Professional Documents
Culture Documents
PEI RP 1000 Marine Fueling
PEI RP 1000 Marine Fueling
FT
Recommended Practices
for the Installation of
Marina Fueling Systems
A
R
D
FT
Inside Front Cover
A
R
D
PEI/RP1000-09
Recommended Practices
FT
for the Installation of
Marina Fueling Systems
A
R
D
Other Reference Publications available from PEI
Order online at www.pei.org/shopping
FT
Systems at Vehicle-Fueling Sites
Foreword
These Recommended Practices for the Installation of Marina Fueling Systems have been prepared as an
industry service by the Petroleum Equipment Institute. The text represents the consensus views of the
PEI Marina Fueling System Installation Committee, comprised of the following members:
FT
Charles S. Allsopp Charles B. Hubbard
First Petroleum Services, Inc. Oil Equipment Sales & Service Co., Inc.
Raleigh, North Carolina Chesapeake, Virginia
Laura Fisher
California SWRCB
R
Sacramento, California
Serving as consultant to the committee was Marcel Moreau, P.O.E., Marcel Moreau
Associates, 73 Bell Street, Portland, Maine 04103.
All questions and other communications relating to this document should be sent only
to PEI Headquarters, addressed to the attention of the PEI Marina Fueling System Installation
D
Committee.
iii
FT
A
R
D
DISCLAIMER
Every effort has been made by the PEI Marina Fueling System Installation Committee to ensure the accuracy
and reliability of the information contained in this document. However, the Committee, its consultant, and the
Petroleum Equipment Institute make no representation, warranty or guarantee in connection with the publica-
tion of these recommended practices. The Institute hereby expressly disclaims any liability or responsibility
for loss or damage resulting from the use of these recommended practices; for the violation of any federal,
state or municipal regulation with which these practices may be in conflict; or for the infringement of any
patent resulting from their use.
Recommended Practices for the Installation of Marina Fueling Systems
Contents
Foreword.................................................................................................................................................. iii
Sections
1. Introduction.................................................................................................................................... 1
1.1 Origin.......................................................................................................................................................................1
1.2 Background..............................................................................................................................................................1
1.3 Purpose.....................................................................................................................................................................1
1.4 Scope........................................................................................................................................................................1
FT
1.5 Sources.....................................................................................................................................................................1
1.6 Use of Other PEI Recommended Practices.............................................................................................................1
1.7 Regulations and Codes.............................................................................................................................................2
1.8 Listing of Marina Piping..........................................................................................................................................2
1.9 Importance of Competent Installers and Technicians..............................................................................................2
1.10 Importance of Competent Operators........................................................................................................................2
2. Definitions...................................................................................................................................... 3
2.1 Anti-Siphon Valve....................................................................................................................................................3
2.2 Approved..................................................................................................................................................................3
2.3 Attended Marina Fueling Facility............................................................................................................................3
2.4 Authority Having Jurisdiction (AHJ).......................................................................................................................3
2.5 Dispenser..................................................................................................................................................................3
2.6 Dispenser Platform...................................................................................................................................................3
2.7 Dock.........................................................................................................................................................................3
2.8
2.9
A
Downstream.............................................................................................................................................................3
Flexible Pipe.............................................................................................................................................................3
2.10 Fueling System.........................................................................................................................................................3
2.11 Gangway...................................................................................................................................................................3
2.12 Listed........................................................................................................................................................................3
2.13 Marina Fueling Facility............................................................................................................................................4
2.14 Navigable Water.......................................................................................................................................................4
2.15 Onshore....................................................................................................................................................................4
R
2.16 Qualified Technician................................................................................................................................................4
2.17 Rigid Pipe.................................................................................................................................................................4
2.18 Safety Break.............................................................................................................................................................4
2.19 Semi-Rigid Pipe.......................................................................................................................................................4
2.20 Upstream..................................................................................................................................................................4
2.21 Vessel........................................................................................................................................................................4
3. Storage Tanks................................................................................................................................ 4
3.1 General.....................................................................................................................................................................4
D
4. Onshore Piping............................................................................................................................... 5
4.1 General.....................................................................................................................................................................5
4.2 Underground Piping.................................................................................................................................................5
4.2.1 Leak Detection for Underground Piping....................................................................................................6
4.3 Aboveground Piping................................................................................................................................................6
4.3.1 Leak Detection for Aboveground Piping....................................................................................................7
4.4 Special Requirements for Underground and Aboveground Marina Piping Systems..............................................7
4.4.1 Anti-Siphon Valve.......................................................................................................................................7
4.4.2 Block Valves and Safety Break...................................................................................................................7
4.5 Seasonal Factors or Weather Emergencies..............................................................................................................8
PEI Recommended Practices 1000-09
5. Gangway Piping.............................................................................................................................. 8
5.1 General.....................................................................................................................................................................8
5.2 Factors to Consider..................................................................................................................................................9
5.3 Piping Materials.......................................................................................................................................................9
5.4 Piping Design...........................................................................................................................................................9
5.4.1 Design #1: Piping Securely Fastened to the Gangway...............................................................................9
5.4.2 Design #2: Piping Flexibly Supported by Gangway................................................................................10
5.4.3 Design #3: Piping Independent of the Gangway...................................................................................... 11
5.5 Dock Transition Sump...........................................................................................................................................12
5.6 Piping Leak Detection............................................................................................................................................13
5.7 Valves and Fittings.................................................................................................................................................13
FT
6. Pier, Wharf, or Quay Piping........................................................................................................... 14
6.1 General...................................................................................................................................................................14
6.2 Factors to Consider................................................................................................................................................14
6.3 Piping Materials.....................................................................................................................................................14
6.4 Piping Location and Support.................................................................................................................................14
6.5 Piping Leak Detection............................................................................................................................................14
6.6 Transition Sumps....................................................................................................................................................14
6.7 Intermediate Containment Sumps..........................................................................................................................14
6.8 Additional Valves...................................................................................................................................................15
7. Floating-Dock Piping..................................................................................................................... 15
7.1 General...................................................................................................................................................................15
7.2 Factors to Consider................................................................................................................................................15
7.3 Piping Materials.....................................................................................................................................................15
7.4 Piping Location and Support.................................................................................................................................15
7.5
A
Dock Transition Sump...........................................................................................................................................15
9. Floating-Dock-Dispenser Installation.............................................................................................. 16
9.1 General...................................................................................................................................................................16
9.2 Floating-Dock-Dispenser Installation....................................................................................................................16
9.2.1 Leak Detection..........................................................................................................................................17
9.2.2 Emergency Shutoff Valve.........................................................................................................................17
9.2.3 Pressure-Regulating Valve........................................................................................................................17
D
vi
Recommended Practices for the Installation of Marina Fueling Systems
11. Electrical...................................................................................................................................... 18
11.1 General...................................................................................................................................................................18
11.2 Electrical Codes.....................................................................................................................................................18
11.3 Emergency Shutoff Switches.................................................................................................................................18
11.4 Continuity...............................................................................................................................................................19
12. Installation and Pre-Operational Testing......................................................................................... 19
12.1 General...................................................................................................................................................................19
12.2 Testing During Installation.....................................................................................................................................19
12.3 Testing Prior to Operation......................................................................................................................................19
FT
13.1 General...................................................................................................................................................................21
13.2 Spill Prevention, Control, and Countermeasure (SPCC) Plans.............................................................................21
13.3 National Fire Protection Association (NFPA) Codes.............................................................................................21
13.4 International Code Council....................................................................................................................................21
vii
FT
This page is intentionally blank
A
R
D
Recommended Practices for the Installation of Marina Fueling Systems
FT
ing companies and regulatory agencies. In addition, the ible or suction pumps to move the fuel,
Committee has had the benefit of reasoned comments
• are located in fresh water or salt water, lake or river
submitted by parties interested in the marina fueling
environments, stable or fluctuating water-level
industry.
conditions, and along stable or fluctuating shore-
1.2 Background. Marina fueling facilities must lines,
perform safely, reliably, and economically in a very • have underground or aboveground storage tanks,
challenging environment. Corrosion, ultraviolet (UV)
radiation, heat, cold, and constant movement, which • have a dispensing device that is stationary or
can range from a few inches to many feet, each pres- mobile (e.g., a hydrant-type system with a mobile
ent engineering challenges that must be understood and fueling cart).
addressed. In addition, marina fueling systems may have These recommended practices do NOT apply to the fol-
to incorporate design elements to cope with hurricanes, lowing:
floods, or drastic water-level changes that are unusual
A
but foreseeable. The typical fuel-system installation
contractor does not construct marina fueling facilities on
• facilities where the storage tanks are in, on, or over
water (e.g., floating tanks, tanks located over water
a frequent basis. As a result, there is often little internal on piers or floating docks),
company experience to draw on when a marina project • facilities where the tank is mobile (e.g., on a
is undertaken. truck).
To date, there has been no industry standard that This document does not provide specifications for dock,
describes how to construct a marina fueling facility that
R
pier, wharf, or quay design, construction, or anchoring,
is protective of human health and the environment, sim- except in so far as the dock, pier, wharf, or quay provides
ple to construct, easy to maintain, and user-friendly for support for piping and other fuel-dispensing components
both the operator and the customer. Consequently, there such as dispensers and hose reels.
is no standard marina design, and many marina facilities
show evidence of having been cobbled together. 1.5 Sources. The recommended practices in this
document constitute a synthesis of literature published
1.3 Purpose. The purpose of this document is to by equipment manufacturers, regulatory requirements
provide a basic reference that conveys concrete, authori- from various jurisdictions across the country, and the
D
tative guidance on how to deal with the challenges of extensive knowledge and experience of the members of
constructing safe, environmentally protective marina the PEI Marina Fueling System Installation Committee.
fueling facilities that will allow reliable and economi-
cal service for many years. This document offers rec- 1.6 Use of Other PEI Recommended Practices.
ommendations for materials, designs, and installation Many aspects of marina fuel-storage and dispensing
procedures suitable for a wide variety of marine environ- systems are not described in this document. Refer to the
ments, including: following PEI documents for additional practices and
procedures related to petroleum-storage systems:
• fresh and salt water
• RP100, Recommended Practices for Installation of
• still and moving water
Underground Liquid Storage Systems
• stable, tidal, and fluctuating water levels.
PEI Recommended Practices 1000-09
• RP200, Recommended Practices for Installation of arina-fueling-system project to determine the appli-
m
Aboveground Storage Systems for Motor-Vehicle cable regulatory requirements.
Fueling
1.8 Listing of Marina Piping. Marina piping must
• RP300, Recommended Practices for Installation operate in a severe environment. In addition to the
and Testing of Vapor-Recovery Systems at Vehicle- usual requirements for fuel compatibility and structural
Fueling Sites (Stage I vapor recovery only) soundness, marina piping may be required to withstand
• RP400, Recommended Procedure for Testing Elec- frequent flexing, physical impact, fire exposure, and
trical Continuity of Fuel-Dispensing Hanging ultraviolet (UV) radiation. Despite the harshness of the
Hardware marina environment, suitable equipment is available.
• RP500, Recommended Practices for Inspection Many fueling-system regulations specify that product
FT
and Maintenance of Motor Fuel Dispensing Equip- piping must bear a listing from a nationally recognized
ment testing organization such as Underwriters Laboratories
(UL), Underwriters Laboratories of Canada (ULC),
• RP600, Recommended Practices for Overfill Pre-
Factory Mutual, or similar organizations. As of the pub-
vention for Shop-Fabricated Aboveground Tanks
lication date of this document, the PEI Marina Fueling
• RP900, Recommended Practices for the Inspection System Installation Committee knows of no recognized
and Maintenance of UST Systems. standard published by a listing organization that can be
used to evaluate marina piping performance. This lack of
1.7 Regulations and Codes. There are a variety of a testing standard makes it impossible for marina piping
regulations and codes that apply to marina fueling facili- to be listed.
ties. These may include, but are not limited to:
• National Fire Protection Association (NFPA) Codes In developing this document, the PEI Marina Fueling
30 and 30A System Installation Committee has used its best judg-
ment in describing certain types of piping products that
A
• International Fire Code (IFC) Chapters 22 and 34
• Federal, state, and local Spill Prevention, Control,
the Committee believes are acceptable for use in marina
environments and approved by the piping manufacturer
and Countermeasure (SPCC) programs for use in marina applications.
• Coast Guard regulations (e.g., Title 33 CFR, section 1.9 Importance of Competent Installers and
154) Technicians. The design and construction of marina
fueling facilities is a specialized craft requiring knowl-
• Army Corps of Engineers (e.g., Title 33 USC,
edge and skills that are unique to these types of facilities.
R
sections 403, 1344, and 1413)
Only knowledgeable, experienced, competent contrac-
• Federal underground tank rules (Title 40 CFR, tors should undertake marina-fueling-system projects.
section 280) Only qualified technicians should perform maintenance
or repair tasks involving the fuel handling, electrical, or
• State underground and aboveground storage tank
electronic components of marina fueling systems.
rules
• National Electrical Code (NEC) NFPA 70. 1.10 Importance of Competent Operators. The on-
site presence of knowledgeable and conscientious facil-
D
Many jurisdictions also have state or local regulations ity operators is key to the reliable and safe operation
that apply to marina facilities. of marina fueling systems. Personnel responsible for
marina fueling systems should be taught how to safely
While the general requirements of regulatory authorities operate these systems and to properly respond to emer-
are similar, specific requirements may differ from juris- gency situations. Refer to Chapter 14 for further guid-
diction to jurisdiction. The PEI Marina Fueling System ance concerning the training of facility personnel.
Installation Committee has not attempted to describe or
interpret specific regulatory requirements in this docu-
ment. Following the guidance presented in this docu-
ment does not guarantee compliance with national, state,
or local codes or regulations. Consult with the authori-
ties having jurisdiction during the planning phases of a
Recommended Practices for the Installation of Marina Fueling Systems
FT
2.2 Approved. Acceptable to the organization, office,
shoreline, that is typically of timber construction.
or individual responsible for approving equipment,
materials, an installation, or a procedure. • Quay – A fixed structure, generally parallel to a
shoreline, that is typically constructed of stone or
2.3 Attended Marina Fueling Facility. A marina earthen fill.
fueling facility where an employee of the marina is pres-
ent to monitor fueling operations whenever the facility 2.8 Downstream. A term used to define the relative
is open for business. The employee typically does not position of piping components in a fuel-distribution
dispense the motor fuel but assists and instructs the boat system. The position is defined relative to the direction
owner or the owner’s representative in the fueling opera- of fuel flow inside the piping. For example, if a safety-
tion. break fitting is “downstream” of a solenoid valve, then
the fuel flowing through the piping would first pass
2.4 Authority Having Jurisdiction (AHJ). An orga- through the solenoid valve and then through the safety-
nization, office, or individual responsible for enforcing break fitting. See also “Upstream.”
the requirements of a code or standard, or for approving
A
equipment, materials, an installation, or a procedure. 2.9 Flexible Pipe. A hollow cylinder, used to convey
motor fuel, that can be bent into curves without damag-
2.5 Dispenser. A device that generally provides the ing the walls of the cylinder. Flexible piping typically
transition point between the marina fuel piping and the has a bend radius of less than 2 feet and can be subjected
hose to which the nozzle is attached. A dispenser usually to significant movement after installation.
includes a metering device to measure the quantity of
fuel dispensed, a control switch that supplies power to 2.10 Fueling System. A generic term that includes all
components of a fuel-storage and distribution system
R
the pump, and a receptacle to hold a fuel nozzle when it
is not in use. A dispenser may consist of any of the fol- from the fill riser through the tank, pump, piping, fit-
lowing: tings, dispenser, hose, and nozzle.
• a cabinet similar to that used for automobile fuel- 2.11 Gangway. A bridge-like structure that allows
ing, with or without a hose reel, access between a floating dock and a fixed structure
• a meter mounted on a stand with a control switch or between two floating docks. The gangway may also
and receptacle to hold a fuel nozzle, provide support for fuel piping and other utilities that
service the floating dock.
D
PEI Recommended Practices 1000-09
FT
2.15 Onshore. Land immediately adjacent to a body of in accordance with PEI/RP100, Recommended Practices
water that is higher than the ordinary high-water mark. for Installation of Underground Liquid Storage Sys-
tems, manufacturer’s instructions, and applicable codes.
2.16 Qualified Technician. A person trained to evalu- Because marina fuel tanks are located near a navigable
ate, maintain, and repair all aspects of marina fueling water body, all underground tanks used for marina fuel
systems. systems should be of double-walled construction. If the
tank is located in a high groundwater area or a mapped
2.17 Rigid Pipe. A hollow cylinder used to convey
flood zone, provide mechanical anchoring for the tank.
motor fuel and designed not to bend to any significant
Design the tank-anchoring system to withstand full sub-
degree after installation. Rigid pipe typically has a bend
mergence of the tank. Preferred methods for anchoring
radius of 50 feet or more.
marina tanks involve the installation of either deadmen
2.18 Safety Break. A device, installed at strategic or a concrete pad under the tank. Refer to PEI/RP100 for
locations in marina fuel piping, which is designed to sep- further information concerning these anchoring meth-
arate when excessive pulling force is placed on the pipe. ods. Make provisions to resist flooding damage (e.g.,
A
Valves within each end of the safety break automatically
close when the device separates, minimizing the release
providing lockable, water-tight caps on all tank risers
except the vent riser).
of fuel from the piping. A safety break is intended to
The weight of flood waters can substantially increase
protect the piping from damage when the movement of a
the external pressure on an underground tank. The tank
floating dock exceeds the design limits. Also known as a
should be designed to withstand the pressures created by
“breakaway.”
the tank burial depth plus the anticipated depth of flood
R
2.19 Semi-Rigid Pipe. A hollow cylinder used to con-
vey motor fuel that can be bent into gentle curves
without damaging the walls of the cylinder. Semi-rigid
pipe typically has a bend radius in the range of 3 to 10
feet and can be subjected to significant movement after
installation.
2.21 Vessel. Every kind of watercraft or other device Figure 3-1. Keeping water out of sumps is critical for
that can be used as a means of transportation on water. effective leak detection. A slight crown on the concrete
sloping away from sump covers will help keep precipita-
tion out of sumps.
Recommended Practices for the Installation of Marina Fueling Systems
FT
barriers to prevent vehicles from
driving over it. If driving marina Figure 3-2. Traffic loads on underground fuel tanks and piping at marinas may be
equipment over the tank cover much greater than traffic loads at a typical gas station. Marina traffic patterns may
pad cannot be avoided, design also be unpredictable. Design underground storage systems to support the maxi-
the cover pad so that it safely mum anticipated loads or place barriers such as bollards to keep heavy vehicles a
carries the weight of vessel- safe distance away from buried storage system components.
moving equipment loaded to
maximum capacity.
supported and the foundation will not be eroded away or The following underground-piping practices are specific
washed out under flooding conditions. to marina fueling systems:
If the tank is located in a hurricane or other high-wind • Because marina fuel-storage systems are located
zone, design a tank-anchoring system that will withstand near a navigable water body, all underground prod-
the maximum anticipated wind conditions with the tank uct piping should be of double-walled construc-
empty of product. tion.
• The industry standard practice of maintaining a
NOTE: Refer to flood maps provided by FEMA continuous slope from the dispenser to the tank
(www.fema.gov) to determine the flooding risk is oftentimes not possible for marina fueling sys-
for a particular underground or aboveground tank tems. However, as long as the outer wall of the
location. piping is liquid-tight, leaked product will flow to
PEI Recommended Practices 1000-09
a containment sump, regardless of the slope of the changes that will likely occur in the above-grade
piping. Equip every containment sump with a con- portions of the piping on the dock will be beyond
tinuously monitored sensor placed on the bottom of the design parameters of the leak detector and will
the sump. Maintain a uniform slope for as much of produce unreliable results. In addition, monitoring
the piping as feasible, whether the slope is toward the aboveground portion of the piping may also
the tank or toward the dispenser. To the extent prac- substantially increase the volume of the piping to
tical, minimize the number of times the direction of be monitored. The increased piping volume may
the piping slope changes. exceed the rated capacity of available line-leak
detectors.
4.2.1 Leak Detection for Underground Piping.
Provide secondary containment for all underground If either of these situations is a concern, it is per-
product piping. Install single-walled, product-con- missible to install a time delay on the normally
FT
taining valves, fittings, and joints in liquid-tight closed solenoid valve installed in the onshore tran-
sumps. Install continuously monitored liquid sen- sition sump (see below). The purpose of the time
sors in the bottom of each containment sump. delay is to isolate the underground piping from the
aboveground piping on the dock by keeping the
NOTE: Welded steel joints, double-walled FRP solenoid valve closed while the mechanical line-
pipe joints, or thermo-welded plastic pipe joints leak detector is conducting a test.
that include integral secondary containment do not
If an electronic line-leak detector is installed, wire
need to be installed in containment sumps.
the normally closed solenoid valve in the transition
sump so that the valve will be closed while the
Provide a containment sump at all low points in electronic line-leak detector is conducting a test.
double-walled piping. A containment sump is not
If a suction pump is used to dispense product at a
required when piping transitions from underground
marina, it is likely that the pump will be at a lower
to aboveground if the transition point is above
elevation than the product in the tank. If this is the
double-walled pipe.
A
ground and is a high point for the underground
case, installing a check valve at the pump will not
provide protection against leaks, and the following
If a submersible pump is used, install a listed actions will be required.
mechanical or electronic line-leak detector. If an
• Install double-walled piping with continuously
electronic line-leak detector is installed, it should
monitored sensors in the bottom of each contain-
provide positive pump shutdown if a leak rate
ment sump to provide leak detection.
of 3 gallons per hour or greater is detected. The
R
electronic line-leak detector should also provide • Install a pressure-regulating valve at the pump
positive pump shutdown if a leak rate of 0.2 gal- and an anti-siphon valve (see below) at the
lons per hour or greater is detected. If the piping tank.
system includes an anti-siphon valve (see below) at • Extend the vent for both the pressure-regulating
the tank, install the leak detector in an appropriate valve and the suction pump air eliminator back
fitting immediately downstream of the anti-siphon to the tank or to an elevation that is higher than
valve. Verify that the line-leak detector is certified the highest point of the storage tank or product
to function with the type of fuel that will be stored piping.
D
Recommended Practices for the Installation of Marina Fueling Systems
FT
piping materials (e.g., stainless steel) or appropri- Control power to the anti-siphon valve with the
ate corrosion-protection measures (e.g., durable facility emergency stop switch(es) as well as the
paint) for onshore, aboveground piping. fueling-system controls so that the anti-siphon
valve will close when an emergency stop switch is
• Maintaining a continuous slope from the dispenser activated.
to the tank is oftentimes not possible for marina
fueling systems. Maintain a uniform slope for as 4.4.2 Block Valves and Safety Break. If the
much of the piping as feasible, whether the slope piping includes a transition from onshore to over-
is toward the tank or toward the dispenser. To the water, provide a fully ported ball valve and safety-
extent practical, minimize the number of times the break valve at a stable point just onshore of where
direction of the piping slope changes. the piping transitions to over-the-water. Install
the safety break according to the manufacturer’s
4.3.1 Leak Detection for Aboveground Piping. instructions.
If piping is clearly visible, frequent visual inspec-
tion is sufficient for leak detection. If any portion If the ball valve and safety break are underground,
A
of the onshore aboveground piping is not clearly
visible, use double-walled pipe with continuously
or if they are aboveground but not clearly visible,
contain them in a continuously monitored liquid-
monitored sumps to provide leak detection for this tight transition sump. The transition sump may be
portion of the pipe. constructed of polyethylene, fiberglass, corrosion-
protected carbon steel, or stainless steel. If located
NOTE: Line-leak detectors designed for use on aboveground, the transition sump must be solidly
underground piping systems may be installed on supported. If located underground, install the sump
according to the manufacturer’s instructions. If
R
aboveground pipe. However, they may be subject
to frequent false alarms and erratic operation. The the sump is subject to floatation from high-water
PEI Marina Fueling System Installation Committee levels, it may require anchoring or ballasting. Use
does not recommend the use of line-leak detectors anchoring or ballasting methods approved by the
designed for underground piping systems to pro- sump manufacturer.
vide leak detection for aboveground pipe. If the transition sump is underground, provide
a chase for the downstream piping between the
sump and the point where the piping transitions to
4.4 Special Requirements for Underground and
D
PEI Recommended Practices 1000-09
Water-Tight Cover
Sump
FT
Solenoid Pipe Sleeve
Valve
Ball
Double-Wall Valve Safety
Pipe to Tank Break
Liquid
Entry Boot Sensor
(typical) Double-Wall
Pipe to Dock
Figure
Figure4-1.
4-1.Onshore
The onshore
A
Transition Sump.
transition sump provides containment and leak detection for several important components
of a marina piping system. The ball valve permits manual isolation of the dock piping. The normally-closed solenoid
valve provides for isolation of the shore piping to improve the performance of the line leak detector. The safety break
protects the shore piping and helps prevent a release in case of a major accident on the dock. All sump penetrations
are made using liquid tight entry boots.
way cover may be installed at finished grade while late and drain portions of the fuel piping at risk of being
R
the top surface of the concrete slab is a few inches damaged. If any of these conditions are anticipated, pro-
below finished grade. This will allow the concrete vide valves and fittings at strategic locations so that the
slab to be covered with grass, decking, or other fuel piping can be conveniently drained.
cosmetic cover.
NOTE: Do not use
If the ball valve and safety break are abovegroundgalvanized pipe or
and clearly visible they do not need to be contained
fittings for diesel-fuel
in a sump. The piping downstream of the applications.
safety
break must be straight so that any tensional The stress 5. Gangway Piping
D
following
placed on the piping will produce a force parallelaboveground piping
to the long axis of the safety break. 5.1 General. One of the most challenging aspects of
practices are specific
to marina marina-fueling-system
fueling design is the routing of the pip-
4.5 Seasonal Factors or Weather Emergencies. In ing between the shore and a floating dock. This portion
systems.
colder climates, most marinas operate on a seasonal of the fueling system is especially challenging when the
• All aboveground
basis, and floating docks may need to be taken ashore in elevation of the floating dock changes significantly due
piping materials
the winter to protect them from storms or ice. In warmer to water-level changes. This chapter describes design
should be structurally
climates, marinas may be threatened by hurricanes. If factors to consider and recommends materials, valves,
sound and resistant to
floating docks containing fuel piping are to be taken fittings, and installation techniques for the fuel pip-
fire and corrosion.
ashore or if a fueling facility is to be idle for an extended ing at the shore-to-gangway and the gangway-to-dock
period, it is advisable to drain the piping. Likewise, Because
if marina
transition.
severe weather is imminent, it may be advisable to iso- storage-tank systems
will be near water,
corrosion resistance
is an especially
important
consideration. Use
Recommended Practices for the Installation of Marina Fueling Systems
Onshore Gangway
Transition
Tank Sump
Floating Dock
Dock
FT
Transition
Sump
Figure 5-1.
Figure 5-1. This drawing shows the major elements of a marina fueling system, including double-walled piping,
containment sumps, and support of the piping under the gangway. This drawing illustrates gangway piping Design #1.
5.2 Factors to Consider. There are many potential tions. Pipe construction should include secondary con-
hazards to fuel piping at the transition from the shore tainment, either factory assembled or field constructed.
to a floating dock. Piping must be able to withstand a
corrosive environment, be resistant to fire and ultra- 5.4 Piping Design. There are many possible designs
violet (UV) radiation, and be protected against physical for product piping between the shore and a floating dock.
A
damage. Piping must also be flexible enough to accom-
modate conditions such as small-scale movement due
As a general principle, piping designs that minimize the
number of joints are preferred. Three acceptable designs
are described below. The range of water-level changes
to wave action, movement of people on the dock, and
larger-scale movement due to seasonal water-level varia- indicated for each design are intended to provide gen-
tions or periodic tidal changes. eral guidance and are not limits on the application of a
specific design. Designs other than those presented here
Designing and constructing a functional and safe system may be as good or better for specific applications, but
requires careful selection of piping materials, knowl- the PEI Marina Fueling System Installation Committee
R
edge of the normal and maximum anticipated range of believes that the general principles on which the designs
motion of the dock, and a detailed plan for supporting described here are based can be applied to a wide variety
the piping while still providing for the required amount of marina facilities.
of flexibility.
5.4.1 Design #1: Piping Securely Fastened to
The piping design should also include appropriate valves the Gangway. This piping design is most practi-
and fittings to improve safety, provide for leak detection, cal where vertical movement of the dock relative
facilitate maintenance, permit draining and disconnec- to the shore is generally small (in the range of
D
tion of piping for seasonal removal of the dock, and/or inches to several feet). This piping design uses
prepare for a severe storm event. In all cases, the piping double-walled, semi-rigid or flexible product pip-
should include double-walled construction provided by ing securely fastened to the gangway framework.
the manufacturer or field-installed secondary contain- The flexibility required at each end of the gangway
ment provided by the installer. where the movement of the piping is the greatest is
provided by the piping itself. Consult with the pip-
5.3 Piping Materials. Selection of appropriate piping ing manufacturer to determine whether this type of
materials for the gangway portion of the product piping application is acceptable.
is a critical step in the design of a marina-fuel-piping
Product piping is typically run beneath the gang-
system. Use flexible or semi-rigid pipe approved by the
way, though it may also be installed along the side
manufacturer and the authority having jurisdiction for
of the gangway. Flexible and semi-rigid product
aboveground, over-water, or underwater marina applica-
PEI Recommended Practices 1000-09
FT
Figure 5-4. This photograph illustrates a variation on
gangway piping Design #1. The piping is supported by
“trapezes” consisting of galvanized steel pipe inside a
Figure 5-2. This photograph illustrates gangway pip- PVC sleeve.
ing Design #1. The fuel piping is clamped to support bars
hung from the gangway framework. If piping will be exposed beneath or beside the
gangway, install the product pipe within a protec-
tive sleeve (e.g., PVC), or provide other protection
against physical damage. In some cases, the piping
manufacturer may indicate that the piping needs no
additional protection, even in relatively exposed
A locations, because protection from physical dam-
age is inherent in the piping design. If this is the
case, follow the piping manufacturer’s installation
recommendations. In all cases, install the piping so
it is protected from chafing, pinching, kinking, and
crushing against shore, gangway, or dock compo-
nents.
R
5.4.2 Design #2: Piping Flexibly Supported
by Gangway. This piping design is most practical
Figure 5-3. This photograph illustrates gangway piping where vertical movement of the dock relative to
Design #1. The fuel piping is supported by a PVC sleeve the shore is moderate (in the range of 3 to 10 feet).
attached to the gangway framework. This piping design uses double-walled, semi-rigid
or flexible product piping suspended beneath the
piping may be attached directly to the gangway gangway framework in an “S” shape. The width
framework or it may be installed inside a rigid, cor- of the “S” shape and the number of “S” curves
D
rosion-resistant sleeve (e.g., PVC). The sleeve is must provide sufficient slack to accommodate the
supported using pipe straps made of stainless steel anticipated range of movement of the dock. The
or other non-corrosive material or commercially “S” shape may have a vertical or horizontal orien-
available steel support systems that are galvanized, tation.
painted, or otherwise protected against corrosion.
Where feasible, the minimum spacing between par- In this design, the piping is suspended from the
allel product pipes should be equal to the diameter gangway using hardware provided or recommended
of the pipe or the pipe sleeve. by the piping manufacturer. The piping should be
suspended sufficiently below the gangway frame-
Install the pipe on the gangway so as to provide as work to provide the required freedom of movement
much protection from physical damage as practical. of the pipe. In this design, the piping is relatively
A common protected location is between the struc- exposed beneath the gangway. Verify with the
tural supports running the length of the gangway. piping manufacturer that the design of the piping
10
Recommended Practices for the Installation of Marina Fueling Systems
Onshore
Transition
Sump Gangway
Dock
Transition
Sump
FT
SIDE VIEW
Floating Dock
Hanger Detail
Shore Gangway
Dock
TOP VIEW
Figure
Figure5-2.
A
5-5. Design #2 for the gangway piping provides for a greater vertical change in the dock elevation by incor-
porating “S” curves in the piping beneath the gangway.
11
PEI Recommended Practices 1000-09
Onshore
Transition
Sump
Dock
Transition
Floating Dock
Sump
FT
Flexible Double-Wall
Piping
Figure
Figure5-3.
5-7. Design #3 for providing fuel to a floating dock does not depend on the gangway for support. This design
is particularly well suited for facilities with a large tidal range.
D
exits the wharf, quay, or pier horizontally. When is suitable for immersion in water and has sufficient
it is necessary to protect the piping from kinking, structural integrity to be installed in a relatively
provide a support saddle where the piping turns exposed location without additional protection. In
from horizontal to vertical so that the piping is all cases, install the piping so it is protected from
evenly supported with a bend radius consistent chafing, pinching, kinking, and crushing against
with the manufacturer’s recommendations. When shore, gangway, or dock components.
necessary, provide another support saddle at the
point where the piping enters the pipe chase that 5.5 Dock Transition Sump. Provide a transition
leads to the dock transition sump. sump on the dock as close as feasible to where the pip-
ing enters the dock. The dock transition sump may also
Verify with the piping manufacturer that the piping serve as a dispenser sump if a dispenser is required in
12
Recommended Practices for the Installation of Marina Fueling Systems
Water-Tight Cover
Sump
FT
Pipe Sleeve
Ball
Safety Valve Double-Wall Pipe
Break to Dispenser
Liquid
Sensor Entry Boot
Double-Wall (typical)
Pipe to Shore
Figure
Figure4-2.
5-8.Dock
The dock
A
Transition Sump.
transition sump is located near the shore end of the dock and provides containment and
leak detection for the piping components it contains as well as the adjacent lengths of double-walled pipe. All sump
penetrations are made using liquid tight entry boots.
this location and the combination transition/dispenser sump provides leak detection for the gangway piping.
sump is big enough to accommodate all of the required Install a continuously monitored sensor in the bottom
components. Generally acceptable materials for the dock of the sump. If the sensor includes a float-based sensing
R
transition sump include polyethylene, fiberglass, stain- mechanism, mount the sensor securely in a vertical ori-
less steel, and carbon steel protected against corrosion. entation so it will operate properly. Mount the sensor at
When selecting a sump material observe the following the lowest part of the sump to provide timely notification
cautions. of a leak.
• Be sure the sump is suitably reinforced and designed 5.7 Valves and Fittings. Install a safety-break fitting
for a submerged application. and a fully ported ball valve in the dock transition sump.
• If fiberglass or polyethylene sumps will be exposed Fittings and valves installed in the sump should be made
D
to direct sunlight, be sure they are treated to pro- of corrosion-resistant materials. Install the safety break
vide protection from ultraviolet (UV) radiation. according to the manufacturer’s instructions. Provide
a chase for the upstream piping between the sump and
Locate the sump below the dock surface and provide a the point where the piping enters the dock. The product
water-tight lid that can be secured so it will not be dis- piping should fit loosely in the chase; the chase diameter
lodged by wave action. Provide a cover for the sump that should be at least twice the piping diameter. The piping
is flush with the deck surface and designed to support the upstream of the dock transition sump must be straight
people and equipment that will travel over it. and in line with the safety break in the sump so that any
tensional stress placed on the piping will produce a force
5.6 Piping Leak Detection. Product piping con- parallel to the long axis of the safety break.
necting the shore to the dock should be secondarily
contained. The sensor mounted in the dock transition
13
PEI Recommended Practices 1000-09
FT
of the structure would be minimal. spacing between parallel product pipes should be equal
to the diameter of the pipe or the pipe sleeve.
6.2 Factors to Consider. Piping on a pier, wharf, or
quay must be able to withstand a corrosive environment, 6.5 Piping Leak Detection. Product piping should be
be resistant to fire and ultraviolet (UV) radiation, and secondarily contained. Install a liquid-tight containment
be protected against physical damage. Designing and sump beneath each dispenser. Equip each dispenser sump
constructing a functional and safe system requires care- with a continuously monitored liquid sensor installed at
ful selection of piping materials and a detailed plan for the bottom of the sump.
protecting and supporting the piping.
Generally acceptable materials for the dispenser sump
The piping design should also include appropriate valves include polyethylene, fiberglass, stainless steel, and car-
and fittings to improve safety, provide for leak detection, bon steel protected against corrosion. When selecting a
facilitate maintenance, permit the draining and discon- sump material observe the following cautions.
nection of piping for seasonal closing of the facility, and
• If the sump will extend below the highest antici-
prepare for a severe storm event. In all cases, the piping
A
should include double-walled construction either pro-
vided by the manufacturer or field-installed secondary
pated water level, be sure it is suitably reinforced
and designed for a submerged application.
containment provided by the installer. • If fiberglass or polyethylene sumps will be exposed
to direct sunlight, be sure they are treated to pro-
6.3 Piping Materials. Selection of appropriate piping vide protection from ultraviolet (UV) radiation.
materials for a pier, wharf, or quay is a critical step in
the design of a marina-fuel-piping system. Use flexible, Maintaining a continuous slope in the piping is often-
times not possible for marina fueling systems. Maintain
R
rigid, or semi-rigid pipe approved by the manufacturer
and the authority having jurisdiction for aboveground, a uniform slope for as much of the piping as feasible,
over-water, or underwater marina applications. Pipe con- whether the slope is toward the tank or toward the dis-
struction should include secondary containment, either penser. To the extent practical, minimize the number of
factory assembled or field constructed. times the direction of the piping slope changes. As long
as the outer wall of the piping is liquid-tight, leaked
NOTE: Do not use galvanized pipe or fittings for product will flow to a containment sump, regardless of
diesel-fuel applications. the slope of the piping.
D
14
Recommended Practices for the Installation of Marina Fueling Systems
Mount the intermediate sump so that it is firmly sup- 7.3 Piping Materials. Selection of appropriate piping
ported by the pier, wharf, or quay framework. Provide materials for the floating dock is a critical step in the
the sump with a water-tight cover that is flush with design of a marina-fuel-piping system. If the floating
the decking. Alternatively, the sump cover may be just dock consists of a reasonably stable platform, require-
below the pier, wharf, or quay decking, with a removable ments for piping flexibility are minimal and both flex-
section of decking above it. ible and semi-rigid piping materials are acceptable. Use
flexible or semi-rigid pipe approved by the manufacturer
6.8 Additional Valves. Consider installing ball valves and the authority having jurisdiction for aboveground,
in containment sumps, as needed, to facilitate isolation over-water, or underwater marina applications. Pipe con-
of segments of the piping system for maintenance, repair, struction should include secondary containment, either
or draining of the piping. Fittings and valves installed in factory assembled or field constructed.
the sump should be of corrosion-resistant materials.
FT
NOTE: Do not use galvanized pipe or fittings for
diesel-fuel applications.
15
PEI Recommended Practices 1000-09
FT
or to an elevation that is higher than the highest
Install dispensers on a firm foundation according to the point of the storage tank or product piping.
manufacturer’s recommendations and industry standard
practices. Depending on the pier, wharf, or quay con- 8.2.4 Dispenser Anchoring. Marina fuel dis-
struction, dispensers may be installed on a concrete base pensers may be located in a flood zone or may be
similar to a standard dispenser island at an automotive subject to higher wind loads than typical automotive
gas station or they may be securely anchored to the struc- dispensers. Dispensers should be securely bolted to
tural framework of the pier, wharf, or quay. a solid base using corrosion-resistant hardware.
Refer to the dispenser manufacturer’s installation
8.2.1 Leak Detection. Install the piping beneath instructions for specific anchoring requirements.
the dispenser in a containment sump with a continu-
ously monitored sensor. If the dispenser is mounted NOTE: Some authorities having jurisdiction may
on an elevated platform, be sure the containment require wind loading and flood-zone analysis.
sump will capture any drips or leaks that may occur
from components within the dispenser cabinet.
A
Generally acceptable materials for a pier, wharf, or
quay dispenser sump include polyethylene, fiber-
glass, stainless steel, and carbon steel protected
against corrosion. When selecting a sump material
observe the following cautions.
9. Floating-Dock-
• If the fill material beneath a quay is rocky or
Dispenser Installation
R
provides an uneven foundation, select a sump 9.1 General. Dispensers mounted on a floating dock
material such as steel that does not require uni- present special challenges. They are exposed to wind
form support. and weather and may be installed close to the water
level, increasing the importance of corrosion-protection
• If the sump will extend below the highest antici-
measures and proper electrical work. Because they are
pated water level, be sure it is suitably reinforced
located directly over the water, containment of leaks and
and designed for a submerged application.
drips from dispensers on floating docks is very impor-
• If fiberglass or polyethylene sumps will be tant.
exposed to direct sunlight, be sure they are
D
16
Recommended Practices for the Installation of Marina Fueling Systems
has sufficient structural integrity, the dispenser platform an elevation that is higher than the highest point of
can be created by extending the sides of the containment the storage tank or product piping.
sump vertically and including a means of attaching the
9.2.4 Dispenser Anchoring. Marina fuel dis-
base of the dispenser cabinet to the top of the contain-
pensers may be located in a flood zone or be sub-
ment sump. If a dispenser platform is used, securely
ject to higher wind loads than typical automotive
anchor the platform to the structural framework of the
dispensers. Dispensers should be securely bolted
dock, and securely anchor the dispenser cabinet to the
to a solid base using corrosion-resistant hardware.
dispenser platform.
Refer to the dispenser manufacturer’s installation
9.2.1 Leak Detection. Install dispensers on instructions for specific anchoring requirements.
floating docks over a liquid-tight containment
sump with a continuously monitored sensor in the NOTE: Some authorities having jurisdiction may
FT
bottom of the sump. Generally acceptable materi- require wind loading and flood-zone analysis.
als for a floating-dock-dispenser sump include
polyethylene, fiberglass, stainless steel, and carbon
steel protected against corrosion. When selecting a
sump material observe the following cautions.
• If the sump will extend below the water level, be
sure it is suitably reinforced and designed for a 10. Dispensing Hose
submerged application.
and Nozzles
• If fiberglass or polyethylene sumps will be
exposed to direct sunlight, be sure they are 10.1 General. Selecting the appropriate hose length,
treated to provide protection from ultraviolet hose-stowing method, and nozzle features for a marina
(UV) radiation. fueling system are important for both safety and the
prevention of spills. Hose materials must be able to with-
A
If the dispenser is mounted on an elevated plat-
form, be sure the containment sump will capture
stand a variety of fuels and in some cases severe expo-
sure to ultraviolet (UV) radiation. Issues such as pressure
any drips or leaks that may occur from components relief and strain relief also need to be addressed.
within the dispenser cabinet. Fasten the sump
securely to the dock framework. 10.2 Hose Materials. Use hoses approved by the
manufacturer for marina use. Hose materials must be
9.2.2 Emergency Shutoff Valve. Install a dou-
compatible with the fuel being dispensed, have low
ble-poppet emergency shutoff valve at the base of
permeation, tolerate heat and cold, and be resistant to
R
any dispenser connected to a pressurized-piping
ultraviolet (UV) radiation. Hoses with colored outer
system. The base of the emergency shutoff valve
coverings are often preferred because they will not mar
must be securely anchored, and the shear section
the finish of the vessel being fueled.
of the shutoff valve should be at the appropriate
height so that the shear section will operate as
NOTE: If Coast Guard approval of the hose is
designed. Install the shutoff valve so that the trip
required, ask the manufacturer to supply hose that
mechanism can operate freely and the test plug
has been tested to Coast Guard specifications.
is readily accessible after the dispenser cabinet is
D
installed.
9.2.3 Pressure-Regulating Valve. Install a 10.3 Stowing the Hose. A typical marine-fueling facil-
pressure-regulating valve at the base of any dis- ity must be prepared to service vessels of many different
pensing device that contains a suction pump where types and sizes. To accomplish this, a substantial length
any portion of the fuel tank or fuel piping is at a of dispensing hose is typically provided. Measures to
higher elevation than the base of the pump. Select protect lengthy marina hoses from physical damage and
a pressure-regulating valve that incorporates a minimize the trip hazard to personnel using the fueling
shear section. Mount the pressure-regulating valve facility are usually required. To safely stow dispensing
securely and at the appropriate height so that the hose when it is not in use, provide a hose reel or sturdy
shear section will operate as designed. Extend the stanchion.
atmospheric vents for the pressure-regulating valve Hose reels should be designed for use in the corrosive
and the air eliminator back to the storage tank or to marine environment. Position the hose reel adjacent to
17
PEI Recommended Practices 1000-09
FT
with the type of fuel to be dispensed and can provide the
design fuel-flow rate. Marina nozzles should incorporate
features that will help minimize the potential for fuel
spills and drips. Nozzles should not be left unattended
Figure 10-1. Proper stowage protects marina fuel hoses during marina fueling operations. Remove hold-open
from physical damage and minimizes tripping hazards. latch devices from nozzles intended for marina service.
Hose reels are convenient to use and encourage the proper
stowage of hoses and nozzles.
18
Recommended Practices for the Installation of Marina Fueling Systems
FT
marina fueling systems.
NOTE: Procedures described in PEI/RP400, Rec- the absence of manufacturer’s instructions, follow the
ommended Procedure for Testing Electrical Conti- procedures in the applicable PEI recommended practice.
nuity of Fuel-Dispensing Hanging Hardware can Consider having a third party conduct the testing to pro-
be used to verify the continuity of dispensing hoses tect the interests of both the installation contractor and
and nozzles with the dispenser cabinet. the facility owner. Document test results and provide
them to the facility owner. The installer should retain
a copy of the test results with the facility installation
records.
19
PEI Recommended Practices 1000-09
Double-walled piping Tightness test primary piping. Air/soap test secondary piping according to
manufacturer’s instructions or RP100.
Containment sumps Hydrostatically test all sumps according to manufacturer’s instructions or RP100.
Leak-detection sensors Verify ability to detect water and/or product, as applicable, according to RP900.
Automatic tank gauges Verify setup parameters (e.g., tank size, construction, tilt) and calibration. If
periodic testing with the tank gauge is to be used for leak detection in underground
FT
tanks, verify that the appropriate testing interval has been programmed (e.g., daily,
weekly, or monthly). Refer to RP900.
Overfill-prevention devices Verify that the device is set at the proper height and test for proper operation
according to RP900. Aboveground tanks should have more than one overfill-
prevention device (see RP600).
Spill-containment manholes Check the operation of the liquid drain (if present) and the clearance between the
fill-pipe cap and the containment-manhole cover. Remove liquids, trash, installation
aids, etc. Refer to RP900.
Emergency-shutoff valves Verify that the valve is securely anchored and that the valve mechanism operates
freely. Check the level of the shear section relative to the base of the dispenser.
Test the operation of the valve according to RP900.
Mechanical line-leak detectors Verify the ability of the leak detector to detect a 3 gallon per hour leak according to
A the manufacturer’s instructions or RP900. If a solenoid valve is used to isolate a
portion of the piping for testing, verify the operation of the solenoid valve.
Electronic line-leak detectors Verify setup parameters (e.g., piping length, diameter, type). Test the leak detector
for the ability to detect a simulated leak of 3 gallons per hour according to the
manufacturer’s instructions or RP900. If a solenoid valve is used to isolate a
portion of the piping for testing, verify the operation of the solenoid valve.
Hanging hardware Test the electrical continuity of the hanging hardware, including any hose mounted
R
on reels, using the procedures described in RP400.
Continuity Test the continuity of grounding wire(s) from dispenser(s) back to the facility earth
ground.
Nozzles Verify that the nozzle hold-open latch mechanism has been removed. Test the
operation of the flow shut-off mechanism according to RP500.
Cathodic protection Verify the continuity/isolation of system components according to RP100. Measure
structure-to-soil potentials and rectifier output according to RP100.
Anti-siphon and solenoid valves Verify the operation of anti-siphon valves and solenoid valves in sumps.
Emergency shutoff switches Test the operation of the emergency shutoff switch and verify that activation of the
switch cuts power to all pumps, dispensers, solenoid valves, and electrical circuits
located in a classified area according to RP500.
Signage Verify that proper signage (per NFPA 30A or IFC 2210) is present.
Fire Extinguishers Verify that the proper type and size of fire extinguishers are present and in their
correct locations according to NFPA 30A and NFPA 10 or IFC 2210.
20
Recommended Practices for the Installation of Marina Fueling Systems
FT
natural disasters. A large part of emergency preparedness
is not in the equipment, however, but in the people who Determine which code applies before beginning
operate the fuel system. This chapter provides references construction of a marina fueling facility.
and brief descriptions to help operators locate the infor-
mation they need to operate storage systems safely and
responsibly. WARNING: There may be other authorities
besides those listed here that need to be con-
13.2 Spill Prevention, Control, and Countermeasure sulted regarding the installation and operation
(SPCC) Plans. SPCC regulations originally went into requirements for marina fueling facilities. It is
effect in 1974. They have been revised in recent years. the facility owner or operator’s responsibility to
It is the owner’s responsibility to determine whether a identify all of the authorities that may have juris-
facility is subject to the SPCC regulations. This deter- diction over a specific marina fueling facility.
mination should be made before a facility is designed or
constructed as SPCC regulations may affect the design
of the fuel-storage system.
A
The basic requirements of the SPCC regulations are to
review the construction and operation of a petroleum-
storage facility, develop a plan, and provide necessary 14. Documentation,
materials to respond to releases of petroleum products Training, Inspection,
near navigable waters. Refer to Title 40 of the Code of
Federal Regulations, Part 112 (usually abbreviated as and Maintenance
R
40 CFR 112) for a full description of the SPCC require- 14.1 General. This chapter describes the types of
ments. documentation that should be provided by the installer
to the owner and the basic operating information that
NOTE: Local authorities may administer the SPCC should be conveyed to facility personnel so that they can
program and have additional requirements beyond operate the marina facility safely and responsibly.
the federal regulations. Consult with the authorities
having jurisdiction to determine applicable SPCC 14.2 Documentation. Provide any documentation sup-
requirements. plied by the equipment manufacturer for the equipment
D
21
PEI Recommended Practices 1000-09
FT
• The location and operation of fire extinguishers
and/or a fire-suppression system
• Procedures to prevent fuel spillage
• Spill-response procedures
• Emergency-response procedures
• Proper fuel-system shutdown and restart proce-
Figure 14-1. Boat fueling procedures are more complex dures
than car fueling procedures. For this reason, marina
fueling facilities should always be attended by trained • Procedures for properly securing watercraft while
personnel. fueling
• Policies and procedures to ensure that all fueling-
A
in time when the marina fuel facility is essentially com-
plete but not yet open for operation.
related signage is readily visible
• Procedures for completing inspection and mainte-
nance checklist(s)
The facility owner is responsible for providing general
and facility-specific training to employees at the time • Recordkeeping requirements.
of their initial employment. Annual refresher training
should also be provided for existing employees. The 14.4 Inspection. A program of ongoing inspections is
fuel-system installer or service provider may provide required to provide safe, reliable operation of the marina
R
training for facility personnel if contracted to do so. fueling system. Daily, monthly, and annual inspection
and maintenance checklists for dispensers are provided
Training topics for personnel associated with the facility in PEI/RP500, Recommended Practices for Inspection
fuel system include but are not limited to: and Maintenance of Motor Fuel Dispensing Equipment,
and for underground tanks in PEI/RP900, Recommended
• The role of facility personnel in the fueling process
Practices for the Inspection and Maintenance of UST
• Proper care and operation of fueling equipment Systems.
• The importance of manually operating the fuel
D
22
Recommended Practices for the Installation of Marina Fueling Systems
FT
evidence of corrosion or deterioration
• Piping supports – visually inspect piping supports
for evidence of corrosion or deterioration. Pay par-
ticular attention to supports that may not be readily
visible but are critical to proper operation and sup-
port of the piping.
23
FT
This page is intentionally blank
A
R
D
Recommended Practices for the Installation of Marina Fueling Systems
APPENDIX A
PUBLICATION REFERENCE
Many of the recommendations contained in this publication have been derived from the standards and recommended
practices of other industry organizations. Listed below are the names, addresses, telephone numbers and websites
of selected industry organizations, followed by the titles of their publications, which have some relation to the
installation of marina fueling equipment.
NOTE: Links to download or purchase many of the references listed below can be found at
www.pei.org/RP1000.
FT
■ International Code Council, Aboveground Storage Systems for Motor-Vehicle
Publications, 4051 West Flossmoor Road, Country Club Fueling, 2008.
Hills, Illinois 60478-5795. (888) 422-7233. Petroleum Equipment Institute, RP300-04,
www.iccsafe.org Recommended Practices for Installation and Testing of
International Code Council, International Fire Vapor-Recovery Systems at Vehicle-Fueling Sites, 2004.
Code, 2009. Petroleum Equipment Institute, RP400-07,
Recommended Procedure for Testing Electrical
■ National Fire Protection Association Continuity of Fuel-Dispensing Hanging Hardware,
1 Batterymarch Park, P.O. Box 9101, Quincy, 2002; Reaffirmed 2007.
Massachusetts 02169-7471. (800) 344-3555. Petroleum Equipment Institute, RP500-05,
www.nfpa.org Recommended Practices for Inspection and
National Fire Protection Association, NFPA 1, Maintenance of Motor Fuel Dispensing Equipment,
A
Uniform Fire Code™, 2009.
National Fire Protection Association, NFPA 10,
2005.
Petroleum Equipment Institute, RP600-07,
Standard of Portable Fire Extinguishers, 2007. Recommended Practices for Overfill Prevention for
National Fire Protection Association, NFPA 30, Shop-Fabricated Aboveground Tanks, 2007.
Flammable and Combustible Liquids Code, 2008. Petroleum Equipment Institute, RP900-05,
National Fire Protection Association, NFPA 30A, Recommended Practices for Inspection and
Code for Motor Fuel Dispensing Facilities and Repair Maintenance of UST Systems, 2005.
Garages, 2008.
R
National Fire Protection Association, NFPA 70, ■ U.S. Army Corps of Engineers Headquarters
National Electrical Code, 2008. 441 G Street, NW, Washington, D.C. 20314-1000.
National Fire Protection Association, NFPA 302, (202) 761-0011. www.usace.army.mil
Fire Protection Standard for Pleasure and Commercial U.S. Army Corps of Engineers, USC, Title 33,
Motor Craft, 2004. Part 403, Obstruction of navigable waters generally;
National Fire Protection Association, NFPA 303, wharves; piers, etc.; excavations and filling in.
Fire Protection Standard for Marinas and Boatyards, U.S. Army Corps of Engineers, USC, Title 33, Part
2006. 1344, Permits for dredged or fill material.
D
25
PEI Recommended Practices 1000-09
FT
Washington, D.C. 20460. (202) 272-0167.
www.epa.gov
U.S. Environmental Protection Agency, Title 40,
Code of Federal Regulations (CFR), Part 112, Oil
Pollution Prevention, November 11, 1976 and Revised
August 11, 2004.
A
R
D
26
FT
This page is intentionally blank
A
R
D
FT
This page is intentionally blank
A
R
D
FT
Inside Back Cover
This page is intentionally blank
A
R
D
Petroleum Equipment Institute
P.O. Box 2380
Tulsa, Oklahoma 74101
(918) 494-9696
Fax: (918) 491-9895
Email: info@pei.org
www.pei.org
FT
A
R
D