council UK Explosions - chemical reaction runaway, Implosions, Toxic gas
poor computer software, poor testing – Appropriate – Preparation of Plant Layouts • Another critically accredited and recognised throughout Europe, North escape, Toxic fumes from fires, BLEVE or Fireball, Dust
decisions • Decision making process should be controlled so important drawing for a process plant – Has major America and Asia) – Chartered Professional Engineer explosions
that: – Decisions should only made by engineers with the influence on safety » effects the ease or difficulty of (CPEng) » Engineers Australia (limited recognition
containing an incident – Poor plant layout can result in a overseas) – CEng or CPEng is a now legal requirement in Most accidents arise from longstanding problemsneed to:
appropriate level of knowledge and competence – The
greater the consequences of an incorrect decision the minor incident becoming a major disaster » Flixborough - QLD to approve drawings and calculations – Must stay up to IDENTIFY the problems (hazards) and MANAGE the risks
greater the competence required • Most design location of control room • Plant layouts must be prepared date with developments • Requirement of:
by competent engineers – Subject to independent checking – Institution of Chemical Engineers – Engineers Australia Need a SAFETY MANAGEMENT SYSTEM: Planning, Leading,
organisations adopt cascaded decision making – Not the
and approval – Preparation of engineering drawings • and similar organisations • Process known as Continuing Organizing, ControllingThe correct procedures applied by the
case in the former Soviet Union » very centralised decision
making – Basic principles •  Need clearly documented Equipment drawings –  Usually prepared electronically - Professional Development (CPD) – Must plan an on-going right people effectively
design procedures that comply with an approved QA CAD –  Temptation to amend/update the last version » high technical and managerial knowledge advancement program
risk owing to the risk of “creeping design” –  New design by: » Attending courses in a range of related topics » Root cause is always the failure to construct and/or maintain
Standard •  Procedures must include the initial conceptual
should be based on a standard design drawing or Participate in conferences and technical meetings » Focused a safe system
stage •  All design decisions should be made by
appropriately qualified and experienced engineers •  A specification (if one exists) –  All drawings and all private study » Maintaining records showing activities and
amendments should be checked for accuracy by someone benefits Some company names occured more than once: clear inability
system of checks and approvals is required to ensure that
other than the person who did them –  Approved by a to learn from other’s mistakes.
the procedures are followed •  Designs must be traceable to
national, industry or company standards, pilot scale tests, senior engineer who is: » familiar with the equipment and • QA System Auditing – Effectiveness of the QA systems
In the ICI Training Video analysing the Pipa-Alpha accident,
etc.. – Design procedures should cover: • Interpreting the understands the client’s requirements are regularly checked by auditing • Internal audits –
what did Brian Atherton say was the “Bottom Line of Safety” in
client’s requirements •  Standards and specifications • Undertaken monthly by the QA manager » usually
concentrating on a different specific area for each audit » his closing remarks?
Calculations – Hand and computer based •  Process • Document control – Standards, codes and specifications •
non-compliances are investigated » findings are fed back to The sum and quality of our individual contributions to the
simulation and modeling – Physical modelling and It is a requirement of all QA Design Standards that: –  Copies
improve the system • External audits – Undertaken twice management of safety determines whether the colleagues we
computer simulations •  Preparation of engineering of all relevant standards, codes and specifications are
yearly by the Registering Body » Standards Australia, work with live or die.
drawings •  Preparation of equipment specifications and available in the design office –  All copes must be the latest
data sheets – Interpreting the client’s requirements • Can be editions/issue –  Out of date standards must be destroyed • Lloyds of London, etc.. – Serious non-compliance can result
an internal or external client • Requirements may be This is most easily achieved by: –  Maintaining a central in de-registration Pressure Relief and Protective Systems
comprehensively specified or quite vague e.g. – Detailed register of all standards, codes and specifications – We need systems to protect against plant failure that can
specifications such as: » process, mechanical, electrical, Subscribing to on-line or automatic updating services so  Concluding Remarks • QA systems are a formal way of create hazards: Tank or vessel overfilled, Vessel over
control and safety specs – Or a simply stated need for, say: » that the latest version is always available – Client supplied minimizing the risk of mistakes The QA system specifies the pressurized, Thermal runaway of a chemical reaction, Ignition
15% increased plant output» 12% reduced energy information and specifications •  A register of all client process for: • Design control• Document control• Process of an explosible mixture, Flame–out in a boiler or furnace, Leak
consumption » a different product mix, etc. No matter how supplied information and specifications should be control• Training Requires that decisions and calculations of process fluid need “Protective Systems”
the client specifies the requirements, it is essential they maintained •  Each document should be clearly identified are checked by competent engineers. The system is subject
are fully understood by the design team – including: – Date of receipt – Date of issue and document to regular internal and external audits to ensure Protective Systems: Engineered systems to protect plant and
number if appropriate – Title or description of document • compliance. people from the consequences of process failures
Standards and specifications • The starting point for all These documents form the basis of the client’s – Two basic types: Pressure relief systems: Designed to vent
designs should be: – Relevant legislation » Environmental requirements and may be critical in the event of a dispute • Hazard & Risk Analysis in the Process Industries over-pressure to a safe place • Safety interlock systems:
and safety requirements – National Standards e.g.: » Must be recorded and effectively managed – Project Designed to prevent dangerous and/or conflicting actions (Will
Standards Australia (AS), British Standards (BSI), German drawings and specifications • Every drawing should have a Why do we need to study safety? – Many plants process override operators and control system and to drive the process
Standards (DIN, VDI), American (ANSI) – Industry unique number – Design is an iterative process so drawings hazardous materials: Petrochemicals & other flammable into “safe mode”, Safe mode is normally (but not always) an
standards» API, NFPA, AGA, etc.. – Client standards and are regularly amended – Each amendment should be materials• Toxic substances such as chlorine• Explosives and emergency shut-down)/ Originally developed in the 1840s to
specifications– Company standards and specifications It is identified on the drawing »  by number and description in explosible substances– Often in very large assist railway signal operators (Mechanical interlocking
essential that the latest edition/issue is available & used the amendment box »  by number in a triangle adjacent to quantities– Potential for disaster is high: High casualties, prevented the setting up of conflicting train movements,
– Calculations • Hand calculations – Should be checked for the amended item – Project drawings and specifications • A including multiple fatalities• High cost of damage to plant, Ensured signals showed the true positions of switches and
accuracy by someone other than the person who did them – project register of all drawings and specifications should be buildings and environment• Substantial consequential losses turnouts)
Approved by a senior engineer who is: » familiar with the maintained – Should include the following information » – A good understanding of the risks and how to manage them
methodology» familiar with the client’s requirements • title » number » current issue » date of latest issue » is essential Two types of vessels subject to overpressure and prevent
Computer based calculations:– Spread sheet based– Process distribution – Control of the design and construction catastrophic failure: Those designed to operate normally at
simulations, in-house computer programs, etc. – processes • Seeks to determine common causes of quality
elevated pressures (Specific legal requirement to protect these Can be made self closing, Must be light weight to minimize (Maximum back pressure 50 – 60% of set pressure, Pilot systemMust be “fail-safe” or designed for a very low risk of
vessels in most cases – pressure vessel codes, etc) / Those that inertia and allow rapid opening operated relief valve (Back pressure up to 80% of set pressure) failure
operate close to ambient pressure (Most likely require – Bursting discs: Back pressure limitations not applicable–
protection as a consequence of general OH&S legislation - less Sizing Pressure Relief Devices: Vessels are subjected to over- Pressure safety valve inlet (PSV) piping (Pressure drop limited Safety shutdown systems: Almost always electrically based
specific requirements) pressure, 2-phase flow considerably increases the pressure to less than 3% set pressure)– Pressure safety valve outlet (Also known as: Trip systems, Safety Shutdown Systems,
compared with vapour only, Although we are relieving piping (Complex with multiple inputs and multiple Burner Management Systems)• Requirements may be
Typical causes of overpressure: Utility failure (single item or pressure, the magnitude of the flow affects the size and type subheaders.) specified in: Codes of practice, National standards, Law Must
plant wide)• Equipment failure (fans, pumps, of relief valve be “fail-safe” or designed for a very low risk of failure,
compressors)• Blocked exit (operator error, control system Potential pressure rise: Must be calculated using empirical Flare sizing and siting: Two types of flare Generally requires that they are completely separate from the
failure)• Open inlet (gas blow though)• Runaway reaction• rules, or •  Determined from tests: Assistance is provided in • Ground flare: Limited capacity, Smokeless design control system
Exchanger tube rupture• Plant fire• Thermal expansion – If applicable standards • Elevated flare: Can be designed with very high capacities,
unchecked vessel will fail Generally smoky at full load, Generates significant radiant heat Achieving an acceptable risk of failure
Process Information Required for Pressure Relieving System fluxMust be high enough to eliminate burns and heat
Option 1: Fail safe relay logic Based on ensuring any failure of
Consequences of vessel failure: Pressure wave causing further Design: Process flow diagram mass balance• Piping and damage
sensor, switch, relay, valve, power supply, etc leads to plant
damage and /or injuries• Release of potentially flammable instrument diagrams• Plant layout and equipment elevations•
shutdown• Plant cannot re-start without operator
materials (May cause fires and secondary explosions escalating Vessel dimensions and design conditions: Temperature and Basic sizing of elevated flare: Exit velocity based on Pressure
intervention• Used since the 1920s: Require little duplication
the damage and injuries)• Release of potentially toxic pressure• Site paving and drainage layout• Pump and loss (Flame extinction and Nozzle exit velocity must not exceed
provided danger was indicated by loss of electrical signal
materials (May cause deaths, illness and environmental compressor performance curves• Control valve sizing• Pipe 20% of sonic velocity of mixture at max duty)• Flare height
(inherent safe design), Very good safety record, Very few
damage) Pressure vessels must therefore be equipped specifications Based on safe levels of radiant heat flux
danger side failures An equivalent level of safety is still not
with pressure relief systems
Flare height and siting: Rule of thumb achievable by computer based systems!
Causes of Equipment over Pressure: Utility failure(Heating/
Consequences of Failure cooling medium, inst. air, power) Single item or Plant wide Option 2: Computer based systems: Computers cannot be
• Equipment failure (Fans, pumps, compressors, etc.)• Blocked made “fail-safe” so system Safety Integrity Level (SIL) is
Distillation tower flooded with hydrocarbons: Control system exit (Operator error, control system failure) • Open inlet (gas defined• Any electronic semi-conductor failure can be two
failure over-pressurized vessel and caused a geyser-like blow though)• Heat exchanger tube rupture• Plant ways: Open circuit to safe condition–Closed circuit to
hydrocarbon leak, Was not released to a safe place DESIGN fire• Thermal expansion dangerous conditions• Introduction of PLC based for safety
FAULT + inadequate protective system Where: All dimensions are in ft: Qm= vapour flow rate (lb/h)-qf
trip systems has increased the number of danger side failures
Understanding potential scenarios: – Two unrelated abnormal = radiation (Btu/h/ft2) at distance Xf-M = ave. molecular
100 fold• This includes sensors with electronic signal
Hydrocarbons plants have high potential for major conditions are not normally considered– Consequential failure weight of vapour -Assumptions: Flame length = 120 df,
processing• To achieve the required level of safety: All safety
incidents, Processing plants are often integrated, making must be considered– Control valves (Those not under Emissivity = 0.048M0.5
instrument circuits must be duplicated or triplicated, Special
design complex , Significant incidents have resulted in consideration as causing overpressure shall be assumed to safety PLCs dedicated solely to this task must be used,
Flare systems: Blow down drum to collect liquid• Knock out
increasing obligations on plant operators and designers relieve pressure based on the valves in their normal operating Extensive failure analysis must be undertaken and recorded,
drum to remove entrained drops• Water seal: Non return
positions)– Block valves, electric switches or other equipment– Separate relay circuits must be used for safety critical circuits•
valve, Pressure control system• Flare tip with: Igniter/pilot
Pressure Relief Devices Operator intervention A target must be set depending on the danger arising from
system, Steam jets, Windshield
failure to act when requiredThe greater the danger, the
Pressure relief location: Generally located on top of vessel– Quantification of Cause of Overpressure: Use process higher the SIL required
Safety Interlock Systems
Must be stand alone connection– Relief pipework: No isolating simulation for physical property data at relieving conditions–
valves • Use long radius bends• Discharge line pipe pressure Assess effect of loss of heating/cooling – Blocked exit (Use flow Applicable Codes and Standards: Pressure Vessels: AS1210
drop must be suitable for relief device type rates at design, Allow credit for reduced flow at relieving Not all hazards are caused by pressure rise: Overfilling a tank, Australian Standard for unfired pressure vessels, ASME VIII US
conditions, Allow credit for outflow from ‘other’ control Fire risk if flammable• Pump running “dry”: Pump damage or standard for unfired pressure vessel• Relief Valves: AS 1271-
•  Safety Pressure relief valves: where: Self closing action valves)– Open inlet (gas blow through): Assume upstream possible explosion from overheating• Flame out in a furnace If 2003 - Safety valves, other valves, liquid level gauges, and
required and relatively slow pressure relief acceptable vessel at normal operating pressure, Allow normal liquid flows fuel continues to flow inSEVERE EXPLOSION RISK ARISES•  other fittings for boilers and unfired pressure vessels• Bursting
– Two basic types: Direct spring acting for low to medium continue, Allow for additional flow due to bypass– Vessels Cooling water failure on an exothermic reactorRunaway discs: AS 1358-2004 Bursting discs and bursting disc devices -
capacities • Pilot acting for high capacities containing liquids: Allow reduction of relieving rate for good reactionSEVERE EXPLOSION RISK ARISES• Flow failure to a Application, selection and installation• Piping: ASME B31.3 (ref
drainage, Use ‘wetted’ vessel surface area to assess pressure petrochemical fired heater Leads to loss of heat sink, tube 5)• Petrochemical specific standards: Offshore Production
Direct spring acting: Slow opening• Low capacity• Impose rise– Gas filled vessels: Relieving temperature limitations failure and ignition of HydrocarbonLARGE FIRE RESULTS Platforms API RP14C, Refineries API RP520, Gen. Hydrocarbon
significant pressure loss across valve• Normally be used in Processing API RP521• Explosible Dusts: VDI 3673 Pressure
pairs: Parallel arrangement or Second valve set at slightly Liquid and Gas Disposal To protect us from other hazards we use control based release of dust explosions, NFPA 654: Standard for the
higher pressure than first Protective Systems Prevention of Fire and Dust Explosions from the
Relief disposal pipe work system required: All relief valve Manufacturing, Processing, and Handling of Combustible
Pilot acting: For high capacities• Rapid opening• Impose lower discharges are connected to flare header• System must be Safety Interlock Systems: Designed to prevent dangerous Particulate Solids, 2000 Ed
pressure loss across valve• Used in pairs: Parallel arrangement able to cope with maximum flows from all credible and/or conflicting actions
or Second valve set at slightly higher pressure than first valve scenarios• Limited backpressure allowed • Free drainage away Hazard and Operability Studies
from valve• Velocity limitation in pipe work• Liquids must not Mechanical systems: Used in the process industries to prevent
be sent to the flare conflicting operation of hand operated devices: e.g. valves: Nothing is “Perfectly Safe”, All activities involve “risk”,Nothing
Bursting discs used where: Very rapid pressure relief
Uses unique keys to limit valve positions, Designed to ensure is achieved without involving riskBasic rule is that the
required•  Self closing action not necessary Two basic types
Modern relief discharge pipe work system: Attempts to only the correct combination(s) of valve positions is possible benefits should be achieved at an acceptable risk
• Forward acting: Utilises a scored discSuited to steady
pressures • Reverse acting: Utilises a non-scored disc bowed recover liquids and gases for re-useReduce costs and add
Electrical systems: override control room operators and In the real world it is often perceived risk rather than the
against pressureLonger life with fluctuating pressures value
control system and to drive the process into “safe mode” - real risk that governs the decision making process
Allowable back pressure in discharge pipe work system: Designed to protect against equipment failure, e.g. Control
Explosion vents: Rip panels: Always remain open after venting Hazard & Risk Analysis
Back pressure limitations for spring loaded pressure relief sensor failure, Valve failure, Process control computer failure,
• Used where: Low opening pressure needed, Leak proof
devices: Conventional spring loaded (Maximum back pressure Flow failure, Over temperature, Distraction, mistake,
sealing required, Rapid opening essential. Explosion doors:
10% of set pressure), Balanced relief valve (not shown) incapacityMust be completely separate from the control
Hazards should be eliminated wherever possible, if the hazard LESS OF (any relevant physical property than there should be) Hazard Analysis FAR should be used to compare the person or group at
cannot be eliminated The risk must be managed in an Could be: Less flow (flowrate or less total quantity), Lower greatest risk not the average for all employees on the plant,
acceptable wayThe risk requires quantifying pressure, Lower temperature, Lower viscosity, etc. Hazard Analysis: Undertaken when the hazard cannot be for UK chemical industry the target for the person at greatest
eliminated risk is FAR of 0.4
•  Hazard analysis is a method of quantifying risk associated PART OF (composition different from what it should be) Could
with identified hazards, Hazards include risks to: people, be: Change in ratio of components (in mixtures), Component Objectives of hazard analysis: To determine how often a What we really need is a Hazard rate: Given a target FAR of
property, environment missing, etc. particular incident is likely to occur, To determine the likely 0.4 then if the person at greatest risk is killed in every
consequences of the incident, To determine what should be dangerous incident (not typical), Then maximum rate of
Hazard and risk analysis must be part of the Safety MORE THAN (more components present than there should be) done about the risk occurrences for a shift worker is: 0.4 incidents in 108 working
Management System: Must be approached in a methodical Could be: Extra phase present e.g. liquid water in steam, hours or once in 2.5 x 108 hours, i.e. once every 30,000
way: Identify the hazards before quantifying the associated vapour in cooling water, Impurities present e.g. water, acid, A rough rule of thumb is: HOW CAFEFUL? > HOW BIG? x HOW years This translates to 3 x10-5 incidents/year, If the person
risks – Hazard identification: Hazard & operability studies dirt, corrosion products, etc. OFTEN?  We have a duty of care to prevent injuries to at greatest risk escapes in 9 out of 10 incidents then the
(HAZOP) – Risk quantifying: Hazard analysis (HAZAN) Always people and damage to the environment tolerable incident rate can increase to 3 x10-4 incidents/year
do a HAZOP before doing a HAZAN OTHER THAN (what else can happen apart from normal
operation)• Usually applied to the vessels after the lines have Reasonably practicable: Must spend sufficient to make risks Risks to employees - Multiple Casualties
Murphy’s law - Observations attributable to the mythical been studied• Could be: Start-up and shutdown, Low rate acceptable But not so much that the business is threatened •  Which is worse?
Irishman: Sooner or later whatever can go wrong will go wrong operation, Power failure, Catalyst change, Failure of plant (a) 1 person killed every year for 100 years
Things which can’t go wrong will still go wrong services, Maintenance operations, etc Stages of hazard analysis: Estimating how often the incident
(b) 100 people killed in 1 incident every 100 years
will occur/ Estimating the consequences to: Employees, The
A difficult dilemma because
HAZOP Additional guide words to the operating instructions: DON’T public, The Environment, Plant and profits
–  (b) will cause more trauma and disruption to the community
CHARGE “A”/ CHARGE MORE “A”/CHARGE LESS “A”/CHARGE but may never happen
Purpose: Identify all foreseeable risk situations associated with “B” AS WELL AS “A”/CHARGE PART OF “A” (if “A” is a mixture)/ Best hazard analysis: Quantitative risk analysis• Uses statistical
data: Based on plant and equipment failures, Based on actual –  (a) will almost certainly happen and cause many deaths
a process, Ensure all reasonably practical steps have been REVERSE CHARGE “A” (i.e. reactants flow back to tank)/
injuries and fatalities in typical events• Combined with fault •  If the plant lasts 25 years:
taken to, eliminate or minimise the risk CHARGE OTHER THAN “A”/“A” is ADDED TOO EARLY/“A” is
tree analysis • To determine how often an event will occur –  The chance is that (b) will happen is 1 in 4 but (a) will almost
ADDED LATE /“A” is ADDED TOO QUICKLY /“A” is ADDED TOO certainly result in 25 deaths
Legal terms frequently encountered in the British and SLOWLY
Australian legislation Targets or Criteria: The simple risk analysis shows us where to •  If we give priority to (b) then we take resources away
HAZOP Studies - Computer controlled plant: Computers are target our efforts but does not tell us anything quantitative  from (a)
So far as is practicable: Must be complied with Regardless of Makes it difficult to know when we comply with the So far as is –  In the meantime (a) will certainly result in many deaths yet
fallible, Instructions (program) should also be studied
cost and Within the light of current knowledge (all sources of (Determine the consequences of the computer failing to take reasonably practicable criteria We need measurable criteria: we
knowledge not just yours or the company’s - if it is published Relatively easy for economic loss but very difficult where injury have applied the resources to something that may never
action and Provide hard wired fail-safe safety interlocks where
somewhere, no matter how obscure, then it is “ current or potential death is concerned happen
appropriate), Computer systems can never be totally fail-safe
knowledge”) •  There have been many attempts to quantify the
No matter what the safe guards that are added in
Economic loss: hazard that is likely to result in an accident tolerable hazard rate for (b) but these have been
So far as is reasonably practicable: Must be complied with HAZOP Hints: Don’t get carried away and install expensive once in 1000 years, Cause plant damage of $1 million, Not somewhat arbitrary
until the cost of additional control measures become equipment to guard against possible but unlikely hazards –  likely to result in any serious injuries it is worth spending •  Probably the only equitable way is to give equal
disproportionate to the reduction in risksThis measure of Cannot spend our way out of every problem– Actions should $1000/year to prevent this accident but no more/If lost priority to (a) & (b) - we’re just as dead in either case
cost seems to vary according to who is paying be changes in equipment or proceduresMain effort should production is important then the value increases (if the
be on prevention additional production loss is $100 million then it is worth Risks to the public: We accept greater voluntary risks than
HAZOP: Systematic method of identification and assessment spending $101,000) imposed risks, for risk to the public, 1 x 10-7 is commonly
Modifications: HAZOP should always be undertaken on considered tolerable •  Difficult to explain: Easy to understand
Undertaken by a small team: The plant is examined process Injuries and fatalities: The target is often set intuitively e.g.
proposed modifications, Many accidents have occurred as a the high number of casualties but Difficult to understand the
line by process line handrails, No formal hazard analysis, The height of handrails is
consequence of the unforeseen effects of modifications•  If a very low frequency of such events
HAZOP is not study undertaken then the attached check list largely accepted as adequate by the general populationWe
Using a series of guide words: NONE, PART OF, MORE OF, find the small risk of falling acceptable despite the fact that a
MORE THAN (or AS WELL AS), LESS OF, OTHER THAN should be used Quantitative Hazard & Risk Analysis
fall is likely to be fatal• Tolerable risk is preferred over HAZARD (OR INCIDENT) RATE (H): The rate (occasion/year) at
All modifications should be examined: Temporary as well as acceptable risk • UK Approach: An upper level of fatalities that which hazards occur
permanent ones• Commissioning as well as those on must never be exceeded no matter what the cost, A lower, PROTECTIVE SYSTEM: Device installed to prevent a hazard
established plant• Cheap as well as expensive modifications negligible level, that there is no need to get below• In occurring
• Modifications to procedures between these limits (ALARP region): Accidents should be TEST INTERVAL (T): Protective systems require regular testing
reduced if reasonably practical Use cost/benefit analysis to to ensure that they are still functional, The time between tests
HAZOP Teams determine whether further reduction is reasonably practicable is the test interval T
DEMAND RATE (D): The rate (occasion/year) at which a
New plant: Project or design engineer (Usually a mechanical We can use ALARP to: Resolve design choices e.g between
protective system is called upon to act
engineer) –  Process engineer (Usually a chemical engineer)–  relief valves and trips, Decide how much redundancy should be
FAILURE RATE (f): The rate (occasion/year) at which a
Commissioning manager–  Instrument design engineer (HAZOP built in to a protective system
protective system develops faults
usually adds instruments and trips) – Independent Chairperson
Not always necessary to consider numerical targets: New FRACTIONAL DEAD TIME (fdt): The time for which a protective
NONE Related to flow this could mean; no flow, no forward (Ensures team follows procedure - should be familiar with
design should NEVER be less safe than the old design system is inactive i.e. the non-availability fdt = 1 - availability
flow or possibly reverse flow HAZOP not an expert in the process being studied)
•  If a protective system always operates when demanded
MORE OF (any relevant physical property than there should Existing plant: Plant Manger (Responsible for plant Fatal accident rate (FAR): Risks to employees: Number of fatal then the hazard rate: H = 0
be) Could be: More flow (flowrate or more total quantity), operation)– Process foreman (Knows what actually happens accidents per 1000 workers in a working lifetime (108 hours) •  If a protective system never operates when demanded then
More pressure, More temperature, More viscosity, etc. rather than what should happen)– Plant engineer (Responsible the hazard rate: H = D
for maintenance) – Instrument manger (Responsible for Chemical Industry FAR 4.25 made up from: Ordinary risks (2)  H= D x fdt = D.fT/2 (based on failure 1/2 way through
instrument maintenance; including testing of alarms and and Chemical risks (2.25)priority should target to areas of the test period T)
interlocks) – Independent Chairperson chemical industry where the FAR is >2
Testing and fractional dead times: Failure not obvious until Limitations of hazard and risk analysis: Most major accidents
demand occursMust be tested regularly and put back into are caused by management systems failure not isolated
service, On average failure occurs midway between tests fdt equipment failures, Risk analysis only considers “How often?”
= fT/2 This is a major limitation for low frequency, high impact
events, Boards of directors have a legal responsibility to
Need failure data to choose appropriate test intervals consider and act on all ways of either eliminating the risk or
The less reliable the component the more often it needs testing minimizing the impact.

Fractional dead times - relief valves Legal responsibilities: Defined under “Common Law” (law of
Failure to operate within 20% of set pressure occurs judicial precedent, does not recognize the concept of low risk
once in 100 yearsfailure frequency is 1/100 = 0.01 if the consequences are severe and that risk is avoidable),
Test once/year i.e. T = 1, Typically failure occurs midway Criticality: Establish critical hazards, Preventability: Identify
between teststhe valve is dead for 6 months or 1/2 T and enact all practical precautions for each critical hazards,
Therefore fdt = 0.5 x 1 x 0.01 = 0.005 of a year Reasonableness: Determine which of the practical precautions
are reasonable, Implementation Of reasonably practical
Hazard frequencies: Take a plant with a demand of 1 per year solutions, On-going monitoring and review
A hazard occurs when a demand arises during a dead time
H = D x fdt

Multiple Protective systems


– Two systems in parallel: fdt = 4/3*FA*FBhazard rate: H =
4/3*D*FA*FB
–Two systems in series: fdt=FA+FB hazard rate: H=D (FA+FB)

Fault trees: Widely used in hazard analysis to determine the


series of events that will lead to creation of a hazard: For AND
Gates we multiply the probabilities, For OR Gates we add the
probabilities
The hazard frequency (vessel over pressurized) once a year is
unacceptable so we use a protective system Dramatically
reduces the frequency of the hazardous occurrence

Pitfalls in hazard analysis: Data may be inapplicable, Designs


change, Using impossibly low fractional dead times, Common
mode failures in parallel systems

Hazard analysis - Methodology


– Common mode failures: Should be minimized by good
design
– Example: pressure in a fire main is maintained by a pump
that switches on whenever the pressure drops below 600kPa
–  A pressure switch is used to do thisdemand rate is
10/yearpressure switch has a failure rate of
0.8/yeartested 10 times a yearThe hazard is the pump
failing to start: H = D x 0.5fT=10 x 0.5 x 0.8 x 0.1 = 0.4/y or once
in 2.5 yearstoo high, therefore install a second pressure
switchFailure rate only fell to once in 4 yearstoo
highinstall a third pressure switch Or remove the common
mode failureFailure rate fell to once in 77 years
–  Greater fall than predicted by: H = D x 0.5fT

– Eliminating common mode failures

Don’t rely on just one technique: Always use HAZOP to look


for potential hazards, Consider all reasonable means of risk
elimination and reduction - not just protective systems • Do
not rely on “Nothing has gone wrong in the past - it must be
safe” syndrome.• Don’t assume that because a proposal
completely satisfies current rules that it must be safe,
Especially with new technology• Remember that fault tree
analysis may provided part of the answer but it will never
provide all the answer• Think about inherently safe design

You might also like