You are on page 1of 8

6/26/2019

Construction Management
Site Management
1. Roles of Consultant and Contractor at Site (Covered
CE403 – Construction under Life of a Project – Construction Management
Introduction)
Management
2. Documents, Records and Meetings
(Slides Set No. 3)
3. Progress Monitoring and Control
4. Site Supervision
By
5. Cash flow management
Dr. Pujitha B. G. Dissanayake 6. Introductionto Material and Construction
Department of Civil Engineering Equipment Management.
Faculty of Engineering
University of Peradeniya
1 CE403 - Construction Management 2

Construction Management Construction Management


Site Management – Cash Flow Management How to Analyse Cash Flow
• Managing cash flow control in construction • An S-curve, such as the one shown below can be
projects is an important aspect of project used to predict the cash flow requirement of the
management plan during the execution stage. project.
• Funding problems usually arise due to many
reasons.
• To ensure the project’s continuity, Cash Flow
Management should be properly carried out.
• Cash flow management means delaying outflow of
cash as long as possible while encouraging any
inflow of money as rapidly as possible.

CE403 - Construction Management 3 CE403 - Construction Management 4

1
6/26/2019

Construction Management Construction Management


Cash Flow Analysis Cash Flow Analysis
• What is an S-Curve? • The S-curve is developed by cumulatively adding the
• S-Curve is the graphical representation of how the costs from the work breakdown structure according
project budget will be spent if the work is carried to their planned completion time (based on the
out exactly as estimated and scheduled. schedule).
• Cash flow and cost incurred are different and will
be discussed in this section.

CE403 - Construction Management 5 CE403 - Construction Management 6

Construction Management Construction Management


Cash Flow Analysis Cash Flow Analysis
• Prepare schedule • The above S-curve is known as the Budgeted Cost of
Work Scheduled.
• The cost will usually increase gradually as the
contractor will use the early days for mobilization
and organizing the work and will steadily increase
and tend to slow down as the project nears
completion.

• Input cost to each activity


• Find cost for each day and get cumulative cost
• Generate S-Curve

CE403 - Construction Management 7 CE403 - Construction Management 8

2
6/26/2019

Construction Management Construction Management


Cash Flow Analysis Cash Flow Analysis
• The S-curve can be used to predict the monthly cash
flow requirements of the contractor and the monthly
payment requirements of the owner.
• The timing of these payments is a matter of
contractual agreements.
• The owner needs to plan the costs of the progress
payments before the project starts and ensure the
funding is available to make the payments.

• During the middle portion of the work, a project will


accumulate costs at a more or less steady rate,
thereby producing the S-shaped curve.
CE403 - Construction Management 9 CE403 - Construction Management 10

Construction Management Construction Management


Cash Flow Analysis Cash Flow Analysis
• The contractor has a slightly different reason for • Although it can happen to any business, cash flow is
making cash flow analysis. one of the major causes of failure for small
• The contractor will need working capital during the construction firms.
construction, and must know how much cash flow is • A positive cash flow indicates that the cash coming
needed before the project starts. in exceed the expenses and a negative cash flow
• The cash flow analysis is used as a key management signifies the opposite.
tool of the contractor. • Cash is the fuel that runs the business and a
• Many contractors have got into financial trouble contractor must maintain a cash balance sufficient to
when they suddenly and unexpectedly run out of meet the payrolls, pay for materials and equipment
cash to pay their bills. etc.

CE403 - Construction Management 11 CE403 - Construction Management 12

3
6/26/2019

Construction Management Construction Management


Cash Flow Analysis Cash Flow Analysis
• The management will need to know when to borrow Generating the S- Curve for a Project
money and how much is required early on so that • The cumulative cost versus time S-Curve can easily
there are no surprises. be prepared by cost loading the bar chart.
• Timing of cash flow is especially important in • The bar chart also known as the Gantt chart was first
determining a firms working capital requirements introduced by Henry Gantt.
and the future cash position of the construction firm • The bar chart is the most commonly used project
is of great importance to the management. planning and control tool.
• Almost all currently available commercial
scheduling software present information in bar chart
format.

CE403 - Construction Management 13 CE403 - Construction Management 14

Construction Management Construction Management


Cash Flow Analysis Cash Flow Analysis
Generating the S- Curve for a Project Generating the S- Curve for a Project
• It is a simple and concise graphical picture for • If cost, equipment or personnel requirements are
managing a project and it also can compare planned superimposed on the activities the total resources
schedule with the actual progress on site. required at any time can also be computed.
• The bar-chart is widely used as a construction
scheduling tool because of its simplicity, ease of
preparation and graphical format.
• The advantage of using a bar chart is that field
personnel can easily understand the information and
can be used as a preliminary planning schedule

CE403 - Construction Management 15 CE403 - Construction Management 16

4
6/26/2019

Construction Management Construction Management


Cash Flow Analysis Cash Flow Analysis
Generating the S- Curve for a Project Generating the S- Curve for a Project
• A typical example of a simple bar chart for a project • In the case of a bar chart not generated from the
is as follows: critical path method, the user must have detailed
knowledge of the particular project and the
construction sequence.
• If the S-curve is required for the above project, a
simple spreadsheet could be prepared to add-up the
total cost incurred on each day if the individual cost
of activities are known.

CE403 - Construction Management 17 CE403 - Construction Management 18

Construction Management Construction Management


Cash Flow Analysis Cash Flow Analysis
Generating the S- Curve for a Project Generating the S- Curve for a Project
• Cost included for each activity is shown below:

Daily Cost Values


S – Curve for the Project

CE403 - Construction Management 19 CE403 - Construction Management 20

5
6/26/2019

Construction Management Construction Management


Cash Flow Analysis Cash Flow Analysis
What is Front Loading? Front Loading
• Front loading is achieved by assigning higher costs • Subcontractors, particularly find it necessary to
to early activities and lower costs to late activities, overbill as they must pay their labour and material
but keeping the total project cost unchanged. bills prior to even submitting their invoices, and then
• Many people consider front loading unethical. wait around 2 months or more after that to receive
• Contractors consider it essential if they are going to
their progress billing.
manage their cash flow effectively.
• It is necessary for cash flow and their least expensive
source of borrowed money.

CE403 - Construction Management 21 CE403 - Construction Management 22

Construction Management Construction Management


Cash Flow Analysis Cash Flow Analysis
Exercise 1: Exercise 1: (Cont.)
The following bill values and cost data are given for a 1. 10% retention is deducted from the monthly bills up
road construction contract of Rs. 10,000,000. to a maximum of 5% of the contract value.
2. Monthly bill is prepared at the end of every month
and employer will pay the bill after 30 days.
3. 20% mobilization advance will be paid at the
beginning of the contract and will be deducted from
the monthly bill at the rate of 20%.
Using the following information, prepare a cash flow
4. Contract period is 6 months and the defects liability
statement for the project.
period is 3 months.
5. Labour, material and plant costs are assumed as 25%,
30% and 45% of the total cost respectively.
CE403 - Construction Management 23 CE403 - Construction Management 24

6
6/26/2019

Construction Management Construction Management


Cash Flow Analysis Cash Flow Analysis
Exercise 1: (Cont.) Exercise 2:
6. No sub-contractors are deployed in this project. A civil engineering contractor has undertaken to carry
7. 50% of the retention money will be paid at the end of out a project for a contract sum of Rs. 240 million. The
the contract and the balance will be paid after the contract duration is 9 months and the defects liability
defects liability period. period is 3 months. The construction schedule and the
8. One month credit is provided for the materials and
value of each of the major activities are as given in the
plants. following figure.
State any other assumptions. Comment on the cash flow
statement

CE403 - Construction Management 25 CE403 - Construction Management 26

Construction Management Construction Management


Cash Flow Analysis Cash Flow Analysis
Exercise 2: (Cont.) Exercise 2: (Cont.)
1. According to the contract, payments will be made as 4. A mobilization advance of Rs. 60 million is paid to
lump sum amounts for each completed major activity the contractor at the beginning of the contract.
after a period of 30 days. 5. The mobilization advance will be deducted from the
2. An amount equal to 1/6th of the above lump sum 1st and 3rd lump sum payments at the rate of 50%.
amounts for each major activity will be deducted as 6. Assume that the contractor has included a profit
retention money from each lump sum payment upto margin of 20% on top of his total cost in the value of
a maximum of 10% of the contract sum. the contract sum.
3. 50% of the retention money will be paid at the end of
the contract period (9th month) and the balance 50%
will be paid at the end of the defects liability period
(12th month).
CE403 - Construction Management 27 CE403 - Construction Management 28

7
6/26/2019

Construction Management
Cash Flow Analysis
Exercise 2: (Cont.)
(i) Using the above data prepare a cash-flow statement
for the above contract. State any assumptions made.
(ii) If the contractor needs to borrow money from the
bank at an interest rate of 3% per month, what would
be the minimum total finance charge incurred by the
contractor to maintain positive cash flow.

CE403 - Construction Management 29

You might also like