Professional Documents
Culture Documents
Pablo Frias
Tomás Gómez San Román
Martin J.J. Scheepers
Project objectives
The objectives of the DG-GRID project are to:
- To review the current EU MS economic regulatory framework for electricity
networks and markets and identify short-term options that remove barriers for
RES and CHP deployment.
- To analyse the interaction between economic regulatory framework, increasing
volume share of RES and CHP and innovative network concepts in the long-term.
- To assess the effects of a large penetration of CHP and RES by analysing
changes in revenue and expenditure flows for different market actors in a
liberalised electricity market by developing a costs/benefit analysis of different
regulatory designs and developing several business models for economic viable
grid system operations by DSOs.
- To develop guidelines for network planning, regulation and the enhancement of
integration of DG in the short term, but including the opportunity for new innovative
changes in networks in the long-term
Project partners
- ECN, NL (coordinator),
- Öko-Institut e.V., Institute for Applied Ecology, Germany
- Institute for future energy systems (IZES), Germany
- RISØ National Laboratory, Denmark
- University of Manchester, United Kingdom
- Instituto de Investigación Tecnológica (ITT), University Pontificia Comillas, Spain
- Inter-University Research Centre (IFZ), Austria
- Technical Research Centre of Finland (VTT), Finland
- Observatoire Méditerranéen de l'Energie (OME), France
2
Table of contents
Acknowledgement .........................................................................................................2
Table of contents............................................................................................................3
Glossary .........................................................................................................................5
Introduction....................................................................................................................6
1 Effect of DG connections on UK distribution network .............................7
1.1 Presentation of the case studies..................................................................7
1.2 Network description ...................................................................................8
1.3 Percentage of lines and substations to be upgraded in rural networks.....11
1.4 Upgrade cost in rural networks ................................................................13
1.5 Costs associated with active management ...............................................15
1.5.1 Energy costs due to curtailment........................................................15
1.5.2 Implementation cost..........................................................................16
1.6 Benefits of active management in rural networks....................................16
1.7 Benefits of active management in urban networks ..................................18
1.8 Effect of DG on distribution losses and distribution network capex .......20
1.8.1 Distribution losses and DG at 11kV .................................................20
1.8.2 Distribution network capex and DG .................................................23
1.9 Reduction of losses and provision of network capacity from micro
generation.................................................................................................25
1.9.1 Micro CHP ........................................................................................25
1.9.2 Photovoltaics.....................................................................................27
1.10 Summary of the effect of DG connections on UK networks ...................28
2 Effect of DG connections on Finnish distribution network .....................31
2.1 Finnish generic distribution network models...........................................31
2.1.1 0.4kV network model........................................................................31
2.1.2 20kV network models .......................................................................32
2.1.3 Load profiles .....................................................................................33
2.1.4 DG data .............................................................................................34
2.2 Description of case studies.......................................................................34
2.2.1 DG penetration levels .......................................................................34
2.2.2 Allocation of DG...............................................................................35
2.2.3 Application of suitable network models for addressing different
issues 36
2.2.4 Operation philosophies used in the studies.......................................36
2.2.5 Modelling of intermittent and non intermittent DG..........................36
2.2.6 Benefits and costs of DG connections ..............................................36
2.3 Benefits of active management ................................................................37
2.3.1 Studies on the generic rural network ................................................37
2.3.2 Studies on the generic urban network...............................................43
2.3.3 Additional cost associated with active management ........................48
2.3.4 Costs and benefits of active management on Finnish networks .......50
2.4 Effect of DG on distribution network losses............................................52
2.5 Effect of DG on distribution network Capex ...........................................57
2.6 Effect of micro or mini generation on Finnish distribution network losses
reduction and network capacity replacement...........................................60
2.7 Summary of the effect of DG connections on Finnish distribution
networks ...................................................................................................61
3
3 Summary ..................................................................................................64
4 References ................................................................................................70
4
Glossary
AM Active Management
Capex Capital expenditure
CHP Combined Heat and Power
DG Distributed Generator
DSO Distribution System Operator
F&F Fit and forget approach (or passive management approach)
FL Fault level or a short circuit capacity
GSP Grid Supply Point. A point of supply from the national transmission system
to the local system of the distribution network operator.
OH Overhead (lines)
O&M Operation and maintenance
PM Passive Management
PV Photovoltaic
UG Under-ground cables
Currencies: Great Britain Pound (£) and Euro (€) are used in this report. One GBP is
approximately equal to 1.5 €.
5
Introduction
This report describes the cost and benefits of DG to distribution networks. The
analyses are based on the reference network models and evaluation methodology
described in the report D7 “Method for Monetarisation of Cost and Benefits of DG
Options”, D. Pudjianto, D.M. Cao, S. Grenard, G. Strbac, DG-Grid, Jan 2006,
http://www.dg-grid.org/results/index.html.
Case studies were performed on the generic distribution network models which uses
UK and Finnish network parameters to evaluate the impact of DG on network losses,
voltage, fault level / short circuit power and investment schemes. The evaluation was
carried out considering different DG technologies such as PV, CHP and small hydro.
The impact of two different operating regimes namely passive and active network
management has also been assessed. The results cover UK and Finnish cases based
on rural and urban networks considering different characteristics of these two
networks. Analyses of the results are presented in this report in details.
The following three main sections of this report are summarised as below:
6
1 Effect of DG connections on UK distribution
network
1.1 Presentation of the case studies
The average generic distribution network which captures both rural and urban
networks characteristics and is described in report D7 has been used to model 200
Grid Supply Points (GSPs) in the UK. Driven by the need for using renewable energy
sources due to environmental concern, it can be foreseen that the penetration of DG in
the UK distribution network will increase. However, the views on the UK picture of
DG capacity, and DG location in the future are not yet clear. For that reason, four
different penetrations of DG in the UK distribution network at 11kV were studied:
2.5GW; 5GW; 7.5GW and 10GW. Considering maximum load of total system is
about 50GW, the ratio of DG’s capacity to peak load capacity are 5% 10%, 15% and
20%. It is expected that these high penetrations of DG will lead to technical problems
especially when DG is connected to a weak distribution network, which is the case of
the 11kV voltage level in the UK, particularly in rural areas. Therefore, for each of the
penetrations chosen above, four different allocation scenarios were assumed and
investigated:
• DG connected over 50% of GSPs and 2/3 of the 11kV feeders (L)
• DG connected over 50% of GSPs and 1/3 of the 11kV feeders (LM)
• DG connected over 25% of GSPs and 2/3 of the 11kV feeders (HM)
• DG connected over 25% of GSPs and 1/3 of the 11kV feeders (H)
For each scenario, active management is applied in each 11kV module of the GSP
model, and DGs are assumed to have a unity power factor. In the case of the “fit and
forget” philosophy (i.e. passive management), the distribution feeders are upgraded so
that they can accommodate the full DG capacity without encountering any voltage or
thermal issues. In the case of active management, two cases are studied for network
reinforcement:
• “Non-intermittent case”: a flat output is used for all DGs installed in the UK.
This profile was derived from the output profile of industrial medium/large
size CHP. Reinforcement of equipment attached to a generator is required if
more than 0.5% of the energy delivered is curtailed.
• “Intermittent case”: The DG profile was derived from the wind generation
output profile which has around 30% load factor. It is observed that the energy
curtailed is equal to 10% of the energy curtailed in the non-intermittent case.
Investment is required if more than 2.5% of the energy delivered is curtailed.
These two cases are described in this section as non-intermittent and intermittent
generation respectively.
7
The study compares the incremental cost of upgrading feeders and substations under
the “fit and forget” design and under active management of the network. However,
implementing the latter comes at a cost. Therefore, under active management, to the
incremental cost of upgrading feeders and substations must be added the cost of
generation curtailment, and also the cost of implementing active management which
includes investment cost in voltage measurement units and investment cost in control
and communication systems.
Even though the average GSP network was used, the costs due to voltage rise and
thermal problems are defined as the costs in rural system because these problems
occur typically in the weak 11kV rural feeders characterised by long and thin
diameter of overhead line sizes. On the other hand, the costs associated with fault
level issues are linked with urban networks where short cables are required.
The low loaded 11kV modules are composed of 2×7.5MVA transformers, whereas
the high loaded 11kV modules are composed of 2×17.5MVA transformers. All these
modules are built with eight 11kV overhead lines of different lengths, varying
between 8 km and 25 km, and different loading conditions.
The 0.4kV modules are designed as follows: the first one has a transformer capacity
of 100kVA and two feeders with different loadings, the second one has a transformer
capacity of 250kVA and two feeders with different loadings, the third one has a
transformer capacity of 250kVA with four feeders connected, while the last one has a
transformer capacity of 630kVA and four feeders connected. The average length of
the 0.4 kV feeders is 0.35km, and in all cases the load and the distribution
transformers are uniformly distributed along the 0.4kV and 11kV feeders respectively.
Urban and rural networks tend to have different network characteristics. In order to be
comparable, it is supposed that both networks are composed of the same number of
circuits and transformers at each voltage level and of the same loading conditions as
the current average GSP networks. Rural and urban network models data are listed in
Table 1-1 to Table 1-5, where OH and UG for circuit type stand for overhead and
underground respectively.
8
Table 1-1 Number and capacity of transformers in different voltage level subsections
Voltage Number × capacity of transformers
level Model 1 Model 2 Model 3 Model 4
11kV/0.4kV 200 x 100kVA 250 x 250kVA 250 x 250kVA 250 x 630kVA
33kV/11kV 12 x 2 x 7.5MVA 12 x 2 x 17.5MVA
132kV/33kV 4 x 2 x 66MVA
GSP substation 1 × 2 × 240MVA
1
Load distribution types: U.D: Uniformly distributed; L.I.: Linearly Increasing
9
Table 1-3 Circuit parameters for UK 11kV network model
Load
11kV Type Size(mm2) Length(km) % of load
Circuit distribution
module
Rural Urban Rural Urban Rural Urban Rural Urban Rural Urban
Circuit 1 OH UG 50 70/50 40 5 5 14 L.I. U.D.
2
Circuit 2 OH UG 300/95 50 40 5 20 11 L.I. U.D.
Circuit 3 OH UG 50 70/50 30 5 5 14 U.D. U.D.
Module Circuit 4 OH UG 300/95 50 30 5 20 11 U.D. U.D.
1 Circuit 5 OH UG 50 70/50 15 2.5 5 14 L.I. U.D.
Circuit 6 OH UG 300/50 50 15 2.5 20 11 U.D. U.D.
Circuit 7 OH UG 50 70/50 10 2.5 5 14 U.D. U.D.
Circuit 8 OH UG 300/50 50 10 2.5 20 11 L.I. U.D.
Circuit 1 OH UG 95/50 185/50 40 5 5 14 U.D. U.D.
Circuit 2 OH UG 300 185/50 40 5 20 11 U.D. U.D.
Circuit 3 OH UG 95/50 185/50 30 5 5 14 L.I. U.D.
Module Circuit 4 OH UG 300/95 185/50 30 5 20 11 U.D. U.D.
2 Circuit 5 OH UG 95/50 185/50 15 2.5 5 14 L.I. U.D.
Circuit 6 OH UG 300/95 185/50 15 2.5 20 11 L.I. U.D.
Circuit 7 OH UG 95/50 185/50 10 2.5 5 14 U.D. U.D.
Circuit 8 OH UG 300/50 185/50 10 2.5 20 11 U.D. U.D.
10
It is assumed that all demand customers are connected at 0.4kV and is composed of
70% of residential customers without electrical heating, 10% of residential customers
with electrical heating, 10% of commercial customers and 10% of industrial
customers. The annual total load has a maximum of 225MW, a load factor of 0.55,
and a power factor of 0.98. Figure 1-1 below shows typical annual load profiles in
nine characteristic days used in the studies. Hourly and seasonal load variations were
captured and used for load flow analysis. This figure is obtained by aggregating
different type of loads, i.e. residential, industrial and commercial loads in the network.
Distribution of the loads along feeders was also modelled.
250
Winter days
200
Winter Saturday
Winter Sunday
150 Autumn/Spring days
MW Load
Autumn/Spring days
100 Autumn/Spring Sunday
Summer days
Summer Saturday
50
Summer Sunday
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Tim e
For capacities of 5GW and 7.5GW of DG installed over 50% of the GSPs in the UK,
less lines require upgrade when DGs are allocated along 2/3 of the circuits than over
1/3 of the circuits, because the capacity of DG installed per line in the first case is low
enough to not require reinforcement, whereas when the concentration increases a
larger number of reinforcements are required.
On the other hand, as the installed capacity of DG increases to 10GW in the UK, it is
the opposite case. The capacity of DG installed per line is such that most of the lines
where DG is installed require an upgrade, whatever the penetration density of DG.
The higher the density of DG as in scenario H, the lower the number of 11kV lines
which need to be upgraded. For the same reasons, when DG is installed over 50% of
the GSPs, the number of lines to be reinforced for any penetration of DG is higher for
high-density allocation of DG.
Similar comments can be made for 33/11kV substations and 33kV lines: for high
11
penetration of DG, the higher the generators concentration in the GSP network, the
lower the number of equipment to upgrade. However, the capacity upgrade required is
higher for high density of DG and the costs associated are higher, as will be shown in
the next sub-section.
6
Percentage of scheme to be replaced (%)
0
L (F&F) L (AM) LM LM HM HM H (F&F) H (AM)
(F&F) (AM) (F&F) (AM)
Penetration scenario (Management policy)
11kV lines 33/11kV transformers 33kV lines
9
Percentage of scheme to be replaced (%)
8
7
6
5
4
3
2
1
0
L (F&F) L (AM) LM LM HM HM H (F&F) H (AM)
(F&F) (AM) (F&F) (AM)
Penetration scenario (Management policy)
11kV lines 33/11kV transformers 33kV lines
12
18
The results obtained with this study also indicate that reinforcement of 11kV lines is
driven by voltage constraints as 11kV feeders are characterised by long overhead lines,
while the reinforcement of 33/11kV substations and 33kV lines is driven by thermal
constraints. As described in the figures above, active management has a positive
impact on the percentage of 11kV lines that need upgrading.
Since the unit cost of various assets is different, it is possible that the upgrade cost for
different cases are different although the percentage of circuits to be upgraded in the
associated cases are the same as presented in Figure 1-2-Figure 1-4. It can be
concluded that if passive approach remains to be used, it will drive more capital
investment and increase the cost for integrating DG.
13
200
180
160
140
Upgrade cost (M£)
120
100
80
60
40
20
0
L (F&F) L (AM) LM LM HM HM H (F&F) H (AM)
(F&F) (AM) (F&F) (AM)
Penetration scenario (Management policy)
250
Upgrade cost (M£)
200
150
100
50
0
L (F&F) L (AM) LM LM HM HM H H (AM)
(F&F) (AM) (F&F) (AM) (F&F)
Penetration scenario (Management policy)
14
450
400
Upgrade cost (M£) 350
300
250
200
150
100
50
0
L (F&F) L (AM) LM LM HM HM H H (AM)
(F&F) (AM) (F&F) (AM) (F&F)
Penetration scenario (Management policy)
11kV lines 33/11kV transformers 33kV lines
Table 1-6 Annuatised reinforcement cost and O&M cost in UK rural network
(M£ /year)
DG L LM HM H
Cost
capac AM AM AM AM AM AM AM AM
type PM PM PM PM
ity NI I NI I NI I NI I
2.5 Reinf 0 0 0 0 0 0 0 0 0 0 0 0
GW O&M 0 0 0 0 0 0 0 0 0 0 0 0
Reinf 0 0 0 11.89 0 0 11.89 0 0 22.47 9.06 7.93
5GW
O&M 0 0 0 0.17 0 0 0.17 0 0 0.31 0.13 0.11
7.5 Reinf 9.44 0 0 27.85 4.63 4.06 27.47 4.53 3.96 33.89 25.49 23.88
GW O&M 0.13 0 0 0.39 0.06 0.06 0.38 0.06 0.06 0.47 0.36 0.33
10 Reinf 22.94 0 0 45.5 18.12 15.95 44.18 16.99 15.01 53.05 37.19 35.49
GW O&M 0.32 0 0 0.64 0.25 0.22 0.62 0.24 0.21 0.74 0.52 0.50
15
200
180
L LM HM H
The second cost associated with active management is its implementation cost.
Implementation of generation curtailment necessitates the installation of voltage
measurement schemes at the generator point of connection as described in (Liew, S.N.,
2002). A reliable communication link between the terminal of the DG and the DSO
centre is also required. Besides, in a coordinated area-based voltage control,
measurements and communication are also required between a 33/11kV substation
and the DSO centre. In this study we suppose that the cost of active management is
flat irrespective of the considered level of DG penetration. This is because the cost of
active management is assumed for simplicity to be fixed, irrespective of the number
of feeders with voltage rise problems as long as there is at least one problem feeder.
In rural areas, the cost of implementing active management is therefore supposed to
be £10,000 per DG. In urban areas, the cost of implementing active management is
assumed £100,000 per substation. However, in practice, the cost of active
management has variable cost components and depending on the number of problem
feeders, the cost of enabling active management varies.
16
Table 1-7 Reinforcement cost (RC) of upgrading feeders and substations in rural
system (in M£) for Passive (PM) and Active (AM) management (considering the
intermittent and non-intermittent cases) and cost of implementing (CoI) active
management
Scenario ⇒ L LM HM H
DG capacity PM AM PM AM PM AM PM AM
⇓ RC RC CoI RC RC CoI RC RC CoI RC RC CoI
0 0 0 0
2.5GW 0 0 0 0
0 0 0 0
0 0 0 84
5GW 0 126 80 126 80 238 40
0 0 0 96
0 43 42 253
7.5GW 100 80 295 80 291 80 359 40
0 49 48 270
0 169 159 376
10GW 243 160 482 80 468 80 562 40
0 192 180 394
1400
1200
1000
Cost (M£)
800
600
400
200
0
2.5 5 7.5 10
Installed capacity (GW)
Passive rural network Active rural network
The benefits of active management are clearly illustrated in Figure 1-9 for each
penetration of DG. For an installed capacity of 5GW, up to 50% of the cost of
upgrading the system could be saved by applying active management, while this
figure varies between 15 and 40% for a penetration of 10 GW.
17
Table 1-7 also suggests that reinforcement costs required in the intermittent case are
smaller than for the non-intermittent case. This is due to the lower occurrence of the
worst-case situation of high output of DG at times of low demand in the intermittent
case.
Average system fault levels are assumed at each voltage level; 350MVA at 11kV and
1,000MVA at 33kV, and two different fault level headrooms available at each voltage
level are examined. The headroom is used to determine how much DG can be added
to various parts of the DSO networks before switchgear fault ratings are exceeded.
The two following cases are investigated:
Table 1-9 and Figure 1-10 provide the range of full cost of upgrading switchboards in
all the penetration scenarios of DG in urban systems. For active management, the cost
of implementing an active managed network is added to the cost of upgrading
switchboards. As for rural systems, the benefits of active management can be clearly
identified. For low DG penetration, more than half of reinforcement costs could be
saved by applying active management.
18
Table 1-9 Reinforcement cost of switchboards (RC) for two different headrooms for
passive (PM) and active (AM) management in urban system (in M£) and cost of
implementing (CoI) active management
Scenario ⇒ L LM HM H
DG PM AM PM AM PM AM PM AM
Head-
capacity RC RC CoI RC RC CoI RC RC CoI RC RC CoI
room
⇓
1400
1200
1000
Cost (M£)
800
600
400
200
0
2.5 5 7.5 10
Installed capacity (GW)
Passive urban network Active urban network
19
Table 1-10 Annuatised reinforcement cost and O&M cost in urban network with 0%
headroom (M£/year)
Cost
GW L(PM) L(AM) LM(PM) LM(AM) HM(PM) HM(AM) H(PM) H(AM)
type
Reinf 75.14 0 37.57 0 37.57 0 37.57 0
2.5
O&M 1.05 0 0.53 0 0.53 0 0.53 0
Table 1-11 Annuatised reinforcement cost and O&M cost in urban network with 10%
headroom (M£/year)
Cost
GW L(PM) L(AM) LM(PM) LM(AM) HM(PM) HM(AM) H(PM) H(AM)
type
Reinf 0 0 0 0 0 0 0 0
2.5
O&M 0 0 0 0 0 0 0 0
Reinf 0 0 0 0 0 0 37.57 0
5
O&M 0 0 0 0 0 0 0.53 0
The presence of DG at 11kV changes the flow patterns and therefore the losses
incurred in transporting electricity through transmission and distribution networks.
The first thought is that DG contributes to power loss reduction as the generation
energy flow is generally against the major net flow. This is, however, normally but
not necessarily true. The impact of DG on losses depends on the penetration and the
location of DG in the network as described in Figure 1-11 to Figure 1-14. Low
penetration of DG reduces the losses, as the generation is absorbed by local load,
20
which then reduces the flow in the 11kV feeder and in the voltage levels above.
However, as the penetration of DG increases, generation starts to exceed local
demand, particularly in low loaded lines and at time of low demand, leading to a
reverse flow in the 11kV feeders. This reverse flow increases the losses at 11kV and
in some cases at higher voltage levels too.
Figure 1-11 describes the behaviour of annual energy losses for the penetration
scenario where DG is allocated to 2/3 of the 11 kV circuits of 50% of the GSPs in the
UK. In that case, for any penetration of DG, the losses in the UK distribution network
are lower than when no DG is connected to the network, and a minimum in energy
losses is obtained for a DG penetration of 5GW. For low penetration of DG, active
management is not required since the system does not need any reinforcement.
However for high penetration of DG, the use of active management tends to increase
the losses since feeders have smaller sizes than for passive management. For a
penetration of 10GW, the corresponding increase in cost of losses is about 3M£/year
in the UK network assuming the electricity cost is 20£/MWh. 2
3.5
2.5
Losses (%)
1.5
0.5
0
0 2.5 5 7.5 10
Penetration of DG (GW)
Passive management Active management
Figure 1-11 Losses in UK’s distribution network (except for LV) for scenario L
Figure 1-12 and Figure 1-13 represent the losses for the penetration scenarios where
DG is allocated to 1/3 of the 11 kV circuits of 50% of the GSPs in the UK and DG is
allocated to 2/3 of the 11 kV circuits of 25% of the GSPs in the UK respectively. The
comments are generally similar to before: the losses for low penetrations of DG
(2.5GW and 5GW) are smaller than if no DG is connected to the network. However,
as the penetration increases the losses tend to increase in the UK distribution network.
Moreover, the losses in these two cases are higher than in the case with a less dense
penetration of DG. Similarly to the previous case, active management has a negative
impact on losses: energy losses increase by about 15% in the case of high penetration
of DG when active management is applied. However the corresponding increases in
cost of losses (about 15M£/year for a penetration of 10GW in scenario HM) do not
question the benefits of applying active management.
2
Cost of losses is calculated from the annual energy losses multiplied by the specified energy cost.
21
5
4.5
4
3.5
Losses (%)
3
2.5
2
1.5
1
0.5
0
0 2.5 5 7.5 10
Penetration of DG (GW)
Figure 1-12 Losses in UK’s distribution network (except for LV) for scenario LM
6
4
Losses (%)
0
0 2.5 5 7.5 10
Penetration of DG (GW)
Passive management Active management
Figure 1-13 Losses in UK’s distribution network (except for LV) for scenario HM
Figure 1-14 depicts the losses for the penetration scenario where DG is allocated to
1/3 of the 11 kV circuits of 25% of the GSPs in the UK, which corresponds to a high-
density penetration. In this scenario, any penetration of DG increases the losses in the
network. This rise can reach 100% when 10GW of DG is connected to the network.
22
10
9
8
7
Losses (%)
6
5
4
3
2
1
0
0 2.5 5 7.5 10
Penetration of DG (GW)
Passive management Active management
Figure 1-14 Losses in UK’s distribution network (except for LV) for scenario H
It is interesting to note that for high and dense penetrations of DG, the maximum flow
in GSPs occurs in times of low demand when power is exported from the distribution
network to the transmission network.
Similarly, the introduction of DG at 11kV in the network changes the flow in the
132/33kV substations. Table 1-13 describes the maximum flow in each 132/33kV
substation when DG is introduced at 11kV. When no DG is installed in the network,
the maximum flow is 55MVA.
23
Table 1-12 Maximum flow (in MVA) in GSP substations for GSPs with DG
Maximum flow (in MVA) in GSP substations
DG scenario
Low density High density
DG penetration
2.5GW 198 172
5GW 172 123
7.5GW 148 95
10GW 122 145
Table 1-13 Maximum flow (in MVA) in 132/33kV substations for GSPs with DG
Maximum flow (in MVA) in 132/33kV
substations
DG scenario
Low density High density
DG penetration
2.5GW 49 43
5GW 43 30
7.5GW 36 23
10GW 30 35
Using the figures in Table 1-12 and Table 1-13, one can derive the potential value (in
£M) of DG in replacing distribution network assets in the entire UK. These potential
benefits are presented in Table 1-14 in capitalised value.
24
1.9 Reduction of losses and provision of network capacity from
micro generation
The Engineering Recommendation G83/1 (ER G.83/1, 2003) defines the capacity
constraints recommendations for the connection of small scale embedded generators
in parallel with public low-voltage distribution networks up to 16A per phase,
equating 3.68kVA for a 230V single phase connection. Electricity from micro-
generation is both produced and consumed on the premises by technologies such as
micro wind, micro hydro, fuel cells, photovoltaics (PV) or micro combined heat and
power (micro CHP). In this research only micro CHP and photovoltaics were studied
because typical daily and seasonal energy outputs can be used for these two
technologies. In the working paper (Distributed Generation Coordination Group, 2004)
the different economic benefits delivered by micro generation are summarised as
follows:
• It will reduce emissions of COx, SOx, NOx and particulates
• It will reduce the total capacity needed within networks
• It will reduce the need for peak provision in electricity networks
• It will reduce power system losses
• It will deliver major energy efficiency gains
• It will reduce the amount of large-scale centralised generating capacity
The results presented below quantify the reduction of distribution energy losses and
the reduction in total capacity needed for different penetration scenarios of micro
CHP and PV in the UK distribution network. Therefore cases studies with
2.5%/5%/7.5%/10% of all UK customers with micro generation over 20%/50% of
GSPs in the UK are displayed.
1.9.1 Micro CHP
Combined Heat and Power (CHP) is the simultaneous production of electrical power
and useful heat. In the case the electrical power of domestic micro CHP is consumed
inside the host premises although any surplus or deficit is exchanged with the utility
distribution system. The heat generated by micro CHP is used for space heating inside
the host premises. Therefore the electrical energy output of micro CHP is driven by
the heat requirements of consumers. Figure 1-15 illustrates the normalised generation
profile of micro CHP used in this study where it was assumed the output of micro
CHP is nil during the summer. Furthermore, it was assumed that 25% of the
customers with micro CHP had a technology with a capacity of 3kW and 75% with a
capacity of 1.1kW.
25
1.2
0.4
0.2
0
0 5 10 15 20
Time (Hr)
Table 1-15 gives the annual energy losses and the maximum flow entering in the
distribution network for different proportion of customers with micro CHP allocated
to 50% of the GSPs in the UK, while Table 1-16 gives the same features when micro
CHP is allocated amongst only 20% of the GSPs in the UK. The increase in the
proportion of customers with micro CHP leads to a significant reduction in energy
losses (from 6.1% to 4.39% in the average network). This reduction is important
because the maximum output of micro CHP occurs at time of high customers demand
decreasing the transfer of power in the distribution network in times of high demand.
For the same reasons the maximum flow entering the GSP network decreases as the
capacity of micro CHP increases up to a point where the maximum flow entering the
network occurs in at a time when no electricity is produced by micro CHP (like in
summer for instance). Similarly to the comments made in section 2.8.2, and since
micro CHP generation coincides with peaks of demand, adding micro CHP generation
capacity at the low voltage end of the power system defers or removes the need for
new network capacity and reduce the utilisation of existing network. This leads
therefore to benefits to DSOs.
Table 1-15 Losses and maximum flow when micro CHP is allocated to 50% of GSPs
in the UK
Proportion of Losses in GSP with generation (%)/Losses in the Maximum
customers entire UK network (%) flow entering
Average Rural network Urban network the GSP (in
network MVA)
0% 6.1 8.69 4.47 251.3
2.5% 5.6 / 5.85 7.92 4.12 228.7
5% 5.16 / 5.63 7.24 3.8 206.5
7.5% 4.75 / 5.42 6.63 3.52 187.9
10% 4.39 / 5.24 6.09 3.36 187.9
26
Table 1-16 Losses and maximum flow when micro CHP is allocated to 20% of GSPs
in the UK
Proportion of Losses in GSP with generation (%)/Losses in the Maximum flow
customers entire UK network (%) entering the
Average Rural network Urban network GSP (in MVA)
network
0% 6.1 8.69 4.47 251.3
2.5% 4.93 / 5.86 6.92 3.72 195.4
5% 4.05 / 5.69 5.62 3.15 187.9
7.5% 3.48 / 5.57 4.78 2.78 187.9
10% 3.18 / 5.51 4.35 2.58 187.9
1.9.2 Photovoltaics
Photovoltaic generation corresponds to the direct conversion of sunlight to electricity.
Interest is now focused on incorporating the photovoltaic modules into buildings and
houses. Thus these small PV installations would be connected directly into customers’
circuits and so interface with the low-voltage distribution network. Figure 1-16
describes the normalised energy profile used in this study based on (Jenkins, N., 1995)
to model the output of PV. It is assumed that customers would have a module with a
capacity of 1kW.
1.2
Normalised electric generation of
0.8
0.6
PV (pu)
0.4
0.2
0
0 5 10 15 20
Time (Hr)
Summer Autumn/Spring Winter
Similarly to Table 1-15 and Table 1-16 for micro CHP, Table 1-17 and Table 1-18
describe the distribution losses for different penetrations of PV at 0.4kV. The impact
of PV on losses and on the provision of network capacity is less significant then the
impact of micro CHP. Indeed, PV in the UK produce electric energy in times of low
demand (during summer daytime), but not during peak demands such as the evening
of winter weekdays. Therefore the maximum flow entering the distribution network is
not affected by the installation of PV (251.3MVA in this example), and even if losses
decrease with higher penetrations of PV, the reduction is not significant.
27
Table 1-17 Losses and maximum flow when PV is allocated to 50% of GSPs in the
UK
Proportion of Losses in GSP with generation (%)/Losses in the Maximum
customers with entire UK network (%) flow entering
PV Average Rural network Urban network the GSP (in
network MVA)
0% 6.1 8.69 4.47 251.3
2.5% 5.93 / 6 8.39 4.33 251.3
5% 5.74 / 5.92 8.12 4.2 251.3
7.5% 5.57 / 5.83 7.86 4.09 251.3
10% 5.41 / 5.75 7.62 3.98 251.3
Table 1-18 Losses and maximum flow when PV is allocated to 20% of GSPs in the
UK
Proportion of Losses in GSP with generation (%)/Losses in the Maximum
customers with entire UK network (%) flow entering
PV Average Rural network Urban network the GSP (in
network MVA)
0% 6.1 8.69 4.47 251.3
2.5% 5.65 / 6.01 7.98 4.15 251.3
5% 5.26 / 5.93 7.4 3.88 251.3
7.5% 4.95 / 5.87 6.93 3.65 251.3
10% 4.71 / 5.82 6.58 3.5 251.3
From Table 1-19 and Table 1-20, we can see that for each DG capacity, in the low
and medium DG penetration density cases, the incremental cost can be reduced
significantly if active network is applied. While with high penetration level, e.g. for
10GW H penetration scenario, the incremental cost is similar or larger in active
management comparing with passive management taking into account the
implementation cost of active management.
28
Table 1-19 Incremental cost for assets reinforcement with passive (PM) and active
(AM) management for various DG penetration scenarios for rural networks (£/kW)
Scenario L LM HM H
⇒
DG PM AM PM AM PM AM PM AM
capacity
⇓ IC IC CoI IC IC CoI IC IC CoI IC IC CoI
0 0 0 0
2.5GW 0 0 0 0
0 0 0 0
0 0 0 0 16.8
5GW 0 25 16 25 16 48 8
0 0 0 0 19.2
0 5.7 5.6 33.7
7.5GW 13.3 10.7 39.3 10.7 39 10.7 47.9 5.3
0 6.5 6.4 36
0 16.9 15.9 37.6
10GW 24.3 16 48 8 47 8 56 4
0 19.2 18 39.4
Table 1-20 Incremental cost for assets reinforcement with passive (PM) and active
(AM) management for various DG penetration scenarios for urban networks (£/kW)
Scenario ⇒ L LM HM H
DG PM AM PM AM PM AM PM AM
capacity Head-
⇓ room IC IC CoI IC IC CoI IC IC CoI IC IC CoI
0% 318.4 0 159.2 0 159 0 159.2 0
128 64 64 32
2.5GW 10% 0 0 0 0 0 0 0 0
0% 159.2 0 79.6 0 79.6 0 79.6 0
64 32 32 16
5GW 10% 0 0 0 0 0 0 79.6 0
0% 106.1 0 53.1 0 164 57.5 55.3 55.3
42.7 21.3 21.3 10.7
7.5GW 10% 0 0 53.1 0 164 57.5 55.3 55.3
0% 79.6 0 39.8 0 123 43.1 101.2 101
32 16 16 8
10GW 10% 0 0 39.8 0 123 43.1 101.2 101
Table 1-21 gives the incremental benefit of DG on network capacity replacement, the
value is on average around 76 £/kW for all the cases except the case of 10GW
penetration with high density level due to large reversed power flow.
29
section 2.9.2, the maximum power flow does not change with PV installation to the
network for each scenario. The incremental value of PV on network capacity
replacement is zero and the table is ignored here.
30
2 Effect of DG connections on Finnish distribution
network
2.1 Finnish generic distribution network models
In order to estimate the costs and benefits of DG connections to Finnish distribution
grid, a number of analysis have been conducted for various DG penetration and
concentration levels. Studies were performed on generic one-GSP distribution
network models. These generic models use several typical circuit parameters, e.g.
conductor sizes, lengths, impedances, costs etc. In developing the generic models,
different characteristics of networks for different voltage levels and for different
network types (rural and urban) are considered, in which the parameters of the
networks are obtained from VTT (Technical Research Centre of Finland).
Finnish distribution networks comprise three operating voltage levels: 110kV, 20kV
and 0.4kV. In developing the generic network models, 110kV networks are excluded
from the model for simplicity. Focus of the studies was on the 20 kV and 0.4 kV
networks where a number of technical issues will arise with high DG penetrations. It
is envisaged that less effect of technical issues DG will bring to the 110 kV networks.
Finnish distribution networks are a mix of urban and rural type networks including
both short 20 kV feeders in city areas and long overhead line feeders in surrounding
areas. In deriving the parameters for the generic models, the Southern Finland is
considered as urban area and the rest of Finland as rural. In total, there are 32 GSPs
for rural and 14 GSPs for urban networks respectively.
In the next sections, models for 0.4kV and 20kV networks are described in more
details.
In total there are 10,040 0.4kV circuits included for the rural model and all of them
are Aerial Cables (AC) lines with an average length of 0.5km for each circuit. For the
urban network model, there are 3135 circuits with an average length of 0.3km for
each circuit, among which 2885 circuits are underground (UG) cables and the rest are
AC lines.
31
In the studies, a number of different conductor types and sizes are available to be used
in the model specifically if 0.4 kV circuits need to be reinforced during the studies.
The size and impedance of various circuits considered in the model are listed below:
Table 2-2 Parameters of 0.4kV circuits for 0.4kV rural and urban network models
Network Cross section
R(Ω/km) X(Ω/km) Type
area (mm2)
16 2.060 0.090 AC
35 0.938 0.104 AC
Rural 50 0.693 0.101 AC
70 0.479 0.097 AC
120 0.273 0.092 AC
70 0.479 0.097 AC
Urban 185 0.182 0.082 UG
240 0.135 0.135 UG
In total there are 100 and 108 20kV circuits for rural and urban network models
respectively. In the generic rural network model the circuit length ranges from 15km
to 70km and in urban network model all the circuits are 5km in length.
In the studies, a number of different conductor sizes are available to be used in the
model specifically if 20 kV circuits need to be reinforced during the studies. The size
and impedance of various circuits considered in the model are summarised in Table
2-4, where OH and UG for circuit type stand for over head and underground
respectively.
32
Table 2-4 Parameters of 20kV circuits for rural and urban networks
Cross section
Network area R(Ω/km) X(Ω/km) Type
(mm2)
34/6 0.847 0.383 OH
54/9 0.535 0.368 OH
Rural 85/14 0.337 0.354 OH
132 0.218 0.344 OH
PAS 70 0.493 0.533 OH
54/9 0.535 0.368 OH
85/14 0.337 0.354 OH
Urban
185 0.169 0.119 UG
240 0.130 0.116 UG
In these studies, the 0.4kV peak load in one rural GSP network is 95MW and 10MW
for 20kV taking into account the diversity of various load types. The 0.4 kV peak load
are 140MW and 80MW for 20kV in an urban GSP network.
Figure 2-1 and Figure 2-2 show the characteristic day load profiles used in the studies
for rural and urban networks. The profiles are obtained by aggregating the value of
various load types at each hour. With different load distribution among different
customer types, it is expected that the load profiles for rural and urban networks are
different.
33
120
100
winter weekdays
Winter Saturdays
80
Winter Sundays
Load MW
Spring/Autumn weekdays
60
Spring/Autumn Saturdays
40 Spring/Autumn Sundays
13
15
17
19
21
23
1
Time (hour)
Winter Saturdays
Winter Sundays
150
Load MW
Spring/Autum n weekdays
Spring/Autum n Saturdays
100
Spring/Autum n Sundays
Sum m er weekdays
50
Sum m er Saturdays
Sum m er Sundays
0
11
13
15
17
19
21
23
1
Time (hour)
Case 1 represents a very similar condition with the present situation where the total
installed DG capacity at 20kV and 0.4kV networks is around 800 MW and distributed
across rural and urban almost equally. Considering the growth of DG in the future
will be higher in rural networks than that in urban networks, other three DG
penetration scenarios namely Case 2, 3 and 4 for rural and urban networks
34
respectively were determined. All the four cases are summarised in Table 2-5. The
last row in Table 2-5 illustrates the ratio between DG penetration and the network
peak load considering the peak load for customers connected to 20 kV and 0.4 kV is
around 6.5GW 3.
Table 2-5 Total DG installed capacity for rural and urban networks
Network area DG installed capacity(MW)
Case 1 Case 2 Case 3 Case 4
Rural 445 490 580 670
Urban 422.5 445 490 535
DG/peak load 13.5% 14.5% 16.6% 18.7%
2.2.2 Allocation of DG
In these studies, we assume all the proposed DGs are medium size DGs and they are
connected at 20kV networks.
It should be noticed that the effect of DG in one GSP network will depend on the
distribution of DG across the network.
3
Source: VTT
35
2.2.3 Application of suitable network models for addressing different issues
The installation of relatively high DG capacity to distribution networks may trigger a
number of technical problems such as voltage rise issues, inadequacy of thermal
capacity and the increase in fault level. In order to alleviate network problems,
network reinforcement becomes necessary. The reinforcement will incur some costs
that need to be minimised.
For voltage rise problem, the studies were conducted only using a rural GSP network
model since the problem mainly occurs in weak rural networks characterised by long
20kV overhead circuits with small diameters. And for investigating network
reinforcement issue due to fault level increase the studies used the urban GSP network
model.
On the other hand, connection of DG may also incur additional costs due to network
capacity reinforcement, new investment in control and communication equipments to
enable active network management and increases in distribution system losses
especially when DG output increases flows etc. The costs can be quantified by
identifying and calculating the cost of upgrading network assets required to facilitate
DG connections while maintaining security and operating constraints in distribution
systems.
The following sections will describe the results for studies conducted on the Finnish
generic network models.
36
2.3 Benefits of active management
In these studies, the costs and benefits of implementing passive and active network
management to facilitate DG connections according to aforementioned scenarios are
quantified. The studies were performed on the urban and rural generic network
models. The benefits of active management were derived from the saving obtained in
the capital investment with reference to the costs when passive networks were applied.
While the cost of active and passive management is quantified by determining the
cost of reinforcing assets which need to be updated to support load or DG connections.
For active management, the cost of control and communication infrastructure is also
added.
Results of case studies performed on the generic rural network for quantifying the
benefits of active management in solving voltage rise problems due to DG
connections are described in this section. Figure 2-3 and Figure 2-4 illustrate the
percentage of 20kV feeders that need to be reinforced to curb the voltage rise effect of
DG connections for different DG penetration scenarios with passive (PM) and active
network management (AM) philosophies. In Finland, the range of statutory voltage
change limit is ±5% for 20 kV networks (SFS, 2003). Since DG penetration scenario
of 445MW and 490MW demonstrate the same impact on updated feeder number, the
results in these two scenarios are shown using the same Figure 2-3. And the same
situation is for 580MW and 670MW scenarios shown as Figure 2-4.
The results presented are for the whole Finnish rural networks. Using passive
management, the ratio of circuits that need to be upgraded varies between 0 % and 9%.
While using active management, the ratio varies between 0% and 4.5%. There will be
no circuit reinforcement required if the DG penetration level is relatively low. The
highest requirement for reinforcement occurs when passive management is applied to
facilitate the connection of 580MW and 670MW LM DG scenarios. In these two
cases, the number of violated feeders is the highest ones comparing with other cases.
It is expected that higher DG penetration level triggers more problems and higher
reinforcement costs.
37
7
r i se pr obl ems
5
occur ( %)
4
0
PM AM
Oper at i on Phi l osophy
L LM HM H
Figure 2-3 The percentage of 20kV feeders upgraded to facilitate connection of
445MW/490MW DG in Finnish rural networks
10
9
f eeder s wi t h vol t age
Per cent age of 20 kV
8
r i se pr obl ems( %)
7
6
5
4
3
2
1
0
PM AM
Oper at i on Phi l osophy
L LM HM H
Figure 2-4 The percentage of 20kV feeders upgraded to facilitate connection of
580MW/670MW DG in Finnish rural networks
In Figure 2-4, the lowest requirement to reinforce 20kV circuits with passive
management occurs at HM scenario. In this case the ratio of 20 kV circuits that need
to be reinforced per GSP is similar as the ratio for the LM case, but because DG in
HM case is located in smaller number (25%) of rural GSPs compared with LM case
(50% of rural GSPs), the total number of circuits that need to be reinforced becomes
less.
The results also demonstrate that active operation regime for example by optimising
tap changer positions and/or by curtailing temporarily generation output will be able
to reduce the requirement to reinforce circuits due to voltage problems. In Figure 2-3
and Figure 2-4 for AM case, there is no circuit reinforcement required for the first
three cases (L, LM and HM). However, if the technical problems raised by DG cannot
be solved economically using active management , for example if the DG needs to be
constrained off too often, a combined active management approach and circuits
reinforcement will be the optimum solution as shown in H scenario. In all cases, it can
be concluded that by using active management, the number of circuits that need to be
reinforced to solve voltage rise problems can be reduced.
38
Capacity reinforcement cost for rural networks
The results of the studies presented in Figure 2-5 to Figure 2-8 show the total Finnish
reinforcement costs for 20kV circuits under both passive and active management and
also for the non-intermittent/intermittent generation case. The costs shown in those
figures correspond to the number of circuits that need to be replaced mentioned in the
previous section.
It is shown in Figure 2-5 and Figure 2-6 that in most of the cases, reinforcement cost
can be avoided by implementing active network management. Even for high DG
concentration (scenario H), significant saving can be achieved if active management
is implemented. Figure 2-5 and Figure 2-6 also demonstrate that intermittent DG will
drive less capacity than non intermittent DG. Thus in both figures, the reinforcement
cost for intermittent DG is always less than the reinforcement cost incurred by non
intermittent DG. It is expected that intermittent generation will drive less investment
since the worst case condition, i.e. when the high output of DG coincides with low
demand conditions, tends to be less frequent.
120
Reinforcement Cost (M€)
100
80
60
40
20
0
445_L 445_LM 445_HM 445_H
DG penetration scenarios
PM AM(Non-Intermittent case) AM(Intermittent case)
39
Reinforcement cost for 490MW DG installation
120
80
60
40
20
0
490_L 490_LM 490_HM 490_H
DG penetration scenarios
PM AM(Non-Intermittent case) AM(Intermittent case)
120
Reinforcement Cost (M€)
100
80
60
40
20
0
580_L 580_LM 580_HM 580_H
DG penetration scenarios
PM AM(Non-Intermittent case) AM(Intermittent case)
120
Reinforcement Cost (M€)
100
80
60
40
20
0
670_L 670_LM 670_HM 670_H
DG penetration scenarios
PM AM(Non-Intermittent case) AM(Intermittent case)
40
Operation and maintenance costs
In order to calculate the annuitised reinforcement cost, it is assumed that the time
scale to fully recover the capital investment is approximately 20 years with 7% rate of
return. Table 2-7 lists the cost of each rural 20kV circuit reinforcement options 4 .
Table 2-8 summarises the annuatised reinforcement cost and O&M cost.
The O&M cost of previous studies is presented in Figure 2-9 to Figure 2-12. Except
for the O&M cost for scenario with intermittent DG (I), which is indicated specially,
all the values of O&M costs are for case studies associated with non intermittent DG.
The O&M cost for case with intermittent DG only occurs for case studies associated
with scenario H (except for 445MW case) while for other scenarios, the cost is zero
(Table 2-8).
Table 2-7 Unit investment cost (capitalised) and O&M cost of 20kV circuits for rural
networks
Circuit type Investment cost (€/km) O&M cost(€/km/year) O&M cost / investment cost
34/6 6,216 191 3.07%
54/9 8,316 191 2.30%
85/14 9,906 191 1.93%
132 11,375 191 1.68%
PAS 70 13,970 177 1.27%
Table 2-8 Annuatised reinforcement cost and O&M cost for rural networks (M€/year)
DG Cost L LM HM H
capacity type (PM) (AM) (PM) (AM) (PM) (AM) (PM) (AM) (AM/I)
Reinf 0 0 6.28 0 6.57 0 9.91 3.14 0
445MW
O&M 0 0 1.28 0 1.50 0 1.83 0.64 0
Reinf 0 0 6.62 0 7.33 0 9.91 3.14 1.70
490MW
O&M 0 0 1.28 0 1.50 0 1.83 0.64 0.41
Reinf 7.91 0 9.63 3.39 7.72 0 10.47 4.82 2.82
580MW
O&M 1.93 0 2.02 0.83 1.50 0 2.02 1.01 0.64
Reinf 7.91 0 10.23 5.64 7.72 3.96 10.74 5.11 4.65
670MW
O&M 1.93 0 2.02 1.29 1.50 0.96 2.02 1.01 1.01
4
Source : VTT
41
14
Annuatised cost(M€/year)
12
10
Figure 2-9 Annuatised reinforcement and O&M cost with 445MW DG installation for
Finnish rural networks
14
Annuatised cost(M€/year)
12
10
0
L(PM) L(AM) LM(PM) LM(AM) HM(PM) HM(AM) H(PM) H(AM) H(AM/I)
Figure 2-10 Annuatised reinforcement and O&M cost with 490MW DG installation
for Finnish rural networks
42
14
Annuatised cost(M€/year) 12
10
0
L(PM) L(AM) LM(PM) LM(AM) HM(PM) HM(AM) H(PM) H(AM) H(AM/I)
Figure 2-11 Annuatised reinforcement and O&M cost with 580MW DG installation
for Finnish rural networks
14
12
Annuatised cost(M€/year)
10
0
L(PM) L(AM) LM(PM) LM(AM) HM(PM) HM(AM) H(PM) H(AM) H(AM/I)
Figure 2-12 Annuatised reinforcement and O&M cost with 670MW DG installation
for Finnish rural networks
2.3.2 Studies on the generic urban network
Results of case studies performed on the generic urban network model for quantifying
the benefits of active management in solving fault level problems due to DG
connections are described in this section. Several methods of fault level reduction are
described in (Wu, X., 2003). Splitting network is the common and cheaper option in
practice and was used as the active operation approach for urban network case studies.
Average system fault level at 20kV urban network is about 80MVA and it is assumed
as the switchboard rating in 110kV/20kV substations. The studies assume that all
generator contribution to fault level is five times the rating of the generator.
43
Two different fault level head-rooms were examined:
• 0% headroom: in this case the introduction of DG at 20kV requires the
upgrade of the switchgear in the 110/20 kV substation.
• 10% headroom: in this case the introduction of DG at 20kV requires the
upgrade of the switchgear in the 110/20 kV substation only if its contribution
to fault level is 10% above of the switchgear rating.
Figure 2-13 and Figure 2-14 shows the percentage of switchboards that need to be
updated in the whole Finnish urban networks for these two cases: 0% headroom case
and 10% headroom case with passive and active management.
35
Percent of switchboard need to be
30
25
reinforced(%)
20
15
10 `
0
422.5MW(PM) 422.5MW(AM) 445MW(PM/AM) 490MW(PM/AM) 535MW(PM/AM)
L LM HM H
35
Percent of switchboard need to be
30
25
reinforced(%)
20
15
10
0
422.5MW(PM/AM) 445MW(PM/AM) 490MW(PM/AM) 535MW(PM/AM)
L LM HM H
44
Except for the 422.5MW L penetration scenario in 10% headroom case, the number
of overloaded switchboard is reduced by applying AM comparing with PM, the
number doesn’t change with the same density level of different DG capacity in other
cases. This is because in these cases the proposed DG capacity for urban network will
trigger all the switchboards overloaded irrespective of penetration scenarios,
management policies and headrooms. Since the number of overloaded switchboard
and the number GSPs with DG are both the highest among all the scenarios, the
maximum percentage value occurs at L scenario. Same changing trend will occur for
later reinforcement cost figures for the same reason.
Figure 2-15 and Figure 2-16 show the effect of various DG penetration levels on fault
level (FL) increment on urban 20kV networks ( there are two types for Finnish 20kV
network model which is respectively named model 1 and model 2 – see Table 2-3 )
with two headrooms cases and two different management philosophies. The highest
FL increment occurs in 0% headroom case with passive management for each DG
penetration scenario. Also the Figures show clearly that active management can
reduce FL increase dramatically for any DG penetration scenario in both headroom
cases.
160
Fault level increment due to
140
120
100
DG (MVA)
80
60
40
20
0
42 M
44 M
49 M
LM
HM
HM
HM
M
H
L
H
L
53 L
5_
5_
5_
0_
5_
H
L
5_
0_
5_
5_
5_
0_
5_
5_
5_
0_
5_
2.
44
49
53
2.
44
49
53
44
49
2.
42
53
2.
42
42
DG penetration scenarios
0% HR (PM) 0% HR (AM) 10% HR (PM) 10% HR (AM)
45
200
120
(MVA)
100
80
60
40
20
0
M
LM
LM
LM
LM
HM
HM
HM
H
L
H
L
L
5_
5_
5_
0_
5_
5_
0_
5_
5_
5_
0_
5_
5_
5_
0_
5_
2.
44
49
53
2.
44
49
53
44
49
53
2.
44
49
53
42
2.
42
42
42
DG penetration scenarios
0% HR (PM) 0% HR (AM) 10% HR (PM) 10% HR (AM)
10.0
8.0
6.0
4.0
2.0
0.0
422.5_L 422.5_LM 422.5_HM 422.5_H
DG penetration scenarios
0% HR (PM) 0% HR (AM) 10% HR (PM) 10% HR (AM)
Figure 2-17 Reinforcement cost with 422.5MW DG installation for urban networks
46
12.0
8.0
6.0
4.0
2.0
0.0
445_L 445_LM 445_HM 445_H
DG penetration scenarios
0% HR (PM) 0% HR (AM) 10% HR (PM) 10% HR (AM)
Figure 2-18 Reinforcement cost with 445MW DG installation for urban networks
14.0
Reinforcement Cost (M€)
12.0
10.0
8.0
6.0
4.0
2.0
0.0
490_L 490_LM 490_HM 490_H
DG penetration scenarios
0% HR (PM) 0% HR (AM) 10% HR (PM) 10% HR (AM)
Figure 2-19 Reinforcement cost with 490MW DG installation for Finnish urban
networks
14.0
Reinforcement Cost (M€)
12.0
10.0
8.0
6.0
4.0
2.0
0.0
535_L 535_LM 535_HM 535_H
DG penetration scenarios
0% HR (PM) 0% HR (AM) 10% HR (PM) 10% HR (AM)
Figure 2-20 Reinforcement cost with 535MW DG installation for Finnish urban
networks
47
Table 2-9 Annuatised reinforcement cost and O&M cost in urban network with 0%
headroom (M€/year)
MW L(PM) L(AM) LM(PM) LM(AM) HM(PM) HM(AM) H(PM) H(AM)
Reinf 0.95 0.25 0.95 0.36 0.95 0.34 0.95 0.41
422.5
O&M 0.10 0.10 0.05 0.05 0.06 0.06 0.03 0.03
Table 2-10 Annuatised reinforcement and O&M cost in urban network with 10%
headroom (M€/year)
MW L(PM) L(AM) LM(PM) LM(AM) HM(PM) HM(AM) H(PM) H(AM)
Reinf 0.75 0.05 0.85 0.26 0.83 0.23 0.89 0.35
422.5
O&M 0.10 0.10 0.05 0.05 0.06 0.06 0.03 0.03
Curtailment of DG output
Table 2-11 shows the results of the studies with reference to the energy curtailed for
various DG penetration levels and for non-intermittent (NI) and intermittent (I) cases.
48
derived as shown in Figure 2-21 and Figure 2-22 respectively for non intermittent and
intermittent cases.
In most of these cases, higher energy curtailed is required for studies with intermittent
DG compared with the energy curtailed for studies with non-intermittent DG. The
reason is that in non-intermittent case, considering energy curtailments limit (0.5% of
total output), it is more economic to reinforce and replace a number of circuits with
larger conductor sizes rather than curtailing energy to mitigates the voltage rise
problems. However, this indicates that the less energy curtailment obtained is at the
expense of higher assets investment cost.
1.4
because of curtailment (M€)
1.2
Energy revenue loss
0.8
0.6
0.4
0.2
0
445 490 580 670
DG installed capacity(MW)
L LM HM H
2
1.8
of curtailment (M€)
1.6
1.4
1.2
1
0.8
0.6
0.4
0.2
0
445 490 580 670
DG installed capacity(MW)
L LM HM H
AM implementation cost
Using the assumption as the UK case studies, the cost for implementing active
management is supposed to be €14,582.4 per DG scheme for Finnish rural networks
and €145,824 per substation for urban networks. Table 2-12 and Table 2-13 represent
49
the capitalised cost of implementing active management in the Finnish rural and urban
networks.
Table 2-12 Total capital cost (M€) for AM implementation at Finnish 20kV rural
networks
DG penetration level
DG scenario
445 MW 490 MW 580 MW 670 MW
Table 2-13 Total capital cost for AM implementation at Finnish 20kV urban networks
DG Total cost for AM
scenario implementation(M€)
L 8.17
LM 4.08
HM 4.67
H 2.33
The total investment costs in 445MW, 490MW and 580MW L penetration scenarios
are zero and not included in Figure 2-23. This figure can indicate clearly the value of
AM in Finnish rural networks. 38% to 90% investment cost can be saved if the
operation philosophy is changed from passive to active. The results (Figure 2-23) also
demonstrate that intermittent DG will drive less investment.
50
140
120
Total cost(M€)
100
80
60
40
20
0
44 M
HM
49 M
HM
58 M
HM
67 M
HM
49 H
58 H
H
67 L
L
L
L
5_
0_
0_
0_
0_
0_
5_
5_
0_
0_
0_
0_
0_
44
49
58
67
67
44
DG penetration scenarios
PM AM ( NI ) AM ( I )
Figure 2-23 Total investment cost with PM and AM philosophy in Finnish rural
networks
For the case studies on the generic urban network models for 422.5MW and 445MW
L DG scenarios and for two different headrooms cases, the total investment costs with
AM exceed those under PM philosophy because the reduction in the reinforcement
cost is less than the implementation cost of the active management. For other
scenarios, implementation of active management has clear benefits with reference to
the reduction of total investment cost. This situation is shown in Figure 2-24.
14
Total investment costs (M€)
12
10
0
H
H
42 _LM
H
H
42 M
HM
M
44 L
49 L
53 L
42 5 _L
44 M
49 M
53 M
5_
0_
5_
5_
0_
5_
5_
H
H
L
5_
0_
5_
5_
0_
5_
5_
2.
44
49
53
2.
44
49
53
5
2.
42
2.
DG penetration scenarios
0% HR ( PM) 0% HR ( AM) 10% HR ( PM) 10% HR ( AM)
Figure 2-24 Total investment costs in the studies on the generic urban network with
PM and AM and two different headroom cases
51
networks. The reinforcement cost strongly depends on the number of models and
GSPs which have DG. Due to the AM implementation costs, except in the special
case mentioned above where AM leads to reduced reinforcement costs, all other cases
indicate that for Finish urban networks modified using the assumption described
above, AM will result in more reinforcement costs than PM.
Figure 2-25 to Figure 2-28 show the impact of DG connections for various scenarios
on distribution network losses. The results are obtained for the case studies with non
intermittent DG. For scenario L with 445MW installed capacity, DG contributes to
the less energy flows from transmission and hence reduces distribution losses.
However, for a large penetration of DG, the losses increase due to the increase in
reverse power flows.
These figures as well as the later figures in intermittent case also show that losses in
the active network tend to be larger than those in the passive network since circuits in
the active network tend to be smaller in size, which consequently leads into higher
losses.
52
3.9
3.8
3.7
3.6
Losses(%) 3.5
3.4
3.3
3.2
3.1
0 445 490 580 670
DG Installed Capacity(MW)
PM AM
Figure 2-25 Losses in the rural distribution networks for scenario L (non-intermittent
DG)
p
6.0
5.0
4.0
Losses(%)
3.0
2.0
1.0
0.0
0 445 490 580 670
DG Installed Capacity (MW)
PM AM
Figure 2-26 Losses in the rural distribution networks for scenario LM (non-
intermittent DG)
5.0
4.5
4.0
3.5
Losses(%)
3.0
2.5
2.0
1.5
1.0
0.5
0.0
0 445 490 580 670
DG Installed Capacity(MW)
PM AM
Figure 2-27 Losses in the rural distribution networks for scenario HM (non-
intermittent DG)
53
p
7.0
6.0
5.0
Losses(%)
4.0
3.0
2.0
1.0
0.0
0 445 490 580 670
DG Installed Capacity(MW)
PM AM
Figure 2-28 Losses in the rural distribution networks for scenario H (non-intermittent
DG)
Considering intermittent case will abate the effect of DG with higher penetration level
on losses increase, it is assumed that losses in intermittent case are 0.9 of losses in
non-intermittent case for ‘H’ and ‘LM’ penetration scenarios. Conversely, it will
decrease the contribution of DG with lower penetration level on the reduction of
losses. We use experimental data 1.1 to multiply losses in non-intermittent case for
‘HM’ and ‘L’ penetration scenarios to get losses value in intermittent case. These
factors adjust the losses percentage and hence form the changing tendency with
various DG installed capacities in intermittent case shown as Figure 2-29 to Figure
2-32.
4.1
4.0
3.9
3.8
Losses(%)
3.7
3.6
3.5
3.4
3.3
3.2
3.1
0 445 490 580 670
DG Installed Capacity(MW)
PM AM
Figure 2-29 Losses in rural distribution network for scenario L (intermittent DG)
54
5.0
4.5
4.0
3.5
Losses(%)
3.0
2.5
2.0
1.5
1.0
0.5
0.0
0 445 490 580 670
DG Installed Capacity(MW)
PM AM
Figure 2-30 Losses in rural distribution network for scenario LM (intermittent DG)
6.0
5.0
4.0
Losses(%)
3.0
2.0
1.0
0.0
0 445 490 580 670
DG Installed Capacity(MW)
PM AM
Figure 2-31 Losses in rural distribution network for scenario HM (intermittent DG)
6.0
5.0
4.0
Losses(%)
3.0
2.0
1.0
0.0
0 445 490 580 670
DG Installed Capacity(MW)
PM AM
Figure 2-32 Losses in rural distribution network for scenario H (intermittent DG)
Figure 2-33 and Figure 2-34 summarise the Finnish rural network losses due to the
penetration of non-intermittent / intermittent DGs for various scenarios applied in the
networks with active and passive operation philosophies.
55
5.5
5.0
4.5
4.0
Losses(% ) 3.5
3.0
2.5
2.0
1.5
1.0
0.5
0.0
0 445(NI) 445(I) 490(NI) 490(I) 580(NI) 580(I) 670(NI) 670(I)
DG Installed CapacityMW(Output Cases)
Without DG L LM HM H
Figure 2-33 Losses in the rural passive distribution networks for non-
intermittent/intermittent cases with various DG penetration scenarios
7.0
6.0
5.0
Losses (%)
4.0
3.0
2.0
1.0
0.0
0 445(NI) 445(I) 490(NI) 490(I) 580(NI) 580(I) 670(NI) 670(I)
DG Installed CapacityMW(Output Cases)
Without DG L LM HM H
Figure 2-34 Losses in the rural active distribution networks for non-
intermittent/intermittent cases with various DG penetration scenarios
Figure 2-35 and Figure 2-36 shows the losses in the generic Finnish urban networks in
non-intermittent and intermittent case respectively. The results for intermittent case
were obtained using the adjusting factor mentioned in rural network case studies.
Since splitting networks is realised by opening the circuit breakers located between
two lower voltage busbars of transformers, the impedance of system between primary
and secondary voltage level will be doubled (Wu, X., 2003). For scenario L, the
losses decrease but start to increase with more DG installed and higher allocation
density.
56
4.5
3.5
3
Loses (%)
2.5
1.5
0.5
0
0 422.5 445 490 535
DG Installed Capacity(MW)
Without DG L LM HM H
Figure 2-35 Urban network losses with various DG penetration scenarios (Non-
Intermittent case)
4.5
4
3.5
3
Losses(%)
2.5
2
1.5
1
0.5
0
0 422.5 445 490 535
DG installed capacity(MW)
Without DG L LM HM H
Figure 2-36 Urban network losses with various DG penetration scenarios (Intermittent
case)
57
Figure 2-37 illustrates the computed maximum power flows measured at the
110kV/20kV substation for various DG penetration scenarios on the generic Finnish
active and passive rural network. Maximum power flows in H density level for all
DG capacity scenarios are larger than the flow in the case without DG. In other cases
the benefit from DG on network capacity replacement can be realised.
14. 00
Maximum power flow (MVA)
12. 00
Wi t hout DG
10. 00 445MW( PM)
490MW( PM)
8. 00 580MW( PM)
670MW( PM)
6. 00
445WM( AM)
4. 00 490WM( AM)
580WM( AM)
2. 00 670WM( AM)
0. 00
L LM HM H
Penetration Scenario
Figure 2-37 Maximum power flow in one 110kV/20kV substation which has DG with
various DG penetration scenarios for AM and PM philosophy in rural model
Also from the curve we can see maximum power flow for each scenario with active
management is smaller than that with passive management but not in a large amount
in magnitude because of energy curtailment limits for active management.
With above maximum power flow value and unit cost for assets, potential benefit of
DG (M€) on replacing distribution network assets (110kV/20kV transformer) are
assessed in Table 2-15.
Positive values mean the Capex will decrease in the corresponding cases. Negative
values in H scenario indicate opposite effect of DG on Capex reduction. For L
scenario, the value of DG on assets replacement tends to increase with DG capacity
increase. For LM and HM cases, it decreases because the excess of maximum flow in
these scenarios over this value of non-DG case in substation becomes bigger in
magnitude with DG capacity increase.
58
Figure 2-38 and Figure 2-39 show maximum flow at different substations (model 1
and model 2) in the generic urban network respectively. Table 2-16 represents the
potential benefit of DG on replacing urban network assets.
Maximum power flow (MVA) 25
20
15 Wi t hout DG
422. 5MW
445MW
10
490MW
535MW
5
0
L LM HM H
Penetration Scenario
Figure 2-38 Maximum power flow in one 110kV/20kV substation (model 1) which
has DG for urban network
35
Maximum power flow (MVA)
30
25
Wi t hout DG
20 422. 5 MW
450MW
15 490MW
535MW
10
0
L LM HM H
Penetration Scenario
Figure 2-39 Maximum power flow in one 110kV/20kV substation (model 2) which
has DG for urban network
The potential benefit of DG on network assets replacement in urban area varies from
0.16M€ to 5.13M€ according to various DG penetration levels except H density level
with 445MW to 535MW capacity scenarios, in which DG causes more network
capacity requirement than non-DG case,.
59
2.6 Effect of micro or mini generation on Finnish distribution
network losses reduction and network capacity replacement
In Finland, several micro or mini generation technologies i.e. small hydro power 5,
diesel generation, biogas and fuel cells, etc exist. These generators are connected at
0.4 kV networks. In order to quantify the effect of small generation connected at the
generic Finnish 0.4kV networks; the studies use the output profile of small hydro
power generation since it is widely used in rural areas due to the availability of hydro
energy from small rivers. The profile is shown in Figure 2-40.
The studies focus on the effect of small hydro plant in rural networks. Currently, the
total small hydro power plants in Finland is about 40MW and the growth rate is about
9%/year. The forecasted generation capacity cases used in these studies are shown in
Table 2-17. The studies assume that all of these generators are allocated at 50% GSPs
for low density (L) scenario and 25% GSPs for high density (H) scenario. The number
of GSPs which have DG for both scenarios is presented in Table 2-18.
1.2
Winter Weekdays
0.8
Winter Saturday/Sunday
Spring Weekdays
P.U.
Summer Weekdays
0.4 Summer Saturday/Sunday
Autum Weekdays
0
1 5 9 13 17 21
Time(Hr)
5
In this context for Finnish case studies, the capacity of small hydro power is less than 1MW
60
Table 2-19 Losses and maximum flow when small hydro power generation connected
at Finnish rural lower voltage network
Small hydro power Losses in the rural Maximum flow
Losses in the whole
generation penetration networks with DG entering
rural networks (%)
scenarios (%) GSP(MVA)
without DG 3.42 3.42 111.56
60MW_L 3.29 3.35 109.62
60MW_H 3.16 3.36 107.68
86.25MW_L 3.23 3.33 108.77
86.25MW_H 3.05 3.33 105.99
172.5MW_L 3.05 3.24 105.99
172.5MW_H 2.73 3.25 100.46
210MW_L 2.97 3.20 104.78
210MW_H 2.60 3.22 98.07
Table 2-19 summarises the effect of small hydro power generation on Finnish rural
distribution network losses and network capacity replacement. Small hydro power
generation connected to Finnish lower voltage rural network decrease the network
losses and maximum flow entering GSPs so that bring benefit on network investment
deferral or reduction. These effects become clearer with DG penetration levels
increase and the minimum losses percent is 2.6% occurring with 210MW H
penetration scenario. From Table 2-19 we can see that small hydro generators
contribute not only to reduce the maximum flow entering GSP but also to reduce the
losses over the distribution network. This is due to the fact that the peak hydro power
generation output coincides with peak demand. Comparing with the UK cases, hydro
power generation technology has the similar effect on network with that from micro-
CHP.
For rural networks, the incremental cost with passive management is from around 122
€/kW to 236 €/kW. For active management, it is from 11.4 €/kW to 81 €/kW for
intermittent case and from 14.8 €/kW to around 99.6 €/kW for non-intermittent case.
The values are zero for scenario L in all cases except in the case where DG installed
capacity is 670MW.
61
250
150
100
50
LM
LM
LM
LM
H
H
HM
HM
HM
HM
L
0_
0_
5_
0_
0_
0_
0_
5_
0_
0_
0_
5_
0_
67
67
44
49
58
58
67
44
49
58
67
44
49
DG penetration scenarios
PM AM(NI) AM(I)
Figure 2-41 Incremental investment cost in active and passive Finnish generic rural
networks for various DG penetration scenarios (€/kW)
Figure 2-42 shows the incremental investment cost for various DG penetration
scenarios with different headrooms and management philosophies for urban network.
The incremental cost ranges from 13.8 €/kW to 25.5 €/kW.
Incremental investment cost (€/kW)
30
25
20
15
10
0
42 _LM
H
H
M
M
49 L
42 M
53 L
44 L
42 5 _L
49 M
53 M
44 M
0_
5_
5_
5_
0_
5_
5_
H
H
H
L
L
0_
5_
5_
0_
5_
5_
5_
2.
49
53
44
2.
44
49
53
5
2.
42
2.
DG penetration scenarios
0% HR (PM) 0% HR (AM) 10% HR (PM) 10% HR (AM)
Figure 2-42 Incremental investment cost with various DG penetration scenarios and
management philosophies for Finnish urban networks (€/kW)
From Table 2-15 and Table 2-16, we could derive the incremental DG benefit on
replacing distribution network assets with passive management and active
management for rural and urban networks shown as Table 2-20 and Table 2-21.
These DGs are connected at 20kV networks. From these two tables we can see the
benefit of DG on network capacity replacement is higher with lower DG penetration
levels. Large amount of DG installation will cause opposite effect on network
capacity reduction, which is reflected from the negative values.
62
Table 2-20 Incremental benefit of DG on replacement of Rural network assets (€/kW)
Scenarios 445 MW 490 MW 580 MW 670 MW
L 14.27 14.19 14.02 13.79
PM LM 7.67 5.68 2.61 0.37
HM 11.26 8.94 5.40 2.77
H -3.26 -4.19 -5.76 -6.92
Scenarios 445 MW 490 MW 580 MW 670 MW
L 14.27 14.19 14.00 13.76
AM LM 7.81 6.09 2.87 0.60
HM 11.34 9.07 5.84 3.01
H -2.80 -3.50 -5.14 -6.43
Table 2-22 shows the incremental benefit from small hydro power generation on rural
network assets replacement. The value is around 15 €/kW for low density level and 31
€/kW for high density level irrespective of generation capacity.
Table 2-22 Incremental benefit of small hydro power generation on of Rural network
assets replacement (€/kW)
Generation Density level
capacity L H
60MW 15.39 30.75
86.25MW 15.38 30.71
172.5MW 15.35 30.59
210MW 15.35 30.54
63
3 Summary
This report describes the cost and benefit of DG on the UK and Finish distribution
networks. On one hand, the cost of DG connections is obtained by calculating the cost
of network reinforcement needed to mitigate the technical problems, such as voltage
rise problems in rural networks and the increase in fault level (short circuit capacity)
in urban networks that are caused by its connection. On the other hand, the benefit of
DG is determined by computing the reduction in distribution losses and the ability of
DG to release network capacity which can be used to accommodate future loads.
The studies were carried out using the developed generic networks. Different network
characteristics in rural and urban areas and different network control schemes i.e.
active and passive control have been modelled and used in these studies to evaluate
the impact of different DG penetration levels within the different distribution
networks. The impact of different micro generation technologies such as PV, CHP
and small hydro on distribution networks was also studied.
The drivers which affect the cost and benefit of DG on the system are summarised as
below.
64
distributed power system, controllability of DG facilitated by active network to
support transmission and distribution system operation is essential.
The results of case studies carried out on the generic UK and Finnish networks can be
summarised as follows, in which the results in the unit of sterling pounds for the UK
studies are converted into Euro using exchange rate: 1 GBP = 1.5 EUR
Rural networks
65
Table 3-1.
66
Table 3-1 Incremental cost comparison between UK and Finnish rural networks
when network assets replacement required (€/kW)
UK rural networks Finnish rural networks
Network
Passive Active Passive Active
Management
Management Management Management Management
Philosophy
€/kW 20-83.7 16-64.9 122-236 11.4-99.6
The values in Finnish cases are much larger than those in UK case. This is caused
mainly due to following reasons.
1. Firstly, the average length of overhead lines which experience problems is around
20km in UK rural networks while this value for Finland is from 30km to 70km
which are 1.5 to 3.5 times of UK cases. With the same order of magnitude of unit
reinforcement cost per kilometre, circuit replacement will result in more
investment costs with longer lines.
2. Secondly, most of the loads in the Finnish network model are located close to the
substation and only a small amount of loads can be used to absorb DG connected
at the end of the feeder. In this case, DG connection will trigger voltage rise
problems and hence require circuit reinforcement in any scenario. Also, the
voltage rise problem is more severe and reinforcement costs are higher compared
with the UK cases since in the UK rural network model, the loads are mainly
distributed increasingly or uniformly along the feeder.
3. The third reason is due to assumptions in the circuit reinforcement options. For
UK case, we assumed the size of circuit can increase linearly. So we increased the
problem circuit size linearly until the voltage problems are resolved so that
minimum cost option can be obtained for circuit reinforcement. But for Finnish
case, indivisibility of circuit sizes was assumed. This means very big circuits
might be needed, with high reinforcement cost, if the second biggest size circuit
can not solve voltage rise problem.
Urban networks
For urban networks, without any headroom left for accommodating the increase in
fault level, DG connections will immediately cause switchboard reinforcement in
passive networks. Under these conditions, the incremental cost in UK urban networks
varies from 58.9€/kW to 471.5€/kW. With 10% headroom available in the switchgear
rating, the incremental cost is in the range of 0 to 243€/kW for the UK. For Finnish
urban networks the incremental cost is from 11.4€/kW to 50.4€/kW for both
headrooms. With Active management, urban networks incremental reinforcement cost
in the UK can be reduced into the range of 23.8€/kW to 189.6€/kW. An exception to
this is the ‘L’ density 422.5MW with 10% headroom case. Other cases show for the
Finnish network that the cost is bigger with AM than the corresponding value with
67
PM with the value for AM varying from 15.7 €/kW– 69.7€/kW. Table 3-2 gives the
range on these values.
Table 3-2 Incremental cost comparison between UK and Finnish urban networks
(€/kW)
UK urban networks Finnish urban networks
Management Passive Active Passive Active
Philosophy Management Management Management Management
Head rooms 0% 10% 0% 10% 0% 10% 0% 10%
58.9 - 0- 23.8 - 23.8 - 11.4- 11.4- 15.7- 15.7-
€/kW
471.5 243 189.6 189.6 50.4 50.4 69.7 69.7
From above results, we can see the same unit DG penetration can lead to much more
network reinforcement costs in UK urban networks than in Finnish urban networks.
This is caused by the network model characteristics as well as the reinforcement cost
of switchboard in either network.
The UK generic distribution network model covers 3 voltage levels of 11kV, 33kV
and 132kV when considering DG effect on network fault level. Therefore the
reinforcement cost on switchboard includes more than one voltage level in large
amount of DG penetration case, for example 7.5GW and 10GW of DG in the HM and
H scenarios in which the maximum incremental costs occur. Also the cost of
switchboards is very high in higher voltage level substations. This can be seen in
Table 1-8 for the UK situation. In Finnish case only fault level rise at 20kV voltage
level networks is considered and the whole switchboard cost is 380,000€. Apparently
more complex networks and more expensive assets contribute to more reinforcement
costs. Generally it can be concluded that active management application can reduce
reinforcement cost if there is still headroom left.
68
with ‘H’ density level scenario in which large reversed power flow occurs. This value
for Finnish rural networks varies from 0.37€/kW to 14.27€/kW and from 0.38€/kW to
9.85€/kW for urban networks apart from the H density level for which almost all the
DG capacity scenarios with negative values occur. In other words, too high DG
penetration will not bring benefit of network reinforcement deferral. The incremental
benefit on UK network capacity replacement is much bigger than Finnish case. This is
because DG connection can bring more contribution to capacity replacement for UK
networks because it covers from 11kV to 132kV voltage level networks including
more expensive substations. For Finnish case, only 110kV/20kV substations capacity
is considered to be replaced.
Because micro (or mini) generation is connected directly at low voltage networks
where the most distribution network customers are connected, these generations could
contribute effectively in the reduction of network losses. In the UK, on average the
losses can be reduced by 0.4 %-0.8% depending on the production profiles of the
micro generation. While the benefit of small hydro power generation in Finnish rural
networks in term of losses is around 0.2%.
69
References
z D. Pudjianto, D.M. Cao, S. Grenard, G. Strbac, “Deliverables D7: Method for
Monetarisation of Cost and Benefits of DG Options”, Report for DG-Grid, Jan
2006, http://www.dg-grid.org/results/index.html.
z Green, P., Smith, S. and Strbac, G. (1999) “Evaluation of alternative distribution
network design policy”, IEE Electric Power Distribution System Engineering, Vol.
146, 53-60.
z Jenkins, N., Allan, R.N., Crossley, P., Kirschen, D. and Strbac, G. (2000)
“Embedded Generation”, Institution of Electrical Engineers, London.
z Liew, S.N. (2002b) “Technical and Economic Assessments of Active Distribution
Networks”. PhD thesis. The University of Manchester Institute of Science and
Technology.
z “Statement of charging methodology for use of united utilities electricity PLC’s
electricity distribution network”. United Utilities Electricity PLC. April 2005.
z Mendez, V.H., Rivier, J., de la Fuente, J.I., Gomez, T., Arceluz, J. and Marin, J.
(2003) “A Monte Carlo approach for assessment of investments deferral in radial
distribution networks with distributed generation”, IEEE Power Tech
Conference’2003, Bologna, Italy.
z Engineering Recommendation (ER) G.83/1, (2003) “Recommendation for the
connection of small-scale embedded generators (up to 16A per phase) in parallel
with public low-voltage distribution networks”, Energy networks association.
http://www.energynetworks.org/spring/engineering/distributedgeneration02.asp
z Jenkins, N. (1995) “Photovoltaic systems for small-scale remote power supplies”,
Power Engineering Journal.
z Skytte, K. and Ropenus, S. (2005) “Regulatory Review and International
Comparison of EU-15 Member States”, Report for DG-GRID. http://www.dg-
grid.org/results/result_report-skytte1.pdf
z “Finnish standards association (SFS)”, 2003. SFS Handbook 142. ISBN 952-
5420-08-6.
z Wu, X., Mutale, J., Jenkins, N. And Strbac, G. (2003) “An investigation of
network splitting for fault level reduction”, Working Paper for Tyndall Center.
z Engineering Recommendation (ER) G.59/1, (1991) “Recommendations for the
connection of embedded generating plant to the public electricity suppliers’
distribution systems” 1991 The Electricity Association”, Electricity Networks
Association.
z Engineering Recommendation (ER) G.75, (2002) “Recommendations for the
connection of embedded generating plant to public distribution systems above
20kV or with outputs over 5MW”, Electricity Networks Association.
70