Professional Documents
Culture Documents
Grignard reagents are widely employed during the with common species, several runaway scenarios and
production of pharmaceuticals and other fine chemi- subsequent explosions or emergency releases may
calsl. A desired intermediate or product is formed by occur during the production and use of a Grignard
the coupling of a Grignard reagent with a variety of reagent. In this paper, several of these potential
compounds. Typically, a magnesium Grignard reagent runaway scenarios and the corresponding emergency
is employed in the absence of water; its formation as relief system design are discussed. In addition, a
shown below is usually highly exothermic2: runaway incident which occurred during the production
of a Grignard reagent will also be addressed.
Initrator
R-X+Mg -R-Mg-X
Initial plant configuration/upset scenario
+heat evolved (-80 kcal mol-l)
definition
where R denotes an alkyl or acyl group, X denotes During the batch production of one of Merck’s
the halides, and Mg denotes the magnesium chips. A products, a Grignard reagent was produced in the
common solvent used for this reaction is tetrahydro- plant and employed immediately to form the desired
furan (THF). intermediate. A schematic illustration of the initial
In general, Grignard reagents can also react equipment employed in the production of this Grignard
readily and exothermically with many common species, reagent is shown in Figure 1. During production, a
such as water, oxygen and carbon dioxidel. The constant nitrogen sweep was employed to minimize
reaction between a Grignard reagent and water, which the potential reaction between the Grignard reagent
is one of the commonly used heating/cooling media, and possible moisture and/or oxygen in the vapour
is shown as follows: above the Grignard batch. The Mg chips and THF
were loaded into the Grignard reactor first. After
R-Mg-X+H,G-+R-H+Mg(OH)X
heating the resultant Mg/THF mixture to the reflux
+heat evolved (20-40 kcal mall’)
temperature of -66”C, a Karl Fischer (KF) test was
In addition to significant heat releases, the reaction conducted to check whether the water content of the
product R-H may be a flammable gas if the alkyl or mixture was within the specification of 0.05%. A
acyl group has only a few carbon atoms. mixture of alkyl halide (R-X) and THF was prepared
Because of the significant heat release during the in a feed tank and checked for a KF less than 0.06%.
production of a Grignard reagent and its reactivity After adding about 0.3 gallons of the initiator,
095c-4230/94:05041~06
fQ 1994 Butterworth-Heinemann Ltd
due to test cell rupture. Based on these observations, according to the recommendations before start-up. A
the situation during emergency relief can be regarded schematic illustration of the modified configuration is
as a tempered (vapour) system4r7. In addition, the shown in Figure 4. The service fluid in the reflux
main contributor to the observed pressure was the condenser was changed to cooling oil. A safety valve/
vapour pressure of THF. The pseudo-one-component rupture disk combination (PSVIRD) with a set pressure
analysis’s (o-method) was then used in the vent- of 43.5 psig was used to handle standard process upset
sizing calculations and the equations are given in the scenarios, such as excessive feed and high jacket
Appendix _ temperature.
From the tempered system calculations, the relief A second 3” rupture disk with a set pressure of
vent diameter for the water intrusion scenario was 62.3 psig was also installed to handle the upset scenario
found to be -14”. Since the estimated vent size was of delayed Grignard initiation and oil intrusion. During
significantly larger than the largest nozzle on the the emergency release from the delayed initiation
Grignard reactor, this scenario was eliminated by scenario, the expected vent flow would be three-phase,
switching to an oil cooling system. For the oil intrusion including THF vapour, R-X/GrignardffHF liquid mix-
scenario, the vent diameter was estimated to be -1.5”, ture, and Mg chips. This vent flow was different from
which was much smaller than the available nozzle on the homogeneous two-phase flow assumed during the
the Grignard reactor. vent-sizing analysis. Consequently, the benefits of
For the scenario of delayed initiation leading to early release through the 2” condenser vent line fitted
reactant accumulation, the relief vent diameters were with a flame arrester and PSV/RD vent line were
estimated at two conditions, with -41% unreacted conservatively ignored due to their relatively small
R-XITHF and with 100% unreacted R-X/THP. The cross-sectional area and/or high flow resistance.
relief vent diameter estimated in both cases was found
to be -3”. Calculation results for the case of -41% The Grignard release incident
unreacted R-X/THF are listed in Table I.
After all the pre-start-up activities and recommended
physical changes to the Grignard reagent production
Revised factory set-up
facility were completed, the first batch of Grignard
After evaluation of the four different potential process reagent was scheduled to be made. Temperature and
upset scenarios, the plant equipment was modified pressure excursion occurred during this first batch and
a release of -30% of the batch through the vent lines
was observed.
Table 1 Tempered system vent sizing calculation for delayed
The events leading to this incident were found to
initiation scenario with -41% R-XTTHF charge
be as follows. The THF and Mg chips were charged
Plant parameters to the Grignard reactor, heated to reflux, cooled to
Volume of plant vessel (VI 1.1355 m3 25°C and checked for KF. The KF was 0.001% versus
Maximum allowable pressure 0.515 MPa
a maximum specification of 0.05%. The alkyl halide
of plant vessel
Charge to plant vessel (mJ 363 kg
Volume of vessel charge (V,,r,) 0.3528 m3
Bulk density of vessel charge 1029 kg rnds
Discharge pressure (P& 0.101 MPa
Relief device set pressure (P,,) 0.536 MPa
Maximum pressure 0.581 MPa
accumulation 1
(P turn-around
I h
I
VSP test data MA WP
Relief set temperature (T.,,) 128.5% 150 psig
RD RD/PSV
Temperature rise rate at relief 25°C min-’ PM Pset
set temperature 62.3 psig 43.5 psig
w
Turn-around temperature 132.1”C 1. Initiator Cooling Oil
I..-
I ~t”,“-.r,u”dl 2. R-X/THF (7%)
Temoerature rise rate at turn- 30°C min-’ 3. R-X/THF (93%)
around temoerature KF<O.OG%
Experimental 7;7 4 232 650 N m-*
( ‘) T-t
w-method
w evaluated at stagnation 8.75
condition
Critical (choked) pressure ratio 0.845 Mgi-fHF
(nJ KF<0.05%
Mass flux (G) 3700 kg m-2 s-’ Brine or Hot Water
Assumed specific heat CC,) 0.5
Flow reduction factor for an RD
and tailpipe UD = 200 (F)
Ideal vent diameter
0.5
2.1 inch
4 Grignard Reactor
Conclusions
Due to the reactivity of the Grignard reagent, several
runaway scenarios may occur during its production.
HAZOP studies and VSP simulation of the runaway
scenarios provided better understanding of the desired
and undesired process chemistry and resulted in safer
operations. In addition, the pseudo-one-component
tempered system analysis was found to provide a G = PtU - w)(l - 4 - w lwc}Yn
conservative emergency relief system design which 1
provided adequate relief venting when one of the
evaluated upset scenarios occurred.
J--
Pset .T
w(- >
77c
-1 +1
Acknowledgements
The authors would like to express their thanks to the
following people at Merck & Co. Inc. for their
and PdisiP,,t less than 7)c, which is estimated from:
assistance during the preparation of this manuscript:
Mr R. Colucci, Mr J. Ella, MS L. Meisenbacher, MS vc = 0.55 + 0.217 lno - 0.046 (lnw)”
K. Murray and MS S. Stopya. + 0.004 (lnw)3