www.hilti.in Hilti PROFIS Rebar 2.5.

1
Company: M/s WVA Engineering Consultant Page: 1
Specifier: Mr. Atul Project: LNG Petronet
Address: Fastening point: revised to wall connection
Phone | Fax: | Date: 20/03/2020
E-Mail:
Specifiers comments: 10mm rebar at 100mm c/c using Re 500 V3 chemical

Design standard: HIT Rebar Design


Application type: All applications/Slab to wall

1. Loads 2. Drilling & Temperature 3. Material & Safety

Loads Drilling Structure


Md 40.0 Hole Dry Concrete class (existing C30/37
kNm/m condition structure)
Nd 0.00 kN/m Drilling Hammer Char. yield strength (existing) 500 N/mm²
method drilling Char. yield strength (new) 500 N/mm²
Vd 200 kN/m
Drilling aid Drilling aid is Cracks
Fire design used
Cracks along parallel No
Fire rating None Temperature (HIT Rebar Design) member top side
Fatigue design During from 5 °C to Cracks along parallel No
None installation 40 °C member bottom side
Seismic During 20 °C / 20 °C
service
Seismic loads No

Input data and results must be checked for agreement with the existing conditions and for plausibility!
PROFIS Rebar ( c ) 2009 Hilti AG, FL-9494 Schaan Hilti is a registered Trademark of Hilti AG, Schaan
www.hilti.in Hilti PROFIS Rebar 2.5.1
Company: M/s WVA Engineering Consultant Page: 2
Specifier: Mr. Atul Project: LNG Petronet
Address: Fastening point: revised to wall connection
Phone | Fax: | Date: 20/03/2020
E-Mail:

4. Eurocode 2 parameters 5. Post-installed reinforcement

αcc 1.00 EC2 3.1.6(1) Number of layers


αct 1.00 EC2 3.1.6(2) Number of top layers 1.00
Number of bottom layers 1.00
αct,bond 1.00
Top reinforcements parameters
εud 0.0200 Table C.1
Top diameter 10.0 mm
k2 0.850 EC2 6.5.4(4b) Top spacing 100 mm
ν' 0.880 EC2 6.5.2(2) Top layer 1: c 50.0 mm
ρmax 0.0400 EC2 9.2.1.1 Top layer 1: cd (EC2, 8.4.4.1) 45.0 mm
εc2 -3 Table 3.1
2.00•10 Top bond condition Good
εc2u 3.50•10 -3 Table 3.1 Top min. reinforcement 100 mm²/m
Bottom reinforcements parameters
Bottom diameter 10.0 mm
Bottom spacing 100 mm
Bottom layer 1: c 50.0 mm
Bottom layer 1: cd (EC2, 45.0 mm
8.4.4.1)
Bottom bond condition Good
Bottom min. reinforcement 100 mm²/m
Other
Transverse pressure 0.00 N/mm²
Cover of tension force line b 0.00 mm

Input data and results must be checked for agreement with the existing conditions and for plausibility!
PROFIS Rebar ( c ) 2009 Hilti AG, FL-9494 Schaan Hilti is a registered Trademark of Hilti AG, Schaan
www.hilti.in Hilti PROFIS Rebar 2.5.1
Company: M/s WVA Engineering Consultant Page: 3
Specifier: Mr. Atul Project: LNG Petronet
Address: Fastening point: revised to wall connection
Phone | Fax: | Date: 20/03/2020
E-Mail:
Selected solution
Bar size Drill bit size Bar spacing Distance Drilled hole required
centre/centre centre/surface
Layer of bars Φ [mm] D [mm] s [mm] cs [mm] ℓvreq [mm]
Top / left 1 10.0 14.0 100 1,055 204
Bottom / right 1 10.0 14.0 100 1,055 109

Required accessories

Drilling Cleaning Setting


- Suitable rotary hammer - Compressed air with required accessories to - Dispenser including cassette and mixer
- Properly sized drill bit blow from the bottom of the hole - For deep installations, a piston plug is
- Proper diameter wire brush necessary

Section Analysis

Strut angle θ 24.2 ° EC2 6.2.3


Inner lever arm z1 137 mm
Action of moment node → fFN 0.850
Reduced lever arm z1R = z1∙fFN 117 mm
Position of neutral axis X 19.1 mm
Compressive reinforcement required? no

Upper layer (tension side)


Design Input

Design force in bar FE 34.2 kN EC2 9.2.1.4(2)


Required reinforcement As,rqd 788 mm²/m
Provided reinforcement Φ = 10 mm, s = 100 mm → As,prov 785 mm²/m
Stress in bars σsd = FE/As,prov 436 N/mm²
Adhesive used Hilti HIT-RE 500 V3

Input data and results must be checked for agreement with the existing conditions and for plausibility!
PROFIS Rebar ( c ) 2009 Hilti AG, FL-9494 Schaan Hilti is a registered Trademark of Hilti AG, Schaan
www.hilti.in Hilti PROFIS Rebar 2.5.1
Company: M/s WVA Engineering Consultant Page: 4
Specifier: Mr. Atul Project: LNG Petronet
Address: Fastening point: revised to wall connection
Phone | Fax: | Date: 20/03/2020
E-Mail:

a) Reactions

M2d -45.0 kNm/m M3d -45.0 kNm/m


N2d 100 kN/m N3d -100 kN/m
V2d 0.00 kN/m V3d 0.00 kN/m
FT2d -M2/(0.9d2)+N2/2+V2•cot(θ)/2 161 kN/m FT3d +M3/(0.9d3)+N3/2+V3•cot(θ)/2 0.00 kN/m

b) Anchorage Post-Installed Reinforcement

Bond condition Good → η1 1.00 EC2 8.4.3(2)


Bond strength fbd,pi 3.00 N/mm² ETA 16/0142
Basic anchorage length lb,rqd = (Φ/4)•(σsd/fbd,pi) 363 mm
Basic anchorage length (Fyd) lb,rqd,fyd = (Φ/4)•(fyd/fbd,pi) 362 mm

Factor for minimum length fmult,min 1.00


Minimum anchorage length lb,min = fmult,min•max(0.3lb,rqd,fyd; 10Φ; 100 mm) 109 mm EC2 8.7.3(1)
and German
Nationaler
Anhang
Min of clear cover or half spacing cd 45.0 mm > 3Φ EC2
8.4.4(1)
Reduction for large cover δ 0.306

Influence cover/spacing α2' = {1/[1/0.7+δ∙(cd-3Φ)/Φ] ≥ 0.25} 0.530


Influence cover/spacing α2 = {0.7 ≤ 1-0.15[(cd-Φ)/Φ] ≤ 1.0} 0.700

Splitting bond strength fbd,HRM1.0 = fbd,pi/α2' 5.66 N/mm²


Splitting bond strength fbd,HRM2.0 4.26 N/mm² bond strength
calculated based
on testing
results database
Pullout bond strength fbd,po 9.71 N/mm² ETA 16/0143
Controlling bond strength fbd,HRM = max(fbd,HRM1.0; fbd,HRM2.0) 5.66 N/mm²

Design anchorage length lbd = max[(Φ/4)•(σsd/fbd); lb,min] 192 mm

c) Compressive strut in node

Drill hole depth linst 204 mm


Lever arm inside node z0 = linst-c2-lbd/2 67.4 mm
Strut angle tan(θF) = z0/z1R → θF 30.0 ° ≥ 30° → ok

Horizontal comp. of strut force Fc0d = (M1d+(V2d+V3d)•z1/2)/z0 593 kN/m


Compression in strut direction D0d = Fc0d/cosθF 685 kN/m
Design compressive strength redfcd = αcc•v’•k2•fck/γc 15.0 N/mm²
Resistance of strut D0Rd = redfcd∙lbd∙cosθF 2,494 kN/m D0d → ok

Input data and results must be checked for agreement with the existing conditions and for plausibility!
PROFIS Rebar ( c ) 2009 Hilti AG, FL-9494 Schaan Hilti is a registered Trademark of Hilti AG, Schaan
www.hilti.in Hilti PROFIS Rebar 2.5.1
Company: M/s WVA Engineering Consultant Page: 5
Specifier: Mr. Atul Project: LNG Petronet
Address: Fastening point: revised to wall connection
Phone | Fax: | Date: 20/03/2020
E-Mail:

d) Splitting force in transition area

Shear stress acting in slab τEd = |V2d|/z2 0.00 N/mm²


Splitting moment Msp,d = Fc0d∙z0∙(1-z0/z2)∙(1-lb1/(2∙z2)) 27.9 kNm/m
Resisting moment to splitting Wsp = z22/2.41 1.04•105 mm³/mm
Splitting stress in slab maxσsp,d = Msp,d/Wsp + τEd 0.269 N/mm²
Resistance to splitting αct∙fctk,0.05/γc = 0,85∙fctk,0,05/1,5 1.35 N/mm² ≥ maxσsp,d→ok

e) Tension reinforcement in node

Additional tensile force Hs2d = (M1d+(V2d+V3d)•z1/2)∙(1/z0-1/z2)+V1d∙(z1/z0-1) 721 kN/m


Tension in top reinforcement 0 ≤ FT0d = FT2d + Hs2d 882 kN/m
Top reinforcement required As0,rqd = FT0d/(fyk/γs) 2,029 mm²/m Amount of
tensile
reinforcement in
the node area
required for
forces out of
connection (in
addition to
previous
loading)

Lower layer
Design Input

Design force in bar FE 0.00 kN EC2 9.2.1.4(2)


Required reinforcement As,rqd 0.00 mm²/m
Provided reinforcement Φ = 10 mm, s = 100 mm → As,prov 785 mm²/m
Stress in bars σsd = FE/As,prov 0.00 N/mm²
Adhesive used Hilti HIT-RE 500 V3

Minimum Anchorage Length

Basic anchorage length (Fyd) lb,rqd,fyd = (Φ/4)•(fyd/fbd) 362 mm EC2 8.4.3

Factor for minimum length fmult,min 1.00 ETA 16/0142


Minimum anchorage length lb,min = fmult,min•max(0.3lb,rqd,fyd; 10Φ; 100 mm) 109 mm EC2 and
German
Nationaler
Anhang

Installation length linst = lbd 109 mm

Remarks
This design exclusively considers the local load transfer from the post-installed tensile reinforcement at the intersection between new and
existing concrete. The joint surfaces for concreting must be roughened to at least such an extent that aggregates protrude. It assumes that
adequate transverse reinforcement is provided in the anchorage area if required.
The shear load carrying capacity of the cross section has to be designed separately.

Input data and results must be checked for agreement with the existing conditions and for plausibility!
PROFIS Rebar ( c ) 2009 Hilti AG, FL-9494 Schaan Hilti is a registered Trademark of Hilti AG, Schaan
www.hilti.in Hilti PROFIS Rebar 2.5.1
Company: M/s WVA Engineering Consultant Page: 6
Specifier: Mr. Atul Project: LNG Petronet
Address: Fastening point: revised to wall connection
Phone | Fax: | Date: 20/03/2020
E-Mail:
The HIT Rebar Design is used in this calculation evaluates solely the strength of the connection; serviceability criteria are not considered.
Indications on displacements and creep of post-installed rebars can be found in the European Technical Approvals for anchors. The Installation
(drilling, cleaning, setting) must be according to the approval!
The user is repsonsible to check the amount of reinforcement in the existing structure. The frame node only works if there is sufficient
reinforcement in the existing part!
Fixed diameter and spacing selected. Please be aware that over-reinforcement of the section may lead to brittle failure of the fastening.
The accessory list in this report is for the information of the user only. In any case, the instructions for use provided with the product have to be
followed to ensure a proper installation.
User has defined the frame node strut angle as 30 degrees with engineering judgement.
Minimum reinforcement requirements are not checked by the software.