Certificate Course
on
PIPING ENGINEERING
December 2 -18, 1998
Introduction
A. S. Moharir
CAD Centre, IIT Bombay
mi MI
Organized by
Piping Cell
Computer Aided Design Centre
Indian Institute of Technology, Bombay
Powai, Mumbai - 400 07620
INTRODUCTION
About two decades ago, in India, the
design procedure for piping systems for
Refineries, Petrochemicals and Fertilizer
Plants, in magnitude, depth and
complexities were not fully evolved. Only
in the recent past, we were exposed in
detail to this field. Now we are self-
the field of piping technology
Piping systems in a chemical plant are
comparable to the vanes and arteries
through which fluids, vapors, slurries,
ids, ete. flow under various
design of the plant. Piping network is
subjected to almost all the severest
conditions of the plant such as high
temperature, pressure, flow and
combination of these. In addition to the
above, corrosion, erosion, toxic conditions
and radioactivity add to more problems
and difficulties in piping design. With
the process conditions becoming more and
more severe by the advancement in
process development, a continuous effort
is required to be carried on simultaneously
to cope up with the demands of process.
This makes the job of a piping engineer
more complex and responsible.
Piping, because of its nature, requires a
number of day to day decisions on matters
of detail, which, in some ways are often
more difficult to solve than major issues
connected with the project. It is this same
detail which can cause expensive delays
in design and construction and
consequently in commissioning All too
often in the past, piping has been
regarded as an unimportant job in the
overall project engineering instead of being
treated as a function requiring as wide
a knowledge, experience and variety
skills as any other branch of engineering
In almost all chemical industries, the
installed capital cost of piping is a
major factor in plant investment, Figs.
1 and 2 show a chart based on oil
refineries, chemical and petrochemical
complexes. Fig. 1 shows that,
excluding major equipment costs, piping is
the largest plant cost component. It
exceeds the next largest component by a
factor of two. It is also observed from
Fig. 3 that piping exceeds all other field
costs by a substantial amount. Fig. 2
indicates that design engineering utilizes
approximately 45% of engineering man-
hours and 50% of these hours are used in
piping design.
In addition to the above, the lost time in
piping has an effect which goes well
beyond its direct cost; as it involves
financial loss in some proportion to the
total plant investment. The delay in and
during start up means idle capital and
losses in plant earning capacity.
In the recent years, the trend is to develop
better techniques so as to save time in
piping activities. Computer is being used
extensively to obtain rapid solutions to the
more complex problems of plant design
and, in so for as piping is concerned,
to the solving, of problems of pipe
stressing. More recently, it is being
employed for production of piping
detail drawings, piping isometrics, bill of
materials, cost estimation and control.
Piping engineer has therefore a
further responsibility in understanding
and application of continually growing
techniques of this nature.WHAT A PIPING ENGINEER SHOULD KNOW ABOUT
Piping engineer requires not only wide
engineering knowledge - not necessarily
in depth, but certainly in understanding
~ but he must also have an understanding
of engineering economics and costs, of
metallurgy, of methods of pipe
fabrication and erection. He must
have some knowledge of industrial
chemistry and chemical engineering in
addition to a sufficient knowledge of
mechanical, civil, electrical and instrament
engineering so as to discuss requirements
and problems with specialists in these
fields, This will be more clear with the
data piping department requires from
other disciplines as given in Annexure A.
He should be co-operative, able to
communicate effectively, lead or take
part in team work, be alive to the
application of new methods, materials and
designs. He must be aware of standards,
codes and practices.
There are several aspects of engineering
technology which the piping engineer must
know something about - at least
PIPING DESIGN FUNCTION
ORGANIZATION
The size and scale of a company or design
office do not change either the basic piping
design requirements or the underlying
design principles and practices. As the
volume of piping design work and the
number of projects executed increases,
so also does the degree of specialization
increase. Functions such as __ piping
layout, piping specifications, detail drafting
and material listing begin to emerge as
11. e117.)
sufficiently to discuss rationally, any
particular subject with specialists
concerned. More importantly, he must
have sufficient broad knowledge to know
that certain conditions can arise at the
early stages of plant design, where lack of
awareness can cause difficulties and even
disasters
A fairly good knowledge of structural
engineering is a must. Piping in operation
is always in movement and subjected to
pressure and forces with consequent
reactions on mechanisms such as pumps,
compressors and equipment in general,
and on structures and related piping.
Lack of knowledge can cause errors
sufficient to cause machine or equipment
break-down or to overstress and even
cause collapse of structures
‘A good knowledge of safety codes and
practices is alse essential
Above all, a piping engineer should be
very well conversant with drafting
procedures and practices.
RGE
separate departments within the design
office. There is little apparent similarity
between piping design organization in a
small office of say, ten men, and a large
company with hundreds of piping men, as
indicated in Figs. 4 and 5, but the job
performed in both cases is identical and
has the same degree of relative importance
to the whole project design organization.The real difference lies in rate of projects
passing through the design office. In the
small office, the flow of projects is such
that each project. is substantially
completed before the succeeding project
commences. This demands flexible
organization of a small group, who have
responsibility for all aspects of design, In
the large company, however, projects
are much more frequent. Thus the greater
A®
volume of work handled by a large group
makes a high degree of specialization
necessary for economic and administrative
reasons
In both cases, piping design is the most
lengthy and complex part of the whole
design procedure and almost always on
the critical path of the project plan
PIPING WITHIN THE PROJECT PLAN
Piping is an important clement of every
stage of project design, purchasing and
construction. It is intimately linked to the
other project work on equipment,
electrical, instrument and —_ civil
engineering. Work on piping is
proceeding at every stage of the project,
partly because of the sheer volume of
design and erection work, but mainly
because of the need to relate other
project activities to the piping design, A
typical activity network and bar chart for a
process plant project are shown in Figs. 6
and 7.
The activity network shows clearly the
interrelated activities of piping and other
branches of project, particularly at
design stage. Itillustrates the unifying role
played by the piping engineer in acting as
a clearing house for data provided from
other specialist engineers, It also indicates
the last stage of the project, when piping
erection is being carried out and when
one faces the difficulties of correcting the
design errors without delaying project
completion. Since the quantum of work
involved in piping is very extensive, the
design and erection activities of piping
appear on the critical path of this
network. The critical path planning helps
in proper allocation and utilization of
man-power for critical activities, thus
avoiding uneconomic and wasteful
allocation of resources.
RESPONSIBILITY OF A PIPING ENGINEER
"The efficiency with which the entire
systems of any particular projects work
depends upon initial phase and is in the
hands of piping analytical engineer. Every
change the engineer makes from his base
design is compounded ten folds down
stream as so many other operations
depend on his design. The analytical
design is the 'BIBLE' and must be
correct in the first instance The
correctness, thoroughness and efficiency
of the design released by the analytical
engineer determines the efficiency of the
piping design and influences, significantly,
the efficiency and quality of overall
plant." 3
Piping engineer is responsible for a
substantial part of total project cost.
Achievement of his program timings is
critical to the completion of project in
time, In addition to his own function as
a specialist design engineer, he must
provide a considerable amount of
information and design continuity inside
the project design organizationHIS PARTICULAR CONCERNS MUST
Adequacy
% Piping design must be adequate to
meet the process specification and
physical conditions in which the plant
is to operate
Economy
%S Adequate design must be achieved
at an economic cost within the
project budget. Design cost must
be minimized by maximizing the use
of standardized methods of detailing
and data presentation.
Clarity
% Much of the piping data is derived
from and used by other engineering
departments and must be clear,
consistent and reliable.
Accuracy
% Details of piping and materials must
be complete and —_ accurate
Rectification of mistakes in these
activities at a later stage may prove to
be very costly and can delay project
completion.
The piping engineer has, therefore,
considerable responsibility for economic
and accurate design. Much development
of design methods and organization has
taken place over the years. In large
design organizations, techniques have
emerged, whereby procedures for
producing simple symbolic data conveying
maximum information at minimum cost
canbe employed. The basic elements of
these procedures are :
> Rapid data retrieval
> Standardization of
design methods for
material selection ete.
engineering
stressing,
Maximum use of standards
Symbolic drawing procedures
Standardization of document format
for issue of piping information.
A. responsible piping engineer would try
to take the maximum use of such methods
and procedures.Painting
Insulation
Building
Stmenie
Foundation
FIG. 1
Design Engineering 45%
ES
FIG. 2
Piping 47%
‘Typical Field Labour
Cost
Instruments
cong
Electricals,
Major Equipment
FIG. 3Project Dept.] [Process Designers] [Design Depts
fFiow Sheet @]___ fPtant layout & eens
Daf tant avout & Piping Details
mons. Eqpt. layout | [vtaterial List & Summary
Purchase Requisitions
Fabrications
[Line Diagram] . | pues
ae ane tans Pipe System ontracors
=a Specification
Cost Control
[Construction
FIG. 4 PIPING DESIGN IN SMALL
ORGANIZATION
Project Dept] [Process Equip. Piping Design Dept
[Design Dept] [Design Dept
y wv ¥ ¥
Flow Sheet ] [_ Detaled Plant | [ Prod. | [Material
[Process Data) | Equip. Design| Layout] }_Drg_| | Controt
[Section] q Section
[Utitities Layout | [Piping | [Bill of
[Auxillary "| Studies pene: [Material
lEquipment| [> Drawing | | Deais | ~~ P
[Data >| Key 1 Model
= : Ltriaton
¥
[Construction
FIG. 5 PIPING DESIGN IN LARGE ORGANIZATIONActivity No. Time Scale
Task name i eal)
Precons tow Sheet q
Pret tayout
Final Equpmect Design
Ping Layouts
Pipe Deas Drawing
a
nr
al
an
atk. rh
or
Werking in. Design
Final iat. ata
ny
ee
rte ,
Foe MTO& Orders
tain Tenders & Selec Pabrcatars
Ma, Oevrion to Faiatoe
Pipe Mat, nvr Ste
Faticate & Dore Pipes to Ste
Deter ret ine O
ere Easoment i
ares ina
Pit aaa
rea Part 8 Piping
Statue
FIG. 6 BAR CHART FOR TYPICAL PROJECT ACTIVITY
(Piping Activity Shaded)10
Is
16
7
18
INPUTS TO PIPING
Data as per project design basis such as indicative Plot
»& IDs, PDS, Process description, Equipment
~ Process.
licensor
uirements on piperack/pipe sleepers ~
nits/fisites
igincering data sheets of equipments like columns,
vessels, tanks, etc
Engg, data sheets giving overall dimensio
process/technological structures
‘Overall foundation layout.
Platform drgs. and special pipe structure support structure
res. 4
General arrangements drgs. of electrical cable tray/trench
‘Sketches for level instruments (nozzle elevation).
Dimensional drawings of all inline instruments,
10.
_ Sea eS
OUTPUTS FROM PIPING
Overall plot plan showing location of various units, tankfarms, offsite.
package units, non-plant buildings, roads, culverts, piperacks, sleepers.
atc
Piping material speci
Equipment layo
TOG Elevations
forall equipment.
General arrangement of piperack and equipment supports structures
including loads,
Piping general arrangement drgs. including platforms, ladders,
overhead cranes:
cutouts, inserts and sleeves, requi
BOM & technical evaluation and technical bidding analysis.
Stress analysis
Nozzle orientation drgs. including location of
‘Vessel cleats location drgs. for pipe supports, platforms and ladders.
Underground piping layout.
Isometrics of piping including system ISOs
Support drgs. of piping and special support details.
Tender for fabrication S.0.Q.
Tender for insulation $.0.Q
Tender for painting SO.Q