 Access road from S/S plot boundary to the proposed permanent road for the S/S (SS-SF1, SS-7-

10, SS-1,SS-SF2,SS-A,SS-DR,SS-DD) Will be under L&T scope. Kindly confirm.


 The proposed S/S, SS-WF is near to the plot no-1 of earlier proposed Wind farm area. ACWA
need to clarify, that any special request received from TRSDC to shift the S/S SS-WF near to
Wind farm Plot-2 or plot-3.
 As per proposed ACWA dwg, CSU unit is outdoor. ACWA has to confirm, TRDC accepted for
outdoor type.
 Proposed UG cable route is final one or it can be changed after detailed survey. ACWA need to
confirm.
 We presume that treatment & discharging of dewatering which occur during S/S excavation will
be under ACWA Scope.
 Geo Tech report for SS-SF-2, SS-SF-1 & SS-WF to be provided by ACWA.
 We presume that clearance of trees and bushes along with Environmental clearance or
clearance from concerned authority will be taken care by ACWA.
 In shyebraha island considerable coral reef surrounding the island upto 500m distance from the
shore side of island. We presume that ACWA will provide necessary arrangement for movement
of the barge movement and removal of coral reef along with shore protection will be taken care
by ACWA. Kindly clarify.
 FGL level for the S/S

1) SS-SF1
2) SS-SF2
3) SS-1
4) SS-7-10
5) SS-WF
6) SS-A
7) SS-DR
8) SS-DD
9) SS-10-1
10) SS-9-3
11) SS-9-4
12) SS-9-5
Need to be obtained by ACWA from TRSDC.