Project Title : Proposed Two Storey Residential Building

Owner : Mr. & Mrs. Rellones


Location : Manga St. Quezon City
Prepared by : BDT
Revision No. : 0
Date of Estimate : Wednesday, October 31, 2018
Project Title: Proposed Two Storey Residential Building Date: 10/31/2018
Location: Manga St. Quezon City Prepared By: BDT
Owner: Mr. & Mrs. Rellones Rev. No. 0

BDT CONSTRUCTION ESTIMATE


(Masonry Works)
2
Wastage Profit OCM VAT
0% 0% 0% 0%

Labor Cost Mobilization Demobilization


35% Php 5,000.00 Php 5,000.00

Materials Price List


Materials Qty Unit Unit Cost
Portland Cement (40 kg) 1 bags Php 244.00
Sand 1 cu.m Php 900.00
Interior CHB Wall
4" (100mm) CHB 1 pc Php 8.00
Exterior CHB Wall
4" (100mm) CHB 1 pc Php 8.00
10mm φ RSB 1 pc Php 118.00
12mm φ RSB 1 pc Php 118.00
GA 16 Tie Wire 1 Kg Php -
xxx Php -
xxx Php -
xxx Php -

Equipment Rental
No. Qty Unit Unit Cost
1 Bagger concrete mixer 0 1 unit Php 500.00
Scaffolding (H-Frame) 0 1 unit Php 800.00
xxx 0 0 sets Php -
xxx 0 0 unit Php -
xxx 0 0 unit Php -

CHB WALL

Interior Wall

Wall Length (Wl) 2.00 meters

Wall Height (Wh) 2.00 meters

Mixture Class

CHB size
Project Title: Proposed Two Storey Residential Building Date: 10/31/2018
Location: Manga St. Quezon City Prepared By: BDT
Owner: Mr. & Mrs. Rellones Rev. No. 0

CHB Capacity

Deducted Area 2
Schedule of Door No. of Units Schedule of Window No. of Units
Door 1 = 1.89 m² 1 W1= 1.44 m² 1
Door 2 = m² W2= m²
Door 3 = m² W3= m²
Door 4= m² W 4= m²

Plastering
Thickness of Plastering (mm)
Mixture Class
No. of sides 2

Exterior Wall

Wall Length (Wl) 2.00 meters

Wall Height (Wh) 2.00 meters

Mixture Class

Size of CHB

CHB Capacity

Deducted Area
Schedule of Door No. of Units Schedule of Window No. of Units
Door 1 = 1.89 m² 1 W1= 1.44 m² 1
Door 2 = m² W2= m²
Door 3 = m² W3= m²
Door 4= m² W 4= m²

Plastering
Thickness of Plastering (mm)
Mixture Class
No. of sides 2
Project Title: Proposed Two Storey Residential Building Date: 10/31/2018
Location: Manga St. Quezon City Prepared By: JDT
Owner: Mr. & Mrs. Rellones Rev. No. 0

engr_bdt@yahoo.com 0936-922-1238

BDT CONSTRUCTION ESTIMATE


(Masonry Works)

Bill Of Materials
Item No. Description No. Qty Unit Unit Cost Total
1.0 Materials:
Interior Wall
1.a Portland Cement (40 kg) 1.00 bags 244.00 244.00
1.b Sand 0.11 cu.m 900.00 100.22
1.c 4 inches (100mm) Non Load Bearing CHB 9 pcs 8.00 72.00
Exterior Wall
1.d Portland Cement (40 kg) 1.00 bags 244.00 244.00
1.e Sand 0.11 cu.m 900.00 100.22
1.f 4 inches (100mm) CHB Non Load Bearing 9 pcs 8.00 72.00
Sub-Total (1) 832.44
2.0 Equipment:
2.a 1 Bagger concrete mixer 0 1 unit 500.00 -
2.b Scaffolding (H-Frame) 0 1 unit 800.00 -
2.c xxx 0 0 sets - -
2.d xxx 0 0 unit - -
2.e xxx 0 0 unit - -
Sub-Total (2) -

Material Cost: 832.44


Equipment Cost: -
Labor Cost: 291.35
Mob/Demob 10,000.00
Total Direct Cost: 11,123.79

Profit -
OCM -
VAT -
Total Indirect Cost: -

Grand Total: PHP 11,123.79