Professional Documents
Culture Documents
DISTRIBUTION SYSTEM
PLANNING
Dr. AHMED-ALARASHI
TOPICS TO BE COVERED
Transmission and Distribution system
planning
• Introduction
• Planning Basic Steps.
• Long Term and Short Term Planning.
• Factors Affecting System Design.
• System Planning Technic.
• Power system analysis packages.
• General Goals of System Design
Introduction
• The objective of planning is to provide the
foundation to be able to supply electrical
energy reliably and economically.
• The system should be of simple configuration,
clearly arranged operation conditions and
flexibility in respect of extensions.
• Proper planning needs clear vision of
electrical energy provider.
• Several data need to be available. Including
load, equipment, advanced in technology.
…..etc.
1
PLANNING BASIC STEPS
Planning involves five basic steps:
1. Identify the problem - forecast where
demand will exceed present capacity.
2. Set the goals - the system must meet
all criteria, at the lowest possible
cost.
3. Identify alternatives - different
reinforcement or alternative plans.
4. Evaluate each for electrical and
reliability performance and for cost.
5. Select the lowest-cost alternative
whose performance meets all criteria.
2
3- Identify the Alternatives
• This is the most critical part of the planning.
• Good deal of skill, breadth of thinking, and
time is required to identify the range of
possibilities.
• Questions to be answered:
• What could be done?
• What options are available?
• What variations on these options would be
possible?
• Planners should study if and how it assures
that all possible options are considered.
3
Long Term and Short Term Planning
Generation 13
EHV Transmission 9
Transmission 8
Sub-transmission 7
Substation 6
Feeder 3
Lateral 5
Service level 1
4
Long Term Planning
• The purpose of long term planning is to look beyond
the lead time to see that short term plans and
commitments make good sense in the long run and
that investment in durable physical assets has lasting
benefit.
• It Provides several useful functions, as listed below:
• Good investment is to be assured.
• Help evaluating short terms plans.
• Forecast of long-range budgets.
• Identification of long-term direction and strategy.
• A basis for evaluation of new ideas or changes in
procedure.
• Coordination of planning among levels of the power
system.
5
Additional Factors Affecting System Design (1)
• Economic factors:
1. Inflation.
2. Availably of fund.
3. Customer rate.
• Demographic factors:
1. Rate of birth
2. Movement of population.
• Technology factors:
1. Availably of new nonconventional energy
sources.
6
Distribution System Planning Technic (2)
• Operational researches methods used for
economical analysis, they include:
• Decision making analysis.
• Linear programing.
• Transportation Problems.
• Assignment Problem.
• Queuing theory.
Load Forecasting
• Purpose: to provide forecast of power delivery
requirements for T&D planning.
• Timing: selected years to cover the period from 1 to 25
years ahead, usually 1, 2, 3, 5, 7,10,15, and 20 years ahead.
• Products: small area forecast by year of peak demand,
annual kWh, customer types, and other factors (e.g., end-
use, reliability).
• Coordinated with: Corporate forecast, customer-level
planning (DSM impacts forecast). Marketing plan. Critical
input to distribution plan.
• Tools used: Spatial load forecast method (simulation or
trending). End-use analysis of load/customer value.
Corporate forecast database.
7
GENERATION PLANNING
• Purpose: short- and long-range planning of
facilities to build new generation plants.
• Timing: short-range - 3 to 7 years; long-range
- 5 to 20 years.
• Products: Power plant, schedule coordinated
with transmission grid plans.
• Coordination with: transmission system, sub-
transmission, distribution and substation
planning.
• Tools used: load flow and short circuit, route.
TRANSMISSION PLANNING
• Purpose: short- and long-range planning of facilities to
deliver power to the sub-transmission and distribution
substations.
• Timing: short-range - 3 to 7 years; long-range - 5 to 20
years.
• Products: schedule coordinated with sub-transmission,
substation plans.
• Coordination with: generation, sub-transmission,
distribution and substation planning.
• Tools used: transmission network load flow and short
circuit, route optimization software, combined sub-
transmission-substation optimization programs.
SUB-TRANSMISSION PLANNING
• Purpose: short- and long-range planning of facilities to
deliver power to the distribution substations.
• Timing: short-range - 3 to 7 years; long-range - 5 to 20
years.
• Products: short-range - sub-transmission project
schedule coordinated with substation and transmission
grid plans; long-range - a base sub-transmission plan.
• Coordination with: "transmission system" planning
(EHV, grid, generation), substation-level planning (must
deliver power to substations).
• Tools used: transmission network load flow and short
circuit, route optimization software, combined sub-
transmission-substation optimization programs.
8
SUBSTATION PLANNING
• Purpose: short- and long-range planning of facilities to
control, route, and transform power from T to D.
• Timing: short-range - 3 to 7 years; long-range - 5 to 20
years.
• Products: short-range - substation project schedule
coordinated with sub-transmission and distribution
plans; long-range - long-range plan.
• Coordination with: sub-transmission planning,
distribution planning.
• Tools used: GIS systems, substation selection
optimization applications, combined sub-transmission-
substation-feeder system optimization application.
FEEDER PLANNING
• Purpose: short-range planning of the feeder system to
produce project definitions and authorization for
feeder additions and enhancements.
• Timing: 1 to 5 years.
• Products: feeder system project specifications,
schedule, and budget.
• Coordination with: feeder system planning, substation
planning, customer planning, and construction.
• Tools used: "feeder design" CAD systems, feeder
optimization programs (either single or multi-feeder),
AM/FM and GIS systems.
9
CUSTOMER LEVEL PLANNING
• Purpose: short- and long-range planning of customer-level
resources including DSM, DG, DS, RTP and TOU rates.
• Timing: 1 to 25 years.
• Products: schedule of customer-side resource
projects/programs; long-range plan of DSM/DG/DS targets.
• Coordination with: all levels of planning, corporate
forecast/rate plan, spatial load forecast. Note: this planning
is often done by the rate or corporate planning department.
• Tools used: End-use load models. Integrated resource
Programs. Customer response models.
Econometric/demographc models. Spatial load forecast.
10
POWER SYSTEM ANALYSIS PACKAGES (2)
3- Circuit breaker duty
• Identify asymmetrical fault current based on
X/R ratio.
4- Protective device coordination
• determine characteristics and settings of medium
voltage protective relays and fuses, and entire low
voltage circuit breaker and fuse coordination.
5- Motor starting
• Identify system voltages, motor terminal voltage,
motor accelerating torque, and motor accelerating
time when starting large motors.
11
Decisions in planning
• Decisions in planning may include:
• Substation (expansion, transformer sizing,
feeder sizing and routing).
• Generation (additional power plants,
Location, Type)
• Transmission System (AC or DC, Overhead
or underground, Voltage selection).
12
GENERAL GOALS OF SYSTEM DESIGN (3)
13