Pengecekan Volume Dermaga Fix
Pengecekan Volume Dermaga Fix
PEKERJAAN PENGERUKAN
1. Pengerukan Kolam Dermaga KBT (D-01 s/d D-04)
POT 02 + POT 03
VOLUME ZONA 2 = x JARAK
2
1283.5 + 1271
= x 100
2
= 1277.25 x 100
= 127725 m 3
POT 03 + POT 04
VOLUME ZONA 3 = x JARAK
2
1271 + 1292.25
= x 100
2
= 1281.625 x 100
= 128162.5 m 3
POT 04 + POT 05
VOLUME ZONA 4 = x JARAK
2
1292.25 + 1253
= x 100
2
= 1272.625 x 100
= 127262.5 m3
POT 05 + POT 06
VOLUME ZONA 5 = x JARAK
2
1253 + 1278
= x 100
2
= 1265.5 x 100
= 126550 m3
POT 06 + POT 07
VOLUME ZONA 6 = x JARAK
2
1278 + 1278
= x 100
2
= 1278 x 100
= 127800 m 3
POT 07 + POT 08
VOLUME ZONA 7 = x JARAK
2
1278 + 1283
= x 100
2
= 1280.5 x 100
= 128050 m3
POT 08 + POT 09
VOLUME ZONA 8 = x JARAK
2
1283 + 1253
= x 80
2
= 1268 x 80
= 101440 m3
POT 01 + POT 02
VOLUME ZONA 1 = x JARAK
2
1173.68 + 1218
= x 125
2
= 1195.84 x 125
= 149480 m 3
POT 02 + POT 03
VOLUME ZONA 2 = x JARAK
2
1218 + 1331.25
= x 100
2
= 1274.625 x 100
= 127462.5 m 3
POT 03 + POT 04
VOLUME ZONA 3 = x JARAK
2
1331.25 + 1448
= x 125
2
= 1389.625 x 125
= 173703.13 m3
Diketahui : r = 175 m
: R = 225 m
t = 7 m
Kolam Putar
Volume = 1/3 π t r2 + R2 + Rr
= 1/3 . 3.14 . 7 . 175 2 + 225 2 + 175 x 225
= 7.3193 x 120625
= 882895.39 m3
TOTAL VOLUME
1002 m2
981.24
960.48 m2
929.865
899.25 m2
889.185
879.12 m2
854.26375
829.4075 m2
814.70375
800 m2
771.065
742.13 m2
723.19
704.25 m2
676.365
648.48 m2
630.24
612 m2
612
612 m2
594.04
576.08 m2
549.665
523.25 m2
505.99
488.73 m2
463.365
438 m2
438
438 m2
421.44
404.88 m2
388.6
372.32 m2
356.32
340.32 m2
324.6
308.88 m2
293.44
278 m2
262.84
247.68 m2
232.8
217.92 m2
203.32
188.72 m2
174.4
160.08 m2
146.04
132 m2
125.085
118.17 m2
111.325
104.48 m2
97.705
90.93 m2
84.225
77.52 m2
77.52
77.52 m2
70.885
64.25 m2
57.685
51.12 m2
44.625
38.13 m2
38.13
38.13 m2
31.705
25.28 m2
18.925
12.57 m2
9.41875
6.2675 m2
3.13375
0 m2
0
0 m2
0
0
0 m2
0
DERMAGA KBT
HITUNGAN MANUAL 969,170 m3
HITUNGAN RAB 963,296 m3
SELISIH 5,874 m3
DERMAGA LAUT
HITUNGAN MANUAL 450,646 m3
HITUNGAN RAB 381,530 m3
SELISIH 69,116 m3
KOLAM PUTAR
HITUNGAN MANUAL 1,046,750 m3
HITUNGAN RAB 1,211,619 m3
SELISIH -164,869 m3
ALUR
HITUNGAN MANUAL 1,400,735 m3
HITUNGAN RAB 1,498,929 m3
SELISIH -98,194 m3
(VOLUME DOKUMEN RAB LEBIH BESAR DIBANDING VOLUME HITUNGAN MANUAL HASIL PENGECEKAN)
PENGECEKAN)
IV. PEKERJAAN TIMBUNAN
1. TIMBUNAN BACK UP AREA (G-01 s/d G-04)
TIMBUNAN JALAN AKSES (Tidak ada gambar denah dan detail potongan)
HITUNGAN MANUAL m 3
HITUNGAN RAB m3
SELISIH m3
(VOLUME DOKUMEN RAB LEBIH BESAR DIBANDING VOLUME HITUNGAN MANUAL HASIL PENGECEKAN)
GEOTEKSTIL TIPE NON WOVEN (Tidak ada gambar denah dan detail)
HITUNGAN MANUAL m 3
HITUNGAN RAB m3
SELISIH m3
TOTAL SELISIH m3 x = Rp -
ENGECEKAN)
III. PEKERJAAN STRUKTUR DERMAGA DAN SHEETPILE
C. PEKERJAAN SHEETPILE
1. PEKERJAAN SHEETPILE SISI BARAT KBT
700 mm
350 mm 350 mm
400 mm
Volume Sheetpile = A x H
= 0.01265 x 20
= 0.253 m /lembar
3
700 mm
350 mm 350 mm
400 mm
Volume Sheetpile = A x H
= 0.01265 x 20
= 0.253 m /lembar
3
SHEETPILE SISI TIMUR KBT (Tidak ada gambar denah penempatan sheetpile)
HITUNGAN MANUAL m 3
HITUNGAN RAB m3
SELISIH m3
HITUNGAN RAB m3
SELISIH m3
(VOLUME DOKUMEN RAB LEBIH BESAR DIBANDING VOLUME HITUNGAN MANUAL HASIL PENGECEKAN)
VI. PEKERJAAN BREAKWATER
1. TETRAPOD
TETRAP OD
Q UARRY RUN
(B ATU 10-30 K G)
TRUNK (L = 550 m)
HEAD TRUNK
Penampang Tetrapod (A) = 30.275 m2 Penampang Tetrapod (A)
Panjang bentang (L) - 2 x 50 m = 100 m Panjang bentang (L)
Berat Volume = 2.2 ton/m 3
Berat Volume
Berat Tetrapod = 1.2 ton/unit Berat Tetrapod
Porositas 50% sesuai dengan Laporan Akhir hal. VI-7, maka Porositas 50% sesuai dengan Laporan Akh
Berat Bersih (Wnet) = W x 50% Berat Bersih (Wnet)
= 6660.5 x 50%
= 3330.25 t
BATU 50-80 KG
TRUNK (L = 550 m)
QUARRY RUN
(BA TU 10-30 KG)
= 25.372 m2
= 550 m
= 2.2 ton/m3
= 1.2 ton/unit
= A x L
= 25.372 x 550
= 13954.6 m3
= Vol. x 2.2 ton/m3
= 13954.6 x 2.2
= 30700.12 t
HEAD TRUNK
Penampang Batu 50-80 kg (A) = 25.838 m 2
Penampang Batu 50-80 kg (A)
Panjang bentang (L) - 2 x 50 m = 100 m Panjang bentang (L)
= A x L
= 30.742 x 550
= 16908.1 m3
VI. PEKERJAAN BREAKWATER
3. BATU 10-30 KG
HEAD TRUNK
Penampang Batu 10-30 kg (A) = 22.187 m 2
Penampang Batu 10-30 kg (A)
Panjang bentang (L) - 2 x 50 m = 100 m Panjang bentang (L)
= A x L
= 22.187 x 550
= 12202.85 m3
VI. PEKERJAAN BREAKWATER
4. GEOTEKSTIL
Volume Total = L x P
= 30.000 x 650
= 19500 m 2
TETRAPOD
HITUNGAN MANUAL 15,568 unit
HITUNGAN RAB 29,174 unit
SELISIH -13,606 unit
BATU 50-80 KG
HITUNGAN MANUAL 19,492 m3
HITUNGAN RAB 19,253 m3
SELISIH 239 m3
BATU 10-30 KG
HITUNGAN MANUAL 14,422 m3
HITUNGAN RAB 15,104 m3
SELISIH -682 m3
GEOTEKTIL
HITUNGAN MANUAL 19,500 m2
HITUNGAN RAB 20,200 m2
SELISIH -700 m2
II Pekerjaan Pengerukan
1 Pengerukan Kolam Dermaga Sungai KTB -8.00 m LWS m3 936,296.00 97,086.81 969,170.00 (32,874.00) (3,191,631,791.94) (D-01 s/d D-04) ada ada
2 Pengerukan Kolam Dermaga Laut KTB -8.00 m LWS m3 318,530.00 97,086.81 450,645.63 (132,115.63) (12,826,684,582.41) (E-01 s/d E-03) ada ada
3 Pengerukan Kolam Putar KTB -8.00 m LWS m3 1,211,619.00 97,086.81 1,046,750.39 164,868.61 16,006,567,656.75 (F-01 s/d F-02) ada ada
4 Pengerukan Alur KTB -8.00 m LWS m3 1,498,929.00 97,086.81 1,400,734.50 98,194.50 9,533,390,764.54 (H-01 s/d H-15) ada ada
III Pekerjaan Struktur Dermaga dan Sheet Pile
A Dermaga Sungai KTB
1 PDA Test titik 8.00 20,000,000.00 8.00 tidak ada gambar tidak ada tidak ada
2 Pekerjaan Tiang Pancang beton D 800
- Pengadaan tiang pancang Spun Pile D 800 mm, L:31m m' 9,672.00 1,508,238.53 9,672.00
- Pemancangan tiang pancang (darat) m' 7,502.00 426,378.09 7,502.00
tidak ada gambar ada ada
- Pemancangan tiang pancang (laut) m' 2,170.00 757,802.01 2,170.00
- Isian kepala tiang pancang m3 141.07 5,832,450.60 141.07
-Grouting non-shirkage m3 19.59 3,750,000.00 19.59
3 Pekerjaan Tiang Pancang beton D 600
- Pengadaan tiang pancang Spun Pile D 600 mm, L:31m m' 14,508.00 1,119,097.72 24,180.00 (9,672.00)
- Pemancangan tiang pancang (darat) m' 11,253.00 358,518.00 11,253.00
(S-01 s/d S-04) ada ada
- Pemancangan tiang pancang (laut) m' 3,255.00 606,521.37 3,255.00
- Isian kepala tiang pancang m3 94.05 8,978,080.45 94.05
-Grouting non-shirkage m3 22.04 3,750,000.00 22.04
4 Pekerjaan Pile Cap Beton Precast
- Pile cap beton D 1,2 m unit 468.00 2,893,477.77 xxx xxx (S-01 s/d S-03) ada ada
- Pile cap beton D 1,4 m unit 312.00 3,357,277.39 xxx xxx
5 PEKERJAAN BALOK BP2 (Balok Crane)
- Balok Precast unit 306.00 16,482,372.03 xxx xxx
tidak ada gambar ada ada
- Sambungan Balok (cast in situ) m3 550.00 2,303,146.37 xxx xxx
- Balok dilatasi BP2 m3 2.34 7,010,378.18 xxx xxx
6 PEKERJAAN BALOK BP1 ( memanjang )
- Balok Precast unit 459.00 10,567,367.91 xxx xxx
tidak jelas ada ada
- Sambungan Balok (cast in situ) m3 495.72 2,420,122.38 xxx xxx
- Balok dilatasi BP1 m3 3.51 5,797,976.06 xxx xxx
7 PEKERJAAN BALOK BP1 ( melintang )
- Balok precast unit 624.00 11,761,396.36 xxx xxx tidak jelas ada ada
tidak jelas ada ada
- Sambungan Balok (cast in situ ) m3 653.92 2,303,489.04 xxx xxx
8 PEKERJAAN BALOK LIST PLANK B1 ( cast in situ ) m3 1,057.08 4,837,779.08 xxx xxx tidak jelas ada ada
9 PEKERJAAN BALOK KONSOL BC1 ( cast in situ ) m3 117.00 9,908,407.96 xxx xxx tidak jelas ada ada
10 PEKERJAAN PLAT UTAMA
- Pelat Precast unit 2,448.00 8,219,877.59 xxx xxx
tidak ada gambar ada ada
- Topping plat ( cast in situ ), t =12 cm m3 2,349.36 4,175,401.15 xxx xxx
- Pelat Konsol dilatasi, t=12 cm m3 12.80 6,256,101.81 xxx xxx
11 PELAT KONSOL, t = 50 cm m3 655.38 6,029,656.97 xxx xxx tidak ada gambar ada ada
12 DILATASI BAJA SIKU L100.100.10 m' 50.00 3,078,319.98 xxx xxx tidak ada gambar ada ada
13 FENDER SYSTEM TYPE CELL FENDER 100 & KELENGKA nos 78.00 252,935,929.45 xxx tidak jelas ada ada
xxx
14 BOLLARD KAPASITAS 60T DAN KELENGKAPANNYA] nos 40.00 35,997,265.81 xxx xxx tidak ada gambar ada ada
15 PEKERJAAN HOLD DOWN ANCHORING BOLT REL CRANE m' 1,500.00 1,602,085.82 xxx xxx tidak ada gambar ada ada
B DERMAGA LAUT
1 PDA TEST tidak ada gambar tidak ada tidak ada
2 PEKERJAAN TIANG PANCANG BETON (D800) titik 4.00 17,173,500.00 xxx xxx
- Pengadaan tiang pancang Spun Pile D 800 mm, L:31m m' 10,850.00 1,119,097.72 xxx xxx
- Pemancangan tiang pancang (darat) m' 10,850.00 606,521.37 xxx xxx tidak ada gambar ada ada
- Isian kepala tiang pancang m3 70.34 8,978,080.45 xxx xxx
- Grouting non-shirkage m3 16.49 3,750,000.00 xxx xxx
3 PEKERJAAN PILE CAP BETON PRECAST
tidak ada gambar ada ada
- Pile cap beton D 1,2 m unit 350.00 2,893,477.77 xxx xxx
4 PEKERJAAN BALOK BP2 (Balok Crane)
- Balok Precast unit 345.00 10,567,367.91 xxx xxx tidak jelas ada ada
- Sambungan Balok (cast in situ) m3 372.60 2,420,122.38 xxx xxx
5 PEKERJAAN BALOK BP1 ( memanjang )
- Balok Precast unit 138.00 11,761,396.36 xxx xxx tidak jelas ada ada
- Sambungan Balok (cast in situ) m3 293.43 2,303,489.04 xxx xxx
6 PEKERJAAN BALOK LIST PLANK B1 ( cast in situ ) m3 490.50 4,837,779.08 xxx xxx tidak ada gambar ada ada
7 PEKERJAAN BALOK KONSOL BC1 ( cast in situ ) m3 52.53 9,908,407.96 xxx xxx tidak ada gambar ada ada
8 PEKERJAAN PLAT UTAMA
- Pelat Precast unit 1,104.00 8,219,877.59 xxx xxx ada gambar ada ada
- Topping plat ( cast in situ ), t =12 cm m3 1,056.63 6,029,656.97 xxx xxx
9 PELAT KONSOL, t = 50 cm m3 356.67 4,837,779.08 xxx xxx tidak ada gambar ada ada
10 FENDER SYSTEM TYPE CELL FENDER 100 & KELENGKA nos 35.00 252,935,929.45 xxx xxx tidak jelas ada ada
11 BOLLARD KAPASITAS 60T DAN KELENGKAPANNYA] nos 19.00 35,997,265.81 xxx xxx tidak ada gambar ada ada
C SHEET PILE
1 PEKERJAAN SHEETPILE SISI BARAT KBT
- Pengadaan Pile Baja OZ-28A.700, L=20m kg 3,881,200.00 14,821.53 2,214,446.00 1,666,754.00 24,703,844,413.62
ada ada ada
- Pemancangan Sheet Pile Baja OZ-28A.700, L=20m titik 1,252.00 8,635,698.79
- Lapisan anti karat (+3,5 sd -9,5 LWS) m2 32,552.00 176,452.73
2 PEKERJAAN SHEETPILE SISI Timur KBT xxx xxx
- Pengadaan Pile Baja OZ-28A.700, L=20m kg 3,434,800.00 14,821.53 xxx xxx
1 Timbunan Back Up Area m3 435,257.31 214,156.32 307,402.50 127,854.81 27,380,915,603.90 (G-01 s/d G-04) ada ada
1 Pengadaan dan Pemasangan Tertrapod 1.2 Ton (K-350) Unit 29,174.00 1,844,837.53 15,568.00 13,606.00 25,100,859,433.18
(I-01 s/d I-06) ada ada
2 Batu 50 - 80 Kg m3 19,253.45 463,233.41 19,491.90 (238.45) (110,458,006.61)
3 Batu 10 - 30 Kg m3 15,104.45 363,213.86 14,421.55 682.90 248,038,744.99
4 Geotekstil Matras Tipe Woven m2 20,200.96 190,194.00 19,500.00 700.96 133,318,386.24
VII PEKERJAAN DRAINASE
1 Pekerjaan Saluran m' 1,098.70 5,623,425.80 xxx xxx
tidak ada gambar ada ada
tidak ada gambar ada ada
2 Pekerjaan Box Culvert A m' 180.00 6,122,877.38 xxx xxx
3 Pekerjaan Box Culvert B m' 200.00 5,423,645.17 xxx xxx
VIII PEKERJAAN PENERANGAN DERMAGA
1 Pekerjaan Pondasi Tiang Lampu titik 11.00 54,587,574.23 xxx xxx tidak ada tidak ada tidak ada
2 Instalasi Penerangan Dermaga unit
SELISIH 95,179,517,795.08