Apr '20 May '20 Jun '20 Jul '20 Aug '20 Sep '2
Mode 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 1
0 Software 95.75 days Mon Mon
Development 30/03/20 10/08/20
1 Scope 3.5 days Mon 30/03/20Thu 2/04/20
7 Analysis/Software 14 days Thu 2/04/20 Wed
Requirements 22/04/20
17 Design 14.5 days Wed 22/04/20Tue 12/05/20
25 Development 21.75 days Wed 13/05/20Thu 11/06/20
32 Testing 48.75 days Wed 13/05/20Mon 20/07/20
48 Training 45.75 days Wed 13/05/20Wed 15/07/20
57 Documentation 30.5 days Wed 13/05/20Wed 24/06/20
67 Pilot 70.25 days Wed 22/04/20Wed 29/07/20
68 Identify test group
1 day Wed 22/04/20Thu 23/04/20 Project Manager
69 Develop 1 day Thu Fri 24/04/20
software 23/04/20
delivery
70 mechanism
Install/deploy 1 day Mon Tue Deployment Team
software 20/07/20 21/07/20
71 Obtain user 1 wk Tue Tue Deployment Team
feedback 21/07/20 28/07/20
72 Evaluate testing 1 day Tue Wed Deployment Team
information 28/07/20 29/07/20
73 Pilot complete 0 days Wed 29/07/20Wed 29/07/20 29/07
74 Deployment 5 days Wed 29/07/20Wed 5/08/20
81 Post 3 days Wed Mon
Implementation 5/08/20 10/08/20
Review
Task Inactive Summary External Tasks
Page 1
ID Task Task Name Duration Start Finish Mar '20 Apr '20 May '20 Jun '20 Jul '20 Aug '20 Sep '2
Mode 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 6 1
86 Software 0 days Mon Mon 10/08
development 10/08/20 10/08/20
template
complete
Page 2