14 (Thomas Kratzer)
Annual Demand : 6000 units/year Ordering Cost : $30 per order Carrying Cost = Holdin
Price : $100 demand for 1 week : 120 units Ordering Cos
Carrying Cost : $10 unit/year 250 working days/year
Setup Cost = $ 30 (D/Q)S = (Q/2)H
Holding Cost = $10
a)
⬚
Q*= 2𝐷𝑆/𝐻 Q*= 2(6000)(30)/10 Q*= 189,74