frequency converter #1
TV Voltage [kV] Value #1
TA Current [A] Value #1
Motor for fan
Heater for motor
Incoming feeder from UPS + Eneble
Emergency Level 0
Dust transport system ---- PAKAGE (with all cables in the scope of supply of the COMMISSIONING cabling supplier)!!!! ----
Emergency Level 0 on new MCC
MCC 415 Volt Enable on new MCC
MCC 110 Volt Enable on new MCC
MCC 24dc Volt Enable on new MCC
Total amount of digital INPUT
Total amount of digital OUTPUT
Total amount of Analog INPUT
Total amount of Analog OUTPUT
Damper actuators
rotary valve
wire heating system for hopper and dust silo
Piston valves
Pressure switch for each compressed air manifold
Limit switch for each pneumatic damper
Dust level sensor for each hopper (high – low level)
Differential pressure transmitter for each bag house compartment
filter inlets pressure transmitters
filter outlets pressure transmitters
filter inlets temperature transmitters
filter outlets temperature transmitters
Tribo bag broken detector for each compartment
Manual slide gate at outlet flange of each hopper switch
rotary valve for dust discharge after manual slide gate at each hopper outlet.
Damper motor position (2 each)
Damper motor torque (2 each)
Proxy rotation control
Hi NOTE:
In your calculation ADD ( and spleet!) 20% more of input and output, to the total amount above, at this stage...
Take care to the input output cards requested as minimum from DARFUR/JSW specification on each remote I/O
Equipment Code
7nos
1nos
1nos
7nos
1nos
8Nos.
1No.
2No.
2No.
1No.
2Nos.
3Nos.
1No.
8Nos.
1No.
1No.
3No.
3Nos.
2Nos.
1No.
Dust transport system ---- PAKAGE (with all cables in the scope of supply of the CO
Designation
Emergency Level 0
ystem ---- PAKAGE (with all cables in the scope of supply of the COMMISSIONING c
Emergency Level 0 on new MCC
MCC 415 Volt Enable on new MCC
MCC 110 Volt Enable on new MCC
MCC 24dc Volt Enable on new MCC
Summary of input and output form Pneumatic Conveying system for Dust on dated on 13-02-2019
Total amount of digital INPUT
Total amount of digital OUTPUT
Total amount of Analog INPUT
Total amount of Analog OUTPUT
Piston valves
Pressure switch for each compressed air manifold
Limit switch for each pneumatic damper
Dust level sensor for each hopper (high – low level)
Differential pressure transmitter for each bag house compartment
Damper value inlet and outlet filter room
TS with indication for heating hooper
limit switch open /close slide get
opacity meter
filter inlets pressure transmitters
filter outlets pressure transmitters
filter inlets temperature transmitters
filter outlets temperature transmitters
Tribo bag broken detector for each compartment
Manual slide gate at outlet flange of each hopper switch
JSW interface
Hi NOTE:
In your calculation ADD ( and spleet!) 20% more of input and output, to the total amount abov
Take care to the input output cards requested as minimum from DARFUR/JSW specification on
Mian Panel
30% spare
Total
Total
30% spare
totsl after spare
MOTOR & SENSOR LIST
BASIC ENGINEERING
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
30 20 8 8
Profibus DP
6,6 KV 3150
Profibus DP
Profibus DP
6,6 KV 3150
240 V 1400 VA
1 1 24 DC
Profibus DP
6,6 KV 3150
Profibus DP
Profibus DP
6,6 KV 3150
240 V 1400 VA
1 1 24 DC
Profibus DP
6,6 KV 3150
Profibus DP
Profibus DP
6,6 KV 3150
240 V 1400 VA
1 1 24 DC
3 24 DC
24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
5 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
5 24 DC
1 24 DC
1 24 DC
35 7
5 1
5 1
35 7
5 1
16
5 1
7 3
7 3
7 3
8 2
21 9 3
5 2
16
7 3
7 3
5 2
21 9 3
14 6
5 2
5 2
5 2
5 2
30 26 8
12
1 24 DC
1 24 DC
1 24 DC
1 1 24 DC
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
15 12 4
2
1 24 DC
1 24 DC
1 24 DC
1 1 24 DC
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
10 8 4
2
24 DC
24 70 lamps
10 8
8 8
ier)!!!! ----
2 24 DC
2 24 DC
2 24 DC
2 24 DC
107 24 DC
90 24 DC
2 24 DC
0 24 DC
3 24 DC
2 24 DC
2 24 DC
2 24 DC
2 24 DC
2 24 DC
2 24 DC
36 36
1 24 DC
2 24 DC
14 24 DC
14 24 DC
14 24 DC
14 24 DC
14 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
Profinet
1 24 DC
1 1 24 DC
1 24 DC
1 24 DC
2 24 DC
1 24 DC
670 329 57 14
Profinet
2 24 DC Wired
2 24 DC
2 24 DC
2 24 DC
2 1 3x415 2
2 1 3x415 2
2 1 3x415 2
2 1 3x415 2
2 1 3x415 2
24 DC Wired 0.2
4 24 DC
6 24 DC
4 24 DC
6 24 DC
6
7
4 24 DC
6 24 DC
4 24 DC
6 24 DC
6
6
4 24 DC
6 24 DC
4 24 DC
6 24 DC
6
6
312 24 DC 24 DC
40 24 DC 24 DC
96 24 DC 24 DC
40 24 DC 24 DC
14 24 DC 24 DC
48
18
32
2
2 24 DC
2 24 DC
2 24 DC
2 24 DC
13 12 24 DC
36 24 DC 24 DC
2 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
2 24 DC
1 24 DC
2 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
2 24 DC
1 24 DC
2 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
2 24 DC
1 24 DC
351 374 96 0
1 24 DC
1 24 DC
1 24 DC
1 1 24 DC
1 24 DC
1 24 DC
1
1
1 24 DC
1 24 DC
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
15 12 4
2
15 10 6 4
15 10 6 4
71 32 21 8
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
36
Power cable
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
15/08/18 1st ISSUE
Remarks
JSW Switchgear
FROM UPS
FROM UPS
FROM UPS
NewMCC
NewMCC
NewMCC
NewMCC
NewMCC
NewMCC
FROM UPS
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW
NewMCC
NewMCC
NewMCC
FROM UPS
NewMCC
NewMCC
NewMCC
FROM UPS
4 Zone
8 Elements
8 Elements
Existing
Existing
Existing
FROM UPS
NewMCC
NewMCC
NewMCC
NewMCC
FROM UPS
Equipment Code
7nos
1nos
1nos
7nos
1nos
8Nos.
1No.
2No.
2No.
1No.
2Nos.
3Nos.
1No.
8Nos.
1No.
1No.
3No.
3Nos.
2Nos.
1No.
Dust transport system ---- PAKAGE (with all cables in the scope of supply of the COM
Designation
Emergency Level 0
ystem ---- PAKAGE (with all cables in the scope of supply of the COMMISSIONING cab
Emergency Level 0 on new MCC
MCC 415 Volt Enable on new MCC
MCC 110 Volt Enable on new MCC
MCC 24dc Volt Enable on new MCC
Summary of input and output form Pneumatic Conveying system for Dust on dated on 13-02-2019
Total amount of digital INPUT
Total amount of digital OUTPUT
Total amount of Analog INPUT
Total amount of Analog OUTPUT
Piston valves
Pressure switch for each compressed air manifold
Limit switch for each pneumatic damper
Dust level sensor for each hopper (high – low level)
Differential pressure transmitter for each bag house compartment
Damper value inlet and outlet filter room
TS with indication for heating hooper
limit switch open /close slide get
opacity meter
filter inlets pressure transmitters
filter outlets pressure transmitters
filter inlets temperature transmitters
filter outlets temperature transmitters
Tribo bag broken detector for each compartment
Manual slide gate at outlet flange of each hopper switch
JSW interface
Hi NOTE:
In your calculation ADD ( and spleet!) 20% more of input and output, to the total amount above,
Take care to the input output cards requested as minimum from DARFUR/JSW specification on ea
Mian Panel
30% spare
Total
Total
30% spare
totsl after spare
MOTOR & SENSOR LIST
BASIC ENGINEERING
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
0 0 0 0
Profibus DP
6,6 KV 3150
Profibus DP
Profibus DP
6,6 KV 3150
240 V 1400 VA
1 1 24 DC
Profibus DP
6,6 KV 3150
Profibus DP
Profibus DP
6,6 KV 3150
240 V 1400 VA
1 1 24 DC
Profibus DP
6,6 KV 3150
Profibus DP
Profibus DP
6,6 KV 3150
240 V 1400 VA
1 1 24 DC
3 24 DC
24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
5 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
5 24 DC
1 24 DC
1 24 DC
35 7
5 1
5 1
35 7
5 1
16
5 1
7 3
7 3
7 3
8 2
21 9 3
5 2
16
7 3
7 3
5 2
21 9 3
14 6
5 2
5 2
5 2
5 2
10 10 5
12
1 24 DC
1 24 DC
1 24 DC
1 1 24 DC
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
10 10 4
2
1 24 DC
1 24 DC
1 24 DC
1 1 24 DC
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
10 8 4
2
24 DC
24 70 lamps
10 8
8 8
ier)!!!! ----
2 24 DC
2 24 DC
2 24 DC
2 24 DC
107 24 DC
90 24 DC
2 24 DC
0 24 DC
3 24 DC
2 24 DC
2 24 DC
2 24 DC
2 24 DC
2 24 DC
2 24 DC
36 36
1 24 DC
2 24 DC
14 24 DC
14 24 DC
14 24 DC
14 24 DC
14 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
Profinet
1 24 DC
1 1 24 DC
1 24 DC
1 24 DC
2 24 DC
1 24 DC
615 291 46 6
Profinet
2 24 DC Wired
2 24 DC
2 24 DC
2 24 DC
2 1 3x415 2
2 1 3x415 2
2 1 3x415 2
2 1 3x415 2
2 1 3x415 2
24 DC Wired 0.2
4 24 DC
6 24 DC
4 24 DC
6 24 DC
6
7
4 24 DC
6 24 DC
4 24 DC
6 24 DC
6
6
4 24 DC
6 24 DC
4 24 DC
6 24 DC
6
6
312 24 DC
40 24 DC
96 24 DC
40 24 DC
14 24 DC
48
18
32
2
2 24 DC
2 24 DC
2 24 DC
2 24 DC
13 12 24 DC
36 24 DC
2 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
2 24 DC
1 24 DC
2 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
2 24 DC
1 24 DC
2 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
1 24 DC
2 24 DC
1 24 DC
351 374 96 0
1 24 DC
1 24 DC
1 24 DC
1 1 24 DC
1 24 DC
1 24 DC
1
1
1 24 DC
1 24 DC
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
10 8 4
2
15 10 6 4
15 10 6 4
66 28 21 8
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Power cable
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
Wired
15/08/18 1st ISSUE
Remarks
JSW Switchgear
FROM UPS
FROM UPS
FROM UPS
NewMCC
NewMCC
NewMCC
NewMCC
NewMCC
NewMCC
FROM UPS
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW Switchgear
JSW
NewMCC
NewMCC
NewMCC
FROM UPS
NewMCC
NewMCC
NewMCC
FROM UPS
4 Zone
8 Elements
8 Elements
Existing
Existing
Existing
NewMCC
NewMCC
NewMCC
NewMCC
FROM UPS
Location DI DO AI AO DI-32ch
Main Panel 615 291 46 6
25% spare 1.25 1.25 1.25 1.25
Total 768.75 363.75 57.5 7.5 24.02
25.00
RIO Panel Plenum Bag filiter Room 351 374 96 4
30% spare 1.3 1.3 1.3 1.3
Total 456.3 486.2 124.8 5.2 14.26
15.00
BF-2 Main ECR Room Building N 12 66 28 21 8
JSW interface 363 99 33 0
Total 429 127 54 8
25% spare 1.25 1.25 1.25 1.25
536.25 158.75 67.5 10 16.76
17.00
DO-16ch AI-8 ch AO-4 ch
1a
1b
2
3
3a
4
5
6
7
8
9
10
10a
11
12
13
13a
14
15
16
17
18
19
DIVISION of SCOPE about ELECTRIC AND AUTOMATION EQUIPMENT
(Totally referr
to "SCOPE of MATRIX" *file !!!)
DESCRIPTION OF EQUIPMENTS AND ACTIVITIES INSIDE SCOPE OF SUPPLY
Whole deitailed Engineering and design of Electric and Automation, including emission of detailed calculation and drawin
according to the DAUSTUR-JSW specification with Supervision and approval STEPS by EKOPLANT. For ea
items, must be included the whole ERECTION and COMMISSIONING!!!
The calculation , ralation, GA drawing, tuning of 6,6kV switchgears of JSW (cascade), mainly for inverter protection as per
Detailed Engineering issue!
The calculation, ralation, GA drawing of tuning of all electrical and automation parameters as per Detailed Engineering iss
The PLC and RIO PANELS CABINETS (ALL Rittal)
The 2 DESK with Steiless Steel TOP, The 3 HUB SWITCH PANEL (ALL Rittal)
THE LOCAL CONTROL BOXES and Junction Boxes (ALL Rittal)
ALL CABLES and TRAYS; ALL CABLES and TRAYS TOOLS for BEST ERECTION
ALL FIBER OPTIC; different type of LIUs; FO connectors; FO patches (glass type!!!)
HUB SWITCHES - COVERTERS FO/RJ45 Ethernet - COVERTERS FO/Pofibus DP (only engeneering of power supply and GA
drawing inside HUB Panels and local, if any )
THE PCC; MCC; PDB; MLCB/SLDB PANELS and LOCAL DISTRIBUTION panels
EARTHING and LIGHTNING design, calculation (refer to DASTUR Standard)
THE AVIATION LAMPS ( see attached proposal...)
All LIGHTS and UPS Panel and the relevant Distribution panel ( only tre
and fitting of Tray + routing design are EKO INDIA SUPPLIER SCOPE)
All SOCKETS (for Maintenance) 415, 240, 24Vac
TRANSFORMERS (6,6kV/415 V - 2MVA-&-415/240 2,5 kVA)...Center of star coils should be provided with measure of curr
for triping) scope of SUPPLIER of EKO INDIA !
VVVF Dirves and relevant incoming circuit breaker ( as per drawing Single Line)
HT MOTORS for FANS
ALL LIMIT SWITCHES, PROXIMITY, INSTRUMENTATION (PRESSURE SWITCH and TRANSMITTER, FLOW SWITCH and
TRASMITTER, TEMPERATURE SWITCH and TRANSMITTER, VIBRATION TRANSMITTERS..., and so on )
PAKAGE for DUST TRASPORTATION and DUST SILO SHELL! All cables are EKO INDIA SUPPLIER SCOPE !!
ALL PC, MONITORS, MOUSE and PRINTER A3 colour
APPLICATION SOFTWARE for PLC and EXCHANGE DATAS on EHTERNET
EXTENSION LICENCES for: PROGRAMMING UNIT and HMI SYETEMS, CLIENTS ONLY! (ABB)
.... AND START UP AND ASSISTANCE for ALL in SCOPE of SUPPLY of EKOPLANT!
SPARE PARTS
WHO SUPPLY? NOTE
SUPPLIER of EKO-INDIA
SUPPLIER of EKO-INDIA
SUPPLIER of EKO-INDIA
SUPPLIER of EKO-INDIA
SUPPLIER of EKO-INDIA
SUPPLIER of EKO-INDIA
SUPPLIER of EKO-INDIA
SUPPLIER of EKO-INDIA
EKOPLANT
SUPPLIER of EKO-INDIA
SUPPLIER of EKO-INDIA
SUPPLIER of EKO-INDIA
JSW
SUPPLIER of EKO-INDIA
EKOPLANT
EKOPLANT
EKOPLANT
EKOPLANT
EKOPLANT
SUPPLIER of EKO-INDIA
SUPPLIER of EKO-INDIA
SUPPLIER of EKO-INDIA
SUPPLIER of EKO-INDIA
SUPPLIER of EKO-INDIA
& EKOPLANT
Division of signals between RIO's and PLC
According to the concept, the RIO' s and the PLC panel must be considered "SEGNAL KEEPING as CONCENTRATOR". So the
PLC (and inside panel RIO): are keeping segnals from all Electrical rooms of Building 33 (from each Electrical panel and r
RIO panel located inside Plenum Bag filter Room: are keeping segnals from all filter area (Filter, instrumentation, fan an
RIO panel located inside Building 12 Pump Station: are keeping segnals from all Building 12 and segnals from/to existin
PCC PANEL
Double Incoming - 4 pole ACB of 3200A with Multifunction meter, Voltmeter & A with Schneider Electric SEPAM
Outgoing Feeders consider as:
4 Pole 1250 Amp ACB - 2 Nos
4 Pole 800 Amp ACB - 2 Nos
4 Pole XXXX Amp ACB - 2 Nos
4 Pole YYYY Amp ACB - 2 Nos
Wired segnals (enable, status) to PLC panel
PDB PANEL
4 pole MCCB ZZZZAmp - Qty. 2 Nos. (from Incomer 1 & Incomer 2) with Multifunction meter, Voltmeter & A
4 pole MCCB TTT Amp - Qty. 2 Nos
4 pole MCCB PPP Amp - Qty. 2 Nos
4 pole MCCB QQQ Amp - Qty. 2 Nos
Wired segnals (enable, status) to PLC panel
MCC PANEL
3 pole MCCB ZZZ Amp - Qty. 2 Nos. (from Incomer 1 & Incomer 2) with Multifunction meter, Voltmeter & Am
Outgoing feeder for light and socket inside each electric panel listed here!!!
Wired segnals (enable, status) to PLC panel
Wired segnals (enable, status) to PLC or RIO panel according to the location
(Filter, instrumentation, fan and motor segnals, dust bin…and relevant Local control panel !!!)