Professional Documents
Culture Documents
Generation 12 PDF
Generation 12 PDF
Electricity
Plan
(Volume 1)
Generation
[In fulfilment of CEA's obligation under
section 3(4) of the Electricity Act 2003]
Government of India
Ministry of Power
Central Electricity Authority
January 2012
National
Electricity
Plan
(Volume 1)
Generation
[In fulfilment of CEA's obligation under
section 3(4) of the Electricity Act 2003]
Government of India
Ministry of Power
Central Electricity Authority
January 2012
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
CONTENTS
1 Introduction 1-18
Acronyms 247-252
Contents
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Chapter 1
INTRODUCTION
demand of the Power Sector due to and supply of domestic coal has widened.
various reasons, major one being delay in Therefore, it has been decided to allocate
development of coal mines in the country. coal blocks to project developers for
This has necessitated the need to import captive use. All UMPPs at pithead have
coal. Moreover, the huge capacity been allocated coal blocks.
addition programme during 11th Plan and
beyond as compared to the actual The number of coal blocks allocated to
capacity addition during the past few Plan various utilities and the geological
periods has further aggravated the reserves of the blocks are given in Table
situation and the gap between demand 1.1 below:
Table: 1.1
Details of Captive Coal Blocks Allocation to Power Sector
16 blocks with a reserve of 1355 MT are fixation of tariff of the project. Merchant
under operation. Mining Plan has been sale is to reduce with delay in
approved for 26 blocks (reserve-7787MT). commissioning of the projects. Provisions
The captive mine blocks have to be have also been made for providing
developed on priority to meet the incentives for local area development
capacity addition targets for the 12th plan. fund and project affected families.
Under the scheme 90% capital subsidy All efforts have been made to ensure that
would be provided for overall cost of the manufacturing capacity for Main Plant
project for provision of: equipment in the country is suitably
enhanced to meet capacity addition
Rural Electricity Infrastructure requirement during 11th Plan and beyond
Backbone (REDB) with at least one by enhancing manufacturing capability of
33/11 KV(or 66/11 KV) substation in existing manufacturers and by
each block encouraging new vendors.
Village Electrification Infrastructure
(VEI) with at least one distribution With above collaborations it may be
transformer in each village/habitation concluded that country have sufficient
Decentralized Distribution Generation manufacturing capability for main plant
(DDG) System where grid supply is equipments.
either not feasible or not cost
effective.
CEA has already reviewed the Pre- tendering of 11 units of 660 MW with
qualification requirement of suppliers of super critical technology for NTPC & DVC
Super Critical boilers and turbine- projects has been initiated with
generators to facilitate entry of new mandatory phased indigenous
players and has recommended the same manufacturing.
for adoption by central and state power
utilities. In order to promote indigenous An assessment of requirement of Balance
manufacturing and transfer of technology of Plant equipment for power plants has
of super critical technology, bulk also been carried out and efforts are
Exhibit 1.1 – All India Installed Capacity (as on 31st December, 2011)
NUCLEAR, NEW
4780, 3% RENEWABLES,
20162.24, 11%
HYDRO,
38748.4, 20%
Exhibit 1.2
All India Installed Capacity (Renewable) As on 31st December, 2011
RENEWABLE INSTALLED CAPACITY
Biomass,
Solar149 MW,
2788MW,
1%
13.7%
Small Hydro,
3121MW, Wind,
15.3% 14105MW,
70%
The growth of Installed Capacity and Generation in India from various sources is shown in
Exhibit 1.3, 1.4 & Table 1.2 below:
Table 1.2
Growth of Electricity Generation
Plan/Year Generation Growth rate in (%) Compound Growth (%)
8th Plan
1992-93 301.07 5.0 6.61
1993-94 323.53 7.5
1994-95 351.03 8.5
1995-96 380.08 8.3
1996-97 394.80 3.9
9th Plan
1997-98 420.62 6.5 5.47
1998-99 448.37 6.6
1999-2000 480.68 7.2
2000-01 499.55 3.9
2001-02 515.25 3.1
th
10 Plan
2002-03 531.61 3.2 5.16
2003-04 558.34 5.0
2004-05 587.42 5.2
2005-06 617.51 5.1
2006-07 662.52 7.3
11th Plan
2007-08 704.47 6.3
2008-09 723.79 2.7
2009-10 771.60 6.6
2010-11 811.10 5.6
Exhibit 1.3
ALL INDIA INSTALLED CAPACITY
200000
180000
160000 RES
Nuclear
140000
120000
MW
100000
80000
Thermal
60000 Hydro
40000
20000
0
1985-86
1986-87
1987-88
1988-89
1989-90
1990-91
1991-92
1992-93
1993-94
1994-95
1995-96
1996-97
1997-98
1998-99
1999-00
2000-01
2001-02
2002-03
2003-04
2004-05
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
Years
Exhibit 1.4
ALL INDIA GROSS GENERATION
1000000
900000 RES
Gross Generation-GWH
800000
Nuclear
700000
600000
500000
400000
300000 Hydro
200000
Thermal
100000
0
1985-86
1986-87
1987-88
1988-89
1989-90
1990-91
1991-92
1992-93
1993-94
1994-95
1995-96
1996-97
1997-98
1998-99
1999-00
2000-01
2001-02
2002-03
2003-04
2004-05
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
Years
Coal based generation contributes major the year 2007-08 (1st year of 11th Plan), the
part of the installed capacity and peak deficit was about 18,000 MW (16.5%)
contributes to about 68.6% of the total and the average energy shortage in the
energy generation (year 2008-09). In country was about 73 Billion kWh (10%).
addition to above, the installed capacity of During the year 2008-09 (2nd year of 11th
captive power plants of 1MW and above is Plan), the peak deficit was about 13,000
of the order of 24,986 MW at the end of MW (12%) and the average energy
2007-08.The energy generated from shortage in the country was about 86
captive power plants during the year Billion kWh (11%). During the year 2009-10
2007-08 was 90477 GWh. (3rd year of 11th Plan), the peak deficit was
about 15,157 MW (12.7%) and the average
Actual Power Supply Position energy shortage in the country was about
84 Billion kWh (10.1%).
The country has been facing growing
shortages over the past five years. During
Table 1.3
All-India Actual Power Supply Position (2010-11)
(April, 2010- March, 2011)
The details of peak and energy shortages 10th and 11th Plans are given in Table 1.4
in the country at the end of 7th, 8th, 9th, below.
Chapter 1: Page | 14 Introduction
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Table 1.4
Details of Power Supply Position during Past Plans
REGION/ PEAK PEAK SURPLUS/ SURPLUS/ ENERGY ENERGY SURPLUS/ SURPLUS/
STATE/ DEMAND AVAIL- DEFICIT DEFICIT REQUIRE- AVAIL- DEFICIT DEFICIT
U.T. (MW) ABILITY (MW) (%) MENT ABILITY (MU) (%)
(MW) (MU) (MU)
At the End of 7th Plan 40385 33658 -6727 -16.7 247762 228151 -19611 -7.9
(1989-90)
At the end of 8th Plan 63853 52376 -11477 -18.0 413490 365900 -47590 -11.5
(1996-97)
At the end of 9th Plan 78441 69189 -9252 -11.8 522537 483350 -39187 -7.5
(2001-02)
At the End Of 10th Plan 100715 86818 -13897 -13.8 690587 624495 -66092 -9.6
(2006-07)
11th Plan
2007-08 108866 90793 -18073 -16.6 705724 628016 -77708 -11.0
2008-09 109809 96685 -13124 -12.0 774,324 689,021 -85,303 -11.0
2009-10 119166 104009 -15157 -13.8 830594 746644 -83950 -10.1
2010-11 122287 110256 -12031 -9.8 861591 788355 -73236 -8.5
2011-12(April-December) 1,27,724 1,14,233 -13,491 -10.6 6,94,780 6,39,908 -54,872 -7.9
Annual Electric Load Factor Electric Load factor has remained close to
80% since 2000-01, primarily because of
The Annual Electric Load Factor is the prevailing shortages in the system and the
ratio of the energy availability in the load staggering measure adopted in the
system to the energy that would have various states particularly staggered
been required during the year if the supply to agriculture in groups. Since the
annual peak load met was incident on the shortages are rising, the Annual Electric
system through out the year. This factor Load Factor also illustrates an increasing
depends on the pattern of Utilization of trend and is depicted in the Exhibit 1.5 as
different categories of load. The Annual follows:
Exhibit 1.5
Variation of System Load Factor
SYSTEM LOAD FACTOR
85
84
SystemLoad Factor (%)
83.74
83
81.95
82 82.11
80.54 81.51 81.62
81 80.8
79.75
80
79.44
79 78.8
78
77
76
2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11
Year
Reserve Margin and Hydro Thermal Mix Reserve margin of a System is defined as
the difference between the Installed
Introduction Chapter 1: Page | 15
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Capacity and the peak load met as a The Hydro thermal mix in generation has
percentage of the Peak load met. This marginally increased from 25.01% in 2000-
factor depends on a number of 01 to about 26.19% as on 31st March 2007
parameters, major ones being the mode and thereafter has been decreasing and
of power generation i.e. hydro, thermal, stands at 23.13 as on 31st March, 2010.
renewable and the availability of the However the Reserve Margin has
generating stations. Reserve Margin in decreased from 34.61% in 2000-01 to 27.71%
other countries varies from 16% to 75%. in 2009-10. This is illustrated in the Exhibit
1.6 below:
Exhibit 1.6
Variation of Reserve Margin and Hydro Thermal Mix
Variation of Reserve Margin and Hydro Thermal Mix
36
33.1
34 32.66
34.61
32 31.25
31.18
30 30.28
30.31 28.16
%
28 27.92 27.71
26.19
26 25.01
26.13 26.01 26.19
24 25.1
24.81 24.9 23.13
22
20
2000- 2001- 2002- 2003- 2004- 2005- 2006- 2007- 2008- 2009- 2010-
01 02 03 04 05 06 07 08 09 10 11
Year
This reduction in Reserve Margin is on and O&M practices and higher efficiency
account of increase in thermal PLF from parameters of thermal machines. This is
69 % in 2000-01 to 77.5 % in 2009-10 on illustrated in the Exhibit 1.7 below:
account of improvement in technology
Exhibit1.7
Variation of Reserve Margin & PLF
Variation of Reserve Margin and Thermal PLF
90
77.5
80
72.7
69.9
70 76.8 78.6 77.2 75.1
74.8 73.6
69 72.2
60
%
50
The plant load factor of gas plant has also An encouraging feature is that this
increased from 48 % in 2000-01 to about decreasing Reserve Margin trend over the
65 % in 2009-10. The increase in PLF of gas years has been observed in spite of the
plants during 2009-10 has been due to hydro thermal mix has been varying
additional availability of gas from KG marginally. This implies that effect of
basin. The nuclear Load Factor however increased PLF of thermal stations is more
has reduced from 82 % in 2000-01 to 46.5% predominant in reducing the Reserve
in 2007-08 due to fuel shortage, but has Margin than the effect of hydro thermal
improved to 65.45% in 2009-10. However, mix of Installed Capacity to increase the
this has only marginal effect on the Reserve Margin.
reserve margin due to nuclear capacity
being a small component in Installed 1.6 12TH PLAN NATIONAL ELECTRICITY
Capacity. It is expected that with further PLAN
improvement in technology of thermal
power generation and higher unit size, as As mandated by the Act and the Policy,
also higher availability of gas and nuclear CEA has prepared the National Electricity
fuel, Reserve margin is further expected Plan for the 12th Plan, the perspective
to improve in future. Plan for the 13th Plan and a review of the
Status of implementation of the 11th Plan.
---+++---
Chapter 2
The capacity addition for the11th Plan was One of the major objectives of the
planned keeping in view the aims and National Electricity Policy is that demand
objectives of the National Electricity is to be fully met by the year 2012 with all
Policy. The capacity addition target set for peaking and energy shortages to be
the 11th Plan was 78,700 MW, about removed. In addition, the overall
quadruple of what could be actually availability of Installed Capacity is to be
th
achieved during the 10 Plan. Achieving enhanced to 85% and a Spinning Reserve
this huge target required timely of at least 5% needs to be created. Also,
placement of orders, augmentation of the per capita availability of electricity is
manufacturing capacity, skilled manpower to be increased to over 1000 kWh by 2012.
and construction machinery, timely Towards fulfilling these objectives and
statutory clearances and close monitoring considering the feasibility of
& coordination between the executing implementation of various projects to
agencies. This Chapter includes details of materialize during the 11th Plan, the
likely capacity addition and the efforts capacity addition target for the 11th Plan
being made to address the constraints was fixed at 78,700 MW as per details
being faced in timely execution of the given in the Exhibits 2.1 to 2.3 below:
power projects.
Table 2.1
th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 19
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Exhibit 2.1
Nuclear
Gas/LNG Hydro
3380
6843 15627
Lignite 4%
9% 20%
2280
3%
Coal
50570 Total: 78700 MW
64%
Exhibit 2.2
Private
15043
19%
Central
36874
47%
State
26783
34% Total: 78700 MW
projects totalling to 21,802 MW were likely made by Ministry of Power & CEA in
th
to slip from 11 Plan on account of various pursuing the developers and other Stake
reasons viz. delay in placement of order for holders. These additional projects total to
main plant, slow progress of civil work, 5,156 MW.
poor geology etc. Further, certain
additional projects which were originally Based on the above, capacity addition likely
th
not included in the 11 Plan target were during 11th plan as per Mid Term Appraisal
th
identified for benefits during 11 Plan by (MTA) was fixed as 62,374 MW. A Summary
expediting the process of project of the likely slippages and additional
implementation and compression of the projects identified is given in Table 2.2
construction schedule. This has been below:
possible through extraordinary efforts
Table 2.2
SUMMARY OF CAPACITY SLIPPING / ADDITIONAL CAPACITY FOR LIKELY BENEFITS DURING 11TH
PLAN
Figures in MW
11th Plan Capacity Addition Target (A) 78,700
Slipped From Target (B) 21,802
Balance Capacity (C) 56,898
Change in Capacity of projects as included in Target (D) 320
Increase in capacity of Anpara C 200
Increase in capacity of Sugen CCGT 20
Increase in capacity of Mettur Ext 100
Additional Capacity Likely during 11th Plan Outside Target (E) 5,156
Total Capacity (F) = (C+D+E) 62,374
Thus capacity addition likely during 11th capacity addition target of 62,374 MW is
Plan as per Mid Term Appraisal (MTA) is furnished in Table 2.3 below:
62,374 MW. A Sector wise Summary of this
Table 2.3
SUMMARY STATEMENT OF MID TERM APPRAISAL TARGET DURING THE 11TH PLAN
(SECTOR WISE AND TYPE WISE)
(Figs in MW)
HYDRO TOTAL THERMAL BREAKUP NUCLEAR TOTAL
THERMAL
CENTRAL SECTOR 2922 14920 13430 750 740 0 3380 21222
STATE SECTOR 2854 18501 14735 450 3316 0 0 21355
th
Chapter 2: Page | 22 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
2.4 ACTUAL/ LIKELY CAPACITY ADDITION likely capacity addition during 11th plan is
DURING 11TH PLAN about 52,063 MW. As against this the total
A capacity of 34,462 MW has been capacity already commissioned during 11th
commissioned during first four years of Plan is 45,965 MW. The latest status of
11th plan. Capacity addition programme commissioning of 11th Plan projects is as
during 2011-12 is 17,601 MW. Therefore the follows in Table 2.4.
Table 2.4
(Figures in MW)
Type
2007- 2008- 2009-10 * 2010-11* 2011- Total
08* 09* 12**
Hydro 2,423 969 39 690 1,990 6,111
Thermal 6,620 2,485 9,106 11,251 13,611 43,073
Nuclear 220 0 440 220 2,000 2,880
Total 9,263 3,454 9,585 12,161 17,601@ 52,063
* Commissioned @ 11503 MW already commissioned by Dec,2011
2.5 CAPACITY ADDITION FROM CAPTIVE and above) is about 32,900 MW. The
POWER PLANTS installed capacity has registered growth
of 4.4 % over the installed captive plant
Large number of captive plants including capacity of 31,517 MW as on 31st March,
co-generation power plants of varied 2010. The energy generation from
type and sizes exist in the country, which captive power plants (1MW and above)
are utilized in process industry and in- during the year 2009-10 was about 106.1
house power consumption. A number of billion units and registered a growth of
industries set up their captive plants to about 6.4 % in generation over
ensure reliable and quality power. Some generation of 99.7 billion units during
plants are also installed as stand-by units 2008-09. During the year 2008-09,
for operation only during emergencies surplus power of 8.4 BU from captive
when the grid supply is not available. was fed into the grid. Further, a capacity
Surplus power, if any, from captive addition of about 15,495 MW from
power plants could be fed into the grid Captive plants is expected by 2012 during
as the Electricity Act 2003, provides for the 11th Plan based on information
non-discriminatory open access. received from captive power plant
manufacturers, industries and other
As on 31st March, 2011, the Installed sources.
Capacity of Captive Power Plants (1MW
th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 23
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
In the 11th Plan, a capacity addition of 14,000 MW from renewable power sources has
been envisaged. Source- wise details are given in Table 2.5 below:
Table 2.5
11TH PLAN TENTATIVE TARGETS FOR GRID INTERACTIVE RENEWABLE POWER
(Figures in MW)
Total 14,000
Source MNRE
th
Chapter 2: Page | 24 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Exhibit 2.3
th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 25
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
competition. A major step has been that has signed an MOU with Bharat Forge Ltd.
a number of new manufacturers have to promote a JV Company for
came forward for setting up manufacture of castings, forgings, fittings
manufacturing facilities for Steam and high pressure piping required by the
Generators and Turbine Generators. These Power Sector.
include:
1. L&T-MHI NPC and L&T have also proposed to set up
2. Toshiba-JSW a JV for manufacturing of forgings, which
3. Alstom-Bharat Forge besides the nuclear plant requirements
4. Ansaldo Caldie-Gammon will also cater to thermal power projects.
5. BGR-Hitachi
6. Dov Construction agencies
7. Thermax-Babcock
8. Cethar vessals- The need to enhance the number of
construction agencies is also being
Based on production schedules of BHEL & stressed upon. A NTPC / BHEL JV has been
various JVs, it is felt that country is likely firmed to take up work related to
to have adequate manufacturing capacity Engineering, Procurement and
as far as main plant equipments are Construction (EPC) for power plants and
concerned. other Infrastructure projects. This JV has
recently obtained some orders for BOPs.
Enhancing Manufacturing Capacity of The latest methods of civil construction
BOP vendors with mechanical equipments and
manpower mobilisation needs to be
There were limited number of vendors for adopted.
BOP in the country. In recent past, it has
been noted that some of the plants could Critical Materials
not commissioned due to delay in Balance
of Plants, though works in main plants There does not appear to be shortage of
were completed. To overcome the key materials except CRGO steel, higher
problem, action has been taken to grade CRNGO & thick boiler steel plants.
sensitize the industry to the needs of
widening the vendor base for Balance of Cold Rolled Grain Oriented (CRGO) steel is
Plants like Coal Handling Plant, Ash most commonly used for manufacture of
Handling Plants, Water treatment plant transformer. There is worldwide shortage
etc. Industry has been impressed upon to of CRGO steel and non availability of good
enhance their manufacturing capacity as quality CRGO steel in India resulted in
well as encourage new entrepreneurs in delay in supply of transformers. To
these areas. Qualifying requirements for overcome such problems, efforts are
new vendors of BoPs have been relaxed being made towards timely availability of
to enable new vendors to qualify for Critical Key Inputs required for power
bidding. Standardisation of BoP systems system expansion. Measures are being
and mandating a central organisation to initiated to develop vendors for critical
maintain a dynamic data base with regard inputs like boiler quality plates, P91 piping,
to BoP order is under consideration. NTPC CRGO sheet steel. Advanced planning has
th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 27
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
th
Chapter 2: Page | 28 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
information can also be accessed of all the CEA is also going to implement IMS-II with
projects and programs in real-time, the following broad objectives:-
helping in determining which projects are
in danger of delay/late completion and More intensive and comprehensive IT
running over-budget. The system would based monitoring of execution of
also help to:- power projects.
To provide adequate redundancy in
ensure online updation of actual dates the existing data centre to enhance
of approval/release of each drawing by reliability and availability of the
engineering deptt. in a manner that system and to prepare a separate
can be accessed by all concerned. disaster recovery data centre.
enable online monitoring of those
transport/logistic activities which are Since the number of projects likely to
critical for timely commissioning of the be commissioned during 12th Plan will
projects. be large, IT based monitoring would
Monitor Poor projects performance be useful to monitor and generate
and poor sequencing of events. reports pertaining to ongoing
Project delays, cost overruns projects.
visibility into scheduling and material
delivery
Cost overruns, unknown implications Fuel Constraints
of material cost increases.
Inefficient use of resources, incorrect Some of the projects have been
mix of skills, project delay. delayed due to non-availability of
coal, gas and nuclear fuel.
All the projects were requested to Konaseema (445MW) and
implement IT based monitoring for Gauthami (464 MW) in A.P. which
effective project monitoring & were ready for commissioning
implementation. However, only a few were delayed due to non-
projects have implemented the same. This availability of gas. These projects
is to be required to be implemented in all have since been allocated gas from
the projects. KG D6 basin and been
commissioned during 2009-10.
Central Electricity Authority has RAPP Unit-5 & 6, 220 MW each
implemented Integrated Management have already been commissioned,
System-I (IMS-I) for centralized collection as imported nuclear fuel is now
of data from various power generations, available for these units.
transmission and distribution entities in
the country through web based interface. Contractual disputes
CEA has already approved the input A number of projects had awarded fixed
formats and reports pertaining to IMS-I price contracts during the 10th Plan period
and date is being obtained in the input which affected adversely due to
formats from respective organizations. unexpected increase in price of inputs.
CEA advised all the utilities not to award
fixed price contracts in future where the
th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 29
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
th
Chapter 2: Page | 30 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
above with sub critical technology and balance of plants are also under
were prepared by CEA with a view to preparation.
reduce the time in design &
engineering and implementation of
thermal projects. Standard
specifications of super critical units
---++---
th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 31
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Appendix-2.1
th
Chapter 2: Page | 32 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 33
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
th
Chapter 2: Page | 34 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
---+++---
th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 35
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
th
Chapter 2: Page | 36 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Chapter 3
DEMAND PROJECTIONS FOR ELECTRICITY
The National Electricity Policy also The 18th EPS draft report which has been
stipulates that CEA, while formulating the brought out now like encompasses
National Electricity Plan, would include various features for fulfilling the Aims and
the Short-term and the Long Term Objectives of the National/ State Policies
demand forecast for different Regions. framed by the Government(s). Due
consideration has been given while
3.1 DEMAND ASSESSMENT BY CENTRAL formulating the electricity demand
ELECTRICITY AUTHORITY – ELECTRIC forecasts to the promotion of high
POWER SURVEY (EPS REPORTS) efficiency and DSM measures in the
Agriculture, Industrial, Commercial
The Electricity Power Survey Committee is sectors as well as in domestic
constituted by CEA, with wide establishments. Future projections of the
representation from the Stake-holders in EPS have also been worked out based on
the Power Sector, to forecast the demand the T & D loss reduction targets assessed
for electricity both in terms of peak in consultation with various States/UTs.
electric load and electrical energy The Long Term Forecast is based on
requirement. CEA has been regularly reducing T & D losses to 23.2%, 18.9% and
bringing out the Electric Power Survey 15.4% by 2011-12, 2016-17 and 2021-22
Reports. The last Report by this respectively.
Committee is the 17th EPS which was
released in March 2007. This Report
TABLE 3.1
SCENARIOS OF ENERGY REQUIREMENT PROJECTIONS FOR 12th PLAN
Table 3.2
SCENARIOS OF ENERGY REQUIREMENT PROJECTIONS FOR 13th PLAN
th
Sc.-2 GR Sc.-3 GR Sc.-4 GR Sc.-5 GR Sc.-6 GR 18 EPS
Year Actual ER % Actual ER % Actual ER % Actual ER % Actual ER %
(upto (upto 2009- (upto (upto (upto
2009-10) 10) & 9% 2009-10) 2009-10) 2009-10)
with EPS GDP; 0.8 & 9% GDP; & 9% GDP; & 9% GDP;
GR Elasticity 0.8 0.95 0.9
Elasticity Elasticity Elasticity
Gwh Gwh Gwh Gwh Gwh
2017-18 1443326 7.1 1448595 7.2 1535902 7.2 1601133 8.6 1641345 8.1 1450982
2018-19 1544936 1552894 1646487 1738030 1774294 1552008
2019-20 1653700 1664703 1765034 1886631 1918012 1660783
2020-21 1770120 1784561 1892116 2047938 2073371 1778109
2021-22 1894736 1913050 2028348 2223037 2241314 1904861
The actual load factor in 2009-10 was 79.5 been considered while estimating the
%. In the past, the demand has not grown peak demand for 2016-17.
as anticipated and due to various other
reasons the decreasing trend of load A Summary of Energy Requirement and
factor as anticipated has not taken place. Peak demand in the various Scenarios
It would therefore be prudent that case of considered above and a Load factor of
GDP growth rate Scenarios with a modest 78% upto 2016-17 & 76% upto 2021-22 is
decline in load factor may be assumed. as follows:
Therefore, a load factor of about 78% has
Table 3.3
VARIOUS DEMAND SCENARIOS - ENERGY REQUIREMENT AND PEAK DEMAND (WITHOUT
EFFECT OF ENERGY CONSERVATION AND DSM MEASURES)
MW in Peak Demand may be made at end above Scenarios (except 18th EPS). The
of 12th Plan and a reduction of about Demand figures thus suitably modified are
15,000 MW in Peak Demand may be as given in the Table below:
made at end of 13th Plan in each of the
Table 3.4
3.3 RECOMMENDED DEMAND SCENARIO end use method is adopted to make these
forecasts. The demand forecasts make
Of the Scenarios detailed above, the projections of unrestricted demand while
demand corresponding to 18th EPS accounting for nominal impact of Energy
projections has been considered for Efficiency and Demand Side Management
Generation Planning studies to assess measures. Generation Planning Studies
capacity addition requirement for 12th based on unrestricted demand were
and 13th plan periods. considered to be prudent and desirable.
However, additional impact of aggressive
These demand estimates were considered measures & other initiatives of BEE which
since they are based on a detailed and take into account the structural changes
systematic approach of load projections taking place in the Power Sector on
by the Electric Power Survey Committee account of various initiatives of the
comprising of various stakeholders. Partial
Government have not been considered in Demand Projections as per 18th EPS draft
this Scenario. Report to be adopted by 12th and 13th
Plan end for the purpose of Generation
Planning Exercise are as follows:
Table 3.5
In the Integrated Energy Policy, Peak 18th EPS demand figures are to be
demand has been estimated assuming adopted for assessing the 12th
decreasing system load factor i.e. 76% up Plan Capacity addition
to 2010, 74% for 2011-12 to 2015-16, 72% for Programme and the 13th Plan
2016-17 to 2020-21 and beyond and these tentative capacity addition
demands are based on actual required, as the demand
consumption up to 2004-05 and it also assessment by the EPS is a
include Captive Demand. On the other through exercise based on end
hand 18th EPS demand projections have use method involving all
been based on actual demand up to Stakeholders.
2009-10 and this corresponds to demand
projections of utilities only. 18th EPS Optimum capacity addition for
demand projections also have taken into 12th and 13th Plans has been
account Demand Side Management and worked out considering 18th EPS
Energy Conservation measures as demand figures. Thereafter,
proposed by BEE. Therefore 18th EPS seasonal variation in demand has
demand projections may be considered also been estimated (peak and
for purpose of Generation Planning off-peak) to ensure that the
optimum capacity addition would
3.4 CONCLUSION meet the demand in all the
seasons.
---+++---
Chapter 4
Table 4.1
Weighted average specific emissions for fossil fuel-fired stations in FY 2008-09
(Figures in tCo2/MWh)
It may be mentioned that India’s Co2 increase primarily due to addition of more
emission rate (tCo2/Mwh) has been coal based power stations as compared to
reducing during the period 2003-04 to hydro stations. The trend of Weighted
2007-08. However, during the years 2008- Average Emission Rate is indicated in
09 and 2009-10 there has been a marginal following Table and Graph.
Table 4.2
Weighted Average Emission Rate (tCo2/Mwh) (incl. imports)
0.84
0.84 0.85
0.82
0.82
0.81
%
0.8
0.8 0.81
0.79
0.78 0.79
0.76
2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11
Year
Table-4.3
Various Unit Sizes and main parameters
Today 210/250 MW and 500 MW units coal based installed capacity. During the
form the backbone of Indian power 11th Plan, 4 nos of 660 MW supercritical
industry and constitute over 75 % of total units have already been commissioned
and few more super critical units are 4.2.2 Introduction of Clean Coal
expected during remaining period of 11th Technologies
Plan. During the 12th Plan, it is being
planned that the percentage of 660 MW Supercritical Technology:
and 800 MW unit sizes with Supercritical
technology would still increase further Supercritical technology is being
and during the 13th Plan, all new coal introduced to further enhance the
based capacity is likely to be on efficiency of coal fired thermal
supercritical technology only. generation. With the advancements in
metallurgy and availability of better
Power generation using gas turbines as materials, adoption of higher parameters
prime movers started in a big way around beyond the critical points has become
the world in early 1960s & 70s. This was possible. With the adoption of higher
basically due to advancement of parameters, efficiency gain of about 2 % is
technology as new and better heat possible over sub critical units, thereby,
resistant alloys were manufactured reducing emissions of CO2, NOx and SOx.
enabling higher firing temperatures, Depending on the steam parameters
consequently higher cycle efficiencies. adopted, supercritical technology can lead
The Gas Turbines (GTs) are normally to about 4 % coal savings and
manufactured in standard sizes based on corresponding reduction in emissions as
development of manufacturing compared to conventional sub-critical
technologies. GTs are now available up to units. Already many supercritical units of
250 MW range. The open cycle operation 660 and 800 MW are under construction
typically achieves a generation efficiency in Central, State and Private Sector. 4
of about 35% and about 53% in combined units of 660 MW each have already been
cycle mode. Since Gas Turbines use commissioned till November, 2011 and
cleaner fuels (natural gas, LNG, distillate other units are likely to be commissioned
oil, Naphtha), GT based plants are more during remaining period of 11th Plan. Initial
environment friendly mode of power supercritical units in the country were
generation. There is a need to encourage based on steam parameters of 246
setting up of gas based plants during 12th kg/cm2, 535/565 deg C at turbine inlet but
Plan and beyond to meet part of the some of the units which have recently
capacity addition requirements. started construction have adopted higher
steam temperatures of 565/593 deg C
The availability of gas, has, however been resulting in higher efficiency. Supercritical
a major issue adversely affecting the technology has been made mandatory for
operation of existing gas turbine stations Ultra Mega Projects being implemented.
at optimum capacity. Development of
new Gas based power plants will depend BHEL have already entered into
on the availability of natural gas in the collaboration with M/s Alstom and
country. Siemens for manufacturing of super-
critical boilers and turbo-generators
respectively. With the view to enhance
the indigenous manufacturing capability,
efforts have been made to attract
CFBC exist in the country and CFBC boilers 4.2.3 Renovation and Modernisation of
of upto 250 MW are being manufactured Thermal Power Stations
indigenously.
Background
IGCC Technology
Renovation and Modernisation (R&M)
The IGCC (integrated gasification and Life Extension (LE) of existing old
combined cycle) technology refers to power stations provide an opportunity to
power generation through gasification of get additional generation at low cost in
coal in gasifiers wherein the syngas is short gestation period. Besides
generated which after cleaning is used in generation improvement, it results in
gas turbine combined cycle systems to improvement of environmental emissions
generate power. Presently, efficiency of and improvement in availability, safety
IGCC plants internationally is comparable and reliability.
to those of supercritical plants but the
technology has the potential to achieve The Indian power sector has immense
higher efficiency than the conventional potential of reducing carbon dioxide
pulverized coal technology. emission by way of Renovation and
IGCC has been adopted internationally for Modernization schemes as some of the
very low ash coals or petroleum based plants are old and are operating at a low
fuels. With low gas and petroleum based efficiency. Benefits of CDM can be
fuels availability in the country, our efforts extended to overcome the fund
are mostly centered on technologies, constraints for the various R & M
which can use Indian high ash coals. schemes, especially for energy efficiency
International cooperation in developing improvements, as these schemes would
IGCC technology is being sought using mitigate carbon dioxide emissions and
typical high ash Indian coals which are save fossil fuel.
presently being used for power
generation in our Thermal Power Stations. R&M programme was initiated in 1984 as
Action has also been initiated for a centrally sponsored programme for 34
developing IGCC technology indigenously. numbers of thermal power stations
BHEL have been doing research on covering 163 thermal units in the country.
gasification of Indian coals and have The programme was successfully
signed an MOU with APGENCO to set up completed in the year 1992 and an
125 MW IGCC based plant. However, the additional generation of about 10,000
results of the past studies do not indicate MU/ annum was achieved.
any improvement in efficiency with IGCC
technology due to high ash contents of The Phase-II R&M programme for 44
Indian coal. numbers of thermal power stations was
taken up in the year 1990-91. Power
Finance Corporation (PFC) was to provide
loan assistance to the State Electricity
Boards (SEBs) for the R&M works.
However, this programme could not
progress as per schedule mainly due to
Table 4.4
LE/R&M Programme-Tentative Achievement during 11th Plan (2007 – 2012)
Programme for 12th Plan DVC units are 4 numbers (840 MW). In
addition to above, R&M works have also
Under 12th Plan, life extension works have been identified on 23 units (4971 MW)
been identified on 72 thermal units of during the 12th Plan, out of this 11units
total capacity 16532 MW. This includes 30 (4050 MW) are from NTPC, 9 units (291
units (5860 MW) from state sector and 42 MW) are from NEEPCO and balance from
units (10672 MW) from central sector. Out state power utilities.
of these 42 number central sector units, The broad details of the programme are
NTPC units are 35 numbers (9202 MW), given in Table 4.5 below:
NLC units are 3 numbers (630 MW) and
Table 4.5
R&M/ LE Programme of Thermal Units during 12th Plan (2012 – 2017) including Units
Slipping From 11th Plan.
Sl Particular State Sector Central Sector Total (State sector +
No. Central Sector)
No. of Capacity No. of Capacity No. of Capacity
units (MW) units (MW) units (MW)
1. LE works
(Programmed) 30 5860 42 10672.19 72 16532.19
(Slipping From 11th 16 2620 17 2527 33 5147
Plan)
Sub-Total 46 8480 59 13199.19 105 21679.19
2. R&M works
(Programmed)
(Slipping From 11th 03 630 20 4341 23 4971
Plan) 07 1530 - - 07 1530
Sub-Total
10 2160 20 4341 30 6501
Total
(Programmed) 33 6490 62 15013.19 95 21503.19
(Slipping From 11th 23 4150 17 2527 40 6677
Plan)
The list of units identified for life Potential candidate units for LE and R&M
extension and R&M during 12th Plan is works during 13th Plan (2017-2022)
enclosed in Appendix-4.1 and 4.2 The Summary of 13th Plan R&M/LE
respectively. programme is given in Table 4.6 below:
Table 4.6
13TH PLAN R&M/LE PROGRAMME (POTENTIAL CANDIDATE UNITS)
Name of the State Sector Central Sector Total identified units
Programme (State + Central Sector)
during 13th Plan
No. of Units Capacity No. of Units Capacity No. of Units Capacity
(MW) (MW) (MW)
LE
Coal 55 12130 16 3940 71 16070
Gas 6 672 5 765.71 11 1438
Sub Total 61 12802 21 4706 82 17508
R&M
Coal 16 3560 6 2420 22 5980
Gas 6 1172 6 1172
Sub Total 16 3560 12 3592 28 7152
Grand Total 77 16362 33 8298 110 24660
Future vision for R&M Programme Technical assistance to CEA by the World
Bank for the efficiency enhanced R&M
So far, R&M activities were confined to The World Bank is providing technical
old, small size units to sustain their assistance of US $ 1.1 million as a part of
operation, improve plant availability and GEF grant under Coal Fired Generation
extend their operating life. However, Rehabilitation Project to CEA for
such units are highly inefficient and beset addressing the barriers to energy efficient
with various operational problems. It is R&M in India. The scheme would be
aimed at gradually decommissioning such implemented through appointment of
units. consultants for carrying out studies
Today, 200/210/250MW/300MW and 500 related to reduction of barriers to R&M
MW units (61655 MW) consisting of 81 % of interventions in India, developing market
coal/lignite based installed capacity form for implementations and strengthening
the backbone of Indian Power sector. A institutional capacity at CEA in the field of
large number of 200/210 MW machines R&M.
and few 500 MW machines are in
operation for 15-25 years or more. Such 4.2.4 Renovation, Modernisation &
machines through efficiency integrated Uprating of Hydro Electric Power Projects
R&M provide a good opportunity for
performance enhancement through Renovation & Modernisation, Life
technology intensive R&M. Plant specific Extension and Up rating (RM&U) of
energy audit studies and techno-economic existing old hydro electric power projects
analysis are proposed to be carried out for is considered a good option, as this is cost
defining & implementation of efficiency effective and quicker to achieve than
integrated R&M/LE scheme. At present, setting up of green field hydro power
three power stations viz., Bokaro 'B' TPS projects.
(3x210MW), Kolaghat TPS (3x210MW) and
Nasik TPS Unit-3 (1x210MW) have been In order to augment the hydro generation
identified for efficiency integrated R&M and improve the availability of existing
study through bilateral cooperation with hydro power projects, Government of
German Government. Contract has been India has laid emphasis on R&M of various
awarded for preparation of Feasibility existing hydro electric power projects in
Study for all the above units. Further, few the country.
units such as Bandel TPS Unit-5 (210MW),
Koradi TPS Unit-1 (210MW) and Panipat Recognising the benefits of the R&M of
TPS (2x110MW) have also been identified hydroelectric power projects, Govt. of
for efficiency integrated R&M through India set up a National Committee in 1987
World Bank assistance. NIT for main plant and a Standing Committee in 1998
package for Bandel TPS Unit -5 has been thereafter, these have identified the
floated. The Energy Efficient R&M projects/ schemes to be taken up for
programme through external assistance is implementation under R&M. The National
intended to be taken up in few more units Perspective Plan document for R&M of
also. hydro electric power projects in the
country was also prepared in CEA during
the year 2000, incorporating the status of
Table 4.7
SUMMARY OF R&M, LIFE EXTENSION & UPRATING PROGRAMME AND ACHIEVEMENTS
FOR 11TH PLAN - HYDRO
Table 4.8
SUMMARY OF R&M AND LIFE EXTENSION PROGRAMME AND ACHIEVEMENTS FOR 12TH
PLAN – HYDRO
The details of Hydro projects considered Emissions. During the 11th Plan, 3,000 MW
for R&M during 12th plan are given in of capacity was targeted to be retired.
Appendix-4.3 This comprised of coal and lignite units of
unit size lesser than 100 MW.
4.2.5 Retirement of Old and Inefficient
Thermal Plants During the 12th Plan, a capacity of about
4,000 MW has been proposed to be
Retirement of Old and Inefficient thermal retired which includes the remaining units
Plants and replacing them with new and of coal & lignite under 100 MW size, gas
more efficient units is an effective way of plants more than 30 years old (1987 &
using the fuel and minimizing GHG
product of electricity generation into the CHP plants can be set up by the building
environment through cooling towers, flue owner as a captive power plant. Or
gas, or by other means. Combined Heat several such buildings can come together
and Power (CHP) captures the by-product and form a group-captive power plant.
heat for domestic or industrial heating Energy from such plants would be viewed
purposes. CHP is most efficient when the as ‘deemed renewable energy” and the
heat can be used on site or very close to it. generators allowed feed-in rights to
Overall efficiency is reduced when the export the excess power to the grid or to
heat must be transported over longer power exchanges.
distances.
An equal, if not greater, opportunity
Combined Cooling, Heating and Power presents itself in the use of (clean) natural
(CCHP) gas for such “within the fence” CCHP
plants. By carefully calibrating the
Large industrial units such as cement allocation and restricting the use of
plants, chemical industries, textile plants, natural gas to CHP applications that can
etc have, for several years, been drawing offer an efficiency of at least 60%.
power from their captive power plants.
Many of these units have also gone in for 4.2.8 Distributed Generation
waste heat recovery to meet the needs of
process steam or chilling. Distributed Generation is the location of
generation source at or near the load
In the last few years, there has also been a centre. Most often this generation would
rise in the number of large commercial be from Wind, biogas, Solar or gas/ diesel
buildings in the form of IT complexes, engines. The major advantages of
multiplexes, data centres, modern Distributed Generation are as follows:
airports, etc that have a tremendous Low transmission losses
amount of power requirement. As these Distributed flexible generation is
buildings are fully air-conditioned, the located close to consumption and
power intensity is extremely high. Due to load centres. Transmission losses
their concentrated load and the possibility are, therefore, minimised.
of using part of their air-conditioning
loads from the waste heat, they are ideal Low transmission investments
candidates for combined heat and cooling Transmission investments are
solutions. Also due to the varying nature minimised, compared with the Rs 1
of their loads, they demand a high degree crore/MW needed to build the
of operational flexibility. transmission line system associated
with a UMPP.
It should be made mandatory for
commercial consumers with loads Rapid capacity addition
exceeding 25 MW, to generate power in It enables a paradigm shift from
situ and to demonstrate a minimum large plants to more number of
thermal efficiency of 60%. Ensuring smaller plants, say in the range of
compliance will not be too difficult, given 25-200 MW. They enable quick
the incentives cited above. capacity addition. These plants
generally use standardised power
washing and yields. Economics of washing the capacity addition programme for the
can be improved by utilizing rejects for 12th and 13th Plans. Energy from these
producing electricity in Fluidized Bed sources, whenever available, has been
Combustion (FBC) boilers. Many private considered foremost to meet the
washeries are setting up small capacity demand. Additional capacity from
FBC units based on washery rejects. conventional sources has been assessed
to meet the balance load of the system.
At present out of a total coal
consumption of about 323 million tones, 4.3.1 Potential of Renewables
washed coal accounts for a mere 33
million tones. With the allocation of coal Thrust is being accorded to development
blocks to private and Govt. power utilities of Renewable Energy Sources which are
for coal mining, washing is set to increase not only a renewable source but are also
rapidly. The large size supercritical units environmentally benign. The Ministry of
are slated to use washed /imported coal. Non-conventional Energy Sources has
projected the potential for Wind energy
4.3 GENERATION FROM RENEWABLE itself to be of the order of 45,000 MW.
ENERGY SOURCES IN INDIA Other forms of non-conventional energy
sources are bio-mass, small, mini and
Use of Renewable Energy Sources is a far micro hydro (using canal falls as cost of
better option than Conventional Energy civil works is minimal), tidal power and
Sources as they are sustainable and cause solar energy. These may also be viable as
comparatively very little pollution. distributed generation to meet the
However at a particular instant their demands of remote locations where
quantity is limited and these are not extension of grid may be difficult or very
capable of meeting the energy costly. In the short term these sources
requirement of the Utility. Also these could be exploited for bridging the
normally provide non despatchable demand-supply gap especially in
energy, dependent on the vagaries of geographically dispersed areas. Today the
nature and thus can not be relied upon to capital cost of non-conventional energy is
meet the peak demand of the system. higher than that of conventional sources
They generally run at an overall PLF of 15% on per kW basis. However, their viability
to 20% (PLF based on total capacity and could be established if financial cost
sum of energy from all the renewable benefit analysis is replaced by economic
sources). In addition, the power cost benefit analysis.
producing technologies are expensive As per the information furnished by
thereby increasing the tariff of power MNRE, the total estimated medium-term
produced. However due to their inherent potential (2032) for power generation
merits, development of these power from renewable energy sources such as
sources are being encouraged and power wind, small hydro, solar, waste to energy
thus generated is being fed into the Grid. and biomass in the country is about
Therefore, renewable energy sources 1,83,000 MW as given in Table 4.9 below:
have been considered while drawing up
Table 4.9
(Figures in MW)
Sources / Systems Estimated Mid-Term (2032) Potential
Wind Power 45,000
Bio-Power (Agro residues & 61,000
Plantations)
Co-generation Baggasse 5,000
Small Hydro (up to 25 MW) 15,000
Waste to Energy 7,000
Solar Photovoltaic 50,000*
TOTAL 1,83,000
*As per Objective of the National Solar Mission,1,00,000 MW shall be the Installed Solar generation capacity by
2030 and 2,00,000 MW by 2050.
4.3.2 Development of Renewable Energy for supplying power to the Utility grid as
Sources well as in Stand-alone systems. It
empowers the State Electricity Regulatory
Renewable Energy has been appropriately Commissions (SERCs) to promote
given the central place in India’s National renewable energy and specify, for
Action Plan on Climate Change. purchase of electricity from renewable
Intergovernmental Panel on Climate sources a percentage of the total
Change(IPCC) in its Fourth Assessment consumption of electricity in the area of a
Report on ‘Mitigation of Climate Change’ distribution licensee. National Electricity
has observed that technologies are Policy also states that non-conventional
available for mitigating the climate energy sources have to be exploited fully
change, however these require and promotional measures have to be
appropriate Policy and financial support. taken for development of technologies
Due to its vast market potential for and sustainable development of these
renewable energy projects, and a sources by SERCs. The tariff policy also
relatively well-developed industrial, mandates minimum percentage of energy
financing and business infrastructure, from renewable sources to be made
India is perceived as an excellent country applicable for the tariffs to be determined
for Clean Development Mechanism (CDM) by SERCs. Thus the Electricity Act,
projects. National renewable energy plans National Electricity Policy and the Tariff
offer ample opportunity for CDM projects Policy of Government of India mandate
and technological innovations. CDM and development of renewable resources
the emerging carbon market in general through a system of obligation of a
have potential to contribute to the distribution company to purchase
financial viability of renewable energy electricity from such sources. These
projects, although not necessarily making Initiatives provide a major boost for
them fully viable. promotion of the renewable energy
sector in India.
The Electricity Act 2003 also recognises
the role of renewable energy technologies
The total Installed capacity from During the 12th and 13th Plans, capacity
renewable energy sources at the end of addition is expected to be more than the
10th Plan i.e. as on 31.03.2007 was 7,761 11th Plan capacity addition from renewable
MW which comprises of 976 MW in sources. A number of Incentives have
State sector and 6785 MW in the Private been given by MNRE for setting up of
sector . The Present Installed capacity as Solar and Wind based power plants.
on 31.03.2011 is 18,456 MW from RES Therefore considering 14,000 MW cap
sources. India ranks fifth in the world in addition from renewable during the 11th
terms of installed capacity of wind turbine Plan. During the 12th and 13th Plans, the
power plants. The capacity addition target capacity addition from renewables is
for 11th Plan from renewable sources is expected to be about 18,700 MW and
14,000 MW (not including solar capacity as 31,000 MW respectively. The same is
proposed under the Solar Mission) illustrated in Exhibit below:
arrays. Solar cells are often electrically then be converted to electrical energy by
connected and encapsulated as a module. turbine.
PV modules often have a sheet of glass on
the front (sun up) side, allowing light to The Salient Features of Comparison of the
pass while protecting the semiconductor 3 thermal technologies i.e. Parabolic
wafers from the elements (rain, hail, etc.). Trough, Power Tower and Dish/Engine are
Solar cells are also usually connected in as follows:
series in modules, creating an additive Towers and troughs are best
voltage. Connecting cells in parallel will suited for large, grid connected
yield a higher current. Modules are then power projects in the 30-200 MW
interconnected, in series or parallel, or size wheras dish/engine systems
both, to create an array with the desired are modular and can be used in
peak DC voltage and current. single dish applications or
To make practical use of the solar- grouped in dish farms to create
generated energy, the electricity is most large multi- megawatt projects.
often fed into the electricity grid using
Parabolic troughs are the most
inverters (grid-connected PV systems); in
mature solar power technology
stand alone systems, batteries are used to
available today and the
store the energy that is not needed
technology most likely to be used
immediately. PV has mainly been used to
for near term deployment. Proven
power small and medium-sized
technology waiting for an
applications, from the calculator powered
opportunity to be developed.
by a single solar cell to off-grid homes
powered by a photovoltaic array. For Power towers, with low cost and
large-scale generation, CSP plants have efficient thermal storage promise
been the norm. However recently multi- to offer despatchable, high
megawatt PV plants are becoming capacity factor, solar only power
common. plants in the near future. However
Newer alternatives to standard crystalline they require the operability and
silicon modules include casting wafers maintainability of the molten-salt
instead of sawing, thin film (CdTe, CIGS, technology to be demonstrated
amorphous Si, microcrystalline Si), and the development of low cost
concentrator modules, 'Sliver' cells, and heliostats
continuous printing processes. Due to
The modular nature of dishes
economies of scale solar panels get less
allows them to be used in smaller,
costly as people use and buy more — as
high value applications. However
manufacturers increase production to
the dish/engine systems require
meet demand, the cost and price is
the development of at least one
expected to drop in the years to come.
commercial engine and the
development of a low cost
4.4.5 Solar Thermal Technology
concentrator
In this technology, the solar energy is
converted into thermal energy, which can
4.4.7 Mission strategy (phase 1 and 2) Obligation (RPO) mandated for power
utilities, with a specific solar component.
The first phase will announce the broad This will drive utility scale power
policy frame work to achieve the generation, whether solar PV or solar
objectives of the National Solar Mission by thermal. The Solar Purchase Obligation
2022. The policy announcement will create will be gradually increased while the tariff
the necessary environment to attract fixed for Solar power purchase will decline
industry and project developers to invest over time.
in research, domestic manufacturing and B. The below 80°C challenge – solar
development of solar power generation collectors
and thus create the critical mass for a The Mission in its first two phases will
domestic solar industry. The Mission will promote solar heating systems, which are
work closely with State Governments, already using proven technology and are
Regulators, Power utilities and Local Self commercially viable. The Mission is setting
Government bodies to ensure that the an ambitious target for ensuring that
activities and policy framework being laid applications, domestic and industrial,
out can be implemented effectively. Since below 80 °C are solarised. The key
some State Governments have already strategy of the Mission will be to make
announced initiatives on solar, the Mission necessary policy changes to meet this
will draw up a suitable transition objective:
framework to enable an early and • Firstly, make solar heaters mandatory,
aggressive start-up. through building byelaws and
A. Utility connected applications: incorporation in the National Building
constructing the solar grid Code,
The key driver for promoting solar power • Secondly, ensure the introduction of
would be through a Renewable Purchase effective mechanisms for certification and
Initiatives and Measures for GHG Mitigation Chapter 4: Page | 63
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
rating of manufacturers of solar thermal solar lights for lighting purposes would be
applications, promoted in settlements without access
• Thirdly, facilitate measurement and to grid electricity and since most of these
promotion of these individual devices settlements are remote tribal settlements,
through local agencies and power utilities, 90% subsidy is provided. The subsidy and
and the demand so generated would be
• Fourthly, support the upgrading of leveraged to achieve indigenization as
technologies and manufacturing well as lowering of prices through the
capacities through soft loans, to achieve scale effect. For other villages which are
higher efficiencies and further cost connected to grid , solar lights would be
reduction. promoted through market mode by
C. The off-grid opportunity - lighting enabling banks to offer low cost credit.
homes of the power- deprived poor: • Set up stand alone rural solar power
A key opportunity for solar power lies in plants in special category States and
decentralized and off-grid applications. In remote and difficult areas such as
remote and far-flung areas where grid Lakshadweep, Andaman & Nicobar
penetration is neither feasible nor cost Islands, Ladakh region of J&K. Border
effective, solar energy applications are areas would also be included.
cost-effective. They ensure that people
with no access, currently, to light and Promotion of other off grid solar
power, move directly to solar, leap- applications would also be encouraged.
frogging the fossil fuel trajectory of This would include hybrid systems to meet
growth. The key problem is to find the power, heating and cooling energy
optimum financial strategy to pay for the requirements currently being met by use
high-end initial costs in these applications of diesel and other fossil fuels. These
through appropriate Government devices would still require interventions to
support. bring down costs but the key challenge
Currently, market based and even micro- would be to provide an enabling
credit based schemes have achieved only framework and support for entrepreneurs
limited penetration in this segment. The to develop markets.
Government has promoted the use of Solar energy to power computers to assist
decentralized applications through learning in schools and hostels,
financial incentives and promotional Management Information System (MIS)
schemes. While the Solar Mission has set a to assist better management of forests in
target of 1000 MW by 2017, which may MP, powering milk chilling plants in
appear small, but its reach will add up to Gujarat, empowering women Self Help
bringing changes in millions of Groups (SHGs) involved in tussar reeling in
households. The strategy will be learn Jharkhand, cold chain management for
from and innovate on existing schemes to Primary Health Centres (PHCs) are some
improve effectiveness. The Mission plans examples of new areas, being tried
to: successfully in the country. The Mission
• Provide solar lighting systems under the would consider up to 30 per cent capital
ongoing remote village electrification subsidy (which would progressively
programme of MNRE to cover about decline over time) for promoting such
10,000 villages and hamlets. The use of innovative applications of solar energy
Chapter 4: Page | 64 Initiatives and Measures for GHG Mitigation
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
4.4.9. Policy and regulatory framework for fixing feed-in-tariff for purchase of
Solar power taking into account current
The objective of the Mission is to create a cost and technology trends. These will be
policy and regulatory environment which revised on an annual basis. The CERC has
provides a predictable incentive structure also stipulated that Power Purchase
that enables rapid and large-scale capital Agreement that utilities will conclude with
investment in solar energy applications Solar power promoters, should be for a
and encourages technical innovation and period of 25 years.
lowering of costs.
In order to enable the early launch of
Although in the long run, the Mission “Solar India” and encourage rapid scale
would seek to establish a sector-specific up, a scheme is being introduced in
legal and regulatory framework for the cooperation with the Ministry of Power,
development of solar power, in the the NTPC and the Central Electricity
shorter time frame, it would be necessary Authority, which would simplify the off-
to embed the activities of the Mission take of solar power and minimize the
within the existing framework of the financial burden on Government.
Electricity Act 2003. The Electricity Act
already provides a role for renewables but Many investors are willing to set up solar
given the magnitude and importance of based power plants. However, sale of
the activities under the Mission, it would power by the IPPs may be an issue due to
be necessary to make specific the high cost of power and realization of
amendments. The National Tariff Policy tariff for the same from the distribution
2006 mandates the State Electricity companies.
Regulatory Commissions (SERC) to fix a
minimum percentage of energy purchase In order to incentivise setting up of a large
from renewable sources of energy taking number of Solar Power Projects, while
into account availability of such resources minimizing the impact on tariff various
in the region and its impact on retail tariff. alternatives were explored. One of the
National Tariff Policy, 2006 would be options is to bundle solar power along
modified to mandate that the State with power out of the cheaper
electricity regulators fix a percentage for unallocated quota of Central stations and
purchase of solar power. The solar power selling this bundled power to state
purchase obligation for States may start distribution utilities at the CERC regulated
with 0.25% in the phase I and to go up to price. This will bring down the gap
3% by 2022. This could be complemented between average cost of power and sale
with a solar specific Renewable Energy price of power. For the purpose of
Certificate (REC) mechanism to allow bundling, power has to be purchased by
utilities and solar power generation an entity and re-sold to the state power
companies to buy and sell certificates to distribution utilities. Such function can be
meet their solar power purchase done only by a trading company/ Discoms,
obligations. as per the existing statutory provisions.
Nigam Ltd. (NVVN). NVVN will be The Mission will encourage rooftop solar
designated as nodal agency by the PV and other small solar power plants,
Ministry of Power (MoP) for entering into connected to LT/11 KV grid, to replace
a Power Purchase Agreement (PPA) with conventional power and diesel-based
Solar Power Developers. The PPAs shall be generators. Operators of solar PV rooftop
signed with the developers who will be devices will also be eligible to receive the
setting up Solar Projects within next three feed-in tariff fixed by the CERC, both on
years (i.e. upto March 2013) and are the solar power consumed by the
connected to the grid at 33 KV level and operator and the solar power fed into the
above. The PPAs will be valid for a period grid. Utilities will debit/credit the operator
of 25 years. For each MW of solar power for the net saving on conventional power
installed capacity for which PPA is signed consumed and the solar power fed into
by NVVN, MOP shall allocate to NVVN an the grid, as applicable. A Generation
equivalent amount of MW capacity from Based Incentive will be payable to the
the unallocated quota of NTPC stations. utility to cover the difference between the
solar tariff determined by CERC, less the
NVVN will bundle this power and sell this base price of Rs. 5.50/kWh with 3% p.a.
bundled power at a rate fixed as per CERC escalation. The metering and billing
regulations. In case of significant price arrangements between the utility and the
movement in the market rate, the rooftop PV operator will be as per
Government will review the situation. guidelines/regulations of the appropriate
When NVVN supplies the bundled power commission.
to distribution utilities, those distribution
utilities will be entitled to use part of the State Governments would also be
bundled power to meet their RPO, as encouraged to promote and establish
determined by the regulatory authorities. solar generation Parks with dedicated
The CERC may issue appropriate infrastructure for setting up utility scale
guidelines in this regard. At the end of the plants to ensure ease of capacity creation.
first phase, well-performing utilities with
proven financial credentials and FISCAL INCENTIVES
demonstrated willingness to absorb solar It is also recommended that custom
power shall be included in the Scheme, in duties and excise duties concessions/
case it is decided to extend it into Phase II. exemptions be made available on specific
capital equipment, critical materials,
The requirement of phased indigenization components and project imports.
would be specified while seeking
development of solar power projects 4.4.9 Solar Manufacturing in India
under this scheme. The size of each One of the Mission objectives is to take a
project would be determined so as to global leadership role in solar
make phased indigenization feasible. The manufacturing (across the value chain) of
tariff and tax regime for key components leading edge solar technologies and
and segments would be suitably fine target a 4-5 GW equivalent of installed
tuned so as to promote the process of capacity by 2020, including setting up of
indigenization. dedicated manufacturing capacities for
poly silicon material to annually make
about 2 GW capacity of solar cells. India (both crystalline and thin film) and
already has PV module manufacturing poly-silicon manufacturing among
capacity of about 700 MW, which is others. The combined capacity
expected to increase in the next few projected by these 15 companies
years. The present indigenous capacity to could result in the production of 8-10
manufacture silicon material is very low; GW solar power by the year 2022
however, some plants are likely to be set which would be sufficient for
up soon in public and private sector. meeting the Mission targets even
Currently, there is no indigenous after accounting for exports.
capacity/capability for solar thermal It is also recommended that solar
power projects; therefore new facilities components be covered under the
will be required to manufacture Bureau of Energy Efficiency’s star
concentrator collectors, receivers and rating programme to ensure high
other components to meet the demand standards.
for solar thermal power plants.
Similar incentives will be required for
To achieve the installed capacity target, manufacture of CSP systems and their
the Mission recommends the following: components. A Committee may be set up
to formulate a policy for promotion of
• Local demand creation: The 20 GW plan solar thermal manufacture in the country.
supported with right level of incentives
for solar generation coupled with large • Ease of doing business: In consultation
government pilot/demonstration with States, create a single window
programs will make the Indian market clearance mechanism for all related
attractive for solar manufacturers permissions.
• Infrastructure & ecosystem enablers:
• Financing & Incentives: SEZ like Create 2-3 large solar manufacturing tech
incentives to be provided to the parks consisting of manufacturing units
manufacturing parks which may include: (across the solar value chain), housing,
Zero import duty on capital offices, and research institutes. These will
equipment, raw materials and excise have 24x7 power and water supply and
duty exemption will likely need to be located near large
Low interest rate loans, priority urban centres with good linkages to ports
sector lending and airports to ensure rapid access to
Incentives under Special Incentive imported raw materials and high quality
Package (SIPs) policy to set up engineering talent.
integrated manufacturing plants; (i) 4.4.11 Research and Development
from poly silicon material to solar This Mission will launch a major R&D
modules; and (ii) thin film based programme in Solar Energy, which will
module manufacturing plants. . focus on improving efficiency in existing
Under the SIP scheme of the applications, reducing costs of Balance of
Department of Information Systems, testing hybrid co-generation and
Technology, there are 15 applications addressing constraints of variability,
in the domain of solar photovoltaic, space-intensity and lack of convenient and
which includes cell manufacturing, cost-effective storage.
capacity of 1 lakh MW each in the 12th and Education and Training under the
13th Plan. This entire capacity has huge Ministry of Labour has agreed to
potential to accommodate electricity introduce training modules for
generated from solar installations in real course materials for technicians in
time without the use of storage devices. order to create a skilled workforce
which could service and maintain
4.4.14 Human Resource Development solar applications. MNRE has
The rapid and large-scale diffusion of Solar already initiated this activity with
Energy will require a concomitant increase the Ministry of Labour and a short
in technically qualified manpower of term training module is to be
international standard. Some capacity introduced during the current
already exists in the country, though academic session. In addition,
precise numbers need to be established. industry is also working with some
of the ITIs to create a skilled work
However, it is envisaged that at the end of force.
Mission period, Solar industry will employ
at least 100,000 trained and specialized A Government Fellowship
personnel across the skill spectrum. These programme to train 100 selected
will include engineering management and engineers / technologies and
R&D functions. scientists in Solar Energy in world
class institutions abroad will be
The following steps may be required for taken up. This may need to be
Human Resource Development: sustained at progressively
declining levels for 10 years. This
IITs and premier Engineering could be covered under the
Colleges will be involved to design ongoing bilateral programmes.
and develop specialized courses in Institution to institution
Solar Energy, with financial arrangements will also be
assistance from Government. developed. Fellowships will be at
These courses will be at B. Tech, M. two levels (i) research and (ii)
Tech and Ph. D level. Some of the higher degree (M. Tech) in solar
IITs, Engineering Colleges and energy. MNRE is already
Universities are teaching solar implementing a fellowship
energy at graduation and post programme in this regard, which
graduation level. Centres for will be expanded to include
Energy studies have been set up by students from a larger number of
some of the IITs and engineering academic institutions. This may be
colleges. These initiatives will be done in consultation with industry
further strengthened. In addition, a to offer employment
countrywide training programme opportunities.
and specialized courses for
technicians will be taken up to Setting up of a National Centre for
meet the requirement of skilled Photovoltaic Research and Education at
manpower for field installations IIT, Mumbai, drawing upon from
and after sales service network. Department of Energy Science and
The Directorate General of
Initiatives and Measures for GHG Mitigation Chapter 4: Page | 73
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Engineering and its Centre for Excellence areas of (i) Feasibility of solar generation
in Nano-Electronics is considered. with respect to space availability, any
constraints foreseen and application areas
4.4.15 Task Force set up by MNRE (ii) Solar technology options and techno-
A Task Force has been set up by MNRE economics (iii) Arrangement for
under the Chairmanship of Chairperson, connectivity and metering of solar plants.
CEA to examine technical issues related
to the feasibility of integrating solar 4.4.16 Fund Requirement
power plants with thermal/ hydro-electric One of the major bottlenecks in the
power plants and connectivity of solar development of Solar Installations is the
rooftops systems with the grid. The Task high Capital cost which results in high
Force comprises of representatives of tariff as compared to power generated
MNRE, MOP, CEA, NTPC, NHPC, BHEL, using Conventional Energy Resources. It
CEL, RRECL, RRUVNL, GSECL, GEDA and has been estimated that the capital cost
KPCL. The objective of the Task Force is to of solar installations is about Rs
prepare implementable project reports 20crs/MW, with Solar thermal being
for setting up solar plants at power plants, marginally lesser i.e. about Rs 18 crs/MW.
one each at coal based, gas based and However it is expected that the cost will
hydro power stations. The project report decline as the technology gets established
shall include complete bill of material, cost and the quantum of orders increase with
estimates, methodology of accounting time. It is expected that the cost which
energy and to establish the commercial would be about Rs 20 crs/MW during the
viability. 11th Plan, will reduce to Rs 16crs/MW
Three Subgroups have been formed under during the 12th Plan and about Rs
the Task Force to look into the specific 12crs/MW during the 13th Plan.
Table 4.11
First Phase Second Phase Third Phase
(2008-13) (2013-17) (2017-22)
Installed Capacity (Solar) in 1000 10000 20,000
MW
Capacity Addition during Plan 1000 9000 10,000
in MW
Funds reqt. per MW (Rs crs) 20 16 12
Funds Requirement (Rs crs) 20,000 1,44,000 1,20,000
As per JNNSM, the fund requirements for The Mission strategy has kept in mind the
the Mission would be met from the two-fold objectives, to scale-up
following sources or combinations: deployment of solar energy and to do this
i) Budgetary support for the activities keeping in mind the financial constraints
under the National Solar Mission and affordability challenge in a country
established under the MNRE; where large numbers of people still have
ii) International Funds under the UNFCCC no access to basic power and are poor
framework, which would enable upscaling and unable to pay for high cost solutions.
of Mission targets. The funding requirements and
Chapter 4: Page | 74 Initiatives and Measures for GHG Mitigation
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
---+++---
Appendix-4.1
(Sheet 1 of 5)
LIST OF THERMAL UNITS PROGRAMMED FOR LIFE EXTENSION WORKS DURING 12TH PLAN
1. STATE SECTOR
Sl. State Name of Utility Name of Station Unit Year of Capacity Make LMZ / Remarks
No. No. Comm. (MW) Boiler TG KWU
Northern Region
th
1 U.P. UPRVUNL Obra 11 1977 200 BHEL BHEL LMZ Slip from 11 Plan
th
2 U.P. UPRVUNL Obra 12 1981 200 BHEL BHEL LMZ Slip from 11 Plan
th
3 U.P. UPRVUNL Obra 12 1982 200 BHEL BHEL LMZ Slip from 11 Plan
th
4 U.P. UPRVUNL Parichha 1 1984 110 BHEL BHEL Slip from 11 Plan
th
5 U.P. UPRVUNL Parichha 2 1985 110 BHEL BHEL Slip from 11 Plan
th
6 U.P. UPRVUNL Panki 3 1976 105 BHEL BHEL Slip from 11 Plan
th
7 U.P. UPRVUNL Panki 4 1977 105 BHEL BHEL Slip from 11 Plan
th
8 U.P. UPRVUNL Anpara”A” 1 1986 210 BHEL BHEL KWU Slip from 11 Plan
th
9 U.P. UPRVUNL Anpara”A” 2 1986 210 BHEL BHEL KWU Slip from 11 Plan
th
10 U.P. UPRVUNL Anpara”A” 3 1988 210 BHEL BHEL KWU Slip from 11 Plan
Sub Total 10 1660
th
11 Punjab PSPCL Ropar 1 1984 210 BHEL BHEL KWU Slip from 11 Plan
th
12 Punjab PSPCL Ropar 2 1985 210 BHEL BHEL KWU Slip from 11 Plan
th
13 Punjab PSPCL Bathinda 4 1979 110 BHEL BHEL Slip from 11 Plan
Sub Total 3 530
14 Haryana HPGCL Panipat 3 1985 110 BHEL BHEL Being taken up under W.Bank
15 Haryana HPGCL Panipat 4 1985 110 BHEL BHEL EE R&M programme
Sub Total 2 220
Boiler TG
16 Rajasthan RRVUNL Kota 1 1983 110 BHEL BHEL
17 Rajasthan RRVUNL Kota 2 1983 110 BHEL BHEL
Sub Total 2 220
Sub Total Northern Region 17 2630
Western Region
18 Gujarat GSECL Ukai 3 1979 200 BHEL BHEL LMZ
Appendix-4.1
(Sheet 2 of 5 )
Appendix-4.1
(Sheet 3 of 5 )
Appendix-4.1
(Sheet 4 of 5 )
th
10 NTPC Singrauli STPS 1 1982 200 BHEL BHEL LMZ Slip from 11 Plan
th
11 NTPC Singrauli STPS 2 1982 200 BHEL BHEL LMZ Slip from 11 Plan
12 NTPC Singrauli STPS 3 1983 200 BHEL BHEL LMZ
13 NTPC Singrauli STPS 4 1983 200 BHEL BHEL LMZ
14 NTPC Singrauli STPS 5 1984 200 BHEL BHEL LMZ
15 NTPC Singrauli STPS 6 1986 500 BHEL BHEL KWU
16 NTPC Singrauli STPS 7 1987 500 BHEL BHEL KWU
th
17 NTPC Korba STPS 1 1983 200 BHEL BHEL KWU Slip from 11 Plan
18 NTPC Korba STPS 2 1983 200 BHEL BHEL KWU
19 NTPC Korba STPS 3 1984 200 BHEL BHEL KWU
Sl. Name of Station Unit Year of Capacity Make LMZ / KWU Remarks
No. Name of Utility No. Comm. (MW) Boiler TG
20 NTPC Korba STPS 4 1987 500 BHEL BHEL KWU
21 NTPC Korba STPS 5 1988 500 BHEL BHEL KWU
22 NTPC Korba STPS 6 1989 500 BHEL BHEL KWU
th
23 NTPC Ramagundam STPS 1 1984 200 Ansaldo Ansaldo KWU Slip from 11 Plan
24 NTPC Ramagundam STPS 2 1984 200 Ansaldo Ansaldo KWU
25 NTPC Ramagundam STPS 3 1984 200 Ansaldo Ansaldo KWU
26 NTPC Ramagundam STPS 4 1988 500 BHEL BHEL KWU
27 NTPC Ramagundam STPS 5 1989 500 BHEL BHEL KWU
28 NTPC Ramagundam STPS 6 1989 500 BHEL BHEL KWU
29 NTPC Farakka Stage-I 1 1986 200 BHEL BHEL KWU
30 NTPC Farakka Stage-I 2 1986 200 BHEL BHEL KWU
31 NTPC Farakka Stage-I 3 1987 200 BHEL BHEL KWU
32 NTPC Vindhyachal 1 1987 210 USSR USSR LMZ
33 NTPC Vindhyachal 2 1988 210 USSR USSR LMZ
34 NTPC Vindhyachal 4 1990 210 USSR USSR LMZ
35 NTPC Vindhyachal 5 1990 210 USSR USSR LMZ
36 NTPC Rihand 1 1988 500 ICL (UK) GEC(UK) KWU
37 NTPC Rihand 2 1989 500 ICL (UK) GEC(UK) KWU
Appendix-4.1
(Sheet 5 of 5 )
Sl. Name of Utility Name of Station Unit No. Year of Capacity Make LMZ / Remarks
No. Comm. (MW) Boiler TG KWU
th
38 NTPC Dadri GT GT-1 1992 131 SIEMENS Slip from 11 Plan
th
39 NTPC Dadri GT GT-2 1992 131 SIEMENS Slip from 11 Plan
th
40 NTPC Dadri GT GT-3 1992 131 SIEMENS Slip from 11 Plan
41 NTPC Dadri GT GT-4 1992 131 SIEMENS
th
42 NTPC Auraiya GT GT-1 1989 111.19 MHI, Japan Slip from 11 Plan
th
43 NTPC Auraiya GT GT-2 1989 111.19 MHI, Japan Slip from 11 Plan
th
44 NTPC Auraiya GT GT-3 1989 111.19 MHI, Japan Slip from 11 Plan
45 NTPC Auraiya GT GT-4 1989 111.19 MHI, Japan
th
46 NTPC Kawas GT GT-1 1992 106 GE Slip from 11 Plan
th
47 NTPC Kawas GT GT-2 1992 106 GE Slip from 11 Plan
th
48 NTPC Kawas GT GT-3 1992 106 GE Slip from 11 Plan
49 NTPC Kawas GT GT-4 1992 106 GE
th
50 NTPC Gandhar GT GT-1 1994 131 ABB Slip from 11 Plan
th
51 NTPC Gandhar GT GT-2 1994 131 ABB Slip from 11 Plan
52 NTPC Gandhar GT GT-3 1994 131 ABB
53 NTPC Faridabad CCPS GT-1 1999 143 Siemens
54 NTPC Faridabad CCPS GT-2 1999 143 BHEL
55 NTPC Rajiv Gandhi CCPS GT-1 1998 115 GE
56 NTPC Rajiv Gandhi CCPS GT-2 1999 115 BHEL
57 NTPC Anta GTPS ST-1 1990 149 ABB
58 NTPC Auraiya CCPS ST-1 1989 109 MHI, Japan
59 NTPC Auraiya CCPS ST-2 1990 109 MHI, Japan
Sub Total 52 11728.76
SUB TOTAL CENTRAL SECTOR 59 13198.76
TOTAL OF 12TH PLAN (LE) :
NUMBER OF UNITS : 105
CAPACITY (MW) : 21679
Appendix-4.2
(Sheet 1of 2 )
LIST OF THERMAL UNITS PROGRAMMED FOR R&M WORKS DURING 12TH PLAN.
2. STATE SECTOR
Sl. No. State Name of Utility Name of Station Unit No. Year of Capacity Make
Comm. (MW) Boiler TG
Northern Region
1 U.P. UPRVUNL Anpara ‘B’ 4* 1993 500 BHEL BHEL
2 U.P. UPRVUNL Obra 5* 1994 500 BHEL BHEL
3 U.P. UPRVUNL Obra 7* 1974 100 BHEL BHEL
4 U.P. UPRVUNL Obra 8* 1975 100 BHEL BHEL
Sub Total 4 1200
5 Punjab PSEB Ropar 5 1992 210 BHEL BHEL
6 Punjab PSEB Ropar 6 1993 210 BHEL BHEL
Sub total 2 420
7 Haryana HPGCL Panipat 6 2001 210 BHEL BHEL
Total Northern Region 7 1830
Eastern Region
8 Jharkhand JSEB Patratu 9* 1984 110 BHEL BHEL
9 Jharkhand JSEB Patratu 10* 1986 110 BHEL BHEL
Sub-Total 2 220
10 West Bengal DPL Durgapur 6* 1985 110 AVB BHEL
Total Eaatern Region 3 330
TOTAL STATE SECTOR 10 2160
2. CENTRAL SECTOR
1 NTPC Unchahar 3 1999 210 BHEL BHEL
2 NTPC Unchahar 4 1999 210 BHEL BHEL
3 NTPC Vindhyachal 7 1999 210 BHEL BHEL
4 NTPC Vindhyachal 8 2000 210 BHEL BHEL
5 NTPC Simhadri 1 2002 500 BHEL BHEL
6 NTPC Simhadri 2 2002 500 BHEL BHEL
7 NTPC Kahalgaon 4 1996 210 BHEL BHEL
Appendix-4.2
(Sheet 2 of 2 )
Sl. No. Name of Utility Name of Station Unit No. Year of Capacity Make
Comm. (MW)
12 NEEPCO Kathalguri CCGT GT-1 1995 33.50 Mitsubishi, Japan
13 NEEPCO Kathalguri CCGT GT-2 1995 33.50 Mitsubishi, Japan
14 NEEPCO Kathalguri CCGT GT-3 1995 33.50 Mitsubishi, Japan
15 NEEPCO Kathalguri CCGT GT-4 1995 33.50 Mitsubishi, Japan
16 NEEPCO Kathalguri CCGT GT-5 1996 33.50 Mitsubishi, Japan
17 NEEPCO Kathalguri CCGT GT-6 1996 33.50 Mitsubishi, Japan
18 NEEPCO Kathalguri CCGT ST-1 1998 30.00 BHEL
19 NEEPCO Kathalguri CCGT ST-2 1998 30.00 BHEL
20 NEEPCO Kathalguri CCGT ST-3 1998 30.00 BHEL
Sub Total
9 291.00
TOTAL CENTRAL SECTOR 20 4341.00
th
Notre:* Slip from 11 Plan
TOTAL OF 12TH PLAN (R&M) :
NUMBER OF UNITS : 30
CAPACITY (MW) : 6501
Total of 12th Plan (LE+R&M) 135
Capacity (MW) 28180
Abbreviations: R&M – Renovation & Modernisation;. U – Uprating; LE – Life Extension; Res – Restoration; MW – Mega Watt; CS-Central Sector: SS- State Sector
$ - Installed Capacity for Dehar (Ph.b) at Sl. No.2 & Nagjhari (U-4 to 6) at Sl. No.21 are not included in the total as the same has already been accounted for at Sl. Nos. 1 and 6 respectively.
Abbreviations: R&M – Renovation & Modernisation;. U – Uprating; LE – Life Extension; Res – Restoration; MW – Mega Watt; CS-Central Sector: SS- State Sector $ - Installed Capacity
for Dehar (Ph.A) at Sl. No. 10, Nagjhari (U-4 to 6) at Sl. No. 22, Chilla at S. No. 4 and Khodri (Ph.B) at Sl. No. 56 are not included in the total as the same has already been accounted for at
Sl. Nos. 1, 21, 37 and 3 respectively.
Abbreviations: R&M – Renovation & Modernisation;
RM&U – Renovation, Modernisation & Uprating,
RM&LE – Renovation, Modernisation & Life Extension
RMU&LE – Renovation, Modernisation, Uprating & Life Extension;
R&M+Res.-Renovation & Modernisation + Restoration;
RM&LE+Res.- Renovation, Modernisation & Life Extension + Restoration;
RM&U+Res. – Renovation, Modernisation & Uprating + Restoration.
MW – Mega Watt; Res – Restoration; U – Uprating; LE – Life Extension
Appendix 4.3
(Page 1 of 5)
STATE WISE LIST OF HYDRO R&M, LIFE EXTENSION & UPRATING SCHEMES PROGRAMMED FOR
COMPLETION DURING THE 12TH PLAN
As on 31.03.2011
S. Project, CS/ SS Installed Estimate Actual Benefits Category Year of
No Agency Capacity d Cost Expenditu (MW) Completi
(MW) on
re
(Rs. in Crs.)
Ongoing Schemes – Under implementation
Himachal Pradesh
1 Bhakra LB, BBMB CS 5x108 489.77 170.92 540.00 RMU&LE 2012-13
(as on (LE) +
31.12.10) 90.00
(U)
Jammu & Kashmir
2 Chenani, J&KPDC SS 5x4.66 39.14 3.49 23.30 (LE) RM&LE 2012-13
(as on
31.12.10)
3 Sumbal Sindh, SS 2x11.3 25.60 13.10 - R&M 2012-13
J&KPDC (as on
31.12.10)
4 Lower Jhelum, SS 3x35 101.30 68.45 15.00 R&M+ 2012-13
J&KPDC (as on (Res.) Res.
31.12.10)
Uttar Pradesh
5 Obra, UPJVNL SS 3x33 31.70 11.454 99.00 (LE) RM&LE 2013-14
(as on
31.12.10)
6 Rihand, UPJVNL SS 6x50 132.20 46.325 300.00 RM&LE 2012-13
(as on (LE)
31.12.10)
Uttarakhand
7 Pathri, UJVNL SS 3x6.8 71.59 - 20.40 (LE) RM&LE 2013-14
Andhra Pradesh
8 Srisailam RB, SS 7x110 16.70 13.36 - R&M 2012-13
APGENCO (as on
28.02.10 )
Kerala
9 Sabirigiri, KSEB SS 6x50 104.36 96.95 300.00 RMU&LE 2012-13
(as on (LE) +
31.12.10) 35.00(U)
10 Idamalayar, KSEB SS 2x37.5 11.70 5.45 - R&M 2012-13
(as on
31.12.10)
Tamil Nadu
Appendix 4.3
(Page 2 of 5)
Orissa
15 Rengali SS 1x50 47.50 3.40 50(LE) RM&LE 2012-13
OHPC (as on
31.12.10)
16 Hirakud-II, OHPC SS 3x24 125.52 58.73 72.00 (LE) RM&LE 2013-14
(as on
31.03.10)
Assam
17 Kopili, NEEPCO CS 2x50 + 66.42 0.218 - R&M & 2013-14
2x50 (as on Refurbis
30.09.10) hment of
Units 1 &
2
18 Khandong, CS 2x25 20.57 0.213 50.00 RM&LE 2013-14
NEEPCO (as on (LE)
30.09.10)
Meghalaya
19 UmiumSt.II , SS 2x9 90.46 19.00 2(U)+ RM&LE 2012-13
MeSEB (as on 18.00 (LE)
31.12.10)
Sub Total(A) 3172.30 1690.03 662.84 2169.70
Ongoing Schemes – Under Tendering
Jammu & Kashmir
20 Ganderbal, SS 2x3+ 39.30 6.24 15.00 (LE) RM&LE XII Plan
J&KPDC 2x4.5 (as on
31.12.10)
Uttar Pradesh
Appendix 4.3
(Page 3 of 5)
21 Matatila, UPJVNL SS 3x10.2 10.29 1.00 30.6 (LE) RM&LE XII Plan
(as on
31.12.10)
Uttarakhand
22 Khatima, UJVNL SS 3x13.8 140.24 - 41.40 (LE) RM&LE XII Plan
23 Chilla(Ph-B), SS 4x36 472.00 - 22(U) + XII Plan
UJVNL 144(LE) RMU&L
E
24 Dhakrani, UJVNL SS 3x11.25 70.00 - 33.75 (LE) RM&LE XII Plan
Appendix 4.3
(Page 4 of 5)
S. Project, CS/ SS Installed Estimate Actual Benefits Category Year of
No Agency Capacity d Cost Expendi (MW) Completion
(MW)
ture
(Rs. in Crs.)
25 Dhalipur, UJVNL SS 3x17 101.25 - 51.00 (LE) RM&LE XII Plan
Appendix 4.3
(Page 5 of 5)
S. Project, CS/ SS Installed Estimate Actual Benefits Category Year of
No Agency Capacity d Cost Expenditu (MW) Completi
(MW) on
re
(Rs. in Crs.)
Meghalaya
39 Kyrdemkulai, SS 2x30 168.00 - 60.00 (LE) RMU & LE XII Plan
MeSEB 6.00 (U)
Sub Total(C) 363.75 419.93 0.044 385.00
Ongoing Schemes – Under RLA Studies
Andhra Pradesh
40 Upper Sileru, SS 4x60 10.00 - - R&M XII Plan
APGENCO
Tamil Nadu
41 Kodayar Ph.I, SS 1x60 30.00 - 60.00 (LE) RM&LE XII Plan
TNEB
42 Kodayar SS 1x40 19.94 - 40.0(LE) RM&LE XII Plan
PH-II, TNEB
Sub Total(D) 340.00 59.94 - 100.00
Total 5248.80 3887.55 674.70 4063.45
(A+B+C+D) [212.25(U)
+
3836.20(LE)
+ 15.0
(Res.)]
Abbreviations:
R&M – Renovation & Modernisation;
RM&U – Renovation, Modernisation & Uprating,
RM&LE – Renovation, Modernisation & Life Extension
RMU&LE – Renovation, Modernisation, Uprating & Life Extension;
R&M+Res.-Renovation & Modernisation + Restoration;
RM&LE+Res.- Renovation, Modernisation & Life Extension + Restoration;
RM&U+Res. – Renovation, Modernisation & Uprating + Restoration.
MW – Mega Watt; Res – Restoration; U – Uprating; LE – Life Extension
Chapter 5
GENERATION PLANNING
The System limits the impact and scope as a result of pressure on Discoms to
of instability and cascading outages source their requirement from renewable
when they occur. energy sources (to meet RPO). Since
The System’s Facilities are protected system stability requires matching of
from unacceptable damage by generation with the demand at all
operating them within Facility Ratings. instances of time, a certain degree of
The System’s integrity can be restored flexibility and ability of the generators to
promptly if it is lost. respond rapidly to the changing demand
The System has the ability to supply the must be introduced into the system
aggregate electric power and energy through appropriate generation plants.
requirements of the electricity System should be able to meet additional
consumers at all times, taking into demand arises due to unexpected
account scheduled and reasonably demand and sudden unexpected outages
expected unscheduled outages of of some units.
system components.
Peaking demand in Indian states has been
To achieve reliability in the system, met, to some extent, by purchasing
adequate Reserve capacity, spinning as power from other states through bilateral
well as non-spinning needs to be planned agreements or through the mechanism of
for in the system. Aspects related to the Unscheduled Interchange (UI) at
operation, ownership, modalities and frequency-linked prices and sometimes by
nature of reserves also need to be load shedding also. The frequency band
determined. The location of the reserve tolerated here (from 50.2 to 49.5 Hz) is far
generation capacity viz-a-viz the load above that permitted in developed
centres is also critical. countries. However in the future this
frequency band is expected to narrow
The National Electricity Policy stipulates a down and this would reduce the available
5% Reserve Margin in our system. This has margin to meet the peaking requirement
been considered while planning capacity or reserve capacity through frequency
addition requirement during the 12th and linked interchange mechanism. Hydro
13th Plans. Details of how this Reserve power plants also can be started up
Margin is to be provided are furnished quickly to meet sudden peaks, but this
later in this Chapter (under Cl. 5.4 on facility is restricted to those few states
‘Planning Approach’). that have adequate water storage, all
through the year.
b) Flexibility of operation
Peaking plants shall be environmentally-
A system that is designed for base-load friendly and must comply with emission
generation will lack the characteristics to norms, so as to be located close to load
respond dynamically or efficiently to the centres. They must be able to start up
variation in demand within a short time. (and stop) instantaneously and ramp up
Apart from variation in demand, there is quickly, and in required steps, to match
expected to be wide variability in the spike in load. Their efficiency curve
generation as well, when the installed must be high and flat at different plant
base of renewable energy plants increases loads. They must be ‘all-season’ plants and
reliability, but also location of the plant in not during off-peak period. As per the
relation to load centres, fuel resources, model, all the DG based stations operate
fuel transportation network and at low PLF. Some of the gas based
extension of the transmission grid. The stations also operate at low PLF. Even
power system planning is generally some of the existing load centre based
carried out over long time horizons and coal stations located at in the state of
the planning model should be capable of Haryana, Punjab, Rajasthan, Gujarat, Tamil
analyzing a large number of scenarios Nadu and even some imported coal based
within a reasonable time and with least stations located in the state of Gujarat and
effort. Maharashtra operate at low plant load
factor (PLF) on account of high delivered
The ISPLAN model has the capability to cost of fuel to these stations.
address these system planning issues as
an indicative planning tool for analyzing However, the least cost expansion plan is
the major features of an optimal not always the feasible plan. From
expansion plan for generating capacity, feasibility point of view, a number of
transmission network and fuel transport. aspects like availability of land, water etc,
The ISPLAN model works out the least obtaining various clearances for setting
cost power development plan based on up the plant, placement of orders for main
minimisation of objective function, which plant etc. need to be looked into.
comprises of Capital cost of projects
(annualised), O&M cost (Annual), Fuel 5.3.2 Electric Generation Expansion
cost, Fuel transportation cost etc. Analysis System [EGEAS]
The Electric Generation Expansion
Based on Linear Programming Analysis System (EGEAS) is a software
formulation, the model is capable of package intended for use for expansion
producing optimal expansion plans planning of an electric generation system.
effectively and quickly with respect to a In this planning model the operation of
large number of alternative input the power system is simulated
assumptions. Criteria of optimality is the probabilistically. The load on the power
minimum discounted present worth of the system is represented both in terms of
total annual system cost for the year magnitude and time variation. The model
under study including the annualized yields the reliability indices, namely the
capital cost of all new facilities Loss-Of-Load-Probability (LOLP), the
(generating plants, transmission lines etc.) expected value of Energy-Not-Served
plus the operation and maintenance cost (ENS), and the reserve margin for an
and cost of energy not served. expansion power plan by minimising the
objective function which is the present
The ISPLAN model considers operation of worth of the costs associated with
the power plants at a particular PLF operation of the existing and committed
depending upon the demand to be met generating stations viz., the annualised/
such that the cost of delivered power is levelised capital cost and operating cost
minimal. Accordingly, thermal stations of new generating stations and cost of
with costly fuel will operate at low PLF i.e. energy not served. The EGEAS model is
only during period of peak demand and capable of giving a number of expansion
Beyond the 11th Plan, a planning approach An All India Load Duration Curve (LDC)
whose exclusive aim is ‘adequacy of was generated from the summation of
power’ (through the addition of base-load hourly data for all states. The data was
capacities equal or close to the maximum collected for three years (2006-09) on
expected demand) would lead to sub- monthly basis from various Regional Load
optimal operation of the system for a Dispatch Centres and State Load Dispatch
majority of the time. This is due to the Centres. The hourly data was analyzed
poor turn-down capabilities inherent in and corrected for any discrepancies in
power production technologies of base terms of load shedding, frequency
load plants such as coal and nuclear fuel. correction, scheduled power cuts and any
Moreover, this pattern of under- loading data errors. The hourly loads for each
coal plants during off-peak hours down to year were normalized, summed and
50% also results in power stations averaged to unity. The peak demand was
operating at sub-optimal PLFs leading to adjusted to unity and other hourly
poor efficiency levels. demands were scaled accordingly. It was
assured that the All India LDC meets both Duration Curve was generated based on
Peak Demand and Energy Requirement Energy Requirement and Peak Load for
monthly and annually published from time 2016-17. A typical Load Duration Curve is
to time by CEA using a mathematical illustrated in the Figure No. 5.2 below.
model. A typical Equivalent All India Load
All the above options have a very quick been considered in the studies while
response time and, therefore, adequately estimating the capacity addition
provide hot reserve, fast replacement requirement from conventional power
reserve and replacement reserve. plants. Wind and solar energy was fixed
with topmost priority as must run in the
Peaking capacity expansion exercise. The remaining
A peaking load occurs owing to several capacity addition required was then
reasons. It could be something that can be estimated to meet the demand of the
anticipated, as in morning peaks and system. Different Scenarios
evening peaks. It could happen when corresponding to likely availability of
irrigation needs have to be met and renewables were worked out.
several thousand pump sets come on
simultaneously. Urban loads can shoot up 4) Retirement of Old thermal units
in certain seasons (example, summer air-
conditioning loads in Delhi). Or the Information was compiled in respect of
peaking shortage could be due to a old thermal power plants and gradually
sudden drop in output from an infirm, and systematically all the inefficient
renewable energy source such as wind thermal units were considered for
turbines. retirement while estimating the capacity
addition requirement. During the 12th and
Plants with rapid-response characteristics 13th Plan, 4,000 MW each was retired.
that make them ideal as ‘reserve’ plants
can also be used to meet expected daily, 5) Facility for Black Start after complete
time-of-day spikes and seasonal peaks. grid collapse.
They can be an integral part of the grid
operator’s armoury to provide flexibility. As suggested above, a peaking capacity of
about 2,000 MW could be provided at
Peaking capacity also needs to come from major metropolitan cities of the country
quick response power plants. Therefore, with a view to ensure reliable power
foremost, pumped storage hydro plants supply. This facility would also be useful in
and hydro plants with storage capacity providing black startup facility in the
provide peaking power. Also, gas based/ event of a grid collapse. Combined Heat
diesel based plants i.e. OCGT and engines and Power Plants with a high efficiency of
are appropriate for peaking power. It is operation could also provide black start
also considered appropriate to have facilities immediately after grid collapse.
distributed peaking capacity at major load
centres in the country, perhaps 2000 MW 6) Time of Day (TOD) Tariff
each at the metropolitan cities to provide
quality, reliable and flexible power supply. The National Electricity Policy and the
National Tariff Policy mandates the State
3) Renewable capacity in Planning Commissions to introduce Time of the
process. day (TOD) metering in order to reduce
the demand of electricity during peak
Renewable capacity has tremendous hours. It is desirable from the system
inherent advantages and has therefore point of view to flatten the load curve for
which it is essential to reduce peak factor causes the Plant Load Factor of the
demand and encourage generating stations to improve, thus
consumption/enhance load during off reducing the generation cost. The
peak hours. This can be done by the consumers ultimately get benefited by
following methods availing power at lower rates during off-
peak hours and also by reduction in supply
Providing incentives to consumers for costs of the utility. The incidence of load
shifting their consumption to off- shedding is also reduced due to reduction
peak hours in the peak load
Providing dis-incentives to consumers
for consumption during peak hours Although, TOD tariff is applicable for high
A combination of the above two. tension consumers in many states, it is not
yet applicable at the retail level. TOD
The above methods require differential metering could be made applicable for
tariffs for different time slots of peak and those consumers where there is possibility
off-peak hours .It is well known that by of shifting the load of peak hours to off-
controlling the price of electricity, it is peak hours. To have TOD tariff imposed at
possible to motivate individual consumers the retail level, all domestic consumers
to either reduce/increase or shift their will have to be given a new meter that will
consumption from one point of time to segregate the peak and non-peak
another during the day, i.e. the consumer consumed units.
can be motivated to change his
consumption pattern during the day. 5.4 CONCLUSION
The major advantage of reducing the peak Planning for capacity addition in 12th and
demand through TOD metering, as a tool 13th Plans has been carried out in Chapter
for Demand Side Management, is that it 6 in accordance with the principles
allows the utility to reduce its outlined in this Chapter. Reliability by
generation/power purchase requirement, providing Reserve Margins and Flexibility
which reduces the overall cost of supply. by providing capacity having suitable
Another advantage, which the utility has, ramp up and ramp down response to take
is that the load factor of the system care of peaking and reserve requirements,
improves due to shifting of some peak forms an important aspect while planning
load to off peak hours and leads to capacity addition in succeeding Chapters.
flattening of load curve. Improved load
---+++---
Chapter 6
GENERATION CAPACITY ADDITION PROGRAMME
FOR 12th & 13th PLANS
MWe PFBR (Prototype Fast Breeder including clean coal technologies. The
Reactor). This is expected to be followed choice of fuel for power generation would
by four more 500 MWe units by the year be governed by principles of sustainable
2020. Thereafter, it will be followed by a development keeping in view energy
number of FBRs. When the capacity security aspect.
through FBRs builds up to reasonable
level, the deployment of thorium for The production and supply of gas had not
power generation through 3rd stage will been keeping pace with the growing
begin and get realized in the long term. demand of gas in the country, including
for that of power sector. The gas supply
Although nuclear energy can make only a for gas based power stations in the
modest contribution over the next 15 country is inadequate, even the
years, longer-term consideration of even a commitments of gas allocations made
modest degree of energy self-sufficiency earlier to power stations were not
suggests the need to pursue the fulfilled. The gas was sufficient to operate
development of nuclear power using these stations at about 52 % PLF only
thorium. during 2007-08. Similarly the average gas
supply during April 2008- January 2009
With the signing up of the '123 was 37.44 MMSCMD, against the
Agreement' on nuclear cooperation requirement of 66.04 MMSCMD to
between USA and India, and NSG’s waiver operate the stations at 90% PLF, which
for supply of nuclear fuel to India, it is was sufficient to operate these stations at
expected that some nuclear plants with about 51% PLF.
foreign technology from friendly
countries would be set up in the country. In the year 2009-10, Government of India
The availability of imported nuclear fuel allocated 18 MMSCMD gas from KG D6
and technology to India will help in basin out of production of 40 MMSCMD in
accelerated capacity addition from Phase I to Power Sector for existing
nuclear power plants. Commencement of power plants which helped in utilizing the
construction of reactors with imported stranded capacity of gas based power
technology during 11th/12th Plans is stations. The production at KG basin was
expected which will get commissioned in expected to go up to 80 MMSCMD.
13th Plan onwards. Development of Accordingly, EGoM allocated bulk of the
nuclear parks with Mega capacity is also additional gas from KG basin to Power
anticipated. Sector. The allocation was based on 75%
PLF to A.P. projects and 70% PLF to non
6.1.3 Gas A.P. projects. This includes 12.29
MMSCMD gas on firm basis and 12
Gas based stations are also restricted due MMSCMD on fall back basis to existing
to limited availability of gas. Therefore, power projects including projects likely to
coal based thermal generation is likely to be commissioned during 2009-10.
continue to dominate power generation in
the country and therefore requisite thrust However, in view of reduced production
is essential for the development of various from KG basin in recent past, even the
environment friendly technologies firm quantity of allocated gas is not being
th th
Chapter 6: Page | 100 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 101
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
6.2 NORMS ADOPTED FOR RELIABILITY electricity which has to be borne by the
CRITERIA consumer. Details of LOLP in some
countries are as follows:
The Power System is planned to meet the
forecasted demand and ensure an
expected level of reliability. Reliability is a
measure of the ability of a system to Name of country LOLP(%)
perform its designated function under the Cambodia 1.8
designed conditions. In our Studies, Loss Laos 0.27
of Load Probability (LOLP) is the criteria Thailand 0.27
adopted to reflect the capacity of the Vietnam 0.27
system to meet the peak load and Energy Hong Kong 0.006
Not Served (ENS) to reflect the Energy Bangladesh 1.0
Requirement not met in the System. LOLP Belgium 0.2
is the probability that a system will fail to USA 0.03
meet its peak load under the specified China 0.14
operating conditions. It is the proportion
of days per year or hours per year when Source: Information collected from website of
the available generating capacity is above countries.
insufficient to serve the peak demand.
This index is dimensionless and can also Up till now, in India the reliability figures
be expressed as a percentage. adopted were of LOLP – 1% and ENS- 0.15%.
This was the case when India was faced by
ENS is the expected amount of energy a huge power deficit situation. Now, the
which the system will be unable to supply power shortage is expected to ease out.
to the consumers as a fraction of the total Therefore from 12th Plan onwards more
energy requirement. This index again is Stringent Reliability norms are required to
dimensionless and can also be expressed be adopted. USA adopts an LOLP of 0.03%
as a percentage. In other words these which appears to be reasonable for a
indicate as to how many units of energy developed economy. LOLP standard
requirement in a year are not met and adopted by some South Asian countries is
correspondingly how many hours in a year 0.27 %.
the power demand is not met. Various
It is therefore proposed that an LOLP of
countries in the world have adopted their
0.2% and the Energy Not Served (ENS) of
own Reliability Criteria depending upon
0.05% shall be adopted for planning
the status of their power system and the
purposes from 12th Plan onwards.
price affordability of the consumers to
pay for the reliability of the system. It is 6.3 PLANNING NORMS (CERC NORMS)
evident that a more stringent and reliable
system would yield higher cost of The planning studies require accurate
th th
Chapter 6: Page | 102 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Table 6.1
PEAKING AVAILABILITY (GROSS) OF THERMAL/ NUCLEAR/ HYDRO POWER STATIONS
Figures in %
Unit Size Existing Units Future Units
Thermal (Coal) 800/660 MW - 88
500/250/210/200 MW 85 85
Below 200 MW 75 85
Below 200 MW operating below 50 -
20 % PLF at present
Gas Based OCGT all sizes 90 90
CCGT all sizes 88 88
DG Sets All sizes 75 75
Lignite Based All sizes 80 80
Nuclear All sizes 68 68
Hydro All sizes 87.5 87.5
6.3.2 Auxiliary Power Consumption: The types of generating units considered are
auxiliary consumption of the various given in Table 6.2
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 103
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Table 6.2
Table 6.3
th th
Chapter 6: Page | 104 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Table 6.4
COST CALORIFIC VALUE
FUEL (RS./TH.CUM) (KCAL /CUM)
LNG 8,000 9,800
GAS (HVJ) 4,400 9,500
GAS (RELIANCE) 5,760 9,500
GAS (NER) 3,000 9,500
6.3.6 Plant load factor: The plant load factor based) considered for the various type of
of thermal power stations (coal and gas- plants are furnished in Table 6.6
Table 6.6
PLANT LOAD FACTORS OF THERMAL/ NUCLEAR POWER STATIONS
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 105
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
For hydro units, the energy generation is Seasonal Studies being carried out
as per the designed energy generation in rather than Annual Studies with a
a 90% dependable year. view to ensure demand being met
in all the seasons
6.4 GENERATION CAPACITY Projects considered in the study
EXPANSION PLANNING DURING 12TH PLAN are as under :-
peak hours so as to utilize the available within the confines of the reliability
gas which is scarce, optimally. criteria.
The balance capacity is proposed to be Hydro, Gas and Nuclear based capacity is
met from coal based projects. Thus, coal is given the foremost priority due to their
expected to be main fuel for 12th Plan inherent advantages towards a Low
capacity addition too. A shelf of projects Carbon growth Strategy. Therefore,
with aggregate capacity of 1,23,135 MW capacity from these sources which is likely
coal based projects have been identified to materialise during 12th Plan has been
which are likely to yield benefits during considered as must run in the various
12th Plan. Project-wise details are Scenarios.
furnished in Appendix 6.3. The coal based Renewable capacity has also been
capacity shall be selected from the shelf considered as must run capacity.
of projects depending on the feasibility
of the various projects. Three scenarios were developed for
generating capacity addition during 12th
6.5 12TH PLAN STUDY AND RESULTS Plan. The scenarios are as follows:
Scenario 1 – Low Renewables, Low Gas
EGEAS Studies were carried out to assess
the total capacity addition requirement Scenario 2 – Low Renewables, High Gas
during the 12th Plan to meet the demand
Scenario 3 – High Renewables, High Gas
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 107
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Scenario – 1– 18th EPS Demand - Low Renewable(18,500 MW), Low gas(1086 MW)
th th
Chapter 6: Page | 108 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Hydro 12,000
Thermal 49,200
Coal 49,200
Gas 0
Nuclear 18,000
TOTAL 79,200
Wind 11,000
Solar 16,000
Other RES 3,500
Total (RES) 30,500
Retirement During 13th Plan 4,000
th th
Chapter 6: Page | 110 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Hydro 12,000
Thermal 51,000
Coal 38,000
Gas 13,000
Nuclear 18,000
TOTAL 81,000
Wind 11,000
Solar 16,000
Other RES 3,500
Total (RES) 30,500
Retirement During 13th Plan 4,000
Hydro 12,000
Thermal 47,000
Coal 34,000
Gas 13,000
Nuclear 18,000
TOTAL 77,000
Wind 20,000
Solar 20,000
Other RES 5,000
Total (RES) 45,000
Retirement During 13th Plan 4,000
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 111
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
12,000 MW, Nuclear -18,000 MW, Coal country during the 12th Five Year Plan
-49,200 MW) assuming likely capacity addition of
about 62,374 MW during the 11th
During the 13th Plan, the capacity addition Plan, spinning reserve requirement
is from more efficient Units based on of 5% as per NEP, retirement of old
latest technologies. Thermal capacity inefficient thermal units of about
addition is from units of higher size i.e. 4,000 MW and reliability criteria of
660/800 MW in all cases with supercritical 0.2% LOLP & 0.05% ENS adopted by
technologies. These Initiatives are in CEA.
accordance with our strategies for clean
and Green Power. It is recommended that The total capacity addition
during the 13th Plan, capacity addition requirement in the country for 12th
from coal fired power plant must be from Plan has been proposed as under:
super critical only.
Total Capacity (excluding
The required capacity addition during the renewable) - 79,690 MW
13th Plan will be of the order of about Hydro - 9,204 MW
80,000 MW. Any projects slipping from Nuclear - 2,800 MW
12th Plan capacity addition programme Thermal - 67,786 MW
MW will be added in the 13th Plan capacity Coal - 66,600 MW
addition programme. Thus it is clear that Gas - 1,086 MW
huge capacity addition will be required Indigenous capacity required to be
during 13th Plan for which advance developed – 79,690 MW (1,200 MW
Planning/advance action is required during imports have been assumed from
the 12th Plan itself by all concerned. neighbouring countries) .
---+++---
th th
Chapter 6: Page | 112 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Annexure 6.1
Installed Benefit in
Sl.No. Name of scheme State Agency
Capacity (IC) 12th. Plan
1 Kashang - I H.P. HPPCL 65 65
2 Tidong-I H.P. Nuziveeedu Seeds Ltd 100 100
3 Kashang -IV H.P. HPPCL 48 48
4 Kashang-II & III H.P. HPPCL 130 130
5 Tangnu Romai H.P. Tangnu Romai Power 44 44
Corp.
6 Bajoli Holi H.P. GMR 180 180
7 Kutehr H.P. JSW 240 240
8 Renuka dam H.P. HPPCL 40 40
9 Sainj H.P. HPPCL 100 100
10 Shongtong Karcham H.P. HPPCL 450 450
11 Dhaula Sidh H.P. SJVNL 66 66
12 Baglihar-II J&K PDC 450 450
13 Kishan Ganga J&K NHPC 330 330
14 New Ganderbal J&K PDC 93 93
15 Kawar J&K NHPC 520 520
16 Kiru J&K NHPC 600 600
17 Singoli Bhatwari Uttarakhand L&T 99 99
18 Phata Byung Uttarakhand LANCO 76 76
19 Lata Tapovan Uttarakhand NTPC 171 171
20 Pala Maneri Uttarakhand UID 480 480
21 Tehri St-II PSS Uttarakhand THDC 1000 1000
22 Vishnugad Pipalkoti Uttarakhand THDC 444 444
23 Alaknanda (Badrinath) Uttarakhand GMR 300 300
24 Kotlibhel-St-1A Uttarakhand NHPC 195 195
25 Kotlibhel-St-1B Uttarakhand NHPC 320 320
26 Kotlibhel-St-II Uttarakhand NHPC 530 530
27 Rupsiyabagar Khasiyabara Uttarakhand NTPC 260 260
28 Hanol Tiuni Uttarakhand Sunflag 60 60
29 Naitwar Mori (Dewra Mori) Uttarakhand SJVNL 56 56
30 Arkot Tiuni Uttarakhand UID 81 81
31 Bowala Nand Prayag Uttarakhand UJVNL 300 300
32 Devsari Dam Uttarakhand SJVNL 252 252
33 Bogudiyar Sirkari Uttarakhand GVK 146 146
34 Mapang Bogudiyar Uttarakhand GVK 200 200
35 Nand Prayag Langasu Uttarakhand UJVNL 100 100
36 Tamak Lata Uttarakhand UJVNL 280 280
37 Tuini Plasu Uttarakhand UID 72 72
38 Shahpur Kandi Punjab PSEB 206 206
39 UBDC-III Punjab Bhilwara Energy Ltd. 75 75
40 Ramam St-III W. B. NTPC 120 120
41 Ramam St-I W. B. WBSEDCL 36 36
42 Ramman Ultimate(IV) W. B. WBSEDCL 28 28
43 Dummugudem A..P. APID 320 320
44 Pollavaram MPP A..P. APID 960 960
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 113
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
th th
Chapter 6: Page | 114 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Annexure 6.1a
HYDRO PROJECTS IDENTIFIED FOR LIKELY BENEFITS DURING 12th PLAN
Sl. Capacity
Project Name State Developer Sector
No. (MW)
1 Pare Ar. Pradesh NEEPCO C 110
2 Kameng Ar. Pradesh NEEPCO C 600
3 Subansiri Lower Ar. Pradesh NHPC C 2000
4 Parbati-II H.P. NHPC C 800
5 Rampur H.P. SJVNL C 412
6 Kol Dam H.P. NTPC C 800
7 Kishan Ganga J&K NHPC C 330
8 Tuirial Mizoram NEEPCO C 60
Tapovan
9 Uttarakhand NTPC C 520
Vishnugad
10 Lower Jurala A.P. APGENCO S 240
11 Pulichintala A.P. APGENCO S 120
12 Kashang - I H.P. HPPCL S 65
13 Uhl-III H.P. BVPC S 100
14 Sawara Kuddu H.P. HPPCL S 111
15 Kashang II & III H.P. HPPCL S 130
16 Sainj H.P. HPPCL S 100
17 Baglihar-II J&K J&K State PDC S 450
18 Thottiar Kerala KSEB S 40
19 Pallivasal Kerala KSEB S 60
20 New Umtru Meghalaya MeECL S 40
N S L Tidong
21 Tidong-I H.P. P 100
Power Gen. Ltd
Himachal Sorang
22 Sorang H.P. P 100
Power Pvt. Ltd
Tangnu Romai
23 Tangnu Romai-I H.P. P 44
Power Gen.Ltd
Gati
24 Bhasmey Sikkim P 51
Infrastructure Ltd.
25 Jorethang Loop Sikkim DANS Pvt. Ltd P 96
Jal Power Corp.
26 Rangit-IV Sikkim P 120
Ltd.
Lanco Energy Pvt.
27 Teesta-VI Sikkim P 500
Ltd.
28 Teesta-III Sikkim Teesta Urja P 600
29 Singoli Bhatwari Uttarakhand L&T P 99
Lanco Energy Pvt.
30 Phata Byung Uttarakhand P 76
Ltd.
AHP Co. Ltd.
31 Srinagar Uttarakhand P 330
(GVK)
TOTAL (HYDRO) 9204
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 115
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Annexure 6.2
CAPACITY
Sl.No. PLANT NAME STATE AGENCY SECTOR FUEL TYPE
(MW)
th th
Chapter 6: Page | 116 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Annexure 6.3
LIST OF SHELF OF COAL BASED PROJECTS FOR LIKELY BENEFITS DURING 12TH PLAN
(a) LIST OF THERMAL PROJECTS- ORDERS FOR MAIN PLANT PLACED WITH CLEARANCES IN
PLACE
S. Unit Capacity
Project Name State Developer Sector Status of Coal
No. No. (MW)
1 BONGAIGAON TPP 3 Assam NTPC C 250 Linkage
2 MAUDA TPP 1 Maharashtra NTPC C 500 Linkage
3 MAUDA TPP 2 Maharashtra NTPC C 500 Linkage
4 VINDHYACHAL ST-IV 11 MP NTPC C 500 Linkage
5 VINDHYACHAL ST-IV 12 MP NTPC C 500 Linkage
6 RIHAND-III 5 UP NTPC C 500 Linkage
7 RIHAND-III 6 UP NTPC C 500 Linkage
Muzaffarpur
8 1 Bihar NTPC JV C 195 Linkage
Ext.(Kanti TPP)
Muzaffarpur Ext.
9 2 Bihar NTPC JV C 195 Linkage
(Kanti TPP)
10 Barh STPP-I 1 Bihar NTPC C 660 Linkage
11 Barh STPP-I 2 Bihar NTPC C 660 Linkage
12 Barh STPP-I 3 Bihar NTPC C 660 Linkage
13 Sipat-I 3 Chhattisgarh NTPC C 660 Linkage
NTECL (NTPC/TNEB
14 Vallur 3 TN C 500 Linkage
JV)
15 Nabinagar TPP 1 Bihar NTPV JV C 250 Linkage
16 Nabinagar TPP 2 Bihar NTPV JV C 250 Linkage
17 Nabinagar TPP 3 Bihar NTPV JV C 250 Linkage
18 Nabinagar TPP 4 Bihar NTPV JV C 250 Linkage
19 Tuticorin JV 1 TN NPTL (NLC JV) C 500 Linkage
20 Tuticorin JV 2 TN NPTL (NLC JV) C 500 Linkage
21 Bokaro TPP A Exp 1 Jharkhand DVC C 500 Linkage
22 Korba West St.III 5 Chhattisgarh CSEB S 500 Linkage
23 SATPURA EXT 1 MP MPGENCO S 250 Linkage
24 SATPURA EXT 2 MP MPGENCO S 250 Linkage
Shree Singati TPP-I
25 1 MP MPGENCO S 600 Linkage
(Malwa)
Shree Singati TPP-I
26 2 MP MPGENCO S 600 Linkage
(Malwa)
27 ANPARA-D U 1 1 UP UPRVUNL S 500 Linkage
28 ANPARA-D U 2 2 UP UPRVUNL S 500 Linkage
29 Durgapur TPP U 8 8 WB DPL S 250 Linkage
30 D B STPS 2 Chhattisgarh M/S D.B. Power Ltd P 600 Linkage
Korba West Power
31 Avantha Bhandar TPP 1 Chhattisgarh P 600 Linkage
Company Ltd.
JHAJJAR THERMAL
32 2 Haryana China Light Power P 660 Linkage
POWER PROJECT
CORPORATE POWER
M/S Corporate
33 LTD, PH-I (MAITRISHI 1 Jharkhand P 270 Linkage
Power Ltd.
USHA TPP)
CORPORATE POWER
M/S Corporate
34 LTD, PH-I (MAITRISHI 2 Jharkhand P 270 Linkage
Power Ltd.
USHA TPP)
35 Amravati TPP-I 1 Maharashtra India Bulls P 270 Linkage
36 Amravati TPP-I 2 Maharashtra India Bulls P 270 Linkage
37 Amravati TPP-I 3 Maharashtra India Bulls P 270 Linkage
38 Amravati TPP-I 4 Maharashtra India Bulls P 270 Linkage
39 Amravati TPP-I 5 Maharashtra India Bulls P 270 Linkage
40 Nasik TPP-I 1 Maharashtra India Bulls P 270 Linkage
41 Nasik TPP-I 2 Maharashtra India Bulls P 270 Linkage
42 Nasik TPP-I 3 Maharashtra India Bulls P 270 Linkage
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 117
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
S. Unit Capacity
Project Name State Developer Sector Status of Coal
No. No. (MW)
43 Nasik TPP-I 4 Maharashtra India Bulls P 270 Linkage
44 Nasik TPP-I 5 Maharashtra India Bulls P 270 Linkage
DHARIWAL
DHARIWAL
45 1 Maharashtra INFRASTRUCTURE P 300 Linkage
INFRASTRUCTURE TPP
(P) LTD
DHARIWAL
DHARIWAL
46 2 Maharashtra INFRASTRUCTURE P 300 Linkage
INFRASTRUCTURE TPP
(P) LTD
EMCO ENERGY LTD Linkage for 270
47 EMCO WARORA TPP 1 Maharashtra P 300
(GMR) MW
EMCO ENERGY LTD
48 EMCO WARORA TPP 2 Maharashtra P 300 Linkage
(GMR)
Bina Power SUPPLY
49 Bina TPP 2 MP P 250 Linkage
COMPANY LTD
Jindal India
50 DERANG TPP 1 Orissa P 600 Linkage
Thermal Power Ltd
Ind. Bharat power
51 Ind Bharat TPP 1 Orissa P 350 Linkage
(Utkal) Ltd.
Ind. Bharat power
52 Ind Bharat TPP 2 Orissa P 350 Linkage
(Utkal) Ltd.
53 TALWANDI SABO TPP 1 Punjab Vedanta P 660 Linkage
54 TALWANDI SABO TPP 2 Punjab Vedanta P 660 Linkage
55 TALWANDI SABO TPP 3 Punjab Vedanta P 660 Linkage
56 BARA TPP 1 UP Jaypee Power Ltd P 660 Linkage
57 BARA TPP 2 UP Jaypee Power Ltd P 660 Linkage
58 BARA TPP 3 UP Jaypee Power Ltd P 660 Linkage
59 ROSA TPP PH-II 3 UP RELIANCE POWER P 300 Linkage
60 ROSA TPP PH-II 4 UP RELIANCE POWER P 300 Linkage
Linkage for 660
61 Nabha ( Rajpura TPP) 1 Punjab Nabha Power Ltd. P 700
MW
Linkage for 660
62 Nabha ( Rajpura TPP) 2 Punjab Nabha Power Ltd. P 700
MW
63 Seoni TPP (Jhabua ) 1 MP Jhabua Power P 600 Linkage
64 Nasik TPP-II 1 Maharashtra India Bulls P 270 Linkage
65 Nasik TPP-II 2 Maharashtra India Bulls P 270 Linkage
66 Nasik TPP-II 3 Maharashtra India Bulls P 270 Linkage
67 Nasik TPP-II 4 Maharashtra India Bulls P 270 Linkage
68 Nasik TPP-II 5 Maharashtra India Bulls P 270 Linkage
69 Amravati TPP-II 1 Maharashtra India Bulls P 270 Linkage
70 Amravati TPP-II 2 Maharashtra India Bulls P 270 Linkage
71 Amravati TPP-II 3 Maharashtra India Bulls P 270 Linkage
72 Amravati TPP-II 4 Maharashtra India Bulls P 270 Linkage
73 Amravati TPP-II 5 Maharashtra India Bulls P 270 Linkage
74 Vizag Hinduja TPP 1 A.P HNPCL P 520 Linkage
75 Vizag Hinduja TPP 2 A.P HNPCL P 520 Linkage
Lanco Babandh
76 Lanco Babandh 1 Orissa P 600 Linkage
Power
MB Power
77 Annoppur TPP-I 1 M.P (Madhya Pradesh) P 600 Linkage
Ltd.
MB Power
78 Annoppur TPP-I 2 M.P (Madhya Pradesh) P 600 Linkage
Ltd.
M/s Vidarbha
79 Butibori TPP Ph -II 1 Maharashtra Industries Power P 300 Linkage
Ltd
K.V.K. Nilachal
80 K.V.K. Nilachal TPP 1 Orissa P 525 Linkage
Power Pvt. Ltd.
K.V.K. Nilachal
81 K.V.K. Nilachal TPP 2 Orissa P 525 Linkage
Power Pvt. Ltd.
M.s Athena
Athena Chattisgarh
82 1 Chhatisgarh Chattisgarh Power P 660 Linkage
Power Pvt. Ltd.
Pvt. Ltd.
th th
Chapter 6: Page | 118 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
S. Unit Capacity
Project Name State Developer Sector Status of Coal
No. No. (MW)
SKS Power
83 Darrampura TPP 1 Chhatisgarh P 300 Linkage
Generation Ltd.
SKS Power
84 Darrampura TPP 2 Chhatisgarh P 300 Linkage
Generation Ltd.
SKS Power
85 Darrampura TPP 3 Chhatisgarh P 300 Linkage
Generation Ltd.
SKS Power
86 Darrampura TPP 4 Chhatisgarh P 300 Linkage
Generation Ltd.
87 Lanco Vidarbha TPP 1 Maharashtra Lanco Vidarbha P 660 Linkage
88 Lanco Vidarbha TPP 2 Maharashtra Lanco Vidarbha P 660 Linkage
D.B. Power 2x660, M/s D.B. Power , Linkage for 660
89 1 MP P 660
Sidhi Sidhi MW
Maurti Clean Coal & M/s Maurti Clean
90 1 Chhattisgarh P 300 Linkage
Power TPP Coal & Power Ltd.
91 Lanco Amarkantak 3 Chhattisgarh LAP Pvt Ltd P 660 Linkage
92 Lanco Amarkantak 4 Chhattisgarh LAP Pvt Ltd P 660 Linkage
500 MW- Tapering
R.K.M. POWERGEN
93 Uchpinda TPP 1 Chhattisgarh P 360 linkage/Coal Block
PVT LTD
, 900 MW - Linkage
500 MW- Tapering
R.K.M. POWERGEN
94 Uchpinda TPP 2 Chhattisgarh P 360 linkage/Coal Block
PVT LTD
, 900 MW - Linkage
500 MW- Tapering
R.K.M. POWERGEN
95 Uchpinda TPP 3 Chhattisgarh P 360 linkage/Coal Block
PVT LTD
, 900 MW - Linkage
500 MW- Tapering
R.K.M. POWERGEN
96 Uchpinda TPP 4 Chhattisgarh P 360 linkage/Coal Block
PVT LTD
, 900 MW - Linkage
Linkage for 500
MW; Block /
97 Kamalanga TPP 1 Orissa GMR Energy P 350
tapering linkage
for 550 MW
Linkage for 500
MW; Block /
98 Kamalanga TPP 2 Orissa GMR Energy P 350
tapering linkage
for 550 MW
Linkage for 500
MW; Block /
99 Kamalanga TPP 3 Orissa GMR Energy P 350
tapering linkage
for 550 MW
Linkage for 520
100 TIRODA TPP PH-I 2 Maharashtra ADANI POWER P 660 MW & Block for
140 MW
Adhunik Power &
101 Adhunik Power TPP 1 Jharkhand Natural Resources P 270 Block
Ltd.
102 Barh STPP-II 1 Bihar NTPC C 660 Block
103 Barh STPP-II 2 Bihar NTPC C 660 Block
104 Kakatiya TPP ST -II 1 AP APGENCO S 600 Block
105 Chandrapur Ext. 8 Maharashtra MAHGENCO S 500 Block
106 Chandrapur Ext. 9 Maharashtra MAHGENCO S 500 Block
107 Koradi TPP EXT 8 Maharashtra MAHGENCO S 660 Block
108 Koradi TPP EXT 9 Maharashtra MAHGENCO S 660 Block
109 Koradi TPP EXT 10 Maharashtra MAHGENCO S 660 Block
110 Sasan UMPP 1 MP Reliance Power Ltd. P 660 Block
111 Sasan UMPP 2 MP Reliance Power Ltd. P 660 Block
112 Sasan UMPP 3 MP Reliance Power Ltd. P 660 Block
113 Sasan UMPP 4 MP Reliance Power Ltd. P 660 Block
114 Sasan UMPP 5 MP Reliance Power Ltd. P 660 Block
115 Sasan UMPP 6 MP Reliance Power Ltd. P 660 Block
Jindal India
116 DERANG TPP 2 Orissa P 600 Block
Thermal Power Ltd
Akaltara (Nariyara)
117 4 Chhattisgarh Wardha PCL (KSK) P 600 Block
TPP
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 119
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
S. Unit Capacity
Project Name State Developer Sector Status of Coal
No. No. (MW)
Coal Block/
118 Vandana Vidyut TPP 2 Chattisgarh Vandana Vidyut P 135
Tapering Linkage
119 Tiroda TPP-II 1 Maharashtra Adani Power P 660 Block
120 Goindwal Sahib TPP 1 Punjab GVK Power P 270 Block
121 Goindwal Sahib TPP 2 Punjab GVK Power P 270 Block
D B STPS- M/S D.B. Power Coal Block/
122 1 Chhattisgarh P 600
CHHATTISGARH Ltd. Tapering Linkage
Coal Block/
123 Parli TPP Ext 8 Maharashtra MAHGENCO S 250
Tapering Linkage
Coal Block (A)/
Tapering Linkage
Akaltara (Nariyara)
124 1 Chhattisgarh Wardha PCL (KSK) P 600 (LOA for tapering
TPP
to 3x600 MW
granted by SECL)
Coal Block (A)/
Tapering Linkage
Akaltara (Nariyara)
125 2 Chhattisgarh Wardha PCL (KSK) P 600 (LOA for tapering
TPP
to 3x600 MW
granted by SECL)
Coal Block (A)/
Tapering Linkage
Akaltara (Nariyara)
126 3 Chhattisgarh Wardha PCL (KSK) P 600 (LOA for tapering
TPP
to 3x600 MW
granted by SECL)
Coal Block/
127 Marwah TPP 1 Chhattisgarh CSEB S 500 Tapering Linkage
(A)
Coal Block/
128 Marwah TPP. 2 Chhattisgarh CSEB S 500 Tapering Linkage
(A)
Coal Block/
129 Kalisindh TPS. 1 Rajasthan RRVUNL S 600 Tapering Linkage
(A)
130 Kalisindh TPS 2 Rajasthan RRVUNL S 600 Block (A)
Coal Block/
131 Chhabra TPS Ext. 3 Rajasthan RRVUNL S 250 Tapering Linkage
(A)
Coal Block/
132 Chhabra TPS Ext. 4 Rajasthan RRVUNL S 250 Tapering Linkage
(A)
Jaypee Power
133 NIGRIE TPP 1 MP P 660 Block (A)
Ventures Ltd
Jaypee Power
134 NIGRIE TPP 2 MP P 660 Block (A)
Ventures Ltd
135 Mahan TPP 1 MP Essar Power P 600 Block (A)
136 Mahan TPP 2 MP Essar Power P 600 Block (A)
137 Malibrahmani TPP Orissa Monet Power P 525 Block
Adhunik Power &
Block/Tapering
138 Adhunik TPP 2 Jharkhand Natural Resources P 270
Linkage
Ltd
Athena Chattisgarh Athena Chattisgarh
139 2 Chhatisgarh P 660 Block
Power Pvt. Ltd.2x660 Power Pvt. Ltd.
COASTAL ENERGEN Imported Coal/
140 Melamaruthur TPP 1 TN P 600
PVT LTD Linkage ( 70:30)
COASTAL ENERGEN Imported Coal/
141 Melamaruthur TPP 2 TN P 600
PVT LTD Linkage ( 70:30)
Sri Damodaram Linkage based on
142 Sanjeevaiah TPP 1 AP APGENCO S 800 70:30
(Krishnapattam TPP) Domestic:Imported
Sri Damodaram Linkage based on
143 Sanjeevaiah TPP 2 AP APGENCO S 800 70:30
(Krishnapattam TPP) Domestic:Imported
th th
Chapter 6: Page | 120 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
S. Unit Capacity
Project Name State Developer Sector Status of Coal
No. No. (MW)
Linkage based on
Thamminapatnam Meenakshi Energy
144 3 AP P 300 70:30
TPP-II Pvt. Ltd.
Domestic:Imported
Linkage based on
Thamminapatnam Meenakshi Energy
145 4 AP P 300 70:30
TPP-II Pvt. Ltd.,
Domestic:Imported
Linkage based on
East Coast Energy
146 Bhavanpadu TPP 1 AP P 660 70:30
Pvt. Ltd.
Domestic:Imported
Linkage based on
M/s. East Coast
147 Bhavanpadu TPP 2 AP P 660 70:30
Energy Pvt. Ltd.
Domestic:Imported
Linkage based on
Thermal Powertech
148 Painampuram TPP 1 AP P 660 70:30
Corporation Ltd.
Domestic:Imported
Linkage based on
Thermal Powertech
149 Painampuram TPP 2 AP P 660 70:30
Corporation Ltd.
Domestic:Imported
Linkage based on
150 Ind Barath TPP 1 TN Ind Barath Power P 660 70:30
Domestic:Imported
151 Sikka TPP Ext. 3 Gujarat GSECL S 250 Imported Coal
152 Sikka TPP Ext. 4 Gujarat GSECL S 250 Imported Coal
Madhucon projects
153 Simhapuri TPP Ph-II 1 AP Ltd (Simhapuri P 150 Imported Coal
Energy pvt. Ltd)
Madhucon projects
154 Simhapuri TPP Ph-II 2 AP Ltd (Simhapuri P 150 Imported Coal
Energy pvt. Ltd)
Linkage based on
155 MUNDRA TPP PH-III 2,3 Gujarat ADANI POWER P 1320 70:30
Domestic:Imported
The Tata Power
156 Mundra UMPP 2 Gujarat P 800 Imported Coal
Company Ltd
The Tata Power
157 Mundra UMPP 3 Gujarat P 800 Imported Coal
Company Ltd
The Tata Power
158 Mundra UMPP 4 Gujarat P 800 Imported Coal
Company Ltd
The Tata Power
159 Mundra UMPP 5 Gujarat P 800 Imported Coal
Company Ltd
TOTAL (COAL) 75650
(b) Projects having coal tied up but order for Main Plant yet to be placed
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 121
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
(c) PROJECTS WHERE ORDER FOR MAIN PLANT PLACED BUT CERTAIN CLEARANCES
AWAITED
Capacity
S.No. Name Agency State Sector
(MW)
1 Raigarh TPP JINDAL POWER Chhattisgarh P 2400
2 Karchana TPP JP U.P. P 1980
TRN Energy Private
3 TRN Energy TPP Chhattisgarh P 600
Limited
4 Malibramani TPP U-2 Monnet Power Orissa P 525
Navabharat Power Pvt.
5 Navabharat Power Pvt. Ltd. Orissa P 1050
Ltd.
Nagarjuna Construction Nagarjuna Construction
6 A.P. P 1320
Company Ltd. Phase-I Company Ltd.
7 Krishnapatnam UMPP Unit-1-6 Reliance Power Ltd. A.P. P 3960
8 Yermarus TPP RPCL (JV of KPCL & BHEL) Karnataka S 1600
9 Edlapur TPP RPCL (JV of KPCL & BHEL) Karnataka S 800
10 Bellary Unit-3 KPCL Karnataka S 700
11 Sagardighi WBPDCL W.B. S 1000
12 Barauni TPP BSEB Bihar S 500
Raigarh TPP (600 MW+660
13 Visa Chhattisgarh P 1260
MW)
14 Lalitpur TPP Hindustan Bajaj U.P. P 1980
15 Avantha Bhandar TPP U 2 KWPCL Chhattisgarh P 600
16 Corporate Power TPP Phase-II AINL Jharkhand P 540
17 Raikheda TPP (2x685 MW) GMR P 1370
18 Pipavav TPP Pipavav Energy Pvt. Ltd. Gujarat P 600
19 Lanco Babandh TPP U-2 Lanco Babandh Orissa P 660
20 Tori TPP Essar Power Jharkhand P 1200
Akaltara ( Nariyara) TPP KSK Mahanadi Power
21 Chhattisgarh P 1200
Unit 5&6 Company Ltd
22 DB Power Sidhi U-2 DB Power M.P. P 660
Total 26505
th th
Chapter 6: Page | 122 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Capacity Status of
S.No. Name of Project Unit No. State Agency Sector
(MW) Coal
1 MEJA JV 1 UP NTPC JV C 660 Linkage
2 MEJA JV 2 UP NTPC JV C 660 Linkage
3 NEW NABINAGAR 1 BIHAR NTPC JV C 660 Linkage
4 NEW NABINAGAR 2 BIHAR NTPC JV C 660 Linkage
5 NEW NABINAGAR 3 BIHAR NTPC JV C 660 Linkage
6 SOLAPUR 1 MAHARASHTRA NTPC C 660 Linkage
7 SOLAPUR 2 MAHARASHTRA NTPC C 660 Linkage
8 MAUDA-II 1 MAHARASHTRA NTPC C 660 Linkage
9 MAUDA-II 2 MAHARASHTRA NTPC C 660 Linkage
10 RAGHUNATHPUR 1 JHARKHAND DVC C 660 Linkage
11 RAGHUNATHPUR 2 JHARKHAND DVC C 660 Linkage
Total 7260
Capacity
S.No. Name of Project Unit No. State Agency Sector
(MW)
Reva Thermal Power NHDC
1 1&2 M.P. C 1320
Project Ltd
Total 1320
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 123
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Annexure 6.4
th th
Chapter 6: Page | 124 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
* Total capacity of the project is 1500 MW(500 MW of Bawana project has already been commissioned)
** Commissioning subject to availability of gas
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 125
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
th th
Chapter 6: Page | 126 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Chapter 7
OPTIMIZATION OF LAND AND WATER REQUIREMENTS FOR
THERMAL POWER PLANTS
7.0 INTRODUCTION
7.1 LAND REQUIREMENT
Large capacity addition is envisaged in the
country during the 12th Plan and beyond. Land requirement for a coal based plant
As per projections of Integrated Energy depends upon a number of factors such as
Policy, about 15,000 MW thermal capacity capacity of the plant & unit size adopted,
is to be added every year over next two quality of coal & its storage requirement,
decades. This requires installation of large type of CW system adopted, source of raw
number of coal and gas based plants. To water & its storage requirement and plant
achieve faster capacity addition targets, design aspects. For coal based plants,
large capacity plants including 4,000 MW land is basically required for main plant
size Ultra Mega power plants(UMPPs) systems/ equipment, ash dyke, pipe
using 660/800 MW supercritical units have corridors (for ash and raw water) and
been envisaged for installation at township. Plants based on imported coal
different sites mainly at pithead and require less land as compared to those
coastal locations. Availability of adequate based on indigenous coal on account of
land and water are key requirements for considerably reduced requirement for
installation of a thermal power plant. ESP, coal handling system, ash handling
system and ash dyke. Type of CW system
In the past, because of comparatively viz. open cycle or cooling tower system
slow pace of capacity addition, availability also has a significant impact on land
of adequate land was not a big constraint requirement of the plant.
and plants could be located as per other
applicable criteria viz. availability of coal Land requirement for ash dyke varies over
and water. However, since expansion of wide range depending upon quality of
power sector has been taken up in a big coal, method of ash disposal and
way, availability of land has become a utilization of fly ash. Fly ash and bottom
constraint and is posing a big challenge ash were earlier conventionally disposed
for currently planned and future plants. off to ash pond in the form of lean slurry
Land has become premium resource and requiring large pond area. However, with
its acquisition has also become difficult on increased concentration of wet slurry
account of other competing sectors and upto 25% and use of other techniques such
opposition of local population. In this as HCSD (High concentration slurry
background, optimum utilisation of land disposal) and dry fly ash disposal, the land
has gained significance so that maximum required for ash dyke has considerably
plant capacity could be installed on the reduced. MOEF’s stipulation for
available land. progressive utilization of fly ash upto 100%
Optimization of Land and Water Requirements For Thermal Power Plants Chapter 7: Page | 127
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
within a given time frame has reduced the large capacity plants with large size units
quantum of ash to be disposed off to ash are required to be installed to achieve the
dyke. Use of washed coal and blending of intended high capacity targets, CEA had
imported coal with indigenous coal has set up a committee in April, 2007 to go
also resulted in reduced land required for into the aspect of land requirement for
ash dyke. New plants based on imported thermal plants and suggest minimum land
coal would be requiring least land for ash requirement for various size plants. The
dyke. Committee submitted its report in
December 2007 and has analysed land
7.1.1 Committee for Optimisation of Land requirement aspects for various sizes &
Requirement combinations of the plants viz. indigenous
coal/imported coal, open cycle/closed
In view of large capacity addition cycle CW system. The committee has
proposed to be based on coal based recommended the land requirement as
plants, need had been felt to optimize the indicated in Table 7.1 & 2 below:
land requirement for thermal plants. As
Table 7.1
Indigenous Coal (Pithead Stations)
Chapter 7: Page | 128 Optimization of Land and Water Requirements for Thermal Power Plants
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Table 7.2
Imported Coal (Coastal Stations)
The Committee has suggested that round development in the country and
further reduction in land requirement is vast growth of thermal power stations,
possible for ash dyke and the colony. The the availability of water has become
land requirement could also be reduced scarce. As drinking and irrigation uses
considerably by setting up of integrated have got priority in allocation of water
projects for fly ash utilization, compact over industrial use and power generation,
design of the plant and adopting multi the thermal power plants are facing
storey concept of the township. constraints in availability of adequate
fresh water. Judicious utilization of water
7.2 WATER OPTIMIZATION TECHNOLOGIES and recycling of plant waste water in
IN THERMAL POWER PLANTS thermal plants has become important so
as to reduce net drawal from the source
7.2.1 Introduction water body to bare minimum.
Water is one of the key inputs for thermal Large coal based capacity is required to be
power generation. Historically, thermal added during 12th Plan and beyond at the
power plants were located near water pace of about 15000 MW per year as per
bodies and adequate quantity of water the projections of Integrated Energy
was assured on sustained basis. With all Policy. This requires large number of new
Optimization of Land and Water Requirements For Thermal Power Plants Chapter 7: Page | 129
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
sites for setting up coal based power water is treated in clarification plant to
stations. Primary criteria for deciding produce clarified water which is used for
selection of sites is availability of land and clarified water applications such as
water. Much of the new capacity is cooling tower make up & service water
envisaged near pit-head due to economics etc. and as input water for DM plant &
of coal transportation and in coastal potable water system. The scheme of DM
regions. Difficulties are already being plant typically consist of pressure filters,
faced in selection of new sites due to non- cation exchanger, degasser, anion
availability of water, particularly in coal exchanger and mixed bed polisher. The
bearing states like Orissa, Jharkhand and scheme of potable water system consist
Chhatisgarh where large number of sites of filtration, chlorine dosing and any other
have been identified. Difficulties are also treatment as required to make water fit
being faced in finding coastal sites for drinking. The waste water generated
particularly on west coast. This problem is in various treatment sections (clarifier
expected to be aggravated in future when sludge, filter back wash and regeneration
more sites would be required. Thus there waste of DM plant etc.) is suitably
is a need to minimise water requirement recycled and reused with or without
in water scarce regions to enhance the treatment to the extent possible.
siting options for thermal power plants.
7.2.3 Water Requirement
7.2.2 Plant Water System
In a thermal power plant, bulk of the
The plant water system including cooling water is required for make up to the
water system depends upon source of condenser cooling water system and for
raw water. Cooling water system may be wet ash disposal. Other water
of once through type or closed cycle open requirements include power cycle make
recirculating type using cooling tower. For up, service and potable uses, coal dust
all inland plants based on fresh water suppression etc. The cooling tower blow
sources such as river, canal, lake, and down is used for disposal of ash.
reservoir, it is now mandatory to install
closed cycle cooling system employing Plant water requirement is governed by a
cooling towers. Open cycle cooling system number of factors such as quality of raw
is permitted only in coastal regions. Sea water, type of condenser cooling system,
water based cooling towers are also quality of coal, type of ash disposal
adopted at coastal sites depending upon system, waste water management
techno-economic considerations. aspects. Consumptive water requirement
for a typical 1000MW capacity plant with
The raw water input to the plant needs to different modes of ash handling system is
be treated to make it suitable for use in indicated in Table 7.3 below:
various plant applications. Typically, raw
Chapter 7: Page | 130 Optimization of Land and Water Requirements for Thermal Power Plants
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Table 7.3
Emergency – Wet
Emergency – HCSD***
* During initial period of plant operation till adequate utilization of fly ash is achieved, wet mode shall be
used for disposal of fly ash and additional requirement of water during this period shall be about 600 m3/h
over that indicated above.
** Cycle of Concentration
*** High Concentration Slurry Disposal
Dry cooling systems which do not involve atmosphere by cooling in finned tubes by
evaporation of water, thus not requiring air. Unlike wet cooling systems which
any make up water for condenser cooling operate with respect to ambient wet bulb
system can also be used for reduction of temperature and involve both sensible
plant consumptive water to a large and latent heat transfer, dry cooling
extent. systems operate with respect to ambient
dry bulb temperature and involve only
7.2.4.2 Optimisation in wet cooling system sensible cooling. Large surface area of
finned tubes is required for heat exchange
Wet cooling towers require make up in dry cooling system. The turbine back
water, the quantum of which depends pressure achievable in dry cooling system
upon cycle of concentration (COC) that is considerably higher than in wet cooling
can be maintained in the CW system. The system on account low heat transfer
COC to be adopted in the CW system coefficient and operation with respect to
primarily depends upon quality of make dry bulb temperature. Dry cooling
up water. Present practice is to use systems can be broadly classified in
clarified water as make up to the cooling following two categories :-
tower and operate the CW system at COC
of 5.0 with suitable chemical dosing so as a) Direct dry cooling systems
to optimize the plant water requirement. b) Indirect dry cooling systems.
This requires CT make up water of
typically 2 % of CW flow, and blow down In direct dry cooling system, steam
water to be effected from CW system exhaust from LP turbine is directly cooled
amounts to 0.35 % of the CW flow. in a system of finned tubes by ambient air
using mechanical draft fans. To reduce
The water for ash handling plant is tapped pressure drop in steam conveying system,
from available blow down water. In case, these units called air cooled condenser
requirement of ash handling plant is less (ACC) need to be installed close to the
than available blow down water from CW turbine hall. The finned tubes are
system, the balance blow down is led to generally arranged in the form of an ‘A’
the CMB of the plant. If water frame or delta over forced draft fans to
requirement of ash handling plant gets reduce the land area requirement.
further reduced viz. by adoption of dry
ash handling, recycling of ash pond water In an indirect dry cooling system, turbine
etc., there shall be increase in blow down exhaust steam is cooled by water in a
water to be disposed off to the CMB. The condenser which can be of surface type or
quantum of blow down water can be direct contact type and hot water is
reduced by increasing the COC of CW cooled by air in finned tube bundles
system which can be achieved by suitably utilizing natural draft tower. Because of
improving the chemical regime of water piping involved, these air cooled
circulating water. units can be located away from the main
plant. Heat exchanger elements are
7.2.4.3 Dry cooling system vertically arranged at base of the tower
Dry cooling systems refer to rejection of along its periphery with cooling taking
power cycle waste heat directly to the
Chapter 7: Page | 132 Optimization of Land and Water Requirements for Thermal Power Plants
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
place by air drawn by buoyancy of hot air system. Fly ash and bottom ash is
inside the tower shell. discharged to low lying ash pond in the
form of a lean slurry. As per requirement
Dry cooling technologies have higher of MOEF, ash pond water is to recovered
equipment cost and result in reduced and reused in ash handling system to
power output of the unit due to high conserve the water. Typically, 70% water
condenser back pressure leading to high can be recovered from the ash pond and
turbine cycle heat rate. However, these reused in ash handling plant. Thus,
technologies provide an option of locating requirement of water to be supplied to
the thermal plants in water scarce the ash handling plant from plant water
regions. There are considerable number of system gets reduced to this extent.
dry cooling installations including for large
size units (≥ 600 MW) operating in 7.2.5.2 Dry ash disposal
different parts of the world. In India, some
small size combined cycle plants, captive Wet ash disposal results in contamination
power plants and industrial units have of ground water on account of seepage
also provided with air cooled condensers. from ash pond, and areas surrounding the
pond are under threat for possible breach
In order to explore the possibility of of ash bund. Dry ash disposal overcomes
reducing the plant consumptive water these issues besides reduction in
requirement by application of dry cooling consumptive water and facilitates
system for condenser cooling in thermal utilization of fly ash in cement plants,
power plants, CEA, has set up a building material, landfill, embankments
committee with members drawn from etc. With progressive increase in
NTPC, BHEL, RRVUNL, MAHAGENCO, utilization in fly ash, the wet disposal of
CESC and TCE to examine the issue of dry ash is getting reduced. The plant water is
cooling system for condensers in thermal required only for wet disposal of bottom
power plants. The committee is expected ash which is about 20% of total ash
to suggest available options of dry cooling generation and part of fly ash which is not
systems for thermal power plants keeping disposed off in dry form.
in view various techno- economic aspects
involved. 7.2.5.3 Dry bottom ash handling
Optimization of Land and Water Requirements For Thermal Power Plants Chapter 7: Page | 133
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
used in one thermal power plant with unit DM plant & condensate polishing plant
size of 300 MW. etc. An optimized plant water scheme
requires that sludge water and filter back
7.2.5.4 High concentration slurry disposal wash water are recycled to pre treatment
(HCSD) system plant and other waste waters are utilized
to maximum extent in low grade
As the name suggests, HCSD refers to applications. The unutilized waste has
disposal of fly ash from coal fired thermal high TDS on account of CT blow down and
power plant to ash disposal area in the regeneration waste. If water is to be
form of high concentration slurry. The recovered from this waste water for
process is environmental friendly and recycling in the plant, its treatment would
involves pumping of high solids require application of reverse osmosis
concentration slurry with more than 60% technology to have maximum recovery of
solids by weight employing positive water and minimum quantity of
displacement pumps as compared to lean concentrated brine reject.
slurry transportation at about 20%
concentration. The slurry forms a natural 7.3 WATER SAVING
slope on the disposal area without need
for mechanical spreading and with As can be seen from above that various
minimal release of water and generates a possibilities exist for reduction of plant
stable and dry landfill. The water water consumption which need to be
consumption of HCSD system is lower by a applied on case to case basis. For plants
factor of about 6 as compared to water with wet cooling towers, water reduction
requirement by lean slurry disposal. can typically be achieved in an optimum
However, if recovery of water from ash manner by operating the CW system at a
pond is taken into consideration, there practically possible higher COC, recycling
may not be very substantial saving in of clarifier sludge water & filter back wash
water consumption as compared to wet in pre treatment plant, reduced
disposal method. consumption in ash handling plant and
maximum utilization of waste water.
7.2.6 Minimising Effluent Discharge These measures can result in plant water
saving of about 20%. If dry cooling system
Waste waters generated in a typical is adopted in combination with dry
thermal power plant include clarifier handling of ash, plant water consumption
sludge, filter back wash, CT blow down, can be reduced by about 80- 85%.
boiler blow down, regeneration waste of
----+++----
Chapter 7: Page | 134 Optimization of Land and Water Requirements for Thermal Power Plants
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Chapter 8
LOW CARBON GROWTH STRATEGY FOR INDIAN POWER SECTOR FOR 12th &
13th FIVE YEAR PLANS
Table 8.1
Installed Capacity ‘MW’ as on 31.12.2011
NUCLEAR, NEW
4780, 3% RENEWABLES,
20162.24, 11%
HYDRO,
38748.4, 20%
th th
Chapter 8: Page | 136 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
8.2 GENERATION MIX DURING 2010-11 665 BU thermal (including gas and diesel),
26 BU nuclear and 28 BU energy from
The energy generation during 2010-11 was Renewables. The generation break-up
839 BU comprising 120 BU hydro during 2010-11 is given below:
(including 5.6 BU imports from Bhutan),
Table 8.2
Energy generation during 2010-11
Chart 8.2
Hydro
Coal
Gas
Diesel
Nuclear
Coal, 564.2, 68% (MNRE)
It may be seen that share of fossil fuels in 8.3 CAPACITY ADDITION DURING 11TH
installed capacity is 65%, while the share of PLAN
the same in energy generation is 80%
indicating that the fossil fuel capacity has During the 11th Plan period (2007- 2012),
been operating at a higher PLF thus Planning Commission had set a capacity
generating more. Fossil fuels based addition target of 78,700, MW comprising
generation, as such is the back bone of 15,627 MW hydro, 59693 MW thermal and
Indian Power Sector. 3380 MW nuclear projects as summarized
in Table 8.3.
th th
Low Carbon Growth Strategy for Indian Power Sector for 12 and 13 Five Year Plans Chapter 8: Page | 137
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Table 8.3
As per the Mid Term Review, the likely commissioned during 11th Plan. The fuel-
capacity addition during the 11th plan wise break-up of likely capacity addition
period is 62,374 MW. A capacity of about during 11th Plan is summarized in Table 8.4.
44,000 MW has already been
Table 8.4
8.4 EMISSION FACTOR (kg/kwh of CO2) of generation as per actual during 2007-08
The weighted average emissions (tonnes and possible with latest technology are
of CO2/Mwh) fuel wise for different types indicated in Table 8.5.
Table 8.5
Weighted Average Emissions Fuel- Wise (tCO2/MWh) *
The actual emission factor and absolute for Indian Power Sector on the basis of
CO2 emission upto 2008-09 and likely total generation is given in Chart 8.3.
scenario by the end of 11th Plan (2011-12)
th th
Chapter 8: Page | 138 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Chart 8.3
It can be seen that emission factor has capacity addition by coal fired generating
been reducing over the years despite rise plants.
in CO2 emissions. It is likely to be around
0.739 kg/kwh by 2011-12 from 0.805 during 8.5 ELECTRICAL ENERGY REQUIREMENT
2002-03 (drop of about 9%) whereas total PROJECTION
emissions are likely to increase to 749 MT
during 2011-12 from the level of 429 MT The requirement of electrical energy by
during 2002-03 due to major increase in the end of 12th & 13th plan as per 18th EPS
report is shown in Chart 8.4.
Chart 8.4
2000 1904
Energy Requirement (BU)
1600
1354
1200 969
831 ER BU
800
400
0
2009-10 Actual 2011-12 11Plan 2016-17 12th 2021-22 13th
End Plan End Plan End
th th
Low Carbon Growth Strategy for Indian Power Sector for 12 and 13 Five Year Plans Chapter 8: Page | 139
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
To meet the power demand of the they have been considered as must run in
country during 12th & 13th Plan with as low the planning exercise.
increase in emissions as practicable, a Low
Carbon Growth Strategy has been (ii) Promote Renewable Energy
adopted in generation planning as including Solar Power
summarized below.
The Renewable Purchase Obligation
8.6 LOW CARBON GROWTH STRATEGY (RPO) has been notified by different
SERCs for respective states. The
Following are a few measures being Renewable Purchase Obligation (RPO) is
considered to ensure low carbon growth the obligation mandated by the State
during the 12th & 13th five year plans. Electricity Regulatory Commission (SERC)
under the Act, to purchase minimum level
(i) Promote Hydro Power of renewable energy out of the total
Development consumption in the area of a distribution
licensee. Feed in tariff for renewable
Development of hydro projects from energy has been notified by CERC and a
planning to commissioning takes a long number of State Electricity Regulatory
time and therefore advance planning of Commissions for different types of
hydro projects is necessary. CEA has renewable generation. To promote use of
prepared hydro development plan for the renewable energy, Renewable Energy
12th five year plan in Sept, 2008. All out Certificate (REC) mechanism has been
efforts were made to get timely Statutory proposed by CERC. REC is a market based
Clearances of Projects identified for 12th instrument to promote renewable energy
Plan capacity and to ensure placement of and facilitate renewable purchase
orders for main packages in 11th Plan itself obligations (RPO). REC mechanism is
so that projects could fructify during the aimed at addressing the mismatch
12th Plan. between availability of RE resources in
state and the requirement of the
Water & Water power is a state subject. A obligated entities to meet the renewable
large no. of hydro project sites have been purchase obligation (RPO).
allocated to public & private companies
for development. These projects are likely Jawahar Lal Nehru National Solar Mission
to be commissioned during 12th & 13th is a major initiative of the Government of
Plans. CEA has been monitoring the India to promote ecologically sustainable
progress of survey & investigation and growth while addressing India’s energy
preparation of Detailed Project Reports security challenge. It will also constitute a
and construction for these projects in major contribution by India to the global
close coordination with the developers. effort to meet the challenges of climate
change and tap the vast renewable
Based on the status of various hydro potential available in India from solar
projects, it has been estimated that a power. MoP and MNRE are finalizing
capacity of about 9200 MW could strategies for development of Solar
materialize during 12th Plan. In view of Projects totaling 1000 MW through
inherent advantages of hydro projects, NVVNL by 2013 which includes 200 MW
th th
Chapter 8: Page | 140 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Table 8.6
Additional gas requirement for 12th plan
The present allocation to power sector first two years of the 12th Plan is for tie up
from all domestic sources is about 79 long term contracts for RLNG for about 40
MMSCMD. Mo P&NG is probably not in MMSCMD for power sector. The current
position to indicate additional availability scenario in international market seems to
of gas from domestic sources during 12th be favourable for long term RLNG
Plan and will be in a position to indicate contracts. 40 MMSCMD for RLNG could
only after DPRs for the project be pooled with 79 MMSCMD indigenous
development are received by them. gas and supplied to the existing and new
However, they have indicated spare gas based projects on pooled price or
availability of LNG terminal capacity of allocated gas from indigenous sources
about 50MMSCMD by the end of the year and RLNG on pro-rata basis which
2011-12. effectively will result in same price of gas
for all the projects, new and old.
One option to develop new gas based
capacity which could come up during the
th th
Low Carbon Growth Strategy for Indian Power Sector for 12 and 13 Five Year Plans Chapter 8: Page | 141
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
(iv) Early notification of CEA regulation to get additional generation at low cost in
on construction of power plants short gestation period. Besides
indicating mandatory minimum generation improvement, it results in
efficiency levels improvement of environmental emissions
and improvement in availability, safety
CEA’s technical regulation for and reliability. To incentivise States, 50% of
construction of electrical plants and lines generation capability of the unit just
have been prepared and submitted to before shut down for R&M may be
MoP. These regulations indicate compensated by way of additional
mandatory minimum efficiency level of allocation from unallocated quota during
power plants and transmission the normative period of shut down. Low
equipments. interest rate financing for enhanced
efficiency based R&M has also been
(v) Retirement of Old and Inefficient initiated.
Coal based Generating units
Retirement of Old and Inefficient thermal (vii) Adoption of Clean Coal Technology
Plants and replacing them with new and
more efficient units is an effective way of As per Low Carbon Growth Strategy,
using the fuel and minimizing GHG adoption of clean coal technology which
Emissions. During the 11th Plan 1500 MW of includes addition of Super Critical units,
capacity is to be retired. This comprises of promotion of IGCC, CFBC technology is
coal and lignite units of unit size lesser being adopted for future plans. During the
than 100 MW. 12th Plan about 50% of Coal based capacity
is being planned on super critical and in
A capacity of about 4000 MW is proposed 13th Plan it has been proposed that all
to be retired during the 12th and 13th Plan coal based capacity is to be based on
each which includes the remaining units of super critical technology. In this regard
coal & lignite under 100 MW, gas plants following action has been taken/required
more than 30 years old (1987 & before) to be taken.
and some coal based units of 110 MW
capacity. Action:
th th
Chapter 8: Page | 142 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
(d) Bulk tendering for projects based modest degree of energy self-sufficiency
on Ultra super critical technology suggests the need to pursue the
with mandatory indigenous development of nuclear power using
manufacturing by 2011-12 may be thorium. India can erect and run nuclear
taken up in consultation with plants to a capacity of 60GW by 2031-32.
indigenous manufacturers. The full development of the country’s
(e) MOEF may be advised not to hydro-electric potential and realization of
clear any Coal based projects the optimistic nuclear scenario by 2031-32
w.e.f. 01-04-2012 on Sub-critical needs to be persued.
technology. No coal linkages for
Sub-critical plants for 13th Plan With the signing up of the '123
(f) It is proposed that on Super Critical Agreement' on nuclear cooperation
Plants there should not be any between USA and India, and NSG’s waiver
custom duty and excise duty i.e. for supply of nuclear fuel to India, it is
the same exemption for excise expected that some nuclear plants with
duty and custom duty as foreign technology from friendly
applicable to Mega Power countries would be set up in the country.
Projects. The availability of imported nuclear fuel
and technology to India will help in
(viii) Nuclear Power Generation accelerated capacity addition from
nuclear power plants. Commencement of
Nuclear generation is also limited due to construction of reactors with imported
availability of natural uranium in the technology during 11th/12th Plans is
country. Department of Atomic Energy expected which will get commissioned in
plans to put up a total installed nuclear 13th Plan onwards. Development of
power capacity of 20,000 MWe by the nuclear parks with Mega capacity is also
year 2020 in the country. As of now, the anticipated. Integrated Energy Policy
first stage programme based on indicates two scenarios of nuclear
indigenous fuel is in progress and has capacity addition of about 48,000 MW in
reached a stage of maturity. A beginning low nuclear scenario and 68,000 MW in
has been made of the 2nd stage high nuclear scenario by 2031-32.
programme with construction of 500
MWe PFBR (Prototype Fast Breeder (ix) Reduction of T&D losses to be
Reactor). This is expected to be followed accorded high priority
by four more 500 MWe units by the year
2020. Thereafter it will be followed by a All India T&D Losses are very high of the
number of FBRs. When the capacity order of 29.24 %. To reduce T&D losses,
through FBRs builds up to reasonable implementation of R- APDRP to reduce
level, the deployment of thorium for technical and commercial losses are being
power generation through 3rd stage will accorded highest priority.
begin and get realized in the long term. Privatization/franchisee of distribution
should be encouraged as these measures
Although nuclear energy can make only a are expected to help in reducing AT&C
modest contribution over the next 15 Losses.
years, longer-term consideration of even a
th th
Low Carbon Growth Strategy for Indian Power Sector for 12 and 13 Five Year Plans Chapter 8: Page | 143
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Table 8.7
Chart 8.5
th th
Chapter 8: Page | 144 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
37.0 35.96
36.0
35.21
35.0
33.86
34.0
33.0
32.0
End of 10th End of 11th End of 12th End of 13th
Plan Plan(with Plan( with Plan( with
retirement) retirement) retirement)
This increase in efficiency of thermal units Studies have been carried out for 12th &
will result in reduced emission factor 13th plan periods taking into account the
further. Further reduction is expected due existing capacity, committed capacity
to increase in generation from nuclear, during the 11th Plan that is a feasible
hydro and renewable resources under capacity of 62,374 MW and the options
various scenarios as listed below. already available for 12th Plan. Capacity
addition required has been assessed to
8.8 CAPACITY ADDITION REQUIRED meet the seasonal requirements also.
DURING 12TH & 13TH PLANS
Hydro capacity has been restricted to the
Three Scenarios have been developed for feasible capacity of 9204 MW in the three
capacity addition during 12th & 13th Plan different scenarios. Retirement of old
periods. They are Business as Usual inefficient units also has been considered
Scenarios with low gas and low renewable as given in the table of capacity addition.
Scenarios. Business as Usual Scenarios i.e. Renewable capacity has been assumed to
SC-1 is the Base Case. The capacity operate at 20% PLF.
addition required during 12th & 13th Plan
has been worked out based on the results Based on results of the studies,
of the Planning studies carried out using generation capacity addition required
EGEAS software model. during 12th & 13th Plans are summarised in
Table 8.8 & 8.9 below:
Table 8.8
th th
Low Carbon Growth Strategy for Indian Power Sector for 12 and 13 Five Year Plans Chapter 8: Page | 145
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Table 8.9
Capacity Addition Scenario-13th Plan
8.9 EMISSION PROJECTIONS UPTO THE On the basis of generation from each fuel
END OF 13th PLAN (2021-22) sources, carbon footprint i.e. Emissions
and the emission factor intensity
th th
Chapter 8: Page | 146 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
considering base year of 2004-05 have considered and the average emission
been worked out, The Electrical factor from total generation are shown in
generation growth during the plans Chart 8.6 below.
Chart 8.6
Average Emission Factor from Total Generation (Kg/kWh)
It may be seen that the average emission of 2004-05 due to various measures
factor is expected to reduce in the range mentioned above. However, the total
of 6.6 % to 20.3 % by the end of 13th Plan emission from power sector would
(2021-22) in three scenarios from the level increase as shown in Chart 8.7 below:
Chart 8.7
Total CO2 Emission (MT) from Thermal Generation
Table 8.10
Emission Intensity based on Power Sector Emissions
Table 8.11
th th
Chapter 8: Page | 148 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Scenarios End of 10th End of 11th Plan End of 12th Plan End of 13th Plan
Plan (2006-07) (2011-12) (2016-17) (2021-22)
(Actual)
Scenario-1 8.1 19.9
Scenario-2 5.1 4.9 9.4 21.8
Scenario-3 10.6 24.3
---+++---
th th
Chapter 8: Page | 150 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Chapter 9
Table 9.1
Type Wise Capacity Additions during 12th Plan
(Figs in MW)
th
Item 12 Plan (2012-17)
Coal based 66,660
Gas based 1,086*
Hydro 9,204
Nuclear 2,800
Total 79,690
* - Gas from local sources
th
Key Inputs for 12 Plan Chapter 9: Page | 151
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
As per the information compiled by CEA, Steel and cement are the key materials
sufficient numbers of vendors are needed for power projects. In case of
available for major BoPs. both hydro and thermal projects, the
requirement of steel and cement are site
NUMBER OF BOP VENDORS specific and the civil engineering works
Coal handling System 15 vary from project to project depending
Ash Handling System 13 upon the features of the projects. In case
Cooling Towers 12 of thermal projects, the civil works would
DM Plants 18 be more when the first unit of the thermal
project is installed on a virgin site than for
Few suggestions regarding BOP an additional unit installed at the same
equipment for ensuring timely capacity site. However for the purpose of
addition are as follows: estimating the requirement, suitable
• Developers may execute BOPs on consumption norms have been worked
EPC basis. out based on the actual consumption of
• A web based portal needs to be steel and cement for the works
designed and managed for all completed during the past and also in
information relating to BOP respect of projects under execution. In
view of this, the assessment of steel and
vendors viz. orders at hand, their
cement required for hydro and thermal
implementation status etc. so that
projects in 12th Plan would be only
developer of projects can take an approximate.
informed decision.
• In second phase the BOP vendors
and Construction agencies could
th
Key Inputs for 12 Plan Chapter 9: Page | 153
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Table 9.2
Norms for Key Inputs
(Figures in Tonnes/MW)
Table 9.3
Key Inputs for 12th Plan
(Figures in Million Tonnes)
Sl. No. Materials Thermal Capacity Hydro Total
Capacity
Coal based Gas based 9204
66,660 MW 1,086 MW MW
1. Cement 9.9 0.065 8.80 17.76
2. Structural steel 5.66 0.0097 0.31 5.92
3. Reinforcement steel 2.99 0.026 0.86 3.87
4. Stainless steel 8.70 0 8.7
5. Aluminium 0.033 0.056 0.001 0.09
th
Chapter 9: Page | 154 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Table 9.4
Key Inputs for 13th Plan
(Figures in Million Tonnes)
Sl. No. Materials Thermal Capacity Hydro Total
Capacity
Coal based No Gas 12000
49,200 based MW
MW considered
1. Cement 7.38 11.47 18.85
2. Structural steel 4.18 0.41 4.59
3. Reinforcement steel 2.21 1.12 3.33
Table 9.5
Key Inputs for 13th Plan Nuclear
(Figures in Million Tonnes)
th
Material 12 Plan 13th Plan
2800 MW 18000 MW
Cement 0.55 3.51
Structural Steel 0.31 1.99
Reinforcement Steel 0.16 1.05
The main inputs for manufacturing regarding these key inputs are given in
power plant equipment are castings & the following Tables.
forgings, steel plates, structural steel,
copper, CRGO/CRNGO etc. While Steel, Castings & Forgings for Turbo-
Cement, Copper, Aluminium etc. are the Generators (TG) Sets:
key inputs needed for erection & As per the details provided by BHEL the
commissioning and transmission & average requirement of castings and
distribution networks. Some estimates forgings for a 500/660/800 MW sets is
as given below:
MT per Set
Equipment Weight of Castings Weight of Forgings
Turbine 384 235
Generator 3 130
Total 387 364
th
Key Inputs for 12 Plan Chapter 9: Page | 155
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
The requirements of Castings and per the projections given by CEA, 60%
forgings for thermal projects, based on supercritical sets have been assumed in
the above average, for the 12th and 13th 12th Plan and 100% supercritical sets
Plans works out to be as given under. As have been assumed for 13th Plan.
Lakh MT
th th
Material 12 Plan 13 Plan
67746 MW 49200 MW
Castings 0.39 0.29
Forgings 0.36 0.27
Note: As norms for nuclear projects are
not received, requirement for nuclear is As per the details provided by BHEL, the
not included. Also, requirement of average requirement of Tubes & Pipes
casting & Forgings for Hydro projects and Thick Boiler Quality Plates
are very project specific, hence not (Imported Plates) is given below. As per
included. the projections given by CEA, 60%
supercritical sets have been assumed in
Sufficient indigenous capacities for 12th Plan and 100% supercritical sets
heavy castings & forgings need to be have been assumed for 13th Plan.
created to reduce dependence on
imports.
Lakh MT
Material 12th Plan 13th Plan
67746 MW 49200 MW
Material 12th Plan 13th Plan
67746 MW 49200 MW
Lakh MT
th th
Material 12 Plan 13 Plan
Tubes & Pipes 3.8 4.2
Thicker Boiler Quality Plates - -
th
Chapter 9: Page | 156 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
As per the information provided by FIMI consumption for 12th plan is given
for Copper, the capacity, production and below:
Lakh MT
Year Capacity Production Consumption
2012-13 10.0 8.0 8.8
2013-14 10.0 8.5 9.8
2014-15 15.0 13.2 11.0
2015-16 15.0 13.5 12.3
2016-17 15.0 13.7 13.3
Aluminium:
Following norms for the Aluminium requirement as projected by CEA have been
considered for working out Aluminium requirement:
th
Key Inputs for 12 Plan Chapter 9: Page | 157
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
destination. Therefore development of the projects also needs to be set up. With
mines/ ports and requisite transportation this objective in view, the assessment of
facilities commensurate with the fuel requirement has been carried out.
completion of the projects is very
necessary. The gestation period in the The coal requirement for thermal power
development of mines and even transport stations depends upon the scheduled
generation, quality of coal being supplied/
facilities are in some cases longer than the
to be supplied and the condition of power
gestation period for setting up of thermal station equipment. However the
power stations. It is therefore imperative normative requirement of fuel during the
for the Power Sector to make its terminal year of 12th Plan has been
prospective coal requirement, over a long estimated based on following Norms:
time horizon, known to the Ministry of
Coal, Railways and port authorities to a) 5 MT of coal per 1000 MW per year.
b) 4.8 MMSCMD gas per 1000 MW at 90
enable them to undertake co-ordinated
% PLF.
development of coal mines and transport
infrastructure with the coming up of Details of fuel requirement during
thermal power stations. Necessary terminal year of 12th Plan are summarised
infrastructure required to transport gas to below:
Table 9.6
th
Chapter 9: Page | 158 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
as adopting basic changes in load and Western DFC (JNPT, Mumbai- Dadri, UP)
handling specifications in Roads, Railways have been sanctioned. Apart from above
and Port sectors. Railways have also planned Gauge
conversion, new railway lines,
Railways electrification of new routes and
procurement of locomotives and wagons.
The long-term strategy of Indian Railways
is to segregate the freight and passenger Broadly, Railways envisage the following
movement through construction of targets for the medium and long-term
Dedicated Freight Corridors (DFCs). At goals (XII five year plan & beyond)
present two DFC projects i.e. Eastern DFC towards creation of infrastructure and
(Dankuni, WB - Ludhiana, Punjab) and capacity build-up.
Table 9.7
th
Key Inputs for 12 Plan Chapter 9: Page | 159
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Table 9.8
The expansion plans detailed in the Vision movement by IWT of 3.0 million tonnes
2020 documents of Railways gives a sense per annum from Haldia to Farrakka
of confidence that to a large extent Project of NTPC is a success. At present,
Railways will be able to meet Power ten thermal power stations are
Sector requirements for 12th Plan and operational on the banks of Ganga and
beyond, provided of course that their these are located in the States of West
expansion takes place as per their vision Bengal (7) and Bihar (3). Further eleven
document. more Thermal Power Stations are
proposed in Bihar and Uttar Pradesh with
Inland Water Transport installed capacity of over 15000 MW. Their
coal requirement is estimated to be
Inland Waterways Authority (IWT) of India around 70 million metric tonnes per
has planned for the development, up- annum, which can be met through IWT.
gradation, modernization and expansion
of National Waterways / other Waterways National Highways
during 12th plan period with an estimated
investment of Rs. 10,460 Crores. Keeping The National Highways comprise of only
this in view, there is a strong possibility of around 2% of the total Road Network in
coal cargo movement through IWT India but carry more than 40% of the
becoming attractive to power companies Traffic. This makes route management of
especially if the contract of imported coal heavy Over Dimensional Consignments
th
Chapter 9: Page | 160 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
th
Key Inputs for 12 Plan Chapter 9: Page | 161
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
8700 km with design capacity of about competitive bidding through EOI route.
209 MMSCMD. PNGRB has received 06 EOIs for setting up
of additional gas pipelines. These are (as
(A) GAIL :
per PNGRB website):
These pipelines are under different stages Keeping in view the estimated capacity
of development. addition of 79,690 MW, the coal quantity
to be imported by the end of 12th plan
Establishment of PNGRB: The Petroleum works out to about 218 MT including the
and Natural Gas Regulatory Board requirement for power plants that would
(PNGRB) Act 2006 provides for the be operating completely on imported
establishment of an independent coal. Based on the Maritime Agenda for
regulatory board (PNGRB) as a Ports, issued by the Ministry of Shipping,
downstream regulator to regulate the major and non major ports together are
activities of companies related to refining, targeted to handle 476.04 Million Tonnes
processing, storage, transportation, of Thermal and Coking coal combined by
distribution, marketing and sale of the end of 12th Plan. Moreover in order to
petroleum, petroleum products and augment the capacity and enhance
natural gas and City Gas productivity levels at major ports, several
Distribution(CGD). The board has been initiatives are being taken by the Ministry
established and started functioning w.e.f. of Shipping including modernisation of
June 2007. The PNGRB have formulated port infrastructure, construction of new
several regulations pertaining to gas berths/ terminals, expansion/ up-
transportation. PNGRB is authorising gradation projects for berths and
entities for laying pipeline on basis of dredging, installation of new and modern
th
Key Inputs for 12 Plan Chapter 9: Page | 163
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
th
Chapter 9: Page | 164 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
9.5.2 Manpower requirement during 12th distribution are required. The personnel
Plan engaged in construction area in the Power
sector during 11th Plan would be adequate
The targeted capacity addition during the to meet the requirement in construction
12th Plan is presently pegged at around during 12th Plan. The category-wise break-
80,000 MW. It has been estimated that up of the Manpower Requirement is
about 5.1 Lakh additional personnel in shown in Table 9.10
O&M of generation, Transmission &
Table 9.10
Table 9.11
th
Key Inputs for 12 Plan Chapter 9: Page | 165
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Through plant specific on-plant, on- The details of assumptions for estimation
site training at power station/sub of cost of generation projects are given as
station, manufacturer’s site. Appendix 9.1.
Through correspondence courses and In addition, funds are also required during
distant learning packages. the 12th Plan for advance action for 13th
Maintenance skill development Plan projects which has been assessed as
through ‘Hands-on’ training on actual 2,72,582 crs. Details of total fund
plants, or obsolete/ redundant requirement for capacity addition during
equipment. 12th plan are as follows:
th
Chapter 9: Page | 166 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Table 9.12
Total Fund Requirement for Capacity Addition during 12th Plan
The total fund requirement for Generation Captive and Renewable capacity additions
Projects during the 12th Plan is 643,831 Crs. Matching funds are also required for
This fund requirement does not include transmission & Distribution sector.
funds required for R&M of power plants,
----+++----
th
Key Inputs for 12 Plan Chapter 9: Page | 167
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Appendix 9.1
Phasing of expenditure of generation projects during the project construction period, which are
expected to be commissioned in 12th Plan is given as follows:
Phasing of expenditure of generation projects during the project construction period, which are
expected to be commissioned in 13th Plan is given as follows:
th
Chapter 9: Page | 168 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Chapter 10
10.0 BACKGROUND
The erstwhile State Electricity Boards
Government of India has taken a number have been unbundled into separate
of Initiatives to adopt a more pro-active, generation, transmission and distribution
market oriented approach to rid the companies. While this Initiative is
Power Sector of the problems being faced expected to be instrumental in making the
by it. These range from changing the power business economically viable, the
structure of the Power Utilities to the States have a very important role to play
operating environment and the Legislative in carrying out integrated planning of the
and Regulatory framework governing the entire electricity chain from generation to
Power Sector. Most significant changes the ultimate consumer such that all the
have been the unbundling of the vertically systems are adequate and are set up
integrated business of generation, within a matching timeframe. This
transmission & distribution and the entry Chapter outlines the planning to be
of private sector in power generation, undertaken by each state in a cohesive
transmission & distribution. These manner.
Initiatives are expected to set the stage
for a quantum jump in the capacity 10.1 CREATION OF STATE ELECTRICITY
addition programme and also making BOARD
electricity available to all including rural
households. The beginning of power supply industry in
the country was through private
The Electricity Act 2003 envisages a strong entrepreneurial initiative and as a principle
push to the structural reforms, de- the generating plants were established
licensing, thrust on rural electrification, close to load centres. The emergence of
incentives to reforming States and grid systems to connect and operate the
importantly mandatory metering with isolated generating units to improve
stronger provisions for punishment for economics and reliability of supply was
theft of electricity. The National Electricity recognized during the forties. A
Policy and the Tariff Policy further provide comprehensive legislation to restructure
guidelines for the development and the power supply industry was made with
operation of the Power Sector within the the enactment of the Electricity Supply
ambit of the Electricity Act. Act 1948. This Act provided for the
creation of State Electricity Boards (SEB) all the Stakeholders as well as it is put up
with the responsibility of promoting on the CEA Website inviting comments of
generation and supply in an efficient and all. The Plan is finalised based on
economic manner and extension of power comments received, as considered
supply facilities in the country. The role of appropriate.
Private Sector for development of Power
at this stage was minimal with private The National Electricity Plan is prepared to
entrepreneurs only in Ahmedabad, serve as a road map towards optimum
Calcutta and Bombay being in the field. growth of the Power Sector. It is based on
an approach of integrated resource
10.2 ELECTRICITY ACT 2003 AND planning so as to optimally utilize the
NATIONAL ELECTRICITY POLICY resources including investments already
made. The Plan is evolved as a result of
Enactment of the Electricity Act, 2003 was detailed studies carried out using
aimed at addressing the problems which sophisticated generation planning
were plaguing the Power Sector in the software models available with CEA. The
past. The Act envisages development of Plan contains project-wise details of
the Power Sector in a market driven capacity addition as well as the fuel type
environment, keeping in view the interest of each project. Generation as well as
of the consumers as well as of the Transmission aspects are covered by the
suppliers of power. Generation has been Plan.
delicensed and Open access in
transmission and distribution has been 10.3 RESTRUCTURING OF THE POWER
stipulated. SECTOR
The National Electricity Policy was Creation of the State Electricity Boards
formulated to act as a functional lever to (SEBS) in the fifties was extremely
facilitate implementation of the Act beneficial for the development of the
towards providing the required thrust to Power Sector. Each State developed its
the Power Sector. integrated system from the power plants
to the transmission and the distribution
Section 3(4) of the Electricity Act 2003 network. This facilitated the reach of
mandates CEA to prepare the National electricity to a wide spatially distributed
Electricity Plan in accordance with the area of the country.
National Electricity Policy. The Plan is
expected to function as a facilitating lever However with time, the performance of
for implementation of the Electricity Act the SEBs deteriorated and they gradually
2003 in keeping with its true spirit. The became financially unviable due to
draft Plan prepared by CEA is circulated to mounting losses. This adversely affected
their developmental plans and the States transmission and distribution system.
started facing increasing power deficits. Short term and Long term Plans need to
This prompted the Government to be evolved for each State. Some of the
unbundled the States into separate specific reasons for this are as follows:
Generation, Transmission and Distribution
Corporations, each being a separate a) Each State has a varying Load
financial entity. Regulatory Commissions dispatch curve which has to be met by
were also set up in each State under setting up baseload as well as peaking
whose regulatory oversight the operation power plants. Even though the country is
and development of each State took expected to operate in an All India grid by
place. 2012, each State is expected to be
responsible for setting up adequate base
The main problem experienced after load as well as peaking generation
unbundling of the SEBs is that since in capacity. It is therefore necessary for each
each State generation, transmission and State to carry out short term as well as
distribution are under separate long term planning. Long term Plans
Corporations, no coordinated short term covering a period of 10 years are very
or long term planning is being done in important since some power projects
most of the States. This is expected to be specially hydro projects are long gestation
extremely detrimental to the overall ones. Also the planning process needs to
power scenario in the country. ensure that , at potential sites for storage
type of hydro projects these projects are
Earlier, the development in each State built rather than run of the river projects
was in accordance with the planning as these provide peaking power.
exercise being done by CEA. However
subsequent to the Electricity Act 2003, the b) Adequate transmission
developer of a power plant does not network needs to be set up in the same
require any clearance from CEA for setting time frame as the associated generation
up a thermal or a hydro power plant project. Also since the Act and the Policy
below a certain financial limit. Therefore provides for Open Access, sufficient
most of the States do not have a regular transmission capacity needs to be created
planning philosophy or developmental to ensure open access to all consumers as
Plans for their system. required.
reliable power, planning may be carried on a priority basis, after considering cost
out for the distribution system also. As and benefits, to facilitate creation of
per the Electricity Act, 2003 it is the prime network information and customer data
responsibility of the Distribution Company base which will help in management of
to develop their distribution network by load, improvement in quality, detection of
carrying out short term and long term theft and tampering, customer
studies to optimize the system network to information and prompt and correct
provide least cost solution, to ensure billing and collection.
voltage at various nodes within stipulated
limits as per IE Rules, Minimise energy 10.5 PROPOSAL AND RECOMMENDATION
losses in the distribution network, FOR SINGLE AGENCY IN EACH STATE FOR
Improve quality and reliability of power INTEGRATED PLANNING
supply etc. Because of multiple agencies
in one supply area, there is a need to have With a view to facilitate coordinated
one single agency to ensure integrated planning in each State covering all aspects
planning for fulfilling the above objectives of the power system, it is necessary to
This agency would coordinate with the have a Single Nodal Agency in each State
developers of generation, transmission, for this purpose. This Agency shall be
distribution and other agencies if any. This designated by each State. It may be
would facilitate development of a robust, effective for the energy department of
most economical and reliable system. the State to perform this function. CEA
shall be the consultant to this Nodal
d) Modern information Agency as it has the requisite expertise for
technology systems need to be planning and is equipped with the suitable
implemented by the distribution utilities software planning tools for this purpose.
----+++----
Chapter 11
FUEL REQUIREMENT
11.0 INTRODUCTION
Fuel for the power project is the main timely completion of the project and
input required to be tied up before therefore avert detrimental implications
implementing the power projects. Coal is of cost and time overruns in case the
the main fuel for the Indian Power Sector power project is delayed.
and it is expected that coal will continue
to dominate the power sector in the next This Chapter broadly deals with a review
few Plans as well. An important aspect of fuel availability during the 11th Plan, an
which therefore needs to be considered is assessment of requirement of fuel for 12th
the availability of adequate coal to fuel Plan & indicative requirement for 13th Plan
the generation of power. Inadequate as well as critical issues which need to be
availability of coal will result in stranding addressed/ constraints being experienced
of generation capacity causing wastage of in the coal sector. This would give
sunken capital expenditure as well as the sufficient inputs to other Ministries and to
perpetuation of power deficit conditions the industry to enable them to take
in the country. Many existing power advance action and plan their production
plants are experiencing generation loss targets etc. according to the requirement
due to non availability of adequate coal. of the Power Sector.
Import of coal is therefore inevitable for
power generation. The timely supply of all 11.1 REQUIREMENT OF COAL
key inputs including fuel would ensure
11.1.1 Coal is the mainstay of India’s of various initiatives being taken by the
energy sector and accounts for over 50% Ministry of Power. The PLF has increased
of primary commercial energy supply. The from 57.1% in 1992-93 to 75.37% in 2010-11.
total power generation capacity ( Utility) This has increased the demand of coal per
of the country is about 1,82,689 MW MW of installed capacity. The growing
as on 31.10.2011, out of which about gap between the demand and the
1,00,098 MW (55%) is coal fired. Of the domestic supply of coal has made it
total power generated in the country, 69% imperative to augment domestic
comes from coal based thermal power production both from public sector and
stations even though they constitute only private sector and expedite the reform
55% of the total installed capacity. The process for realizing efficiency gains
Plant Load Factor (PLF) of the thermal through increased competition in the
power stations in the country has been sector during the 11th Plan.
improving steadily over the years in view
11.1.2 The Government has introduced the corresponding to 42.5% for 5 years for
New Coal Distribution Policy (NCDP) that generating stations having PPA for supply
assures supplies at pre-determined prices of power for 25 years.
to some categories of consumers and
reintroduces e-auctions to encourage a 11.1.3 Coal Stocking Norms:
vibrant market for the commodity. The
Main Features of the Policy which is Coal stocking norms for power stations as
effective from 1st April 2009 are as fixed by a Committee headed by
follows: Secretary, Planning Commission depend
on the distance of the power plant from
– 100% Normative Requirement of coal the pit-head as per details given below:
would be considered for supply to
Power Utilities Pit-head Station
– Supply of coal through commercially 15 days’ stock
enforceable Fuel Supply Agreements Upto 500 Kms. away from Coal mine
( FSAs) at notified prices by CIL. 20 days’ stock
– 10% of annual production of CIL to be Upto 1000 Kms. away from Coal mine
offered through e-auction for 25 days’ stock
consumers who are not able to Beyond 1000 Kms. away from Coal
source coal through available mine 30 days’ stock
institutional mechanism.
– FSAs to indicate Annual Contracted 11.1.4 Import of coal
Quantities (ACQ) of coal to Power
Utilities by coal companies during In the past, Power Utilities were advised
entire year. Incentive and penalty to import coal to maintain the stipulations
clauses incorporated in FSAs. of Ministry of Environment and Forest
regarding use of coal of less than 34% ash
Signing of Fuel Supply Agreement (FSA) content and also to occasionally
for the Units Commissioned after 31st supplement the coal from indigenous
March, 2009: sources. The quantity of coal imported by
the power stations during the previous
For thermal power plants commissioned years is as given below:-
before 31st March, 2009, FSAs were (In Million Tonnes)
signed with a trigger value of 90% of the Year Target Actual
Annual Contracted Quantity (ACQ). 2004-05 10.0 4.5
2005-06 13.5 10.4
FSAs for thermal power plants 2006-07 20.0 9.7
commissioned after 31st March, 2009 2007-08 12.0 10.2
have not been signed , primarily due to 2008-09 20.0 16.1
CIL’s insistence for (a) keeping the 2009-10 28.7 24.6
assured supply as low as 50% of ACQ and 2010-11 35.0 30.5
(b) signing the FSA for 5 years. ACQ for 2011-12 55.0 33.7(Upto
new power plants generally being Dec, 2011)
commensurate with 85% PLF, this will
tantamount to assured supply of coal
Exhibit 11.1
TYPE WISE CAPACITY ADDITIONS DURING 12th PLAN
(Figs in MW)
TYPE 12thPlan Capacity
th
(With 18 EPS demand + 5% S.R.) (MW)
Hydro 9,204
Thermal 67,686
Coal 66,600
Gas 1,086
Nuclear 2,800
TOTAL 79,690
Wind 11,000
Solar 4,000
Other RES 3,500
TOTAL (RES) 18,500
Retirement During 12th Plan 4,000
Coal demand and availability during 12th accorded to maximize generation from
plan other conventional and non-conventional
sources, coal based generation is likely to
Availability of coal for the coal based be the main stay of electricity generation
thermal power stations is a matter of for 12th and 13th Plan to support the
serious concern. Although thrust is being targeted GDP growth envisaged by the
value basis. This could be a deterrent to facilities at power stations to the extent
the Power Utilities at coastal areas which possible.
would be asked to use a higher chunk of
imported coal as it will increase their cost Pooled price is to be evaluated based on
of generation. the heat value(Rs/Kcal) of the coal. CIL
shall be responsible for importing coal
A case, therefore, exists for importing and levying the pooled price on the
coal to bridge the gap between various power utilities. This is reasonable
requirement and availability of domestic in view of the fact that the New Coal
coal and the cost of the same to be Distribution Policy stipulates that CIL is
equitably borne by all the power utilities. responsible for meeting 100% of the
It may however be mentioned that the normative requirement of coal of the
concept of pooling cost is to be applicable power utilities, and import of coal may be
to power stations designed for domestic resorted to the extent required.
coal only. Imported coal based stations
and stations linked to dedicated coal Demand side management of Coal
blocks are not to be considered in this
pooling mechanism. All the new units planned in12th plan
(excluding which are already under
Following categories of power plants may construction) thrust to be given for super
be accorded higher preference for critical technology, which will result in
utilizing imported coal (subject to 15% saving of about 5-8 % of fuel requirement
blending with imported coal for existing and correspondingly less emission. As,
stations and upto 30% blending for new coal is increasingly becoming a scarce
stations) under the pooling of price resource, India’s long term fuel security
concept:- depends on its efficient utilization. In
Coastal power stations order to optimally utilize coal, efficient
Stations where availability of coal consumption (heat rate and auxiliary
indigenous coal is a major consumption) norms be used for
constraint. according linkage (FSA).
Stations situated at long distances
from pithead e-Auction of coal
Stations which have to comply
with MOEF stipulations on ash As per NCDP, around 10% of total
content. domestic coal production is allowed for e-
Auction by CIL. It is to be ensured that
The above are to be prioritized before offering 10% quantity, FSA/MOU
considering the existing coal handling commitments are met with. The issue of
rail connectivity to such mines from
where coal for e-auction is sourced should to coal conservation thereby maximising
be taken up immediately. percentage of coal recovery from
geological blocks.
Coal Regulator
The Regulator must standardise norms of
A need is being felt for long to institute an operation, establish benchmarks and
independent regulatory body to regulate ensure that coal companies raise their
the upstream allotment and exploitation level of competence to be at par with
of available coal blocks to yield coal, coal international standards.
bed methane, coal-to-liquid and for in-situ
coal gasification. The proposed The proposed Coal Regulator should also
Regulatory Body, as an interim measure, be entrusted with following aspects of
may approve coal price revisions, ensure coal mining:
supply of coal to the power sector under Coal Resources Management
commercially driven long-term FSAs, Safety, Health, and Employment in
facilitate the development of coal mines
formulae/indices for resetting coal prices Prices, Taxes, Royalty, Value Added
under long-term fuel supply agreements, Tax, Property Tax, and Salary of
monitor the functioning of the proposed Workers
e-auctions, ensure that the price discovery Environment Management
through e-auctions is free of distortions, Policy-Legal, Public Relations,
regulate trading margins, develop a Statistics, and Dispute Resolution
mechanism for adequate quantities of Recommendation to CIL for issuance
coal imports under long-term contracts to of LoAs
bridge the gap between supply and Approval of mine plans including mine
demand thereby assuring that the e- closure plans
auctions and consequent price discovery Optimization of current linkages to
does not take place in a supply minimize Rail/Road transportation
constrained market and, finally, create the Oversight role on captive coal block
environment for a competitive coal auctions
market to operate.
Dispute resolution - primary forum for
:
Once a competitive market is developed,
dispute resolution among entities;
the role of Regulator in determining the
entities aggrieved due to decisions
prices would be to ensure a free and
given by MOC/MOEF relating to mine
transparent market for coal. The
closure, etc.
Regulator must ensure that mines are
planned, designed and developed in a
scientific manner giving due importance
Fuel Requirement Chapter 11: Page | 183
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
State Total[MT]
Rajasthan 4835.29
Gujarat 2722.05
Total 40905.86
Table -7.7
Lignite Demand & Production Plan by M/s. Neyveli Lignite Corporation Ltd. (NLC)
Brief year-wise anticipated demand & companies (other than NLC) during
production plan of Lignite by other 12th five year plan period are shown
State Electricity Boards and private below (TABLE 7.8).
Table 7.8
Lignite Demand & Production Plan by State Electricity Board
(ii)Supply of Gas to Gas based power demand of gas in the country, including for
plants: that of power sector. Supply of gas to gas
based power plants during last few years
The production and supply of gas had not had been as under:
been keeping pace with the growing
Table 7.9
was sufficient to operate these stations at generation was augmented by use of such
about 63.73% PLF. fuels. On account of the prevailing high
costs of liquid fuels resulting in high cost
(iii). Generation loss due to gas shortage of generation, the actual generation using
these fuels was, however, dependent
There was a shortage in availability of gas. upon the requirement/acceptance by the
This resulted in loss of generation of beneficiaries. Loss of generation due to
power. In case of gas based power shortage in availability of gas as reported
stations having provision for the use of to CEA and based on possible operation of
alternate fuels, such as naphtha, HSD, power plants at 90% PLF were as under:
Table 7.10
basins of the country under the New Prices” under the Chairmanship of
Exploration Licensing Policy (NELP). Saumitra Chaudhary. The committee
● MOP&NG is encouraging import of gas has submitted its report in August,
in the form of Liquefied Natural Gas 2011. The committee has emphasized
(LNG) and also making efforts for for increasing share of RLNG in the
import of gas through international Power Sector.
pipelines projects.
● In order to explore and produce new (v) Gas Requirement for power sector
th
sources of natural gas from coal for 12 Five Year Plan
bearing areas, government has
formulated a Coal Bed Methane (CBM) A capacity addition of about 80,000 MW
Policy providing attractive fiscal and may be required in power sector to meet
contractual framework for exploration the growing demand of power during the
and production of CBM in the country. 12th Five Year Plan. Due to uncertainty in
● Government is encouraging Under availability of domestic gas, a gas based
Ground Coal Gasification (UGCG) and capacity of only 1086 MW has been
coal liquification and investment by considered for the 12th Plan i.e. only those
private entrepreneurs in development projects in case of which gas is assured
of these frontier technologies. The from local sources. However, there is an
notification specifying coal gasification urgent need to plan for additional gas
and liquefaction as end-uses has been based capacity to the tune of 25,000 MW
published in the Gazette of India on depending on the availability of gas. Bulk
12th July, 2007. of this capacity could be developed in
● Implementation of Natural Gas next 3 years at the brown field sites or
Hydrate Programme (NGHP) for green field sites where land is already
evaluation of hydrate resources and available. This additional GT capacity will
their possible commercial exploitation. help in meeting particularly the shortfall
● Efforts are also being made to which is expected due to delay in
persuade Government to accord commissioning of the ongoing thermal
priority to Power Sector while and hydro projects.
finalizing Gas Utilization Policy of the
Government for all future domestic By the end of the year 2012-13, a
gases. substantial coal based capacity is going to
● While allocation was made for RIL gas be operationalised. The base load
from KG basin (D-6), the power sector requirement by the country will be met
has been given priority. from nuclear, pit head coal based
● Planning Commission had constituted generation and partly by non pit-head
an Inter-Ministerial Committee on coal based generation and gas based
Policy for Pooling of Natural Gas generation. The intermediate and peak
load is required to be met by hydro, non- may have to plan our gas based
pit head coal based generation and gas generation at an average PLF of around
based generation. The wind, solar and 70 - 75%.
small hydro will be “must run” generation
and will have to be accommodated by The additional gas requirement for 12th
backing down thermal generation. Thus, plan is worked out as under :
by the end of year 2012-13/2013-14 , we
Table 7.11
th
12 Plan Gas Requirement
Table 7.12
capacity base in the country. 300 tonnes approval for five coastal sites to set up
of Uranium concentrates has already been nuclear power parks of 6000 to 10000
imported from France. Steps are on to get MWe capacity based on LWRS with
long term supply of 2,000 tonnes of cooperation from Russian Federation,
Uranium pellets from Russian federation USA and France. A total LWRs capacity of
in a phased manner. 40,000 MWe is possible to be added
progressively by 2032 depending up on
The Fast Breeder Reactor programme is the actual start of work on these reactors.
set to be launched with the prototype 500 The spent fuel of LWRs is planned to be
MWe Fast Breeder reactor plant being reprocessed and deployed in safeguarded
built at Kalpakkam, which is likely to be FBRs and additional PHWRs. This would
commissioned by March 2012. This is first further enhance the FBR capacity in the
of its kind project in India and is being long term and thus increase the role that
implemented by the BHAVINI, a public nuclear energy can play in long term
sector company set up to build this energy security. without the need for any
project and all future fast breeder reactor further import of nuclear fuel. This would
projects. Successful commissioning of this significantly increase the role that nuclear
project would go a long way in achieving energy can play in our long term energy
the three stage development of India’s security.
nuclear power programme for the future.
The 3rd phase of the 3-phase nuclear
DAE envisages start of work on eight units energy program, has several complex
of indigenous 700 MWe PHWRS in the 11th technological issues to be tackled before
Plan for commissioning during 13th Plan. our ability to use Thorium. A clear analysis
Four units have been already approved and assessment of the need of additional
and work has commenced. These are Manpower, R&D investment and new
slated for commissioning in 2016/2017. facilities are called for including the
Work is also planned to be started on elements to be covered in the remaining
LWRs based on international cooperation. 11th plan period. Schedules are of serious
The Government has accorded in principle concern on this front.
---+++---
Chapter 12
Table 12.1
Electrical Energy Consumption and Conservation
Potential in India (in BU)
12.2 ENERGY CONSERVATION (EC) ACT Act – 2001 and established Bureau of
Energy Efficiency.
Recognizing the fact that efficient use of
energy and its conservation is the least- The Act provides for institutionalizing and
cost option to mitigate the gap between strengthening delivery mechanism for
demand and supply, Government of India energy efficiency services in the country
has enacted the Energy Conservation (EC) and provides the much-needed
coordination between the various entities.
Energy audit studies in buildings have for such buildings. Buildings with a
shown large potential for energy savings connected load of 100 KW and above are
in government and commercial office being considered under the BEE Star
buildings. BEE is promoting the rating scheme. It will be subsequently
implementation of energy efficiency extended to other building types and
measures in existing buildings through different climatic zones.
Energy Service Companies (ESCOs) which
provide an innovative business model 12.3.2 Bachat Lamp Yojana: The
through which the energy-savings residential sector accounts for 25.87
potential in existing buildings can be percent of the electricity demand in the
captured and the risks faced by building country. The lighting load comprises of
owners can also be addressed. BEE has 28% of this electricity demand in the
facilitated implementation of energy residential sector and contributes almost
efficiency improvement in some large fully to the peak load as well. To promote
government buildings in New Delhi, the penetration of energy saving CFLs in
notably Rashtrapati Bhavan, PMO, etc. the residential sector, BEE has developed
The implementation of these measures the “Bachat Lamp Yojana” (BLY) Scheme.
have indicated a reduction in electricity Under the BLY scheme, a maximum of 4
bills by about 30% and simple payback on nos. long-life, quality CFL would be
investments by Energy Service Companies distributed by the CFL supplier to the grid-
(ESCOs), who invested in these measures, connected residential households in
of 1-2 years. exchange of equivalent no. of
incandescent lamp (ICL) and Rs. 15 per
In order to further accelerate the energy CFL. Approximately 700,000 CFLs can be
efficiency activities in the commercial distributed within a single project. The
building sector, BEE developed a Star savings in electricity that would mitigate
labelling programme (Voluntary) for day GHG emissions will be leveraged in the
use office buildings, BPOs and Shopping international market by the CFL supplier
complexes have been developed, which is under the Clean Development Mechanism
based on the actual performance of a (CDM) of the Kyoto Protocol.
building in terms of its specific energy
usage in kwh/sqm/year, and 123 buildings Three types of ICL lamp wattages
have been awarded energy star ratings commonly in use viz. 40 W, 60 W and 100
label. The programme rates office W are likely for replacement under the
buildings on a 1-5 Star scale, with a 5 Star BLY scheme. This Bachat lamp Yojana
labeled building being the most efficient. Scheme is registered as Programme of
The Star rating Programme provides Activities (PoA) with the CDM executive
public recognition to energy efficient board to reduce the transaction cost
buildings and creates a ‘demand side’ pull associated with CDM. The project brings
together the three key players, namely validation, and CDM Project Activities
BEE, the Electricity Distribution (CPA).
Companies (DISCOMs) and investors to Bachat Lamp Yojana has been registered
supply the households with CFLs. To with UNFCCC. The projected electricity
bridge the cost differential between the saving at the end of 12th Plan is i.e. 2016-17
market price of the CFLs and the price at about 4.4 BU with the financial budget
which they are distributed to households, requirement of Rs. 6 crore.
the Clean Development Mechanism
(CDM) is harnessed. The CFL supplier 12.3.3 Strengthening of State Designated
(Investor) would cover the project cost Agencies (SDAs): State Designated
through the sale of greenhouse gas (GHG) Agencies (SDAs) are statutory bodies set
emission reductions achieved in their up by states to implement energy
respective project areas. conservation measures at state level.
BEE, the Coordinating and Managing State designated agencies (SDAs) in
Entity (CME) will have to keep a different states need to play a very
functionary to handle the various important role in terms of carrying
documentation and protocols required by forward various energy efficiency
the UNFCCC (United Nations framework initiatives at the state level. The main
Convention for Climate Change) and the emphasis of the scheme is to build
PoA. Further to facilitate the capacity of the SDAs to enable them to
implementation of BLY projects and CFL discharge regulatory, facilitative and
distribution, this functionary will have to enforcement functions under the EC Act
continuously engage with the State 2001. The thrust of the SDA program
Electricity Distribution Companies and CFL during the 12th Plan will be on
suppliers. The database management of strengthening the 32 SDAs which would
the BLY projects and Capacity building of enable them to implement various
State Electricity Distribution Companies programs and activities initiated by BEE or
and CFL suppliers along with BEE SDAs themselves.
functionary will be the key focus areas in
12th Plan. In the 11th Plan, BEE supported State
In 12th Five Year Plan, activities proposed designated agencies (SDAs) in preparation
to be undertaken are: strengthen the on- of action plan, building institutional
going BLY scheme by continued capacity of SDAs, to perform their
engagement with the state electricity regulatory, developmental and
distribution companies and streamlining promotional functions in their respective
and sustaining operations-mainly states, by way of technical assistance,
database management, data security, BLY guidance and funding etc. Each SDA has
system audit, PoA updation & re- been supported to develop a five year
Energy Conservation Action Plan,
The 11th Plan has already envisaged Introduction of fuel economy norms
completion of 21 appliances under S&L effective from 1st year of 12th Plan,
programme and the 12th Plan also Technical study for 2 & 3 wheelers
envisage similar numbers. However, data and commercial vehicles (Truck &
on some of the appliances/equipments Buses) to finalise S&L programme
such as chillers, pumps, data centres, The targeted energy saving by the end of
furnaces, boilers, desert coolers, laptop the 12th Five Year Plan is 4.3 mtoe.
chargers, deep freezers etc. is not
Based on the above proposed schemes,
available and is planned to be collected
fund requirement of Rs. 183 crores have
through baseline survey.
been envisaged for the Standard &
The proposed activities in 12th Five Year Labeling programme for the 12th Plan.
Plan under S&L for equipments and Based on the above investment, the likely
appliances include: saving from the S&L scheme in the year
Inclusion of at least 5 selected new 2016-17 is estimated to be 10.4 BU of
equipment and appliances (selection electrical energy and 4.3 mtoe of thermal
is to be made from the list provided energy. The proposed savings are based
in the table given below). Standby on the baseline data of 2006-07 on which
power loss reduction in few of the basis the energy savings have been
electrical appliances will also be assessed.
focussed in the 12th Plan.
Awareness creation among all the
stakeholders,
Chapter 12: Page | 200 Energy Conservation and Demand-Side Management
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
(c) Super Efficient Equipment Program average purchase and that of the most
(SEEP) efficient technology available
internationally.
SEEP is a part of Market Transformation
for Energy Efficiency (MTEE) initiative, Super efficient appliances (SEA) may
one of the four initiatives of the National consume 30 to 50 percentages less energy
Mission on Enhanced Energy Efficiency than the five star rated equipments of
(NMEEE). The primary objective of MTEE BEE. SEAs will have their high first cost
is to accelerate the shift to energy which can be decreased by large scale
efficient appliances through innovative production facilities, but due to
measures to make the products more uncertainty of market demand,
affordable. NMEEE seeks to achieve manufacturers feel reluctant to make the
annual savings of 19,598 MW of power initial investment to change production
and 23 million tonnes of fuel and lines for super efficient appliances. This
greenhouse gas emissions reduction of barrier needs to be removed by innovative
98.55 million tonnes. The mission is one of policy interventions.
the eight mission under the Prime BEE has already announced the SEEP for
Minister's National Action Plan on Climate ceiling fans, and has initiated a dialogue
Change (NAPCC). BEE is the mission with manufacturers on setting the
implementing agency for NMEEE. technical specification, monitoring
This programme proposes to deal directly process etc. SEEP would also be extended
with the manufacturers of select key to LED Tube lights & LED bulbs. Financial
appliances. Usually, only a handful of incentives of Rs 244 crore per year would
manufacturers account for 70 to 90% of be required (depending on the market
the market share of these appliances. situation and technical preparation).
SEEP would compensate the The ceiling fan market will undergo a
manufacturers for a major part of the significant transformation because of the
incremental cost of producing Super SEEP intervention. It is expected that
Efficient Appliances (SEAs), and 26.86 million SEA ceiling fans will be sold
encourage them to not just produce but in 12th Plan which will provide savings of
also sell SEAs at an affordable price to 2.2 billion units in the year 2016-17 of 12th
common consumers. The need for five year Plan.
incentive is expected to reduce very fast
Estimated market of Tube Fluorescent
as volumes pick up.
Lamp (TFL) in terms of lighting points
In this manner, the programme would shall be about 270 million in 2016-17. With
help to introduce appliances that are far an incentive pattern under SEEP, it is
more efficient than the ones currently assumed that about 33.96 million lighting
available in India thus, narrowing the points would get converted from
massive gap between the efficiency of the conventional lighting to LEDs lighting
points giving a saving of around 10 -12 the ULBs. The situation analysis was
Watt per lighting point. The savings the carried out in the Municipal sector in 2007
year 2016-17 of 12th five year Plan from covering 23 States/UTs. The finding across
sales of 33.96 million LED TL would be all the 171 cities spread in 23 states points
around 0.91 billion units. out that only 9 cities have exclusive
Further, currently both in the S&L and energy cell. Other Municipal’s region
SEEP programme, no intervention in the neither had energy cells nor having any
bulb market was envisaged, although, BLY medium for collection of data for
scheme considers the replacement of improvement of energy efficiency. Bureau
inefficient incandescent lamps (bulb) by of Energy Efficiency has initiated a
CFL. The new emergent technology under programme to cover 175 municipalities in
SEEP through LEDs bulb (replacement of the country by conducting energy audits
60 W incandescent bulbs with 8-12 Watt and preparation of Detailed Project
LED bulb) would give large savings about Reports(DPRs) and implementation
70-80%. The saving in the year 2016-17 of through ESCO mode.
12th five year Plan from sales of 33.96 Energy Efficiency in ULBs
million LED bulbs would be around 3.42
As low as only 38 cities out of 171 have
billion units.
separate allocation in their budget for
12.3.5 Municipal Demand Side any energy efficiency initiative.
Management (MuDSM)- The global trend Notably out of total budget allocation
towards increased urbanization requires of Rs. 12,123 crore across these 171
municipal bodies to provide services such cities, only Rs 128.5 crore (1.06%) was
as streetlights, solid waste management, allocated exclusively for energy
sewage treatment & disposal, etc. All efficiency initiatives in the year 2006-
these activities consume significant 07. This subsequently went down to
amount of electricity, usually in an 0.88% in 2007-08 with the allocation of
inefficient manner. The cost of energy Rs 161.8 crores out of total budget
sometimes constitutes more than 50% of provision of Rs 18,430 crore. Based on
the municipality’s budget and the data collected in the situation
implementing efficiency measures could analysis survey, the energy saving
reduce it by at least 25%. The basic potential for 12th Plan has been
objective of the Municipal Demand Side estimated as 257 million units (MU) in
Management (MuDSM) programme is to the urban local bodies.
improve the overall energy efficiency of Energy Efficiency in Water pumping
the Urban Local Bodies (ULBs) which
could lead to substantial savings in the During the course of initial Investment
electricity consumption, thereby Grade Audits (IGAs) of ULBs, it was
resulting in cost reduction/savings for found that over a period of time, many
of the water pumping bodies (Jal accounts for about 27% of electricity
Nigam/ Jal Sansthan/ Water consumption in the country, which is
Department) have separated out from increasing due to rural electrification
the scope of ULBs and therefore, a efforts of the Government. The electricity
separate situation analysis of these is largely used in agricultural pump sets
bodies was carried out. The which generally have very poor efficiency.
representative water bodies, Since agricultural tariffs are usually the
encompassing total of 3520.65 lakh of lowest and also highly subsidized, there is
population in 1896 Sq.km spread no incentive to the agricultural consumer
across 105 cities, were covered during to improve efficiency of the pump set.
this sample based survey for situation However, utilities are not able to recover
analysis covering 19 states. economic price on every unit of energy
In this study, the overall estimated sold to these categories of consumers and
electricity consumption in the pumping therefore need to aggressively target
was 1040 MU with an estimated electricity these consumers for DSM measures. Ag
saving potential of 208 MU. DSM promises immense opportunity in
reducing the overall power consumption,
Based on the above survey, funding
improving efficiencies of ground water
requirement of Rs. 45 crores is assessed
extraction and reducing the subsidy
for the MuDSM Scheme as this scheme
burden of the states without sacrificing
would create an institutional mechanism
the service obligation to this sector. To
for implementation of the MuDSM in the
tap the energy saving potential in the
country. The above budget is meant for
agriculture sector, which is estimated to
undertaking investment grade energy
be 20.75% (2007-08) of the total energy
audits in both ULBs and Jal-Nigams. It is
consumption, the activities planned to be
envisaged that implementation of the
undertaken in the 12th Plan would focus
proposed IGAs can be achieved through
on development of innovative financial
funding under JNNURM and linking the
mechanisms like Venture Capital Fund
same through development fund of
(VCF) and Partial Risk Guarantee Fund
MoUD to realize the savings. Any
(PRGF) for the large-scale implementation
implementation programme under BEE
of AgDSM projects on Public Private
scheme is to be considered for separately
Partnership (PPP) mode, in the states for
funded.
which DPRs have been prepared in the
The projected electricity saving at the end 11th Five Year Plan. The major impacts of
of 12th Plan i.e. 2016-17 is about 0.47 BU the Ag DSM scheme during the 11th Five
with the financial budget requirement of Year Plan includes 97 MU of annual
Rs. 45 crore. energy saving potential assessed across
12.3.6 Agriculture Demand Side eight different states covering about
Management (AgDSM)- : Agriculture 20,885 pump sets.
Based on the results achieved during the transformation of agriculture pump sets,
11th Plan, the targeted reduction in major manufacturer of agriculture pumps
electricity consumption at the end of 12th in the organized SME sector would
Plan is 0.7 billion units (BU) which would transform into manufacturing of energy
be about 0.57% of the electricity efficient star labelled pumps through the
consumption in the agriculture pumping various initiatives of BEE
system. The following instruments are schemes/programmes.
proposed to meet the proposed target: Wider involvement of stakeholders like
Financing mechanism for promoting DISCOMs, state regulatory commissions,
investments in Ag DSM projects State Designated Agencies, State
(Target – 0.25 million pump sets, 0.7 Governments, pump manufacturers,
BU of energy savings, Total Budgetary energy saving companies, farmers/
Provision: Rs. 352 crore). consumers etc. is one of the key initiatives
Placement of partial risk guarantee under the scheme.
fund for risk mitigation of The projected electricity saving at the end of
Manufacturer/Implementer/ESCOs/FIs 12th Plan i.e. 2016-17 is about 0.7 BU with the
. financial budget requirement of Rs. 393 crore.
the efficacy and virtues of adopting a plan for Cinema and internet has also
habit for energy conservation. been proposed.
Many activities to promote awareness on
The General Awareness Campaign would energy conservation amongst the
create awareness to motivate people to targeted sectors and general public and
save power by rational use of electricity. also for school children were undertaken
This campaign will serve as the umbrella during 11th Plan which include National
campaign for the energy conservation Energy Conservation Award for industries,
initiatives and lay emphasis on the subject buildings and railways and Painting
as the need of the hour. A Multi media Competition on energy conservation for
outreach strategy has been prepared to school children.
achieve maximum reach to the targeted
audience. The combination of Media National Energy Conservation
taken in the plan viz. Print, TV, Satellite, Awards
Radio, Cinema, Internet would give 96%
reach. The National Energy Conservation Award
Scheme of Ministry of Power covers about
The multimedia campaign is being carried 34 sectors of industry, thermal power
out in a phased manner: TV, Print and stations, office buildings, hotels and
Radio plan has already been rolled out. hospitals, zonal railways, state designated
Channel selection in TV/Satellite is based agencies, municipalities and
on TAM ratings to achieve 65%+ reach at manufacturers of BEE Star labelled
5+ OTS. For print, popular and top English, appliances. In the last 11 years of Award
Hindi and regional language newspapers Scheme of the period 1999-2009, the
along with vernacular magazines have participating units have collectively saved
been taken up. The stations for radio Rs 11261 Crores and the investment made
campaign have also been selected in such on energy efficiency projects was
a way so as to attain the maximum reach. recovered back in 17.6 months. In energy
All the channels, stations and newspapers terms, 12113 Million kWh of electrical
have been selected as per the DAVP power, 24 lakhs kilolitre of oil, 67 lakhs
policy. Alongside, monitoring and metric tonne of coal and 21.2 billion cubic
performance evaluation would be metre of gas was saved, through the
stepped up to ensure that the scheme energy conservation measures of the
attains its designated targets. participating units. The progressive
industrial units and other establishments
The allocation of resources over the have already realized the cost
various media platforms is such that TV effectiveness of energy conservation
and satellite constitutes the highest measures and honouring their efforts on
allocation followed by print and radio. The National Energy Conservation Day, gives a
Chapter 12: Page | 206 Energy Conservation and Demand-Side Management
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
message to thousands of other industrial for students in the standards 4th, 5th &
units and establishments who may have 6th at the School, State and at National
not yet fully utilized their cost effective level, Essay writing competition for
potential through energy conservation. It students in the standards 6th to 8th at the
is hoped that National Energy School and State level, Debate
Conservation Award Scheme would help competition for students in the standards
in motivating the other energy consumers 9th to 12th at the District and State level
in joining and promoting of a nation wise has been included as one of the activities
energy conservation movement. of the campaign, which would not only
make aware the children about the need
of conserving energy but at the same time
It is proposed to strengthen all ongoing
would educate and involve their parents
activities during the 12th Plan and
as well in the above cause. The identified
introduce the following specific activities:
activity is one of the measures, which can
Creation of data base and its analysis help in creating awareness in the
EC Award participating units domestic sector. In 2009, around 40,814
Compilation and dissemination of schools and 911,553 students participated
best-practices in industry and building in the Painting competition. In the year
sector 2010, about 15.63 lakh students
Continuation of EC Awards and participated in the competition in
paintings competition on energy comparison to 3.43 lakh in the year 2005.
conservation
12.3.9 Results achieved / expected
Awareness creation on energy
The Ministry has set up a targeted
conservation through print, electronic
reduction of 5% energy consumption by
and other media for general public
the end of XI Five year Plan. The energy
The projected saving in the year 2016-17 of conservation potential as assessed is
12th Plan is about 3.42 BU of electrical energy
20,000 MW and the target planned for the
and 5 mtoe of thermal fuel saving with the
XI Plan is 10,000 MW.
financial budget requirement of Rs. 100 crore.
revealed that the power stations are Reduction of the non-technical losses
losing heavily due to poor condenser could be achieved with better
vacuum, non-availability of HP heaters, management at a little extra cost.
excessive consumption of DM water, air Schemes have been drawn up to reduce
ingress into the boiler, high flue gas technical losses by installation of
temperature and a number of other additional capacitors, appropriate size of
reasons. Most of the power stations were the transformers, installation of
incurring huge financial losses due to sub- amorphous core transformers,
optimal operation resulting in increased augmentation and strengthening of
coal & oil consumption. transmission and distribution lines and
reduction of the length of low voltage
12.4.3 Benefits have accrued in terms of lines. Based on the guidelines issued for
higher generation, improvement in heat reduction of transmission and distribution
rate, and reduction in specific fuel oil and losses and energy audit in power system,
coal consumption at a number of TPSs Utilities have been encouraged to reduce
where the recommendations given by CEA the T&D losses by implementing the
in the mapping reports have been schemes in regard to computerised
implemented. Monitoring of system load management through
implementation of the recommendations segregation of load to agriculture and
is being carried out regularly. CEA has also introduction of Time of Use (TOU)
prepared “Guidelines for establishment of differential tariffs etc. T.O.U. Tariffs
Energy Audit Cells at TPS” to encourage should be such designed in the form of
thermal power stations to conduct energy incentive of lower rate that it should
audits on their own. Energy Conservation encourage use of more energy during off-
Act 2001 makes it mandatory to get peak hours and higher rate should be
energy audit of power stations done fixed to discourage the use of energy
through Accredited Energy Auditors. during peak-hours. Regional staggering of
Energy Audit and implementation of load should be aimed to stagger the load
recommendations to improve operational and minimizing the load of the system
efficiency may form part of regular during peak hours. These efforts have to
activity and necessary financial be vigorously followed up along with
arrangements may be made accordingly. steps to curb pilferage and theft of
electricity. The High Voltage Distribution
12.4.4 Transmission and Distribution system (HVDS) has greater potential to
(T&D) losses in the Indian system are reduce T&D losses and should be
amongst the highest in the world. encouraged.
Presently the all-India T&D losses are
around 27%, out of which substantial 12.4.5 The Indian power system is around
portion is non-technical losses and theft. hundred years old. With latest technology
12.5 ACHIEVEMENT UNDER THE 11th Plan 12.6 UTILITY BASED DEMAND SIDE
MANAGEMENT IN THE 12TH PLAN
Bureau of Energy Efficiency (BEE) and
Ministry of Power (MoP) had introduced a Demand-Side Management (DSM) is the
number of schemes during 11th Five Year selection, planning, and implementation
Plan for promotion of energy efficiency in of measures intended to have an influence
India. The schemes of BEE include on the demand or customer-side of the
Standards and Labeling (S&L), Energy electric meter. DSM program can reduce
Conservation Building Code (ECBC) & energy costs for utilities, and in the long
Energy Efficiency in Existing Buildings, term, it can limit the requirement for
Bachat Lamp Yojana (BLY), SDA further generation capacity augmentation
strengthening, Energy Efficiency in Small and strengthening of transmission and
and Medium Enterprises (SMEs), distribution system. BEE would provide
Agriculture & Municipal Demand Side the technical assistance for establishment
Management (DSM) and Contribution to of DSM cells in the DISCOMs and capacity
State Energy Conservation Fund (SECF). building of personnel of DSM cells for
enabling them to undertake the following
The schemes of the Ministry of Power strategies and schemes of DSM in 12th Five
(MoP) include Energy Conservation Year plan:
Awareness, Energy Conservation Awards
& Painting Competition on Energy (I) LOAD SURVEY
Conservation for school students and The questionnaire based surveys are the
National Mission for Enhanced Energy most commonly adopted tools to study
Efficiency (NMEEE). In the 11th Five Year the consumption pattern of the
Plan (2007–12), it was proposed to achieve consumers by a utility. “Standard load
the energy saving of 5% of the anticipated survey techniques” need to be developed
be used for DSM/DR activity. In other the demand side (equivalent to 60.17 BU
words, the DSM/DR should have a target at Bus bar) and an additional energy
(say 0.5% to 1%) of peak demand reduction saving equivalent of 21.3 mtoe in the
and the net saving in infrastructure due to industrial sector (including Thermal Power
that should be used for DSM/DR activity. Stations (TPS) and Small and Medium
Enterprises), Transport Sector and Energy
The total funds required for providing
Conservation (EC) award scheme. The
technical assistance for capacity building
share of target energy saving (Electrical &
of DSM cells established by DISCOMs under
Thermal) for various proposed schemes
12th Five Year Plan is Rs. 300 crore.
under 12th Plan is given below:
12.7 ENERGY CONSERVATION STRATEGY
IN THE 12TH PLAN 12.8 THE NATIONAL ACTION PLAN ON
th
The strategies adopted during the 11 Five CLIMATE CHANGE (NAPCC)
Year Plan have started showing
encouraging outcomes. It is necessary to The National Action Plan on Climate
carry forward the existing schemes as well Change(NAPCC) released by the Prime
as further strengthen the activities to Minister on 30th June, 2008, recognizes
accelerate the process of implementation the need to maintain a high growth rate
of energy efficiency measures to achieve for increasing living standards of the vast
majority of people and reducing their
The NMEEE spelt out the following four new initiatives to enhance energy efficiency,
(in addition to the programmes on energy efficiency being pursued by MOP and BEE
in the 11th Plan):
iii) Creation of mechanisms that would help finance demand side management
programmes in all sectors by capturing future energy savings. (Energy
Efficiency Financing Platform (EEFP);
Other potential areas that BEE has initiated and which offer significant energy efficiency
potential:
Trigeneration
The HVAC market size in India in the year 2007 was about 13 million kW; 14 % of that was for
the domestic sector. The ratio of window to split ACs in 2004-05 was 3:1 and now the figure is
1:1. HVAC market in India is mainly characterized by the air-conditioning market.
There is a market for hot water generators (i.e. geysers) in the Northern and Central part of the
country. About 1.6 million of such heaters are sold annually in India. Assuming average power
consumption of 1.5 kW/ heater, total installed capacity would be about 2400 MW.
It has been estimated that about 3000 MW gas based power system is already installed in India,
out of that about 1000 MW are recently added in Indian building sector and out of the 1000
MW installed 522 MW are for cogeneration/tri-generation projects.
The tri-generation and cogeneration market is expected to grow very rapidly in future. Present
market size has been estimated at 13 x 106 kW (3.7 X 106 TR) out of which about 2.3 x 106 kW
(0.65 x 106 TR) represents chilled water based central system, which is likely to be the
immediate target market for cogeneration/tri-generation system.
10.5
Hotel
731
9.5 A irport
1,698
Market Attractiveness
Hospital
8.5
270
7.5
Retail
754
6.5
Off ice
5.5 2,590
4.5
7.0 7.5 8.0 8.5 9.0 9.5 10.0 10.5
Financial Attr active ne s s
India has nearly 13 million of micro, small & medium enterprises which constitute more
than 80% of the total number of industrial enterprises in the country. Small industries
have a 45% share of the total manufacturing output and they contribute nearly 40% of
total exports in the economy. They are one of the biggest employers providing
employment to about 41 million people and according to recent estimates, constitutes
about 8-9% of the country’s GDP. The SME sector is one area which demonstrates high
overall potential for reductions in energy intensity ranging from 20 – 25% as per study
conducted by the BEE. SMEs, especially those for whom energy costs represent a large
portion of total production costs, can reap especially high benefits from improving
efficiency of energy conversion and reduction of energy losses, yet numerous barriers
and market failures have prevented widespread adoption of these measures.
Rising energy costs can lead to higher production and distribution costs for business,
eroding long term competitiveness and profitability. SMEs are particularly vulnerable due
to limited resources and tight operating margins. Cutting energy waste can be quick way
for them to reduce costs, but they often lack the knowledge, financing and dedicated
personnel needed to identify efficiency opportunities and implement improvements.
Potential savings can be unlocked through simple measures, one of which can be the
waste heat recovery in some of the clusters. Also, demonstration in few units will have
high replicability potential as these units are located in clusters.
The following initiatives will be taken in (vi) Training to drivers in road transport
the area of HRD: on fuel efficient driving
(i) Capacity building: a) Officials of BEE (vii) Nationwide campaigns: a) through
& SDAs abroad/ in India; b) Code media; b) awareness programs for
officials from SDAs, urban & general public & institutions in state
municipal bodies for promoting & capitals and other locations; c)
enforcement of energy conservation painting competition for school
building codes; c) Orientation children; d) Eco clubs activities for
programs every year for senior youth clubs
officials from Central & State Govt. (viii) Introduction of the modules on
departments to review the energy efficiency/ DSM in the
achievements, impediments and curricula of a) schools b) technical
strategies to step up the tempo of institutes engineering colleges c)
energy conservation. other degree/ postgraduate courses
(ii) Capacity building for new breed of including MBA programs.
professionals: a) energy 12.11 OTHER TECHNOLOGIES/AREAS FOR
managers/auditors being developed ENERGY CONSERVATION
under the EC Act from 2003 by BEE
Award for manufacturer offering the most
through National Certification energy efficient appliance models
Examination by offering Refresher
Appliances manufacturing companies may
training modules for lifelong training
have started producing energy efficient,
for Energy Auditors & Managers; b) star rated models. However, they also
Tutorial /help-line support for produce a wide range of models that are
prospective candidates in the cheaper and popular but energy
national examination for energy inefficient. An award will incentivize the
managers/auditors. manufacturing companies to offer more
energy efficient models and will act as
(iii) Demonstration centres in 2 industrial
recognition of their commitment to
estates to showcase and convince
energy efficiency.
the entrepreneurs & plant
The Ministry of Power already has the
engineers/technicians for industrial
National Energy Conservation Award
energy efficiency products (NECA) scheme to recognize the
/technologies innovation and achievements in energy
(iv) Orientation workshops on energy conservation & efficiency by the industry,
efficiency for top management, and the above proposed award can be a
middle level executives and shop part of the scheme.
floor operating personnel ENERGY EFFICIENCY RESEARCH CENTERS
(v) Farmers training by display of Setting up of 10 energy efficiency research
energy efficient pump-sets & other centres for selected energy consuming
relevant products sectors may be considered in
Chapter 12: Page | 218 Energy Conservation and Demand-Side Management
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
---+++---
Chapter 13
Requirement of Peaking Power & Reserve Margin Chapter 13: Page | 223
operate almost continuously system stability requires matching of
(approximately 70 to 80 percent of the generation with the demand at all
time), except when down for scheduled instances of time, a certain degree of
maintenance, repairs, or unplanned flexibility and ability of the generators to
outages. They take a long time to ramp respond rapidly to the changing
back up to full capacity and have limited demand/availability for RE sources must
ability to vary their output of electricity. In be introduced into the system through
contrast, plants that satisfy peak demand appropriate generation plants.
(peaking plants) are highly responsive to
changes in electrical demand. They can be 13.1 RESERVE MARGIN (RM)
turned off and on relatively quickly.
However, they typically operate less than A reserve margin is the electric generating
20 percent of the time. Peaking plants are capacity the utilities maintain beyond
most often either reservoir based Hydro demand to handle unpredicted needs and
projects or Pumped storage systems or shut downs, both planned & forced. It is
natural gas combustion turbines. The cost the generation capacity above the annual
and flexibility of intermediate load plants peak requirement. Normal practice
fall in between those of base and peak requires utilities to maintain at least a 15
load plants. These plants are designed percent reserve margin in their electric
more specifically for cyclic operation, or generation planning.
they can be older coal plants that have Reserve Margin (RM) = (Installed Capacity
become too expensive to run as base load – Peak Load) / Peak Load
plants. They normally operate during
times of elevated load demand, between At present our system has about 28%
30 and 60 percent of the time. Compared reserve margin. In spite of having a
to peaking plants, they are generally more significant reserve margin the system has
efficient or utilize a cheaper fuel source a high loss of load probability. This is due
and, therefore, cost less to operate. to the following factors:
A system that is designed for base-load
generation will lack the characteristics to i) The outages both forced and due
respond dynamically or efficiently to the to maintenance are high.
variation in demand within a short time. ii) The share of Renewables which is
Apart from variation in demand, there is about 10% does not generate
expected to be wide variability in during peak hours and are of highly
generation as well, when the installed non-dispatchable in nature.
base of renewable energy plants increases iii) The share of Hydro projects is
as a result of pressure on Discoms to about 23% and the energy of the
source their requirement from renewable hydro projects is relatively low.
energy sources (to meet RPO). Since
Chapter 13: Page | 224 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Requirement of Peaking Power & Reserve Margin Chapter 13: Page | 225
and they should be in full output typically initiated when the frequency
within 15 minutes. The activation is drops below the given limits. The
done automatically. The secondary manual actions are initiated by starting
control reserves should release the the reserve power plants (non-
primary reserves for the next spinning reserves), or by increasing
disturbance in the system. the load of the operating plants
Tertiary Reserve/Replacement (spinning reserves). Tertiary control is
Reserve: Tertiary control actions based mainly on manual actions
should free the secondary control initiated by the operator.
reserves in 15 minutes from the start
of the disturbance. Part of the actions The time periods over which all three
will be taken automatically and some kinds of reserve power operate is
manually. Automatic actions are illustrated in the diagram given below.
13.3 REQUIREMENT OF RESERVE PLANTS meet the distribution in the system. The
reserves should be activated within a
The Optimal power system should have period of 30 seconds and should give full
about 15-20 % reserve plants, about 20- output within the next 15 minutes, with a
30% peaking plants, 10-20 % Intermediate view to release the primary control
plants, and about 50-60% Base load reserves. In addition the system should
plants. In Indian power system also, the have tertiary reserves also which can
standard frequency control reserves are take over from the scanty reserves
also need to be created. These are within fifteen minutes of the disturbance
reserves which are primarily reserved to and release these scanty reserves. These
Chapter 13: Page | 226 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
are generally non spinning reserves to a drop in frequency of say 0.1 to 0.2
which can be brought into service at Hz is to bring on line a hot reserve plant
very short notice. As such it is important (equal to the largest single unit in the
to discuss as to what should be the grid) in 5-30 seconds, through automatic
quantum of each of these resources. generation control (AGC). As a second
step, fast reserve power plants (FRPP)
13.4 PRACTICES IN DEVELOPED are started in 4-15 minutes and ramped
COUNTRIES up to full load, after which the AGC plant
will retreat to reserve mode. As a third
As regards the Reserves in the Power
step, replacement reserve power plants
System, in developed electricity markets
(RRPP) come on in 45-60 minutes, after
abroad, it is customary to have several
which the FRPP plants return to their
layers of reserves to meet the
stand-by mode. These reserves are as
contingencies. The first rapid response
illustrated in Figure 13.1 below:
Figure 13.1
Chapter 13: Page | 228 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
The following figures show respectively the all India load duration curve (as met) for 2008-
09 and projected for 2016-17:
Requirement of Peaking Power & Reserve Margin Chapter 13: Page | 229
13.5 REQUIREMENT OF PEAKING frequency-linked prices and sometimes by
POWER load shedding also. The frequency band
tolerated here (from 50.5 to 49 Hz) is far
Power supply position in the country above that permitted in developed
indicates continued energy and peaking countries. However in the future this
shortages. While the energy shortage frequency band is expected to narrow
makes it imperative to set up base load down to 49.9 to 50.1 Hz and this would
stations, the peak shortage underscores reduce the available margin to meet the
the need for separate dispensation to peaking requirement or reserve capacity
meet demands during peak periods. through frequency linked interchange
Peaking demand in Indian states has been mechanism. Hydro power plants also can
met, to an extent, by purchasing power be started up quickly to meet sudden
from other states through bilateral peaks, but this facility is restricted to
agreements or through the mechanism of those few states that have adequate
Unscheduled Interchange (UI) at water storage, all through the year.
response during peak hours could be
Peaking power can ideally be provided by provided by the gas engine based
pondage / reservoir based hydro plants. generation because of their excellent
However, hydro capacity alone may not peaking support capability.
be able to meet the peaking demand. Fast
Given the continuing peaking shortages meet mainly the peaking and intermediate
on all India level and the region specific or load demand.
State specific shortages there is a need for The trends both in terms of volume and
peaking power plants. At the same time, price of electricity in the short-term
given the fact that energy shortages also market further reiterate the need for
persist we would continue to need setting up of adequate generation
investment in the base load / intermediate capacity in general and peaking power
load stations. The major capacity addition plants in particular to enable the
is expected in hydro, coal and renewable. distribution companies to make long-term
Hydro capacity addition though small is planning for meeting their requirements
also mainly in run of the river type or with for power for base-load as well as peak-
small pondage. No peaking stations are load.
under execution except 1000MW pumped
storage scheme at Tehri, order for which 13.6 OPTION FOR PEAKING POWER
is yet to be placed. Thus there is an urgent GENERATION
need to plan for peaking capacity. It
would also be desirable to operate the The optimum base load capacity is the one
combined cycle gas based capacity to which can supply energy under the Load
Duration Curve (LDC) running at nearly full
Chapter 13: Page | 230 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Table 13.1
Peak load management can be very alone plants supplying peak demand.
useful in the short term. It can be With the National grid in place the role
developed further with remote of distributed plants is to meet the peak
measuring and a new load based tariff load and reserve loads. Distributed
system or time of the day metering & power can be a major source to meet
tariff. However, as there is a significant the peak demand in the future. In peak
demand during peaking specially in cities load service the most profitable
and big towns separate peaking plants investments are the gas & Diesel engine
are to be setup. These are to be plants and Aero derivative gas turbine
distributed generating plants or stand plants. The most common applications
Requirement of Peaking Power & Reserve Margin Chapter 13: Page | 231
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
of the internal combustion engines are in that even CCGT can work on load shift
standby and reserve capacities. They are basis as peaking stations.
distributed in hospitals, super markets,
airports, nuclear power plants and The hydro generating stations, other
industrial facilities to ensure safety in than run of the river type, can be
case of blackout or in a sudden spurt of operated, as and when required. In
demand. these stations water can be stored
during off-peak hours so as to generate
Typical diesel engines can be more power during peak hours. As such
synchronized in one minute, and can these hydro generating stations are
deliver full output within 3 minutes. Gas normally used as peaking power
Engines can be synchronized in 2 stations. The pumped storage hydro
minutes and can deliver full output generating station is also a good option
within 8 minutes. An Aero derivative gas for meeting peak demand.
turbine can be synchronized within five
minutes & can deliver full output in ten Similarly we may also have to plan some
minutes. These options may be GTs / Reciprocating Gas Engines to meet
considered to meet the peak demand the peaking requirements. These plants
and the tariff may be as per CERC will be expected to be operated for
guidelines for peaking tariff. about 6-8 hours a day. It is
recommended that part of such plants
13.7 ISSUES IN PEAKING PLANTS may be constructed near the metro
cities in the vicinity of existing or
Peaking plants are generally gas turbines proposed gas grid. Besides meeting the
that burn natural gas or Pumped storage peaking demand these plants could also
systems. A few plants burn petroleum- be operated during the system
derived liquids, such as diesel oil and jet contingencies such as low voltage,
fuel, but they are usually more expensive transmission constraints, etc., thus
than natural gas, so their use is limited. adding to reliability of power supply of
However, many peaking plants are able the metro city.
to use petroleum as a backup fuel. The
thermodynamic efficiency of open cycle Operation of CCGTs in peaking mode as
gas turbine power plants ranges suggested above and OCGT for peaking
between 30 to 42% for a new plant. may result in higher heat rate and O&M
Reciprocating gas engines are also good costs (on account of higher repair and
options for the peaking plants near the maintenance cost) for which the power
load centres and can provide higher plant will have to be compensated.
efficiency of about 44%. It is now stated
Chapter 13: Page | 232 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Most of the combined cycle plants have power would be costlier as compared to
modules with 2 GTs and 1 steam turbine. off peak power. To determine the peak
It is proposed to close down 1 GT in each and off peak tariff a Task Force under
module after the evening peak hours the chairmanship of Shri Rakesh Nath,
and restart at the commencement of the then Chairperson, CEA was constituted
morning peak hours. Thus, during night by CERC and the task force has already
hours such plants may operate at about submitted the report. The notification
50% capacity. Some modern combined for separate tariff for peak and off peak
cycle gas based plants have single shaft power would help in flattening of Load
configuration with 1 GT and 1 ST. Such Duration Curve and ultimately it would
unit may have to be closed down result in lesser capacity addition to meet
completely during night hours after the same power demand in the country.
evening peak hours or may have to be
operated at partial load during off-peak 13.9 Policy Initiatives for peaking
night hours. power plants
specific factors which may form the cycling requirement at different times of
basis to justify differential tariffs, the day and also complement infirm
including nature of renewable energy plants. This
a) Total consumption of
will result into huge economical benefit
electricity during any specified
period; in terms of operational & capital
b) Time at which supply is expenses.
required;
c) Nature of supply; and Gas based power plants are amongst the
d) Purpose for which supply is best available options for meeting the
required. peaking power needs. Also as Natural
gas is a scarce resource it needs optimal
In the above, efficiency and rewarding
utilization. For gas based peaking power
efficiency performance needs special
generation, cost of generation would be
mention during formulation of peaking
on higher side if domestic fuel is not
power policy. As consistent with the
allocated. Hence, for gas based peaking
nature of Peaking, technology used for
power plant, there could be separate
meeting such needs should have certain
allocation of Domestic Natural Gas.
specific characteristics which are listed
as under:
Specific quantity of domestic gas may be
Fast start up & shut down times
allocated for peaking plant for assuring
Fast ramp up rate
reasonable cost to DISCOMs. Initially
Wide load range
introduction of about 2000 MW (in
Black start capability
various sizes ranging from 100 –150 MW)
Un restricted up/down times
dedicated peaking power capacities is
Fuel flexibility envisaged which would need about 2
Low emissions MMSCMD of natural gas (@ 25% PLF).
In the bidding process for selecting Such Plants should be located in vicinity
dedicated peaking power plants, a of major cities/ industrial load centres of
critical evaluation needs to be done on the State for deriving the optimum
above parameters. benefits.
Plants specifically dedicated for peaking, Legislative and policy support required
shall be a part of planned capacity
addition and like the renewables, a 1. In line with National Electricity Policy,
target figure of 10% of installed capacity notification of Peaking Power Policy
by 2020 may be incorporated for peaking needs to done which provides
power plants. This will optimise the necessary directives to mandate the
generation mix, where “Base Load State distribution companies to
Plants” can run on high PLF & the provide universal access to power
“Peaking Power Plants” can meet the (by every section of society – rural,
Chapter 13: Page | 234 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Chapter 13: Page | 236 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
---+++---
Requirement of Peaking Power & Reserve Margin Chapter 13: Page | 237
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
Chapter 13: Page | 238 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
Chapter 14
With a view to expedite new capacity (i) Central Electricity Authority (CEA)
addition, following issues may be has been carrying out Integrated
addressed expeditiously: Power Planning for the country
as a whole. The States are
Availability of land and water. responsible for State specific
Environment and forest clearance planning for generation,
at State level to expedite E& F transmission and distribution
clearance to the project with a view to optimally utilize
To incentivise new BOP resources and to meet their
manufacturers and the existing demand. Earlier, State Electricity
manufacturers to increase their Boards which were integrated
capacity and/or diversify, in order entities were doing integrated
to meet the complete demand of power planning for the States.
the new power generating After unbundling of power sector
capacity. This would also be in the States and formation of
instrumental in introducing generation, transmission and
competition and reducing prices. distribution companies, there is
To incentivise setting up of more no single organization
number of erection and responsible for integrated
(ii) National Electricity Policy Coal requirement during the year 2016-17
stipulates that a spinning = 842 MT
reserves of 5% needs to be
provided in the system. However, Coal availability from :
this implies a large capacity to
provide spinning reserve which (a) CIL = 415 MT
would otherwise be idle in the (b) SCCL = 35 MT
system. Since this implies setting (c) Captive Blocks allocated to Power
up of power projects involving Utilities = 100 MT
huge sum of money , which are (d) Coal to be imported by TPSs
required to operate only under designed on imported coal 54 MT
emergency condition, it is Total, coal availability = 604 MT
suggested that the amount of Shortfall = 238 MT
spinning reserves may be
reduced to Largest unit size + In order to bridge the above gap
fraction of peak load (1 % may be between demand and coal availability as
considered). For the 12th Plan, this referred above, Power Utilities are
corresponds to about 3000 MW. expected to import around 159 MT to
A discussion on what should be meet shortage in coal supply from CIL.
the optimum Spinning Reserve is This quantity of imported coal would be
required. in addition to 54 MT coal likely to be
imported by Thermal Power Stations
(iii) Earlier the generation planning designed on imported coal. Therefore,
exercise was carried out the total quantity of coal expected to be
corresponding to reliability imported is about 213 MT.
criteria of 1% LOLP and 0.15% ENS.
While planning for 12th & 13th Plan
capacity addition the reliability (ii) Limited availability of coal for running
criteria has been made more of power stations is a matter of grave
stringent and the criteria
target and also to reduce our total CO2 requirements far more reliably compared to
emission. other available options.
(10) NEED FOR PEAKING POWER PLANTS creation of additional peaking plants
in other major cities and higher
(i) It is recommended to plan for at capacity in future plans.
least 2000 MW gas based peaking
power plants during 12th Plan, 400 (ii) It is also recommended that a Task
MW each in five major metro cities Force under CERC to deliberate
of India with proper regulatory upon the various aspects associated
support. The experience gained with setting up of peaking plants
from operation of these peaking and creation of adequate system
plants would pave the way for reserve may be set up at the earliest.
----+++----
ACRONYMS
ACRONYMS EXPANSION
AC Alternating Current
AG&SP Accelerated Generation & Supply Programme
AHWR Advanced Heavy Water Reactor
AIIMS All India Institute of Medical Sciences
AMD Atomic Minerals Directorate
APM Administered Price Mechanism
AREP Accelerated Rural Electrification Programme
BARC Bhabha Atomic Research Centre
Bcum, Billion cubic metre
BCM,Bm3
BEE Bureau of Energy Efficiency
BFP Boiler Feed Pump
BHEL Bharat Heavy Electricals Ltd.
BSES Bombay Suburban Electric Supply
BU Billion units or Billion kWh
C&I Control & Instrumentation
CAD & CAM Computer-Aided Design & Computer-Aided Management
CAGR Compounded Annual Growth Rate
CBIP Central Board of Irrigation & Power
CBM Coal Bed Methane
CCEA Cabinet Committee on Economic Affairs
CCGT Combined Cycle Gas Turbine
CD Compact Disc
CDAC Centre for Development of Advanced Computing
CDM Clean Development Mechanism
CEA Central Electricity Authority
CFBC Circulating Fluidized Bed Combustion
CFL Compact Fluorescent Lamp
CFRI Central Fuel Research Institute
CIL Coal India Ltd.
CLA Central Loan Assistance
CPP Captive Power Producer
CPRI Central Power Research Institute
CPSU Central Public Sector Undertaking
Acronyms Page | 247
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
ACRONYMS EXPANSION
Crs Crores
CS Central Sector
CSIR Council for Scientific and Industrial Research
CSMRS Central Soil & Materials Research Station
CWC Central Water Commission
DAE Department of Atomic Energy
DC Direct Current
DDG Decentralised Distributed Generation
DGH Director General Hydro Carbon
DG Set Diesel Generating Set
DISCOM Distribution Company
DMLF Data Management & Load Forecasting
DOPT Department of Personnel & Training
DPR Detailed Project Report
DSM Demand - Side Management
DST Department of Science & Technology
DSTATCOM Distribution Static Compensation
DVC Damodar Valley Corporation
DVR Dynamic Voltage Restorer
EA 2003 Electricity Act 2003
ECIL Electronic Corporation of India Ltd.
EGEAS Electric Generation Expansion Analysis System
ENS Energy Not Served
EPS Electric Power Survey
ERDA Electric Research & Development Association
ESCO Energy Service Company
ESP Electro Static Precipitator
EPC Engineering Procurement Contract
FAUP Fly Ash Utilisation Programme
FBC Fluidised Bed Combustion
FO Forced Outage
FOR Forum of Regulators
GCV Gross Calorific Value
GDP Gross Domestic Product
GHG Green House Gas
GIS Gas Insulated Switchgear
GPS Geographic Positioning System
Page | 248 Acronyms
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
ACRONYMS EXPANSION
GR General Review
GSPC Gujarat State Petroleum Corporation
GT Gas Turbine
GWe Gega Watt (Electrical)
HBJ Hazira-Bijapur-Jagdishpur ( pipeline)
HFO Heavy Fuel Oil
HEP Hydro Electric Project
HPS Heavy Petroleum Stock
HRD Human Resource Development
HSD High Speed Diesel
HT High Tension
HVDS High Voltage Distribution System
ID Induced Draft
IEP Integrated Energy Policy
IGCAR Indira Gandhi Centre for Atomic Research
IGCC Integrated Gasification Combined Cycle
IISC Indian Institute of Science
IIT Indian Institute of Technology
IPP Independent Power Producer
IS Indian Standard
ISCC Integrated Solar Combined Cycle
ISO International Standard Organisation
ISPLAN Integrated System Planning
IT Information Technology
kCal kilo Calorie
kg kilogram
KKNPP Kudankulam Nuclear Power Project
kW kilo Watt
kWh kilo Watt hour
LEP Life Extension Programme
LF Load Factor
LNG Liquefied Natural Gas
LOA Letter of Award
LOLP Loss of Load Probability
LP Linear Programming
LRVI Loss Reduction & Voltage Improvement
LSHS Low Sulphur Heavy Stock
Acronyms Page | 249
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
ACRONYMS EXPANSION
LT Low Tension
LWR Light Water Reactor
MAPS Madras Atomic Power Station
MCFC Mother Carbonate Fuel Cell
Mcm Million cubic metre
MHD Magneto Hydro Dynamics
MMSCMD Million Metric Standard Cubic Metre per Day
MNRE Ministry of New & Renewable Energy
MNP Minimum Need Programme
MoEF Ministry of Environment & Forest
MoP Ministry of Power
MT Million Tonne
MToe Million Tonnes Oil equivalent
MU Million Units
MW Mega Watt
MWe Mega Watt electric
NAPS Narora Atomic Power Station
NCPS National Capital Power Station
NDT Non-Destructive Test
NEP National Electricity Policy
NFC Nuclear Fuel Complex
NHPC National Hydroelectric Power Corporation
NMDC National Mineral Development Corporation
NML National Metallurgical Laboratory
NOX Oxides of Nitrogen
NPC National Productivity Council
NPCIL Nuclear Power Corporation of India Ltd.
NPTI National Power Training Institute
NTC Nuclear Training Centre
NTPC National Thermal Power Corporation
OCGT Open Cycle Gas Turbine
OGIP Original Gas In Place
O&M Operation & Maintenance
PAFC Phosphoric Acid Fuel Cell
PC Pulverized Coal
PFBC Pressurised Fluidized Bed Combustion
PFC Power Finance Corporation
Page | 250 Acronyms
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003
ACRONYMS EXPANSION
PFR Preliminary Feasibility Report
PGCIL Power Grid Corporation of India Limited
pH Hydrogen Ion Concentration
PIE Partnership In Excellence
PIB Public Investment Board
PHWR Pressurised Heavy Water Reactor
PLF Plant Load Factor
PMGY Pradhan Mantri Gramodaya Yojna
PMI Power Management Institute
PMO Prime Minister’s Office
PPM Parts Per Million
PS Private Sector
PSC Production Sharing Contract
PSP Power Supply Position
PSS Pumped Storage Schemes
PSU Public Sector Undertaking.
R&D Research & Development
R&M Renovation & Modernisation
RAPP Rajasthan Atomic Power Project
RAPS Rajasthan Atomic Power Station
REB Regional Electricity Board
REC Rural Electrification Corporation
REDB Rural Electricity Distribution Backbone
RHE Rural Household Electrification
RLA Residual Life Assesment
RM Reserve Margin
SAARC South Asian Association for Regional Corporation
SEB State Electricity Board
SERC State Electricity Regulatory Commission
SOG Sanctioned & Ongoing
SOX Oxides of Sulphur
SPIC Southern Petro India Chemicals Ltd.
SPM Suspended Particulate Matter
SS State Sector
SSB Solid State Breakers
SSTS Solid State Transfer Switches
STPP Super Thermal Power Plant
Acronyms Page | 251
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority
ACRONYMS EXPANSION
STPS Super Thermal Power Station
STUs State Transmission Utilities
T&D Transmission & Distribution
TAPP Tarapur Atomic Power Project
TAPS Tarapur Atomic Power Station
TIFAC Technology Information Forecasting & Assessment Council
TOU Time of Use
TPS Thermal Power Station
UCIL Uranium Corporation of India Ltd.
UMPP Ultra Mega Power Project
UN United Nations
UNDP United Nations Development Programme
UT Union Territory
VEI Village Electrification Infrastructure
WBPDCL West Bengal Power Development Corporation Limited