Tasks All

Data
Year Quarter Week Day Cost Cumulative Cost
2011 Q4 Week 45 11 80224703.58 80224703.58056
12 0 80224703.58056
Week 45 Total 80224703.58 80224703.58056
Week 46 13 0 80224703.58056
14 60387539.25 140612242.8278
15 74783057.75 215395300.575
16 87985999.75 303381300.3222
17 123124213.3 426505513.6111
18 72484138.47 498989652.0833
19 0 498989652.0833
Week 46 Total 418764948.5 498989652.0833
Week 47 20 0 498989652.0833
21 43014784.97 542004437.0556
22 45314299.05 587318736.1028
23 30402650.15 617721386.25
24 22137824.15 639859210.3972
25 23030734.23 662889944.6278
26 0 662889944.6278
Week 47 Total 163900292.5 662889944.6278
Week 48 27 0 662889944.6278
28 23806201.73 686696146.3583
29 23742181.73 710438328.0889
30 16190125.63 726628453.7194
1 27255041.63 753883495.35
2 24125662.59 778009157.9389
3 0 778009157.9389
Week 48 Total 115119213.3 778009157.9389
Week 49 4 0 778009157.9389
5 14139857.7 792149015.6389
6 40433566.62 832582582.2556
7 5260677.728 837843259.9833
8 8200997.028 846044257.0111
9 8232997.028 854277254.0389
10 0 854277254.0389
Week 49 Total 76268096.1 854277254.0389
Week 50 11 0 854277254.0389
12 10402963.94 864680217.9758
13 12749147.4 877429365.3793
14 10949147.4 888378512.7828
15 10089813.8 898468326.5864
16 9714702.692 908183029.2788
17 0 908183029.2788
Week 50 Total 53905775.24 908183029.2788
Week 51 18 0 908183029.2788
19 5591310.192 913774339.4712
20 5591310.192 919365649.6636
21 5591310.192 924956959.8561
22 14714874.49 939671834.3485
23 14714874.49 954386708.8409
24 0 954386708.8409
Week 51 Total 46203679.56 954386708.8409
Week 52 25 0 954386708.8409
26 14586874.49 968973583.3333
27 18991011.08 987964594.4167
28 28373193.58 1016337788
29 8568283.5 1024906071.5
30 8500139.75 1033406211.25
31 0 1033406211.25
Week 52 Total 79019502.41 1033406211.25
Q4 Total 1033406211 1033406211.25
2011 Total 1033406211 1033406211.25
2012 Q1 540378850.8 1573785062
2012 Total 540378850.8 1573785062
Grand Total 1573785062 1573785062