Item Description WHO Concern/Status Design/Plan Days Start End


Zone1B

1 Excavation of End Column PCC On Going 7 20-Mar-19 27-Mar-19


2 Concreting and Curing PCC 14 days curing period 14 28-Mar-19 11-Apr-19
3 Column Erection PCC 7 12-Apr-19 19-Apr-19
4 Roofing Installation of Zone 1B CSC Awarding of 14 20-Apr-19
Contractor 04-May-19
Awarding of
5 Earth Cutting WE/TJBC Cutting Plan 3 20-Apr-19 23-Apr-19
Contractor
6 Deisel Tank relocation TJBC/CSC Relocation Plan 7 24-Apr-19 01-May-19
7 Canal Construction at Zone 1B PCC/TJBC Plan 14 24-Apr-19 08-May-19
8 Rain Water Collector Pipe CSC ATAD gutter; 2 05-May-19
CSC Downspout 07-May-19
9 Crane Rail Installation CSC Meeting with installer 7 05-May-19 12-May-19
10 Electrical works - Power & light CSC Electrical Plan 10 05-May-19 15-May-19
11 Roof Siding Installation 14 08-May-19 22-May-19
12 Overhead Crane Installation CSC/MHE Meeting with installer 3 13-May-19 16-May-19