Professional Documents
Culture Documents
2.1. Project Management
2.1. Project Management
Management
Chapter 3 –
Project Management
PowerPoint presentation to accompany
Heizer/Render
Principles of Operations Management, 6e
Operations Management, 8e
© 2006
© 2006 Prentice
Prentice Hall, Inc. Hall, Inc. 3–1
Bechtel Projects
Restoring over 650 oil wells in Kuwait left ablaze or
uncapped after Desert Storm
Building 26 massive distribution centers in just two years
for the internet company Webvan Group
Constructing 30 high-security data centers worldwide for
Equinix, Inc.
Building and running a rail line between London and the
Channel Tunnel ($4.6 billion)
Developing an oil pipeline from the Caspian Sea region to
Russia ($850 million)
Research Project
Controlling
Monitor, compare, revise, action
© 2006 Prentice Hall, Inc. 3 – 10
Project Planning, Scheduling,
and Controlling
Figure 3.1
Figure 3.1
Figure 3.1
Figure 3.1
Budgets
Delayed activities report
Slack activities report
CPM/PERT
Gantt charts
Milestone charts
Cash flow schedules
Figure 3.1
Human Quality
Resources Marketing Finance Design Production
Mgt
Project 1 Project
Manager
Mechanical Test
Technician
Engineer Engineer
Project 2 Project
Manager
Electrical Computer
Technician
Engineer Engineer
Figure 3.2
Project 1
Project 2
Project 3
Project 4
Figure 3.3
Design
Prototype
Test
Revise
Production
C and D cannot
A C begin until A A C
(d) and B have
both been
B D completed B D
C cannot begin
until both A and B
A C are completed; D A C
(e) cannot begin until Dummy activity
B is completed. A
B D dummy activity is
introduced in AOA
B D
Figure 3.5
© 2006 Prentice Hall, Inc. 3 – 37
A Comparison of AON and AOA
Network Conventions
Activity on Activity Activity on
Node (AON) Meaning Arrow (AOA)
B and C cannot
begin until A is
completed. D
A B D cannot begin A B D
until both B and
(f) C are completed. Dummy
A dummy activity
C
C
activity is again
introduced in
AOA.
Figure 3.5
© 2006 Prentice Hall, Inc. 3 – 38
AON Example
Milwaukee Paper Manufacturing's
Activities and Predecessors
Immediate
Activity Description Predecessors
A Build internal components —
B Modify roof and floor —
C Construct collection stack A
D Pour concrete and install frame A, B
E Build high-temperature burner C
F Install pollution control system C
G Install air pollution device D, E
H Inspect and test F, G
Table 3.1
© 2006 Prentice Hall, Inc. 3 – 39
AON Network for Milwaukee
Paper
Activity A
A
(Build Internal Components)
Start
Activity B
Start B (Modify Roof and Floor)
Activity
Figure 3.6
© 2006 Prentice Hall, Inc. 3 – 40
AON Network for Milwaukee
Paper
Activity A Precedes Activity C
A C
Start
B D
Activities A and B
Precede Activity D Figure 3.7
© 2006 Prentice Hall, Inc. 3 – 41
AON Network for Milwaukee
Paper
F
A C
E
Start H
B D G
H
1 Dummy 6 7
Activity (Inspect/
Test)
D
3 5
(Pour
Concrete/
Install Frame) Figure 3.9
© 2006 Prentice Hall, Inc. 3 – 43
Determining the Project Schedule
Latest LS LF Latest
Start 2 Finish
EF = ES + Activity time
2 EF of B =
ES ES of B + 3
0
Start
0 of B
B
0 0 3
3
© 2006 Prentice Hall, Inc. 3 – 52
ES/EF Network for Milwaukee
Paper
A C
0 2 2 4
2 2
Start
0 0
B
0 3
2 2
Start
0 0
= Max (2, 3) D
0
3 7
B
0 3
3
4
© 2006 Prentice Hall, Inc. 3 – 54
ES/EF Network for Milwaukee
Paper
A C
0 2 2 4
2 2
Start
0 0
B D
0 3 3 7
3 4
2 2 3
Start E H
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
3 4 5
Figure 3.11
LS = LF – Activity time
2 2 3
Start E H
0 0 4 8 13 15
13 15
0 4 2
B D – Activity time
LS = LF G
0 3 3 7 8 13
3 4 5 LF = EF
of Project
Figure 3.12
10 13
2 2 3
Start E H
0 0
LF =4 Min(LS
8 of 13 15
following activity) 13 15
0 4 2
B D G
0 3 3 7 8 13
3 4 5
Figure 3.12
A C F
0 2 2 4 4 7
2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
8 13
3 4 5
Figure 3.12
0 2 2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
Figure 3.12
Slack = LS – ES or Slack = LF – EF
A 0 2 0 2 0 Yes
B 0 3 1 4 1 No
C 2 4 2 4 0 Yes
D 3 7 4 8 1 No
E 4 8 4 8 0 Yes
F 4 7 10 13 6 No
G 8 13 8 13 0 Yes
H 13 15 13 15 0 Yes
Table 3.3
0 2 2 4 10 13
2 2 3
Start E H
0 0 4 8 13 15
0 0 4 8 13 15
0 4 2
B D G
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5
Figure 3.13
A Build internal
components
B Modify roof and floor
C Construct collection
stack
D Pour concrete and
install frame
E Build high-
temperature burner
F Install pollution
control system
G Install air pollution
device
H Inspect and test
A Build internal
components
B Modify roof and floor
C Construct collection
stack
D Pour concrete and
install frame
E Build high-
temperature burner
F Install pollution
control system
G Install air pollution
device
H Inspect and test
Expected time:
t = (a + 4m + b)/6
Variance of times:
v = [(b – a)/6]2
Expected time:
t = (a + 4m + b)/6
Variance of
Probability
1 in 100 of
oftimes:
Probability
Probability
< a occurring v = [(b − a)/6]2 of 1 in 100 of
> b occurring
Activity
Time
A 1 2 3 2 .11
B 2 3 4 3 .11
C 1 2 3 2 .11
D 2 4 6 4 .44
E 1 4 7 4 1.00
F 1 2 9 3 1.78
G 3 4 11 5 1.78
H 1 2 3 2 .11
Table 3.4
15 Weeks
(Expected Completion Time)
Figure 3.15
.5 = due .69497
Z.69146 − expected.71566
date /s
.71904
p
date of completion
.6 .72575 .72907 .74857 .75175
= (16 wks − 15 wks)/1.76
15 16 Time
Weeks Weeks
Figure 3.16
Probability
of 0.01
2.33 Standard Z
From Appendix I deviations
0 2.33
Figure 3.17
Table 3.5
$30,000 —
Normal
Normal —
Cost
| | |
1 2 3 Time (Weeks)
Figure 3.18
Crash Time Normal Time
© 2006 Prentice Hall, Inc. 3 – 89
Critical Path And Slack Times For
Milwaukee Paper
A C F
0 2 2 4 4 7
0 2 2 4 10 13
2 2 3
0 0 4 8 13 15
0 4 2
B D Slack = 0 G Slack = 0
0 3 3 7 8 13
1 4 4 8 8 13
3 4 5