Construction of 4 nos. ROB for Bridges 187 (Ch. 47482.378M), 190( ch.

47960.00 M),197(Ch.49036.121 M) & 195-A(Ch.48602.00 M)


and 1 RUB for Bridge no. 144(Ch.37898.004) along with pucca approach
Name of the Work: road and other ancillary works in between station Bairabi and Sairang in
connection with construction of new BG Railway line from Bairabi to
Sairang (Mizoram)

C.A No: CON/B-S/2327, dated- 24.03.2017.


Name of Contractors: Durga Krishna Stores Pvt Ltd
Date of Commencement: 12/24/2016

Earth Cutting at D/hill Slope at Zero Point.

Schedule-A USSOR- 013110


E/w in cutting (classified ) in formation…etc

Cumulative E/work done: 4400 Cum (approx)


Scope of Work: 45000 Cum (approx)

E/work in excavation for foundation of Br 197


Cumulative E/work done: 4800 (approx)
Scope of Work: 5300 (approx)
Sl No- 01