PRODUCTION SCHEDULE
Video Title: Brotherhood
Client: Mr. Morgan, Miss Welling
Producer: Ralph Slee
Date: 05/10/19

Date: Date:
Planning 08/10/19 Completed: 01/03/20
Started:
Proposal 16/10/19 Completed: 25/10/19
Started:

Agreement from 25/10/19


Client:

Audience 26/10/19 Completed: 28/10/19


Research
Started:
Audience 29/11/19 Completed: 05/11/19
Research
Analyzed:
Drafting Started: 06/11/19 Completed: 15/01/20

Production 16/01/20
Started:

Rough Cut 20/03/20 Agreed with 23/03/20


Supplied to Client:
Client:
Final Version to 03/04/20