WorkFace Planning Infrastructure

Document Number: COP-WFP-SPD-04-2013-v

DOCUMENT VERSION

Revision Description Date

Rev. A Document imported to 2013 04 Mar 13


template

AUTHORSHIP AND APPROVALS

Originated By COAA WFP 01 JAN 07 Signature


Committee
Reviewed By COAA WFP 01 JAN 07 Signature
Committee
Approved By COAA WFP 01 JAN 07 Signature
Committee

WFP Infrastructure.docx
Record of Revision

Revision Date Revision Description Originated By Reviewed By Approved By

Rev. 0 01 JAN 07 Original WFP COAA WFP COAA WFP COAA WFP
Infrastructure Committee Committee Committee
Rev. A 04 MAR 13 published
WFP Infrastructure COAA WFP COAA WFP COAA WFP
document imported Committee Committee Committee
to COAA template
2013

Copyright and Disclaimer Information

COAA and respective logos are either registered trademarks or trademarks of Construction Owners
Association of Alberta in Canada and / or other countries. All other trademarks are the property of their
respective owners.

© 2013 COAA. All rights reserved.


Contents
WORKFACE PLANNING INFRASTRUCTURE...................................................................................................1

REQUIRED POSITIONS..............................................................................................................................1

JOB DESCRIPTIONS..................................................................................................................................1

STAFFING.................................................................................................................................................2

REPORTING RELATIONSHIPS....................................................................................................................2

IMPLEMENTATION PLAN.........................................................................................................................2
WFP-PRC-2013-106-A WFP Infrastructure cument Number:Error! Reference source not found. WFP-PRC-2013
Revi
Do

WORKFACE PLANNING INFRASTRUCTURE

Based on the cultures of the organizations involved, legal considerations, and other issues, your
organization needs to determine:

REQUIRED POSITIONS

After determining the IWP requirements construction management need to:

Determine which positions will be required to satisfy the following roles and responsibilities:

 IWP Preparation
 IWP Integration
 Resource Coordination
 IWP Administration

One approach would be:

 The workface planner could satisfy the roles of IWP preparation and administration.
 Resource coordination could be the responsibility of individuals in materials
management, equipment management, or construction support services
 IWP Integration is the responsibility of the construction superintendent

JOB DESCRIPTIONS

What should the job descriptions look like?

 What experience should they have?


 What should they do?
 What level should their position be?

While each organization will have its own format for job descriptions, a sample planner job
description is provided in the implementation guide.

WFP-PRC-2013-106-A WFP Infrastructure.docx Page 1 of 2


WFP-PRC-2013-106-A WFP Infrastructure cument Number:Error! Reference source not found. WFP-PRC-2013
Revi
Do

STAFFING

After determining the positions and job descriptions construction management need to determine:

 How many of each position type are required?


 When they need to be hired?
 How they will be recruited and selected?
 How they will be trained and developed?

REPORTING RELATIONSHIPS

Based on the contractual arrangements, construction management needs to determine:

 Who employs the individuals?


 What level are the positions?
 Who reports to whom?
 How are dual supervisory relationships addressed? (e.g. dedicated planner hired
by subcontractor but managed by other parties)

IMPLEMENTATION PLAN

The construction management team need to determine:

 When will the first IWP need to be prepared?


 How will all the affected parties be advised of their roles and responsibilities in WorkFace
Planning? (e.g. Field supervision, project controls, quality assurance, planners, resource
coordinators, engineering, contractors, and owners)