Professional Documents
Culture Documents
com
Chapt~r 1 .0 Introduction
1.1 Constructioil management as a discipline
is related with the construction of infrastructure within the budget, time and quality. Essential
.planning, design and execution is required for the construction projects. There are various types of
construction like building construction, industrial construction, in:fi·astructure construction and
heavy construction.
The J 950s marked the beginning of the modem Project Mm1agenient era. Again, in the United
States, prior to the 1950s, pi·ojects were managed on an ad hoc basis using mostly Gantt Charts,
and informal techniques and tools. At that time, two mathematical project scheduling models were
. de~·eloped: (1) tl1e "Program Evaluation and Reviev\; technique" or PERT, developed by Booz~
Allen & Hamilton as patt of the United States Navy's (in COI\junction with the Lockheed
Corporation) Polaris .missile submarine progni:m; and (2) the "Critical Path Method" (CPl\·f)
developed in a joint venture by both DuPont Corporation and Remington Rand Corporation for
managing plant maintenance projects. These mathematical teclmiques quickly spread into many
private enterprises.
At the same time, teclmology foi' project cost estimating, cost management, and engineering
economics was evolving, with pioneering work by Hans Lang and others. In 1956, the American
Association of Cost Engineers (now AACE International; the Association for the Advancement of
Cost Engineering) was formed by early practitioners of project management and the associated
specialties of planning and scheduling, cost estimating, and cost/schedule control (project control).
AA CE has continued its pioneering work and in 2006 released the fixst ever integrated process for
portfolio, program mid project management (Total Cost Management Framework).
In 1969, the Project Management Institute (PMI) was formed to serve the interests of the project
management industry. The premise ofP:t\11 is that the tools and techniques of project management
sre common even among the widespread ap*lication of projects :fi·om the software industry to the
___ construction_inclnst:cy .. JnJ 98l,Jhe_ Pl\11 Bo1rd o£Dir_ectors_ant11Dxize_cUhe_d_eveJopment _of_ wbaL _____ _
has become A Guide_to t~1e Project M_anagentm B~dy ofKnowledge (PMBOK Gui~e), containing ·
the standards and gmdelmes of practice that p-e w1dely used throughout tl1e profess10n. ·.
I
The International Project Management As:so-:iation (IPMA), founded in Europe in 1967, has
1mdergone a similar development and instituted :.he IPMA Competence Baseline (ICB). The focus
of the ICB also begins with knowledge ;::s 2 :::~;::~:.:::dation, and adds considerations about relevant
Prepared By: Er. Subash K. Bhattarai (B.E C-.:: ?GDESD I MPA I MSc CM) I I Chapter 1.0
experience, interpersonal skills, and competence. Both organizations are now pm'ticipating in the
development of an ISO project management standard
In general, Construction management is a diverse discipline focused on the delivery of projects
that compose the world's built environment. Included are the determination of project
requirements, management of design, procurement of materials, and management of the
construction of the project within cost, time, and design parameters.
In terms of money value output, the construction industry is the largest single production activity
in the most of developed countries. The construction industry is heterogeneous and enormously
complex. The major classifications of construction differ markedly from one another: residential,
commercial, industrial, and infrastructme, as well as specialties such as electrical, mechanical,
framing, excavation, and roofing.
Construction management is the study of how projects are conceived, designed, and built; the types
of materials and methods used; techniques for estimating the cost of con$truction; design and
contract law; construction accounting; oral and written communications; safety requirements;
project planning and project manageme1it.
Constr~J;Ction management is the study and practice of managerial and technological factors in the
indnstt~Y of construction. This includes construction, the science of construction, construction
manag6h1ent and technology in construction. Construction management also refers to a business
re;:;res~;itation wherein a crew to a construction contract serves as a consultant to the construct,
hercby-_providing design and advice ofthe co11struction.
The education for construction management has a wide array of formats; these are the formal .
degree programs, on the job trainings, and. continuing education or professional development.
Examples of formal degree programs are two year associate degree programs, four year
baccalaureate degree programs and graduate degree programs.
The agencies supporting the construction industty include but are not limited to the
following
a. Construction business promoters like government bodies, public and ptivate enterprises for
real estate m1d industrial development, and other similar agencies.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I j Chapterl.O
f. Construction plant and machinery manufacturing, distributing and repair and maintenance
organizations
g. Banking and financial i11stitutions
h. Risk insurance and legal services companies
1. Construction quality assurance and research and development establishment
In general, there are three groups involve in the industry of construction; the owner, architect or
engineer or more known as the designer, and the builder or contractor. As th~se three groi1ps plan,
design and construct together, two contracts work between these groups. The .first contract is
known as the owner and designer contract. This first contract involves the planning, designing and
some possible factors of c;onstruction. The second contract is known as the owner and builder
contract. This contract involves the actual construction. On most cases, an indirect go-between
relationship exists among the designer and the builder because of these contracts.
A . . .
The h1~]o~· relation between these three pmiies are governed by the type of the contract and the
nature ~f the work. Client is investor who invest the money for the project. Tne consultant phys
the bricl~e between the payment to contractor and the owner. Basically according [0 1Lc;e r..arure of
role, th~relation between them can be divided into either two party system or u:rree pan:y s:;:•s:e::::r.L
_:-:-
,.,_,.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I I Chapter 1.0
(Consultancy Agreement)
Employer
I Consultant J
Report
~ Administrator
Contractor
'{··
Client,
Client i~ also an employer of the construction project. Client may be owner, occupier, developer,
implen}~nting agencies etc. Client may be governmental department, ministry, a public
corpora:t'ion, private limited, NGOs, INGOs, an individual etc.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I I Chapter 1.0
For more Notes and Tutorials Visit www.masenzworld.com
·: ..
Downloaded from www.masenzworld.com
Contractor
The contractor is one who carried construction works.
• Executes the works taking full responsibility of quality, timely completion and safety of
the work.
• He I She will set out the work, construct the wotk, carryout tests, care of works, rectify the
·defects, insure for the workmen, work and materials, insure the equipment, insure for third
part liabilities, take responsibility for the health and safety of the worker, maintain
specification, complete the work, conduct tests on work and hand over the project.
• After handing over, the Contractor is also responsible for maintenance of defects during
defects liability period.
Consultant / Engineer
An individual engineer/architect, an independent professional orgmii~ation, practicing consulting
firm, a government entity
Prepared By: Er. Subash K Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I I Clwpter 1.0
1. Physical space
2. Construction materials
4. Human resources
5. Technology
6. Finance
3, 1 o arrange the cornpletion of the work in the minimum possible time duration
4. To improve the quality and speed of work by adopting modern equipment and machineries
Prepared By: Er. Subash K. Bhanarai (B.E Civil I PGDESD I MPA I MSc CM) I I Chapter 1.0
For more Notes and Tutorials Visit www.masenzworld.com
Downloaded from www.masenzworld.com
Consttuction is an everlasting activity across the globe. From econ01nics angle, the construction
industry is that sector of economy that plans, design, constructs, maintains, alters and repairs
physical immobile structures and facilities like buildit1g complexes, transportation networks,
processi11g plants, 111anufactttring installations, power plants, traii.smission lines, ports and harbors,
water supply and sewerage disposals, and other utility works involving civil, mechanical,
telecommunication and other skills. It is an aggregate ofbusiness that are closely linked with the
physical constructions, repair and maintenance of buildings, infrastructure works and industrial
facilities involving application of various engineering skills.
Construction industry is.oi1e ofthe main contributors to the growth of the economy of a country.
It generates nearly half of fixed capital formation·, employs large Work force, and has national and
international markets. The construction industry undertakes wide variety of works spread over in
different regions. In general construction industry possesses following characteristics:
Constn!Ction projects co.ri1e in many form with varying purposes. There is no simple method
classif)i''them. These projects can be categorized by nature of construction works, mode execution,
cost a:ndtime constraints, the inherent uncertainty (maturity level). Btoadlydepending upon nature
of construction facility, the major construction projects are:
Building works include all type of buildings such as residential and commercial complexes,
educational and recreational facilities, hospitals and hotels, estates and offices, warehouse and
shelters. 'Building' constitute the largest segment of construction business. The building
business serves mankind by providing shelter and services for its habitation, educational,
recreational, social and commercial needs_ Th:c building works are mostly designed by the
Architect-Engineering firms and are financed by government, public and private sectors.
These are capital intensive-and heavy equipmen:c uriented works, which involve nio merit of
large qua tity of bulk material like ear~11,. s::~~ ;]Tid concrete. These work include
canals, hi hways and airports, railways :m.2 cC::dg.:s oil/gas pipelines and tttmsmiss on lii1es,
7
large water supply and sewage dispos:::= ne::-:;'.'.:''ff"~,. d0cks and harbors, nuclear an thermal
power plant and other specialist cons:E::=5~·c '>':bich build up the infrastructure for the
s;;e.:ialist engineering firms.
Prepared By: Er. Subash K. Bhattarai .,~L=: ..:::.- lf':::I:F·~=; \llPA! iVISc CM) I I Chapter 1.0
The first engineering structure to be built in Nepal was an iron bridge over river Bagmati in 1850.
The first public water supply system was laid in Kathmandu valley during 1888- 1895. The royal
palace, the clock tower and the si1spension bridge on the river in Kathmandu were built during
these years. The first hydro-electric project at Pharphing was completed in 1911. The Raxaul-
Amleki]'ganj Railway line by M/s Martin and Co. Ltd of Calcutta and Dhursingh-Matatirtha
Ropeway by M/s Keyner Son and Co. of London, were constructed in 1926-1927. Other public
construttion works were d0ne departmentally by the central government.
The ne<y age of the Nepalese construction industry started only after 1951. The First Five Years
DeveloJ}ment Plan was stmied ii1 1956. After that, coi1struction activities in the country boostup
automatically. The Industrial Resolution, 1957 adopted by the govermnent of Nepal declared
construction as the 'Priority Sector' industry. As the priority sector, construction firms enjoy
income tax holiday along with other tax concessions for seven years :fi·om the date of incorporation,
a more liberal depreciation rate, capitalization of pre-investment expenditui"e, provision of foreign
exchange facilities etc. The first act which defined 'Contractor' was The Industrial Enterprises Act,
1974. It made provision for the classification and registration of contractors. According to this act
all construction firms must register themselves with the then Ministry of Works and Transpmi in
class A, B or C, contractors depending upon the technical manpower, value arid number of works
done, machinery and liquid assets available.
Some construction projects like 'Siddhartha Highway', 'Trishuli hydro power', and 'East· West
Highway' etc. were stmied in epal which were handled by Nepalese contractors for the first time.
After the completion of these roje~ts, Nepalese contractors began to appear _all()ver the c_oun:~ry
and started to take part in the development work. They developed their capital, managerial skill
and equipment simultaneously Till then construction act had not come into existence so Nepalese
construction industry could no develop so much as it should have been in the period ofPanchayat
system. After the restoration of the parliamentary democracy in 1989, Nepalese contractors got
some favorable condition to develop their capacity and got opportunities to take pari it1 several
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I I Chapter 1.0
For more Notes and Tutorials Visit www.masenzworld.com
Downloaded from www.masenzworld.com
construction projects. Nepalese contractors then came in position to do all kinds of natim1al
construction works as roads, buildings, dams etc. except niega projects.
At present, there are all together 3,25 class A, 374 Class B, 1347 Class C and around 15000 Class
D Contractors (according to FNCCI: renew of contractors registration 2013)
(Source,: FNCCI)
Role of Construction lndust1y in Nationitl Economy
Construction industry is one of the important sectors in any economy. Its contribution to the GDP
and employment is very significant and plays important role in the development of infi:astructure
that is essential for th~ development of all other sectors. In Nepal, more than 10 percent of the
GDP is contributed by the ,construction sector and is one of the largest employers. It is estimated
mat this sector is creating employment opportunities to more than one million people in the
country. Nepalese Contractors are now saving a huge amount of foreign cul'rency from its fl,ight
:,J abroad by foreign contractors. So it is contributing as export industries to the national econ01'hy.
Therefore any enhancement made to this sector will have positive impact on the national economy ..
::=. •Ceveloping countries about 60 percent of the national bndget is allocated on development works
si::Prfi.cant portion ofthe development budget is allocated to construction sector in Nepal.
::JJe goal of economic development can only be achieved through the establishment of adequate
ZDi efficient transport facilities. Nepal has rugged topography about two third area of the country.
Hence, an efficient road network has become a challenge. Likewise Nepal is land locked com1.try.
E.::,wever, an improvement and extension of transportation network provides the oppmiunities to
,.::~.lJiw the economy. Nepal is still lacking sufficient road network. If road networks are extended,
~·~q1al can be "LandLink:ed" between India and China. From which it can reap the benefit oftransir· ·
;:cint between these countries. Similarly, for tourism industry, which is :regarded as one of the
=zjor source of foreign currency earning, many infi:astructures development in different pmis of
:.::C country including regional and international airports are the opportunities of the construction
.r:::C..:s:.:::y in Nepal. On the other hand, investment form the government in road sectot is low and is
.:rc 2.~1e to meet the requirements of the country and aspirations of the people. Hence, contractors
.e.:::.d. consultants can and have to play key role :in th:i regard to attraCt the private sector to make
:.:11:estments in the road sector following the Bui]t, 0 erate and Transfer (BOT) approach.
-:\epal is second richest country after Brazil in its wa er resource and it has the great prospects in
generating hydroelectricity and constructing irrigation projects tlu·oughout the cotmtty. Although
Nepal has a large reserve of water resources, it is not able to utilize them properly. At the end of
FY 2070/71, the total peak demand is around 1176 (M\V) Provisional but the power production is
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I I Chapter 1.0
less than the demand. Hydropower production is around 700 MW only, which is merely 0.8 5
pe1'cent of the total potentiality of 83,000 MW. So there is wider scope of hydro electricity market
inside the nation and the possibility of exporting to India as well.
The extension of irrigation facilities in the agricultural land can bring crop integration and crop
diversification, which can help to generate employment ai1d reduce poVerty. At present ot1ly 4 0
percent ofcultivated land is covered by round the year irrigation. If power supply generation and
irrigation is possible :fi·om the same project, it will be beneficial and cost effective. In this regard,
the feasibility studies of such projects are required to develop the Nepalese construct~on industry.
According to population census 2011, ~he growth rate ofpopulation is 1.35 petcent per ammm.
With the ·economic development of the country, the tendency or the flow of population is :fi·om
rural areas to urban areas. It requires better real state, housing, market complex, good hospitals,
schools and colleges. Still there are insufficient such facilities in Nepal. Though there are lots of
opportunities for local contractor on building real state a11d housing.
The government ofNepalliberalizes its policies after 1980's. Now governmenthas released the
act·Tel~ted to Build, Operate, Own and Transfer BOOT Act (PPP) - 2063, Road Sector Policy
1999, BOOT Regulation (PPP) - 2064, Hydropower Act ""': 1992, Public Infrastructure Build
Operaie and Transfer Policy - 2057, Private Investment in Infi·astructure Build and Operate
Ordinance- 2060. There is still some oppmtunity for the contractoi"s through Contractual PPP' s
as:
Sitapaila-Dharke Roadway
Airpmis- Nijgadh,Pokhara, Bhairahawa
Dry ports
Truck Terminals
Bus Terminals
Cargo Complex at TIA
Cable Car and Ropeway
Road and Infrastructure Maintenance
Road Intersection
Sky Bridge
Sub Way
Flyovers and Interconnections
City Parking
In conclusion, there is huge task on constrnction of in:fi·astructure facilities, both basic as well as
developmental. Living between the two developing economies giants, who are accounted as the
fbture superpower of the World in next twodecades, and living at neighborhood ofBhutan, Nepal
is still searching and endeavoring to find lasting solution to reduce poverty. Time is rich to learn
lessons :fi:om the neighboring ~ountries and march ahead for real achi~vements, which will largely
dependupon development projects through construction industry.
'X·
Prepared By: Er. Subash K. Bbattarai (B.E Civil I PGDESD I MPA I MSc CM) I I Clwpter1.0
"A pr~ject is defined as a temporary endeavor under taken to create a unique products or
service.~. "Project Managemuit Body of J(nowledge (PMBOJ()
"Proje~·t is a one which starts from scratch with a definite 111ission, generales aclivity involving ({
verity o_[human, non-human resources all dil-ected tovvCtrdsfuljWment ofrhe mission and stop once
the miSsion is fulfilled." - S. Chaudhary
"A project can be defined as a unique task (however large or small) with defined goal, limited in
cost and time and giving some benefits to the users when the rask is completed."
S.J(.Bizattacharjee
A project is a unique group of tasks designed to attain a specific objective within the oom""traints
of time, cost and quality based on plmming and controltln·ough the use of a variety of resources in
a dynamic environment.
A plan is an image, map or vision .ito represent the forrns and/or features of desired simar.~~~:cfs). It
is the process
.
of setting
.
futme goa s for organization and choosing the actions to achieYe :LS,em.. It
is bunch of programme
Similarly, a program is the exte s1ve and consistent set of action units stating the nee3s of
interrelated activities to achieve th plan's objectives and goal. It is group of projects
Ingeneral, the term 'construction project' refers to a high-value, time-bound, special construction
mission with pre-determined performance objectives. Construction projects employ huge
resources of men, materials and machines. The construction project mission is accomplished
within complex project environments by putting together human and non-human resources to form
a temporary organization (like the special mission task force of the army), headed by a project
manager.
1. Specific objectives
A project has clearly defined specific objectives. It is focused on end results. A project
without objectives is unthinkable. Its output is measltrable. The objectives are predetermined.
2. Life Span ·
All projects have a life span. It has definite beginning and end. Projects cannot continue
endlessly. A project is a one-time- only set of activities, it is a temporary endeavor. Its life
span can be short or long depending on its nature and scope. It has a life cycle consisting of
formulation, planning, implementation and termination phases.
3. Constraints
}\11 projects have constraints. A project operates within the constraints of time, cost and
q{iality performance. It has a time schedule for various activities and a completion date as
deadline. It has clearly laid down quality specifications. The scope and boundaries of a
project are clearly delineated. Project schedule sets deadlines.
4. U~1ique
E*ch project is different. No similar project do exist. Clearly, no two projects are exactly
similar. Every project is unique in some elements. It consists of customized non-repetitiYe
activities. It has a specific geographical location. It involves complex set of actiYities.
5. Team Work 1
Projects work through team work. A project consists of multi-functional team. Te2:m
members are temporarily assigned :fiom other functional departments and or required human
resources fi·om various disciplines with varied experiences are pulled together to form a
temporary organization. The project manager is the leader of the team. He/She coordinates
project activities. He/She builds and maintai11s a cohesive team. He achieves unity in
diversity. He/She effectively manages conflicts. The manager is supported by a project team.
6. Flexibility
Projects have flexibility. They are not rigid. Aproje t operates in adynai11ic environment. It
needs flexibility to provide rapid response to chan ing environmental forces. The project
complexity prodLJces riskS~ Flexibility is essential o control arid ~ni.anage project risks a(
different stages of life cycle. Project risks can be r lated to time, costs, technology, scope
aHd performance.
7. Resource Integration
Prepared By: Er. Subash K Bbattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 2.0
Projects consume and coordinate resources. A project integrates physical, fmancial, human
information. It maintains appropriate interrelationships \\ith them. Resource use is
prioritized in disciplined way for optimization.
8. Planning and Control
Projects work to a plan. A project requires effective and et11cient planning and coritrol
systems. Standards are set for project activities through planning. They serve as yardsticks
for measuring project performance. Actual performance is compared with standards to find
out deviations. Corrective actions are taken to control deviations.
9. Contracting and subcontracting
Most projects are contract-based. The project work is characterized by high level of
· contracting and subcontracting. Contracts can be of various types, such as lump- sutn
contract, unit price contract, negotiated cost plus fixed fee contract and turnkey contract.
Proper contract plam1ing and management is the key to effective project management.
10. Beneficiaries
All projects have beneficiaries. Beneficiaries are the ultimate users of the project outputs.
They are the client ofthe project. A project has a specific group ofbeneficiaries. It should
be focused on fulfilling or exceeding their requirements. Projects should clearly identify the
needs of their beneficiaries .
. Some .Qf tlze core features which makes construction project management d{ffers from rest of
the oth[~rs are summatized as follows:
a. ,Construction Projects are unique and transient in nature. Its organization is temporary.
b. i_Every construction Projects are time bound with fixed life span and new tasks. These tasks
,·.c:reate never-ending problems, especially when projects are crashed, under relatively risk-
.;,,1]rone, complex situations and resource constraints.
c. -Project time and cost are correlated. Time delays can increase costs exponentially instead
oflinearly as in the case of most of ongoing enterprises.
d. Project tasks leave no time for the training or learning process. It is handled and managed
by multidisciplinary experts headed by a single responsible center, project manager.
e. Projects are flexible and runs with operational autonomy to manage the complexities due
to risks and adaptation to enviromnental change.
f. Projects being handled by a company; generally interact with each other socially,
organizationally, technically and economically.
g. Project integration is relatively complex under dyr1amic project environments.
h. Construction projects are executed with the support of contracting agencies, whereas
ongoing industrial processes are managed by the departmental sta and workers.
1. Construction projects ate c:bangeoriented and self-managed.
2.3 Project Life cycle
The project life cycle of a construction project generally follow similar p ttern. It is divided into
several phases for management control. These phases in a typical construction project are:
Prepared By: Er. Subash K. Bhat1arai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 2.0
Planning phase.
The objective of this phase is to develop a workable and manageable plan to accomplish me p:rojec:
mission. It involves creating the planning documents to guide the team throughout the projec:
deliverx. Various planning documents regarding project management are prepared prior to project
.J.;._~
executloi.1.
~~:~.
Execut'ibg phase.
I
~his phi1se is concerned with coordinating and managing people and other resources to carry out
:.~::~~ plan>tExecuting phase is also lmown as implementing phase. This phase of the lifecycle implies
:-aiidin'ffphysical deliverables and is presented to customers. It is longest phase and consumes lot
,c;:i ener!y, effort and resources. In this phase, the activities like allocation of the tasks to teai11
=embers; procurement activities, contract administration, MIS set up etc. are carried out.
Controlling phase
:?'roject plan indicates the path to achieve objectives. During the implementation phase, the project
.:ontrol aims to track the progress of work as per the plam1ed schedule and take corrective actions
:..J:cluding re-planning, when necessary, to achieve the project objectives. Project control follows a
system concept. Monitoring and Evaluation is done collectively for the controlling of project
::::,:tivities.
Closing phase
Tills formalizes the ac eptance of the project and brings it to an orderly end. After completion o
;'TOject by the contra tor, it is handed over to the client. The team also prepares a projec
completion· report wl ch -includes the scope arid schedule of work, the imp-ortant events,· th
contract executed, th addresses of the suppliers of materials and equiprrtent, the equipment
:naintenance manual, 1e as-built drawings, the costs involved, the problems encour:ttered durin
=xecution, the lessons learned and the minor defects noticed at the time of handing over.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 2.0
Noie:
The project phases are not discrete, one-time events; they do overlap at varying levels of intensity
throughout the project life cycle.
l
• Investment appraisal
1• Performing Phase review
,l
Project Planning I• Creating a project Plan
Phase • Creating a resource Plan
• Creating a fmancial Plan
,.
• Creating a Quality Plan
• Creating a Risk Plan
• Creating a Construction contracts procurement plan
• Creating an acceptance plan
• Creating a communication plan
• Coi1tracting the suppliers
• Performing phase review
Project Executing • Time management
Phase • Cost Management
• Quality Management
• Change Management
• Issue management
• Procurement Mailagement I Conttact Administration
• Acceptance management
..•
Commun ·cation Management
Performin g phase review . - -- -- .. - ---- .. .. -
- -
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 2.0
• Quality control
• Risk response c011trol
• Perfol'martce rep01iing
OR
Project is a temporary job. 1t cannot continue endlessly. A project depending upon its nature, size
and type, undergoes through different well defined phases right from its inception to successfi.1l
completion. Collectively, the project phases are known as project life cycle phases. The breakdown
and terminology ofthese phases differs depending upon the nature of the project or organization.
The following impo1iant five phases contribute to develop a project :fi.·om an idea to reality.
..
a. Initiation Phase
.•
b. Planning Phase
c. Engineering and Design Phase
d. Implementation Phase
e. Termination Phase
a. irtitiation Phase
This phase includes:
• Conceptual study: projects are born with creative ideas. It includes preliminary evaluation
of ideas, such as project identification, project formulation.
• Feasibility study: the objective of the feasibility study is to have more detailed information
about the location, nature, dimensions, raw material needed, equipment, cost-benefit
analysis, and the detail abolit the users who will be benefitted :fi.·om the project.
• Market study: it includes the study ofthe mai·keting prospects and demand ofthe product,
considering (a) potential size and composition of the market (b) present and projected
demand ofthe product/services.
b. Planning phase
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 2.0
• Work breakdown structure: the project is broken down into small elements so that all the
activities to be perforrned in the project are included.
• Cost and Schedule Planning: after breaking down the project, the time arid cost of each
activity is determined and overall time and cost of the project is determi11ed.
• Contract terms and co11dition: the contract terms in which the project activities are to
accomplish is determined in this phase. The contract rnay be lump-sum, fixed price, unit
rate etc.
)
After the end ofthis phase time and cost estimate of the project is made and major contracts are
let.
It invol~'es the process of successively breaking down, analyzing and designing the structme and
its elenl.ents. This detailed phase include architects, interior designers, landscape architects, and
several engineering disciplines including chemical, civil, electrical, mechanical etc.
d. Implementation Phase
Thi phase is the end of project and project is brought to its completion. In t is phase, the final
testing and maintenance of the project is done and handed over to the customer and resources are
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Clwpter2.0
released to other projects. The basic tasks in this phase are evaluation and handover of the project
output to the beneficiaries.
• _Cost and staffing levels are low at the star1, higher towards the end, and drop rapidly as
project draws to a conclusion as shown in fig below.
• The probability of successfully completing the project is lowest, and hence risk and
uncertainties are higher at the start. The probability of successful completion gets
progressively higher as the project continues.
• Most project life cycles tend to progress slowly at the stm1, quicken their momentum
towards the middle and drop their momentum towards the end.
Resources /Risk
I
Resources
I
'
Project life:cycle
'
I
1. The Success Principle The goal ofProject Management is to produce a successful product or
servtces
2. The commitment Prin iple: A mutually accepted commitment between a project sponsor and
a project team must e ist before a viable project exists.
3. The Tetrad- Tradeoff rinciple: The core variable of the project management process, namely:
scope, quality grade, time to complete and cost to complete (time cost trade off) must all
mutually consistent
Prepared By: Er. Subasb K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 2.0
Project' management is the application of Knowledge, skills, tools and teclmiques to project
activities to meet the project requirements. Project management is accomplished through the use
of planbing, executing, contt·olling and closing processes. Basically nine managerial functions are
involve'0 in managing the project.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 2.0
Planning involves formulation of a number of alternative realistic Work plans for achieving
specified objectives and selecting a plan which is best suited fi-om the stand point of available
resources and constraints imposed upon the project. It is essentially covers the aspects of 'what to
do' and 'how to do'
Scheduling is the fitting of the final work plan to a time scale. It shows the duration and order of
~,~arious construction activities. It deals with the aspect of 'when to do'
2. Organizing
Jc:-ganizjng is concerned with the division of the total construction work into manageable
5:::pannients I sections and systematically arranging various operations by delegating specific tasks
1:: :i;.dividuals. The relationship between various persom1el are established and the organizational
:; . Staffing
:~·c-g:::rizing
involves the division of project work into sections ai1d staffing is the provision of ·
w fill the positions so created. Recruiting the right people, arranging staff training courses
C&'1)·ing out proper staff assessment are all part of the staffing :fimction
...::_ Directing
.crrecting function is concerned with training sub ordii1ates to carry out assigned tasks,
:;;n::e:-Yising their work and guiding their efforts. The essence of directing lies in the ability to
~""',,..,,""••.,_,.1f=- people individually and as groups to utilize their creative efforts in achieving specified
Controlling
Il:ing is necessary for ensuring effective and efficient workir g. It involves a constant review
;~.crk plan to check on actual achievements and to discover and recJify deviations fhro.ugh
ll!.lliii:::JJL=;;r:zre corrective measures. The essential steps in manageme t control are:
' Measurement of actual performance in terms of progre s, quality and cost incurred
.., Comparison of actual and planned perfonnances
?repared By: Er. Subash K Bhattarai (B.E Civil. PGDESD I MPA I MSc CM) I Chapter 2.0
7. Conummicating
There should be an effective communication in every direction within the organization. Quick
and accurate flow of information is a vital aspect of the controlling action.
Prepared By: Er. Subash K Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 2.0
After project has been initiated, next phase ofproject life cycle begins with planning and design.
"Ifyou fail to plcm, you are bound to fail"
Planning is the rhost imp01iant constitue1it of the construction managenient. In the simplest sense
planning is the mental process deciding about the future line of actions. Planning is the course of
action to achieve the desired results taking into consideration the present needs and future
requirements. Planning is critical to the project management process. It forms the basis for the
project scope, schedule, reso1.1rces, quality, risk, and integration
Planning is done to
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) II Chapter 3.0
Features of Planning
Planning is an integral part of management. A manager expects problems in future, analyzes them
and expects their possible effects on the activities of the enterprises. This is why features of
plmming is important. The following are the important features ofPlaiming.
• Identifying the likely problems to be encountered m the execution of the work and
obtaining necessary n1formation useful in the execution of the work.
• Ascertaining alternative feasibility of execution of work and selection of the optimum plan
• Fixing the time of starting the execution of work
• Deciding the time of delivering the materials at site
• Deciding the quantities and duration ofvarious types of machines and equipment
• Deciding the number of different types f labors for various works and duration of their
employment
• Estimation of financial help if needed
• Estimation of the duration of completiOI of the work
• Evaluation of the effectiveness of plan a· opted
Prepared By: Er. Subash K Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) II Clrapter 3.0
1. Preplanning
During this stage objectives are clearly spelt out. A general frame work ofthe project is formulated .
.-\ cost benefit analysis is to be canied out along with cost analysis of alternative sites.
Thus this stage of planning is before a decision finally is taken to undertake a project.
1. Detailed planning
During this stage detailed design and drawings are carried out. Specifications of materials and
2:rawings are also prepared in this stage. Quantities calculation along with preparation ofWBS is
ione. ~equence and scheduling ofthe activities are done
.::~\:
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) II Chapter 3.0
• Carefi.1l Study of tender documents and drawings to find out the quantities of each item of
work
• Study of specifications and workout the detailed quantities of materials required for
different items
• Determine the availability of construction materials at site or nearby site.
• Determine the method of work execution i.e. by labor or equ:ipment
" .Thorough study of site and site investigations
b. Con~truction stage planning
After the acceptance of the tender, the contractor further needs ir1 depth planning. This stage of
ph::ni::g is also known as contract planning. Here are following steps in this stage of planning:
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) II Chapter 3.0
Design
It stresses on:
• .AJ:chitectural concepts,
• Evaluation of teclmological process alternatives,
• Size and capacity decisions,
• Comparative economic studies.
For example, in designing dam, hydropower, irrigation channel preliminary design reqtmes
analysis of hydrological characteristics, geological condition, precise location of dam etc.
"' ._;Analyzing
, and designing the structure and its elements .
o 'A set of explicit drawings and specification
s :Setting standards of safety and performance
~ ,;rechnology (construction methods)
• /Consultation of experts like geologist, economists and enviromnentalist
• Detail estimation of project
This detailed phase include architects, interior designers, landscape architects, and several
engineering disciplines including chemical, civil, electrical, n1echanical etc.
The construction project scope defines the \YOrks that must be undertaken in order to deliver a
facility, a product or a service with the specified attributes and features. Project work scope
management aims at ensuring that planned v.-odcs are done to ensure the achievement of the stated
purpose of the project. It focuses on the proje.:t scope of work and its components.
_-\typical project scope definition 9oYe:rs ill.; .P'Jjecr purpose, project objectives, brief statement of
•sork, Work Breakdown .Structurel('.\"BS)"
. .~
o:n.I:ille execution methodology,
. - . .
milestone
. -
time - plan,
- . . -
..:ash flow pattern, outline project.lganization and potential risks and problem areas
.?roject Scope Management mcludfs the processes regmred to ensure that the proJect mcludes all
<he work required, and only the \\·ork required, to complete the project successfully. It is primarily
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) II Chapter 3.0
concerned with defining and controlling what is or is not included in the project. Below Figtu·e
provides an overview of the major project scope management processes:
These processes interact with each other and with the processes in the other knowledge areas as
well. Each process may involve effort from one or more individuals or groups of individuals based
on the needs of the project. Each process generally occurs at least once in every project phase.
Although the processes are presented here as discrete elements with well-defined interfaces, in
practice they may overlap and ii1teract in ways not detailed here. In the project context, the term
"scope" may refer to:
• Product scope-the features and functions that are to be included in a product or service.
• Proje1fscope-the work that must be done in order to deliver a product with the specified features
and funCtions.
The processes, tools, ai1d techniques used to manage product scope vary by application atea and
are usuit.lly defined as part of the project life cycle. A project consists of a single product, but that·
product)nay include subsidiary elements, each with their own separate but interdependent product
scopes)For example, a new telephone system would generally include four subsidiary elements-
hardwate, software, training, and implementation. Completion of the product scope is measured
against the requirements while completion of the project scope is measuted against the plan. Both
types of scope management must be well integrated to ensure that the work of the project will
result in delivery of the specified product.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) II Chapter 3.0
Cost estimate
_-'\. cost estimate is the approximation of the cost of a ptogram, project, or operation. The cost
estimate is the product of the cost estimating process. The cost estirnate has a single total value
and may have identifiable component values. A problem with a cost overr n can be avoided with
4 c~·edible, reliable, and accurate cost estimate. An estimator is th~ pr~fess~ · nal who prep~res cost
Jstmmtes
e Materials
Prepared By: Er. Subash K. Bhat1arai (B.E Civil I PGDESD I MPA I MSc CM) II Chapter 3.0
Material (Matetial is a very imp01iant part ofbusiness). Materials can be direct material or indirect
material
• Labor
.. ';;;'Occupancy (Rent)
.. ·.:Depreciation
',>
Capital cost:
The capital cost for a construction project includes the expenses related to the initial establishment
of the facility:
O&M cost:
The operation and maintenance cost in subsequent years over the project life cycle includes the
following expenses:
The magnitude of each of these cost components depends on the nature, size and location of the
;roject as well as the management organization, among many considerations. The owner is
:T:Kerested in achieving the lowest possible overall project cost that is consistent with its investment
. ::bjectives.
:: ~s in1portant for design professionals and construction managers to realize that while the
z,.:-:!struction cost may be the single largest conl.ponent of the capital cost, other cost components
.::.:;:: not insignificant. For example, land acquisition costs are a major expenditure for building
.:. =·r-.siruction in high-density urban areas, mid construction financing costs can reach the same order
:::-:.2gnitude as the construction cost in latge projects such as the constmci:on ,Jf nud=:'E:"
?::.J<m the owner's perspective, it is equally impm1ant to estimate the correspondir"lg operation and
=-2i"'tenance cost of each alternative for a proposed facility in order to analyze the life cycle costs.
-::-:ce large expenditures needed for facility maintenance, especially for publicly owned
=:::nrastructure, are reminders of the neglect in the past to consider fully the implications of
cperation and maintenance cost in the design stage.
Contingency cost:
Contingei1t amounts not spent for construction can be tel eased neal' the end of construction to the
owner or to add additional project elements.
Approaches to Cost Estimation
Cost estimating is one of the most iinportant steps in project mahag,ement. A cost estimate
establishes the base line ofthe project cost at different stages of development ofthe project. A cost
estimate at a given stage of project development represents a prediction provided by the cost
engineer or estimator on the basis of available data. According to the American Association of
Cost Engineers, cost engineering is defin:ed as that area of engineei·ing practice where engineering
judgment and experience are utilized in the application of scientific principles and techniques to
the problem of cost estimation, cost control and profitability.
VirtuaJly all cost estimation is performed according to one or some combination of the
following basic approaches:
·Production function. In microeconomics, the relationship between the outpL1t of a process and
· the nep;~ssary resources is referred to as the production function. In construction, the production
functioi1 may be expressed bythe relationship between the volume of coi1struction and a factor of
produCtion such as labor or capital. A production function relates the amount or volume of output
to theyarious inputs oflabor, material and equipment. For example, the amount of output Q may
. be deri~ed as a function of various input factors x1, x2 ... Xn by meahs of mathematical and/or
· statistiSal methods. Thus, for a specified level of output, we may attempt to find a set of values for
· ·· the inpl.it factors so as to minimize the production cost. The relationship between the sizes of a
building project (expressed in square feet) to the input labor (expressed in labor hours per square
foot) is an example of a production fimcticin for construction.
Empirical cost inference. Empirical estimation of cost functions requires statistical techniques
which relate the cost of constructing or operating a facility to a few important characteristics or
attributes of the system. The role of statistical inference is to esti1i1ate the best parameter values oi·
constants in an assumed cost fimction. Usually, this is accOmplished by means of regression
analysis techniques.
Unit costs for bill of quantities. A unit cost is assigned to each of the facility components or tasks
as represented by the bill of quantities. The total cos is the summation of the products of the
quantities multiplied by the coHesponding unit costs. he unit cost l'nethod is .straightforward i11
principle but quite laborious in application. The initia step is to break down or disaggregate a
process into a number of tasks. Collectively, these task must be completed for the construction of
a facility. Once these tasks are defined and quantities r presenting these tasks are assessed, a unit
cost is assigned to each and then the total cost is determined by summing the costs incurred in each
Prepared By: Er. Subash K. Bhat1arai (B.E Civil I PGDESD I MPA I MSc CM) II Chapter 3.0
task. The level of detail in decomposing into tasks will vary considerably :fi-om one estimate to
another.
Allocation of joint costs. Allocations of cost fi:om existing accounts may be used to develop a
cost furiction of an operation. The basic idea in this method is that each expenditure item can be
assigned to particular characteristics of the operation. Ideally, the allocation of joint costs should
be causally related to the category of basic costs in an allocation process. In many instances,
however, a causal relationship between the allocation factor and the cost item cannot be identified
1J>r may not exist. For example, in construction projects, the accounts for basic costs may be
.:!assified according to (1) labor, (2) material, (3) construction equipment, ( 4) construction
supervision, and (.5) geheral office overhead. These basic costs may then be allocated
. . 1 .
-::si.r{1ttion cost estimates may be viewed from different perspectives because of different
n::;Iimti6nal requirements. In spite of the many types of cost estimates used at different stages of a
1c~~.:t, cost estimates can best be classified into three major categories according to their
.1rcctions. A construction cost estimate serves one of the tlu·ee basic functions: design, bid and
.:.n:r:.:rol. For establishing the financing of a project, either a design estimate or a bid estimate is
__ Design Estimates. For the owner or its designated design professionals, the types of cost
estimates encountered tun parallel with the planning and design as follows:
o Screening estimates (or order of magnitude estimates)
o Preliminary estimates (or conceptual estimates)
o Detailed estimates (or definitive estimates)
o Engineer's estin1ates based on plans and specifications
For each of these different estimates, the amount of design information available typically
rncreases.
Bid Estimates. For the contractor, a bid estimate submitted to the owner either for
competitive bidding or negotiation consists of direct construction cost including field
Prepared By: Er. Subash K. Bhat1arai (B.E Civil I PGDESD I MPA I MSc CM) II Chapter 3.0
supervision, plus a markup to cover general overhead and profits. The direct cost of
construction for bid estimates is usually derived from a combination of the folloWiiig
approaches.
o Subcontractor quotations
o Quantity takeoffs
o Construction procedures.
3. 3. Control Estimates. For monitoring the project during construction, a control estimate
is derived from available information to establish:
c Budget estimate for financing
o Budgeted cost after contracting but prior to construction
o Estimated costto completion dtiring the progress of construction. -
Design Estimates
In the plmming and design stages of a project, various design estimates reflect the progress of the
design. At the very early stage, the screening estimate or order of magnitude estimate is usually
made before the facility is designed, and must therefore rely on the cost data of similar facilities
built in the past. A preliminary estimate or conceptual estimate is based on the conceptual design
of the facility at the state when the basic technologies for the design are known. The detailed
estima~%' or definitive estimate is made when the scope of work is clearly defined and the detailed
design';~~ in progress so that the essential features of the facility are identifiable. The engineer's
estimate is based on the completed pl~ms and specifications when they are ready for the owner to
solicit bids fi·om construction contractors. In preparing these estimates, the design professional
.;
The c6~ts associated with a facility may be decomposed into a hierarchy of levels that are
appropriate for the purpose of cost estimation. The level of detail in decomposi:n.g the facility into
tasks depends on the type of cost estimate to be prepared. For conceptual estimates, for example,
the level of detail in defining tasks is quite coarse; for detailed estimates, the level of detail can be
quite fine.
As an example, consider the cost estimates for a proposed bridge across a river. A screening
estimate is made for each of the potential alternatives, such as a tied arch bi·idge or a cantilever
truss bridge. As the bridge type is selected, e.g. the technology is chosen to be a tied arch bridge
instead of some new bridge form, a preliminary estimate is made on the basis of the layout of the
selected bridge form on the basis of the preliminary or conceptual design. When the detailed design
has progressed to a int when the essential details are known, a detailed estimate is made on t e
basis of the well-de med scope of the project. When the -detailed plans -and specifications· a e
completed, an en gin er's estimate cm.1 be made on the basis of itern:s and quantities of work.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) 1/ Chapter 3.0
Bid Estimates
The contractor's bid estimates often reflect the desire of the con:traetor to secure the job as well as
the estimating tools at its disposal. Some contractors have well established cost estimating
procedures while others do not Since only the lowest bidder will be the winner of the contract in
most bidding contests, any effort. devoted to cost estimating is a loss to the contractor who is not a
successful bidder. Consequently, the contractor may put in the least amount of possible effort for
making a cost estimate if it believes that its chance of success is not high.
If a general contractor intends to use subcontractors in the construction of a facility, it may solicit
price quotations for various tasks to be subcontracted to specialty subcontractors. Thus, the general
subcontractor will shift the burden of cost estimating to subcontractors. If all or part of the
construction is to be undertaken by the general contractor, a bid estimate may be prepared on the
basis of the quantity takeoffs :fi·om the plans provided by the owner or on the basis of the
construction procedures devised by the contractor for implementing the project. For example, the
cost of a footing of a certain type and size may be found in commercial publications on cost data
which can be used to facilitate cost estimates from quantity takeoffs. However, the contractor may
want to assess the actual cost of construction by considering the actual construction procedures to
be used and the associated costs if the project is deemed to be 'different :fi·om typical designs.
Hence;jtems such as labor, material and equipment needed to perform various tasks may be used
as pararr1eters for the cost estitnates.
Control Estimates
Both the owner and the contractor must adopt some base line for co SOL .c:ontro~ d'!Hir':g .:fie
constit12tion. For the owner, a budget estin1ate must be adopted early ena,ugh ic•:r ?kn~'n,1mrg Th21gg
term fii{ancing of the facility. Consequently, the detailed estimate is o:Tien 1E...-;erll :35 rl:e rot!~
estimate since it is sufficient definitive to reflect the project scope and is c.YailaHe i:~ re:i~e ~
engineer's estimate. As the work progresses, the budgeted cost must be re;.iseJ. pecio,,S.::::iE~; ;:;:::
reflect the estimated cost to completion. A revised estimated cost is necessary c!v;;..,,=r re~il..~
change orders initiated by the owner or due to unexpected cost overruns or sa,·i11gs.
For the contractor, the bid estimate is usually regarded as the budget estimate, which wiH be used
for control purposes as well as for planning construction financing. The budgeted cost should also
be updated periodically to i·eflect the estimated cost tb completion as well as to insure adequate
cash flows for the completion of the project.
There are various methods employed for estimating the project costs. These include unit service
cost estimation during conceptualization phase, parameter estimation planning phase, definitive
Prepared By: Er. Subash K Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) II Clzapter 3.0
estimate during execution phase and contractoi"'s detailed bid estin:lation at the time oftendering.
The methods used depends upon the nature of the project, the life cycle phase, the purpose for
which the estimate is requrred; the degree of accuracy desired, and the estimating effort employed.
Broad classification of estimates and the estimation methodology is otttline in given table beloW:
A proHct budget reflects the financial plan of the operations, divided into responsibility centers,
with sp'bcific goals clearly outlined along with the costs expected to be incurred. The pi"imary
purpose of having budget is:·
The project budget uses language of accounting to state objectives and measl!re performance. The
project budget integrates monetary objectives, responsibilities and allocated resources. The base
of budget is the project cost plan and its schedule ofwork. Each responsibility center is assigned
goals in the form of earned value or earn value budget. It ·s allocated resources in the form of
materials, labor, equipment and budgeted cost for the assi. ned goals. And finally, the project
financial plan is presented in the forin "c)f master budge . w11ich .stninnariie's- all the budget
information like profit and loss statements, balance sheets, apital expenditure budget, cash flow
forecast and performance indicators.
Prepared By; Er. Subash I<. Bhattarai (B.E Civil IPGDESD I MPA I MSc CM) II Chapter 3.0
In construction project, the client and the contractor have separate budgets. The client's
construction budget is primarily a capital bndget. It is what the client has earmarked the p1'oject. It
includes:
Client cash flow forecast time- phased fi.mds requirement and the sot"'trces :fi·om which these funds
are to be provisioned.
On the other hand, a contractor's budget is earned vaJue income ai1d resources expenditure oriented
budget. It includes quarterly statements of income and expeildittire a:nd forecast of fiiiancial
statements of projected balance sheet, cash flow, profit and loss and performance measunng
baselines.
O'iemwcs
Budg•t
·C:Rsh F:to<N
Fo;ni e:.ns t
Prepared By: Er. Subash K Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) II Chapter 3.0
The process of offering a tender or bid to execute some specified work or to supply some specified goods
at a certain rate/amount or to give service w'ithin a fixed time fi·ame under certain co1idition of agreement.
It is a process of procurement.
Tender or bid
It is an offer in written by the tenderer (the person who offers the tender). It is the first step in the
formulation of contract.
In making procurement by bidding, an invitation to bid can be made by the following process:-
Bidding Stages
·i) Single stage Single-Envelope Bidding Procedure
In the single-stage one-envelope bidding procedure, bidders submit bids in one envelope containing both
the Financial Proposal and the Technical ProposaL
In the single-stage, two-envelope bidding procedure, bidders submit two sealed envelopes simultaneously,
one col\taining the Technical Proposal and the other the Price Proposal, enclosed together in an outer
single ~hvelope.
::1 me 1\Yo-s.ilage: t\vo-envelope bidding procedure, at the first stage, Bidders submit two sealed envelopes
:::.::u::::::.:2;ec:-us~y~ cne containing the Technical Proposal and the other the Price Proposal, enclosed together
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) II Chapter 3.0
LSequence of operations
-~ ;
Planning
Scheduling
Use of scheduling
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 4.0
Advantages of scheduling
Classification of scheduling
• Construction schedule
• Materials schedule
• Labor schedule
• Equipment schedule
• Financial schedule
• Control schedule
• Organizational schedule
• Summary schedule
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) J Chapter 4. 0
Methods of scheduling .
IDENTIFYTHEPR(.DJEGTACTIVlTIES ·
1
REVIEW AND ANALYSE THE SCHEDULE
IMPLEMENT
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I JvlPA I JvlSc CM) I Chapter 4.0
The WBS provides a common framework for work from which the following
important aspects can be covered:
Levels of WBS
1 Total program
2 Project
3 Task (activity)
4 Sub-tasks
5 Work package·
6 Levelofeffort
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 4.0
comprises the total program. The reason for this subdivision of effort is simply
ease of control.
The upper three levels of the Wl3S are normally specified by the project
management office (customer), while the lower levels are generated by the
contractor for in-house control. Each level serves a vital purpose: level 1 is
generally used for the authorization and release of all work, budgets are
prepared at level 2, and schedules are prepared at level 3.
• Top tln·ee levels of the WBS reflect integrated efforts and not
department specific.
• The summation of all elements in one level must be the sum of all work
in the next lower level.
• Each element ofwork shonld be assigned to one and only one level of
effort. For example, the construction of the foundation of a house
shotild be included in one project (or task), not extended over two or
three.
• The WBS must be accompanied by a description ofthe scope of effort
required. Ifnot, only those.individuals who issue the WBS will have a
complete understanding of what work has to be accomplished.
Project
!
r BuCget Shopping Tab leslChairs RSVPs
l
Cooks TranspOtt
j
i List
i
Shopping Setting/ Nmne Tags (f . .,.T .,.,
.A:t, er, Coordinate
Disb""em•<sl
ReconcilL1tion Utensils Topics
Prepared By: Er. Subash K. Bhattm'ai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 4.0
Example ofWBS
.r-·~
Building
--:-......_
s1te aQ; formwork
ci~~JJce w~~ws ~
1-w----...r'~
excavation masonry reinforcement
"".............../ "-..-/
~ ~
concreting concreting painting
-~ ~ ~/
__....../""--.....
,_/
masonry
L--.1"~
uamp
pr~o~g
• BarChart
• Milestone Chart
• Netwoi"k Teclmiques
o CPM
o PERT
Gantt chart/Bar chart
The oldest formal planning tool is the bar chart. It is developed as a production control
tool in 1917 by Henry L. Gantt, an American mechanical engineer, hence also called
Gantt chart in his respect. A Gantt chmi provides a graphical illustration of a schedule
that helps to pla:n, coordinate, and track specific tasks in aproject.
A Gantt chart is constructed with a horizontal axis representing the t · al time span of
the project, broken dow11 into i11crements (for example, days; weeks, · · mo11ths)and a
vertical axis representing the tasks that make up the project (for examp e, if the project
Prepared By: Er. Subash K Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) J Chapter 4. 0
is outfitting your computer with new software, the major tasks involved might be:
conduct research, choose software, install software). ·
Horizontal bars of varying lengths represent the sequences, timing; and til'ne span for
each task. As the project progresses, secondary bars, arrowheads, or darkened bars
may be added to indicate completed tasks, or the portions of tasks that have been
completed. A vertical line is used to represent the report date.
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 4.0
. The Bar chart suffers from some disadvantageswhich limits its usefulness:
1. There 1i1ay be physical limit to the size of the bar chart, which may lii11it the
size 6f the project that cari be plabned with this technique or only major
activities are showi1. Hence, _it is not useful for large and complex projects.
2. There are some· activities of a project which are taken lip concurrently, w-hile
there m'e others which cai1 be taken up o11ly after con1pletion of some other
activities. Similal'ly some activities can be started few days after the other
activity stmis. The activities whose start and end depend on other activities
are shown serially. In a project, there may be large nui11ber of activities which
can start with certain degree of concurrency. By merely depicting them
parallel, interrelationship between them caimot be clearly depicted.
3. Each activity receives equal importance due to the lack of special indication
in the chart. Thus in bar chart, long duration activity may appear most
important ones, which may not be true. In building constJ'uction, plastering
work, may take long time but concreting may be completed in a single day
and cOiTcreting is more in'iportant activity.
4. It cam1ot be used as coi1trol device for large projeCts.
5. It is diffici1lt to show critical path, critical activities i:uid floats available.
6. Data is hard to manipulate i.e. it cannot easily cope with frequent changes or
updating. The bar cha ·t is a static representatim1 of the planned activities and
does not respond to t e dynamic happening on the construction site of the
complex project.
7. Updating means drawi1g the entire chart again and again
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 4. 0
Example
H 4
i:. Draw the bar chati and find out the completion time of the p'roject.
···;
i')' Solution
Activity/week 1 2 3 4 5 6 7 8 9 10 11 12 13
A
B
c
D hi·
E
F
G
H
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 4. 0
Milestone chart
To overcome some ofthe limitations ofBar chart, Milestone Chal't and Linked
bar charts are developed.
Milestone cha1i is a modification over the original Gantt chart (bar chart). Milestones
are the key events i.e. start or end ofthe activity. A Chart that graphically depicts key
evel1ts along a timescale, usually with ti'iangles repres'enting each event, is called
milestone chart. It can mark specific points in the project where checks can be made·
to see if the project is on time and \vhere it should be. The best place to locate
milestones is at the completion of a major activity. For a building construction, there
are various activities but milestones may be considered as laying foundation stone,
concreting, inauguration etc.
One of the main drawbacks of simple bar chart is that it does not show the
interrelationship between activities. The links between tasks are the heart of project
scheduling. Linked bar chart uses the Jinks (arrow) to show the relationship betweei1
activities. There are mainly four types of relationship between activities.
1. Finish to Start
2. Start to Start
3. Start to Finish
Fi11isli to Fiitisb
The linl<ed bar chart has advantage of exhibitii1g the effect of delay 011 succeeding
·activities and also it can provide sortle information of the extra tit'ne available (if there
is) with an activity for its cot'npletion. The extra tifne available for an activity for its
completion is called float. Similarly, the activities, which do not have extra time for
co1npletion, are called critical activities.
Network Techniques
-·
It is one of the efficient modern tools for planning and scheduling in Project
management. In a complex projects, there involves large number ofactivities, hence
project scheduling becomes almost impossible with the use of conventional method of
scheduling like bar charts. Complex projects, if not correctly schedilled, will most
probably result in either under estimation or over estirnatioi1 of ·the project
•iinplementation period. Both of the estimation will have serio1.1s conseqnences in any
project. If the project com:pleti6n tih1e is underestimated, the actl1al it'nplemel1tation
period will be more tha11 the estimated period of time resulting in 'time oven·on' and
ultimately leads to cost overrim of the project. If the additii:mal cost dt\e to cost
overrun is not made available in time, the project completiot1 will sllffer a setback.
Network · ased scheduling of projects come handy in solving cotnplex projects
scheduling problems, There are two popular network based scbedoling techniques.
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 4.0
a) Critical Path Method - CPM developed in the year 1957 .by Morgan R.
Walker of DU Pont arid James E. Kelly ofRemihgton Rand for preparing
shutdown schedLlle of a chemical phtnt. .
b) Program Evaluation and Revie'\v Technique - PERT, develbped by US
Navy in 1958 for scheduling Polaris Missile Project
Though the two methods are conceptually similar except for certain minor differences,
they were developed independently in USA.
1. ACtivity (Task): An activity is any identifiable job which requires time, manpower,
material, alld other resources to complete. It means the performance of the specific
task of project. Arrow in a network diagram ~presents activity. The following are the
examples of activity for a building construction project.
• · Layout
• Excavation offoundation
• Construction of wail Layout
• Concreting
• Construction of roofing
• Wiring and electrification
• Plastering and paining work
Prepared By: Er. Subash K. Bhattarai.(B.E Civil I PGDESD I MPA I MSc CM) I Chapter 4.0
Sel·ial Activities: Those aCtivities which are to be performed one afteJ· the other, in
succession are known as serial activities. Serial activities canimt be performed
independently. In the figure below construCtion ofwall and plast~ring are serial
activities.
For a given activity, the activity that occurs immediately before it is its predecessor
whereas for a given activity, the activity that follows immediately after it, is its
successor.
2. Activity D nration
An activity's duration is the amoilnt of time estimated for its completion. The tin1e
•·.·. unit for the project can be minutes, hours, work days, caJendar days, weeks or months.
Most construction schedule comn1oi1ly use dt:1rations of work days or calendar days.
The use of the time units expressed should be consistent throughotit the schedule.
• Resource availability,
• Work quantity,
• Nature or complexity of work,
• Labor and equipment productivity,
• Quality of field management,
• Weather and site conditions,
• Concurrent activities .
Two conventions can b'e used for developing networks are: Activity on
Arrow (AOA) and Activity on Node (AON).
Activity oti Arrow (AOA): Ui:rder this convention the following rtlles a'pply.
Generally, the name of the activity (Or symbol of the activity is) is indicated above
the arrow while the dtlration ofthe activity is indicated below the arrow.
Event 2 is the head event. of activity -Earthwork in excavation as well as tail event of
activity- construction of wall.· Hence event 2 is doa1 role event.
0E70~
T2i~/ Burst . Head/ Merge event Dual Role event
4. Dummy activity
Prepared By: Er. Subash K. Bhattarai (B.E CiYii. PGDESD I MPA I MSc CM) I Chapter 4.0
2. Logical pmpose: Dummies are also used to give logical clear represe11tation in
a network having an activity common to t\vo sets of operations running
parallel to each other.
1 Dummy
D
c
Set I activity A and Bare tobe performed serially while Set 2 ~ctivities C and D are
to be performe serially. Both the sets are performed simultaneously. However, for
practical consi erations; we fii1d that activity D of set 2 cannot be performed unless
activity A of s t 1 is completed. He11ce a dummy is used joining i1ode 2 and 5
indicating that ·ctivity D cm1nbt be started unless activity A is cmnpleted.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) j Cht1pter 4.0
a.All activities shall be represented by way of straight arrows pointing from left
towards the right. This means flow of 11etwork shall be from the left to the
right.
b. There must be only single initial node (tail event) as well as ending node
(head event) in a network. Initial node has only o11tgoing arrows, whereas
ending node has incomii1g a1Tows.
c. An event cannot occur morethan once, i.e. there cannot be any i1etwork path
looping back to previously occurred evel1t. Thi.ts network show11 in figure
below is incorrect.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD IMP A I MSc CM) I Chapter 4.0
e. There should be only one arrow for an activity, i.e. nun1ber of arrows should
be equal to number of activities.
f. There shall not be unnecessary dumt11)1 activities in the network. Dummy
activity shall be introduced oi1ly when it is absolutely necessary and without
which the netwod<: diagram cannot be completed.
g. In short, CPM network diagram must answers the following questions:
1. What activity or activities must immediately precede this activity?
u. What activity or activities cannot be started until after the completion
of this activity?
m. What activity or activities can be performed COJicurrelitly with this
activity?
7. Event Time
a. Earliest Event Time
The earliest occurrence time or earliest event til11e (TE) is he earliest time at which an
event can occur. It is the time by which all the activities accomplishing an event are
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc c,f} Chapter 4.0
completed. In CPM network, the time of completion of each activity (tij) is known.
Hence the earliest 6cctirrence time can be easily calculated. We can. formulate the
following expressions for (TE) of any event j using forward pass calculation.
.The latest event tii11e or latest allowable occurrence time (TL) is the latest time by
which an event must occur to keep the project on schedule. The latest event time for
an activity is completed by. sta1iing from tail event and using backward pass and
taking minimtun valt\e.
(TE) j
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 4.0
8. Activity time
CPM is activity otiented; CP.rvi: consist of following activity times which are
useful for network computations.
tH
Examples: 1
Draw a network with the following details. Number the events using Fulkerson's rule
Solution: D
'•
Examples: 2
Draw a network with the following details. Number the events using Fulkerson's rule.
.......
Solution
SN Activity Predecessor Successor
1 A - B,C
.2 B A D
3 c A E,F
4 D B F
5 E c -·
6 F C,D -
"
/"
"" E
It uses circle to represent the project activities, with arrows linking them together to
show the sequence in which they are to be performed. The main a:dvaiitages ofAON
techniques are that it does not require dLimm activity and show EST and LST directly
in the network. In AOA there can be only ore type of relationship bet\-veen activities
i.e. Finish to Start however in AON it is poss le to establish four types of relationship
as i11entioned in Linl<ed bar. This is also kno 11 as Precedence Diagramming Method.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM)I Chapter 4.0
A network represents the logical sequence ofactivities ccintait1ed inthe project. The
activities are represented by anows and arrows flow frol'n left to right. In a network,
there may be many paths starting fi·om the initial event and leading to the last event. If
the duration of all the activities that lie on particular paths is added, it gives the
duration of the path. Each path in a network will have a different duration. The path
that has the longest duration is called the critical path and the activities lying on the
critical path are critical activities. It is the critical path that sets the overall duration of
the project In a following network, there are seven activities and from event 1 to
event 6 there are tlu·ee paths.
D (3)
Thus Activities A, C, E and G are critical activities and Project duratioi1 is l9days.
1. Critical path is the longest path (time wise) connecting the initial and final
events.
2. Critical activity may run through dt\mmy activity/activ ties also.
3. The number of activities lyil1g on critical path may be ess than the Tiul'nber of
activities in other non -critical activities.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) [ Chtrpter 4.0
4. It is possible that a network may have 1i1ore that:i one critical path i.e, if two or
more paths have the same time duration which is !'naxin1um, then all such
paths will be critical paths.
The method of fii1di1ig out the number of paths available in a given network
connecting the initial and fit:ial events, finding the time duration of all the available
paths and identifying the critical paths is suitable for small networks. If the network is
relatively larger in size; there will be larger number of pa.ths available connecting the
initial and final events. The method uses two series of computatio11s viz., Forward
pass computation m1d Backward pass computation.
Event 1 2 4 5 6
No.
Early vent 0 0+4 = 4 4+2 = 6 4+5= 9 6+3= 9 15 + 4 =19
time
9+6 = 15 9+1 = 10
Late vent 4-4=0 12-2=10 15-3=12 19-1=18 19-4=15 19
Time
9-5=4 15-6=9
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I JvlSc CM) I Chapter 4.0
Thus in the above network, Events 1, 2, 4, 5 & 6 have both the times (early event time
ai1d late event tirnes) ire equal.
In the above network, Activities A, C, E and G are critical activities. Since the two
time estimates of all the critical activities are same, it means that succeeding activity
in a critical path shall commet1ce immediately after preceding activity is completed so
that project will be completed in time (19 days). Activity G shaJ] stmi immediately .
after activity E is completed; activity E shall start in1mediately after activity C is
completed; Activity C shf:tll start immediately after aCtivity A is completed. If there is
any delay in either starting a critical activity or if time taken to complete the critical
activity exceeds the estimated time, project implementation period will get extended.
Thus it is obvious that only the critical activities get more attention fi·om the
management. Any delay in critical activities lead to time overrun of the project which
ultimately results in cost overrun. All paths in the n·etwork other than critical path are
called non critical path. A non-critical path may have only non-critical activities or a
combination of both critical and non-critical activities.
Floats means the available fi·ee time for an activity, which is useful for managers to
manage the limited -resources. There are four types of activity floats (slacks) in
network problem. A detailed study of non-Ci·itical activities with regard to the 'free
time' available is worth doing sihce it will help in better conu·o] of the project
· implementation and better allocation of resources. This study is ktlown as activity
float analysis.
1. Total Float (TF): Total Float represents the maximiun time by which the
completion of the activity can be delayed without affecting the project completion
time. If an activity is delayed by a time equal to its total float, that activity and all
other subsequent activities in that path bE:come critical. Mathematically,
2. Free Float (FF): It is the delay that can be permitted i.e. the spare tin1e allowable
for ai'J activity so that sl.Jcceeding activities in the path are not affected. If the
succeeding activities are to remain tin-affected by the delay in a particular activity
the earliest· start Time Of the head event of that activity shall not be exceeded.
Mathematically,
FF = ESTj - ESTi- ij
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 4.0
3. Independent Float (lF): It is the spare til'ne available for the activity, if preceding ·
activity is started as late as possible and succeeding activities are finished as early
as possible. It is maxin1um delay allowable for an activity so that the start time of
succeeding activities are not affected. It may come negative (super critical
activities) but should he taken as zero. Mathematically,
4. Interfering Float (IF1 ): It is the nari1e given to head eve11t slack (Sj ). It is the
difference between total floa:t and free float. It is the excess of minimum available
time over activity time.
IFl = TF- FF = Sj
All the floats are equal to zero for critical acttvtttes. Critical path JS that path
connecting activities having Total Float Equal to Zero;
Ll
FF E-l IFl L-J
~----~~--~·+---~
TF
IF
Pi"epared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 4.0
I A 4 0 4 0 4 0 0 0 0 Critical
2 B 2 4 6 10 12 6 0 0 6
3 c 5 4 9 4 9 0 0 0 0 Critical
4 D 3 6 9 12 15 6 6 0 0
5 E 6 9 15 9 15 0 0 0 0 Critical
6 F I 8 10 18 19 9 9 9 0
7 G 4 15 19 15 19 0 0 0 0 Critical
1. Total float belongs to the path. If the total float is used entirely for a:n activity,
it would make that activity and all other activities in that path critical. Hence
it is not advisable to use the total float completely in an activity as there will
be no cushion available if subsequent activities need additional time for
completion than originally planned.
2. Free float can be used completely for the activity since this does not disturb.·
the succeeding activities. However the preceding activity should have been
completed as planned.
3. Independent float of an activity does not depend on precedi11g activities and it
also does not disturb succeeding activities. Hence independent float can be
used without any constraint.
5. Determine earliest start a:nd finishing tin'H::s using a forward pass through the network.
Equations: forward pass EST of the activity is Early occurrence time of tail event and EFT =
EST+D
6. Determine the latest start and .fmish times for .each task. LFT is' equal to the Latest
occurrence time of the head event and LST = LFT- D.
7. Determine slack/ float for each task using difference between latest and arliest start times.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) J Chapter 4.0
8. Find tasks with zero slack. These are critical tasks lying on the critical path.
Numerical examples: Find all the components of CPM from the following
inforn'lation.
Computing the forward pass from left hand side to right hand side i.e. from tail
event to the head event. We have to add the given duration (ti.i) to compute the
forward pass. This will give the earliest start time (EST) of an activity. The
higher values will the taken while computing forward pass.
Similarly, the backward pass is computed from head event towai'ds toil event.
The lowest value is taken to compute LST:
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) J Chapter 4. 0
0EST
~
0LFT
0 A 3
G),--~>Q)
.C.
Where,, 10r EST, t-IJ·= 3
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 4.0
Now, computing total float (TF), free float (FF), Independent float (IF) and
Interfering float (IF 1)
=1 =1
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 4. 0
Computing all the values for all activities as shown in above calculation.
Summarizing the values as shown below:
,., ,.,
F .) 2 5 6 6 4 1 -3( 0) .)
G 7 6 13 6 6 0 0 0 0
,.,
H 3 7 10 10 10 3 .) 0 0
., ,.,
I 4 6 10 9 9 .) .) 0 0
Here, the longest path is critical path B -dummy - F ~ 13 days and critical
activities are B & F
SoJD . Drawing the network diagram and computing EST, EFI, I STand LFT
first and then calculating floats.
Prepmed By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I \1Sc 01:, Chapter 4;0
I~ 9
9.
0, 3, 7
13
. 13
n :>
5 0 5 0 5 0 0 0 0 Ic- £
~
'!i
~~
·.-;:.
,.., i '
.·
c ·:·
.J 0 3 7 10 7 2 2 b I
\.·;:.
·,?i·: i
D 4 5 9 5 9 0 0 0 0 ic
E 2 5 7 10 12 5 2 2 3
F 4 9 13 9 13 0 0 0 0 c
G 1 9 10 12 13 3 3 0 0
I
,..,
H .) 5 8 10 13 5 5 0 0
I 2 5 7 14 16 9 9 4 0
,..,
J .) 13 16 13 16 0 0 0 0 0
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Clraptet 4.0
Example:
Draw a CPM network diagram. Find Critical path, critical activities, project duration, EST, EFT, LST, LFT, TF, IF (both independent
and interfering).
S.N. Activity Duration (days) Predecessor Successor
1 A 1 - D,E
2 B 6 - F,J
,
.) c 2 - G
4 D 2 A H I
5 E 4 A H
6 F 3 B I
7 G ~
4 c J
8 H 2 D,E K
9 I 5 F L
10 J 3 B,G -
11 K 3 H L
12 L 4 I,K -
''
Prepared By: Er. Subash K Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 4.0
........
Solution
~
·l:J-
\
H(2) .,
\
''
0
ffi c (2
1\
Prepared By: Er. SubashK. Bhattarai (B.E Civil I PGDESD I Ml't\ I MSc CM) I Chapter 4,0
Activity Duration EST EFT L:S'.E '.;c; 'LFT-' Tli:;-; FF IF IFl Remark
1 A 1 0 1 4 5 4 0 0 4
2 B 6 0 6 0 6 0 0 0 0 Critical
,
.) c 2 0 2 9 ]1 9 0 0 9
4 D 2 1 3 7 9 6 2 0 4 -veiF
5 E 4 1 5 5 9 4 0 0 4 -ve IF
,
6 F .) 6 9 6 9 0 0 0 0 Critical
'
7 G 4 2 6 11 15 9 0 0 9
8 H 2 5 7 9 11 4 0 0 4
9 I 5 9 14 9 14 0 0 0 0 Critical
10 J 3 6 9 15 18 9 0 0 9
,
11 K .) 7 ! 10 11 14 4 4 0 0
12 L 4 14 18 14 18 0 0 0 0 critical
• The critical path is 1-:-3-..7-10-11 show1i in dark arrow line.
•· The critical activities are B-F-1-L. The project completion time is 18 days
Prepared By: Er. Subash K. Bhattaral (B.E Civil I PGDESD IMP A I MSc CM) I Chapter 4.0
r' I I 9 ·1
---·-·-·~- ['tl~Ltl.
"~~~.li•mJ··········· J I j0l
=~~s;;r~e-
=<~~= ~L.z_''"''"'"~'''''""1~~
=P
5 »W<-;·, 7;
, 4 r -· · E 4 --:tl~·-~--
~---,-~,J-=
~---·- r
· ·- ··;:; . • !riq 'Jjl'41 L.,.fhrl 18
~ =:r~~~=jT ----~Fln!sh (18)
: :I~ .:..-=:~~:~-~=-:31
5
) - .J __ .. =r4===:-=I=s··
i«=BJ J~ .. ·
"""""'"" '"'""""'""
1§.. . . _j
. . J.9. . . . . . . . .''"""""'"~ ri ---] (· .
..... ::!...........................A..... L] ' .
,4ot~.
< ~
8,F,\ ~ L; <.n·uo;;:.l·'l"b-.,,1,.,,.
' , •• , • • • • • • • , • •• ' >
1_;;=----=--t---"1 ~ 9 ~ .·.H~;ir:9.·:?.~~~;~.:~~~··.··it~-·
li N·· m"'· w;.,+met.t
f"'
.- ;;>htit , lt)l,.
="' . . EP: earfi.IJ!!t Fink£:'1 Tlm.;;
Ls~ L~1t-asl SEs1t:.T:Wr~c
LF:. Litbl~ .Fini'Sh. TirniJ
TF ·TolaJ Hm"t
Froje·ci Ccrnr:•'"tirm ·durst,•c•"•: HI d:py.'}
><
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 4.0
There many pros of using the critical path n]ethod dnring ptoject planning and
execution. The critical path method:
For large and complex projects, it is best to use specialized software like Ms-
Project and Primavera:. This software generates data, such as activity float,
automatically for you. Next, let's. take a look at some Critical Path Method
disadvantages.
There aren't many disadvantages to Y;itical Path Method. Me11tioned below are
the cons of Critical Path Method. · ·
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc 01) l Chapter 4.0
• The Critical Path Method does not account for resource and resource
allocation. Critical Chain will be handy in these situations.
PERT -Program Evaluation and Review Technique.
Project manager would be i1iterested in completing the project at the mmunum
possible time but it is not entirely in his hand to do so. There are many factors, both
internal and external to the organizations which have influence on the completion time
of each activity in the project. It is a probabilistic approach for estimating the duration
of an activity and event oriented network diagram. PERT is used in the completely
newly developed project such as Reseat-ch and design, new industries product design
·.and there may not be record of past experiences in the pa1iicular field. PERT system is
preferred for those projects in which correct time determination for various activities
cannot be made.
PERT uses three time estimates for each activitY with a view to overcome uncertainty
in time estimates.
a) Optimistic time estiniate (to): It is the shortest possible time· i!'t \\ihich an
activity can be completed under ideal conditions. Til arriving at the optimistic
time estimate, it is assumed that everything is favorable in co.nipleting the
activity in the shoiiest possible time.
b) Pessimistic time estimate (tp): It is the maximum possible time it would take
to complete an activity under worst conditions. In arriving at the pessimistic
time, it is assumed that everything is unfavorable for completing the activity
in time and every possible delay and difficult situation is encouhtered.
c) Most likely time estimates (tm): It lies between optimistic and pessimistic
time estimates. It is the time in which an activity can be completed under
normal conditions. In arriving at the most likely time, it is assu111ed that
conditions are neither favorable nor unfavorable, but normal.
Expected time estimate (te): PERT assumes that the optimistic time (to) and the
p·essimistic time (tp) are equally likely to occur while the most likely thne (th1) is four
times more likely to occur tha11 the others. Hence foi" arriving at the expected ti111e (te)
,.,.e use following fon'nula
To arrive at this formula we must assume s0Ii1e functional fon of the activitytime as
shown in the figure below. It was observed that beta disti·ib ttion suits well for the
purpose and hence same was accepted as a mathematical rn del fot arriving at the
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) j Chapter 4. 0
mean (te). The formula is a linear approxi!'nation of beta distribution whose accuracy
is considered reasonably stJfficient.
Aftei" having arrived at the expected time (te) for each activity, tl~e critical path is .
found out by making forwardpass computation and backwardpass computation as in
CPM. Variance in activity times: Consider the followiJ1g two tiine estin1ates.
Activity to tm tp
te
to + 4tm. · + tp
--
6
A 3 4 5 4
B 2 3 10 4
For the activities A & B the expected time arrived at is the same. However as seen, the
diffel·ence. between to and tp is more for activity B than for activity A. Thus, thot1gh the
estimated expected time (te) is the same for both the activities, there is greater extent
of uncertainty in the same estimate for activity B. Thus the reliability of the expected
time (te) depend uponthe variability of two time estimates to and tp.
1. Variilnce and
2. Stai1dard deviation.
PERT uses the following simplified formula for arnv111g at the variance and
standard deviatiai1 of activity times.
Variance ( 0 2)
t "-t
= [. P
6
°]2 andStandartl deviation (0) = [t °]
P
6
~t
1.00 .
Probability of occurrei1ce
0.80
0.60
0.40
.20
Activity time
.00 1
I
tm
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 4.0
Example
~ - 4 5 6
B - ~ 6 8
c A 3 5 7
D B I 3 5
E C,D 2 5 8
F C,D 3 ~ 11
G E ~ 5 12
H E 4 4 10
I F,H 5 6 13
Draw a PERT i1etworkfor the following data. Arrive at the criticalpath and find out
the estimated project duration along the critical path.
Solution:
The first step involves is to calculate the expected time (te) for all the activities from
the given three time estimates, llsing the formula.
A 4 5 6 5 0.33. 0.11
B - 4 6 8 6 0.67 0.44
c A 3. 5 7 5 0.67 0.44
D B 1 3 5 5 0.67 0.44
E C.D 2 5 8 5 1 1
F C.D 3 ~ 11 5 1.33 1.77
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 4.0
G E 4 . 5 12 ~ 1.33 1.77
H E 4 4 10 iS 1 1
I F,H 5 6 13 17 1.33 1.77 ..
5
15115
0 0
I
·~ .
Critical Path is 1-2-4-5-6-7
Variance of Te(Which is nofhilig but the suni of variai1ces ofali activities along the
critical path)= 0.11+1.77+1+1+0.44 = 4.32
Let's assume that we have identified the critical path for·a given PERT network. The
expected project completion time (Te) is the sum of expected corilpietion time (te) of
all the activities lying on critical path. The activity expected time (te) has a probability
of 0.5. Hence, the probability of cuniulative expected time (Te) also has a probability
of0.5.
For the easiness in calculation, it is assum d that the project completiol1 time follows
the normal distribution. If'Z' is the numqer of standard away fi·om the mean for an
observation, Z can be represented as,
Prepared By: Er. Subash K. Bhattarai (B.E Ci"i,il I PGDESD IMP A I MSc CM) [ Chapter 4. 0
Where 'Z' is known as standardized normal deviation. Tbe value of 'Z' also follows a
normal probability distribution with a mean of 'zero' and a standard deviation of
'one'. This probability distribution is know:n as standal·d normal probabili1ty
distribution and it allows us to use single table areas under the normal curve fOlr all
types of normal distributions.
z Probability z !. Pmbabii1iiD>--
0.00 0.5000 0.00 !0.5000
-0.1 0.4602 0.1 ""' li 0.539:S
-0.2 0.4207 0.2 0.5 .i :S3 :
-0.3 0.3821 0.3 . 0.6119 :
Prepared By: Er. Subash K. Bhattarai (J3.E Civil I PGDESD I MPA I MSc CM) I Chapter 4. 0
In the abOve example, mean value of project completioi1 time is 27 this means
probability of completing the p1~oject in 27 days is 0.5 {50%). 1f the project manager
wants to know the probability of co1i1pletion of the project in 25 days, i.e. observed
valne is eqlial to 25, then 'Z' value is equal to (25-27)/2.08 = -0.9615 from table
probability is equal to 16.84 %(Interpolating)
CPM originated from construction project whereas PERT is originated from R & D
projects. Both CPM a11d .PERT share same. approach for coristructing the project
network and for determining the critical path of the network. However there are some
basic differences between CPM and PERT.
SN CPM PERT
1 Time estimates are Time estimates are
deterministic so use single probabilistic with m1certainty .
time estimate for activity in activity dtiration so liSe three
duratioi1. time estil'nates
2 Activity oriented network Event oriented network
diagram diagram
3. Focused on time cost trade Focused on time only; 110 cost
off
4 More suitable for simple More stJitable for new and·
and repetitive projects like complex projects like research
construction and developinent.
5 . Easy to maintain. Costly to maintain
Resource
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc Cd) Chapter 4;0
Resource Allocation
Resource Aggregation
The step-by-step proced'L1re fo:r obtaining resources histograms for a given prq_iect \\Eu1
or without computer usage are as listed below.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 4.0
allocation carried out in the previous stage. The results are usually shown graphically
as a histogram. Such aggregation maybe done on an hourly, daily, or weekly basis,
· · -
7
depei1din)forftne-fiine-unitusea-to ·anocafer-esot1rces.-wh'ei1-a oar- Ciiarf is usea-a·s -tile-------
planning tool, the resource aggregation is fairly siniple ai1d straightfohvard. For a ·
given bar chmi, there is a unique resoilrce unit aggregation chart which can be drawn
underneath the bar cha:rt.An example is shown in Figure below, where, for a particular
resource, the reqLiircd resource units for each time period are annotated o'n the bar
chart. The total number of resource Linits for each time period can then be summed
and a resource aggregation or load chart can be produced.
Resource Leveling
When performing project planning activities, the manager will attempt to schedt1le
certai11 tasks simultaneously. When more resources such as mac ines or people are
needed thari are available; or perhaps a specific person is neede it1 bOth tasks, the
tasks will have to be rescheduled concurrently or even seguenti lly to manage the
constraint. Project planning resource leveling is the process f resolving these
conflicts. It cai1 also be used to balance the .workload of primary resources over the
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Ch(lpter 4. 0
course of the p1"oject[s], usually at the expense of one of the traditional triple
-------- -- C-constni:iiits-(titne,-cost;-scope]--- ~-- -- ----- -- --------- ---'-~7-----
--- - ---------- -- - ~ -------- -~ - -
Resource Leveling is the method of scheduling activities within their available float so
as to minimize fluctuations in day~ to- day resource _requirements. By resource
leveling, we try to optirnize the use of resources required to complete a project.
Resource leveling helps in obtaining uniformity (as far as possible) in resource
requirement throughout the life of a p1'oject. The benefit of resource leveling is to ease
resource management so that cost~ involved in managing resources can be minimized.
It is an attempt to reduce peak resources requireme11t and smooth out period to period
assignments within the constraitits of project duration. A project 111anager often comes
across mismatch between the availability of resources m'ld the· requirement of
resoUrces. This means that there are surplus resources available on someday and there
is deficit of resource on some other days. It will be uneconomical to perni~nently.
employ personi1el to satisfy peak time requirements since there will be .under
utilization of personnel_ to many days. Hence only less number of persotmel than
peak time reqt1irement during peak time can be handled by hirii1g on casualbasis.
Since the personnel require1nent varies from day to day, the project manager should
plan properly in such a way that optimum utilization of available personnel is
achieved. Thns the objective of project manager in such a situation is to level as far as
possible the demand for resources throughout the project executi011 tin1e keeping in
view that project completio:n time does not exceeds.
Prepared By: Er. Subash K. Bhattarai (D.E Civil I PGDESD I MPA I MSc CM) I Chapter 4.0
Resource Smoothing
Spending more rnoney to get somethi11g done more quickly is called "crashing." .
The objective of prqject crashing is to reduce prqject duration while minimizing the
cost of crashing. Since the project completion time cai1 be shortened only by crashing
activities on the critical path, it may turn out that not all activities have to be crashed.
However, as activities are crashed, the critical path may change, reqLiiring crashing of
previously noncritical activities to reduce the project completion time even further.
The project manager is frequently ccmfi·onted. with havi1ig to reduce the schedtlled
completion ti1:ne of a project to meet a deadline . .In other words, the manager nmst
finish the prqject sooner than i11dicatedby the CPM/PERT network ~m~lysis. Prqject
duration can often be reduced by assigning more ]~bor to prqject activities, in the form
of overtime, and by a:ssi ning rriore resources (material, equipment, and so on).
However, additional labor nd resources increase the prqject cost. Thus, the decision
to reduce the project dmat · n must be based on an analysis of the trade-off between
time and cost. Project era hin;; is a method for shortening the project duration by
reducing the time of one or more) of the critical project activities to less than its
normal activity time. Thi reduction in the normal activity time is referred to
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 4.0
! ..
Project cost
For any project total expenditure incurred in terms of. man power, equipment,
machinery and materials and time to achieve aparticulargoal is known as total cost of
the project. The total sum of the project is the sum of two distinct costs.
• Direct cost
• Indirect cost
Direct cost
The cost of materials, equipment and money spent on man power form the direct cost.
The direct costs of project ate of major concern and behavior panem of direct costs
with time is of importance. Direct cost of a project depends on the c.ompktilO>n tiiw.e of
project, but the variation is not linear.
Total cos:<:
Cost rises if . . .
projects is . Cost ns~ 1f
...------crashed T. /project JS
une cost j)i·o]onaed
~ "
Minimum cost
Indirect cost
The expenditures which cannot be allotted clearly·. o the i11dividual activities of the
project, but are assessed as a whole are called indii·e t costs. The ii1direct cost includes
overhead charges, administrative and establishment harges, supervision charges, Joss
of revenue, loss in profit and penalty etc.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGD:ESb I MPA I MSc CM) [ Chapter 4.0
Definitions ofTenns
Normal time
The time usually allowed for an activity by the estimator is known as normal time. It
is the standard time for that activity and is denoted by (Tn).
Crash time
The miniinum possible time in which an activity can be completed by deployii1g extra
resources is known as crash time. Beyond the crash time the d11rationof m1 activity
cannot be reduced or shortened by any an1ount of increase in mobilization. It is
denoted by (Tc).
~ormal cost
The direct cost required to complete the activity in the normal duration IS called
normal cost and is denoted by (Cn).
Crash cost
The direct cost corresponding to the crash time of completing an activity is known as
crash cost and is denoted by (Cc ).
Cost slope
The direct cost curve generally is a curve as shown below. But this ctlrve can be
approximated by the straight line ot more than one stl'aight lines deper1ding upon the
.'$!' .
flatness of the curve. Thus the slope of this. straight. line is cost slope.
Minimum duration
The duration obtained after crashing all activities is k11owi1 as 111inirntn. dl!ration:
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 4.0
Time and cost are the two most in1portant resources that a project manag'er deals with.
Both of these resources have constrains and the job of a project nianage:r is to have
judicious balance between them. The judicious balance between·· tin'!e and cost is
called Time-Cost trade-off and it cai1 be achieved by studying the availability and
demand of these resources for the given project.
The. sut'n of direct costs and indirect costs is known as total costs of the project. The
relationship between indirect costs~ direct cost and total cost with duration is given in
figure above. Frmil figure it is see11 that the curve of direct costs do~s not have a linear
relationship with time. Thus the conl.bination of direct and if1direct cost gives a
curvilinear relationship with time as shown. •
From the total cost ACB, it can be seen that the total cost of a project is mit1imum for
certain time duratiol'L This duration is known as optii11Uli1 duration for the
corresponding minimum cost. Fu:rther if the project duration is increased, the total cost
will also increase. On the other hand if the project duration is decreased to the crash
value, the project cost will be the highest. The optimum duration is less than the
normal duration con"esponding to· the direct costs. This is due to the fact that both
direct and indirect cost increases beyond the normal duration, whereas below the
, normal duratior:i indireCt cost decrease, but the direct cost increases .
...._.....
The jollovi1ing table shows the costs ai1d duration of each activity of a projec:!. The
netwOJ-k is shown. The indirect cost may be taken as Rs. 3150.- per week. Derr?Tm7ne
the optimum duration of the project and corresponding minimum cost.
B 9 5000 6 ·9500
c 5 7000 2 10000
D 6 9000 4 16000
E 6 6000 4 12000
Prepared By: Er. Subash K. Bhat1arai (B.E Civil/ PGDESD I MPA I MSc CM) I C//(/pter 4.0
·. 7, 7
' _:,,'-c·-':B---------__:_,_ ______ ~-·-~--·----- -:-' ::_ ___ ~~----
6
0, 0 18,18
12, 12
. . .
Sol". From the given netwodc diagram: Stii11marizing the dnration and critical path:
Duration (w)
Path Normal Crash
A-D 13 8
rA·=. c·=£· . . . . . . . . . . . . . . . . ··1s.......................................1 10
: :
B-E 15 10
B 4500 3 1500
,.,
c 3000 .) 2500
D 7000 2 3000
E 6000 2 3000
Prepared By: Er. Subash K Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) i Chapter 4;0
-c
b:as minimum cost slope therefore starting fron1 activity 'C'
Here, actiiYii::c
____________ the_r:~nkingjs d<2ne mascendiJ!g~'2.r:.<!~ o:(_~Q§_!_§lope. Start crashing__!h_~w.k_c__!,_ _ --'- ________ _
initiation frcm ilie CP. '"'ith lowest cost slope.,·. Ctashingthe activity 'C' by 3
weeks.
Path Duration
A-D 13 w
['A·::::··c··=·E··-····-- --····:] 18 - 3 = 15 w
And the project duration after crashing is show in table below. Here we can see
that, there are two critical path A- C - E and B - E ~lth dt.n'ationeqi.1als to
15w. So, crashing most be carried out in such a way that the activity JTitJSt be
selected which belongs to both of the path for immediate restllt: As we see in
both paths activity 'E' is cominoi1. So crashiilg it by 2 weeks:
Path Duration
A-D 13 w
r·A·::::··c··=·E··--- ----·------··--·I·s··=-·2·-;;--1"3··-w··l
1.1.?...::::..~---··-·-·------·-·- __ }} __ :."__________________________________________ ,
Extra cost of crashing= 2 x 3000 = 6000, Direct cost= 6000+ 38000 = 44000,
Indirect cost= 13 x 3150 ~ 40950, Total cost= 84950/-
Here, we can see that, all the path becomes critical at this Stage. Tbe project
duration is reduced to 13 w.
Now, Selecting 'A' from path A - -'- - D and A- C - E to crash and simt!ltaneously
selecting 'B' fi·om path B-E. 'A' is selected due to COihmon of both paths.A- D
and A - C -E. So, crashing activities 'A' and 'B' b · 3 weeks simoltaneously we
get,
Prepared By: Er. Subash K: Bhattal'ai (B.E Civil I PGDESD/ MPA/ MSc CM) I Chapter 4.0
Path Duration
A-D
------~------
13 '-= 10 w
-------·-- ---- -- '-----·---------- -·--- ------·---·----'--·-----------------,.----- ---------
A-C-E 13-3=10w
B-E 13-3=10w
Conclusion
We see that after crashing the project from 13w to lOw the total cost of project
increases from 84950 to 87500. Therefore further crashi11g beyond '13 w'
increases the cost. Hence, the optional duration of project is 13 w, the minimum
cost of project is 84950.The minimum duration of project is 10 w, if crashed to
minimum duration corresponding cost be Rs. 87500.
Cost
I I I I
.....
..
--•••••••·-----~----~-~-A
91700 I
I
I
I
I
I
I
I
85250 .
84950
82500
3 6 9 12 5 18 Time
. Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 4. 0
Investments on large scale in:fi:astructures are critical to enable a country to achieve long term. grov;th
·and Sl1stainable povertyreduction. It played an important role in enabling the poor to participate in
the growth process. Access to education and health which are also the indicators of economic
development, can be vastly improved through better road, electricity, communications, water supply,
and sanitation services.
We can eas'ily trace out the investments sectors in the field ofinfrastructttre in Nepal.
The ggal of economic development can only be achieved through the establishment of adequate and
effiti~Bt transport facilities. Nepal has rugged topography about two third area of the country. Hence~
an effi;~iet1t road network has become a challenge. Likewise Nepal is land locked country~ HoweYero
an imHi·ovement and extension of tni11spodation network provides the opportunities to grO'-'-_- the
ecOi10;)1y. Nepal is stilllackiilg sufficient road network. If road networks are extended, Nepal can be
"Land'iLinked" between India and China. From which it can reap the benefit of transit poim bern"ce:n
these 6otmtries. Similarly, for tourism industry, which is regarded as one of the major somce of
foreign· currency earning, m:any infrastructures development in different pans of the comm~
including regional and international airports are the opportunities of the construction induS!r::• 8
Nepal. On the other hand, investment forn1 the gdvei"nment in road sector is 10\v and is nm able ;r,J.
meet the requirements of the country _and aspirations of the people. Hence, contractors 2nd
consultants can and have to play key role in this regard to attract the private sector to make
investme11ts in the road sector following the Built, Operate and Transfer (BOT) approach.
2.lrrigation andHydropower:
Nepal is second richest eountry after Btazil in its water resomce and it has the great pto~pects in
generating hydroelectricity and constructing irrigation projects throughout the country. Although
Nepal has a large reserve 'fwater resources, it is not able toutilizetheirt propetly. At the endofF .
2070/71, the total peak de ahd is arol.fnd l176 (MW) Provisional but the power production is les•
than the demand. Hydropo er p1'oduction is m·ound 700 MW only, which is merely 0.85 percent o
the total potentiality of 83 000 MW. So there is wider scope of hydto electricity market inside th
nation and the possibility o exp01iing to India as well.
The extension of irrigation facilities in the agricultural land can bring crop integration and crop
diversification, which can help to generate employment and reduce poverty. At present only 40
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
percent of cultivated land is covered by round the year liTigation. If power supply generation and
irrigation is possible from the same project, it will be beneficial and cost effective. In this regard, the
feasibility studies of such projects are required to develop the Nepalese construction industry.
-------3.-:ReaJ-S.tate-a.ri.d.J:Iousi-n-g---- -------------+-----~--- --- '-- ----'- -- -_- --- ---· :-'-'------ ---- ----'---'-~---'~-"-·
According to population census 2011, the growth rate of population is 1.35 percent per annnm. With
the economic development of the co uritry, the tendency or the flow of population is from rutal areas
to urban areas. It requires better real state; housing, market complex, good hospitals, schools and
colleges. Still there are insufficient such facilities in Nepal. Though there are lots of opportunities for
local contractor on building real state and housing.
The governme11t ofNepalliberalizes its policies after 1980's. Now government has released the act
related to Build, Operate, Own and Transfer BOOT Act (PPP) -'- 2063, Road Sector Policy 1999,
BOOT Regulation (PP:P) -2064, Hydtopower Act- 1992, Public Infrastructure Build Operate and
Trai1sfer Policy - 2057, Private Investment in Infrastructure Build and Operate Ordinance-~ ·2060.
There is still sol'rie opportunity for the contnictors tlu'otigh Contrattual PPP's as:
Prepared By: Er. Subash K Bhattarai (RE Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
For more Notes and Tutorials Visit www.masenzworld.com
Downloaded from www.masenzworld.com
In conclusion, there is huge task on construction of infi:astructme facilities, both basic as well as
developmental. Living between the two developing economies giants, who are accounted as the
future superpower oftl:e _World innext two decades, and living at neighborhood ofBhutan, Nepal is
still searching and endeavoring to find lasting solution to reduce poverty. Time is rich to learn lessons
fi·om the neighboring countries and march ahead for real achievements, Which will largely depend
upon development projects tlu·ough construction industry .
..,
'1. \1ii51lfl~lwl
~- --~ (fl41%1141dlii'?ll<:'1'l-
' .·. ··~:\
J~.~<-<r trm1 ~ +n1T - 9\9\3"' F<P.m.
:;;~~ ~ - 9 \S'<,c:; F<P.m.
:.'¢w"llli m~ +=rfr~T ~ - \3".. ~ F<P.+TI.
~ ~- ~ ,C!i'r~fr. ~ <: ~) - c:;~9 F<P.m.
-~ m"i"iilfCJ<q(ill:l ~~- 9~9\3.){ F<P.m.
¥.~~
ffi<R:r ~~ - ~~.\3"'"' ~
<l.-1'i>iili<l ~~ - ~o.~oo ~
~ ~~-9'<,,ooo ~ ~ (lL!i- <: ~9,ooo ~ m~
~. ~. ~ \'l¥.ll'illi\'(Cf> ~ ~
~ 3J"d<lf~£1 ~~. ~. mn -~"'oo ){~ ~m ,~) -mx ··
'8\i\cllfCJBI'it~ ~otl£1fCJiil'if~C1fC!Cf>ltl -rR- ~000 m.
X){~ m.~. C:l!C1CJ!illl
~ ~ li'lotl£1fC!lil'i~<11ilfC!Cf>ltl -rR - ~~00 -mx ){~ m. afCf'il1TTT
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
Some of the highlights of the Budget in the field of construction industries are as follows (F'f
2071/72)
: . ...
--- -:· ....:...: ,..:..: __
·------Tn e ·goiie rn riTe nfffas u8ve'r]fci~R'#61'8~b~ itrcfn-"ifefag"et"'for-'fififfs'-&~·1\;~~i~i(h_-~j§- Jtpt- ~- ·.:....:....~-""'";---·---~
Procure sixaircraftsf()r international services and ·15 a(~~rafts for dom~stidir services
J6 construct
% one library and ascienc~
. . . lab in each high
. school
.
)\utom~~~ion of Nepa!'Stoci<Exchang~
- .. . . ' ·-. -~·
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
For more Notes and Tutorials Visit www.masenzworld.com
·: .
Downloaded from www.masenzworld.com
delivery methods." The financing ofthese projects m:ust be distributed amorrg mnltiple pal'ties, so as
to distribute the risk associated with the project while simultaneonsly ensuting profits for each party
involved.
Jarties_i]_z_l!_q_b!'if! in I'Lf!il!Sf_}[_i[£ql!Cing __________________ _____ ~---~--- _ --~'---'-~--:-- ____ _c _ _ ..:.,-.,.'-'-~--c __ _
There are several parties in a project financing depending on the type and the scale of a p'i'oject. The
most usual parties to a project financing are;
1. Project
2. Sponsor
,.,
.). Financial Advisors
4. Technical Advisors
5. Legal Advisors
6. Debt Financiets
7. Equity Investors
8. R.egulatoty Agencies
9. Multilateral Agencies
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) Chapter 5.0
J
e;xtt'Jrrl.~l ~p~ncl,
c:.pt¢i"f21U6hlf3 mhd
ott!t;>1' Vt;.til.Je <;or'ltrlbufinni\.'
In :rtJ'i':1J"It1G:\F ti~1:at fflupport:::; .
th~ C\:lff>Otat..W.tflQ(iJntJ¥¥1
Before knowing about the procurement strategy we should know about the theme of procurement.
Public Procurement Act 2063 and Public Procurement Regulations 2064 (with amendment) Specify
that there are three kinds of job which can be procured and executed. They are procurement of goods,
consultancy services or carrying out any consttuction works. Prior to procuring goods, constructioli.
works, or services, organization shall have to prepare specifications, plan, drawing, design, spe'cial
requirement, or other descriptions.
:BeforeWgoing to procurement strategy employer should prepare the ptocurei:nent plan. Procurement
).(.·
plan is;;a_ document stating the types of procurement jobs and the methods of procurement along \Vith
~ .
PPA, ~PR along with Guidelines prepared by Public :P:rocutemertt Monitoti11g office (PPM())··
describ~s the following ptocurement strategies for procure1ne11t ofeonstruction works as per the total
cost and types of works.
i
!i. i
- 'o_ Procurement Method Contract Size Cont:ractot
I Sealed Bidding
,..,
.) Direct Procurement Up to 5,00,0( 0 All
Prepared By: Er. Subash K Bhattarai (B.E Civil I PGDESD • .\1PA I MSc CM) I Chapter 5.0
For more Notes and Tutorials Visit www.masenzworld.com
Downloaded from www.masenzworld.com
6
~---······----
Users' Co:rnr:nittee
~---·--- -----·---·-·-----·-~
:..Y_R_!QJ?J~1illi.911.'Y9Ll~~9f~!mpJ~- ..:~.9.l11!:.a.£19L _Q.mQt_:___b~ __
nature used
• :(;)\!hete the goods or construction works as requisitioned by a Public Entity are not available
(hnder competitive price from more than one construction entreprene~n· or supplier within the
State ofNepal,
• Where no bid was subi11itted in response to invitation to national level bidding for the
procurement of goods, construction works or other services, and the same has to ~e procured
fi-om abroad,
• Where under an agreement entered into with a donor pmiy; foteign goods, or construction
works have to be procured from foreign assistance soutce,
• Where the Public Entity has certified that the goods or construction works, being of complex
and special nature, have to be procured through an iritetmitionallevel bidd.ing.
Z Sealed Quotation
me Public Procure1i.1ent ·Act and Public Procurement Regulation, g ,ods ancl other services v~lning
:..'P to one million Rupees and construction works valuing np to two Ii illion Rupees may be procured
by inviting a sealed quotation. Provision relating to Sealed Quotation i :
• Before inviting a sealed quotation, a form of sealed quotati h stating clearly therein the
specifications, quality, quantity terms and conditions of supply and time a:nd other necessary
matters of the goods, construction work or othet services to be 'procured shall have to be
prepared.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
• In inviting a sealed quotation, a notice shall be published in a·naticmal or local level news paper
by giving a period at least of 15 days.
• The sealed quotation, once submitted, cannot be withdrawn ot arh.ended.
• The lowest evaluated sealed quotation falling within the cost estimate after fulfilling the terms
--- -----a~<fC0ilci!tioilisilaTi1lav~to-Be-apiJrovecr.--------------------------------- --- --------- -----------
3. Direct Procurement
Expendable or capital goods or consultancy services valuing up to three lakhs at1d construction work
valuing up to five lakhs Rupees may be directly procmed. Provided that a construction work 1.mder
this Section cannot be directly procured fi·om the same individual, firm, company or organization
more than one time ii1 a fiscal year. But Nepali products goods valuii1g up to fifteen hund1"ed
thousand Rupees may be directly procured.
• If only one supplier or con$ttuction entrepreneur or consultant or service provider has the
technical efficiency or capacity to fulfill the procurement requirement,
• If only one supplier has the exclusive right to supply the goods to be procured and no other
appropriate alternative is available,
If the service of a pai"ticular consultant with his unique qualifications is immediately needed for
tHe concerned work or where the service of same consultant is indispensable.
Wo1;ks thi·ough Users Committee
"Force Account'; means any construction work to be carriedoutby a Public E11tity itself It is the
execution of public works by l1sir1g the resources of a public agency of the government, without
recourse to competitive bidding or negotiated contract. Works done by force account may apply it1
following situation:
• The Si e, nature and location of the works being unsuitable for competitive biddi g .
• Works must be carried ol.lt without disrupting existing operations, by crews fam· iar with those
operati ns.
• When he implementing agency can bear the associated risks in a better way than he contractor.
• No co 'tractor is interested in canying out the works .
• Emergencies .
• Institutional development
Prepared By: Er. Subash K Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
For more Notes and Tutorials Visit www.masenzworld.com
·: ..
Downloaded from www.masenzworld.com
SA Project·Delivery Methods
Project Delivery is the. process by which all of the procedures and components of designing and
building a project are organized and put together in an agreement that results in a eompletedproject.
The Owner's approach to organizing the project team that will manage the entire design and
construction process.
Project Delivery is the contractual relationships between the owner, architect/engineer (A./E),
contractor(s), and the management services utilized to design and construct a project.
A project delivery method is a system used by a.n agency or owner for orgm1izing and financing
design, construction, operations, and maintenm1ce services for a Stl'Ucture or facility by enteting into
~;egal agreements with one or more entities or pa1iies.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) [Chapter 5.0
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD · ?\iPA I MSc CM) I Chapter 5.0
For more Notes and Tutorials Visit www.masenzworld.com
-: ..
Downloaded from www.masenzworld.com
consultants for some or all ofthe detail design and can depend upon construction contractor for the
actual hiring and supervision of the labor.
3.Design-Negotiate-Build
• Same structure as Design-Bid-'Build usually the design is complete before:Iiegotiations .
• The coJitractor may be selected on other fattots than low price irtclnding q'ualifica:tiohs,
expertise, reputation and timeline.
• This negotiating process allows both parties to work together on issues including design,
product selection, and project phasing, optimum constructability, scheduling and budgeting.
• Cost is not usually the primary c.onsidetation for selection but the firm's history of
successfully completing complex ptojects on time which will ustially mean an ultimate
savings of money and time with collaboration arid worki11g together.
Negotiated Contracts
A Negotiated Contract is one where the. Principal negotiates directly with a contractor to anive at· a
mutually satisfactory agreement to undertake the work. An owner can enter into contract with a
constnwtor by negotiating the price and method of reimbursement.
·.r·;.:-·
Major items
,, of negotiation are:
Level
il
. and amount of fee in addition to the charge :Schedule.
.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
.· . Wity De~·ign/Build?
OAbilit:y for fast track/phased construction.
/:,(
DBetter relations and communication, more ContraCtor involvement throughout the process. The
design-builder provides only the necessm·y documentation tobuild .the projeCt efficiently.
5. EPC
The EPC contrac stands for 'Engineering, Ptocurement and Constrt1ction' contract. Tend·· an EPC
contract, the co··· ractor designs, procures the necessary materials and builds the proj ·:· t, either
directly or by su contracting part of the work. In some cases, the contractor carties the pi ject risk
for schedule as w 11 as budget in return for a fixed price depending on the agreed scope of\vork. The
cost is negotiated and finalized and paid in mutually agreed installments.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
Own: own the asset for the coi1cession period a:nd the license for the equipmem used.
Operat~: manage and operate plant, carryolit maintenance, deliver product or service and receive
off take Payments.
Transfer: handover plant in operating condition at.the end of the concession period.
professional management.
• Knowledge of construction; systems costs and scheduling is utilized dt.tring the desigt1 phase.
Good opportunities for cost savings and value engineering by having construction expel'tise
involved early.
• The Owner receives the cost be efit of the competition among the subcontractor a:ndsupplier
bids.
• Good communication leads to a ess difficult change process.
• This delivery system requires the project team to share responsibilities where trust, proper
ethics and a cooperative envirom11ent is a must.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
Construction management is defined as- " that group of tnanagernerit activities related· to a
construction program, carried out during the pre~de·sign, design, and construction phases, that
contributes to the control of time m1d cost in the constrt:tction of a 11ew facility. This approach unites a
a
three party team consisting of owner, designer and CM in non- adversary reh1.tionship.
Construction management contracts are particularly attractive to organizations that periodically build
con1plex structures (e.g., hospital authorities, municipalities etc.) but do not desire to maintain a full
tiine c'bi1struction staff to supervise projects·on recurring basis .. In suchcases;.ari owner can retain a
.·firm as construction manager to plan, develop arid co-ordinate the activities of one or more design
· professionals; trade contractors, vendors and other interested pmiies snch as licensing and control
bodies.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
For more Notes and Tutorials Visit www.masenzworld.com
·: ..
Downloaded from www.masenzworld.com
• If a person advances a proposal to a person, who gives his acceptm1ce, contract exists. Offer
can be specific or general.
2. Consideration . . .
It is the cause, motive, price or impelling influence that inducesa contracting party to ,el1tet into
---contract~- Cons-ideration -caii-be-de~crll)ed -as--something- orviiiue~ thit~is-ixchanged-_by~the____ _
conti·acting pm1ies.
3. Capacity to contract
For a contract to be legally binding and enforceable, all parties must be capable to enter into
contract. As per the contract act, the following persons are not capable of contract. Idiots,
drunkards, insane; and children below 16 years are 11ot capable ?fsigning contract. ·
4. La-vvful pwpose
Illegal contract are invalid. If two pmiies agree to perform a job, Which is against the country law,
the contract is invalid.
:>. Possibility ofpe;formance
Impossible contract is invalid. If two parties agi-ee to build a house on air, which is impossible,
contract is invalid.
6. Free consent
Co.htract
,,,·,
should not involve coercion, fraud, undue influence, deceit. Otherwise, cm1tract 1s
in9n1id.
- Certainty/ u11certainty
Coi1tract which cannot be carried out because of various reasons (vague/ an1biguous etc.) are not
valid. . ·· · .. ·
:; Legbl Relationship
There should be a clear intention of parties to enter into contract i.e, all the necessary documEmts
should be fulfilled. ·
l: Written
Verbal agreement cmmot be a contract.
"·o. Tvvo or m.ore competent parties
Contract is made between two or more pmiies.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
1. Valid Contract -Ifall the ele1nentsof conhact are present, the contl'act is valid.
2. Voidable Contract- As per con:tract act; following contracts ate voidable, i.e. if the pmifdesire to
make it void (invalid).
- -- - -- -;----Fc>-rce:ful C:on1lictoi-coiitiac1 ag~ii-isr:&~e-conse111oico111raCi:'::invBTt-ing':':fra:ua.- --~- -.~-----,------
• Entered dl.1e to undue influence
• Contract involving :fi:aud 6:r misstatement.
3. Void Contract- As per contract act the following contracts become null a11d Void.
Engineering contracts, whether Main Contracts or Subcontracts, can ntrther be classified in a number
of·ways, each ofwhich depends upon a particular characteristic o~ feature · ·
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5. 0
For more Notes and Tutorials Visit www.masenzworld.com
. ~ ...
Downloaded from www.masenzworld.com
The Three most commonly used characteristics for this purpose are:
I) The method by which payment· for the wol'k under the contract is evaluated.
2) The method by which the contractor is selected.
---- ·- --2.l--Co1npefifivetencre1.-ecr ------ --------------- - ------------ -~--------------- ----- ~ ~- ---
2.2
Negotiated contract
3) The method by which the responsibility for the technical and administrative aspects ofthe.work is
allocated. (as discussed in project delivery methods)
A brief description of different contract types under above .mentioned categories are as summarized
below.
The method of payment is of such in1portance, particularly to the Coritl'actor, that contracts are often
classified solely by the method of payment. There are three basic methods of payme11t used in
Engineering Contracts:
• ·....Lump sum contracts
• }~chedule of rates or unit-price contracts
ao ·'Cost plus conti·acts
Sounetimes, Part .Lump Sum arid Part Unit-Price Contract is aJso adopted in a. single J:Yroject as a
:burth type also. The Lump Sum and the Unit-Price Conttacts rnay be either ''fixed" or "stibject to
::ost adj~1stment" as specified in the contract.
"]I·
L tis type of contract is the one in which the contractor based on the available col'nplete set of plans
:m.J specifications quotes one single price which covers all works and services required by the
:ontract plans and specifications. The lump sum price includes all direct costs. ofthe contractor for
~bor, machines, materials and indirect costs such as field and front office snp·ervision, secretarial
s::::pp01i and equipment maintenance and support costs and also incltldes prcifit of the contractor.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
In unit price contracts, the progress payments for the contractors are based on precise measurerbent of
the field quantities placed.
A variation of the profit sharing approach is the sliding fee, which not m11y provides a bonus for
underrun but also penalizes the contractor for overrunning the target value. The amount of fee
Prepared By: Er. Subash K. Bhattarai(B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
For more Notes and Tutorials Visit www.masenzworld.com
Downloaded from www.masenzworld.com
. .
increases as the contractor falls below the target and decteases as he overruns the target valne. ·Ot1e
formula for calculating the contractor's fee based on slidingscaleis,
Fee="=R (2T-A)
Where; · ·. . · ·
--T~Targetprlce _______________ _ . ··- -· _;__~_· _____._: ___--;_ -·-· - -..-- ,.:..-"---·--·-----_..:...... ~.:..__ -:-.:...:..._....:.. -· --~ ·-.- -·----- ·....,.-=:-- _,__--=:- --~.:..... _.:. . : _.___;._~---'--~--::...:~:..:..:.:._._____ -·
R=Base percent value
A=Actual cost ofthe construction.
Contracting for construction services is an inherently risky venture for the owner, desigl'1 agent and
contractor. All of these parties are exposed to tmanticipated risks, exposure to economic loss and
unforeseen contract liability while performing under the contract . Riskresponsibility plays an
important role in the development of contract dispt'ij,es that arise duting the construction process.
Though the risk of doing business cani1ot be eliminated, proper risk management can le~d to a
smoother operation and ultimately reduce the total cost of the project for the owner, designer and
contractor alike. Likewise, improper risk allocation can result in increased bid contingencies, higher
projects costs, poor working relationships, a higher probability of disputes and the increased ris...\: of
judici~}intervention between the parties. This chapter concentrates on the developrnem, :illocatiion
and ni.ii'nagement of risk· as it effects the construction process.
Whrtt is claim?
ln sin1ple contractual terms it is a tequest for reimbursement of cost and I or time from one pany to
anothe{:
. .:;·::.
A forinal contract procedure 'L1sed to review contract disputes between the contracting panY:es. Tne
claim process is ideaitified in the contract provisions which describes the steps to be taken to prmesr
an initial decision oVer the merits of a change order proposal.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
Claiin docunieizt
It contains four basic features
• The narrative: records relevant events, both cause and effects
• The entitlement: demonstrates the contractual or legal entitlement to compensation
• The argument or discussion: linking cause to effect, event to entitlen1eilt
• Quantum: quantity reimbursement or ti e being claimed
Note: either party should notifY the claim ithin. the 28 days form the event occtirred for
compensation with the documents stated above · s per PP A/ PPR
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 5.0
· Earth \vorkin excavation is basic task in any civil engineering projects~ Excavation may be in the
. surface· of ground or below the surface of ground: Excavation is done for foundation ?r fat
collection and production of consttuction matei'ials. Following arethe eon1Iiloi1ly used exca\rating
equipni_ent in the construction works:
a. Ex~:avator
It has ~l'nall hoe in its back. Hoe is teeth attached bucket. It is capable of excavating to a depth.
Excavation is done by teeth attached to a bucket, which is also capable o:f loadingthe excavated ·
material directly to the transporting vehicle. By changing the bucket it can be converted to driller,
power shovel etc. Excavators are classified on.,;the digging motion. An t1pwai'd tnotion u11it is
known as shovel and downward motion is Hoe.
b. Dozers
Dozer is versatile mechanical instrument for scraping and the excavating in both firm i.u1d hard
soil. It can work in worst condition of site like water logged as well as loose soil where other
equipment cam1ot run. It can push the excavated material to the other place with its blade. The
dozer with pneumatic wheel is more suitable in case ofnormal site condition, a11d for movemeJit
oflong distance, rather crawler mounted.
c. Power Shove]/ Loaders
It has a square tilting bucket on the end of themoveable a.nns t' lift and move material around.
The loader assembly may be a removable attaclm1ent or permane tly mounted mi. the vehicle. The
bucket can be removed or changed with other devices foi· the o her purpose of work. These are
also called loader because they are used to excavate earth atid load into a tl"i.1ck or on to a conveyer
belt. They may be either crawler mounted or pi1euinatic wheel mot.mted.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Ch'apter 6.0
Loader Excavator'
--<fit
e. Drag Lines
The drag line is a multipurpose machine capable in wide range ofopen:ttions. n. works on soft to .
medium hard material. It has a long light crane boom with buckets sb that it candig and dump.the ·
excavated materials over long distances eliminating the need of battling equipment. It cai1 har1dle
digging wet material or tmder water digging standing on the finn soil £·om the pit. Generally, the
draglines are of three ki11ds track mounted, wheel mounted, truck mounted and walking draglines.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 6.0
pipeline, cable trenches and· sewer ditches, where the soil ai1d job conditi011 perrriits. U swilly they
are crawler mounted which increase their stability and distribute its weight over a greater atea.
h. Scrappers
.The_;Lare-the..machines- capable-of-cutting...thin Ja.y:er .of earth- and- taki1:.tg -Som€-eX:Gavated-ma:.teria-1-~- --·-
in its bowl to be discharged in depressions uniformly. They can cut, haul arid d.ischarge m~terl.als
by themselves. Scrapper can be self.:propelled or tractor pulled type~ Self-propelled can be chiwler
mounted type or rubber tire ri1omited. These are not suitable in such location where the cutting
blade cannot work, like gravely and rocky strata.
i. Graders
Graders are basically the equipment meant to grade the road surface and other large area. With the
help of teeth attached to them, they can scarify earth surface to loosen the material which can
eventually be shifted forward or to the sides by grading blades. These blades rotate up to 270° in
the ceritral ring making it unique to shift the material 011 all sides. The self-propelled grader are
also known as motor grader and can be Classified in four different types a) Light Grader -up to 9
'ions b) Medium Grader- 10-12 tons and c) heavy grader 13-15 tons and D) Very Heavy Grader
17-24 tons.
Grader
j. Power Jack Hammers and PneumatiC Drills
Powe.r Jack Hammer ....
These are the equipment used to drill holes :in the hard rock arid are used to excavate hard rock by
drilling and blasting method. Engine to drive the .drilling bit is mounted ovet the jack Hammel'.
These types of jack hammer are very use:fi.ll fo:r the openit1g track in mou11taino1Js road whe11larger
equipment like air compressor cannot be taken to site to r'un types of drilling bids.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 6.0
drilling machine can be driven With the help of o·ne compressor. ·.·Compressor used in t11e
construction project is relatively small, simple and. strong enough sO that they need minimum
maintenance. Some other uses ofcompressor are:
• Drill hole in rock for blasting and clearing.
---
~ ~- --.- -euttingliiateriaJ·s-wttlrthe~netrforpfieumatic- circular saws ol.·-chairiS.----
~-- -----~----- - - - -----
~
e) Belt Conveyor
Belt conveyor are generally of fixed type, Belt conveyor are loaded with the help ofloaders. ·It is
used in gravel and sand quarries.
-- ~--:1)-Rue-ket"e-o-nv.e-y:et:s- ---------- --'- -,--~--c- ,.,.."'-~--:--- --·---'---·-"'"-'-~-_c.- --'--:-~•:.c-"~.:.·-c--- -"--'-.- ---'~----~-'--~--~--
. '
They are commonly used to trarispmi earth in vertical dii·ection. Bucket conveyors are efficient .
means of transporting loose materials vertically. Loading is done n1anually or mechanically and
emptying is done automatically.
g) Ropeways
Ropeways are used when matel'ial to be transp01ied is :fiotn a fixed location to a fixed location.
Rope way buckets are loaded manually 01~ by i11achine. This is more often used in quarrying
operation.
Equipment for Compaction
Emih compaction is done to remove the air entrapped in the soil mid making it denser to acquire
required strength. The equipment use to remove the air fi:om the soil is called compacting
equipme1it. Rollers are used for earth compaction.
a. Smooth wheel roller
·"(
:° Foi tl{~:'compaction of cohesive soils, sinooth wheel rollers are commonly us~d. It consist dfthree
'.":
c. Grid roller
The working principle of grid roller is same ofthatsheep footed. Th~ drum ofthis roller is covered
by steel chain grids which gives more pressute on the surface to be c' ffip~ded. These compactoi-s
are used on granular materials when size ofthe grain is relatively lat er.
d. Vibrating Rollers
Ordinary vibrating rollers are single drum type steel wheel. It is suitable for granular soil.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 6.0
- . ~ .
A Manual on Construction Project Management {PurbanchalUniversity) 2014
. .
6.2 Aggregate handling and concrete construction Equipment
Equipment for Aggrega e Handling
Screening Plants
Screening is necessary i order to separate the aggregates by size. Scree11ing plants are seH~cted
depending upon the speci 1cation of aggregates that are required fot the work. The following two
types of screens are generally in t1se.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) /Chapter 6.0
Revolving Screens
Revolving screens are the most conunon types of screens used to wash imd screen sand and gravel.
The maintenance and repair costs are low as compa.redto other type of screens. Streams ofwater.
may be sprayed on the aggregates as it ~~y~_s_t~o-~lgh_t]~~~~~~~Q:._ ~_g~E·~ge!_:t~~§:~~ ~~-aJ?!~d_l;>y~i_ze _ ,..-- __ _
---and store(:fteidpo-rai:ny-irt-bills-b~lo~~the screen. . . . . . ..
Vibrating- Screens
It is the most widely used screens fot aggregate production for their efficiency and capacity to
handle large amount of materials. These plants come under multiple deck type. Screens are
installed one above another. Each screen is called deck. A vibrating mechanism is filled to the steel
frame whichholds the screens; Therefore all the screeiis Vibrate siniultan:eously;
Crushing Plants
A crusher is a machine designed to break and rednl'!e large rocks.into aggregates, gravel, or rock
dust. Crushers may be used to rednce the size, or change the foni1, c:if'waste materials so that they
can be more easily disposed of or recycled, or to reduce the size of a solid mix ofraw materials
(as in rock ore), so that pieces of diffetent composition can be differentiated. The stone chips-
aggregates are the most important ingredients of concrete constmi::tion of buildings, dams,
·irrigati$n structures bridges, water stipply projects and similar civil engineering constmctio~
: constr~d~tion of road and highways airports and rail road. The product :fi:om the crusher is taken to
.screeni11g plant to separate various sizes of aggregates. The range of the sizes depends upon me
need specific project.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 6. 0
b) Gyratory Crushers
The crusher unit consists of a heavy cast iron or steel :fi·ame with an eccentric shaft and driving
gear in the lower part ofthe unit.
c) Cone Crushers
These crushers are used as secondary or tertiary crushers. They are capable of producing large
quantities of uniformly fine crushed stone aggregates.
d) Roll crushers
It can 1Je used as tertiary crushers to produce additional reductions in the size of stone after the
output'bf a quarry has been subject to one or more stages of prior crushitig.
e) Imf}act Crushers
Impact crushers involve the use of impact rather than pressure to crush materiaL The material is
contai1ied within a cage, with openings of the desired size to allow rnHvetized material to escape.
Hani1TI¢i mills can a type of impact crusher. R.od mill is used to produce sand from cru_shed
aggregcites. If steel balls are used to give impaCt in place of rod theri it is named as ,ball milL
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 6.0
Batching is generally done by weight. For small construction simple weighing scale are comrnonly
used whereas for larger concrete construCtion, automatic batching plant are:used. Water and liquid
admixtures are generally measi1red by volume and other in:gredients by weight. The batching plarits
are available in 3 clitego:ries.
-- --- --.--·Manuai------- ---- ----·------- ---------------------------- - - - - - - --- -- - - ---
~ -~-- ·--··-·---·-·-~----
• 'Semiautomatic and
• Fully automatic.
The ob}ective of mixil)g of concrete is to coat the surface of all aggregates particles with cement
paste. J\,Jixing allows the blend all ingredients of concrete into a uniform mass. Small quantity of
concrete at micro level are mixed by hand which is termed as hand mixing. For good quality of
works ~~t macro level mixing are done tbJough mixing plant. Batch mixers and continuous mixers
are t\~li. types of readily available mixers for concrete mixing. Batch l'nixers can be further
classifi~d. as:
Transit mixers are mounted in a tntck These mixers is feed with aggregates arid cement fi'Ofu a
hatching. plant and add water to mix coilcl'ete. The drum: c'>f these Ii::iixets revolve 70 - 100
revolutions for complete mixing of concrete.
Concrete ate transported throngh pumps in tmmel construction. The gtmiting and shortcreting are
specially done tln·ough pum:ps in high pressure.
g) Builders Hoist
Now a days at multistory building sites up to 150m hoists are tised totra.n:spmi the cm1ctete,
h) Cranes
Cranes a:re commonly used to transfer concrete fi·om mixer or a place of delivery to the for1Il wodc
where it has to be laid. It is very suitable transferring system as it can take concrete to the right
location where it is required.
Concrete Compaction Equipment
Concrete mixes are heterogeneous mixtnre of cement, aggtegates an water m a stiff state
containing large voids and entrapped air. Consolidation can be catried ot' thi'ough compactio1'1 to
remove air voids. Compaction is achieved by the use ofmechanicalvibta.tio11s.
a) Internal Vibrators
Prepared By: Er. Subash K Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 6.0
An internal vibrators are also called needle vibrator. It consist ofthree parts. Power unit, flexible
tube and vibratory head. They are introduced into the fresh concrete to vibrate and give compacting
effect to the concrete. Power is given to vibrator either by patrol engine or electricity input. Flexible
rubber tube connects wer connecting device and the vibrating needle. Vibrating head is a straig t
iron tube having ec · weight fitted inside it.
b) Plate Vibrators
-
They are used to compact concrete with lesser thickness. This vibrators falls under the category of
surface vibrator. It is extensively used in slab construction.
c) Vibrating Screed
Vibrati!1g screed are also the type of surface vibrators capable of compacting large section of
concrete surface giving i1eat shape to the concrete. They are used in finishing bridge decks and
also concrete pavement of roads, aprons and parking area.
d) Form Vibrator
These vibrators are external vibrators and are attached to the outside of the concrete formwork.
They vibtate formwork and in turn formwork vibrates the concrete. These are used in compaction
ofprecast concrete.
c) Concrete Rollers
Large static rollers are also used for compacting Plum concrete construction with greater thickness
of concrete layer. Generally used in compaction of Dams.
Equipment for Finishing of Concrete
After compaction of concrete, the concrete surface is finished by trawling, floating or by belts.
Most ofthe concrete surface is finished by hand trowels for smaller surface area but power trowels
are used for larger area. Similarly power floats are used to level area of concrete to a accurate level.
Power are given by electric motors.
6.3_Equipm~nJ for CoosJn1~JionofPipes~mdC~iss_ons
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 6.0
It is the only single machine capable of providing three dimensional movements to a load virtually
in one continuous operation. It is able to perform the operations with speed, safety and precision.
It is necessary to know the lifting capacity and working range of a crane to be selected to perform
a giv njob.
Clas ification of cranes
Broa ly cranes are classified into four categories
a) Stationary crane: It is also called derrick crane. These cranes give ~n e eptionally large
working radius and can be designed to give any lifting capacity. They may be steam,
electric or diesel driven. The derrick cranes may be used on a wide ra1ige of works, from
large civil works to industrial building construction, erection of plants, handling timber,
hoisting works at ship yards, loading and un-loading cargos at ports etc. It consist of:
• AbMast
" ABoom
• A bull wheel
• Guys
b) Over head or gantry crane: These cranes are used for handling loads over a long rectangular
area such as in factories and workshops to move machines and other loads in any directions.
These cranes consist of a hoisting mechanism mounted on carriage or crab capable
travelling laterally across a girder which spans. The girder resisting on wheels travels
longitudinally on rails on an overhead gantry.
c) Mobile crane: These Cranes are mounted on mobile units. Truck cranes have high mobility,
whereas crawler mounted cranes move slowly. Classification of mobile cranes are as
follows:
• Crawler
• Telescopic boom truck mounted cranes
• Lattice boom truck mounted cranes
• Rough terrain cranes
• All terrain cranes
" Heavy lift cranes
d) Tower crane: Usuallythis crane is used in the consttuction of industrial and multi-storied
residential buildings. These cranes provide high lifting a11d good working radius. Theytake
up limited space around the work site. These are generally of fixed base type motu1ted on
a foundation block. Structural sections can be added to increase the height of the crane.
There is a vertical limit called "maximum fi·ee-standing" height to which these cranes can
sately rise above the base. A self-erecting tower to grater vertical heights is fairly easy and
economical. A self- erecting crane has a short section of hydraulically operated erecting
tower that is situated below the slewing ring for this purpose. It is also used in assembling
.of high industrial-pla-Rts- -with--elernents of steel structure including loading and unloading
works. The principal components of tower crane are:
• Under carriage
• Slewing platform
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 6.0
-
Tower crane
6.5 Equipment for Tunnel Construction
Basically there are two methods of tmmel construction. The first one is conventional method and
another is construction using tunnel boring machine.
Conventional method of tunnel construction
The excavation of tunnel by drilling and blasting method 1s the traditional method of tunnel
construction. Excavation by manual operation or using excavating equipment is done for the soft
soil. For rocks drilling and blasting method for excavation is adopted. The process oftaking out
the excavated materials or blasted materials from the tmmel is known as mucking. It is done
manually in wheel barrows for small section of tunnel whereas for the larger diameter tunnel
tippers and loaders are operated inside. Railway wagons are also used for mucking operation.
Excavated material is taken out as the excavation progress. Tunnel ventilation is needed when
. excavation is in sufficient depth. Ventilation arrangements are done through exhaust pipes.
Exhaust pipes consist of two numbers one pulls foul air fi·om inside and another push fi·esh air
inside. Power is supplied into the tmmel to provide light as well as to run equipment like exhaust
fans.
Conventional tunnel construction process uses the following equipment:
• ... Excavators f61; s6rfgt:6\.md
• Drilling machine
• Compressors to run drilling heads
• Earth transpmiing equipment for mucking or clearing the excavated material
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 6.0
Tunneling by TBM
Modern tunnels constructions are done ith the tunnel boring machines. These are the machines
which have programmed boring head or · oles which drill mountain to bore tmmel through them.
The muck is taken out tlu·ough a pipe att ched to the boring machine. This method oftmmeling is
very fast and efficient. These machines a every costly. The length of the tmmel can justifY the use
of TBM's they are economical. TBM's are available of different capacity and size. Once
programmed before operating, these machines can progress in the fixed co-ordinates in all the X,
Y and Z direction.
Prepared By: Er. Subash K Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 6.0
b) Bitumen distributor
They load preheated bitumen fi:om bitumen boilers. Bitumen distributor is truck which consist of
tank. These machines come with burners fi·ied by organic fi.tel, generally diesel or crude oil to
control the temperature during transportation. These burners heat the bitumen to required
temperature before spraying. The distributors have bitumen spraying attachment which sprays
bitumen in fan shapes through nozzles.
c) Aggtcgate Spreadet·
Aggregate Spreader is use for surface dressing work. Aggregates are spread uniformly in layer
covering the bitumen sprayed. A dump truck with spreading attaclm1ent is fixed on the tail which
spread aggregate in uniform manner.
d) Asphalt Distributor
Asphalt distributors are used to apply prime or tack coats on a surface in preparation for paving.
They are available in either truck mounted or trailer models and are considered the most important
piece of equipment on any asphalt surface treatment project. It consists of an insulated tank with a
heating system, a spray bar and unique control system
d) Asphalt Concrete Plant
To make asphalt concrete pavei11ents asphalt concrete is used. Asphalt concrete is the mix of
bituminous binder and different types of graded aggregates. For patch works asphalt concrete is
batched and mixed manually. However for large jobs and quality of work it is done in a hatching
and mixing plant called asphalt concrete plant.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Clwpter 6.0
f) Rollers
Compaction of aggregates are done by rollers. Generally, pneumatic roller is used to ensure that
aggregates are not broken and remain intact.
f) Water truck
Selection of Construction Plant basically involves planning the equipment, careful selection
considerations and the basis for selection. The selection process may vary fl-om company to
coni.panyand within the company fi:om project to project. Equipment selection plays an important
role in execution of any construction project, since proper selection of equipment contributes to
the completion of the project timely; economically; and of desired quality standards. Basically
there are two principal aspects of equipment.,. selection they are:
..
After the selection is carried out purely from a technical point of view, it is necessary to test the
viability of the selection fiom an economic or business point of view also. Planning for Equipment
Selection involves working out to get the answer to the following questions
a) What for is the equipment needed?
b) When is the equipment needed and for how long? (The duration of equipment use)
G)... .. How big e.quipment is need.ed? (The capacity assessment)-
d) Which one is preferred based upon the history of performance ofthe equipment?
At the planning stage it is necessary to take concrete decisions on the method of achieving the
ultimate target by utilizing resources (Men, Machinery, and Material & Money) in the best possible
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) /Chapter 6.0
.. :.
For more Notes and Tutorials Visit www.masenzworld.com
Downloaded from www.masenzworld.com
way. This may be done in the pre tender stage by the contractors by studying the contract
documents, plans and the local conditions. Depending on the type of the project the contractor may
be required to survey the following:
" Geological conditions:
.. Weather conditions:
• Site conditions:
• Transport facilities
• Availability of Fuel
• Availability of Labor
• Availability of services (Electricity, Water)
• Pollution Standards
Apart Jiom the above general and broad principal considerations, there are several other tactors
that influence selection of equipment
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 6.0
B. Site Constraints
• Accessibility to location.
• Maneuverability at site.
• Working space restrictions.
• Altitude and weather conditi · ns.
• Working season and workin hours.
• Availability of local resourc s of manpower, materials and equipment.
• Availability ofland, power s 1pply and water supply for workshop and camp.
• Availability of local equipment hiring, repair and maintenance facilities locally.
• Availability of fl!el, oil and lubricants.
C. Equipment Suitability
• Type of equipment considered suitable for the task.
• Make models and sizes of special purpose and general purpose equipment available, which
can handle the task.
• Production capability, service conditions and delivery time of each equipment available.
• Equipment already owned by the contractor.
• Usefulness ofthe equipment available for other and future tasks.
D. Operating Reliability
• Manufacturer's reputation.
"' Equipment components, engine transmission, brakes, steering operator's cabin.
• Use of standard components.
o Warranties and guarantees.
• Vendor's after sales service.
• Operator's acceptability, adaptability and training requirements.
• Structural design.
• Preventive maintenance program.
• Safety features. ...,.
• Availability of :fhel, oil and lubricants.
E. Maintenance
.. Ease of repair and maintenance.
• Vendor's after sales service, repairs, spares and maintenance.
• Availability of spare parts.
• Standardization consideration.
F. Economic Considerations
• Owning costs.
• . Operatiug£Q;>t_$,
.. Resale or residual value after use.
• Replacement costs of existing equipment.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 6.0
.. ·
For more Notes and Tutorials Visit www.masenzworld.com
Downloaded from www.masenzworld.com
G. Commercial Considuations
• Buy second-hand or new equipment.
• Rent equipment.
• Hire- rchase equipment.
• Purch se or lease.
Eqt:ipment se ection analysis is not necessarily limited to the above. It leads to alternativ choices
for acquiring the required equipment. It is followed up with the management decidi1 g on the
required equi ment. It may be noted that, in most cases, the final equipment selection d cision is
likely to be ~ compromise between what is ideally required and what can actually be obtained
economically.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) Cflapter 6.0
J
Performance is referred to as being about doing the work, as well s beingabout the results
achieved. It can be defined as the outcomes of work becausethey pro vi e the strongest linkage to
the strategic goals of an organization,customer satisfaction and econom c contributions.
Introduction
Throughout the last two decades a number of industries, primarily manufacturing,have
introduced new methods and techniques to shift traditional paradigms in order toimprove their
performance. This has led to the creation of new philosophies such asconcurrent
engineering/construction, lean production/construction and many otherssuch as JIT, TQM, and
TPM etc. The main driver behind those philosophies is to optimize an organization's
performance both internally and externally within its respectivemarketplace. Therefore,
performance measurement is the process of "determining howsuccessful organizations or
individuals have been in attaining their objectives [andstrategies]". To achieve this, the outputs
of organizational strategicand operational processes are measured, in a quantifiable form, to
monitor the vitalsigns of an organization.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I CIL(Ipter 7.0
current pe1jormance. In effect, theyare reporting on the organization's past performance rather
its current pe1jormance.
Asimplistic analogy to illustrate this point can be drawnfrom the field a,[ sports, and inparticular
football, where knowing the result of a match offi rs you an indication ofhow the team pe1jorrned
but it does little to suggest future improvement~ identifymistakes and wrong strategies, assess
individual pe1jormance or identify weaknesses.! . any case the match was either lost or won.
Hovvever, during the 1990s there has been some interest in 'emerging' techniques and
philosophies such as total quality management (TQM), benchmarking, businessprocess re-
engineering (BPR) and business process management that have shifted thefocus fl·om 'lagging'
towards 'leading' indicators of performance. The majority ofthose concepts have been imported
to construction from the manufacturing industry.
The construction industry often acts as a catalyst to stimulate the growth of a nation's economy.
The industry is often referred to as an engine of growth. However, numerous govenm1ent reports
have criticized the industry's poor performance, especially in terms of productivity, quality and
quality systems. In order to improve performance, many construction companies implement the
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 7.0
... ·
For more Notes and Tutorials Visit www.masenzworld.com
Downloaded from www.masenzworld.com
A Reading Manual on Construction Project Management (Purbanchal University) 2014
ISO 9000 series, an integrated system to ensure consistency and better performance of
construction projects. This is achieved by creating a framework for continuous improvement and
by providing the necessary criteria to guide construction firms setting up and maintaining quality
system in the organizations.
The construction industry has numerous problems to deliver quality construction projects
because it comprises of a multit de of professions, occupations and organizations. The quality of
service delivered by consultants has often been a subject of thorough investigations. Some clients
have underestimated the impa: ts of substandard consultancy service to the success of a
construction project. Many delays, cost overruns, reworks, variations, claims and disputes can be
traced back to erroneous design, poor contract administration or lax supervision of the client's
representative. Furthermore, the production processes of construction projects are generally non-
standardized; hence, it is difficult to ensure quality. Therefore, some local building authorities
seek to alleviate the quality problem by making certification to ISO 9000 mandatory for all
contractors who are tendering for public sector projects.
Errors induced by a system can be prevented or at least minimized through the implementation
of a quality management system (QMS). Among various QMSs, ISO 9000 certification has been
widely adopted by the construction industry in many countries. For instance, in Hong Kong all
consultants must have a certified ISO 9000-based QMS before they can bid for public
construction projects. With the release of ISO 9000:2000, an unprecedented emphasis is placed
on customer satisfaction and continual improvement. 'Satisfaction' can be measured by
comparing the difference between what is expected and actually received, and clients would
satisfy with the performance of a consultant when the quality of service provided exceeds or at
least meets their expectations. Continual improvement can only be realized if consultants are
aware of their weaknesses or deficiencies and make corresponding adjustments to satisfy the
expectations oftheir clients.
ISO 9000-based QMSs have been repotied to be able to improve the service quality ofthe firm.
This will subsequently increase the clients' satisfaction, market share, revenue as well as
workers' morale. However, to what extent International Organization for Standardization (ISO)-
certified contractors could satisfY clients' needs in construction projects are still inconclusive.
There are still a lot ofcomplaints reported r~lating to the quality of delivery.
B S 5750 (1987) defines quality as 'The totality of features and characteristics of a product or
service that bear on its ability to satisfY stated or implied needs'.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) [Chapter 7.0
definitions imply that the needs of the customer must be identified first because satisfaction of
those needs is the 'bottom line' of achieving quality.
As quality became a major focus of business throughout the world, various organizations started
to practice standards and guidelines. This sees the introduction of the ISO 9000 series in 1987,
which has since become a worldwide quality management norm for organizations, regardless of
their sizes and products. The ISO 9000, originated Jiom the military procurement standards in
the Second World War, is a series of guidelines for companies that establish their quality systems
by focusing on procedures, control and documentation. ISO 9000 standards are supposed to help
---
companies identify mistakes, streamline their operations and be able to guarantee a consistent
level of quality. The standard also drew the attention of quality professionals worldwide. Owing
to its original intent to create a two-pmiy, non-binding standard, it penetrated barriers of culture
and language, which no other quality standard could achieve. Therefore, it became a non-
political baseline for quality, accepted internationally as quality management framework and an
excellent marketing tool for entering the global market. It gradually spread fi:om Europe to North
Ameri;::a, Japan and the rest of the world.
The ISO 9000 series for the revision of year 2000 consist of the following:
The ISO 9000 series concentrate on the fiye key areas of quality-management systems, that is,
management responsibility, resource management, product or service realization, measurement,
analysis and improvement
It is widely accepted view that, at 2. rr;rJ:i:r.Jc""E performance measures of a project are based on
time cost· and quality noted tillit thcs.~ Ik.::.: .;:,;::;mpvnents of project performance -as the -'iron - -·
triangle'. However some conside;:-ed. "•:::i-?::::::• .::ri:eria in measuring a project. This includes
meeting budget, schedule, and r.he c.. ::J2~i:y ''':err~::aaship, stakeholder's satisfaction, transfer of
technology, and health and safety. Si.'11It~b-. other key components also used in measurmg
Prepared By: Er. Subash K. Bbattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 7.0
Basically, six variables have been identified for measuring proje performance. They are cost,
time, quality, clients' satisfaction, health and safety and functional" y.
Cost pe1jormance
Cost is defined as the degree to which the general conditions prom te the completion of a project
within the estimated budget. Cost variance was the most comm n technique used to measure
design performance. It is not only confined to the tender sum, but the overall cost that a project
incurs fi:om inception to completion, which includes any costs arise :fi:om variations, modification
during construction period and the cost arising :fi:om the legal claims, such as litigation and
arbitration. It can be measured in terms of unit cost, percentage of net variation over final cost.
Cost variance is a very important factor in measuring project performance because it indicates
how much the project is over or under budget.
Time pe1jormance
It is very important for construction projects to be completed on time, as the clients, users,
stakeholders and the general public usually looks at project success :fi:om the macro view where
their first criterion for project success appeared to be the completion time. The time variance is
one of the teclmiques. for assessing project performance in construction projects. The element of
time could indicate to project managers that the project was not running as smoothly as
scheduh~d. Furthermore, timely delivery of projects is one of the important needs of clients of the
construction industry. Construction time can be regarded as the elapsed period fi·om the
commencement of site works to the completion and handover of a building (facility) to the client.
The construction time of a building is usually specified before the conm1encement of
construction. Construction time can also be deduced :fi·om the client's brief or derived by the
construction planner :fi·om available project information.
Qita!ity pe1jormance
In the construction industry, quality is defined as the totality of features required by a product or
services to satisfy a given heed, or fitness for purpose. In other words, the emphasis of quality in
construction industry is on the ability to cooform to established requirenlents. Requirements are
the established characteristics of a product, process or service as specified in the contractual
agreement and a characteristic is any specification or property that defines the nature of those
products, processes or services, which are determined initially by the client. In order to achieve a
completed project that meets the owner's quality expectations, all parties to a project must
acquire an understanding of those expectations, incorporate them into the contract price and
other contract documents to the extent possible, and commit in good faith to carry them out
Clients' satisfaction
Satisfaction is regarded as a function of comparison between an individual's perception of an
outcome and its expectation for that outcome. In the construction industry, client's satisfaction
)19:s l'~lll?:!I~e<:I _(lJ~- ~l~rsiy~ _(ltlci_ch?-Jlel1ging iss_L!yJQL sOJIJ,e con~idecahle time. Dissatisfaction is __
widely experienced by clients ofthe construction sector and may be caused by many aspects but
is largely attributable to overrunning project costs, delayed completion, inferior quality and
incompetent service providers including contractors and consultants. Research findings have
suggested that it is five times more expensive to develop a new construction client than to
maintain an existing one and companies could increase their profits by almost 100 per cent by
Prepared By: Er. Subash K. Bhattarai (B.E Ci~i! I P_GDESD I MPA I MSc CM) I C!wpter 7.0
retaining just 5 per cent more of their clients. Client's satisfaction is therefore a fundamental
issue for construction participants who must constantly seek to improve their performance if they
are to survive in the global marketplace. In the construction industry, the measurement of client's
satisfaction is often associated with perfo mance and quality assessment in the context of
products or services received by the eli nt. Usually the client's requirements are to get
construction needs translated into a design tl at specifies characteristics, performance criteria and
conformance to specifications, besides to get the facilities built within cost and time.
Funcliunality
'Functionality' refers to one of the success measure that is made in the post construction phase
when tl1e project is finished and delivered to service. Opined that there vvould be no point in
undertaking a project if it does not fulfil its intended function at the end. This indicator correlates
with expectations of project participant and can best be measured by the degree of conformance
to all technical performance specifications. Both financial and technical aspects implemented to
teclmical specifications should be considered, achieving the fitness for
purpose objective. Specification is workmanship guidelines provided to contractors by clients or
clients' representatives at the commencement of project execution. The measure of technical
specification is to the extent that the technical requirements specified can be achieved. In
addition to that, consider meeting specifications as one success criterion for design-and-build
projects that is consistent with the measurement of technical performance, which is to be
measured in both the preconstruction and construction phases when the technical requirements
are laid down.
Pmject implementation in Nepal has remained poor. Most development projects have failed to
achieve the desired results. Time and cost overruns are corm11011. There are various reasons
behind the failure of the projects. Some of them are as listed below:
Prepared By: Er. Subash K. Bhattm-ai (B.E Civil I PGDESD I MPA I !VISe C!VI) I Chapter 7.0
a. Governmental Agencies: They prepare and compile various industry reports to judge the
overall economic health of the nation. Examples of these are reports by the Bureau of
Labor Statistics (BLS) and International Monetaty Fund (IMF).
b. R~~~~r~h.Fixms: These finns Qondu.ct market surveys and compile different industry
repotis and sell them to companies and government organizations. These reports are
purchased to facilitate decision marking. Standard & Poor's is one of the most popular
research firms.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Clwpte~· 7.0
An industry report contains graphs, charts and tables, generally supported by written
commentary. This enables even non-professionals to get an understanding of!he industry
Hence, there is a great need in the construction industry for identifying a set of common
--. - -indioaters to se used by cons-truction exec-utive and project managers in meastu'ing constmcticnl
performance at the project level as a part of achieving business strategy to delive1y project on time,
on budget, fi·ee fi·om defects, efficient, right first time and safety. This set of key performance indicators
willmake objectives quantifiable, providing visibility into the performance of organizations and
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM).I Chapter 7.0
enabling decision makers to take action in achieving the desired outcomes. However, in general
here are 10 popular Business Performance Measurement tools that every construction sectors
should follow:
In time and well planning is essential for construction "1dustty. The construction projects
follows the complex life cycle, hence planning is one tool to measure its performance.
Construction planning possess, the planning of 5 M's (Manpower, machine, material,
money and minute). Similady, in time and proper allocation of the budget for every
activity is essentiaL
The BSC is another popular management tool that has been designed to articulate the
strategic objectives of a business and then align performance measures and action plans
to these strategic objectives to ensure the strategy gets executed.
The BSC proposes that compames develop objectives in the following interrelated
4111•·
perspectives:
• Financial
• Customer
• Internal processes
• Learning and growth (people, culture, IT)
4. Benchmarking
Benchmarking is the process of comparing one's business processes and performance
metrics to industry bests or best practices fi:om other companies. Dimensioqs typically
rneasuredare~_quality,.. time and cost. In the. process .. of best practice benchrnarking,
management identifies the best firms in their industry, or in another industry where
similar processes exist, and compares the results and processes of those studied (the
"targets") to one's own results and processes. In this way, they learn how well the targets
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Clwpter 7.0
.. :.
For more Notes and Tutorials Visit www.masenzworld.com
Downloaded from www.masenzworld.com
A Reading Manual on Construction Project Management (Purbanchal University)
perform and, more importantly, the business processes that explain why these firms are
successful. For example, banks might learn about customer service from Hotels and
hotels might learn from insuran e companies about optimizing back office processes
5. Business excellence Model
The business excellence mod ls come fi:om the quality movement and have been
developed by national bodies to assess quality standards in companies. There are various
national standards that are often used as the basis for quality awards.
In Europe, the most popular tool is the EFQM model, which refers to "outstanding
practices in managing the organization and achieving results, all based on a set of eight
fimdamental concepts."
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 7.0
The six sigma model can be adapted to a project environment. The six process involved in the sox
sigma model is as follows:
• Define: determination of the quality characteristics of the output from the project that are
critical to cus omers satisfaction
• Measm·e: de ermine what to measure, sources of information and data and data collection
plan
• Analyze: use of appropriate quality planning or quality control tools and techniques to
analyze the c Jlected data
• Impmve: based on performance and comparing with standards, modify or redesign existing
methods and implement the change
• Control: monitoring the change to assure the required performance level is satisfied or not
8. Performance Dashboards
Most organizations today are ·bursting with data, metrics, reports and analyses.
Dashboards provide single-page at-a-glance overviews of areas of performance (e.g.
corporate overview, sales, finance, HR, business units, etc.).They are designed to
effectively conmmnicate performance information using elements such as visuals,
graphs, traffic lights and text.
Good dashboards make it easy for the reader to understand the key messages so they can
concentrate on using the insights to make better-informed business decisions. Dashboards
should be as effective as good newspaper fi:ont pages in conununicating a story.
Most companies want to make sure they not only have satisfied customers but that they .
turn their customers into profitable and loyal customers.
-
CRM
.... --· -·
systems
····-·· --·- -- -··-
are. used
·-·-··· ----- --- --
~-- ··--
to manage --····
a company's interactions
. --- ----------·········· .. - ---- ...... ·-···· --- ----. ---- ...
and relationships
.... --- -------------·-. ---- -------· ........ .....
-----·
with
--
their
··-··--- ·--.
--··. -····-
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 7.0
to customer service or customer support.The simplest form of CRM is just tacking the
various levels of interactions.
Recently the UK best practice progranm1e has launched the 'key performance indicators' (I<Pis)
for construction. These KPis give information on the range of performance being achieved on all
construction activity and they comprise of:
a. Client satisfaction- product
b. Client satisfaction- service
c. Defects
d. Predictability - cost
e. Predictability- time
f. Profitability
a
v· Productivity
h. Safety
1. Construction cost
J. Construction time
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I CIJapter 7.0
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 7.0
Management is a key subsystem in the organization systems. It spans the entire organization and is the
vital force that links all other subsystems. Management is _the process of planning, organizing, directing,
coord iiwti ng and controlling of human resources, physical resources, financial resources and information
resources in order to achieve desired goals.
According to Marry Parker Fillet, "Management IS the art of getting things done with and through
people."
According to James L Lundy, "Management is principally the task of planning, coordinating, motivating
and controlling efforts of others towards a specific objective."
.r~
( ® ® 1
___
\~!]...../'
--........._ ,....
.. J<,,j::::!t \I[nrnnn)
• 1'-·fo(,:Jlin.,;':<-
• tv\t:il}llds
• krt.'int:::y
• Mnrb:tx
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 8.0
A profession
Multi-disciplinary in nature
Function of management
Management Functior ·
Organizing
For Knst and Rosenzweig organization implies structuring and interacting activities. i.e. people working
or cooperating together in interdependent relationships. They say an organization consists of:
~ Goal oriented arrangements (people with purpose)
. ~ Psychosocial systems (people interacting in groups)
~ Technological systems (people using knowledge and techniques)
~ An integration of structured activities (people working together in patterned relationships)
Characteristics
Common characteristics of organizations are:
· a) Social interaction: an organization consists of people. They interact with each other while in
work. This interaction leads to the devetOpment of a network of social relations in the work place.
b) Shared goals or purposes: organization has its own definite goals or purposes to attain. Without
shared goals, people rarely come together and establish definite pattern of interaction.
c) Coordination of efforts: the divided tasks performed by individuals need to be linked together to
keep the activities of each division goal focused. This is accomplished by coordination.
d) Hierarchy of authority: The jobs to be performed in an organization are arranged in a ladder Iike
hierarchy. The bases of this hierarchy construction are job responsibility and accountability, skill
demands of the job, and complexity of the job. A clear hierarchy of authority makes direction,
supervision and coordination easier and more effective.
e) Division of work: it means dividing large tasks into smaller packages of work to be handled by
one person.
f) Social control: organization maintains their control over the behavior of their members and
-regu-lates their activities. Tirey- make ·use of· vari-ons n.des, I10f'f11s a11d staiidatds to ensLil'e
acceptable conduct and behavi~r.
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I 1\tlSc CM) /Chapter 8.0
...
For more Notes and Tutorials Visit www.masenzworld.com
Downloaded from www.masenzworld.com
A manual On Construction Project Management (Purbanchal University)
Note: Broadly orgamzatwn ts dtvtded mto two groups. They are; formal and 111jormal orgamzal!0/1
Prepared By: Er. Subasb K. Bhattarai (B.E Civil/ PGDESD I MPA /MSc CM) I Chapter 8.0
. . .
management, which are universally acceptable and applicable in all types of organizations. Brief
descriptions of principles of management propounded by him are as follows:
1. Division ofwork.
This principle is the same as Adam Smith's division of labor. Specialization increases output by making
employees more efficient.
2. Authority
Managers must e able to give orders. Authority gives them this right. Along with authority, l owever
goes responsibili y. Whenever authority is exercised, responsibility arises.
3. Discipline
Employees must obey and respect the rules that govern the organization. Good discipline is the result of
effective leadership, a clear understanding between management and workers regarding the organization's
rules and the judicious use of penalties for infractions of the rules.
4. Unity of command
Every employee should receive orders from only superior
5. Unity of direction
Each group of organizational activities that have the same objective should be directed by one manager
using one plan
6. Subordination of individual interests to the general interests
The interests of any one employee or group of employees should not take precedence over the interests of
the organization as a whole.
7. Remuneration
Workers must paid a fair wage for their services
8. Centralization
Centralization refers to the degree to which subordinates are involved in decision making. Whether
decision making is centralized (to management) or decentralized (to subordinates) is a question of proper
proportion. The problem is to find the optimum degree of centralization for each situation.
9. Scalar chain
The line authority from top management to the lowest ranks represents the scalar chain. Communications
should follow this chain. However, if following chain creates delays, cross-communication can be
allowed if agreed to by all pmties and superiors are kept informed.
10. Order
People and materials should be in the right plac~.at the right time.
11. Equity
Managers should be kind and fair to their subordinates.
12. Stabi liLy of tenure ofpersonnel
High employee turnover is inefficient. Management should provide orderly personnel planning and
ensure that replacements are available to fill vacancies.
13. Initiative
Employees who are allowed to originate and carry out plans will exert higb levels of effort.
14. Spirit de crops
Promoting team spirit will build harmony and unity within the organization.
Prepared By: Er. Subash K. Bbattarai (B.E Civil I PGDESD I MPA I MS~ CM) I Chapter 8.0
Centralizati·:>·r:. -::;; :.rt:: :r;:c:::::s t>v which the actlvttles of an organization, particularly those regarding
planning, :Cr.::.:ome concentrated within a particular location and/or group. In political
science, this:-.::~.:::--~ 11::: :::<::- :.::::-:::<:emration of a government's power- both geographically and politically,
into a centrali:z.:-:2 ;:•;, :::::-:LT"c::. The implication of centralization can be:-
" Reserv.::.:3~-:~ :·:- :;;;::;:j:;..:;:: :naking power at top level.
• Rese;n.J.:';;: ::-, : f' :•;c::·.:.:~::; authority with the middle level managers.
• Resernrri~::: n ar lower level at the directions of the top level.
,.,.
Advantages of centr.:diz:aa:'it~m
• Facility fur ~crs.:or::::d ~::adership.
• Equitable disiri:Ccn:,:n of work.
• Unifonnitv of a.:::~·. ::i::s.
.. Specializatio:1.
" Economy .
., No duplication of ',\·.,x;.;:.
.. Quick decision.
• Greater flexibili"Y··
.. Standardization 2:nj training facilities enhanced.
"' Effective control.
t~ Fixing of respons!biiiiy is facilitated.
Disadvantages of centralization
• Delay in work.
• Bureaucracy.
• Distinctive to subordinates.
,. No loyalty.
• Lack of secrecy.
Decentralization
Decentralization is the process of dispersing decision-making governance closer to the people or citizen.
[t includes the dispersal of administration or governance in sectors or areas like engineering, management
science, political science, political economy, sociology and economics. Decentralization is also possible
in the dispersal of population and employment. Law , science and technological advancements lead to
hi.,ghly decentralized human endeavors.
Decentralization is a systematic delegation of authority at all levels of management and in all of the
. or~anization. In adesentmlization conc-ern, author-ity in reta-ined by the top mana:genrentfor taking major
de cis ions and framing policies concerning the whole concern. Rest of the authority may be delegated to
the middle level and lower level of management.
Tille degree of centralization and decentralization will depend upon the amount of authority delegated to
the lowest level. According to Allen, "Decentralization refers to the systematic effort to delegate to the
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) /Chapter 8.0
lowest level of authority except that which can be controlled and exercised at central points. There is a
saying that "Everything that increasing the role of subordinates is decentralization and that decreases the
role is centralization".
in a crisis)? i
Good way ()f trammg and developing JUlllor Harder to achieve tight financial control.- risk of I
management Should improve staff motivation cost-overruns 1
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 8.0
• Leadership is situation bound. There is no best style of leadership. It all depends upon tackling
with the situations.
Leadership is an important function of management which helps to maximize efficiency and to achieve
orgatiizational goals. The following points justify the importance of leadership in a concern.
• Initiates action- Lea er is a person who starts the work by communicating the policies and plans
to the subordinates fr m where the work actually starts.
• Motivation- A leadet proves to be playing an incentive role in the concern's working. He
motivates tl1e employ es with economic and non-economic rewards and thereby gets the work
from the subordinates.
• Providing guidance- A leader has to not only supervise but also play a guiding role for the
subordinates. Guidance here means instructing the subordinates the way they have to perform
their work effectively and efficiently.
• Creating confidence- Confidence is an important factor which can be achieved through
expressing the work efforts to the subordinates, explaining them clearly their role and giving
them guidelines to achieve the goals effectively. It is also important to hear the employees with
regards to their complaints and problems.
• Building morale- Morale denotes willing co-operation of the employees towards their work and
getting them into confidence and winning..,;their trust. A leader can be a morale booster by
achieving full co-operation so that they perform with best of their abilities as they work to
achieve goals.
• Builds wot·k envit·onment- Management is getting things done from people. An efficient work
environment helps in sound and stable growth. Therefore, human relations should be kept into
mind by a leader. He should have personal contacts with employees and should listen to their
problems and solve them. He should treat employees on humanitarian terms.
" Co-ordination- Co-ordination can be achieved through reconciling personal interests with
organizational goals. This synchronization can be achieved through proper and effective co-
~1rdination which should be primary motive of a leader.
Leadership Styles
All leaders do not possess same attitude or same perspective. Fe\v leaders adopt the carrot approach and a
few adopt the stick approach. Thus, all of the leaders do not get the things done in the same manner. Their
style varies. The leadership style varies with the kind of people the leader imeracts and deals with. A
perfect/standard leadership style is one which assists a leader in getting the besr our of~:he people who
follow him.
Some of the important leadership styles are as follows:
Autocratic leade•·ship style: In this style of leadership, a leader has complete cc·m:::;::n:Di aJU:d bcM C1ie-.r
their employees/team. The team cannot put forward their views even if they are best t';c~r n"::e Ef::lL'l:""JS '""
organizational interests. They cannot criticize or question the leader's way of gerring tllri::1gs d:=n;;e:.. Tdi!E:
leader himself gets the things done.
• The advantage of this style is that it leads to speedy decision-making and greater productivity
under leader's supervision.
• Drawbacks of this leadership style are that it leads to greater employee absenteeism and turnover.
This leadership style works only when the leader is the best in performing or when the job IS
monotonous, unskilled and routine in nature or where the project is short-term and risky.
The Laissez Fai1·e Leadership Style: Here, the leader totally trusts their employees/team to perform the
job thet:nse!ves. He just concentt:ates on the intel!ectua.l/rational aspect of his work and does not. focus. on
the management aspect of his work.
• The team/employees are welcomed to share their views and provide suggestions which are best
for organizational interests.
• This leadership style works only when the employees are ski lied, loyal, experienced and
intellectual.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc. CM) I Chapter
.
8.0
.
Democratic I Participative leade1·ship style: The leaders invite and encourage the team members to play
an important role in decision-making process, though the ultimate decision-making power rests with the
leader. The leader guides the employees on what to perform and how to perform, while the employees
communicate to the leader their experience and the suggestions if any.
• The dvantages of this leadership style are that it leads to satisfied, motivated and nore skilled
emp oyees. It leads to an optimistic work environment and also encourages creativity.
• Tbis leadership style has the only drawback that it is time-consuming.
Bureauct·ati leadet·ship: Here the leaders strictly adhere to the organizational rules and p licies. Also,
they make sure that the employees/team also strictly follows the rules and procedures. Promotions take
place on the basis of employees' ability to adhere to organizational rules.
• This leadership style gradually develops over time.
• This leadership style is more suitable when safe work conditions and quality are required. But this
leadership style discourages creativity and does not make employees self-contented.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) [Chapter 8.0
.. . . -
Effective Communication is significant for managers in the organizations so as to perform the basic
functions of management, i.e., Planning, Organizing, Leading and Controlling. Communication helps
managers to perform their jobs and responsibilities. Communication serves as a foundation for planning.
All the essential information must be communicated to the managers who in-turn must communicate the
plans so as to implement them. Organizing also requires effective communication with others about their
job task. Similarly leaders as managers must communicate effectively with their subordinates so as to
achieve the team goals. Controlling is not possible without written and oral communication.
Managers devote a great part of their time in communication. They generally devote approximately G
hours per day in communicating. They spend great time on face to face or telephonic communication with
their superiors, subordinates, colleagues, customers or suppliers. Managers also use Written
Communication in form of letters, reports or memos wherever oral communication is not feasible.
Thus, we can say that "effective communication is a building block of successful organizations". In
other words, communication acts as organizational blood
The importance of communication in an organization can be sm:nmarized as follows:
l. Communication promotes motivation by informing and clarifYing the employees about the task
to be done, the manner they are performing the task, and how to improve their performance if it is
-- - i1oti:q:J to the ,:;:;ad<. · ·- ·- - ·· - -- - · - · ·· · - -
2. Communication is a source of information to the organizational members for decision-making
process as it helps identifying and assessing alternative course of actions.
3. Communication also plays a crucial role in altering individual's attitudes, i.e., a well-informed
individual will have better attitude than a less-informed individual. Organizational magazines,
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 8.0
journals, meetings and various other forms of oral and written communication help in molding
employee's attitudes.
4. Communication also helps in socializing. In today's life the only presence of another individual
fosters communication. It is also said that one cannot survive without communication.
5. As discussed earlier, communication als assists in contt·olling process. It helps controlling
organizational member's behavior in var· us ways. There are various levels of hierarchy and
certain principles and guidelines that en ployees must follow in an organization. They must
comply with organizational policies, perfmm their job role efficiently and communicate any work
problem and grievance to their superiors. hus, communication helps in controlling function of
management.
b. Encoding: it is the process by which the message is tt'anslated from an idea or through into
transmittable symbols (e.g. sound, word, number, picture or gesture etc.)
c. Transmission: it is the process through'which the symbols that represent the message are sent to
the receiver. The medium is the channel or path of transmission. (E.g. mass media (like
newspaper, TV), talking, touching etc.)
d. Decoding: it is the process by which the rece1ver of the message interprets the message's
mean Ill g.
e. Receivet·: the receiver is the individual, group or organization that perceives the encoded symbols
and may or may not decode them and try to understand the intended message.
f. Feedback: it is the process in which the receiver returns a message to the sender that indicates
receipt of the message
g. . Noise: it as at1y disfLit:bal1ce iii-the coi11i11i:Ii1icatioii process that illlecfen~s-wlrli of' distbrts···
communication
Prepared
..
By: Er. Subash
. -K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM)
.
I Chapter 8.0
.
Barriers to communication
Follovving are the barriers to communication
I. Physical Barl"iers: The excessive hierarchy in an organization creates physical barriers. The formal
communication must go through certain prescribed channels of many layers by which there will be
possibility of distractions
2. Personnel Ban·iers: People involve emotionally and instead of decoding objectively. This loses
rationality and people become stereotyped by which one hears what he expects. Such a preconceive
notion may disturb the interpretation wrongly.
3. Material Barriers: Organization channeling of information introduces both physical and
individual barriers into material barriers. When information passes, people interpret differently by
which distortion creates.
4. Semantic Barders: Language complexity is one ofthe great hindrances. Communication is made
difficult due to tyranny of words. Words, phrases and idioms of the same language may differ from
country to country. Similarly meaning of words may vary from person to person depending upon
time and situation.
5. Outside Bm-riers: Overload to the receiver, credibility of the message and sender, communication
climate can prevail atmospheric effects to distortion.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chap~er 8.0
The type of information required by decision makers in an organization is directly related to:
Prepared By: Er. Subash K.. Bhattarai (B.E Civil I PGDESD I .MPA I MSc CM) I Cltapter 8.0
The levels of management decision making that must be supported by information technology in a
successful organization (independently of its size, shape, and participants), are often shown as a
managerial pyramid
u. monitor the strategic performance of the organization and its overall direction in the
Tactical management: Business unit managers and business professionals in self-directed teams
1. develop short- and medium-range plans, schedules, budgets and specify policies,
procedures, and business objectives for their sub-units of the company, and
11. Allocate resources and monitor the performance of their organizational sub-units,
including departments, divisions, process teams, project teams, and other workgroups.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 8.0
It. direct the use of resources and the performance of tasks according to procedures and
within budgets and schedules they establish for the teams and other workgroups of the
organization.
Decision makers need information products., hose characteristics, attributes or quality are having
Decision maker at different levels of the organization are making more or less structured decisions.
There are three vital roles that information systems can perform for a business enterprise: support of
business processes and operations, support of decision making by employees and managers, and support
Prepared By: Er. Subash K. Bbattarai (B.E Civil I PGDESD I MPA I MSc CM) / Chapter 8:0
The npplications of information systems that are implemented tn today's business world can be
Operations Support Systems (OSS) produce a variety of information products for internal and external
use, such as processing business transactions, controlling industrial processes, supporting enterprise
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I iVIPA I MSc CM) I Chapter 8.0
communications and collaborations, and updating corporate databases effectively. They do not emphasiz::
the specific information products that can best be used by managers. Further processing by manageme::
auHgement Suppot·t Systems (Support of Managerial Decision Making) is n ore specifically on li:::
p ocess of providing information and support for decision-making by different lev Is of responsibilities
tl e managers and business professionals. The management classifications of information systems can t·::
J11mwgement luforniation Systems (MIS): provide information in the form of reports and displays K
managers and many business professionals that support their day-to-day decision-making needs. Usualb
the· information has been specified in advance to adequately meet the expectations on operational and
tactical levels of the organization, where the decision making situations are more structured and better
defined.
Decision Support Systems (DSS) are computer-based information systems that provide interactive
information support to managers and business professionals during the decision-making process. DSS use
analytical models, specialized databases, a decision maker's own insights and judgments, and an
Executive b~formation Systems (EfS) or Executive Support Systems (ESS) are information systems that
combine many of the futures of MIS and DSS. Here the information is presented in forms tailored to the
preferences of the executives using the syste.u1, such as graphical user interface, customized to the
executives graphics displays, exception reporting, trend analysis, and abilities to 'drill-down' and retrieve
Specialized Processing Systems (PS) are information systems characterized as functional business
systems, strategic information systems, knowledge management systems, and expert systems.
Prepared By: Ec Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) j C!wpter 8.0
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Clwpter 8.0
Theories of Motivation
A. Content Theot·y of Motivation
• They are also called universalistic theories. They explain the dynamic of human needs, such as
why people have different needs at different times. By understanding an employees need we can
discover the condition that mo ·vate that person.
• [mportant theories in this cate ories are Maslow's need hierarchy theory, Herzberg's motivator-
hygiene theory, Alderfer's ER theory and McClelland's theory of learned needs etc.
B. Process theories of motivation
• These theories do not directly plain how needs emerge. They only describe the process through
which needs are translated into behavior. These theories help us understand, predict, and
influence employee performance, attendance, work satisfaction and other outcomes. Important
process theories of motivation are: ·equity theory, expectancy theory and reinforcement theory etc.
• Important theories in these categories are Equity theory of Stacy Adam, Expectancy theory of
Victor Vroom and Reinforcemerit theory ofB.F Skinner.
A. Content Theory of Motivation
I. Maslow's Need Hierat·chy TheOIJ'
Maslow's need priority model is one of the most popular theories of motivation. This theory is clinically
derived theory and is based on human needs. Theory believed that once a given level of need is satisfied,
it no longer serves to motivate human. Then, the next level of need emerges. According to Maslow, needs
exist in a hierarchy. Only when lower order needs are satisfied can huger order needs be activated and
serve as sources of motivation. It has classified human needs in five categories viz., biological needs,
need social needs, esteem and self-actualization needs.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 8.0
c. Social Needs
After satisfying lower needs prior to it, the social, love or belongingness needs become important
motivators of behavior. Human is social being. Hence is interested in conversation, sociability, exchange
of feelings and grievances, companionship, belongings etc.
d. Esteem I Ego needs
They are high r order needs, also called egoistic needs. They are concerned with prestige and s atus of the
person. Acco ding to Maslow they are of two types. First one is self-esteem which inc! des; self-
confidence, a hievement, competence, self-respect, independence and freedom whei·eas sec nc! one is
esteem tooth ·s which includes; status, recognition, attention and appreciation.
e. Selt:.actuali ation needs
The final step under this model is the need for self-fulfillment. It comprises self-fulfillment, achieving
ones potential personal growth. It is person's motivation to transform perception of self into reality. These
needs are unique in that once activated, they can never be fully satisfied. In short, it is "what a man CAN
be MUST be."
2. Het·zbet·g's Two- Factor the01-y
It is also called dual factor theory and motivation hygiene theory of work motivation. It is extended work
of Maslow and is specific content theory of Motivation. He conducted a widely reported motivational
study on about 200 accounts and engineers eJTl_J~oyed by firm and used critical incident method of
obtaining data by asking two question: when did you feel particularly good about your job -what turned
you on? And when did you feel exceptionally bad about your job- what turned you off? Finally he derived
this motivation theory. ft has classified human needs in two broad categories. They are
"' Extrinsidlzygiene.faciors (Factor 10)
o They are related to the conditions under which job is performed. They are associated with
negative feelings. They do not help to improve motivatiori. The feature of hygiene factors are:
they are related to job environment, they prevent dissatisfaction, they are zero level motivation,
they a!·e never satisfied and money is most hygiene factor. (E.g., company policy and
:tdministration: work conditions: salary, relationship with superior. peers and subordinates:
personal life: status: security: and supervision)
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 8.0
Prepared By: Er: Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 8.0
. . .
Training
It is the process of learning, a sequence of programmed behavior. In other words, training is learning
experience in that it seeks a relatively permanent change in an individual that will improve his or her
ability to perform on the job. It is application of knowledge. It gives people an a ware ness of the rules and
procedures to guide their behavior.
defeciency
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 8.0
Need of Training
Desired performance- Actual Performance= Training Need
Factors affecting major issues and challenges of training
• Lack of management Commi ment
• Less Attention and help from trade unions
• Lack of closer ties between o ganization and training institutes
• Nonexistence of vocational g idance and pre service training system
• Poor budgetary provision
• HR fishing and Poaching
• Traditional role of HR department
Methods of employee training
The forms and types of employee training methods are interrelated. It is difficu It to say which type of the
method or combination of methods is more useful than the other.
Traininu
b
method can be broadly classified as follows
T1·aining Methods
Prepared By: Er. Subash K. Bbattarai (B.E Civil/ PGDESD I MPA I MSc CM) Chapter 8.0
J
Labor relations have been defined by different experts/organization differently. Some of them are as
follows:
"Industrial relations are the complex of inter-relations mnong workers, managers and government. "
Unionization
A union is an organization of workers. The process of labor relations begins with the formal
establishment of labor union and its recognition by the employer. A union is ai1 organization of
workers, acting collectively, seeking to promote and protect its mutual interests through
collective bargaining.
Characteristics of union
The following are the characteristics of union
• Organization
-~· --- P·errn·anenoy
• Collectivity
• Mutual interests
• Collective bargaining
Prepared By: Er. Subash K Bbattarai (B.E Civil I PGDESD I MPA_I M~c CM) I Chapter 8.0
Unions are goal oriented. The reasons behind joining an individual to the union are as follows:
• Higher compensation
• Job security
• Better working conditions
• Influence work place
• Obtain political power
Process of unionization
1. Legal basis
2. Organizing drive
3. registration
4. Election
5. recognition
Collective bargaining
Collective bargaining is an important function of union. It refers to negotiation, administration
and interpretation of time-bound written agreement between two parties. It is collective because
the union represents the workers as a bargaining agent, whereas employer associations or
managers represents employers.
The collective bargaining has two aspects one is it defines employer-employee relations on the
job through a collective agreement where as another is it interprets and administers the collective
agreement.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 8.0
Labor disputes
Labor disputes are differences, conflicts or strife between workers and the employers. It can be
individual disputes or collective disputes. They are related to rights and interests of workers.
Disputes can be between employers and workers, between employers and employers, between
workers and workers and between employers nd governments. In practice most of the disputes
are between workers and employers
Types of disputes
The disputes can be of following types
a. Right disputes
Disputes over rights concerned with interpretation and application of work standards.
b. Interest disputes
Disputes due to conflict of interests related to pay, benefits, conditions of work and
working environments
Prepared By: Er. Su?ash _K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I C!tapter 8.0.
Cause of disputes
There are various causes of labor disputes. They can be generalized as follows:
1. Economic causes
a. Compensation demands
b. Bonus
c. Working cond · ions
d. Conditions of mployment
e. Industrial sick! ess
2. Managerial causes
a. Non recognitio to labor union
b. Lack of consultation in recruitment and development
c. Job security
d. Disciplinaryactions
e~ Lack of communication
3. Political causes
a. Political interference
b. Union rivalry
c. Collective bargaining
d. Multiplicity of labor law
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 8.0
. .
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 8.0 ·
9.1 Benchmarking
Benchmarking is the process of comparing one's business proc sses and performance metrics to
industry bests or best practices fi·om other companies. Dim 1sions typically measured are
quality, time and cost. In the process of best practice benchmar ing, management identifies the
best firms in their industry, or in another industry where simila' processes exist, and compares
the results and processes of those studied (the "targets") to ones own results and processes. In
this way, they learn how well the targets perform and, more importantly, the business processes
that explain why these firms are successfuL
Benclunarking is used to measure performance using a specific indicator (cost per unit of
measm;e, productivity per unit of measure or defects per unit of measure) resulting in a metric of
performance that is then compared to others.
Also referred to as "best practice benchmarking" or "process benchmarking", this process is used
in management and particularly strategic management, in which organizations evaluate various
aspects of their processes in relation to best practice companies' processes, usually within a peer
group defined for the purposes of comparison. This then allows organizations to develop plans
on how to make improvements or adapt specific best practices, usually with the aim of increasing
some aspect of performance. Benchmarking may be a one-off event, but is often treated as a
continuous process in which organizations continually seek to improve their practices.
Benefits and uses
In 2008, a comprehensive survey on benchmarking was commissioned by The Global
Benchmarking Network, a network ofbenclunarking centers representing 22 countries. Over 450
organizations responded fi-om over 40 countries. The results showed that:
1. Mission and Vision Statements and Customer (Client) Surveys are the most used (by
77% of organizations) of 20 improvernent tools, followed by SWOT analysis( strengths,
weaknesses, opportunities, and tlu·eats) (72%), and Informal Benchmarking
(68%). Performance Benchmarking was used by 49% and Best Practice Benchmarking
by 39%. .,.,
2. The tools that are likely to increase in popularity the most over the next three years are
Performance Benchmarking, Informal Benchmarking, SWOT, and Best Practice
Benchmarking. Over 60% of organizations that are not currently using these tools
indicated they are likely to use them in the next three years.
Procedure
There is no single benchmarking process that has been universally adopted. The wide appeal and
acceptance of benchmarking has led to the emergence of benchmarking methodologies. The 12
stage methodology according to Robert Camp 1989 consists of:
L_ Select.subjecL
2. Define the process
3. Identify potential partners
4. Identify data sources
5. Collect data and select patiners
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 9.0
• Identify problem areas: Because benchmarking can be applied to any business process or
function, a range of research techniques may be required. They include informal
conversations with customers, employees, or suppliers; exploratory research techniques such
as focus groups; or in-depth marketing research, research, surveys, questiom1aires, re-
engineering analysis, process mapping, quality control variance reports, financial ratio
analysis, or simply reviewing cycle times or other perforniance indicators. Before embarking
on comparison with other organizations it isessential to know the organization's function and
processes; base lining performance provides a point against which improvement effort can be
measured.
.. Identify other industries that have similar processes: For instance, if one were interested
in improving hand-offs in addiction treatment one would identifY other fields that also have
hand-off challenges. These could include air traffic control, cell phone switching between
tovv·crs, transfer of patients fi:om surgery to recovery rooms.
" IdentitY organizations that arc leaders in these areas: Look for the very best in any
industry and in any country. Consult customers, suppliers, financial analysts, trade
associations, and magazines to determine which companies are wotihy of study.
.. Survey companies for measUI:es and practices: Companies target specific business
processes using detailed surveys of measures and practices used to identify business process
alternatives and leading companies. Surveys are typically masked to protect confidential data
by neutral associations and consultants.
• Visit the "best practice" companies to identify leading edge practices: Companies
typically agree to mutually exchange information beneficial to all parties in a benchmarking
group and share the results within the group.
• Implement new and improved business practices: Take the leading edge practices and
develop implementation plans which include identification of specific opportunities, funding
the project and selling the ideas to the organization for the purpose of gaining demonstrated
value fiom the process.
Cost
• Visit Costs - This includes hotel rooms, travel costs, meals, a token gift, atid lost labor time.
• Jin1,e Costs - Me_ll1Qe!"$_9f the benchmarking. team will b~. il1Y~$ting time in r~se~rching
problems, finding exceptional companies to study, visits, and implementation. This will take
them away from their regular tasks for part of each day so additional staff might be required.
.. Benchmarking Database Costs - Organizations that institutionalize benchmarking into their
daily procedures find it is useful to create and maintain a database of best practices and the
companies associated with each best practice now.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Clwpter 9.0
Types
Benchmarking can be internal (comparing performance between different groups or teams within
an organization) or external (comparing performance with companies in a specific industry or
across industries). Within these broader categories, there are tbxee specific types of
benchmarking: 1) Proc s benchmarking, 2) Performance benchmarking and 3) strategic
benchmarking. These can be further detailed as follows:
• Process benchmarl ng- the initiating firm focuses its observation and investigation of
business processes w th a goal of identifying and observing the best practices fi:om one or
more benclunark firms. Activity analysis will be required where the objective is to
benchmark cost and efficiency; increasingly applied to back-office processes where
outsourcing may be a consideration.
• Financial benchmarking - performing a financial analysis and comparing the results in an
effort to assess your overall competitiveness and productivity.
• Benchmarking ft·om an investor perspective- extending the benchmarking universe to also
compare to peer companies that can be considered alternative investment opp01tunities fJ:om
the perspective of an investor.
• Benchmarking in the public sector- fimctions as a tool for improvement and innovation in
public administration, where state organizations invest efforts and resources to achieve
quality, efficiency and effectiveness ofthe services they provide.
• Performance benchmarking- allows the initiator firm to assess their competitive position
by comparing products and services with those of target firms.
.. Product benchmarking - the process of designing new products or upgrades to current
ones. This process can sometimes involve reverse engineering which is taking apart
competitors' products to find strengths and weaknesses.
• Strategic benchmarking- involves observing how others compete. This type is usually not
industry specific, meaning it is best to look at other industries.
• Functional benchmarking - a company will focus its benchmarking on a single function to
improve the operation of that particular function. Complex functions such as Human
Resources, Finance and Accounting and Information and Conununicatioi1 Teclmology are
unlikely to be directly comparable in cost and efficiency terms and may need to be
disaggregated into processes to make valid comparison.
• Best~in-class benchmarking - involves•studying the leading competitor or the company that
best carries out a sl)ecific function.
• Operational benchmarking- embraces everything from staffing and productivity to office
flow and analysis of procedures performed.
• Energy benchmarking - process of collecting, analyzing and relating energy performance
data of comparable activities with the purpose of evaluating and comparing performance
between or within entities. Entities can include processes, buildings or companies.
Benchmarking may be internal between entities within a single organization, or - subject to
confidentiality restrictions - external between competing entities.
Prepared B_y: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 9.0
In general, risk is a function of uniqueness of a project and the experience of the project team.
Risk=f (wiiqueness, experience of project team)
Project Risk -
Project risk is an uncertain event or condition that, if it occurs, has a positive or negative effect
on a project objective. A risk has a cause and, if it occurs, an impact. For example, the cause may
be requiring a permit or having limited personnel assigned to the project. The risk event is that
the permit may take longer than planned or the persotmel may not be adequate for the task.
Project risk includes both tlu·eats to the project's objectives and opportunities to unprove on
those objectives.
The notion of project risk involves two concepts:
A project will be ordinarily considered risky \Yhene·,·er at least one factor- either the likelihood
or the impact- is large. For example, a project will be considered risky ·where the potential impact
is human fatality or massive financial loss even when ilie Iii.;:dli1mod of either is small.
Risk A1rawgement
Risk management is the systematic application of the risk management processes on a project.
The processes consist of risk management planning, identification, analysis, responding, and
monitoring & control.
The objective of risk management is to maximize the probability and impact of positive events
and minimize the probability and consequences of events adverse to project objectives.
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Chapter 9.0
Minimising Risk in
Proj cts
c
0
n
t
_____ _\-,,¢,('
----------
r
a
1
""""
n
t
U ncertai nt'~/
The curved line indicates the 'acceptable level of risk', whatever that may be in the
individual case. The risk may be reduced to an acceptable level by reducing either or
both of uncertainty and constraint. In practice, few people have the opportunity to
reduce constraint, so most focus on the reduction of uncertainty. It is also worth noting
from the diagram that total elimination of risk is rarely achieved. So we have to
consider how to manage that remaining risk most effectively.
The processes of risk management are updared throughout the project life. It involves following
steps:
Risk
Hanagement
Pleinnlng
(2 Find tl1em)
Risk Qualitative (3 Sift)
r·-· >Ieientiflcatron ('·~"~··~"·····• Risk
:....~~2.~!t,sis
I
RISk Quantitative
Risk
· cor1tror &.· ·
·Honltorino
Risk
Response
Planning
<f5~'C1Be'a·e:nons)
Prepared By: Er. Subash K. Bhattarai (B.E Civil /PGDESD I MPA I MSc Ci'vl) I Chapter 9.0
Ri>k M;tnagL~men!
..
- PrQc(\SS Ffow
Prepared By: Er. Subash K. Bhattarai (RE Civil I PGDESD I MPA I MSc CM) I Chapter 9.0
What is dispute?
Unsettled claims in construction leads to dispute.
(;J~t£~1~ l~_s~u!s~
wlzic!t generally tutns_ ~Qdisprttes_ itz constrr!cti()n
Owner and Designer Initiated Changes
The most common types of owner and designer initiated changes that tend to result in
disputes include:
• Numerous last minute addenda during bid period.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) [Chapter 9.0
· ·····Glahn Afanagementflowchart
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 9.0
Prepared By:Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Cltapter 9.0
. ,.
.. The disputing parties has right to choose a learned adjudicator having expertise in subject
related to dispute
e .-\djudicator in1poses a fair and impartial decision like arbitrator or judge
• It is faster than arbitration or litigation, it could be within 28 days
• Disputes can be resolved hile works are still in progress
• Better understanding of fi cts and figures tlu-ough site investigations and studies
• Amicable settlement can e done after adjudication award
o Adjudication is private an confidential
Dispute resolution through Arhi ration
Arbitration is a process to resolve disputes between contracting parties based on a contract
agreement. It is supp01ied by law. Arbitration is initiated when one party gives notice to the
other. The parties then appoint independent person as an arbitrator to resolve disputes. The
decision by the arbitrator called an award is legal and binding. In Nepal NEPCA does the ad-hoc
procedures of arbitration. Arbitrator is usually a lawyer.
Advantages/ Features ofArbitration
• Neutrality
0 Expertise
Cl Flexible procedures
,. Appeal is limited
" Confidentiality
• Binding internationally
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 9.0
In the current global work environment, most companies focus on lowering employee
turnover and retaining the talent and knowledge held by their workforce. New hiring not only
entails a high cost but also increases the risk of the newcomer not being able to replace the
person who was working in that position before. HR departments also strive to offer benefits that
will appeal to wo ·kers, thus reducing the risk of losing knowledge.
Nature of HRM
• Human fl cus: HRM is people centered. It is concerned with human element at w rk in
organizat on. It focuses on people possessing energyand competencies. It develo s and
utilizes h man potential.
• Management functions: HRM applies management fimctions and principles which
involves acquisition, development, utilization and maintenance ofhuman resources.
'~~ Continuous conunitment: HRM is a continuous on-going activity which does not
concerned in present also with future. It ensures continuous conunitment of employees
G Dynamic: HRM is dynamic concept. It is affected by changes in environm.ent. It adapts
the political-legal environment, economic environment, socio-cultural environment and
technological environment.
e Mutuality oriented: HRM promotes mutuality between employers and employees 111
terms of objectives, influence, respect, rewards and responsibilities.
1-/RJlf ilforlel
Prepared By: Er. Subash K. Bhattarai (B.E Civil/ PGDESD I MPA I MSc CM) I Clrapter 9.0
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 9.0
\
l
'¥
Benefits/ Objectives of KM
• Awareness to employees
• · Accessibility of Information
~ Availability of Usable Knowledge
.. Timely available of information
~ Improve decision making
• Reducing cost and risk
• Improve strategic planning
• Increase versatility of workforce
9. 7 Total Quality Management (TQM)
What is Quality?
According to advanced learner dictionary, quality is degree of goodness. Similarly cross-by
defines as conformance to requirements. According to Juran, Quality is fitness for purpose.
• Zero defects
• Consistent conformance to expectation
• Doing things right the first time
• Quality is the totality of characteristics of an entity that bears on its ability to satisfy
stated-and implied needs- · ·· ·
• Quality is not grade (grade is an indicator of category or rank related to features that
cover different sets of needs for products or services intended for the same functional use.
Prepared By: Er: Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 9.0
L;:r,-el is a general indication of the extent of departure fi:om the ideal. A higl1 grade
2-~~:;::le can be of inadequate quality as far as satisfying needs and vice versa. E.g. a
luxurious hotel with poor services or small guest house with excellent service)
• Quality costs more, but lack of quality costs even more
• Quality is means of a hieving project success. It is not the goal in itself
• Process quality is more than product quality
o Quality standards d not demand the best quality; they establish the mmrmum
requirements to be acl ieved
• Quality' does not happen by accident, it has to be properly planned and implemented
Quality Management
Quality Control
Quality Control is the operational techniques and activities that are used to fidfill requirements
for quality. Quality Inspection is done first for quality control. Activities Sllch as measuring,
examining, testing, gauging one or more characteristics of a product or service and comparing
these with specified requirements to determine conformity is quality inspection.
Inspection is concerned with sentencing the product as good or bad, by comparison with the
standard. On the other hand, quality control is concerned with feedback of the comparative
information in order to regulate the process. In quality control, the limits are set so that the
process can be adjusted before product fi:om the process reaches the limit where it has to be
rejected.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 9.0
Quality Assurance
All planned and systematic actions necessary to provide adequate confidence that a product or
service will satisfy given requirements or quality both within the organization and Quality
assurance:
·Quality Management
Quality management includes Quality Assurance (QA) and Quality Control (QC) as well as other
concepts of quality planning, quality policy and quality improvement. Total quality management
(TQM) develops these concepts as a long - term global management strategy and the
participation of all members of the organization for the benefit of the organization itself: its
members, its customers and society as a whole.
Total quality management is a new concept of quality management and is that aspect of the
overall management function that determines and implements the quality policy. The essential
elements ofTQM are:
• Quality audit
0 Quality surveillance
• Quality Assurance
• Quality Circles
Fig: TQM
TQM consists of organization-wide efforts to install and make permanent a clin1ate in which an
· · ·
-- En:gamzat-JoncGntmuous 1y 1mproves-1ts
· · a b·r·
Hty to r1"'e 1·1ver ,11g
1• 1 1-quc>.r·1ty pro d.ucts and, serv1ces
· to
customers.
It is a management philosophy of continuously improving project quality through everyone's
conm1itment and involvement to satisfy customer needs. It puts quality first.· TQM creates a
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 9.0
project culture committed to continuous improvement in all aspects \Yhicb seeks incremental
improvements.
CompOFzents of TQM
• Strategic conunitment
• Continuous quality improvement
o Customer focus
s Employee involvement
• Accurate measurement
• Improved materials, teclmology and methods
Tools and techniques of TQM
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 9.0
• Oxford Advanced Learner's Dictionary defines the term "safety" as 'being safe; Jiee
fi:om danger'.
e Safety hazards are those that pose imminent danger of causing injury or death to workers
or damage to materials, equipment or structures.
• Theoretically, safety would mean the ab ence of danger at work, which is made possible
by eliminating hazards that create the da ger.
• A more practical definition used in an ILO document states "A thing is provisionally
categorized as safe if its risks are deer ed known and, in the light of that knowledge,
judged to be acceptable."
• Safety may be defined as an act of being safe fiom the materials, substance and the
process at construction site. Safety basically is concerned with no loss of life at the work
place and minimizing injuries to the workmen and other common people. It is also
concerned with the safety of works and with the damage of property and loss oftime.
Accident
An event that happens all of a sudden unexpectedly which may cause injury, death or damage to
men/equipment/material and affects the life of individuals and his family as well as ultimately
entire society.
Causes of Accidents
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 9.0
Prepared By: Er. Subash K. Bhattarai (B.E Civil /PGDESD I MPA I MSc CM) I Chapter 9.0
"'
Unsafe conditions may be grouped into:
o Inadequate mechanical guarding
o Defective condition of equipment, tools, f1oors, stairs etc.
o Unsafe design and construction
o Unsafe process, operation or arrangement e.g. unsafe piling, sto king, storage,
overloading, overcrowding etc.
o Inadequate light and ventilation and
o Unsafe dress e.g. loose clothing, no gloves, no aprons and shoes etc
What ar · the Unsafe Acts?
• nsafe acts of the persons are those types of behavior at the work pl ce that cause
accident and leads to injuries or death.
• They include:
o Working unsafely
o Contravention of safety orders
o Removing or altering safety devices
o Operating at unsafe conditions
o Use ofunsafe or improper equipment etc.
Human elements in safety
• Safety policy
• Recruitment and Placing
• Alcoholism
• Training
Safety Programfor Construction
qt Safety planning
e Safety Implementation
• Safety Monitoring
• Safety Control
The Growth of safety Regulation/Legislation: Nepalese Scenario
In Nepal, the government's first response towards safety in projects might possibly be the
. -
enactment of the "Labor Act 2048", which came into force on 15 May 1992. Before this, there
was no special law regarding labor in construction industry.
'Labor Act, 2048' contains provisions on health and safety of the workers. As provided under
chapter 5 of the act, management of an organization should ensure the following:
• General Safety
o The working area should be cleaned, painted, cleared of waste and necessary
insecticides spread on the area.
o Proper light and ventilation as well as appropriate temperature should be
maintained.
o ArrangemeJ1tshouldbe madeforthe disposal ofwastematerial..
o Working area should be free from dust, air, vapor and other material, which could
adversely affect the health of the worker.
o Arrangements to be made for the control of noise and necessary equipment to be
provided if workers have to work on loud noise area.
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc Ci\11) I Chapter 9.0
... ::.
For more Notes and Tutorials Visit www.masenzworld.com
A Reading Manual on Construction
Downloaded Project Management (Purbanchal University)
from www.masenzworld.com
o Work area should not be congested. Every worker should get at least 15 Cum. Of
\vorking space within 4m. Height from the ground.
o Adequate potable drinking water should be provided.
o Gents and ladies latrines to be provided at appropriate place.
o Medical checkup of the workers should be d ne at least once a year.
e Safety for Eye
o Eye shield or goggles should be provided o safeguard eyes from flying dust,
object, welding and gas cutting light etc.
• Safety from Chemicals
o Personal safety arrangement has to be made for the workers who handle
dangerous chemicals.
• Fire Safety
o Modern safety equipment
o Provision of ftre escape
o Provision offtre extinguisher at required places.
• Guarding the Machines
• Heavy load handling
•. Pressure Plant
• Safety Order
• Information ofthe accidents
Prepared By: Er. Subash K. Bhattarai (B.E Civil I PGDESD I MPA I MSc CM) I Chapter 9.0
>.,-.
:~ pro~a~i!ities assq~~W;th
pmr. '>!A: i::'.li>o:th"' values as extreme as
observeclv;~l:U.1es of z in ·t®. st':'~Gl.':':~.~·ii:6~lgistri,butio:h.. Where