RENCANA CCO JMF

No Lapisan / Overlay Aspal Beton (AC) Tebal 5 cm (m²) Volume Kontrak Volume JMF
Satuan Koef Harga Koef Harga
1 Pekerja O/H 0.125 65,100.000 8,137.50 0.125 65,100.000 8,137.50
2 Mandor O/H 0.017 94,500.000 1,634.85 0.017 94,500.000 1,634.85
3 Tandem Roller 6-8 T. Jam 0.002 734,000.000 1,614.80 0.002 734,000.000 1,614.80
4 Wheel loader 1.0-1.6 m3 Jam 0.003 432,919.905 1,428.64 0.003 432,919.905 1,428.64
5 Tire Roller 8-10 t. Jam 0.003 729,000.000 2,332.80 0.003 729,000.000 2,332.80
6 Dump Truck 3-4 m3 Jam 0.103 276,000.000 28,510.80 0.103 276,000.000 28,510.80
7 Asphalt Finisher Jam 0.003 559,000.000 1,844.70 0.003 559,000.000 1,844.70
8 Asphalt Mixing Plant Jam 0.003 5,240,551.000 17,293.82 0.003 5,240,551.000 17,293.82
9 Generator set Jam 0.003 468,000.000 1,310.40 0.003 468,000.000 1,310.40
10 Aspal Kg 7.933 11,500.000 91,232.95 6.669 11,500.000 76,693.50
11 Agregat kasar (batu spilt 2/3) M³ 0.034 310,000.000 10,509.00 0.034 310,000.000 10,509.00
12 Batu pecah (batu split 1/2) M³ 0.035 340,000.000 11,730.00 0.035 340,000.000 11,730.00
13 Pasir Aspal/ Abu Batu/ Screening M³ 0.035 260,000.000 8,970.00 0.035 260,000.000 8,970.00
Jumlah M2 186,550.25 Jumlah M2 172,010.80
M3 3,731,005.08 M3 3,440,216.08
SELISIH
10305 186,550.25 1,922,400,367 10305 172,010.80 1,772,571,335 149,829,032.25