You are on page 1of 1

CUSTOMER : Premier Oil Natuna Sea B.

V
PO / APPROVE No. : 034/EWP/SPH/III-2019
PROJECT : Provision of HVAC Maintenance Services
UNIT : Condenser Coil – HVAC Swichgear Anoa Platform
TEST LOCATION : WORKSHOP PT. ESKIMO WIERAPERDANA

LEAKS TEST REPORT

Test Method : Dry Test Immersion Test Standing Pressure

Design Working Pressure (Max.) : …………………………………………Psig *Refrigerant Type - …….


Leaks test Pressure (Max.) : …………………………………………Psig
Testing Time Period : ………………………………………….Hours

Dry Gas Pressure (Psig)


NO Equipment Standing Pressure Testing Time
Pressure Test Dropped
………….Psig ………….. *Days/Hours
1. Condenser Coil – Unit A ………
………….Psig …...…….. *Days/Hours
………….Psig ….…..….. *Days/Hours
2. Condenser Coil – Unit B ………
………….Psig ….…..….. *Days/Hours

Note:

Tangerang, ……….. November 2019


Prepared by. Approved by
PT. Eskimo Wieraperdana Premier Oil Natuna Sea B.V

(…………………………………….) (…………………………………….)