LAND CLEARING, CUT SOIL, FILL SOIL & COMPACTED, REMOVED BAD SOIL, SLOPE PROTECTION OF EARTH WORK

FOR KCM #2

WORK DESCRIPTION
S/N STAGE
Land Clearing ( M2 ) Cut ( M3 ) Fill & Compat'ed ( M2 ) Distance ( M ) Slope Protection
BLOCK A
1 A1 479.9 0 25
2 A2
3 A3
4 A4
5 A5
6 A6
SUB TOT

BLOCK B
1 B1
2 B2
3 B3
4 B4
5 B5
6 B6
SUB TOT

BLOCK C1
1 C1.1
2 C1.2
3 C1.3
4 C1.4
5 C1.5
SUB TOT

BLOCK C2
1 C2.1
2 C2.2
3 C2.3
SUB TOT

BLOCK D
1 D1
2 D2
3 D3
4 D4
5 D5
6 D6
SUB TOT

BLOCK E
1 E1
2 E2
3 E3
4 E4
5 E5
6 E6
TH WORK FOR KCM #2 PROJECT

TARGET VOLUME ( M3 )
Cut Plan Cut Act Fill Plan Fill Act