STATUS OF PENDING B-3 NEW CONNECTION UPTO 31-07-2018

1ST CIRCLE FESCO FAISALABAD


Sr. Application Load Approved/ Ripe/ Un
Name of Consumer Unapproved
Status
No. No. (KW) Ripe
1 42/B-3/New JUBILEE CLOTH MILLS (PVT) LTD, 1200 KW Approved DN paid on 05-12-14 Un Ripe
20-03-2014 05-Km Jaranwala Road Khurrianwala, Feeder has been
Chak Jhumra Faisalabad. completed on 01/16.
WTR and IC of
transformer awaited.
2 48/B-3/New FAZAL-E-RABBI TEXTILES, 750 KW Approved DN paid on 09-02-15. Un Ripe
28-10-2014 Plot No. 774 to 777, Small Industrial Estate, Feeder under
Civil Line Faisalabad. constrcution with PD
(Const). IC of metering
panel awaited.
3 50/B-3/New AR ENTERPRISES, 510 KW Approved DN paid on 30-06-15, Un Ripe
11-12-2014 22-Km Satiana Road Faisalabad Extension of HT line of
Jaranwala 11 KV Wanhar feeder
under construction with
PD (Const). WTR and IC
of metering panel
4 72/B-3/New 3000 KW Approved awaited.
DN paid on 23-10-17. Un Ripe
TRICON BEVERAGES (PVT) LTD,
23-02-2017 Chak No. 165/RB Jandwali, Chak Jhumra, Feeder under
Chak Jhumra Faisalabad. construction with PD
(Const). WTR, IC of
transformer and metering
panel awaited.
5 76/B-3/New VITAL FLOUR MILLS (PVT) LTD, 719.748 KW Approved DN paid on 07-09-17. Ripe
28-04-2017 Near Bypass Chowk Satiana Road Faisalabad. Committee constituted
Jaranwala for energization of
connection vide O/o No.
59/3229-35 dt 07-05-18.
6 93/B-3/New AL-FAJAR FLOOR MILLS (PVT) LTD, 896 KW Under approval Un Ripe
03-05-2018 Chak No. 211/RB, Jaranwala Road, Faisalabad.
Abdullahpur

STATUS OF PENDING B-3 NEW CONNECTION FIEDMC UPTO 31-07-2018


1ST CIRCLE FESCO FAISALABAD
1 69/B-3/New MALIK MIJ CHUNXING RESOURCES 1434.50 KW Approved DN paid on 07-12-16. Un Ripe
27-10-2016 Committee is being
RECYCLING COMPANY LIMITED,
Chak Jhumra constituted for
P-50 Phase-1A, M-3 Industrial City FIEDMC
energization of the
Sahianwala Faisalabad.
connection

2 75/B-3/New KHAWAJA COTTON INDUSTRIES, 757.285 KW Approved Revised DN paid on 01- Un Ripe
27-04-2017 Plot No. 6, M-3 Industrial City Sahianwala 03-18. WTR and IC of
Chak Jhumra Faisalabad. panel & transformer
awaited.
3 81/B-3/New CHEM TECH INTERNATIONAL, 596.80 Approved DN paid on 08-03-18. Un Ripe
13-07-2017 Plot No. B-9, M-3 Industrial City Sahianwala KW Feeder under const. with
Chak Jhumra Faisalabad. PD (const). WTR, IC of
transformer and metering
panel awaited.
4 89/B-3/New NISHAT MILLS LTD, 4956 KW Notice issued on 19-01- Un Ripe
22-11-2017 Plot No. 172-208, M-3 Industrial City, 2018
Chak Jhumra Faisalabad.

5 90/B-3/New HUAFON PAKISTAN LTD, 800 KW Notice isued on 22-02- Un Ripe


08-12-2017 Plot No. 148-151, M-3 Industrial City, 2018
Chak Jhumra Faisalabad.

Page 1 of 9
STATUS OF PENDING B-3 EXTENSION OF LOAD CASES UPTO 31-07-2018
1ST CIRCLE FESCO FAISALABAD
1 98/B-3/EXT. FAISAL FABRICS LTD, 2162 + 1338 Approved D/N paid on 23-04-14 Un Ripe
07-08-2013 1-Km Jaranwala Road Khurrianwala = 3500 KW Feeder under const. with
Chak Jhumra Faisalabad. PD (Const), WTR, IC of
24-13153-5309400 U grid panel and
transformer awaited.
2 99/B-3/EXT. HASSAN LTD, 4320 + 650 Approved D/N paid on 23-04-14. Un Ripe
15-08-2013 Chak No. 77/RB Khurrianwala Faisalabad. = 4970 KW Feeder under const. with
Chak Jhumra 24-13153-5309201 R PD (Const), WTR and IC
of transformer awaited.
3 154/B-3/Ext. IDEAL SPINNING MILLS LTD, 2791 + 980 Approved DN paid on 10-11-17. Un Ripe
22-04-2014 32-Km Sheikhupura Road, Faisalabad. = 3771 KW Reconductoring of feeder
Chak Jhumra 24-13154-5403200 R under const. with PD
(Const).
4 172/B-3/COL/ NATIONAL SILK & RAYAN MILLS 452 + 995 = Approved DN paid on 03-03-15. Un Ripe
Ext. 1447 + 1051 Feeder under const. with
LTD,
17-11-2014 = 2498 KW PD(Const). WTR and IC
Jaranwala Road Faisalabad.
Abdullahpur of grid panel &
24-13131-5101600 U
transformer awaited.
5 176/B-3/Ext. RASHID TEXTILE PROCESSING 980.510+52 Approved DN paid on 22-07-15, Un Ripe
16-12-2014 0 = 1500 Feeder under const. with
INDUSTRY,
Civil Line KW PD(Const). WTR and IC
Chak No. 07/JB, Sargodha Road, Faisalabad.
of transformer awaited.
24-13123-5304500 U
6 178/B-3/Ext. USMAN CLOTH MILLS (PVT) LTD, 454 + 326 = Approved DN paid on 23-07-15. Un Ripe
16-12-2014 Chak No. 7/JB Sargodha Road, Faisalabad. 977 KW Feeder under const. with
Civil Line 24-13123-5302200 U PD (Const). WTR and IC
of transformer awaited.
7 188/B-3/Ext. YASIR AFZAL TEXTILE DYING & 989 + 61 = Approved DN paid on 26-06-15. Un Ripe
26-01-2015 1050 KW Feeder under const. with
PRINTING INDUSTRY,
Civil Line PD (Const). WTR and IC
Sargodha Road, Faisalabad.
of transformer awaited.
24-13125-5504015 U
8 196/B-3/Ext. MIMA COTTON MILLS LIMITED, 2985 + 1965 Approved DN paid on 10-09-15. Un Ripe
12-03-2015 38-Km Sheikhupura Road Faisalabad. = 4950 KW Double circuit 11 KV line
Chak Jhumra 24-13154-5402600 U of Mima feeder under
const. with PD (Const).
WTR and IC of
transformer awaited.
9 204/B-3/Ext. MOON TEXTILE INDUSTRIES (PVT) 989 + 1140 Approved DN paid on 19-09-16. Un Ripe
29-04-2015 = 2129 KW Feeder under
LTD,
Civil Line construction with PD
Sargodha Road, Faisalabad.
(Const). WTR and IC of
24-13123-5307000 U.
grid panel awaited.
10 205/B-3/Ext. CHAWALA ENTERPRISES, 972.20 + Approved DN paid on 11-07-16. Un Ripe
29-04-2015 3-Km Jhumra Road, Chak No. 189/RB, 127.80 = Feeder under
Chak Jhumra Faisalabad. 24-13153-5300123 R. 1100 KW construction with PD
(Const). WTR and IC of
grid panel awaited.
11 210/B-3/Ext. IMAGE TEXTILE MILLS (PVT) LTD, 980 + Approved DN paid on 30-06-16. Un Ripe
24-08-2015 02-Km Jaranwala Road Khurrianwala 1141.952 = Feeder under
Chak Jhumra Faisalabad. 24-13153-5304200 R 2121.952 construction with PD
KW (Const). WTR and IC of
tranformer awaited.
12 211/B-3/Ext. AMMAR BILAL TEXTILE, 453 + 597 = Approved DN paid on 29-08-16. Un Ripe
08-09-2015 Chak No. 7/JB, Same Nala Small Estate 1050 KW Feeder under
Civil Line Sargodha Road, Faisalabad. construction with PD
24-13123-5303166 U (Const).
13 212/B-3/Ext. BASHIR PRINTING INDUSTRIES 643 + 557 = Approved DN paid on 23-09-16. Un Ripe
08-09-2015 1200 KW Feeder under
(PVT) LTD,
Civil Line construction with PD
Chak No. 07/JB, Sargodha Road, Faisalabad. (Const). WTR and IC of
24-13123-5303700 tranformer awaited.
14 213/B-3/Ext. KASHIF TEXTILE, 502 + 248 = Approved DN paid on 22-09-16. Un Ripe
08-09-2015 Sadiqabad off Sargodha Road, punj puli, 750 KW Feeder under
Civil Line Faisalabad. 24-13123-5311750 U construction with PD
(Const). WTR and IC of
grid panel and tranformer
Page 2 of 9 awaited.
15 219/B-3/Ext. NAGRA SPINNING MILL (PVT) LTD, 3484 + 1219 Approved Approved for kept Un Ripe
11-01-2016 Sheikhupura Road Adda Johal Faisalabad. = 4700 KW pending till decision of
Chak Jhumra 24-13154-5403800 R High Court regarding
duplicate source of
supply.
16 226/B-3/Ext. SAMIRA FABRICS (PVT) LTD, 435 + 545 = Approved DN paid on 04-10- 17. Un Ripe
06-04-2016 Sheikhupura Road Khurrianwala Chak No. 980 KW Feeder under
Chak Jhumra 74/RB Faisalabad. 24-13153-5302970 R construction with PD
(Const). WTR and IC of
tranformer awaited.
17 241/B-3/Ext. FAISAL FEEDS, 270 + 606 = Approved DN paid on 20-02-18. Un Ripe
28-07-2016 Chiniot Road Faisalabad. 876 KW Feeder under
Chiniot 24-13161-5100902 R construction with PD
(Const). WTR, IC
Certificate of panel &
transformer awaited.
18 242/B-3/Ext. AL-NOOR PROCESSING AND 752 + Approved DN paid on 19-03-18. Un Ripe
29-07-2016 237.50 = WTR sent to XEN (O) for
TEXTILE MILLS (PVT) LTD,
Civil Line 989.50 KW verification on 16-04-18
Chak No. 7/JB Sargodha Road Faisalabad.
and IC of transformer
24-13123-5315102 U
awaited.
19 243/B-3/Ext. AL-REHMAN PAPER MILLS, 452 + 448 = Approved DN paid on 13-04-18 Un Ripe
01-08-2016 Moza Rajoya near Zamindar Chemical Mills 900 KW Feeder under
Chiniot Chiniot. 24-13161-5101014 R construction with PD
(Const). WTR and IC of
grid panel and tranformer
awaited.
20 245/B-3/Ext. AZ APPAREL (PVT) LTD, 450 + 750 = Approved Revised DN paid on 25- Un Ripe
09-09-2016 Chak No. 117 JB Millat Road Faisalabad. 1200 KW 06-18. Amount under
Civil Line 24-13127-5702050 U verification.
21 246/B-3/Ext. BISMILLAH TOWEL INDUSTRIES, 450 + 400 = Approved DN paid on 17-04-18. Un Ripe
14-10-2016 Near Darbar Jewan Shah Faisalabad Road 850 KW Feeder under
Chiniot Chiniot. 24-13161-5100911 R construction with PD
(Const). WTR and IC of
grid panel and tranformer
awaited.
22 250/B-3/Ext. KAMAL HOSIERY MILLS, 2520 + 2450 Pending to obtain NOC Un Ripe
28-11-2016 03-Km Jhumra Road Khurrianwala Faisalabad. = 4970 KW from VAC.
Chak Jhumra 24-13152-5200840 R
23 253/B-3/Ext. ABDUR RASHID S/O GHULAM 496 + 411 = Approved DN paid on 14-05-18. Un Ripe
13-12-2016 859 KW WTR, IC of panels and
RASOOL,
Civil Line transformers awaited.
Chak No. 117/JB Dhanola Near Saeem Nala
Faisalabad. 24-13127-571710 U
24 255/B-3/Ext. KAY & EMMS (PVT) LTD, 947 + 653 = Approved Revised DN paid on 21- Un Ripe
27-01-2017 Chak No. 117/JB Dhanola Near Millat Road, 1600 KW 06-18. Feeder under
Civil Line Faisalabad. 24-13127-5701000 U construction with PD
(Const). WTR and IC of
grid panel and tranformer
awaited.
25 259/B-3/Ext. MJ TEXTILE, 492 + 706 = Approved DN paid on 15-05-18. Un Ripe
19-04-2017 6.5 Km Jaranwala Road Khurrianwala 1198 KW Feeder under
Chak Jhumra Faisalabad. 24-13153-5309502 R construction with PD
(Const). WTR and IC of
grid panel and tranformer
awaited.
26 261/B-3/Ext. GOHAR ENTERPRISES, 490 + 706 = Approved DN paid on 18-05-18. Un Ripe
08-05-2017 Chak No.103/RB Jaranwala Road Khurrianwala 1196 KW Feeder under
Chak Jhumra Faisalabad. 24-13153-5309501 R construction with PD
(Const). WTR and IC of
grid panel and tranformer
awaited.
27 263/B-3/Ext. MULTAN CHEMICAL LTD, 877 + 3323 Approved DN paid on 10-04-18. Un Ripe
12-06-2017 Plot No. 06,07 and 08, M-3 Industrial City = 4200 KW WTR and IC of
Chak Jhumra FIEDMC Faisalabad. 24-13152-5200555 R transformer awaited.

Page 3 of 9
28 264/B-3/Ext. MUMTAZ MAHAL TEXTILE 474 + 400 Approved Kept pending till removal Un Ripe
15-06-2017 = 874 of load from 11 KV 7/JB
PROCESSING MILLS (PV) LTD,
Civil Line KW feeder on consumer's
Chak No. 07/JB Faisalabad. 24-13123-5304000
request.
U.
29 267/B-3/Ext. WAQAS ENTERPRISES, 62 + 1013 Approved DN issued on 12-06-18 Un Ripe
27-09-2017 = 1075 and applied for extension
Chak No. 106/RB, Cgaudharywala Faisalabad.
Chak Jhumra KW upto 09-08-2018.
28-13152-5309506 R.

30 270/B-3/Ext. UNITED INDUSTRIES LTD, 1205 + 1800 Approved DN paid on 14-06-18. Un Ripe
20-11-2017 = 3005 Feeder under
Kashmir Road Nishatabad Faisalabad.
Abdullahpur KW construction with PD
28-13132-5204300 U.
(Const). WTR and IC of
grid panel and tranformer
awaited.
31 271/B-3/Ext. SAHIB TEXTILE (PVT) LTD, 680 + 300 Approved DN issued on 30-07-18 Un Ripe
05-12-2017 = 980
10-Km Sargodha Road Faisalabad.
Civil Line KW
24-13125-5507300 U.
32 272/B-3/Ext. Z.N. FIBERS (PVT) LTD, 516 + 474 Approved Kept pending till physical Un Ripe
08-12-2017 33-Km Sheikhupura Road, Faisalabad. = 990 KW removal of load from 11
Chak Jhumra 24-13154-5402400 R KV Johal feeder.

33 274/B-3/Ext. JUBILEE TEXTILE INDUSTRIES (PVT) 800 + 180 Approved DN issued on 30-07-18. Un Ripe
18-12-2017 = 980 KW
LTD,
Abdullahpur
Street No.37, Waheed Park Abdullahpur,
Faisalabad. 24-13132-5200600 R
34 276/B-3/Ext. GILLAN DYING, 699 + 600 Due to consumer's own Cancelled on
28-12-2017 Chak No. 117/JB, Millat Road, Faisalabad. = 1299 KW request. 30-0718
Civil Line 24-13127-5701172 U
35 277/B-3/Ext. AA PROCESSING INDUSTRY, 495 + 455 Under approval Un Ripe
05-01-2018 Samana pull, Sargodha Road, Faisalabad. = 950 KW
Civil Line 24-13123-5300155 U
36 278/B-3/Ext. AL-ROUF TEXTILE PROCESSING, 490 + 500 Approved DN not issued because Un Ripe
22-02-2018 = 990 KW senior case is under
Shadman/chibban Road, Faisalabad.
Civil Line approval.
24-13124-54005200 U
37 281/B-3/Ext. ITTEHAD FABRICS (PVT) LTD, 580 + 138 Under approval Un Ripe
12-04-2018 01- Km Jaranwala Road Khurrianwala, = 718 KW
Chak Jhumra Faisalabad. 24-13153-5300325 R
38 282/B-3/Ext. MUHAMMAD AKBAR S/O ABDUL 288 + 462 Under process Un Ripe
24-05-2018 = 750 KW
MAJEED,
Chak Jhumra
Chak No. 68/RB, tehsil jaranwala District
39 283/B-3/Ext. Faisalabad.
KLASH 24-13154-5400510
(PVT) LTD, , R 2880 + 1120 Under process Un Ripe
06-06-2018 Chak No. 117/JB Millat Road Faisalabad. = 4000 KW
Civil Line 28-13127-5700320 U
40 284/B-3/Ext. GHULAM RASOOL TEXTILE MILLS, 453 + 537 Under process Un Ripe
08-06-2018 Chak No. 168/RB Sheikhupura Road = 990 KW
Chak Jhumra Faisalabad. 24-13154-5400510 R
41 285/B-3/Ext. PAK PUNJAB PAPER AND BOARD 498 + 198.5 Under process Un Ripe
08-06-2018 = 696.5 KW
MILLS,
Chak Jhumra
32-Km Sheikhupura Road Faisalabad.
24-13154-5400525 R
42 286/B-3/Ext. AA FABRICS, 1077 + 713 Under process Un Ripe
20-06-2018 04-Km Jaranwala Road Faisalabad. = 1790 KW
Chak Jhumra 24-13153-5303202 R
43 287/B-3/Ext. STATION INCHARGE PARCO, 1987 + 1013 Under process Un Ripe
25-06-2018 Chak No. 202/RB Gatti Faisalabad. = 3000 KW
Chak Jhumra 24-13151-5101600 R
STATUS OF PENDING B-3 REDUCTION OF LOAD CASES UPTO 31-07-2018
1ST CIRCLE FESCO FAISALABAD
1 275/B-3/ROL SWEETY TEXTILES (PVT) LTD, 975 - 470 = Under process Un Ripe
18-12-2017 3.5 Km Jaranwala Road, Faisalabad. 505 KW
Chak Jhumra

Page 4 of 9
STATUS OF PENDING B-4 NEW CONNECTION CASES UPTO 31-07-2018
1ST CIRCLE FESCO FAISALABAD
1 33/B-4/New FIRST TREET MANUFACTURING 9.985 MW Approved Principal approval Un Ripe
12-01-2016 accorded for constrcution
MODARABA (BATERY DIVISION),
Chak Jhumra of grid stion vide O/o No.
M-3 Phase-II, Industrial City sahianala,
2183-89 dated 07-09-16.
Faisalabad.
2 38/B-4/New LIBERTY STEEL (PVT) LTD, 69.447 MW Load flow study under Un Ripe
06-044-2018 5-Km Sahianwala Road Interchnage Chiniot process.
Chak Jhumra Road, Faisalabad.

STATUS OF PENDING B-4 EXTENSION OF LOAD CASES UPTO 31-07-2018


1ST CIRCLE FESCO FAISALABAD
1 31/B-4/Ext. MASOOD TEXTILE MILLS LIMITED, 5400 + Approved DN paid on 06-01-17. Un Ripe
02-04-2014 32-Km Sheikhupura Road, Faisalabad. 2550 = 7950 Work at grid station is
Chak Jhumra 24-13152-5201800 U KW under execution with
PD(GSC). WTR and IC
of transformer awaited.
2 32/B-4/Ext. BEST FIBRES (PVT) LTD 4950 + Approved Principal approval Un Ripe
03-04-2015 1925 = 6875 accorded for constrcution
(FORMERLY BEST EXPORT)
Chak Jhumra + 4125 = of grid stion vide O/o No.
19-Km Sheikhupura Road Khurrianwala,
11000 KW 196/9648-54 dated 14-07-
Faisalabad. 24-13152-5309700 R
2016 (Revised approval
under process).

3 37/B-4/Ext./COL GOHAR TEXTILE MILLS (PVT) LTD, 4181+2525+ Approved DN paid on 06-02-18. Un Ripe
12-09-2017 3-Km Jhumra Road Khurrianwala, Faisalabad. 2494 = 9200 Amount transferred to PD
Chak Jhumra KW GSC for execution of
work of T/L.
4 39/B-4/Ext. ZA CORPORATION (PVT) LTD, 4950 + 5050 DN for load flow study Un Ripe
29-05-2018 22-Km Sheikhupura Road Khurrianwala, = 10000 KW charges issued on 31-05-
Chak Jhumra Faisalabad. 2018.
STATUS OF PENDING A-1 EXTENSION OF LOAD CASES UPTO 31-07-2018
1ST CIRCLE FESCO FAISALABAD
1 01/A-1/Ext. AZIZ FATIMA TRUST HOSPITAL, 400 + 350 = Approved DN paid on 28-10-16. Un Ripe
15-04-2016 Gulistan Colony Faisalabad. 24-13124- 750 KW IC of metering panels
Civil Line 5401310 U and 24-13124-5401200 U and transformer awaited.

STATUS OF PENDING CHANGE OF NAME CASES UPTO 31-07-2018


1ST CIRCLE FESCO FAISALABAD
1 15/B-3/CON 15- FAISALABAD OIL REFINERY (PVT) 750 KW Approved SJO issued for Ripe
08-2017 Chak implementation on 31-07-
LTD,
Jhumra 2018.
Faisalabad Road Chiniot. 24-13161-5101100
STATUS OF PENDING C-2 EXTENSION OF LOAD CASES 31-07-2018
1ST CIRCLE FESCO FAISALABAD
1 66/C-2/Ext. ALLIED HOSPITAL/PUNJAB 2766 + 2184 Under process Un Ripe
31-08-2017 = 4950 KW
MEDICAL COLLEGE,
Civil Line
Faisalabad .
STATUS OF PENDING A-2(C) NEW CONNECTION CASE UPTO 31-07-2018
1ST CIRCLE FESCO FAISALABAD
1 23/A-2(C)/New LYALLPUR GALLERIA, 3025 KW Approved DN paid on 27-11-17. Un Ripe
24-08-2017 Chak No. 213/RB Canal Road Faisalabad. Feeder under const. with
Abdullahpur PD (Const.).
2 24/A-2(C)/New GRAND ATRIUM, 972.32 KW Under process Un Ripe
29-03-2018 West Canal Road adjacent toyota motors
Abdullahpur Faisalabad.

STATUS OF PENDING B-3 NEW CONNECTION CASES UPTO 31-07-2018


2ND CIRCLE FESCO FAISALABAD

Page 5 of 9
1 59/B-3/New LYALLPUR OIL REFINERY (PVT) 760.89 KW Approved DN paid on 01-08-16 Un Ripe
06-04-2016 Feeder under const. with
LTD,
G.M. Abad PD (Const). WTR, IC of
Chak No. 217/RB, Narwala Road Faisalabad.
panels & transformer
awaited.
2 77/B-3/New MOTI FABRICS (PVT) LTD, 800 KW Approved DN paid on 22-12-17 and Un Ripe
02-05-2017 Ghulam Rasool Nagar Dagranwan Road 28-12-17. WTR and IC of
Peoples Colony Faisalabad. panel and transformer
awaited.
3 84/B-3/New NINE STAR FLOUR MILLS, 682 KW Approved DN paid on 15-12-17. Ripe
29-08-2017 Narwala Road Bypass Faisalabad. Committee constituted
G.M. Abad for energization of
connection vide O/o No.
48/2943-64 dt. 26-4-18.
4 88/B-3/New ZATOON TEXTILE MILLS 1746 KW Under approval Un Ripe
05-10-2017 Chak No. 245/JB, Abaspur Jhang Road,
G.M. Abad Faisalabad.
5 91/B-3/New PAK FIBERS, 2000 KW Under approval Un Ripe
11-12-2017 Chak No. 245/RB, Abaspur Jhang Road,
G.M. Abad Faisalabad.
STATUS OF PENDING B-3 EXTENSION OF LOAD CASES UPTO 31-07-2018
2ND CIRCLE FESCO FAISALABAD
1 180/B- TAUSEEF ENTERPRISES (PVT) LTD, 975.3 + 334 Approved DN paid on 08-09-15. Un Ripe
3/COL/Ext. Chak No. 219/RB, Jugewala, Faisalabad. 24- + 119 = Feeder under const. with
22-12-2014 13223-5306910 U 199+801 = PD (Const). WTR and IC
G.M. Abad 3000 KW of panel & transformer
awaited.
2 235/B-3/Ext. HILAL TEXTILE CORPORATION 900 + 90 = Approved Dn paid on 29-09-17. Un Ripe
07-06-2016 990 KW WTR sent to XEN(O) for
(PVT) LTD,
Peoples Colony verification on 07-03-
Major Tufail Shaheed Road Faisalabad.
2018.
24-13143-5301201 R
3 266/B-3/Ext. ZAM ZAM TEXTILE INDUSTRIES 146 + 814 Approved DN paid on 11-07-18. Un Ripe
25-09-2017 = 960 KW WTR, IC of panels and
(PVT) LTD,
Peoples Colony transformer awaited.
Satiana Road, Chak No. 214/RB, Faisalabad.
24-13241-5101800 R
4 288/B- UNITED TEXTILE PRINTING 451 + 450 + Under process Un Ripe
3/Ext./COL 85 = 986
INDUSTRIES 9PVT) LTD,
10-07-2018 KW
Maqbool Road, Faisalabad. 24-13247-5501700
Peoples Colony
R and 24-13-247-5500600 R
STATUS OF PENDING A-2 NEW CONNECTION CASES UPTO 31-07-2018
2ND CIRCLE FESCO FAISALABAD
1 21/A-2 (C)/New PARADISE TOWER, 1117.67 KW Approved DN paid on 23-09-15. Un Ripe
31-03-2015 136-C Peoples Colony, Faisalabad. Feeder under const. with
Peoples Colony PD (Const). WTR, I.C. of
Metering Panel, Grid
Panel and transformer
awaited
STATUS OF PENDING C-2 EXTENSION OF LOAD CASES 31-07-2018
2ND CIRCLE FESCO FAISALABAD
1 69/C-2/Ext. SDO (MES) PAKISTAN AIR FORCE, 200 +300 = Under approval Un Ripe
08-12-2017 Risalawala, Faisalabad 500 KW
Nazimabad

STATUS OF PENDING A-1 NEW CONNECTIONS CASES 31-07-2018


2ND CIRCLE FESCO FAISALABAD
1 03/A-1/New GOVT GENERAL HOSPITAL, 2460.185 Approved DN issued on 02-03-18 Un Ripe
28-12-2017 Chak No. 224/RB Faisalabad Faisalabad. KW and date extended upto
Nazimabad 02-05-2018.

STATUS OF PENDING A-1 EXTENSION OF LOAD CASES 31-07-2018


2ND CIRCLE FESCO FAISALABAD

Page 6 of 9
1 04/A-1/New MS THQ HOSPITAL SAMUNDRI, 237.14 + Under process Un Ripe
05-06-2018 Samundri. 24-13231-5102151 and 24-13231- 276.206 =
Samundri 5102150 515.346 KW

2 05/A-1/New MS THQ HOSPITAL TANDLINAWALA. 227.5 + Under process Un Ripe


05-06-2018 Tandlianwala. 24-13251-5101125 and 24- 287.846 =
Tandlianwala 13251-5101100 515.346 KW

STATUS OF PENDING B-3 EXTENSION OF LOAD CASES UPTO 31-07-2018


JHANG CIRCLE FESCO FAISALABAD
1 104/B-3/Ext. HASSAN LTD, 8- 2880 + 2010 Approved DN paid on 23-05-2014 Un Ripe
03-09-2013 Km Samundri Road Gojra. = 4890 KW Feeder under
Gojra 24-13332-5207800 U construction with PD
(Const).
2 254/B-3/Ext. MIAN KHALID FLOUR & GENERAL 486.57 + Approved DN paid on 27-09-17. Un Ripe
02-01-2017 53.3 = IC of metring panel
MILLS,
Gojra 539.87 KW awaited.
Chak No. 362/JB, Tehsil Gojra .
24-13335-5500803 U
3 258/B-3/Ext. FECTO BOARDS (PVT) LTD, 990 + 2987 Approved DN paid on 07-12-17. Un Ripe
06-03-2017 Bhakkar Road Darya Khan District Bhakkar. = 3977 KW Feeder under const. with
Bhakkar PD (Const). WTR and IC
24-13335-5500803 U
of panel and transformer
awaited.
4 279/B-3/Ext. HAR TEXTILE MILLS (PVT) LTD, 1876 + 274 Approved DN paid on11-07-18. Un Ripe
01-03-2018 Fatehabad Near Nia Lahore = 2150 KW WTR, IC of transformer
Gojra awaited.
28-13334-5400900 R
5 280/B-3/Ext. ZAHID COLD STORAGE, 506 + Approved DN paid on 25-06-18. Un Ripe
05-03-2018 Jhang Road, Gojra 284.462 = WTR sent to XEN(O) for
Gojra 790.462 KW verification on 10-07-18.
28-13331-5101700 U

STATUS OF PENDING C-2 EXTENSION OF LOAD CASES 31-07-2018


JHANG CIRCLE FESCO FAISALABAD
1 61/C-2/Ext. UAF SUB CAMPUS T.T.SINGH 143 + Approved DN paid on 08-03-16. Un Ripe
07-09-2015 1178.63 = Feeder under
Kheekha Road T.T.Singh.
T.T.Singh 1321.63 KW construction with PD
24-13322-5201106 R
(Const).
2 70/C-2/Ext. GE (AIR) PAG BASE RAFIQUI, 2400 + 2400 Approved DN paid on 27-06-18. Un Ripe
05-03-2018 = 4800 KW Reconductoring from Dog
Shorkot Cantt. 24-
T.T.Singh to Double Circuit osprey
13328-5101800 U.
line of exisitng feeder
under construction with
PD (Const).

STATUS OF PENDING B-4 NEW CONNECTION CASES UPTO 31-07-2018


JHANG CIRCLE FESCO FAISALABAD
1 35/B-4/New PAK ARAB REFINERY CO LTD, 5003 KW Approved Principal approval Un Ripe
11-08-2016 PARCO pumping station No. 6, Kot Bahador accorded for constrcution
Sultan Bhu ShahTehsil Shorkot District Jhang. of grid stion vide O/o No.
4887-93 dated 30-06-
2017.
STATUS OF PENDING B-3 NEW CONNECTIONS UPTO 31-07-2018
1 85/B-3/New SLATER HOUSE, 512 KW Approved DN paid on 20-02-2018 Un Ripe
31-08-2017 Ainwan City Old Pir Pinai Thana Gulan Khel, WTR sent to XEN (O) for
Mianwali Mianwali verification on 14-03-18,
IC of metering panel and
transformer awaited.
STATUS OF PENDING B-3 EXTENSION OF LOAD CASES UPTO 31-07-2018
SARGODHA CIRCLE FESCO FAISALABAD
1 268/B-3/Ext. CITRO PAK LIMITED, 2365 + 2446 Under approval Un Ripe
16-10-2017 Chak No. 84/Janubi, Lahore Road, Sargodha. = 4811 KW
Sargodha-II 24-13424-5402200 R
2 269/B-3/Ext. NOON SUGAR MILLS LTD, 403 + 597 = Approved DN not issued because Un Ripe
09-11-2017 Bhlawal. 1000 KW the senior case is under
Bhalwal 24-13431-5102700 U Page 7 of 9 approval.
STATUS OF PENDING C-2 NEW CONNECTION CASES UPTO 31-07-2018
SARGODHA CIRCLE FESCO FAISALABAD
1 28/C-2/New ARMY CAMP SODHI, 4000 KW Approved Committee constituted Ripe
09-02-2007 Sodhi Jaywali, Khushab for energization of
Jauharabad connection vide O/o No.
45/2082-85 dt. 26-03-15.
2 65/C-2/New UNIVERSITY COLLEGE OF 800 KW Approved DN paid on 21-03-2018. Un Ripe
14-04-2017 WTR and IC of panels
ENGINEERING & TEECHNOLOGY,
Sargodha and transformer awaited.
Chak No. 51/NB Sargodha
3 67/C-2/New GARRISON ENGINEER (ARMY) CMH 1000 KW Approved DN paid on 16-02-18. Un Ripe
09-10-2017 Feeder under const. with
SARGODHA,
Sargodha PD (Construction) and
Cantt Sargodha.
WTR sent to XEN (O) for
verfication on 27-4-18.

STATUS OF PENDING C-2 EXTENSION OF LOAD CASES UPTO 31-07-2018


SARGODHA CIRCLE FESCO FAISALABAD
1 50/C- DHQ HOSPITAL, KHUSHAB 303.350 + Approved D/N paid on 20-08-14 Un Ripe
2/Ext./COL Jauharabad. 216.65 = IC of tranformer awaited.
02-06-14 520 KW
Jauharabad
2 51/C-2/Ext. UNIVERSITY OF SARGODHA 901.04 + Approved DN paid on 29-04-15. Un Ripe
04-06-14 Sargodha. 1217.65 = Feeder under const. with
Sargodha 24-13423-5316600 U 2118.69 KW PD (Const).

3 71/C-2/Ext. CENTRAL AMMUNITION DEPOT, 1000 + 1000 Under process Un Ripe


24-04-18 Sargodha. = 2000 KW
Sargodha-II 24-13428-5814600 U
STATUS OF PENDING C-2 REDUCTION OF LOAD CASES 31-07-2018
SARGODHA CIRCLE FESCO FAISALABAD
1 63/C-2/ROL CHASHMA HYDEL POWER STATION. 19800 - Under approval Un Ripe
09-08-16 Mianwali 19150 = 650
Mianwali 24-13456-5600400 U KW

2 64/C-2/ROL CHASHMA HYDEL POWER STATION. 19800 - Under approval Un Ripe


09-08-16 Mianwali 16060 =
Mianwali 24-13456-5600400 U 3740 KW

STATUS OF PENDING C-3 REDUCTION OF LOAD CASES UPTO 31-07-2018


SARGODHA CIRCLE FESCO FAISALABAD
1 16/C-3/ROL CHASHMA NUCLEAR POWER 36-18 = 18 Approved Approved vide O/o No. Un Ripe
22-11-2016 MW 01/04-14 dt. 02-01-2017
PROJECT UNIT-3.
Mianwali
PAEC Colony Chashma Mianwali.
STATUS OF PENDING C-3 NEW CONNECTIONS CASES UPTO 31-07-2018
SARGODHA CIRCLE FESCO FAISALABAD
1 15/C-3/New CHASHMA NUCLEAR POWER 18 MW Approved Approved vide O/o No. Un Ripe
21-11-2016 02/15-25 dt. 02-01-2017
PROJECT UNIT-4.
Mianwali
PAEC Colony Chashma Mianwali.
2 17/C-3/New PAKISTAN ATOMIC ENERGY 70 MW Approved DN paid on 31-08-2017 Un Ripe
28-11-2016 and 20-10-2017. Grid
COMMISSION,
Sargodha station under
04-Km Wan Bachrian Harnoli Road Mianwali.
construction.

STATUS OF PENDING B-4 EXTENSION OF LOAD CASES UPTO 31-07-2018


SARGODHA CIRCLE FESCO FAISALABAD
1 34/B-4/Ext. FLYING CEMENT COMPANY 24811.52 + Under approval Un Ripe
11-08-2016 24830.10 =
LIMITED,
Jauharabad 49642.10
25-KM Lilla Interchange (LHR-ISB Motorway)
KW
Mangwal District Khushab. 24-13442-
5204101
Page 8 of 9
2 36/B-4/Ext. MAPLE LEAF CEMENT FACTORY 40 + 10 = 50 Under approval Un Ripe
08-06-2017 KW
LIMITED,
Mianwali
Sakandarabad District Mianwali.
24-13453-5300102

Page 9 of 9