You are on page 1of 255

National

Electricity
Plan
(Volume 1)
Generation
[In fulfilment of CEA's obligation under
section 3(4) of the Electricity Act 2003]

Government of India
Ministry of Power
Central Electricity Authority

January 2012
National
Electricity
Plan
(Volume 1)
Generation
[In fulfilment of CEA's obligation under
section 3(4) of the Electricity Act 2003]

Government of India
Ministry of Power
Central Electricity Authority

January 2012
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

CONTENTS

Chapter No. Subject Page

1 Introduction 1-18

2 Review of Capacity addition in 11th Five Year Plan (2007-12) 19-36

3 Demand Projections for Electricity 37-42

4 Initiatives and Measures for GHG Mitigation 43-88

5 Generation Planning 89-98

6 Generation Capacity addition Programme for 12th & 13th 99-126


Plan
7 Optimisation of Land and Water Requirement for Thermal 127-134
Power Plants
8 Low Carbon Growth Strategy for Indian Power sector for 135-150
12th & 13th Five Year Plan
9 Key Inputs for 12th Plan 151-168

10 Integrated Planning by the States 169-172

11 Fuel Requirement 173-192

12 Energy Conservation and Demand side management 193-222

13 Requirement of Peaking Power and Reserve Margin 223-238

14 Conclusions and Recommendations 239-246

Acronyms 247-252

Contents
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 1

INTRODUCTION

1.0 BACKGROUND 1.1 ELECTRICITY ACT 2003 AND


NATIONAL ELECTRICITY POLICY
Growth of power sector is the key to the
economic development of our country. 1.1.1 Electricity Act 2003 and Stipulations
Growth in production of electricity has led regarding National Electricity Plan
to its extensive use in all the sectors of
economy in the successive five years The Electricity Act, 2003 provides an
plans. Over the years the installed enabling legislation conducive to
capacity of Power Plants (Utilities) has development of the Power Sector in
increased to about 1,86,655 MW (by transparent and competitive
December,2011) from a meagre 1713 MW environment, keeping in view the interest
in 1950. Similarly, the electricity of the consumers.
generation increased from about 5.1
Billion kwh to 789 Billion kwh in 2010-11. As per Section 3(4) of the Electricity Act
The per capita consumption of electricity 2003, CEA is required to prepare a
in the country also increased from 15 kWh National Electricity Plan in accordance
in 1950 to about 814 kWh in 2011. About with the National Electricity Policy and
90% of the villages have been electrified. notify such Plan once in five years. The
However, the country continues to have draft plan has to be published and
mismatch between demand and supply suggestions and objections invited
and experienced energy and peak thereon from licensees, generating
shortages to the tune of 8.5% and 10.3% companies and the public within the
respectively during the year 2010-11. The prescribed time. The Plan has to be
ongoing RGGVY (Rajiv Gandhi Gram notified after obtaining the approval of
Vidyuthikaran Yojana) envisages access to the Central Government. The National
electricity to households in rural areas 56% Electricity Policy stipulates that the Plan
of which do not have access to electricity. prepared by CEA and approved by the
The per capita electricity consumption in Central Government can be used by
India is 24% of the world’s average and 35% prospective generating companies,
& 28% respectively that of China and transmission utilities and
Brazil. transmission/distribution licensees as
reference document.

Introduction Chapter 1: Page | 1


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

1.1.2 National Electricity Policy and including rehabilitation and


Stipulations regarding National Electricity resettlement;
Plan  Integration of such possible locations
with transmission system and
The Aims and Objectives of the National development of national grid including
Electricity Policy are as follows: type of transmission systems and
requirement of redundancies; and
 Access to Electricity - Available for all  Different technologies available for
households in next five years efficient generation, transmission and
 Availability of Power - Demand to be distribution.
fully met by 2012. Energy and peaking  Fuel choices based on economy,
shortages to be overcome and energy security and environmental
adequate spinning reserve to be considerations.
available.
 Supply of Reliable and Quality Power The Policy also stipulates that while
of specified standards in an efficient evolving the National Electricity Plan, CEA
manner and at reasonable rates. will consult all the stakeholders including
 Per capita availability of electricity to state governments and the state
be increased to over 1000 units by governments would, at state level,
2012. undertake this exercise in coordination
 Minimum lifeline consumption of 1 with stakeholders including distribution
unit/household/day as a merit good licensees and STUs. While conducting
by year 2012. studies periodically to assess short-term
 Financial Turnaround and Commercial and long-term demand, projections made
Viability of Electricity Sector. by distribution utilities would be given due
 Protection of consumers’ interests. weightage. CEA will also interact with
institutions and agencies having economic
As per the Policy, the National Electricity expertise, particularly in the field of
Plan would be for a short-term framework demand forecasting. Projected growth
of five years while giving a 15 year rates for different sectors of the economy
perspective and would include: will also be taken into account in the
exercise of demand forecasting.
 Short-term and long term demand
forecast for different regions; The Policy stipulates that in addition to
 Suggested areas/locations for capacity enhancing the overall availability of
additions in generation and installed capacity to 85%, a spinning
transmission keeping in view the reserve of at least 5% at national level
economics of generation and would need to be created to ensure grid
transmission, losses in the system, security and quality and reliability of
load centre requirements, grid power supply.
stability, security of supply, quality of The Policy states that efficient
power including voltage profile, etc; technologies, like super-critical
and environmental considerations technology, IGCC etc; and large size units
would be gradually introduced for

Chapter 1: Page | 2 Introduction


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

generation of electricity as their cost allocation such as captive mines


effectiveness gets established. available, which the procurer
intends to set up under tariff based
1.2 VARIOUS INITIATIVES OF THE bidding process (Case 2).
GOVERNMENT
Guidelines for procurement of Power by
1.2.1 Development of Power Projects on Distribution licensees and Standard
Tariff Based Bidding Bidding Documents have been issued by
the Ministry of Power. Many projects in
Promotion of competition in the Haryana, UP, Gujarat, Maharashtra etc,
electricity industry in India is one of the are being implemented through tariff
key objectives of the Electricity Act, 2003 based competitive bidding (Case 1/Case 2).
(the Act). Competitive procurement of
electricity by the distribution licensees is 1.2.2 Development of Ultra Mega Projects
expected to reduce the overall cost of
procurement of power and facilitate An Initiative has been launched by the
development of power markets. Government for development of coal
based Ultra Mega Power Projects
Section 61 & 62 of the Act provide for (UMPPs) of about 4,000 MW capacity
tariff regulation and determination of each under Tariff based competitive
tariff of generation, transmission, bidding. The UMPPs will be located either
wheeling and retail sale of electricity by at pit head based on domestic coal or at
the Appropriate Commission. Section 63 coastal locations based on imported coal.
of the Act states that – For UMPPs based on domestic coal, coal
block will also be allocated to the project
“Notwithstanding anything contained in developer. The Objective is to achieve
Section 62, the Appropriate Commission faster capacity addition and to minimize
shall adopt the tariff if such tariff has been the cost of power to consumers due to
determined through transparent process economy of scale. Nine numbers of
of bidding in accordance with the UMPPs are being planned at various
guidelines issued by the Central locations in the country. 4 projects, two
Government.” each at pithead and coastal location have
already been awarded at competitive
Tariff Policy was issued in January, 2006 to tariffs. These projects are Sasan in
facilitate procurement of power on tariff Madhya Pradesh, Tillaya in Jharkhand,
based bidding. Power projects can be Mundra in Gujarat and Krishnapattanam in
developed by States under Case I and Andhra Pradesh. 5th UMPP is already in
Case II bidding as follows: the bidding stage. Efforts are being made
to bring the remaining 4 UMPPs to the
(i) Where the location, technology or bidding stage.
fuel is not specified by the procurer
(Case 1); 1.2.3 Allocation of Captive Coal Blocks
(ii) For hydro-power projects, load
centre projects or other location The coal production in the country has not
specific projects with specific fuel been keeping pace with the increasing

Introduction Chapter 1: Page | 3


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

demand of the Power Sector due to and supply of domestic coal has widened.
various reasons, major one being delay in Therefore, it has been decided to allocate
development of coal mines in the country. coal blocks to project developers for
This has necessitated the need to import captive use. All UMPPs at pithead have
coal. Moreover, the huge capacity been allocated coal blocks.
addition programme during 11th Plan and
beyond as compared to the actual The number of coal blocks allocated to
capacity addition during the past few Plan various utilities and the geological
periods has further aggravated the reserves of the blocks are given in Table
situation and the gap between demand 1.1 below:

Table: 1.1
Details of Captive Coal Blocks Allocation to Power Sector

Utility Coal Blocks Geological Reserves (MT)


CPSU 13 6893
State Utilities 39 12717
UMPPs 7 2607
Private 32 6076
Total 91 28294

16 blocks with a reserve of 1355 MT are fixation of tariff of the project. Merchant
under operation. Mining Plan has been sale is to reduce with delay in
approved for 26 blocks (reserve-7787MT). commissioning of the projects. Provisions
The captive mine blocks have to be have also been made for providing
developed on priority to meet the incentives for local area development
capacity addition targets for the 12th plan. fund and project affected families.

1.2.4 New Hydro Policy New Hydro Policy enables developer to


recover his additional costs through
With a view to ensure accelerated merchant sale of upto a maximum of 40%
development of the hydro power, a New of the saleable energy. Further, 1% free
Hydro Policy has been announced by the power from the project is to be allocated
Government. As per this Policy, the State for Local Area Development for welfare
Governments would be required to follow schemes, creation of additional
a transparent procedure for awarding infrastructure and common facilities. The
potential sites to the private sector. The State Governments are also expected to
concerned private developer would be contribute a matching 1% from their share
required to follow the existing procedure of 12% free power for local area
such as getting DPR prepared and other development.
statutory clearances and then
approaching the appropriate regulator for

Chapter 1: Page | 4 Introduction


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

1.2.5 Private Sector Participation in through tariff based competitive bidding


Transmission Sector subsequently takes over the SPV company
of REC/PFC and then has to approach to
The Inter-state transmission sector was CERC for grant of transmission license and
opened up for private sector participation acceptance of market discovered tariff by
through joint venture with Powergrid and the Commission, and in the meanwhile
through selection of Transmission System also has to achieve financial closure.
Provider through competitive bidding.
Transmission is a licensed activity and MoP has constituted empowered
Powergrid as the Central Transmission committee headed by Member, CERC for
Utility is a deemed licensee. Therefore, identifying projects to be implemented
the Central Commission had to be through competitive bidding and
approached by the joint venture (JV) providing guidance to the Bid Process
companies for grant of transmission Coordinator. MoP has appointed REC and
license. Torrent Powergrid Company Ltd., PFC as Bid Process Coordinator. Three
Jaypee Powergrid Ltd., Parbati Koldam Inter-State Transmission projects have
Transmission Co. Ltd., Teesta Valley Power been awarded to private sector recently
Transmission Ltd. and North-East through competitive bidding route. Three
Transmission Co. Ltd. were granted more projects have been taken up and
licenses for purpose of developing specific these are now in the RFQ stage. In future,
transmission projects. Subsequently, MoP more projects are to be taken up through
issued Guidelines for Encouraging competitive bidding route.
Competition in Development of
Transmission Projects and Tariff based 1.2.6 National Action Plan for Climate
Competitive Bidding Guidelines for Change
Transmission Services, as well as Standard
Bid Documents for procuring transmission The National Action Plan for climate
services through the market route. change (NAPCC) was launched by the
While selecting the transmission projects Prime Minister in June 2008. NAPCC seeks
for competitive bidding, the lead time to promote sustainable development
requirement of about one year for through use of clean technologies. The
completing the bidding process has to be Plan aims to limit India’s greenhouse gas
kept in view. The Transmission Service emissions to less than that of developed
Agreement is required to be pre-signed by countries. The Plan will be implemented
the beneficiaries before the RFP stage. thorough eight missions which represent
There are large numbers of beneficiaries multi-pronged, long-term and integrated
of an Inter-State Transmission schemes strategies for achieving key goals in the
some times in more than one region and it context of climate change.
takes considerable efforts and time to get
the Transmission Service Agreement The stated objective is to establish an
initialled from all the beneficiaries. Also, effective, cooperative and equitable
the scope has to be frozen before RFP global approach based on the principle of
stage as no modification is possible after common but differentiated
invitation of the tariff bids. The responsibilities and relative capabilities
transmission service provider selected enshrined in the UNFCC.

Introduction Chapter 1: Page | 5


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

The Mission will adopt a 3-phase


Success of India’s efforts would be approach, spanning the remaining period
enhanced if the developed nations fulfil of the 11th Plan and first year of the 12th
their commitments under UNFCC to Plan (up to 2012-13) as Phase 1, the
transfer additional financial resources and remaining 4 years of the 12th Plan (2013-17)
climate friendly technologies to the as Phase 2 and the 13th Plan (2017-22) as
developing countries. Phase 3. At the end of each plan, and mid-
term during the 12th and 13th Plans, there
NAPCC identifies following eight National will be an evaluation of progress, review
Missions of capacity and targets for subsequent
phases, based on emerging cost and
 National Solar Mission technology trends, both domestic and
 National Mission for Enhanced global. The aim would be to protect
Energy Efficiency Government from subsidy exposure in
 National Mission on Sustainable case expected cost reduction does not
Habitat materialize or is more rapid than
 National Water Mission expected. The immediate aim of the
 National Mission for sustaining the Mission is to focus on setting up an
Himalayan Ecosystem enabling environment for solar
 National Mission for a “Green technology penetration in the country
India” both at a centralized and decentralized
 National Mission for sustainable level. The first phase (up to 2013) will
Agriculture focus on capturing of the low-hanging
 National Mission on Strategic options in solar thermal; on promoting
Knowledge for Climate Change off-grid systems to serve populations
without access to commercial energy and
Jawaharlal Nehru National Solar Mission - modest capacity addition in grid-based
Towards Building SOLAR INDIA systems. In the second phase, after taking
into account the experience of the initial
The National Solar Mission is a major years, capacity will be aggressively
initiative of the Government of India and ramped up to create conditions for up
State Governments to promote scaled and competitive solar energy
ecologically sustainable growth while penetration in the country.
addressing India’s energy security
challenge. It will also constitute a major To achieve this, the Mission targets are:
contribution by India to the global effort
to meet the challenges of climate change. • To create an enabling policy
The objective of the National Solar framework for the deployment of
Mission is to establish India as a global 20,000 MW of solar power by 2022.
leader in solar energy, by creating the
policy conditions for its diffusion across • To ramp up capacity of grid-connected
the country as quickly as possible. solar power generation to 1000 MW
within three years – by 2013; an
additional 3000 MW by 2017 through

Chapter 1: Page | 6 Introduction


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

the mandatory use of the renewable 1.2.7 Restructured Accelerated Power


purchase obligation by utilities backed Development and Reform
with a preferential tariff. This capacity Programme (R-APDRP) during XI
can be more than doubled – reaching Plan (2007-12)
10,000MW installed power by 2017 or
more, based on the enhanced and The Govt. of India has accorded sanction
enabled international finance and to implement Restructured Accelerated
technology transfer. The ambitious Power Development and Reform
target for 2022 of 20,000 MW or more, Programme (R-APDRP) during the 11TH
will be dependent on the ‘learning’ of Plan with revised terms and conditions as
the first two phases, which if a Central Sector Scheme. The focus of the
successful, could lead to conditions of programme is on actual, demonstrable
grid-competitive solar power. The performance in terms of sustained loss
transition could be appropriately up reduction.
scaled, based on availability of
international finance and technology. Restructured APDRP was approved with
an outlay of Rs 51,577 crore.
• To create favourable conditions for
solar manufacturing capability, It is proposed to cover urban areas -
particularly solar thermal for towns and cities with population of more
indigenous production and market than 30,000 (10,000 in case of special
leadership. category states). In addition, in certain
high-load density rural areas with
• To promote programmes for off grid significant loads, works of separation of
applications, reaching 1000 MW by agricultural feeders from domestic and
2017 and 2000 MW by 2022. industrial ones, and of High Voltage
Distribution System (11kV) will also be
• To achieve 15 million sq. meters solar taken up. Further, towns / areas for which
thermal collector area by 2017 and 20 projects have been sanctioned in X Plan R-
million by 2022. APDRP shall be considered for the XI Plan
only after either completion or short
• To deploy 20 million solar lighting closure of the earlier sanctioned projects.
systems for rural areas by 2022. Projects under the scheme shall be taken
up in Two Parts. Part-A shall include the
Strategy for implementation of first projects for establishment of baseline
phase of 1300 MW data and IT applications for energy
accounting/auditing & IT based consumer
• Bundling of 1000 MW unallocated service centres and Part-B shall include
power. regular distribution strengthening
• Roof top reimbursement to states. projects.

Power Finance Corporation (PFC) as nodal


agency for R-APDRP in XI plan will provide
necessary assistance for smooth
implementation of programme.

Introduction Chapter 1: Page | 7


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

1.2.8 Rajiv Gandhi Grameen Vidyutikaran


Yojana Guidelines for village electrification
through Decentralized Distributed
Central Govt. has launched Rajiv Gandhi Generation (DDG) under RGGVY in the XI
Grameen Vidyutikaran Yojana of Rural plan have been approved and circulated
Electricity Infrastructure and Household vide OM No.44/1/2007-RE dated 12th
Electrification on 4th April, 2005 for the January,2009.
attainment of the National Common
Minimum Programme (NCMP) goal for Government of India has approved the
providing access to electricity to all continuation of the scheme in 11th Plan for
households in five years. The scheme aims attaining the goal of providing access to
at electrification of 125,000 un-electrified electricity to all households, electrification
villages and un-electrified hamlets and of about 1.15 lakh unelectrified villages
electrification of 7.8 crore households. and electricity connections to 2.34 crore
The estimated cost of the scheme BPL households by 2012 with a capital
(including XI Plan) was Rs.16000 crores subsidy of Rs. 28,000 crores .
approximately and Rs.5000 crores were
earmarked for capital subsidy in phase- I 1.2.9 Augmentation of Indigenous
during the 10th Plan Period. Equipment Manufacturing Capacity

Under the scheme 90% capital subsidy All efforts have been made to ensure that
would be provided for overall cost of the manufacturing capacity for Main Plant
project for provision of: equipment in the country is suitably
enhanced to meet capacity addition
 Rural Electricity Infrastructure requirement during 11th Plan and beyond
Backbone (REDB) with at least one by enhancing manufacturing capability of
33/11 KV(or 66/11 KV) substation in existing manufacturers and by
each block encouraging new vendors.
 Village Electrification Infrastructure
(VEI) with at least one distribution With above collaborations it may be
transformer in each village/habitation concluded that country have sufficient
 Decentralized Distribution Generation manufacturing capability for main plant
(DDG) System where grid supply is equipments.
either not feasible or not cost
effective.
CEA has already reviewed the Pre- tendering of 11 units of 660 MW with
qualification requirement of suppliers of super critical technology for NTPC & DVC
Super Critical boilers and turbine- projects has been initiated with
generators to facilitate entry of new mandatory phased indigenous
players and has recommended the same manufacturing.
for adoption by central and state power
utilities. In order to promote indigenous An assessment of requirement of Balance
manufacturing and transfer of technology of Plant equipment for power plants has
of super critical technology, bulk also been carried out and efforts are

Chapter 1: Page | 8 Introduction


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

being made to enhance the implementation of policy programmes


manufacturing capacity of existing and co-ordination of implementation of
vendors and encourage new vendors also. energy conservation activities.

It is necessary to sensitize the industry The mission of BEE is to develop policy


about the long term requirement of BoPs and strategies with a thrust on self-
for the power sector to attract regulation and market principles, within
investment in BoP segment. Ministry of the overall framework of the EC Act with
Power and CEA have already taken an the primary objective of reducing energy
initiative in coordination with CII to intensity of the Indian economy.
sensitize the industry about the
requirement of BoPs. Mandatory Provisions of the EC Act

BoP is not a high technology area and a  Strengthening energy management


vendor having experience of executing and energy auditing capabilities of
other infrastructure project could also energy professionals
develop BoP execution capabilities. This  Accreditation of energy auditors
has been considered to avoid the  Fixation of norms for different
overburdening the existing BoP industrial sectors
manufacturers. CEA has already reviewed  Conduction of Mandatory energy
the pre-qualification requirement for BoP audits by designated consumers
vendors and the pre-qualification report  Notification of State Designated
for the various BoP packages has been Agencies
finalised by CEA in consultation with the  Standards & Labelling for notified
stakeholders. The recommendations of energy consuming equipment and
CEA have been forwarded to all state and appliances
central power utilities for adoption.  Energy Conservation Building Codes for
new commercial buildings having
1.2.10 Demand Side Management connected load of 500kW or more
Initiatives by BEE
PROGRAMME AND MEASURES
Recognizing the fact that efficient use of
energy and its conservation is the least- Bureau of Energy Efficiency (BEE) has
cost option to mitigate the gap between already identified thrust areas and
demand and supply, Government of India prepared a detailed Action Plan listing out
has enacted the Energy Conservation (EC) associated activities to be carried out by it
Act – 2001 and established Bureau of for implementing projects and
Energy Efficiency (BEE). programmes to promote efficient use of
energy and its conservation. The Action
The Act provides for institutionalizing and Plan was launched by the Honourable
strengthening delivery mechanism for Prime Minister on 23rdAugust, 2002 at the
energy efficiency services in the country International Conference on Strategies for
and provides the much-needed Energy Conservation in New Millennium
coordination between the various entities. held in New Delhi. The Action Plan, inter-
The Bureau would be responsible for alia, covers:
Introduction Chapter 1: Page | 9
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

strengthened to produce quality


 Indian Industry Program for Energy technicians. As per this scheme, ITIs are to
Conservation be adopted or new ITI established by
 Demand Side Management power developers in the vicinity of their
 Standards and Labelling program projects to provide opportunity to local
 Energy efficiency in buildings and population to develop skill in construction
establishments and O & M of the power projects. Central
 Energy conservation building codes Public Sector Undertakings have already
 Professional certification and adopted some ITIs. Private sector is also
accreditation being encouraged to help in developing
 Manuals and codes large skilled workforce required for
 Energy efficiency policy research accelerated development of power
program sector.
 Delivery Mechanisms for energy
Services 1.2.12 Creation of National Electricity
Fund(NEF) for Distribution Scheme
 School education etc.
Investment in Sub-transmission and
1.2.11 Human Resource Development –
distribution has been lacking due to
Adopt an ITI scheme
resource crunch being experienced by the
State transmission and distribution
To meet the manpower requirement
utilities. The break-up of the generation
during the 11th Plan and beyond, high
and transmission & distribution schemes
priority is being accorded to human
shall normally be 50:50. However, more
resource development and training of
investment is taking place in generation
power sector personnel. A very
and investment in intra-state transmission
comprehensive and pragmatic approach
system and distribution System has been
has been adopted to attract, utilize,
much less than the desired proportion.
develop and conserve valuable human
There is need to create National Electricity
resources. It has been estimated that an
Fund (NEF), has, therefore been proposed
additional about 1 million workmen,
to be created for providing financial
supervisors and engineers would be
support to State Power Utilities for
required for Construction, Operation and
improving their transmission &
Maintenance of power equipment during
distribution infrastructure. Planning
11th Plan. In particular, technicians of
Commission has already submitted a
specified skills would be required in very
proposal for creation of NEF for financing
large numbers. To bridge the gap
of state sector Transmission and
between supply and demand, a scheme
distribution schemes.
called “Adopt an ITI” has been initiated
with a view to building up of skilled work
1.2.13 IT Based Project Monitoring
force in the vicinity of the project. Even
though we have adequate ITIs, the
Monitoring of construction of Power
infrastructure available in terms of
Projects is very complex due to a number
workshop facilities and faculty is
of activities being taken up simultaneously
inadequate. It is required to be

Chapter 1: Page | 10 Introduction


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

and in parallel. It is no longer possible to construction, operation and maintenance


carry out monitoring of progress of of electrical plants & lines; grid standards
execution of a power project by manual for operation and maintenance of
system. IT based monitoring has been transmission lines and the conditions for
promoted to have effective monitoring installation of meters for transmission and
system. Only a few projects being supply of electricity.
undertaken in 11th Plan are presently being
monitored through IT based system which 1.4 NATIONAL ELECTRICITY PLAN FOR 11TH
gives day to day progress of the project. PLAN
This needs to be replicated in all ongoing
projects to identify bottlenecks and to The National Electricity Plan covering the
take timely action for removal of hurdles review of 10th Plan, detailed plan for 11th
in project execution. plan and perspective plan for 12th Plan was
prepared by CEA in November 2004 and
1.3 POWER PLANNING BY CEA was circulated to all stakeholders as well
as put up on the CEA Website inviting
Central Electricity Authority (CEA) was comments by 15th March 2005, later
established under Section 3 of the extended to 15th April 2005. CEA received
Electricity (Supply) Act 1948 and it has comments on draft National Electricity
continued to exercise the functions and Plan from various stakeholders. After
perform duties as assigned to it under the taking in to consideration various
Electricity Act 2003. CEA is responsible for comments and suggestion received from
overall planning & development of the various stakeholders, the plan was
Power Sector in the country. CEA is a finalised by the Authority. The Plan was
technical organization to advise and assist finally approved by Government in July,
the central government on matters 2007 and it was notified in the Gazette of
relating to generation, transmission, India vide gazette No.159 dated 3rd
distribution, trading and utilization of August,2007. A review of the Plan is given
electricity. CEA has also been entrusted in the next Chapter.
with the responsibility of advising Central
and State Regulatory Commissions, State 1.5 PRESENT POWER SCENARIO IN THE
Governments, licensees, generating COUNTRY
companies on any matter on which advice
is sought or on any matter which shall Installed Capacity
enable them to operate the electrical
system efficiently. Certain other functions The Installed Capacity of the country as on
as entrusted to CEA as per Electricity Act 31st December, 2011 was 1,86, 655 MW as
2003, include specifying technical depicted in the Exhibit 1.1 as follows:
standards for construction of electrical
plants; safety requirements for

Introduction Chapter 1: Page | 11


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Exhibit 1.1 – All India Installed Capacity (as on 31st December, 2011)

NUCLEAR, NEW
4780, 3% RENEWABLES,
20162.24, 11%

HYDRO,
38748.4, 20%

GAS, 17742.85, COAL,


DIESEL,
10% 104021.4, 55%
1199.75, 1%

Note: Capacity of Renewables is available only up to 30.06.2011

The country has significant potential of Total Renewable Installed Capacity


generation from renewable energy comprises of 14104.62 MW from Wind,
sources. All efforts are being taken by 3120.83 MW from Small Hydro Plants,
Government of India to harness this 2787.63 MW from Biomass Power &
potential. The Installed capacity as on 31st Biomass Gasifiers and 149.16 MW from
December, 2011 from renewable energy Solar power & Urban & Industrial waste.
sources is 20,162 MW which comprises India ranks fifth in the world in terms of
of 3225.92 MW in the State sector and installed capacity of wind turbine power
16936.32 MW in the Private sector. The plants.

Exhibit 1.2
All India Installed Capacity (Renewable) As on 31st December, 2011
RENEWABLE INSTALLED CAPACITY

Biomass,
Solar149 MW,
2788MW,
1%
13.7%

Small Hydro,
3121MW, Wind,
15.3% 14105MW,
70%

Note: Capacity of Renewables is available only up to 30.06.2011

Chapter 1: Page | 12 Introduction


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

The growth of Installed Capacity and Generation in India from various sources is shown in
Exhibit 1.3, 1.4 & Table 1.2 below:
Table 1.2
Growth of Electricity Generation
Plan/Year Generation Growth rate in (%) Compound Growth (%)
8th Plan
1992-93 301.07 5.0 6.61
1993-94 323.53 7.5
1994-95 351.03 8.5
1995-96 380.08 8.3
1996-97 394.80 3.9
9th Plan
1997-98 420.62 6.5 5.47
1998-99 448.37 6.6
1999-2000 480.68 7.2
2000-01 499.55 3.9
2001-02 515.25 3.1
th
10 Plan
2002-03 531.61 3.2 5.16
2003-04 558.34 5.0
2004-05 587.42 5.2
2005-06 617.51 5.1
2006-07 662.52 7.3
11th Plan
2007-08 704.47 6.3
2008-09 723.79 2.7
2009-10 771.60 6.6
2010-11 811.10 5.6

Exhibit 1.3
ALL INDIA INSTALLED CAPACITY
200000

180000

160000 RES
Nuclear
140000

120000
MW

100000

80000
Thermal
60000 Hydro
40000

20000

0
1985-86

1986-87

1987-88

1988-89

1989-90

1990-91

1991-92

1992-93

1993-94

1994-95

1995-96

1996-97

1997-98
1998-99

1999-00

2000-01

2001-02

2002-03

2003-04

2004-05

2005-06

2006-07

2007-08

2008-09

2009-10

2010-11

Years

Introduction Chapter 1: Page | 13


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Exhibit 1.4
ALL INDIA GROSS GENERATION
1000000
900000 RES
Gross Generation-GWH

800000
Nuclear
700000
600000
500000
400000
300000 Hydro
200000
Thermal
100000
0
1985-86
1986-87
1987-88
1988-89
1989-90
1990-91
1991-92
1992-93
1993-94
1994-95
1995-96
1996-97
1997-98
1998-99
1999-00
2000-01
2001-02
2002-03
2003-04
2004-05
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11
Years

Coal based generation contributes major the year 2007-08 (1st year of 11th Plan), the
part of the installed capacity and peak deficit was about 18,000 MW (16.5%)
contributes to about 68.6% of the total and the average energy shortage in the
energy generation (year 2008-09). In country was about 73 Billion kWh (10%).
addition to above, the installed capacity of During the year 2008-09 (2nd year of 11th
captive power plants of 1MW and above is Plan), the peak deficit was about 13,000
of the order of 24,986 MW at the end of MW (12%) and the average energy
2007-08.The energy generated from shortage in the country was about 86
captive power plants during the year Billion kWh (11%). During the year 2009-10
2007-08 was 90477 GWh. (3rd year of 11th Plan), the peak deficit was
about 15,157 MW (12.7%) and the average
Actual Power Supply Position energy shortage in the country was about
84 Billion kWh (10.1%).
The country has been facing growing
shortages over the past five years. During
Table 1.3
All-India Actual Power Supply Position (2010-11)
(April, 2010- March, 2011)

Peak (MW) Energy


(Billion kWh)
Requirement 1,22,287 861
Availability 1,10,256 788
(-) Shortage/(+) Surplus (-) 12,031 (-) 73
(%) (-) 9.8 % (-) 8.5 %

The details of peak and energy shortages 10th and 11th Plans are given in Table 1.4
in the country at the end of 7th, 8th, 9th, below.
Chapter 1: Page | 14 Introduction
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Table 1.4
Details of Power Supply Position during Past Plans
REGION/ PEAK PEAK SURPLUS/ SURPLUS/ ENERGY ENERGY SURPLUS/ SURPLUS/
STATE/ DEMAND AVAIL- DEFICIT DEFICIT REQUIRE- AVAIL- DEFICIT DEFICIT
U.T. (MW) ABILITY (MW) (%) MENT ABILITY (MU) (%)
(MW) (MU) (MU)
At the End of 7th Plan 40385 33658 -6727 -16.7 247762 228151 -19611 -7.9
(1989-90)
At the end of 8th Plan 63853 52376 -11477 -18.0 413490 365900 -47590 -11.5
(1996-97)
At the end of 9th Plan 78441 69189 -9252 -11.8 522537 483350 -39187 -7.5
(2001-02)
At the End Of 10th Plan 100715 86818 -13897 -13.8 690587 624495 -66092 -9.6
(2006-07)
11th Plan
2007-08 108866 90793 -18073 -16.6 705724 628016 -77708 -11.0
2008-09 109809 96685 -13124 -12.0 774,324 689,021 -85,303 -11.0
2009-10 119166 104009 -15157 -13.8 830594 746644 -83950 -10.1
2010-11 122287 110256 -12031 -9.8 861591 788355 -73236 -8.5
2011-12(April-December) 1,27,724 1,14,233 -13,491 -10.6 6,94,780 6,39,908 -54,872 -7.9

Annual Electric Load Factor Electric Load factor has remained close to
80% since 2000-01, primarily because of
The Annual Electric Load Factor is the prevailing shortages in the system and the
ratio of the energy availability in the load staggering measure adopted in the
system to the energy that would have various states particularly staggered
been required during the year if the supply to agriculture in groups. Since the
annual peak load met was incident on the shortages are rising, the Annual Electric
system through out the year. This factor Load Factor also illustrates an increasing
depends on the pattern of Utilization of trend and is depicted in the Exhibit 1.5 as
different categories of load. The Annual follows:

Exhibit 1.5
Variation of System Load Factor
SYSTEM LOAD FACTOR

85
84
SystemLoad Factor (%)

83.74
83
81.95
82 82.11
80.54 81.51 81.62
81 80.8
79.75
80
79.44
79 78.8
78
77
76
2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11

Year

Reserve Margin and Hydro Thermal Mix Reserve margin of a System is defined as
the difference between the Installed
Introduction Chapter 1: Page | 15
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Capacity and the peak load met as a The Hydro thermal mix in generation has
percentage of the Peak load met. This marginally increased from 25.01% in 2000-
factor depends on a number of 01 to about 26.19% as on 31st March 2007
parameters, major ones being the mode and thereafter has been decreasing and
of power generation i.e. hydro, thermal, stands at 23.13 as on 31st March, 2010.
renewable and the availability of the However the Reserve Margin has
generating stations. Reserve Margin in decreased from 34.61% in 2000-01 to 27.71%
other countries varies from 16% to 75%. in 2009-10. This is illustrated in the Exhibit
1.6 below:

Exhibit 1.6
Variation of Reserve Margin and Hydro Thermal Mix
Variation of Reserve Margin and Hydro Thermal Mix
36
33.1
34 32.66
34.61
32 31.25
31.18
30 30.28
30.31 28.16
%

28 27.92 27.71
26.19
26 25.01
26.13 26.01 26.19
24 25.1
24.81 24.9 23.13
22
20
2000- 2001- 2002- 2003- 2004- 2005- 2006- 2007- 2008- 2009- 2010-
01 02 03 04 05 06 07 08 09 10 11
Year

Reserve Margin RM (%) Hydro Thermal Mix

This reduction in Reserve Margin is on and O&M practices and higher efficiency
account of increase in thermal PLF from parameters of thermal machines. This is
69 % in 2000-01 to 77.5 % in 2009-10 on illustrated in the Exhibit 1.7 below:
account of improvement in technology

Exhibit1.7
Variation of Reserve Margin & PLF
Variation of Reserve Margin and Thermal PLF
90
77.5
80
72.7
69.9
70 76.8 78.6 77.2 75.1
74.8 73.6
69 72.2
60
%

50

40 33.1 32.66 30.28


30.31
30 28.16
34.61 31.25 27.71
27.92 31.18
20
2000- 2001- 2002- 2003- 2004- 2005- 2006- 2007- 2008- 2009- 2010-
01 02 03 04 05 06 07 08 09 10 11
Year

Reserve Margin RM (%) Thermal PLF

Chapter 1: Page | 16 Introduction


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

The plant load factor of gas plant has also An encouraging feature is that this
increased from 48 % in 2000-01 to about decreasing Reserve Margin trend over the
65 % in 2009-10. The increase in PLF of gas years has been observed in spite of the
plants during 2009-10 has been due to hydro thermal mix has been varying
additional availability of gas from KG marginally. This implies that effect of
basin. The nuclear Load Factor however increased PLF of thermal stations is more
has reduced from 82 % in 2000-01 to 46.5% predominant in reducing the Reserve
in 2007-08 due to fuel shortage, but has Margin than the effect of hydro thermal
improved to 65.45% in 2009-10. However, mix of Installed Capacity to increase the
this has only marginal effect on the Reserve Margin.
reserve margin due to nuclear capacity
being a small component in Installed 1.6 12TH PLAN NATIONAL ELECTRICITY
Capacity. It is expected that with further PLAN
improvement in technology of thermal
power generation and higher unit size, as As mandated by the Act and the Policy,
also higher availability of gas and nuclear CEA has prepared the National Electricity
fuel, Reserve margin is further expected Plan for the 12th Plan, the perspective
to improve in future. Plan for the 13th Plan and a review of the
Status of implementation of the 11th Plan.
---+++---

Introduction Chapter 1: Page | 17


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Chapter 1: Page | 18 Introduction


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 2

REVIEW OF CAPACITY ADDITION IN 11TH FIVE YEAR PLAN (2007-12)

2.0 INTRODUCTION 2.1 11TH PLAN TARGET

The capacity addition for the11th Plan was One of the major objectives of the
planned keeping in view the aims and National Electricity Policy is that demand
objectives of the National Electricity is to be fully met by the year 2012 with all
Policy. The capacity addition target set for peaking and energy shortages to be
the 11th Plan was 78,700 MW, about removed. In addition, the overall
quadruple of what could be actually availability of Installed Capacity is to be
th
achieved during the 10 Plan. Achieving enhanced to 85% and a Spinning Reserve
this huge target required timely of at least 5% needs to be created. Also,
placement of orders, augmentation of the per capita availability of electricity is
manufacturing capacity, skilled manpower to be increased to over 1000 kWh by 2012.
and construction machinery, timely Towards fulfilling these objectives and
statutory clearances and close monitoring considering the feasibility of
& coordination between the executing implementation of various projects to
agencies. This Chapter includes details of materialize during the 11th Plan, the
likely capacity addition and the efforts capacity addition target for the 11th Plan
being made to address the constraints was fixed at 78,700 MW as per details
being faced in timely execution of the given in the Exhibits 2.1 to 2.3 below:
power projects.
Table 2.1

11th Plan Capacity Addition Target


Figures in MW
SOURCE Central State Private TOTAL

Hydro 8654 3482 3491 15627


Thermal 24840 23301 11552 59693
Nuclear 3380 - - 3380
Total 36874 26783 15043 78700

th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 19
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Exhibit 2.1

Nuclear
Gas/LNG Hydro
3380
6843 15627
Lignite 4%
9% 20%
2280
3%

Coal
50570 Total: 78700 MW
64%

Exhibit 2.2

Private
15043
19%
Central
36874
47%

State
26783
34% Total: 78700 MW

2.2 PREPARATION FOR CAPACITY addition requirements of the 11th plan.


ADDITION IN 11TH PLAN Before the commencement of the 11th
plan, CEA teams visited the BHEL works
2.2.1 Indigenous Manufacturing and held detailed discussions with BHEL
Capacity: BHEL being the largest supplier executives about the requirement of
of power plants equipment was expected power sector and their plans for
to get major orders for the 11th plan. CEA expansion to meet the increasing
had anticipated placement of order of requirement of the power sector. CEA in
over 50% of generation capacity on BHEL its report of March,2007 recommended
and power sector was heavily dependent augmentation of manufacturing capacity,
on BHEL for timely supply and execution enhancing of vendor list to outsource
of power projects. CEA reviewed the manufacturing of some of the items,
preparation of BHEL to meet the capacity enhancing manpower in manufacturing,
th
Chapter 2: Page | 20 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

design & engineering and project manufacturing capacity as well as


execution, advance procurement action encourage new entrepreneurs in these
for critical items, such as forging, areas to meet the requirement of the
castings, high pressure boiler materials for Power Sector. The constraints being faced
which there are few suppliers world wide , in this regard were also discussed and a
procurement of adequate construction view was formed to deal with these.
machinery instead of depending on the
leased one and IT based monitoring. 2.2.4 Government of india also
Review meetings were held with BHEL to constituted a Committee under Dr Kirit
discuss the augmentation plan of BHEL. Parekh then Member (Energy) Planning
Commission on Development of
2.2.2 Action was also taken to arrange Additional Vendors for Balance of Plants.
coal linkage for 11th plan projects. Matter The major recommendations of the
was taken up with MoE&F to accord committee are summarized below:
priority to identified 11th plan projects for
Environment and Forest clearance. (a) Order for BOPs (or EPC of BoPs)
should be placed within six months of
2.2.3 An International conclave on Key placement of order for main plant and
Inputs for Accelerated Development of equipment.
Power Sector for 11th Plan & beyond was (b) Liquidated damages for delay in
organised by CEA on 4th and 5th July,2007 execution of project in time should be
to sensitise the utilities, IPPs and the enhanced to discourage cornering of large
Industry about the requirement of the number of contracts by few suppliers.
power sector during the 11th plan. CEA (c) CEA to finalize the pre-qualification
furnished the requirement of different requirements for BoP vendors by
types of equipments and materials in February, 2008 end.
generation, transmission & distribution (d) CEA and NTPC to complete the
required for implementation of the 11th exercise for finalizing the guidelines for
plan. The major recommendations of standardization/ broad design criterion for
conclave were augmentation of various packages of BoPs progressively by
manufacturing capacity both for main the end of August, 2008.
plants and balance of plants, timely (e) Capacity building for availability of
placement of orders , review of pre- skilled manpower to be taken up by the
qualification requirements to permit project developers.
participation of new players in the bids, (f) Whether a level playing field is
measures to augment skilled work force provided to domestic supplier and foreign
including adopt an ITI schemes by project suppliers needs to be examined.
developer around the project area to
develop skills amongst the locals, 2.3 MID TERM APPRAISAL TARGET FOR
standardisation, etc. These 11TH PLAN
recommendations were followed by
organising Regional Workshops at As mentioned above, the target set for
Chennai, Chandigarh and Mumbai. During capacity addition during the 11th Plan was
these Conferences, the industry was 78,700 MW. As per Mid Term Appraisal
impressed upon to enhance their (MTA) of Planning Commission, certain
th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 21
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

projects totalling to 21,802 MW were likely made by Ministry of Power & CEA in
th
to slip from 11 Plan on account of various pursuing the developers and other Stake
reasons viz. delay in placement of order for holders. These additional projects total to
main plant, slow progress of civil work, 5,156 MW.
poor geology etc. Further, certain
additional projects which were originally Based on the above, capacity addition likely
th
not included in the 11 Plan target were during 11th plan as per Mid Term Appraisal
th
identified for benefits during 11 Plan by (MTA) was fixed as 62,374 MW. A Summary
expediting the process of project of the likely slippages and additional
implementation and compression of the projects identified is given in Table 2.2
construction schedule. This has been below:
possible through extraordinary efforts
Table 2.2
SUMMARY OF CAPACITY SLIPPING / ADDITIONAL CAPACITY FOR LIKELY BENEFITS DURING 11TH
PLAN
Figures in MW
11th Plan Capacity Addition Target (A) 78,700
Slipped From Target (B) 21,802
Balance Capacity (C) 56,898
Change in Capacity of projects as included in Target (D) 320
Increase in capacity of Anpara C 200
Increase in capacity of Sugen CCGT 20
Increase in capacity of Mettur Ext 100
Additional Capacity Likely during 11th Plan Outside Target (E) 5,156
Total Capacity (F) = (C+D+E) 62,374

Thus capacity addition likely during 11th capacity addition target of 62,374 MW is
Plan as per Mid Term Appraisal (MTA) is furnished in Table 2.3 below:
62,374 MW. A Sector wise Summary of this
Table 2.3
SUMMARY STATEMENT OF MID TERM APPRAISAL TARGET DURING THE 11TH PLAN
(SECTOR WISE AND TYPE WISE)

(Figs in MW)
HYDRO TOTAL THERMAL BREAKUP NUCLEAR TOTAL
THERMAL
CENTRAL SECTOR 2922 14920 13430 750 740 0 3380 21222
STATE SECTOR 2854 18501 14735 450 3316 0 0 21355

PRIVATE SECTOR 2461 17336 13725 1080 2531 0 0 19797


ALL-INDIA 8237 50756.9 41890 2280 65867 0 3380 62374

th
Chapter 2: Page | 22 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

2.4 ACTUAL/ LIKELY CAPACITY ADDITION likely capacity addition during 11th plan is
DURING 11TH PLAN about 52,063 MW. As against this the total
A capacity of 34,462 MW has been capacity already commissioned during 11th
commissioned during first four years of Plan is 45,965 MW. The latest status of
11th plan. Capacity addition programme commissioning of 11th Plan projects is as
during 2011-12 is 17,601 MW. Therefore the follows in Table 2.4.

Table 2.4
(Figures in MW)
Type
2007- 2008- 2009-10 * 2010-11* 2011- Total
08* 09* 12**
Hydro 2,423 969 39 690 1,990 6,111
Thermal 6,620 2,485 9,106 11,251 13,611 43,073
Nuclear 220 0 440 220 2,000 2,880
Total 9,263 3,454 9,585 12,161 17,601@ 52,063
* Commissioned @ 11503 MW already commissioned by Dec,2011

2.5 CAPACITY ADDITION FROM CAPTIVE and above) is about 32,900 MW. The
POWER PLANTS installed capacity has registered growth
of 4.4 % over the installed captive plant
Large number of captive plants including capacity of 31,517 MW as on 31st March,
co-generation power plants of varied 2010. The energy generation from
type and sizes exist in the country, which captive power plants (1MW and above)
are utilized in process industry and in- during the year 2009-10 was about 106.1
house power consumption. A number of billion units and registered a growth of
industries set up their captive plants to about 6.4 % in generation over
ensure reliable and quality power. Some generation of 99.7 billion units during
plants are also installed as stand-by units 2008-09. During the year 2008-09,
for operation only during emergencies surplus power of 8.4 BU from captive
when the grid supply is not available. was fed into the grid. Further, a capacity
Surplus power, if any, from captive addition of about 15,495 MW from
power plants could be fed into the grid Captive plants is expected by 2012 during
as the Electricity Act 2003, provides for the 11th Plan based on information
non-discriminatory open access. received from captive power plant
manufacturers, industries and other
As on 31st March, 2011, the Installed sources.
Capacity of Captive Power Plants (1MW

th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 23
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

2.6 GRID INTERACTIVE RENEWABLE POWER SOURCES DURING 11TH PLAN

In the 11th Plan, a capacity addition of 14,000 MW from renewable power sources has
been envisaged. Source- wise details are given in Table 2.5 below:

Table 2.5
11TH PLAN TENTATIVE TARGETS FOR GRID INTERACTIVE RENEWABLE POWER

(Figures in MW)

Sources / Systems Target for 11th plan


Wind Power 10,500
Biomass Power & Biomass Gasifiers 2,100
Small Hydro (up to 25 MW) 1400

Total 14,000
Source MNRE

th
Chapter 2: Page | 24 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Exhibit 2.3

Biomass Power Small Hydro


& Biomass (up to 25 MW)
Gasifiers 1400 Wind Power
2,100 10% 10,500
15% 75%

2.7 YEAR-WISE TARGETS & ACTUAL


CAPACITY ADDITION
Out of the above target of 14,000 MW, a
capacity of 9,717 MW has been added CAPACITY ADDITION TARGET /
during the first four years of 11th Plan. Till ACHIEVEMENT DURING 2007-08, 2008-09,
date the capacity addition from 2009-10,2 010-11
renewable during 11th Plan is about 12,400 A summary of revised programme/targets
MW. The above target of 14,000 MW for and actual achievement for 2007-08,
grid interactive renewable power does 2008-09, 2009-10 and 2010-11 is as below:
not include proposed addition of 1000
MW from Distributed Renewable Power
System (DRPS).

Capacity addition Target/Achievement during 2007-08,2008-09, 2009-10 & 2010-11


(Figures in MW)
Hydro Thermal Nuclear Total
Target Actual Target Actual Target Actual Target Actual
2007-08 2372 2423 8907 6620 660 220 12039 9263
2008-09 1097 969 5773 2485 660 0 7530 3454*
2009-10 845 39 13002 9106 660 440 14507 9585
2010-11 1,346 690 17,793 11,251 1,220 220 20,359 12161
*Low achievement due to change in definition of commissioning by CEA/MoP
Details of projects planned & likely during 11th Plan are furnished in Annexure 2.1

th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 25
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

2.8 CHANGES IN DEFINITION OF 2.9 REASONS FOR DELAY IN


COMMISSIONING BY CEA/MoP IN AUG, 08 COMMISSIONING OF PROJECTS DURING
11th PLAN.
The commissioning / capacity addition
shall be deemed to have taken place only  Delay in placement of orders - mainly
after a unit has demonstrated its Civil Works and Balance of Plants
capability to generate power at name (BOPs)
plate rating except for nuclear plants and  Delay and non-sequential supply of
reservoir based hydro stations. The date material for Main Plant and BoPs.
of capacity addition shall be the date  Shortage of skilled manpower for
when the following conditions have been erection and commissioning.
fulfilled:  Contractual dispute between project
developer and contractor and their sub-
A. Thermal (Coal , Gas, Lignite) vendors/sub-contractors.
i. The construction and  Inadequate deployment of
commissioning of all plants and construction machinery.
equipment required for safe  Shortage of fuel (Gas and Nuclear).
operation of the unit is complete.  Land Acquisition.
ii. The trial run operation has started.  Inadequate infrastructure facilities like
iii. The unit has touched full rated load reliable construction power supply and
with designated fuel. constraints in transportation of heavy
equipment.
B. Hydro
i. The trial run operation has started. 2.10 MAJOR CONSTRAINTS IN POWER
ii. The unit has achieved full rated SECTOR DEVELOPMENT AND THE
capacity in case of purely run of STRATEGY INITIATED BY THE
river stations and run of GOVERNMENT TO MEET THESE
river stations with pondage. CHALLENGES ARE AS FOLLOWS:
iii. The unit has achieved full rated
capacity or the design capacity  Enhancing Manufacturing Capacity of
corresponding to prevailing Main Plant
reservoir level in case of storage
power stations. BHEL has augmented its manufacturing
capacity from 6000 MW/year to 15,000
C. Nuclear MW/year and is in the process of
Nuclear units shall be declared to have augmenting its capacity further to 20,000
been commissioned after these are MW per annum by March 2012.
declared “Commercially operational” by
plant authority. Pre-qualifying requirements for super
critical Boiler-Turbine-Generator have
Prior to this, a unit was considered been reviewed by CEA and revised
commissioned just on synchronization advisory given to utilities in order to
with the grid. encourage new entrants in manufacturing
sector to enhance supplies and encourage
th
Chapter 2: Page | 26 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

competition. A major step has been that has signed an MOU with Bharat Forge Ltd.
a number of new manufacturers have to promote a JV Company for
came forward for setting up manufacture of castings, forgings, fittings
manufacturing facilities for Steam and high pressure piping required by the
Generators and Turbine Generators. These Power Sector.
include:
1. L&T-MHI NPC and L&T have also proposed to set up
2. Toshiba-JSW a JV for manufacturing of forgings, which
3. Alstom-Bharat Forge besides the nuclear plant requirements
4. Ansaldo Caldie-Gammon will also cater to thermal power projects.
5. BGR-Hitachi
6. Dov  Construction agencies
7. Thermax-Babcock
8. Cethar vessals- The need to enhance the number of
construction agencies is also being
Based on production schedules of BHEL & stressed upon. A NTPC / BHEL JV has been
various JVs, it is felt that country is likely firmed to take up work related to
to have adequate manufacturing capacity Engineering, Procurement and
as far as main plant equipments are Construction (EPC) for power plants and
concerned. other Infrastructure projects. This JV has
recently obtained some orders for BOPs.
 Enhancing Manufacturing Capacity of The latest methods of civil construction
BOP vendors with mechanical equipments and
manpower mobilisation needs to be
There were limited number of vendors for adopted.
BOP in the country. In recent past, it has
been noted that some of the plants could  Critical Materials
not commissioned due to delay in Balance
of Plants, though works in main plants There does not appear to be shortage of
were completed. To overcome the key materials except CRGO steel, higher
problem, action has been taken to grade CRNGO & thick boiler steel plants.
sensitize the industry to the needs of
widening the vendor base for Balance of Cold Rolled Grain Oriented (CRGO) steel is
Plants like Coal Handling Plant, Ash most commonly used for manufacture of
Handling Plants, Water treatment plant transformer. There is worldwide shortage
etc. Industry has been impressed upon to of CRGO steel and non availability of good
enhance their manufacturing capacity as quality CRGO steel in India resulted in
well as encourage new entrepreneurs in delay in supply of transformers. To
these areas. Qualifying requirements for overcome such problems, efforts are
new vendors of BoPs have been relaxed being made towards timely availability of
to enable new vendors to qualify for Critical Key Inputs required for power
bidding. Standardisation of BoP systems system expansion. Measures are being
and mandating a central organisation to initiated to develop vendors for critical
maintain a dynamic data base with regard inputs like boiler quality plates, P91 piping,
to BoP order is under consideration. NTPC CRGO sheet steel. Advanced planning has
th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 27
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

been suggested for materials to be CEA has recently recommended to


imported. Development of manufacturing Ministry of Power to make changes in
capacities for castings & forgings for National Electricity Policy, Tariff Policy and
turbine/ generators is also suggested. competitive Bidding Guidelines to include
BHEL has been requested to take advance the cost of skill development in and
procurement action for critical equipment around the project area in the project cost
like forgings and castings which have a of generation and transmission projects.
long lead time, so as to reduce time taken CERC has also been requested by CEA to
to commission any unit. Matter was taken consider the cost of human resource
up with Government of India to give development in and around project area
advisory to BHEL for advance as a pass through in generation and
procurement of a critical forgings and transmission tariff. It has been proposed
castings. Accordingly advisory has been that the provision on this account should
given by Ministry of Finance to BHEL to be restricted to actual expenditure or a
facilitate advance procurement action for pre-specified percentage of project cost
critical forgings/castings. whichever is lower.

 Manpower and training facilities in  IT based monitoring


Power Sector
The IT based monitoring is a system which
There is shortage of skilled manpower in enables to receive all information about
the country. It was been estimated that an the project to be monitored and
additional about 1 million workmen, programmes in real time, thereby helping
supervisors and engineers would be to highlight the critical issues, the cost
required for Construction, Operation and over runs and other aspects related to be
Maintenance of power equipment during reported at various levels of
11th Plan. In particular, technicians of management.
specified skills would be required in very
large numbers. To overcome the above It may be utilized to track the daily
problem, high priority is being accorded to progress of ongoing power projects and
human resource development and expedite the process of getting
training of power sector personnel. A very clearances from various agencies and
comprehensive and pragmatic approach would also be helpful in placing orders of
has been adopted to attract, utilize, BOP/equipments on time. The system can
develop and conserve valuable human also alert the authority for appropriate
resources. To bridge the gap between action if the project is not progressing as
supply and demand, a scheme called per schedule.
“Adopt an ITI” has been initiated with a
view to train new technicians and to The IT based monitoring system through
upgrade the skills of existing ones. As per use of software which would integrate
this scheme, ITIs are to be adopted by the master network with L1 and L2 level
power developers in the vicinity of their networks to facilitate simultaneous online
projects. updation from different geographical
locations. Summary dashboard

th
Chapter 2: Page | 28 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

information can also be accessed of all the CEA is also going to implement IMS-II with
projects and programs in real-time, the following broad objectives:-
helping in determining which projects are
in danger of delay/late completion and  More intensive and comprehensive IT
running over-budget. The system would based monitoring of execution of
also help to:- power projects.
 To provide adequate redundancy in
 ensure online updation of actual dates the existing data centre to enhance
of approval/release of each drawing by reliability and availability of the
engineering deptt. in a manner that system and to prepare a separate
can be accessed by all concerned. disaster recovery data centre.
 enable online monitoring of those
transport/logistic activities which are Since the number of projects likely to
critical for timely commissioning of the be commissioned during 12th Plan will
projects. be large, IT based monitoring would
 Monitor Poor projects performance be useful to monitor and generate
and poor sequencing of events. reports pertaining to ongoing
 Project delays, cost overruns projects.
 visibility into scheduling and material
delivery
 Cost overruns, unknown implications  Fuel Constraints
of material cost increases.
 Inefficient use of resources, incorrect  Some of the projects have been
mix of skills, project delay. delayed due to non-availability of
coal, gas and nuclear fuel.
All the projects were requested to  Konaseema (445MW) and
implement IT based monitoring for Gauthami (464 MW) in A.P. which
effective project monitoring & were ready for commissioning
implementation. However, only a few were delayed due to non-
projects have implemented the same. This availability of gas. These projects
is to be required to be implemented in all have since been allocated gas from
the projects. KG D6 basin and been
commissioned during 2009-10.
Central Electricity Authority has RAPP Unit-5 & 6, 220 MW each
implemented Integrated Management have already been commissioned,
System-I (IMS-I) for centralized collection as imported nuclear fuel is now
of data from various power generations, available for these units.
transmission and distribution entities in
the country through web based interface.  Contractual disputes
CEA has already approved the input A number of projects had awarded fixed
formats and reports pertaining to IMS-I price contracts during the 10th Plan period
and date is being obtained in the input which affected adversely due to
formats from respective organizations. unexpected increase in price of inputs.
CEA advised all the utilities not to award
fixed price contracts in future where the
th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 29
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

implementation period is longer. A model been incorporated. It is expected that


contract document with appropriate price adoption of the proforma would
calculation formula was circulated for the reduce contractual disputes between
guidance of the utilities. the employer and the contractors to a
large extent.
During the one-day international Conclave
on “Contract Management for ii. Institutional Arbitration Mechanism:
Accelerated Development of Hydropower To ensure speedy and efficient dispute
Projects” on 16th November, 2007 at New redressal, Institutional Dispute
Delhi organized by the Ministry of Power Resolution Mechanism has been
and Central Electricity Authority, it was proposed which is in line with
concluded that there are deficiencies in emerging global best practices.
the existing contract documents and Globally the increased emphasis on fair
management systems/practices, leading and timely determination of
to contractual disputes affecting the compensation events and claims has
development of the hydropower projects. tilted the scales in favour of
A need was felt to prepare equitable Institutional Arbitration Mechanisms
documents as guidelines for adoption by that ensures a more accountable and
stakeholders. transparent process for timely
resolution of disputes.
In pursuance of the same, a Task Force
was constituted by Ministry of Power, iii. Other issues suitably incorporated /
Govt. of India under the Chairmanship of modified inter-alia include
Chairperson, CEA & comprising members  Claims towards idling of resources,
from Utilities, IPPs/Developers,  Cost control,
consultants. The Construction Industry  Procedures for claims,
Development Council (CIDC) was engaged  Price adjustment formulae,
for the purpose.  Incentive bonus,
 Payment upon termination /
The draft document has been finalized foreclosure of contract
and sent to MoP for acceptance. Key
elements / concepts introduced in iv. Review committee provision –
Standard Bidding Document(SBD) inter- Constitution of a review committee has
alia include the following: been proposed for periodic revision of the
SBD and other documents for mid-course
i. Risk Register: It is seen that delays in correction.
most of the hydro projects occur on
account of contractual issues The Standard Bidding Document after
especially on account of risk sharing getting legal vetting has been finalized
arising out of unforeseen situations. and sent to MoP.
A proforma for risk register
incorporating risk sharing/allocation of  Standardization: Standard
different types of risks generally specification for steam generator and
encountered in hydro projects has Turbine generator for 500MW and

th
Chapter 2: Page | 30 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

above with sub critical technology and balance of plants are also under
were prepared by CEA with a view to preparation.
reduce the time in design &
engineering and implementation of
thermal projects. Standard
specifications of super critical units

---++---

th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 31
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Appendix-2.1

LIST OF PROJECTS COMMISSIONED/ BEING MONITORED FOR LIKELY BENEFITS DURING


11TH PLAN

Capacity Capacity Capacity


Fuel Capacity as per as per as per
Sl.No. Plant Name State Agency Status
Type (MW) 78,700 62,374 52,063
MW MW MW
CENTRAL SECTOR
1 Chandrapura U-7,8 Jharknd DVC Comnd Coal 500 500 500 500
2 Mejia U-6 WB DVC Comnd Coal 250 250 250 250
3 Mejia Ph II U7,8 WB DVC Comnd Coal 1000 1000 1000 1000
4 Kodarma U1 Jharknd DVC Comnd Coal 500 500 500 500
5 Kodarma U2 Jharknd DVC UC Coal 500 500 500
6 Durgapur Steel U1 WB DVC Comnd Coal 500 500 500 500
7 Durgapur Steel U2 WB DVC UC Coal 500 500 500
8 Raghunathpur Ph-I U1,2 WB DVC UC Coal 1200 1200 1200
9 Bokaro Expansion Jharknd DVC UC Coal 500 500
10 Kameng HEP Ar.Pr NEEPCO UC Hydro 600 600
11 Omkareshwar HEP MP NHDC Comnd Hydro 520 520 520 520
12 Teesta V U 1,2,3 HEP Sikkim NHPC Comnd Hydro 510 510 510 510
13 Sewa-II U1,3,2 HEP J&K NHPC Comnd Hydro 120 120 120 120
14 Chamera-III HEP HP NHPC UC Hydro 231 231 231 231
15 Parbati - II HEP HP NHPC UC Hydro 800 800
16 Parbati - III HEP HP NHPC UC Hydro 520 520 520
17 Uri-II HEP J&K NHPC UC Hydro 240 240 240 180
18 Nimoo Bazgo HEP J&K NHPC UC Hydro 45 45 45
19 Chutak HEP J&K NHPC UC Hydro 44 44 44 44
20 Teesta Low Dam-III HEP WB NHPC UC Hydro 132 132 132
21 Teesta Low Dam-IV HEP WB NHPC UC Hydro 160 160 160
22 Subansiri Lower HEP Ar.Pr NHPC UC Hydro 2000 2000
23 Barsingsar Lig U1,2 Rajas NLC Comnd Lignite 250 250 250 250
24 Neyveli - II Lig TN NLC UC Lignite 500 500 500 250
25 Tuticorin JV TN NLC UC Coal 1000 1000
26 Kaiga U-3,4 Karntk NPC Comnd Nuclear 440 440 440 440
27 RAPP U-5,6 Rajas NPC Comnd Nuclear 440 440 440 440
28 Kudankulam U 1,2 TN NPC UC Nuclear 2000 2000 2000 2000
29 PFBR(Kalapakkam) TN NPC UC Nuclear 500 500 500
30 Ratnagiri (Dhabol) JV Maha NTPC Comnd Gas/LNG 740 740 740 740
31 Sipat-II U4,5 Chattis NTPC Comnd Coal 1000 1000 1000 1000
32 Sipat-I U1 Chattis NTPC Comnd Coal 660 660 660
33 Sipat I U2-3 Chattis NTPC UC Coal 1320 1320 660
34 Bhilai JV U 1,2 Chattis NTPC Comnd Coal 500 500 500 500
35 Korba III U-7 Chattis NTPC Comnd Coal 500 500 500 500
36 Kahalgaon II U6,7 Bihar NTPC Comnd Coal 1000 1000 1000 1000
37 Dadri Ext U-5,6 Up NTPC Comnd Coal 980 980 980 980
Indira Gandhi TPP (Jhajjar)
38 Haryana NTPC Comnd Coal 500 500 500 500
JV U1
Indira Gandhi TPP (Jhajjar)
39 Haryana NTPC UC Coal 1000 1000 1000 500
JV U2,3
40 Farakka Stage-III U6 WB NTPC Comnd Coal 500 500 500 500
41 Simhadri-Ext U-3 AP NTPC Comnd Coal 500 500 500 500

th
Chapter 2: Page | 32 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Capacity Capacity Capacity


Fuel Capacity as per as per as per
Sl.No. Plant Name State Agency Status
Type (MW) 78,700 62,374 52,063
MW MW MW
42 Simhadri-Ext U-4 AP NTPC UC Coal 500 500 500
43 Bongaigaon TPP U 1-3 Assam NTPC UC Coal 750 750 500
44 Lohari Nagpala HEP Ut.Khand NTPC UC Hydro 600 600
45 Tapovan Vishnugarh HEP Ut.Khand UC Hydro 520 520
46 Koldam HEP HP UC Hydro 800 800
47 Mauda TPP U1,2 Maha UC Coal 1000 1000
48 Barh I U 1,2,3 Bihar UC Coal 1980 1980
49 Barh II U1 Bihar UC Coal 660 660
50 Nabinagar JV U-1,2,3 Bihar UC Coal 750 750
51 Vallur (Ennore) JV U1,2 TN UC Coal 1000 1000 1000
52 Tripura Gas ILFS JV Tripura UC Gas/LNG 726 750
53 Rampur HEP HP UC Hydro 412 412
54 Koteshwar U 1,2 HEP Ut.Khand Comnd Hydro 200 200 200 200
55 Koteshwar U3-4 HEP Ut.Khand UC Hydro 200 200 200 200
Sub Total (Central Sector) 35824 21222 16175
State Sector
1 Jurala Priya U 1-6 AP Comnd Hydro 234 234 234 234
2 Rayalseema U4,5 AP Comnd Coal 420 420 420 420
3 Vijaywada TPP St-IV, U1 AP Comnd Coal 500 500 500 500
4 Kakatiya TPP AP Comnd Coal 500 500 500 500
5 Kothagudem St-VI AP Comnd Coal 500 500 500 500
6 Nagarjuna Sagar TR AP UC Hydro 50 50 50
7 Lower Jurala U1-6 HEP AP UC Hydro 240 240
8 Pulichintala HEP AP UC Hydro 120 120
9 Kakatiya Ext U1 AP UC Coal 500 500
10 Lakwa Wh Assam UC Gas/LNG 37.2 37.2 37.2
11 Korba East Ext U2 Chattis Comnd Coal 250 250 250 250
12 Marwah TPP U 1,2 Chattis UC Coal 1000 1000
13 Korba West Ext PH III Chattis UC Coal 500 500
14 Pragati-III (Bawana) GT-1,2 Delhi Comnd Gas/LNG 500 500 500 500
Pragati-III (Bawana) GT-3,4
15 Delhi UC Gas/LNG 1000 1000 1000 500
& St-1,2
16 Kutch Lign TPS Gujarat Comnd Lignite 75 75 75 75
17 Dhuvran St Gujarat Comnd Gas/LNG 40 40 40 40
18 Utran CCPP-GT+ST Gujarat Comnd Gas/LNG 374 374 374 374
19 Surat Lignite Ext U3,4 Gujarat Comnd Lignite 250 250 250 250
20 Ukai Ext U6 Gujarat UC Coal 490 490 490
21 GSEG Hazira Ext Gujarat UC Gas/LNG 351 351 351 351
22 Pipavav JV Ccgt Gujarat UC Gas/LNG 702 702 702
23 Sikka TPP Ext Gujarat UC Coal 500 500
24 Yamuna Nagar U1,2 Haryana Comnd Coal 600 600 600 600
Rajiv Gandhi TPS (Hissar)
25 Haryana Comnd Coal 1200 1200 1200 1200
U1,2
26 Uhl - III HEP HP HPJVVNL UC Hydro 100 100
27 Sawara Kuddu HEP HP PVC UC Hydro 110 110
28 Baglihar-I U1,2,3 HEP J&K JKPDC Comnd Hydro 450 450 450 450
29 Varahi Ext U1,2 HEP Karntk KPCL Comnd Hydro 230 230 230 230
30 Bellary TPP U 1 Karntk KPCL Comnd Coal 500 500 500 500
31 Bellary TPP U 2 Karntk KPCL UC Coal 500 500 500 500
32 Raichur U 8 Karntk KPCL Comnd Coal 250 250 250 250
33 Kutiyadi Ext U1,2 HEP Kerala KSEB Comnd Hydro 100 100 100 100
34 Pallivasal HEP Kerala KSEB UC Hydro 60 60
35 Ghatghar Pss U1,2 Maha GOMID Comnd Hydro 250 250 250 250
36 Paras Ext U1,2 Maha MSPGCL Comnd Coal 500 500 500 500

th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 33
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Capacity Capacity Capacity


Fuel Capacity as per as per as per
Sl.No. Plant Name State Agency Status
Type (MW) 78,700 62,374 52,063
MW MW MW
37 New Parli Ext U-2 Maha MSPGCL Comnd Coal 250 250 250 250
38 Khaper Kheda Ext Maha MSPGCL Comnd Coal 500 500 500 500
39 Bhusawal TPP U4,5 Maha MSPGCL UC Coal 1000 1000 1000 1000
40 Myntdu St-I HEP Meghal MESEB UC Hydro 84 84 84 84
41 Myntdu St-I Addl Unit Meghal MESEB UC Hydro 42 42 42
42 New Umtru HEP Meghal MESEB UC Hydro 40 40
43 Birsinghpur Ext MP MPPGCL Comnd Coal 500 500 500 500
44 Amarkantak U-5 MP MPGENCO Comnd Coal 210 210 210 210
45 Malwa TPP U1,2 MP MPGENCO UC Coal 1000 1000
46 Satpura Ext U-1,2 MP MPPGCL UC Coal 500 500
47 Balimela HEP St-II U7,8 Orissa OHPC Comnd Hydro 150 150 150 150
48 GhTPP-II U-3,4 Punjab PSEB Comnd Coal 500 500 500 500
49 Giral Lignite U-2 Rajas RRVUNL Comnd Lignite 125 125 125 125
50 Chhabra TPS U-1,2 Rajas RRVUNL Comnd Coal 500 500 500 500
51 Kota TPP U7 Rajas RRVUNL Comnd Coal 195 195 195 195
52 Suratgarh Ext U6 Rajas RRVUNL Comnd Coal 250 250 250 250
53 Dholpur GT2+ST Rajas RRVUNL Comnd Gas/LNG 220 220 220 220
54 Kalisindh TPS U1 Rajas RRVUNL UC Coal 600 500
55 Valuthur Ext TN TNEB Comnd Gas/LNG 92.2 92.2 92.2 92.2
56 Bhawani Barrage II & III TN TNEB UC Hydro 60 60 60
57 Mettur Ext U1 TN TNEB UC Coal 600 500 600
58 North Chennai Ext U1,2 TN TNEB UC Coal 1200 600 1200
59 Baramura Gt Tri Comnd Gas/LNG 21 21
60 Maneri Bhali HEP Ut.Khand UJVNL Comnd Hydro 304 304 304 304
61 Parichha Ext U-5,6 Up UPRVUNL UC Coal 500 500 500
62 Harduaganj Ext U-8 Up UPRVUNL Comnd Coal 250 250 250 250
63 Harduaganj Ext U-9 Up UPRVUNL UC Coal 250 250 250 250
64 Anpara-D U1,2 Up UPRVUNL UC Coal 1000 1000
65 Purlia Pss WB WBSEB Comnd Hydro 900 900 900 900
66 Sagardighi U 1,2 WB WBPDCL Comnd Coal 600 600 600 600
67 Santaldih U5 WB WBPDCL Comnd Coal 250 250 250 250
68 Santaldih Ext-U 6 WB WBPDCL Comnd Coal 250 250 250 250
69 Bakreshwar U 4,5 WB WBPDCL Comnd Coal 420 420 420 420
70 Durgapur Ext U 7 WB DPL Comnd Coal 300 300 300 300
Sub Total (State Sector) 26783 21355 17237
Private Sector
Konaseema
1 Konaseema Gt+St AP Comnd Gas/LNG 445 445 445 445
Power
Gautami
2 Gautami AP Comnd Gas/LNG 464 464 464 464
Power
3 Kondapalli CCPP Ph-II Gt+St AP LANCO Comnd Gas/LNG 366 366 366
Raigarh TPP Ph-
4 Chattis Jindal Power Comnd Coal 1000 1000 1000 1000
I, U-1, 2; Ph II U 3,4
5 Lanco Amarkantak U1,2 Chattis LANCO Comnd Coal 600 600 600 600
6 Rithala CCPP (Gt1+Gt2+St) Delhi NDPL Comnd Gas/LNG 108.0 108.0 71.5
7 Sugen Torrent Block I, II & III Gujarat Torrent Comnd Gas/LNG 1147.5 1128 1147.5 1147.5
8 Mundra TPP Ph-I, U 1-4 Gujarat Adani Power Comnd Coal 1320 1320 1320 1320
9 Mundra TPP Ph-II U1,2 Gujarat Adani Power Comnd Coal 1320 1320 1320
10 Mundra TPP Ph-III U-1 Gujarat Adani Power UC Coal 660 660
11 Ultra Mega Mundra U1 Gujarat Tata Power UC Coal 800 800 800
12 Allain Duhangan U1,2 HP Adhpl Comnd Hydro 192 192 192 192
13 Karcham Wangtoo U1-4 HP Jpkhcl Comnd Hydro 1000 1000 1000 1000
Evrest Hydro
14 Malana HEP II U1,2 HP Comnd 100 100 100 100
Power
15 Budhil HEP HP LANCO UC Hydro 70 70 70 70

th
Chapter 2: Page | 34 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Capacity Capacity Capacity


Fuel Capacity as per as per as per
Sl.No. Plant Name State Agency Status
Type (MW) 78,700 62,374 52,063
MW MW MW
Himachal Hydro
16 Sorang HEP HP Sorang UC 100 100
Power
17 Maithan Rbc JV U1* Jharknd IPP Comnd Coal 525 525 525 525
18 Maithan Rbc JV U2* Jharknd IPP UC Coal 525 525 525 525
19 Torangallu U1,2 Karntk JSW Energy Comnd Coal 600 600 600 600
Udupi TPP (LANCO
20 Karntk NPCL Comnd Coal 1200 1015 1015 1200
Nagarjuna) U1,2
21 Trombay TPS Maha Tata Power Comnd Coal 250 250 250 250
22 JSW Energy, RaTNagiri U1-3 Maha JSW Comnd Coal 900 900 900 900
23 JSW Energy, RaTNagiri U4 Maha JSW UC Coal 300 300 300 300
Wardha
24 TPS At Warora U1,2,3,4 Maha Comnd Coal 540 540
Powerco
25 Tiroda TPP Ph-I U1 Maha Adani Power UC Coal 660 660 660
26 Maheshwar 1-10 MP SMHPCL UC Hydro 400 400 400
Sterlite
27 Sterlite TPP U 2,1 Orissa Comnd Coal 1200 600 1200 1200
Energy
Sterlite
28 Sterlite TPP U3 Orissa Comnd Coal 600 600
Energy
Raj West
29 Jallipa Lignite U 1,2 Rajas Comnd Lignite 270 270 270 270
Power
Raj West
30 Jallipa Lignite U 3-8 Rajas UC Lignite 810 810 810 135
Power
31 Teesta III Sikkim Teesta Urja UC Hydro 1200 1200 600
32 Chujachen Sikkim GATI UC Hydro 99 99 99
33 Srinagar Ut.Khand GVK UC Hydro 330 330
Reliance
34 Rosa St-I U1,2 UP Comnd Coal 600 600 600 600
Power
35 Anpara-C U1,2 UP LANCO UC Coal 1200 1000 1200 1200
36 Budge-Budge Ext WB CESC Comnd Coal 250 250 250 250
Sub Total (Private Sector) 16093 19797 18651
Total (11th Plan) 78700 62374 52063
Note - UC: Under Construction

---+++---

th
Review of Capacity Addition in 11 Five Year Plan (2007-12) Chapter 2: Page | 35
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

th
Chapter 2: Page | 36 Review of Capacity Addition in 11 Five Year Plan (2007-12)
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 3
DEMAND PROJECTIONS FOR ELECTRICITY

3.0 BACKGROUND forecasted year-wise electricity demand


for each State, Union Territory, Region
Demand assessment is an essential and All India in detail up to the end of 11th
prerequisite for planning of generation Five Year Plan i.e. 2011-12 and project the
capacity addition required to meet the perspective electricity demand for the
future power requirement of various terminal years of 12th & 13th Plans i.e. year
sectors of our economy. The type and 2016-17 and year 2021-22 for the Utility
location of projects planned is largely systems. The 18th EPS Committee was
dependent on the magnitude, spatial constituted in February 2010 and its draft
distribution as well as the variation of Report is under finalisation. The impact of
demand during the day, seasons and on a DSM and Energy Conservation Measures
yearly basis. Therefore, reliable planning during the 12th and 13th Plans on the
for capacity addition for future is largely demand of the country has been suitably
dependent on an accurate assessment of taken into account while finalizing the 18th
the future demand. EPS demand.

The National Electricity Policy also The 18th EPS draft report which has been
stipulates that CEA, while formulating the brought out now like encompasses
National Electricity Plan, would include various features for fulfilling the Aims and
the Short-term and the Long Term Objectives of the National/ State Policies
demand forecast for different Regions. framed by the Government(s). Due
consideration has been given while
3.1 DEMAND ASSESSMENT BY CENTRAL formulating the electricity demand
ELECTRICITY AUTHORITY – ELECTRIC forecasts to the promotion of high
POWER SURVEY (EPS REPORTS) efficiency and DSM measures in the
Agriculture, Industrial, Commercial
The Electricity Power Survey Committee is sectors as well as in domestic
constituted by CEA, with wide establishments. Future projections of the
representation from the Stake-holders in EPS have also been worked out based on
the Power Sector, to forecast the demand the T & D loss reduction targets assessed
for electricity both in terms of peak in consultation with various States/UTs.
electric load and electrical energy The Long Term Forecast is based on
requirement. CEA has been regularly reducing T & D losses to 23.2%, 18.9% and
bringing out the Electric Power Survey 15.4% by 2011-12, 2016-17 and 2021-22
Reports. The last Report by this respectively.
Committee is the 17th EPS which was
released in March 2007. This Report

Demand Projections for Electricity Chapter 3: Page | 37


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

3.2 DEMAND SCENARIOS Scenario:3


Actual Demand up to 2009-10 with 9%
A number of Demand Scenarios have been GDP Growth Rate & 0.9 Elasticity
worked out and a choice is required to be during 12th Plan and 0.8 Elasticity
made as to which of these demands is to during 13th Plan.
be adopted for carrying out Planning
studies for estimating the most accurate Scenario:4
Generation Capacity addition Programme Actual Demand up to 2009-10 with 9%
for the 12th and 13th Plans. The various GDP Growth Rate & 0.95 Elasticity
possible Demand Scenarios analysed in during 12th & 13th Plans.
this Chapter are as follows:
Scenario:5
Scenario:1 Actual Demand up to 2009-10 with 9%
Actual demand up to 2009-10 & then GDP Growth Rate & 1.0 Elasticity
applying Actual Cumulative Growth during 12th Plan and 0.9 Elasticity
Rate (CAGR) of past few years in 12th during 13th Plan.
plan & EPS growth rate in 13th plan.
Scenario:6
Scenario:2 18th EPS Demand Projections
Actual Demand up to 2009-10 with 9%
GDP Growth Rate & 0.8 Elasticity Details of Year-wise Energy Requirement
during 12th & 13th Plans projections by 12th & 13th Plan end are
furnished in Table 3.1 & 3.2 below:

TABLE 3.1
SCENARIOS OF ENERGY REQUIREMENT PROJECTIONS FOR 12th PLAN

Sc.-1 GR Sc.-2 GR Sc.-3 GR Sc.-4 GR Sc.-5 GR Sc-6


Year Actual ER % Actual ER % Actual ER % Actual ER % Actual ER % 18th EPS
(upto (upto 2009- (upto (upto (upto
2009-10) 10) & 9% 2009-10) 2009-10) 2009-10)
with GDP; 0.8 & 9% GDP; & 9% GDP; & 9% GDP;
actual Elasticity 0.9 0.95 1.0
CAGR Elasticity Elasticity Elasticity
Gwh Gwh Gwh Gwh Gwh
2003-04 559264 559264 559264 559264 559264
2004-05 591373 591373 591373 591373 591373
2005-06 631554 631554 631554 631554 631554
2006-07 690587 690587 690587 690587 690587
2007-08 739343 739343 739343 739343 739343
2008-09 777039 777039 777039 777039 777039
2009-10 830594 830594 830594 830594 830594
2010-11 890123 890397 897872 901610 905347
2011-12 953919 954505 970600 978697 986829 929111
2012-13 1022287 7.17 1023230 7.2 1049218 8.1 1062376 8.6 1075643 9.0 1001922
2013-14 1095555 1096902 1134205 1153209 1172451 1080438
2014-15 1174074 1175879 1226076 1251809 1277972 1165108
2015-16 1258221 1260543 1325388 1358838 1392989 1256413
2016-17 1348399 1351302 1432744 1475019 1518358 1354874

Demand Projections for Electricity Chapter 3: Page | 38


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Table 3.2
SCENARIOS OF ENERGY REQUIREMENT PROJECTIONS FOR 13th PLAN
th
Sc.-2 GR Sc.-3 GR Sc.-4 GR Sc.-5 GR Sc.-6 GR 18 EPS
Year Actual ER % Actual ER % Actual ER % Actual ER % Actual ER %
(upto (upto 2009- (upto (upto (upto
2009-10) 10) & 9% 2009-10) 2009-10) 2009-10)
with EPS GDP; 0.8 & 9% GDP; & 9% GDP; & 9% GDP;
GR Elasticity 0.8 0.95 0.9
Elasticity Elasticity Elasticity
Gwh Gwh Gwh Gwh Gwh
2017-18 1443326 7.1 1448595 7.2 1535902 7.2 1601133 8.6 1641345 8.1 1450982
2018-19 1544936 1552894 1646487 1738030 1774294 1552008
2019-20 1653700 1664703 1765034 1886631 1918012 1660783
2020-21 1770120 1784561 1892116 2047938 2073371 1778109
2021-22 1894736 1913050 2028348 2223037 2241314 1904861

The actual load factor in 2009-10 was 79.5 been considered while estimating the
%. In the past, the demand has not grown peak demand for 2016-17.
as anticipated and due to various other
reasons the decreasing trend of load A Summary of Energy Requirement and
factor as anticipated has not taken place. Peak demand in the various Scenarios
It would therefore be prudent that case of considered above and a Load factor of
GDP growth rate Scenarios with a modest 78% upto 2016-17 & 76% upto 2021-22 is
decline in load factor may be assumed. as follows:
Therefore, a load factor of about 78% has
Table 3.3
VARIOUS DEMAND SCENARIOS - ENERGY REQUIREMENT AND PEAK DEMAND (WITHOUT
EFFECT OF ENERGY CONSERVATION AND DSM MEASURES)

GDP growth GDP / Electricity Energy Energy Peak Peak


rates Elasticity require- require- Demand Demand
ment ment (MW) (MW)
(MkWh) (MkWh)
2016-17 2021-22 2016-17 2021-22
Actual 0.80 1351302 1913050 197767 287348
Energy 0.90/0.8 in 1432744 2028348 209686 304667
requirement 12th/13th Plans
( upto 2009- 0.95 1475019 2223037 215873 333910
10) with 9 % 1.0/0.9 in 1518358 2241314 222216 336655
th th
Growth rate 12 /13 Plans
Actual Energy requirement 1348399 1894736 202535 284598
( upto 2009-10) with actual
Growth rates
18th EPS 1354874 1904861 199540 283470
Considering the savings in energy Efficiency Measures and DSM
requirement and reduction in Peak programmes, a reduction of about 60 BU
Demand on account of BEE’s Energy in Energy Requirement and about 12,000

Demand Projections for Electricity Chapter 3: Page | 39


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

MW in Peak Demand may be made at end above Scenarios (except 18th EPS). The
of 12th Plan and a reduction of about Demand figures thus suitably modified are
15,000 MW in Peak Demand may be as given in the Table below:
made at end of 13th Plan in each of the

Table 3.4

VARIOUS DEMAND SCENARIOS - ENERGY REQUIREMENT AND PEAK DEMAND


(CONSIDERING EFFECT OF ENERGY CONSERVATION AND DSM MEASURES)

GDP growth GDP / Energy Energy Peak Peak


rates Electricity require- require- Demand Demand
Elasticity ment ment (MW) (MW)
(MkWh) (MkWh)
2016-17
2016-17 2021-22
2021-22
Actual Energy 0.80 1321972
185967 1877313
272348
requirement 0.90/0.8 in 1403414
197686 1992611
289667
th th
( upto 2009-10)12 /13
with 9 % Plans
Growth rate 0.95 1445689 2187300 203873 318910
1.0/0.9 in 1489028 2205577 210216 321655
12th/13th
Plans
Actual Energy requirement 1319069 1858999 190535 269598
( upto 2009-10) with actual
Growth rates
18th EPS* 1354874 1904861 199540 283470
* Reduction in Peak Demand and Energy Requirement on account of BEE’s Energy Efficiency
Measures and DSM programmes has not been reduced from 18th EPS figures as these have
already been accounted for while arriving at 18th EPS Peak Demand & Energy Requirement.

3.3 RECOMMENDED DEMAND SCENARIO end use method is adopted to make these
forecasts. The demand forecasts make
Of the Scenarios detailed above, the projections of unrestricted demand while
demand corresponding to 18th EPS accounting for nominal impact of Energy
projections has been considered for Efficiency and Demand Side Management
Generation Planning studies to assess measures. Generation Planning Studies
capacity addition requirement for 12th based on unrestricted demand were
and 13th plan periods. considered to be prudent and desirable.
However, additional impact of aggressive
These demand estimates were considered measures & other initiatives of BEE which
since they are based on a detailed and take into account the structural changes
systematic approach of load projections taking place in the Power Sector on
by the Electric Power Survey Committee account of various initiatives of the
comprising of various stakeholders. Partial

Demand Projections for Electricity Chapter 3: Page | 40


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Government have not been considered in Demand Projections as per 18th EPS draft
this Scenario. Report to be adopted by 12th and 13th
Plan end for the purpose of Generation
Planning Exercise are as follows:

Table 3.5

DEMAND ADOPTED FOR GENERATION PLANNING STUDIES

Energy Requirement Gwh Peak Load (MW)


2016-17 1354874 199540
(12TH Plan end)
2021-22 1904861 283470
(13th Plan end)

In the Integrated Energy Policy, Peak  18th EPS demand figures are to be
demand has been estimated assuming adopted for assessing the 12th
decreasing system load factor i.e. 76% up Plan Capacity addition
to 2010, 74% for 2011-12 to 2015-16, 72% for Programme and the 13th Plan
2016-17 to 2020-21 and beyond and these tentative capacity addition
demands are based on actual required, as the demand
consumption up to 2004-05 and it also assessment by the EPS is a
include Captive Demand. On the other through exercise based on end
hand 18th EPS demand projections have use method involving all
been based on actual demand up to Stakeholders.
2009-10 and this corresponds to demand
projections of utilities only. 18th EPS  Optimum capacity addition for
demand projections also have taken into 12th and 13th Plans has been
account Demand Side Management and worked out considering 18th EPS
Energy Conservation measures as demand figures. Thereafter,
proposed by BEE. Therefore 18th EPS seasonal variation in demand has
demand projections may be considered also been estimated (peak and
for purpose of Generation Planning off-peak) to ensure that the
optimum capacity addition would
3.4 CONCLUSION meet the demand in all the
seasons.

---+++---

Demand Projections for Electricity Chapter 3: Page | 41


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Demand Projections for Electricity Chapter 3: Page | 42


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 4

INITIATIVES AND MEASURES FOR GHG MITIGATION

4.0 INTRODUCTION significant opportunities to accelerate


growth while controlling the carbon
Human-induced climate change is posing a intensity of its development path. This
substantial threat to global development can be achieved by harnessing the
efforts. Therefore, global efforts to substantial synergies between “low
mitigate and moderate human-induced carbon” and economic performance
climate change are consistent with India’s through improving the efficiency of
national interest. At the macro-economy electricity generation, reducing technical
scale, India is a low-intensity producer of losses in the power sector, enhancing
CO2 emissions with per capita CO2 end-use energy efficiency in various
emissions being among the lowest in the sectors, developing hydropower and
world, at around 1 metric ton (MT) per renewable potential, and accelerating the
person compared with 4 metric ton per adoption of new technologies. Moreover,
person for the world average and 20 there are many development benefits that
metric ton per person for the United India can capture with a well-designed
States. India also performs very well low-carbon strategy including energy
when compared to other economies in security, rural access though distributed
respect of CO2 intensity per capita GDP renewable applications and cleaner air in
(tons of CO2 emissions per unit of GDP). cities and homes. In short, a low carbon
Having signed the 1992 UNFCCC growth strategy could be an opportunity
convention, India affirms the principle of to improve health, productivity and
“common but differentiated quality of life.
responsibility” for climate change.
The National Action Plan on Climate
The Initiative and Plans proposed by the Change (NAPCC) outlines India’s Strategy
Government’s Integrated Energy Policy to meet the challenge of Climate change
Report are projected to keep CO2 intensity and to enhance the ecological
declining while massively expanding rural sustainability of India’s development path.
access and increasing power generation Eight National Missions form the core of
to meet the demands of a rapidly-growing the National Action Plan, representing
economy. India needs to evaluate and multi-pronged, long term and integrated
develop strategic options that address strategies for achieving key goals in the
concern about changing climate without context of climate change, two out of
compromising – but rather reinforcing – which are National Solar Mission and
its growth and development objectives, Mission on Enhanced Energy Efficiency.
by facilitating additional investments and
transfer of technology, India has

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 43


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Choice of fuel for power generation is an have to go for major technological


important factor to mitigate GHG innovation so that maximum energy
emission. Renewable energy sources available from fossils fuel is converted to
being benign sources are being electrical energy. This would pose a
encouraged to the maximum extent challenge to engineers and technicians on
possible. In case of conventional sources, the means to tackle environmental
hydro and nuclear are the preferred degradation. Another problem dogging
options. Gas is preferred to coal and the thermal power stations is the
lignite for power generation. In case of proportion of ash content in coal and
coal based generation, technology stringent environmental norms for
options with higher efficiency are being emissions.
encouraged since there is an inverse The thermal generation today, is causing
correlation between efficiency and carbon atmospheric pollution through the
emission. Details of CO2 emission for emission of carbon dioxide, carbon
different types of power plants are as monoxide, nitrous oxide (nox) and
follows: sulphur dioxide (sox). New technology to
reduce GHG has to be developed. This is a
Type of Power Specific CO2 big challenge for engineers and
Plant emission technologists all over the world.
T CO2 /MWh
Coal 1.04 4.1 CARBON EMISSIONS FROM
Lignite 1.28 GENERATION - EXISTING STATUS
Gas-CC 0.43
Gas-OC 0.66 As per UNDP Human Development report
Gas Engine (Elect 0.46 2007-08, India’s per capita Carbon dioxide
only) emission in the year 2004 was only 1.2
Gas Engine (CHP) 0.22 tonnes which was amongst the lowest in
Oil 0.66 the world. The world average per capita
Diesel Eng 0.59 Carbon dioxide emission is around 4.5
Diesel OC 0.69 tones and highest being 20.6 tones for
Naptha 0.61 USA. India’s contribution is around 4% of
the world total CO2 Emission.
Hydro 0
Nuclear 0 The Installed generating capacity of India
Wind 0 is around 1, 82,690 MW at the end of
Solar 0 October, 2011. Installed capacity based on
Ref- CDM baseline data published by CEA (25-09- thermal generation is around 65% of which
08) based on IPCC 2006
coal constitutes about 84 %.
There has not been any major change in Table 4.1 below shows the weighted
basic power generation technology since average specific emissions for fossil fuel
its invention except improvement in power stations in the five regional grids of
efficiency. Even today, a substantial the country. It is evident that coal and
amount of heat energy of coal is wasted in lignite have highest emission rate
the power generation process. To meet (tCO2/MWh) among various fossil fuels.
the rising demand for power, it would

Chapter 4: Page | 44 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Table 4.1
Weighted average specific emissions for fossil fuel-fired stations in FY 2008-09
(Figures in tCo2/MWh)

Coal Diesel Gas Lignite Naphtha Oil


India 1.09 0.63 0.47 1.44 0.44 0.73
(All figures are based on Net Generation)

It may be mentioned that India’s Co2 increase primarily due to addition of more
emission rate (tCo2/Mwh) has been coal based power stations as compared to
reducing during the period 2003-04 to hydro stations. The trend of Weighted
2007-08. However, during the years 2008- Average Emission Rate is indicated in
09 and 2009-10 there has been a marginal following Table and Graph.

Table 4.2
Weighted Average Emission Rate (tCo2/Mwh) (incl. imports)

2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11


0.85 0.84 0.81 0.80 0.79 0.82 0.81 0.79

Weighted Average Emission Rate tCO2/Mwh


0.86

0.84
0.84 0.85

0.82
0.82
0.81
%

0.8
0.8 0.81
0.79
0.78 0.79

0.76
2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11
Year

Weighted Average Emission Rate tCO2/Mwh

4.2 INITIATIVES/ MEASURES • Technology Development –


Adoption of higher unit size & Clean
Major Initiatives being taken to develop Coal technologies
the power generation sector pertain to  Supercritical Technology – 2
increasing the efficiency of coal based percent point efficiency gain
power stations. These are as follows: possible
• Increase of unit size with higher
steam parameters.

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 45


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

 Ultra Supercritical Technology


–additional efficiency 0.75% 4.2.1 Increase in Unit Size with Higher
over 800 MW supercritical Steam Parameters
 Integrated Gasification The Indian Power Sector has witnessed
Technology – higher efficiency rapid technological development over the
of 40-45% last few decades. The largest size unit of
• R & M and Life Extension of old coal based plant which was a mere 30 MW
power stations – Benefits of CDM to in 1950s, rapidly increased to 60 MW in
be extended to overcome fund 60s, and 110/120/140 MW in 70s.
constraints Thereafter, 200 MW units of Russian
• Energy Efficiency improvement (LMZ) were introduced in 1977 and of
• Retirement of old inefficient units Siemens KWU design in 1983. The 500 MW
• Coal quality Improvement units were introduced in 1984. The
Other measures include increase in unit size was associated with
corresponding increase in steam
• Reduction in T & D losses – All India parameters (Pressure and Temperature)
T&D losses- 28.65% in 2006-07. Aim and efficiency. Enhanced efficiency
to bring down to 15% implies lesser GHG emission. The
• Efficiency in use of energy improvement in steam parameters and
• Setting up of pithead stations for design efficiency of various units are
reduction in transportation of coal indicated in Table 4.2 below:

The benefits from reduction in T&D losses


will be discussed in the Volume-II of the
Plan.

Table-4.3
Various Unit Sizes and main parameters

Unit Size M/s. MS/RH Gross Design


Pressure Temperature Efficiency
o
MW kg/cm2 C (%)
30-50 60 482 28.20
60-100 90 535 31.30
210 LMZ 130 535/535 35.63
210 KWU 150 535/535 37.04
250 150 535/535 38.3
500 169 538/538 38.6
660 247 538/565 39.5
565/593 40.5
800 247 565/593 40.5

Today 210/250 MW and 500 MW units coal based installed capacity. During the
form the backbone of Indian power 11th Plan, 4 nos of 660 MW supercritical
industry and constitute over 75 % of total units have already been commissioned

Chapter 4: Page | 46 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

and few more super critical units are 4.2.2 Introduction of Clean Coal
expected during remaining period of 11th Technologies
Plan. During the 12th Plan, it is being
planned that the percentage of 660 MW Supercritical Technology:
and 800 MW unit sizes with Supercritical
technology would still increase further Supercritical technology is being
and during the 13th Plan, all new coal introduced to further enhance the
based capacity is likely to be on efficiency of coal fired thermal
supercritical technology only. generation. With the advancements in
metallurgy and availability of better
Power generation using gas turbines as materials, adoption of higher parameters
prime movers started in a big way around beyond the critical points has become
the world in early 1960s & 70s. This was possible. With the adoption of higher
basically due to advancement of parameters, efficiency gain of about 2 % is
technology as new and better heat possible over sub critical units, thereby,
resistant alloys were manufactured reducing emissions of CO2, NOx and SOx.
enabling higher firing temperatures, Depending on the steam parameters
consequently higher cycle efficiencies. adopted, supercritical technology can lead
The Gas Turbines (GTs) are normally to about 4 % coal savings and
manufactured in standard sizes based on corresponding reduction in emissions as
development of manufacturing compared to conventional sub-critical
technologies. GTs are now available up to units. Already many supercritical units of
250 MW range. The open cycle operation 660 and 800 MW are under construction
typically achieves a generation efficiency in Central, State and Private Sector. 4
of about 35% and about 53% in combined units of 660 MW each have already been
cycle mode. Since Gas Turbines use commissioned till November, 2011 and
cleaner fuels (natural gas, LNG, distillate other units are likely to be commissioned
oil, Naphtha), GT based plants are more during remaining period of 11th Plan. Initial
environment friendly mode of power supercritical units in the country were
generation. There is a need to encourage based on steam parameters of 246
setting up of gas based plants during 12th kg/cm2, 535/565 deg C at turbine inlet but
Plan and beyond to meet part of the some of the units which have recently
capacity addition requirements. started construction have adopted higher
steam temperatures of 565/593 deg C
The availability of gas, has, however been resulting in higher efficiency. Supercritical
a major issue adversely affecting the technology has been made mandatory for
operation of existing gas turbine stations Ultra Mega Projects being implemented.
at optimum capacity. Development of
new Gas based power plants will depend BHEL have already entered into
on the availability of natural gas in the collaboration with M/s Alstom and
country. Siemens for manufacturing of super-
critical boilers and turbo-generators
respectively. With the view to enhance
the indigenous manufacturing capability,
efforts have been made to attract

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 47


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

International manufacturers for taking up supercritical technology has already been


the equipment manufacturing in India. adopted in Japan and some European
Already, L&T have formed JV companies countries. Some latest units in China are
with MHI Japan to manufacture super- also stated to be based on ultra-
critical boilers and turbines in India. supercritical technology. International
Bharat Forge-Alstom, JSW-Toshiba efforts are also underway to further
Thermax -Babcock and GB industries- increase the steam temperatures to 700
Ansaldo are other joint ventures set up for deg C and necessary technology
manufacture of supercritical power development is being undertaken through
equipment in the country. various R&D programmes. The 700 deg C
plants are slated to achieve an efficiency
A proposal for bulk ordering of eleven of over 50%.
numbers supercritical units of 660 MW for
various projects of NTPC and DVC has In the Indian scenario, large capacity
been approved by GOI . The proposal induction of supercritical units would have
envisages mandatory conditions of the taken place by the end of 12th plan, and
suppliers setting up manufacture of super- significant manufacturing capacity of
critical units in the country. This would supercritical units would be achieved
ensure few initial orders for the new joint through BHEL and other JV companies
ventures being set up to kick-start coming up in this area. Thus introduction
indigenous manufacturing. The bulk of ultra supercritical technology with
tendering of 5 projects having 11 such 660 steam parameters of about 600/600-620
MW units is under process by NTPC and deg C could be considered for specific
order is expected to be placed shortly. It sites based on relative techno-economics.
has been proposed to go for bulk It is expected that wider availability of
tendering with mandatory phased ultra supercritical technology over the
indigenous manufacturing for 800 MW next five years could lower the costs.
units immediately after the present bulk Further, the International partners of new
tendering of 11units is included. JVs are manufacturers of ultra
supercritical plants and could stimulate
Setting up of indigenous production the introduction of this technology in
facilities for supercritical plants and India in 13th Plan.
increase in indigenous components of
such units is expected to bring down their Circulating Fluidized Bed Combustion.
cost in future. It is expected that during (CFBC) Technology
the 12th Plan, the total coal based capacity
addition would be about 66,600 MW out CFBC technology has selectively been
of which 27,900 MW (42% ) is based on applied in India for firing high sulphur
supercritical units. refinery residues, lignite etc. A number of
125 MW CFBC units have been installed for
Ultra Supercritical Technology firing high sulphur lignite. Neyveli Lignite
Corporation is installing 250 MW CFBC
Ultra supercritical technology refers to boilers for their NLC TPS II expansion
adoption of still higher steam project. Complete technology know how
temperatures of 600/600 deg C. Ultra and commercial arrangement (licensee) of

Chapter 4: Page | 48 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

CFBC exist in the country and CFBC boilers 4.2.3 Renovation and Modernisation of
of upto 250 MW are being manufactured Thermal Power Stations
indigenously.
Background
IGCC Technology
Renovation and Modernisation (R&M)
The IGCC (integrated gasification and Life Extension (LE) of existing old
combined cycle) technology refers to power stations provide an opportunity to
power generation through gasification of get additional generation at low cost in
coal in gasifiers wherein the syngas is short gestation period. Besides
generated which after cleaning is used in generation improvement, it results in
gas turbine combined cycle systems to improvement of environmental emissions
generate power. Presently, efficiency of and improvement in availability, safety
IGCC plants internationally is comparable and reliability.
to those of supercritical plants but the
technology has the potential to achieve The Indian power sector has immense
higher efficiency than the conventional potential of reducing carbon dioxide
pulverized coal technology. emission by way of Renovation and
IGCC has been adopted internationally for Modernization schemes as some of the
very low ash coals or petroleum based plants are old and are operating at a low
fuels. With low gas and petroleum based efficiency. Benefits of CDM can be
fuels availability in the country, our efforts extended to overcome the fund
are mostly centered on technologies, constraints for the various R & M
which can use Indian high ash coals. schemes, especially for energy efficiency
International cooperation in developing improvements, as these schemes would
IGCC technology is being sought using mitigate carbon dioxide emissions and
typical high ash Indian coals which are save fossil fuel.
presently being used for power
generation in our Thermal Power Stations. R&M programme was initiated in 1984 as
Action has also been initiated for a centrally sponsored programme for 34
developing IGCC technology indigenously. numbers of thermal power stations
BHEL have been doing research on covering 163 thermal units in the country.
gasification of Indian coals and have The programme was successfully
signed an MOU with APGENCO to set up completed in the year 1992 and an
125 MW IGCC based plant. However, the additional generation of about 10,000
results of the past studies do not indicate MU/ annum was achieved.
any improvement in efficiency with IGCC
technology due to high ash contents of The Phase-II R&M programme for 44
Indian coal. numbers of thermal power stations was
taken up in the year 1990-91. Power
Finance Corporation (PFC) was to provide
loan assistance to the State Electricity
Boards (SEBs) for the R&M works.
However, this programme could not
progress as per schedule mainly due to

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 49


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

non-availability of funds and poor financial


conditions of State Electricity Boards 4.2.3.1 Formulation of R&M / LE
(SEBs). programme & Achievement during 11th
Plan
The R&M programme continued to be
implemented during 8th, 9th, 10th and 11th A Summary of Programme & tentative
Plan periods but met with limited success Achievement during 11th Plan is given in
due to various reasons such as non- Table below.
availability of units for shut down, delayed
supply of materials, fund constraint, lack
of agencies to undertake R&M works etc.

Table 4.4
LE/R&M Programme-Tentative Achievement during 11th Plan (2007 – 2012)

Sl Particular State Sector Central Sector Total (State sector +


No. Central Sector)
No. of Capacity No. of Capacity No. of Capacity
units (MW) units (MW) units (MW)
1. LE works
(Programme) 33 4524 20 2794 53 7318
(Tentative
Achievement) 15 1664 3 267 18 1931
2. R&M works
(Programme) 27 6015 49 12950 76 18965
(Tentative
Achievement) 20 4485 49 12950 69 17435
Total
(Programme) 60 10539 69 15744 129 26283
(Tentative
Achievement) 35 6149 52 13217 87 19366

Programme for 12th Plan DVC units are 4 numbers (840 MW). In
addition to above, R&M works have also
Under 12th Plan, life extension works have been identified on 23 units (4971 MW)
been identified on 72 thermal units of during the 12th Plan, out of this 11units
total capacity 16532 MW. This includes 30 (4050 MW) are from NTPC, 9 units (291
units (5860 MW) from state sector and 42 MW) are from NEEPCO and balance from
units (10672 MW) from central sector. Out state power utilities.
of these 42 number central sector units, The broad details of the programme are
NTPC units are 35 numbers (9202 MW), given in Table 4.5 below:
NLC units are 3 numbers (630 MW) and

Chapter 4: Page | 50 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Table 4.5
R&M/ LE Programme of Thermal Units during 12th Plan (2012 – 2017) including Units
Slipping From 11th Plan.
Sl Particular State Sector Central Sector Total (State sector +
No. Central Sector)
No. of Capacity No. of Capacity No. of Capacity
units (MW) units (MW) units (MW)
1. LE works
(Programmed) 30 5860 42 10672.19 72 16532.19
(Slipping From 11th 16 2620 17 2527 33 5147
Plan)
Sub-Total 46 8480 59 13199.19 105 21679.19
2. R&M works
(Programmed)
(Slipping From 11th 03 630 20 4341 23 4971
Plan) 07 1530 - - 07 1530
Sub-Total
10 2160 20 4341 30 6501
Total
(Programmed) 33 6490 62 15013.19 95 21503.19
(Slipping From 11th 23 4150 17 2527 40 6677
Plan)

Grand Total 56 10640 79 17540.19 135 28180.19


Of LE/R&M

The list of units identified for life Potential candidate units for LE and R&M
extension and R&M during 12th Plan is works during 13th Plan (2017-2022)
enclosed in Appendix-4.1 and 4.2 The Summary of 13th Plan R&M/LE
respectively. programme is given in Table 4.6 below:

Table 4.6
13TH PLAN R&M/LE PROGRAMME (POTENTIAL CANDIDATE UNITS)
Name of the State Sector Central Sector Total identified units
Programme (State + Central Sector)
during 13th Plan
No. of Units Capacity No. of Units Capacity No. of Units Capacity
(MW) (MW) (MW)
LE
Coal 55 12130 16 3940 71 16070
Gas 6 672 5 765.71 11 1438
Sub Total 61 12802 21 4706 82 17508

R&M
Coal 16 3560 6 2420 22 5980
Gas 6 1172 6 1172
Sub Total 16 3560 12 3592 28 7152
Grand Total 77 16362 33 8298 110 24660

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 51


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Future vision for R&M Programme Technical assistance to CEA by the World
Bank for the efficiency enhanced R&M
So far, R&M activities were confined to The World Bank is providing technical
old, small size units to sustain their assistance of US $ 1.1 million as a part of
operation, improve plant availability and GEF grant under Coal Fired Generation
extend their operating life. However, Rehabilitation Project to CEA for
such units are highly inefficient and beset addressing the barriers to energy efficient
with various operational problems. It is R&M in India. The scheme would be
aimed at gradually decommissioning such implemented through appointment of
units. consultants for carrying out studies
Today, 200/210/250MW/300MW and 500 related to reduction of barriers to R&M
MW units (61655 MW) consisting of 81 % of interventions in India, developing market
coal/lignite based installed capacity form for implementations and strengthening
the backbone of Indian Power sector. A institutional capacity at CEA in the field of
large number of 200/210 MW machines R&M.
and few 500 MW machines are in
operation for 15-25 years or more. Such 4.2.4 Renovation, Modernisation &
machines through efficiency integrated Uprating of Hydro Electric Power Projects
R&M provide a good opportunity for
performance enhancement through Renovation & Modernisation, Life
technology intensive R&M. Plant specific Extension and Up rating (RM&U) of
energy audit studies and techno-economic existing old hydro electric power projects
analysis are proposed to be carried out for is considered a good option, as this is cost
defining & implementation of efficiency effective and quicker to achieve than
integrated R&M/LE scheme. At present, setting up of green field hydro power
three power stations viz., Bokaro 'B' TPS projects.
(3x210MW), Kolaghat TPS (3x210MW) and
Nasik TPS Unit-3 (1x210MW) have been In order to augment the hydro generation
identified for efficiency integrated R&M and improve the availability of existing
study through bilateral cooperation with hydro power projects, Government of
German Government. Contract has been India has laid emphasis on R&M of various
awarded for preparation of Feasibility existing hydro electric power projects in
Study for all the above units. Further, few the country.
units such as Bandel TPS Unit-5 (210MW),
Koradi TPS Unit-1 (210MW) and Panipat Recognising the benefits of the R&M of
TPS (2x110MW) have also been identified hydroelectric power projects, Govt. of
for efficiency integrated R&M through India set up a National Committee in 1987
World Bank assistance. NIT for main plant and a Standing Committee in 1998
package for Bandel TPS Unit -5 has been thereafter, these have identified the
floated. The Energy Efficient R&M projects/ schemes to be taken up for
programme through external assistance is implementation under R&M. The National
intended to be taken up in few more units Perspective Plan document for R&M of
also. hydro electric power projects in the
country was also prepared in CEA during
the year 2000, incorporating the status of

Chapter 4: Page | 52 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

various projects/schemes already 2011-12. The summary of 11th Plan is given


identified for implementation/ completion in Table 4.7
till the end of the 11th Plan, i.e. the year
A Summary of the 12th Plan programme for completed and on which work is ongoing in
hydro R&M, Life Extension & Uprating the 12th Plan is as furnished in Table 4.8
Schemes and of the projects planned, below.

Table 4.7
SUMMARY OF R&M, LIFE EXTENSION & UPRATING PROGRAMME AND ACHIEVEMENTS
FOR 11TH PLAN - HYDRO

Description R&M LE & Uprating


No. of Projects Covered 15 5
Capacity (MW) 4883.50 935.00
Estimated Cost (Rs. Crores) 512.87
Expenditure incurred (Rs. Crores) till 354.76
31.03.2011
Targeted Benefits (MW ) - 491
Actual Benefits achieved - 380

Table 4.8
SUMMARY OF R&M AND LIFE EXTENSION PROGRAMME AND ACHIEVEMENTS FOR 12TH
PLAN – HYDRO

Description R&M LE & Uprating


No. of projects Covered 5 37
Capacity (MW) 1390.00 3858.80
Estimated Cost (Rs. Crores) 3887.55
Expenditure incurred (Rs. Crores) till 674.70
31.03.2011
Targeted Benefits (MW) - 4063.45
Actual Benefits achieved - -

Abbreviations: MW – Mega Watt; Res. – Restoration; U – Uprating; LE – Life Extension

The details of Hydro projects considered Emissions. During the 11th Plan, 3,000 MW
for R&M during 12th plan are given in of capacity was targeted to be retired.
Appendix-4.3 This comprised of coal and lignite units of
unit size lesser than 100 MW.
4.2.5 Retirement of Old and Inefficient
Thermal Plants During the 12th Plan, a capacity of about
4,000 MW has been proposed to be
Retirement of Old and Inefficient thermal retired which includes the remaining units
Plants and replacing them with new and of coal & lignite under 100 MW size, gas
more efficient units is an effective way of plants more than 30 years old (1987 &
using the fuel and minimizing GHG

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 53


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

before) and some coal units of 110 MW


capacity. 1. To designate or appoint energy
During the 13th Plan, retirement of 4,000 manager in charge of the activities
MW capacity has been considered which of energy efficiency and
includes all coal units lesser than 200 MW conservation;
(commissioned before 1982) and gas units 2. To get Energy Audit conducted by
commissioned before 1992 (more than 30 an accredited energy auditor ;
years old). 3. Furnish information with regard to
the energy consumed and action
4.2.6 Generation and Energy Efficiency taken on the recommendation of
Measures accredited energy auditors ;
4. Comply with the norms of energy
In a scenario where India tries to consumption.
accelerate its development process and
cope up with increasing energy demands, Central Electricity Authority has also
conservation and energy efficiency initiated action on creation of Energy
measures are to play a central role in our Efficiency Cells at all the thermal Power
energy policy. A national movement for Stations. Central Electricity Authority in
energy conservation can significantly collaboration with
reduce the need for fresh investment in M/s GTZ, Germany has also finalized the
energy supply systems in coming years. It training needs required by these cells
is imperative that all-out efforts are made under Indo-German Energy programme
to realize this potential. Energy (IGEN). Various regional
conservation is an objective to which all workshops/seminars on Energy Efficiency
the citizen in the country can contribute. are being held for effective working of
Whether a household or a factory, a small these Energy Efficiency cell under IGEN
shop or a large commercial building, a programme.
farmer or a office worker, every user and
producer of energy can and must make About 100 no. of units below the size of
this effort for his own benefit, as well as 100MW with total capacity of 5500 MW
that of the nation. are very old. These units are running at
low Plant load factor of about 50% on an
average.
Government of India has already enacted
Energy Conservation Act ,2001 (EC Act) 4.2.7 Efficient Use of Resources
which provides much needed legal
framework and institutional arrangement Efficiency in the use of resources is an
for promotion of energy efficiency in all important factor as it promotes more
sectors of economy. Under this EC Act, productive output from limited resources
Thermal Power Stations have already as well as it reduces the carbon footprint
been declared as Designated Consumers on the environment.
vide Government notification dated Cogeneration is the use of a heat engine
19.3.2007. or a power station to simultaneously
generate both electricity and useful heat.
Following are some of the relevant Cogeneration is a thermodynamically
provisions under the EC Act for Power efficient use of fuel. Conventional power
Stations as designated consumers: plants emit the heat created as a by-
Chapter 4: Page | 54 Initiatives and Measures for GHG Mitigation
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

product of electricity generation into the CHP plants can be set up by the building
environment through cooling towers, flue owner as a captive power plant. Or
gas, or by other means. Combined Heat several such buildings can come together
and Power (CHP) captures the by-product and form a group-captive power plant.
heat for domestic or industrial heating Energy from such plants would be viewed
purposes. CHP is most efficient when the as ‘deemed renewable energy” and the
heat can be used on site or very close to it. generators allowed feed-in rights to
Overall efficiency is reduced when the export the excess power to the grid or to
heat must be transported over longer power exchanges.
distances.
An equal, if not greater, opportunity
Combined Cooling, Heating and Power presents itself in the use of (clean) natural
(CCHP) gas for such “within the fence” CCHP
plants. By carefully calibrating the
Large industrial units such as cement allocation and restricting the use of
plants, chemical industries, textile plants, natural gas to CHP applications that can
etc have, for several years, been drawing offer an efficiency of at least 60%.
power from their captive power plants.
Many of these units have also gone in for 4.2.8 Distributed Generation
waste heat recovery to meet the needs of
process steam or chilling. Distributed Generation is the location of
generation source at or near the load
In the last few years, there has also been a centre. Most often this generation would
rise in the number of large commercial be from Wind, biogas, Solar or gas/ diesel
buildings in the form of IT complexes, engines. The major advantages of
multiplexes, data centres, modern Distributed Generation are as follows:
airports, etc that have a tremendous  Low transmission losses
amount of power requirement. As these Distributed flexible generation is
buildings are fully air-conditioned, the located close to consumption and
power intensity is extremely high. Due to load centres. Transmission losses
their concentrated load and the possibility are, therefore, minimised.
of using part of their air-conditioning
loads from the waste heat, they are ideal  Low transmission investments
candidates for combined heat and cooling Transmission investments are
solutions. Also due to the varying nature minimised, compared with the Rs 1
of their loads, they demand a high degree crore/MW needed to build the
of operational flexibility. transmission line system associated
with a UMPP.
It should be made mandatory for
commercial consumers with loads  Rapid capacity addition
exceeding 25 MW, to generate power in It enables a paradigm shift from
situ and to demonstrate a minimum large plants to more number of
thermal efficiency of 60%. Ensuring smaller plants, say in the range of
compliance will not be too difficult, given 25-200 MW. They enable quick
the incentives cited above. capacity addition. These plants
generally use standardised power

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 55


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

generating blocks, and deploy far not cause strain on natural


higher extent of prefabrication and resources.
modularisation. Due to this, the
time of site work is greatly reduced,  Better Grid support
and thus, time-to-start up is much Distributed generation provides
shorter. better grid support, and islanding
schemes can insulate load centres
 Lower physical vulnerability, and from cascade tripping.
risk mitigation
Distributed generation, apart from 4.2.10 Coal Quality Improvement:
increasing reliability, improving Coal characteristics have a significant
quality, reducing transmission costs, impact on the power plant performance.
reducing right-of-way acquisition Indian coal available for power generation
costs, etc, lowers the vulnerability is by and large of poor quality with high
of the electricity system, by ash content leading to low efficiencies of
spreading the points of generation the power plants. The average Gross
over a wider geographical area. If Calorific Value of the coal available for
large centralised plants are affected Indian power plant is in the range of
by natural disasters or acts of 3000.- 4500 Kcal/kg with ash content as
terrorism, the impact can be high as 40%. The use of Beneficiated coal
immediate and much higher, as either by coal washing or blending with
large chunks of power supplies low ash imported coal is being done at
drop out of the system. Distributed some of the stations. The use of
plants that ensure generation in beneficiated coal will not only improve the
smaller chunks from different sites performance of the plant leading to low
removes this weakness and carbon emissions but also would reduce
improves the resilience of the the over all operation and maintenance
system. Urban agglomerations costs. Many stations have started using
having several installations of highly washed coal and are in process of
sensitive or strategic importance blending with imported coal thereby
will particularly benefit from the risk improving their plant performance.
mitigation that such distributed
flexible generation offers. Ministry of Environment & Forests have
issued a notification requiring thermal
 Quicker financial closure power stations located 1000 kms. from pit
Project investments are smaller, heads or those located in urban, sensitive
and thus can be financially closed and critically polluted areas to use raw or
much faster. blended or beneficiated coal with ash
content not exceeding 34% on an annual
 Smallest land requirement, lowest average basis.
water use
Indian coals are less amenable to washing
Distributed generation technologies
and are characterized as difficult, as the
help in reducing the area footprint
washing yield is rather low. Hence,
per MW significantly. They also do
appropriate technical solutions have to be
not consume much water and do
found with a view to optimize cost of
Chapter 4: Page | 56 Initiatives and Measures for GHG Mitigation
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

washing and yields. Economics of washing the capacity addition programme for the
can be improved by utilizing rejects for 12th and 13th Plans. Energy from these
producing electricity in Fluidized Bed sources, whenever available, has been
Combustion (FBC) boilers. Many private considered foremost to meet the
washeries are setting up small capacity demand. Additional capacity from
FBC units based on washery rejects. conventional sources has been assessed
to meet the balance load of the system.
At present out of a total coal
consumption of about 323 million tones, 4.3.1 Potential of Renewables
washed coal accounts for a mere 33
million tones. With the allocation of coal Thrust is being accorded to development
blocks to private and Govt. power utilities of Renewable Energy Sources which are
for coal mining, washing is set to increase not only a renewable source but are also
rapidly. The large size supercritical units environmentally benign. The Ministry of
are slated to use washed /imported coal. Non-conventional Energy Sources has
projected the potential for Wind energy
4.3 GENERATION FROM RENEWABLE itself to be of the order of 45,000 MW.
ENERGY SOURCES IN INDIA Other forms of non-conventional energy
sources are bio-mass, small, mini and
Use of Renewable Energy Sources is a far micro hydro (using canal falls as cost of
better option than Conventional Energy civil works is minimal), tidal power and
Sources as they are sustainable and cause solar energy. These may also be viable as
comparatively very little pollution. distributed generation to meet the
However at a particular instant their demands of remote locations where
quantity is limited and these are not extension of grid may be difficult or very
capable of meeting the energy costly. In the short term these sources
requirement of the Utility. Also these could be exploited for bridging the
normally provide non despatchable demand-supply gap especially in
energy, dependent on the vagaries of geographically dispersed areas. Today the
nature and thus can not be relied upon to capital cost of non-conventional energy is
meet the peak demand of the system. higher than that of conventional sources
They generally run at an overall PLF of 15% on per kW basis. However, their viability
to 20% (PLF based on total capacity and could be established if financial cost
sum of energy from all the renewable benefit analysis is replaced by economic
sources). In addition, the power cost benefit analysis.
producing technologies are expensive As per the information furnished by
thereby increasing the tariff of power MNRE, the total estimated medium-term
produced. However due to their inherent potential (2032) for power generation
merits, development of these power from renewable energy sources such as
sources are being encouraged and power wind, small hydro, solar, waste to energy
thus generated is being fed into the Grid. and biomass in the country is about
Therefore, renewable energy sources 1,83,000 MW as given in Table 4.9 below:
have been considered while drawing up

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 57


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Table 4.9
(Figures in MW)
Sources / Systems Estimated Mid-Term (2032) Potential
Wind Power 45,000
Bio-Power (Agro residues & 61,000
Plantations)
Co-generation Baggasse 5,000
Small Hydro (up to 25 MW) 15,000
Waste to Energy 7,000
Solar Photovoltaic 50,000*
TOTAL 1,83,000

*As per Objective of the National Solar Mission,1,00,000 MW shall be the Installed Solar generation capacity by
2030 and 2,00,000 MW by 2050.

4.3.2 Development of Renewable Energy for supplying power to the Utility grid as
Sources well as in Stand-alone systems. It
empowers the State Electricity Regulatory
Renewable Energy has been appropriately Commissions (SERCs) to promote
given the central place in India’s National renewable energy and specify, for
Action Plan on Climate Change. purchase of electricity from renewable
Intergovernmental Panel on Climate sources a percentage of the total
Change(IPCC) in its Fourth Assessment consumption of electricity in the area of a
Report on ‘Mitigation of Climate Change’ distribution licensee. National Electricity
has observed that technologies are Policy also states that non-conventional
available for mitigating the climate energy sources have to be exploited fully
change, however these require and promotional measures have to be
appropriate Policy and financial support. taken for development of technologies
Due to its vast market potential for and sustainable development of these
renewable energy projects, and a sources by SERCs. The tariff policy also
relatively well-developed industrial, mandates minimum percentage of energy
financing and business infrastructure, from renewable sources to be made
India is perceived as an excellent country applicable for the tariffs to be determined
for Clean Development Mechanism (CDM) by SERCs. Thus the Electricity Act,
projects. National renewable energy plans National Electricity Policy and the Tariff
offer ample opportunity for CDM projects Policy of Government of India mandate
and technological innovations. CDM and development of renewable resources
the emerging carbon market in general through a system of obligation of a
have potential to contribute to the distribution company to purchase
financial viability of renewable energy electricity from such sources. These
projects, although not necessarily making Initiatives provide a major boost for
them fully viable. promotion of the renewable energy
sector in India.
The Electricity Act 2003 also recognises
the role of renewable energy technologies

Chapter 4: Page | 58 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

The total Installed capacity from During the 12th and 13th Plans, capacity
renewable energy sources at the end of addition is expected to be more than the
10th Plan i.e. as on 31.03.2007 was 7,761 11th Plan capacity addition from renewable
MW which comprises of 976 MW in sources. A number of Incentives have
State sector and 6785 MW in the Private been given by MNRE for setting up of
sector . The Present Installed capacity as Solar and Wind based power plants.
on 31.03.2011 is 18,456 MW from RES Therefore considering 14,000 MW cap
sources. India ranks fifth in the world in addition from renewable during the 11th
terms of installed capacity of wind turbine Plan. During the 12th and 13th Plans, the
power plants. The capacity addition target capacity addition from renewables is
for 11th Plan from renewable sources is expected to be about 18,700 MW and
14,000 MW (not including solar capacity as 31,000 MW respectively. The same is
proposed under the Solar Mission) illustrated in Exhibit below:

Considering 7,761 MW from renewables at


the beginning of 11th Plan i.e. 31/3/2007, 4.4 DEVELOPMENT OF SOLAR POWER
the capacity from renewables at the end 4.4.1 Introduction
of 11th, 12th and 13th Plans is expected to be
21,761 MW, 40,461 MW and 71,461 MW. Out of all the Non-conventional resources
As per MNRE’s perspective Plan, a of power generation, Solar energy is the
capacity addition of 50,000 MW is most readily available and abundant
envisaged during the 12th and 13th Plan source of energy. India being a tropical
periods. These estimates includes likely country with abundant sunshine, solar
capacity addition through Grid – energy could be easily harnessed for
interactive Solar Power. The National power generation. It is especially
Action Plan on Climate Change has advantageous while considering power
identified large-scale Solar Power options for rural electrification, both as
generation as one of the thrust areas grid-connected power and distributed
under proposed Solar Mission, An power option.
indicative target of 20,000 MW Solar
Power by 2020 is envisaged in this Plan. A National Solar Mission has been
launched under the National Action Plan

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 59


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

for Climate Change (NAPCC) to


significantly increase the share of solar 4.4.2 Potential in India for solar energy
energy in the total energy mix while India gets plenty of sunlight due to its
recognizing the need to expand the scope proximity to the equator. About 5,000
of other renewable and non-fossil options trillion kWh energy is incident over India’s
such as nuclear & wind energy and land area with most parts receiving 4 – 7
biomass. kWh per sq. m per day. As a thumb rule, 1
The ingress of solar technology for energy MW of solar capacity without storage
use has been slow due to a number of facility produces 1.6 MU of electricity per
factors predominantly the high capital annum. In India potential of solar energy
cost and large land requirement for solar is available in the States which are rich in
installations. A further constraint has been Sunshine, particularly in the States of
its availability only during the day for Rajasthan, Gujarat, Andhra Pradesh, Tamil
energy use, thereby requiring additional Nadu and Ladakh. A mapping of the solar
high cost for storage system. For any potential is available which could be
technology to play an effective role and to utilized for while setting up Solar
bring down the costs, it is necessary to installations.
take up capacity building in “Mission 4.4.3 Power from solar energy-
mode”. Accordingly all efforts are being Technology Options
made to harness Solar energy in the most
effective manner, with an eye on Solar power entails producing power from
sustainability in the near future. the energy of the sun. Sunlight can be
converted into electricity predominantly
MNRE has launched a new scheme in by using 2 types of technologies i.e.
March 2008 for installation of Megawatt Photovoltaic (PV) cell and Solar Thermal
Capacity Grid Interactive Solar Power or Concentrating Solar Power (CSP)
Plants. Under this project, the Ministry will technology as follows:
provide a generation based incentive of a
maximum of Rs.12 per KWh for the (i) Solar Photovoltaic Panels
electricity generated from Solar (ii) Solar Thermal (CSP and heating),
Photovoltaic and the maximum of Rs.10 which includes Parabolic Trough,
per KWh for the electricity generated Power Towers Dish Design and
through Solar Thermal Power Plants and Fresnel Reflector.
fed to the grid from a grid interactive solar
power plant of a capacity of 1 MWp and Each technology has its own merit and
above. This incentive will be provided to demerit and a judicious choice needs to be
the project developers at a fix rate for a made depending upon the requirement
period of ten years and will be worked out and inputs available.
taking into account the tariff provided by 4.4.4 Solar Photo-voltaic (PV) Technology
the utility to the solar power producer.
This programme will be limited to an A solar cell or photovoltaic cell is a device
aggregate installed capacity of 50MWp of that converts sunlight directly into
Solar Power during the 11th Plan period electricity by the photovoltaic effect.
with each State being allowed to set up Assemblies of cells are used to make solar
upto 10MWp aggregate capacity. panels, solar modules, or photovoltaic
Chapter 4: Page | 60 Initiatives and Measures for GHG Mitigation
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

arrays. Solar cells are often electrically then be converted to electrical energy by
connected and encapsulated as a module. turbine.
PV modules often have a sheet of glass on
the front (sun up) side, allowing light to The Salient Features of Comparison of the
pass while protecting the semiconductor 3 thermal technologies i.e. Parabolic
wafers from the elements (rain, hail, etc.). Trough, Power Tower and Dish/Engine are
Solar cells are also usually connected in as follows:
series in modules, creating an additive  Towers and troughs are best
voltage. Connecting cells in parallel will suited for large, grid connected
yield a higher current. Modules are then power projects in the 30-200 MW
interconnected, in series or parallel, or size wheras dish/engine systems
both, to create an array with the desired are modular and can be used in
peak DC voltage and current. single dish applications or
To make practical use of the solar- grouped in dish farms to create
generated energy, the electricity is most large multi- megawatt projects.
often fed into the electricity grid using
 Parabolic troughs are the most
inverters (grid-connected PV systems); in
mature solar power technology
stand alone systems, batteries are used to
available today and the
store the energy that is not needed
technology most likely to be used
immediately. PV has mainly been used to
for near term deployment. Proven
power small and medium-sized
technology waiting for an
applications, from the calculator powered
opportunity to be developed.
by a single solar cell to off-grid homes
powered by a photovoltaic array. For  Power towers, with low cost and
large-scale generation, CSP plants have efficient thermal storage promise
been the norm. However recently multi- to offer despatchable, high
megawatt PV plants are becoming capacity factor, solar only power
common. plants in the near future. However
Newer alternatives to standard crystalline they require the operability and
silicon modules include casting wafers maintainability of the molten-salt
instead of sawing, thin film (CdTe, CIGS, technology to be demonstrated
amorphous Si, microcrystalline Si), and the development of low cost
concentrator modules, 'Sliver' cells, and heliostats
continuous printing processes. Due to
 The modular nature of dishes
economies of scale solar panels get less
allows them to be used in smaller,
costly as people use and buy more — as
high value applications. However
manufacturers increase production to
the dish/engine systems require
meet demand, the cost and price is
the development of at least one
expected to drop in the years to come.
commercial engine and the
development of a low cost
4.4.5 Solar Thermal Technology
concentrator
In this technology, the solar energy is
converted into thermal energy, which can

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 61


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

 Towers and dishes offer the solar thermal; on promoting off-grid


opportunity to achieve higher systems to serve populations without
solar-to electric efficiencies and access to commercial energy and modest
lower cost as compared to the capacity addition in grid-based systems. In
trough type but uncertainty the second phase, after taking into
remains as to whether these account the experience of the initial years,
technologies can achieve the capacity will be aggressively ramped up to
necessary capital cost reduction create conditions for up scaled and
and availability improvements competitive solar energy penetration in
the country.
4.4.6 Objectives and Targets For Solar
Power in India To achieve this, the Mission targets are:
• To create an enabling policy framework
As per JNNSM, the objective of the for the deployment of 20,000 MW of
National Solar Mission is to establish India solar power by 2022.
as a global leader in solar energy, by • To ramp up capacity of grid-connected
creating the policy conditions for its solar power generation to 1000 MW
diffusion across the country as quickly as within three years – by 2013; an
possible. additional 3000 MW by 2017 through
The Mission will adopt a 3-phase the mandatory use of the renewable
approach, spanning the remaining period purchase obligation by utilities backed
th th with a preferential tariff. This capacity
of the 11 Plan and first year of the 12 can be more than doubled – reaching
Plan (up to 2012-13) as Phase 1, the 10,000MW installed power by 2017 or
th
remaining 4 years of the 12 Plan (2013-17) more, based on the enhanced and
th
as Phase 2 and the 13 Plan (2017-22) as enabled international finance and
Phase 3. At the end of each plan, and mid- technology transfer. The ambitious
th th target for 2022 of 20,000 MW or more,
term during the 12 and 13 Plans, there will be dependent on the ‘learning’ of
will be an evaluation of progress, review the first two phases, which if
of capacity and targets for subsequent successful, could lead to conditions of
phases, based on emerging cost and grid-competitive solar power. The
technology trends, both domestic and transition could be appropriately up
global. The aim would be to protect scaled, based on availability of
Government from subsidy exposure in international finance and technology.
case expected cost reduction does not • To create favourable conditions for
materialize or is more rapid than solar manufacturing capability,
expected. particularly solar thermal for
The immediate aim of the Mission is to indigenous production and market
focus on setting up an enabling leadership.
environment for solar technology • To promote programmes for off grid
penetration in the country both at a applications, reaching 1000 MW by
centralized and decentralized level. The 2017 and 2000 MW by 2022.
first phase (up to 2013) will focus on
capturing of the low-hanging options in

Chapter 4: Page | 62 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

• To achieve 15 million sq. meters solar • To deploy 20 million solar lighting


thermal collector area by 2017 and 20 systems for rural areas by 2022.
million by 2022.

4.4.7 Mission strategy (phase 1 and 2) Obligation (RPO) mandated for power
utilities, with a specific solar component.
The first phase will announce the broad This will drive utility scale power
policy frame work to achieve the generation, whether solar PV or solar
objectives of the National Solar Mission by thermal. The Solar Purchase Obligation
2022. The policy announcement will create will be gradually increased while the tariff
the necessary environment to attract fixed for Solar power purchase will decline
industry and project developers to invest over time.
in research, domestic manufacturing and B. The below 80°C challenge – solar
development of solar power generation collectors
and thus create the critical mass for a The Mission in its first two phases will
domestic solar industry. The Mission will promote solar heating systems, which are
work closely with State Governments, already using proven technology and are
Regulators, Power utilities and Local Self commercially viable. The Mission is setting
Government bodies to ensure that the an ambitious target for ensuring that
activities and policy framework being laid applications, domestic and industrial,
out can be implemented effectively. Since below 80 °C are solarised. The key
some State Governments have already strategy of the Mission will be to make
announced initiatives on solar, the Mission necessary policy changes to meet this
will draw up a suitable transition objective:
framework to enable an early and • Firstly, make solar heaters mandatory,
aggressive start-up. through building byelaws and
A. Utility connected applications: incorporation in the National Building
constructing the solar grid Code,
The key driver for promoting solar power • Secondly, ensure the introduction of
would be through a Renewable Purchase effective mechanisms for certification and
Initiatives and Measures for GHG Mitigation Chapter 4: Page | 63
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

rating of manufacturers of solar thermal solar lights for lighting purposes would be
applications, promoted in settlements without access
• Thirdly, facilitate measurement and to grid electricity and since most of these
promotion of these individual devices settlements are remote tribal settlements,
through local agencies and power utilities, 90% subsidy is provided. The subsidy and
and the demand so generated would be
• Fourthly, support the upgrading of leveraged to achieve indigenization as
technologies and manufacturing well as lowering of prices through the
capacities through soft loans, to achieve scale effect. For other villages which are
higher efficiencies and further cost connected to grid , solar lights would be
reduction. promoted through market mode by
C. The off-grid opportunity - lighting enabling banks to offer low cost credit.
homes of the power- deprived poor: • Set up stand alone rural solar power
A key opportunity for solar power lies in plants in special category States and
decentralized and off-grid applications. In remote and difficult areas such as
remote and far-flung areas where grid Lakshadweep, Andaman & Nicobar
penetration is neither feasible nor cost Islands, Ladakh region of J&K. Border
effective, solar energy applications are areas would also be included.
cost-effective. They ensure that people
with no access, currently, to light and Promotion of other off grid solar
power, move directly to solar, leap- applications would also be encouraged.
frogging the fossil fuel trajectory of This would include hybrid systems to meet
growth. The key problem is to find the power, heating and cooling energy
optimum financial strategy to pay for the requirements currently being met by use
high-end initial costs in these applications of diesel and other fossil fuels. These
through appropriate Government devices would still require interventions to
support. bring down costs but the key challenge
Currently, market based and even micro- would be to provide an enabling
credit based schemes have achieved only framework and support for entrepreneurs
limited penetration in this segment. The to develop markets.
Government has promoted the use of Solar energy to power computers to assist
decentralized applications through learning in schools and hostels,
financial incentives and promotional Management Information System (MIS)
schemes. While the Solar Mission has set a to assist better management of forests in
target of 1000 MW by 2017, which may MP, powering milk chilling plants in
appear small, but its reach will add up to Gujarat, empowering women Self Help
bringing changes in millions of Groups (SHGs) involved in tussar reeling in
households. The strategy will be learn Jharkhand, cold chain management for
from and innovate on existing schemes to Primary Health Centres (PHCs) are some
improve effectiveness. The Mission plans examples of new areas, being tried
to: successfully in the country. The Mission
• Provide solar lighting systems under the would consider up to 30 per cent capital
ongoing remote village electrification subsidy (which would progressively
programme of MNRE to cover about decline over time) for promoting such
10,000 villages and hamlets. The use of innovative applications of solar energy
Chapter 4: Page | 64 Initiatives and Measures for GHG Mitigation
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

and would structure a non-distorting package, similar to SIPS, could be


framework to support entrepreneurship, considered for setting up manufacturing
up-scaling and innovation. plants for solar thermal systems/ devices
and components.
In order to create a sustained interest The SME sector forms the backbone for
within the banking community, it is manufacture of various components and
proposed to provide a soft re-finance systems for solar systems. It would be
facility through Indian Renewable Energy supported through soft loans for
Development Agency (IREDA) for which expansion of facilities, technology up
Government will provide budgetary gradation and working capital. IREDA
support. IREDA would in turn provide would provide this support through
refinance to NBFCs & banks with the refinance operations.
condition that it is on-lend to the It should be ensured that transfer of
consumer at rates of interest not more technology is built into Government and
than 5 per cent. The Mission would private procurement from foreign
provide an annual tranche for the purpose sources.
which would be used for refinance E. R&D for Solar India: creating
operations for a period of ten years at the conditions for research and application
end of which the funds shall stand A major R&D initiative to focus: firstly, on
transferred to IREDA as capital and improvement of efficiencies in existing
revenue grants for on-lending to future materials, devices and applications and on
renewable energy projects. reducing costs of balance of systems,
D. Manufacturing capabilities: innovate, establishing new applications by
expand and disseminate addressing issues related to integration
Currently, the bulk of India’s Solar PV and optimization; secondly, on developing
industry is dependent on imports of cost-effective storage technologies which
critical raw materials and components – would address both variability and
including silicon wafers. Transforming storage constraints, and on targeting
India into a solar energy hub would space-intensity through the use of better
include a leadership role in low-cost, high concentrators, application of nano-
quality solar manufacturing, including technology and use of better and
balance of system components. Proactive improved materials. The Mission will be
implementation of Special Incentive technology neutral, allowing
Package (SIPs) policy, to promote PV technological innovation and market
manufacturing plants, including domestic conditions to determine technology
manufacture of silicon material, would be winners.
necessary. A Solar Research Council will be set up to
Indigenous manufacturing of low oversee the strategy, taking into account
temperature solar collectors is already ongoing projects, availability of research
available; however, manufacturing capabilities and resources and possibilities
capacities for advanced solar collectors of international collaboration.
for low temperature and concentrating An ambitious human resource
solar collectors and their components for development programme, across the skill-
medium and high temperature chain, will be established to support an
applications need to be built. An incentive expanding and large-scale solar energy

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 65


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

programme, both for applied and R&D 6. Solar-based space-cooling and


sectors. In Phase I, at least 1000 young refrigeration systems to meet daytime
scientists and engineers would be and summer season peak load. These
incentivized to get trained on different could be installed on selected government
solar energy technologies as a part of the buildings and installations.
Mission’s long-term R&D and HRD plan. The configurations and capacities as
Pilot demonstration projects would be mentioned above are indicative and
closely aligned with the Mission’s R & D would be firmed up after consultations
priorities and designed to promote with various stakeholders. Bidding
technology development and cost process will be adopted to set up solar
reduction. The Mission, therefore, power demonstration plants which would
envisages the setting up of the following help in better price discovery for
demonstration projects in Phase I, in determining tariff for solar power. It will
addition to those already initiated by be ensured that indigenous content is
MNRE and those, which may be set up by maximized. The bid documents will also
corporate investors: include a technology transfer clause. It is
1. 50-100 MW Solar thermal plant with 4-6 expected that these plants will be
th
hours’ storage (which can meet both commissioned in the 12 plan period.
morning and evening peak loads and
double plant load factor up to 40%). 4.4.8 Proposed Roadmap
2. A 100-MW capacity parabolic trough
technology based solar thermal plant. The aspiration is to ensure large-scale
3. A 100-150 MW Solar hybrid plant with deployment of solar generated power for
coal, gas or bio-mass to address variability grid-connected as well as distributed and
and space-constraints. decentralized off-grid provision of
4. 20-50 MW solar plants with/without commercial energy services. The
storage, based on central receiver deployment across the application
technology with molten salt/steam as the segments is envisaged as in Table 4.10
working fluid and other emerging below:
technologies.
5. Grid-connected rooftops PV systems on
selected government buildings and
installations, with net metering.
Table 4.10
S. Application segment Target for Phase Target for Phase Target for Phase
No. I (2010-13) 2 (2013-17) 3 (2017-22)

1. Solar collectors 7 million sq 15 million sq 20 million sq


meters meters meters
2. Off grid solar 200 MW 1000 MW 2000 MW
applications
3. Utility grid power, 1,000-2000 MW 4000-10,000 MW 20000 MW
including roof top

Chapter 4: Page | 66 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

4.4.9. Policy and regulatory framework for fixing feed-in-tariff for purchase of
Solar power taking into account current
The objective of the Mission is to create a cost and technology trends. These will be
policy and regulatory environment which revised on an annual basis. The CERC has
provides a predictable incentive structure also stipulated that Power Purchase
that enables rapid and large-scale capital Agreement that utilities will conclude with
investment in solar energy applications Solar power promoters, should be for a
and encourages technical innovation and period of 25 years.
lowering of costs.
In order to enable the early launch of
Although in the long run, the Mission “Solar India” and encourage rapid scale
would seek to establish a sector-specific up, a scheme is being introduced in
legal and regulatory framework for the cooperation with the Ministry of Power,
development of solar power, in the the NTPC and the Central Electricity
shorter time frame, it would be necessary Authority, which would simplify the off-
to embed the activities of the Mission take of solar power and minimize the
within the existing framework of the financial burden on Government.
Electricity Act 2003. The Electricity Act
already provides a role for renewables but Many investors are willing to set up solar
given the magnitude and importance of based power plants. However, sale of
the activities under the Mission, it would power by the IPPs may be an issue due to
be necessary to make specific the high cost of power and realization of
amendments. The National Tariff Policy tariff for the same from the distribution
2006 mandates the State Electricity companies.
Regulatory Commissions (SERC) to fix a
minimum percentage of energy purchase In order to incentivise setting up of a large
from renewable sources of energy taking number of Solar Power Projects, while
into account availability of such resources minimizing the impact on tariff various
in the region and its impact on retail tariff. alternatives were explored. One of the
National Tariff Policy, 2006 would be options is to bundle solar power along
modified to mandate that the State with power out of the cheaper
electricity regulators fix a percentage for unallocated quota of Central stations and
purchase of solar power. The solar power selling this bundled power to state
purchase obligation for States may start distribution utilities at the CERC regulated
with 0.25% in the phase I and to go up to price. This will bring down the gap
3% by 2022. This could be complemented between average cost of power and sale
with a solar specific Renewable Energy price of power. For the purpose of
Certificate (REC) mechanism to allow bundling, power has to be purchased by
utilities and solar power generation an entity and re-sold to the state power
companies to buy and sell certificates to distribution utilities. Such function can be
meet their solar power purchase done only by a trading company/ Discoms,
obligations. as per the existing statutory provisions.

The Central Electricity Regulatory NTPC has a wholly owned subsidiary


Commission has recently issued guidelines company engaged in the business of
trading of power – NTPC Vidyut Vyapar
Initiatives and Measures for GHG Mitigation Chapter 4: Page | 67
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Nigam Ltd. (NVVN). NVVN will be The Mission will encourage rooftop solar
designated as nodal agency by the PV and other small solar power plants,
Ministry of Power (MoP) for entering into connected to LT/11 KV grid, to replace
a Power Purchase Agreement (PPA) with conventional power and diesel-based
Solar Power Developers. The PPAs shall be generators. Operators of solar PV rooftop
signed with the developers who will be devices will also be eligible to receive the
setting up Solar Projects within next three feed-in tariff fixed by the CERC, both on
years (i.e. upto March 2013) and are the solar power consumed by the
connected to the grid at 33 KV level and operator and the solar power fed into the
above. The PPAs will be valid for a period grid. Utilities will debit/credit the operator
of 25 years. For each MW of solar power for the net saving on conventional power
installed capacity for which PPA is signed consumed and the solar power fed into
by NVVN, MOP shall allocate to NVVN an the grid, as applicable. A Generation
equivalent amount of MW capacity from Based Incentive will be payable to the
the unallocated quota of NTPC stations. utility to cover the difference between the
solar tariff determined by CERC, less the
NVVN will bundle this power and sell this base price of Rs. 5.50/kWh with 3% p.a.
bundled power at a rate fixed as per CERC escalation. The metering and billing
regulations. In case of significant price arrangements between the utility and the
movement in the market rate, the rooftop PV operator will be as per
Government will review the situation. guidelines/regulations of the appropriate
When NVVN supplies the bundled power commission.
to distribution utilities, those distribution
utilities will be entitled to use part of the State Governments would also be
bundled power to meet their RPO, as encouraged to promote and establish
determined by the regulatory authorities. solar generation Parks with dedicated
The CERC may issue appropriate infrastructure for setting up utility scale
guidelines in this regard. At the end of the plants to ensure ease of capacity creation.
first phase, well-performing utilities with
proven financial credentials and FISCAL INCENTIVES
demonstrated willingness to absorb solar It is also recommended that custom
power shall be included in the Scheme, in duties and excise duties concessions/
case it is decided to extend it into Phase II. exemptions be made available on specific
capital equipment, critical materials,
The requirement of phased indigenization components and project imports.
would be specified while seeking
development of solar power projects 4.4.9 Solar Manufacturing in India
under this scheme. The size of each One of the Mission objectives is to take a
project would be determined so as to global leadership role in solar
make phased indigenization feasible. The manufacturing (across the value chain) of
tariff and tax regime for key components leading edge solar technologies and
and segments would be suitably fine target a 4-5 GW equivalent of installed
tuned so as to promote the process of capacity by 2020, including setting up of
indigenization. dedicated manufacturing capacities for
poly silicon material to annually make

Chapter 4: Page | 68 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

about 2 GW capacity of solar cells. India (both crystalline and thin film) and
already has PV module manufacturing poly-silicon manufacturing among
capacity of about 700 MW, which is others. The combined capacity
expected to increase in the next few projected by these 15 companies
years. The present indigenous capacity to could result in the production of 8-10
manufacture silicon material is very low; GW solar power by the year 2022
however, some plants are likely to be set which would be sufficient for
up soon in public and private sector. meeting the Mission targets even
Currently, there is no indigenous after accounting for exports.
capacity/capability for solar thermal  It is also recommended that solar
power projects; therefore new facilities components be covered under the
will be required to manufacture Bureau of Energy Efficiency’s star
concentrator collectors, receivers and rating programme to ensure high
other components to meet the demand standards.
for solar thermal power plants.
Similar incentives will be required for
To achieve the installed capacity target, manufacture of CSP systems and their
the Mission recommends the following: components. A Committee may be set up
to formulate a policy for promotion of
• Local demand creation: The 20 GW plan solar thermal manufacture in the country.
supported with right level of incentives
for solar generation coupled with large • Ease of doing business: In consultation
government pilot/demonstration with States, create a single window
programs will make the Indian market clearance mechanism for all related
attractive for solar manufacturers permissions.
• Infrastructure & ecosystem enablers:
• Financing & Incentives: SEZ like Create 2-3 large solar manufacturing tech
incentives to be provided to the parks consisting of manufacturing units
manufacturing parks which may include: (across the solar value chain), housing,
 Zero import duty on capital offices, and research institutes. These will
equipment, raw materials and excise have 24x7 power and water supply and
duty exemption will likely need to be located near large
 Low interest rate loans, priority urban centres with good linkages to ports
sector lending and airports to ensure rapid access to
 Incentives under Special Incentive imported raw materials and high quality
Package (SIPs) policy to set up engineering talent.
integrated manufacturing plants; (i) 4.4.11 Research and Development
from poly silicon material to solar This Mission will launch a major R&D
modules; and (ii) thin film based programme in Solar Energy, which will
module manufacturing plants. . focus on improving efficiency in existing
Under the SIP scheme of the applications, reducing costs of Balance of
Department of Information Systems, testing hybrid co-generation and
Technology, there are 15 applications addressing constraints of variability,
in the domain of solar photovoltaic, space-intensity and lack of convenient and
which includes cell manufacturing, cost-effective storage.

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 69


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

for the Solar industry. It is envisaged that


The R&D strategy would comprise dealing the Solar Energy Centre of the MNRE will
with five categories viz. i) Basic research become part of the National Centre of
having long term perspective for the Excellence.
development of innovative and new
materials, processes and applications, ii) - The Research Council, in coordination
Applied research aimed at improvement with the National Centre of Excellence,
of the existing processes, materials and inventorize existing institutional
the technology for enhanced capabilities for Solar R&D and encourage
performance, durability and cost the setting up of a network of Centres of
competitiveness of the systems/ devices, Excellence, each focusing on an R&D area
iii) Technology validation and of its proven competence and capability.
demonstration projects aimed at field These Centres may be located in research
evaluation of different configurations institutes, academic institutions or even
including hybrids with conventional private sector companies. They will be
power systems for obtaining feedback on encouraged to bid for various
the performance, operability and costs, iv) components of the Solar Technology
development of R&D infrastructure in PPP Development Plan, and may do so
mode, and v) support for incubation and adopting a consortium approach,
start ups. collaborating with other institutions,
including foreign collaboration, with
To support the R&D Strategy, the Mission proven capabilities.
may include the following:
- The NCE will provide a national platform
- Setting up a high level Research Council for networking among different centers
comprising eminent scientists, technical of excellence and research institutions,
experts and representatives from including foreign R&D institutions and
academic and research institutions, high-tech companies.
industry, Government and Civil Society to
guide the overall technology development - The NCE will serve as the funding agency
strategy. The Council may invite eminent to support performance-linked solar R&D
international experts in the field to programmes. This will include funding, or
support its work. The Council will review co-funding of pilot demonstration
and update the technology roadmap to projects in areas relevant to Mission
achieve more rapid technological objectives. Funding will need to be
innovation and cost reduction. adequate, predictable and should typically
cover a time frame extending from 5-10
- A National Centre of Excellence (NCE) years.
shall be established to implement the
technology development plan formulated - The NCE will be the main interface with
by the Research Council and serve as its international research institutions,
Secretariat. It will coordinate the work of research groups from foreign countries,
various R&D centres, validate research high-tech start-up companies and
outcomes and serve as an apex centre for multilateral programmes (such as those
testing and certification and for which may emerge from current
developing standards and specifications negotiations under the UNFCCC). It will

Chapter 4: Page | 70 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

encourage joint projects between entrepreneurs and innovators for R&D


international partners and Indian centres and pilot of new solar related
of excellence, with sharing of IPR, as also technologies and for creating new and
encourage the setting up of R&D bases in unique business models which have a
India by advanced high-tech companies potential of increasing the deployment of
from abroad. solar related technologies in India – for all
segments including consumer, SME and
- The NCE will coordinate with the IMD, commercial usage. The initiative shall be
ISRO and other concerned agencies, the structured ideally in a private-public
detailed mapping of ground insulation, partnership model, to be able to provide
particularly in high potential solar regions risky capital to the aspiring entrepreneurs.
of the country. Accurate and reliable data It would also attract contributions from
is a critical requirement for all solar private stakeholders, amounting to, at
applications, in particular, concentrated least 10% of that of the Government. The
solar power (CSP). returns generated on the Government
- In drawing up the Solar Technology support to the Fund shall be ploughed
Development Plan, the Research Council back for further promoting incubation
will review ongoing and proposed R&D activities in this space.
initiatives of MNRE, the Department of The Mission would also explore the
Science and Technology, the Ministry of possibility of collaborating with CSIR to
Earth Sciences and other agencies and launch an Open Source Solar
institutions and incorporate them, as Development initiative on similar lines as
appropriate, in its Plan. the Open Source Drug Discovery platform
In order to provide support for incubation of CSIR
and start ups, the Mission could tie up 4.4.12 Institutional Arrangements for
with institutions like Centre for implementing the Mission
Innovation, Incubation and
Entrepreneurship (CIIE) based in IIM This Mission will be implemented by an
Ahmedabad to incubate solar energy autonomous Solar Energy Authority and
start-ups and SMEs in India through or an autonomous and enabled Solar
mentoring, networking and financial Mission, embedded within the existing
support. A fund could be established to structure of the Ministry of New and
aim at supporting at least 50 start-ups Renewable Energy. The Authority/Mission
developing and deploying solar related secretariat will be responsible for
technologies across India over the next 5 monitoring technology developments,
years and would be managed by a review and adjust incentives, manage
professional entity. The Fund shall be funding requirements and execute pilot
structured as a Venture Fund and would projects. The Mission will report to the
be operated as a hub and spoke model Prime Minister’s Council on Climate
with the professional entity coordinating Change on the status of its programme.
the fund activities and also identifying like
minded institutions for administering the The broad contours of an autonomous
fund. The Fund would provide financial and enabled Mission would comprise of:
(equity/debt) support to start-ups,

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 71


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

i) A Mission Steering Group, chaired would have Joint secretary/


by the Minister for New and Scientist G level officers including
Renewable Energy and composed other scientists, experts and
of representatives from all relevant consultants.
Ministries and other stakeholders,
will be set up to over see the over 4.4.13 Sites and Land for Solar Installation
all implementation of the National Identifying suitable site and adequate land
Solar Mission. The Mission Steering for setting up of a particular type of Solar
Group will be fully empowered to installation is our foremost requirement.
approve various schemes/ projects/ Solar energy can be utilised in the
policies and the related financial following ways:
norms for all schemes covered
under the National Solar Mission i) Solar thermal energy being used as
(NSM). The Mission Steering group process heat for domestic,
will also authorize any commercial and industrial
modifications/deviations in the applications
norms on ongoing schemes. ii) Solar power being used in the DDG
ii) A Mission Executive Committee, mode
chaired by Secretary, Ministry of iii) Solar power being fed into the
New and Renewable Energy, will Utilities’ grid system
periodically review the progress of In case of Alternative (i.) and (ii) the site
implementation of the projects for setting up the solar installation would
approved by the Mission Steering most likely be the roof-top or land within
Group. the premises of the user/group of users.
iii) An empowered Solar Research However in case of Alternative (iii) it
Council headed by an eminent would be preferable to have the site of
scientist will advise the Mission on installation in the vicinity of the grid
all R&D, technology and capacity system since connectivity of the power
building related matters. In generated to be injected into the grid
addition, Industry Advisory Council would also be an issue. In case the site is
will advise the Mission on all away from the power station or the
matters relating to industrial substation, additional cable/lines would
development, technology transfer/ have to be laid to inject this power into
absorption/joint ventures, the grid. It is therefore considered that
incentives and investment related solar installations at generation stations
matters. or grid substations are the best option. In
iv) A Mission Director, with the rank of case this is not feasible, alternate barren
an Additional Secretary, would head land shall have to be identified for this
the Mission secretariat and be purpose.
responsible for day to day At present, the Installed Capacity in the
functioning and also achieving the country is about 1, 51, 000 MW. A capacity
goals laid out in a time bound of about 64,000 MW is under execution
manner. The Mission Secretariat for commissioning during 11th Plan and a
Chapter 4: Page | 72 Initiatives and Measures for GHG Mitigation
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

capacity of 1 lakh MW each in the 12th and Education and Training under the
13th Plan. This entire capacity has huge Ministry of Labour has agreed to
potential to accommodate electricity introduce training modules for
generated from solar installations in real course materials for technicians in
time without the use of storage devices. order to create a skilled workforce
which could service and maintain
4.4.14 Human Resource Development solar applications. MNRE has
The rapid and large-scale diffusion of Solar already initiated this activity with
Energy will require a concomitant increase the Ministry of Labour and a short
in technically qualified manpower of term training module is to be
international standard. Some capacity introduced during the current
already exists in the country, though academic session. In addition,
precise numbers need to be established. industry is also working with some
of the ITIs to create a skilled work
However, it is envisaged that at the end of force.
Mission period, Solar industry will employ
at least 100,000 trained and specialized  A Government Fellowship
personnel across the skill spectrum. These programme to train 100 selected
will include engineering management and engineers / technologies and
R&D functions. scientists in Solar Energy in world
class institutions abroad will be
The following steps may be required for taken up. This may need to be
Human Resource Development: sustained at progressively
declining levels for 10 years. This
 IITs and premier Engineering could be covered under the
Colleges will be involved to design ongoing bilateral programmes.
and develop specialized courses in Institution to institution
Solar Energy, with financial arrangements will also be
assistance from Government. developed. Fellowships will be at
These courses will be at B. Tech, M. two levels (i) research and (ii)
Tech and Ph. D level. Some of the higher degree (M. Tech) in solar
IITs, Engineering Colleges and energy. MNRE is already
Universities are teaching solar implementing a fellowship
energy at graduation and post programme in this regard, which
graduation level. Centres for will be expanded to include
Energy studies have been set up by students from a larger number of
some of the IITs and engineering academic institutions. This may be
colleges. These initiatives will be done in consultation with industry
further strengthened. In addition, a to offer employment
countrywide training programme opportunities.
and specialized courses for
technicians will be taken up to Setting up of a National Centre for
meet the requirement of skilled Photovoltaic Research and Education at
manpower for field installations IIT, Mumbai, drawing upon from
and after sales service network. Department of Energy Science and
The Directorate General of
Initiatives and Measures for GHG Mitigation Chapter 4: Page | 73
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Engineering and its Centre for Excellence areas of (i) Feasibility of solar generation
in Nano-Electronics is considered. with respect to space availability, any
constraints foreseen and application areas
4.4.15 Task Force set up by MNRE (ii) Solar technology options and techno-
A Task Force has been set up by MNRE economics (iii) Arrangement for
under the Chairmanship of Chairperson, connectivity and metering of solar plants.
CEA to examine technical issues related
to the feasibility of integrating solar 4.4.16 Fund Requirement
power plants with thermal/ hydro-electric One of the major bottlenecks in the
power plants and connectivity of solar development of Solar Installations is the
rooftops systems with the grid. The Task high Capital cost which results in high
Force comprises of representatives of tariff as compared to power generated
MNRE, MOP, CEA, NTPC, NHPC, BHEL, using Conventional Energy Resources. It
CEL, RRECL, RRUVNL, GSECL, GEDA and has been estimated that the capital cost
KPCL. The objective of the Task Force is to of solar installations is about Rs
prepare implementable project reports 20crs/MW, with Solar thermal being
for setting up solar plants at power plants, marginally lesser i.e. about Rs 18 crs/MW.
one each at coal based, gas based and However it is expected that the cost will
hydro power stations. The project report decline as the technology gets established
shall include complete bill of material, cost and the quantum of orders increase with
estimates, methodology of accounting time. It is expected that the cost which
energy and to establish the commercial would be about Rs 20 crs/MW during the
viability. 11th Plan, will reduce to Rs 16crs/MW
Three Subgroups have been formed under during the 12th Plan and about Rs
the Task Force to look into the specific 12crs/MW during the 13th Plan.

Table 4.11
First Phase Second Phase Third Phase
(2008-13) (2013-17) (2017-22)
Installed Capacity (Solar) in 1000 10000 20,000
MW
Capacity Addition during Plan 1000 9000 10,000
in MW
Funds reqt. per MW (Rs crs) 20 16 12
Funds Requirement (Rs crs) 20,000 1,44,000 1,20,000

As per JNNSM, the fund requirements for The Mission strategy has kept in mind the
the Mission would be met from the two-fold objectives, to scale-up
following sources or combinations: deployment of solar energy and to do this
i) Budgetary support for the activities keeping in mind the financial constraints
under the National Solar Mission and affordability challenge in a country
established under the MNRE; where large numbers of people still have
ii) International Funds under the UNFCCC no access to basic power and are poor
framework, which would enable upscaling and unable to pay for high cost solutions.
of Mission targets. The funding requirements and
Chapter 4: Page | 74 Initiatives and Measures for GHG Mitigation
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

arrangements for Phase II will be analysis of the efficacy of the model


determined after a review of progress adopted for capacity building of utility
achieved at the end of the 11th Plan and an scale solar power.

---+++---

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 75


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Appendix-4.1
(Sheet 1 of 5)
LIST OF THERMAL UNITS PROGRAMMED FOR LIFE EXTENSION WORKS DURING 12TH PLAN

1. STATE SECTOR
Sl. State Name of Utility Name of Station Unit Year of Capacity Make LMZ / Remarks
No. No. Comm. (MW) Boiler TG KWU
Northern Region
th
1 U.P. UPRVUNL Obra 11 1977 200 BHEL BHEL LMZ Slip from 11 Plan
th
2 U.P. UPRVUNL Obra 12 1981 200 BHEL BHEL LMZ Slip from 11 Plan
th
3 U.P. UPRVUNL Obra 12 1982 200 BHEL BHEL LMZ Slip from 11 Plan
th
4 U.P. UPRVUNL Parichha 1 1984 110 BHEL BHEL Slip from 11 Plan
th
5 U.P. UPRVUNL Parichha 2 1985 110 BHEL BHEL Slip from 11 Plan
th
6 U.P. UPRVUNL Panki 3 1976 105 BHEL BHEL Slip from 11 Plan
th
7 U.P. UPRVUNL Panki 4 1977 105 BHEL BHEL Slip from 11 Plan
th
8 U.P. UPRVUNL Anpara”A” 1 1986 210 BHEL BHEL KWU Slip from 11 Plan
th
9 U.P. UPRVUNL Anpara”A” 2 1986 210 BHEL BHEL KWU Slip from 11 Plan
th
10 U.P. UPRVUNL Anpara”A” 3 1988 210 BHEL BHEL KWU Slip from 11 Plan
Sub Total 10 1660
th
11 Punjab PSPCL Ropar 1 1984 210 BHEL BHEL KWU Slip from 11 Plan
th
12 Punjab PSPCL Ropar 2 1985 210 BHEL BHEL KWU Slip from 11 Plan
th
13 Punjab PSPCL Bathinda 4 1979 110 BHEL BHEL Slip from 11 Plan
Sub Total 3 530
14 Haryana HPGCL Panipat 3 1985 110 BHEL BHEL Being taken up under W.Bank
15 Haryana HPGCL Panipat 4 1985 110 BHEL BHEL EE R&M programme
Sub Total 2 220

Boiler TG
16 Rajasthan RRVUNL Kota 1 1983 110 BHEL BHEL
17 Rajasthan RRVUNL Kota 2 1983 110 BHEL BHEL
Sub Total 2 220
Sub Total Northern Region 17 2630
Western Region
18 Gujarat GSECL Ukai 3 1979 200 BHEL BHEL LMZ

Chapter 4: Page | 76 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Appendix-4.1
(Sheet 2 of 5 )

19 Gujarat GSECL Ukai 4 1979 200 BHEL BHEL LMZ


20 Gujarat GSECL Wanakbori 1 1982 210 BHEL BHEL KWU
21 Gujarat GSECL Wanakbori 2 1983 210 BHEL BHEL KWU
Sub Total 4 820
22 Maharashtra MAHAGENCO Nashik 3 1979 210 BHEL BHEL LMZ Taken up under KfW funded
EER&M programme. Feasibility
study report / DPR under
preparation
23 Maharashtra MAHAGENCO Nashik 4 1980 210 BHEL BHEL LMZ
24 Maharashtra MAHAGENCO Koradi 5 1978 210 BHEL BHEL LMZ
25 Maharashtra MAHAGENCO Koradi 6 1982 200 BHEL BHEL LMZ Being taken up under W.Bank EE
R&M programme.
26 Maharashtra MAHAGENCO Bhusawal 2 1979 210 BHEL BHEL LMZ
27 Maharashtra MAHAGENCO Bhusawal 3 1982 210 BHEL BHEL LMZ
28 Maharashtra MAHAGENCO Chandrapur 1 1983 210 BHEL BHEL LMZ
29 Maharashtra MAHAGENCO Chandrapur 2 1984 210 BHEL BHEL LMZ
30 Maharashtra MAHAGENCO Parli 3 1980 210 BHEL BHEL LMZ
Sub Total 9 1880
31 Chattisgarh CSEB Korba (West) 1 1983 210 BHEL BHEL KWU
32 Chattisgarh CSEB Korba (West) 2 1984 210 BHEL BHEL KWU
Sub Total 2 420
33 Madhya Pradesh MPPGCL Satpura 6 1979 200 BHEL BHEL LMZ
34 Madhya Pradesh MPPGCL Satpura 7 1979 210 BHEL BHEL LMZ
Sub Total 2 410
Sub Total Western Region 17 3530
Southern Region
35 Tamil Nadu TNEB Tuticorin 1 1979 210 BHEL BHEL LMZ
36 Tamil Nadu TNEB Tuticorin 2 1980 210 BHEL BHEL LMZ
Sub Total 2 420
37 Andhra Pradesh APGENCO Dr. N.T. TPS (Vijaywada) 1 1979 210 BHEL BHEL LMZ
38 Andhra Pradesh APGENCO Dr. N.T. TPS (Vijaywada) 2 1980 210 BHEL BHEL LMZ
Sub Total 2 420

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 77


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Appendix-4.1
(Sheet 3 of 5 )

39 Karnataka KPCL Raichur 1 1985 210 BHEL BHEL KWU


40 Karnataka KPCL Raichur 2 1986 210 BHEL BHEL KWU
Sub Total 2 420
Sub Total Southern Region 6 1260
Eastern Region
41 West Bengal WBPDCL Kolaghat 1 1990 210 AVB BHEL LMZ
42 West Bengal WBPDCL Kolaghat 2 1985 210 AVB BHEL LMZ
43 West Bengal WBPDCL Kolaghat 3 1984 210 AVB BHEL LMZ Taken up under KfW funded
EER&M programme.
th
44 West Bengal WBPDCL Bandel 5 1982 210 AVB BHEL LMZ Slip from 11 Plan
Sub Total 4 840
th
45 Bihar BSEB Barauni 6 1983 110 BHEL BHEL Slip from 11 Plan
th
46 Bihar KBUNL Muzaffarpur 2 1986 110 BHEL BHEL Slip from 11 Plan
Sub Total 2 220
Sub Total Eastern Region 6 1060
SUB TOTAL STATE SECTOR 46 8480
2. CENTRAL SECTOR
Sl. Name of Station Unit Year of Capacity Make LMZ / KWU Remarks
No. Name of Utility No. Comm. (MW) Boiler TG
1 NLC Neyveli M/C 1 1988 210 TE FT KWU
2 NLC Neyveli M/C 2 1987 210 TE FT KWU
3 NLC Neyveli M/C 3 1986 210 TE FT KWU
Sub Total 3 630
4 DVC Bokaro 'B' 1 1986 210 ABL BHEL LMZ Taken up under KfW funded
5 DVC Bokaro 'B' 2 1990 210 ABL BHEL LMZ EER&M programme.
6 DVC Bokaro 'B' 3 1993 210 ABL BHEL LMZ Feasibility study report / DPR
under preparation
7 DVC Durgapur 4 1982 210 BHEL BHEL LMZ
Sub Total 4 840
th
8 NTPC Badarpur 4 1978 210 BHEL BHEL LMZ Slip from 11 Plan
th
9 NTPC Badarpur 5 1981 210 BHEL BHEL LMZ Slip from 11 Plan

Chapter 4: Page | 78 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Appendix-4.1
(Sheet 4 of 5 )
th
10 NTPC Singrauli STPS 1 1982 200 BHEL BHEL LMZ Slip from 11 Plan
th
11 NTPC Singrauli STPS 2 1982 200 BHEL BHEL LMZ Slip from 11 Plan
12 NTPC Singrauli STPS 3 1983 200 BHEL BHEL LMZ
13 NTPC Singrauli STPS 4 1983 200 BHEL BHEL LMZ
14 NTPC Singrauli STPS 5 1984 200 BHEL BHEL LMZ
15 NTPC Singrauli STPS 6 1986 500 BHEL BHEL KWU
16 NTPC Singrauli STPS 7 1987 500 BHEL BHEL KWU
th
17 NTPC Korba STPS 1 1983 200 BHEL BHEL KWU Slip from 11 Plan
18 NTPC Korba STPS 2 1983 200 BHEL BHEL KWU
19 NTPC Korba STPS 3 1984 200 BHEL BHEL KWU
Sl. Name of Station Unit Year of Capacity Make LMZ / KWU Remarks
No. Name of Utility No. Comm. (MW) Boiler TG
20 NTPC Korba STPS 4 1987 500 BHEL BHEL KWU
21 NTPC Korba STPS 5 1988 500 BHEL BHEL KWU
22 NTPC Korba STPS 6 1989 500 BHEL BHEL KWU
th
23 NTPC Ramagundam STPS 1 1984 200 Ansaldo Ansaldo KWU Slip from 11 Plan
24 NTPC Ramagundam STPS 2 1984 200 Ansaldo Ansaldo KWU
25 NTPC Ramagundam STPS 3 1984 200 Ansaldo Ansaldo KWU
26 NTPC Ramagundam STPS 4 1988 500 BHEL BHEL KWU
27 NTPC Ramagundam STPS 5 1989 500 BHEL BHEL KWU
28 NTPC Ramagundam STPS 6 1989 500 BHEL BHEL KWU
29 NTPC Farakka Stage-I 1 1986 200 BHEL BHEL KWU
30 NTPC Farakka Stage-I 2 1986 200 BHEL BHEL KWU
31 NTPC Farakka Stage-I 3 1987 200 BHEL BHEL KWU
32 NTPC Vindhyachal 1 1987 210 USSR USSR LMZ
33 NTPC Vindhyachal 2 1988 210 USSR USSR LMZ
34 NTPC Vindhyachal 4 1990 210 USSR USSR LMZ
35 NTPC Vindhyachal 5 1990 210 USSR USSR LMZ
36 NTPC Rihand 1 1988 500 ICL (UK) GEC(UK) KWU
37 NTPC Rihand 2 1989 500 ICL (UK) GEC(UK) KWU

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 79


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Appendix-4.1
(Sheet 5 of 5 )

Sl. Name of Utility Name of Station Unit No. Year of Capacity Make LMZ / Remarks
No. Comm. (MW) Boiler TG KWU
th
38 NTPC Dadri GT GT-1 1992 131 SIEMENS Slip from 11 Plan
th
39 NTPC Dadri GT GT-2 1992 131 SIEMENS Slip from 11 Plan
th
40 NTPC Dadri GT GT-3 1992 131 SIEMENS Slip from 11 Plan
41 NTPC Dadri GT GT-4 1992 131 SIEMENS
th
42 NTPC Auraiya GT GT-1 1989 111.19 MHI, Japan Slip from 11 Plan
th
43 NTPC Auraiya GT GT-2 1989 111.19 MHI, Japan Slip from 11 Plan
th
44 NTPC Auraiya GT GT-3 1989 111.19 MHI, Japan Slip from 11 Plan
45 NTPC Auraiya GT GT-4 1989 111.19 MHI, Japan
th
46 NTPC Kawas GT GT-1 1992 106 GE Slip from 11 Plan
th
47 NTPC Kawas GT GT-2 1992 106 GE Slip from 11 Plan
th
48 NTPC Kawas GT GT-3 1992 106 GE Slip from 11 Plan
49 NTPC Kawas GT GT-4 1992 106 GE
th
50 NTPC Gandhar GT GT-1 1994 131 ABB Slip from 11 Plan
th
51 NTPC Gandhar GT GT-2 1994 131 ABB Slip from 11 Plan
52 NTPC Gandhar GT GT-3 1994 131 ABB
53 NTPC Faridabad CCPS GT-1 1999 143 Siemens
54 NTPC Faridabad CCPS GT-2 1999 143 BHEL
55 NTPC Rajiv Gandhi CCPS GT-1 1998 115 GE
56 NTPC Rajiv Gandhi CCPS GT-2 1999 115 BHEL
57 NTPC Anta GTPS ST-1 1990 149 ABB
58 NTPC Auraiya CCPS ST-1 1989 109 MHI, Japan
59 NTPC Auraiya CCPS ST-2 1990 109 MHI, Japan
Sub Total 52 11728.76
SUB TOTAL CENTRAL SECTOR 59 13198.76
TOTAL OF 12TH PLAN (LE) :
NUMBER OF UNITS : 105
CAPACITY (MW) : 21679

Chapter 4: Page | 80 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Appendix-4.2
(Sheet 1of 2 )
LIST OF THERMAL UNITS PROGRAMMED FOR R&M WORKS DURING 12TH PLAN.
2. STATE SECTOR
Sl. No. State Name of Utility Name of Station Unit No. Year of Capacity Make
Comm. (MW) Boiler TG
Northern Region
1 U.P. UPRVUNL Anpara ‘B’ 4* 1993 500 BHEL BHEL
2 U.P. UPRVUNL Obra 5* 1994 500 BHEL BHEL
3 U.P. UPRVUNL Obra 7* 1974 100 BHEL BHEL
4 U.P. UPRVUNL Obra 8* 1975 100 BHEL BHEL
Sub Total 4 1200
5 Punjab PSEB Ropar 5 1992 210 BHEL BHEL
6 Punjab PSEB Ropar 6 1993 210 BHEL BHEL
Sub total 2 420
7 Haryana HPGCL Panipat 6 2001 210 BHEL BHEL
Total Northern Region 7 1830
Eastern Region
8 Jharkhand JSEB Patratu 9* 1984 110 BHEL BHEL
9 Jharkhand JSEB Patratu 10* 1986 110 BHEL BHEL
Sub-Total 2 220
10 West Bengal DPL Durgapur 6* 1985 110 AVB BHEL
Total Eaatern Region 3 330
TOTAL STATE SECTOR 10 2160
2. CENTRAL SECTOR
1 NTPC Unchahar 3 1999 210 BHEL BHEL
2 NTPC Unchahar 4 1999 210 BHEL BHEL
3 NTPC Vindhyachal 7 1999 210 BHEL BHEL
4 NTPC Vindhyachal 8 2000 210 BHEL BHEL
5 NTPC Simhadri 1 2002 500 BHEL BHEL
6 NTPC Simhadri 2 2002 500 BHEL BHEL
7 NTPC Kahalgaon 4 1996 210 BHEL BHEL

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 81


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Appendix-4.2
(Sheet 2 of 2 )

8 NTPC Talcher STPS 1 1995 500 BHEL BHEL


9 NTPC Talcher STPS 2 1996 500 BHEL BHEL
10 NTPC Talcher STPS 3 2003 500 BHEL BHEL
11 NTPC Talcher STPS 4 2003 500 BHEL BHEL
Sub Total 11 4050

Sl. No. Name of Utility Name of Station Unit No. Year of Capacity Make
Comm. (MW)
12 NEEPCO Kathalguri CCGT GT-1 1995 33.50 Mitsubishi, Japan
13 NEEPCO Kathalguri CCGT GT-2 1995 33.50 Mitsubishi, Japan
14 NEEPCO Kathalguri CCGT GT-3 1995 33.50 Mitsubishi, Japan
15 NEEPCO Kathalguri CCGT GT-4 1995 33.50 Mitsubishi, Japan
16 NEEPCO Kathalguri CCGT GT-5 1996 33.50 Mitsubishi, Japan
17 NEEPCO Kathalguri CCGT GT-6 1996 33.50 Mitsubishi, Japan
18 NEEPCO Kathalguri CCGT ST-1 1998 30.00 BHEL
19 NEEPCO Kathalguri CCGT ST-2 1998 30.00 BHEL
20 NEEPCO Kathalguri CCGT ST-3 1998 30.00 BHEL
Sub Total
9 291.00
TOTAL CENTRAL SECTOR 20 4341.00
th
Notre:* Slip from 11 Plan
TOTAL OF 12TH PLAN (R&M) :
NUMBER OF UNITS : 30
CAPACITY (MW) : 6501
Total of 12th Plan (LE+R&M) 135
Capacity (MW) 28180

Chapter 4: Page | 82 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Abbreviations: R&M – Renovation & Modernisation;. U – Uprating; LE – Life Extension; Res – Restoration; MW – Mega Watt; CS-Central Sector: SS- State Sector
$ - Installed Capacity for Dehar (Ph.b) at Sl. No.2 & Nagjhari (U-4 to 6) at Sl. No.21 are not included in the total as the same has already been accounted for at Sl. Nos. 1 and 6 respectively.

Abbreviations: R&M – Renovation & Modernisation;. U – Uprating; LE – Life Extension; Res – Restoration; MW – Mega Watt; CS-Central Sector: SS- State Sector $ - Installed Capacity
for Dehar (Ph.A) at Sl. No. 10, Nagjhari (U-4 to 6) at Sl. No. 22, Chilla at S. No. 4 and Khodri (Ph.B) at Sl. No. 56 are not included in the total as the same has already been accounted for at
Sl. Nos. 1, 21, 37 and 3 respectively.
Abbreviations: R&M – Renovation & Modernisation;
RM&U – Renovation, Modernisation & Uprating,
RM&LE – Renovation, Modernisation & Life Extension
RMU&LE – Renovation, Modernisation, Uprating & Life Extension;
R&M+Res.-Renovation & Modernisation + Restoration;
RM&LE+Res.- Renovation, Modernisation & Life Extension + Restoration;
RM&U+Res. – Renovation, Modernisation & Uprating + Restoration.
MW – Mega Watt; Res – Restoration; U – Uprating; LE – Life Extension

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 83


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Appendix 4.3
(Page 1 of 5)
STATE WISE LIST OF HYDRO R&M, LIFE EXTENSION & UPRATING SCHEMES PROGRAMMED FOR
COMPLETION DURING THE 12TH PLAN
As on 31.03.2011
S. Project, CS/ SS Installed Estimate Actual Benefits Category Year of
No Agency Capacity d Cost Expenditu (MW) Completi
(MW) on
re
(Rs. in Crs.)
Ongoing Schemes – Under implementation
Himachal Pradesh
1 Bhakra LB, BBMB CS 5x108 489.77 170.92 540.00 RMU&LE 2012-13
(as on (LE) +
31.12.10) 90.00
(U)
Jammu & Kashmir
2 Chenani, J&KPDC SS 5x4.66 39.14 3.49 23.30 (LE) RM&LE 2012-13
(as on
31.12.10)
3 Sumbal Sindh, SS 2x11.3 25.60 13.10 - R&M 2012-13
J&KPDC (as on
31.12.10)
4 Lower Jhelum, SS 3x35 101.30 68.45 15.00 R&M+ 2012-13
J&KPDC (as on (Res.) Res.
31.12.10)
Uttar Pradesh
5 Obra, UPJVNL SS 3x33 31.70 11.454 99.00 (LE) RM&LE 2013-14
(as on
31.12.10)
6 Rihand, UPJVNL SS 6x50 132.20 46.325 300.00 RM&LE 2012-13
(as on (LE)
31.12.10)
Uttarakhand
7 Pathri, UJVNL SS 3x6.8 71.59 - 20.40 (LE) RM&LE 2013-14
Andhra Pradesh
8 Srisailam RB, SS 7x110 16.70 13.36 - R&M 2012-13
APGENCO (as on
28.02.10 )
Kerala
9 Sabirigiri, KSEB SS 6x50 104.36 96.95 300.00 RMU&LE 2012-13
(as on (LE) +
31.12.10) 35.00(U)
10 Idamalayar, KSEB SS 2x37.5 11.70 5.45 - R&M 2012-13
(as on
31.12.10)
Tamil Nadu

Chapter 4: Page | 84 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Appendix 4.3
(Page 2 of 5)

11 Periyar,TNEB SS 4x35 161.18 82.43 140.00 RMU&LE 2013-14


(as on (LE) +
28.02.11) 28.00(U)
West Bengal
12 Maithon, CS 2x20 49.05 3.76 40.00 (LE) RM&LE 2013-14
U-1&3, DVC (as on
31.03.10)
S. Project, CS/ SS Installed Estimate Actual Benefits Category Year of
No Agency Capacity d Cost Expenditu (MW) Completi
(MW) on
re
13 SS 3x9 88.62 (Rs. in Crs.) RM&LE 2012-13
Jaldhaka St.I, 59.80 27.00(LE)
WBSEB (as on
31.12.10)
14 Koyna St.III, SS 4x80 16.65 5.79 320 (LE) RM&LE 2012-13
MSPGCL (as on
30.6.10)

Orissa
15 Rengali SS 1x50 47.50 3.40 50(LE) RM&LE 2012-13
OHPC (as on
31.12.10)
16 Hirakud-II, OHPC SS 3x24 125.52 58.73 72.00 (LE) RM&LE 2013-14
(as on
31.03.10)
Assam
17 Kopili, NEEPCO CS 2x50 + 66.42 0.218 - R&M & 2013-14
2x50 (as on Refurbis
30.09.10) hment of
Units 1 &
2
18 Khandong, CS 2x25 20.57 0.213 50.00 RM&LE 2013-14
NEEPCO (as on (LE)
30.09.10)
Meghalaya
19 UmiumSt.II , SS 2x9 90.46 19.00 2(U)+ RM&LE 2012-13
MeSEB (as on 18.00 (LE)
31.12.10)
Sub Total(A) 3172.30 1690.03 662.84 2169.70
Ongoing Schemes – Under Tendering
Jammu & Kashmir
20 Ganderbal, SS 2x3+ 39.30 6.24 15.00 (LE) RM&LE XII Plan
J&KPDC 2x4.5 (as on
31.12.10)
Uttar Pradesh

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 85


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Appendix 4.3
(Page 3 of 5)

21 Matatila, UPJVNL SS 3x10.2 10.29 1.00 30.6 (LE) RM&LE XII Plan
(as on
31.12.10)
Uttarakhand
22 Khatima, UJVNL SS 3x13.8 140.24 - 41.40 (LE) RM&LE XII Plan
23 Chilla(Ph-B), SS 4x36 472.00 - 22(U) + XII Plan
UJVNL 144(LE) RMU&L
E
24 Dhakrani, UJVNL SS 3x11.25 70.00 - 33.75 (LE) RM&LE XII Plan

Chapter 4: Page | 86 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Appendix 4.3
(Page 4 of 5)
S. Project, CS/ SS Installed Estimate Actual Benefits Category Year of
No Agency Capacity d Cost Expendi (MW) Completion
(MW)
ture
(Rs. in Crs.)
25 Dhalipur, UJVNL SS 3x17 101.25 - 51.00 (LE) RM&LE XII Plan

26 Tiloth, UJVNL SS 3x30 163.75 - 90 (LE) RM&LE XII Plan

27 Kulhal, UJVNL SS 3x10 38.75 - 30(LE) RM&LE XII Plan

28 Chibro, UJVNL SS 4x60 201.25 - 240(LE) RM&LE XII Plan

29 Khodri(Ph-B), SS 4x30 120.00 - 120(LE) RM&LE XII Plan


UJVNL
Tamil Nadu
30 Sholayar-I, TNEB SS 2x35 40.681 - 14.00(U) + RMU&LE XII Plan
70.00(LE)
Kerala
31 Poringal- SS 4x8 9.55 2.34 (as 32.00 (LE) RM&LE XII Plan
kuthu,KSEB on
31.12.10)
Jharkhand
32 Panchet, CS 1x40 58.22 1.99 40.00 RM&LE XII Plan
U-1, DVC (as on (LE)
31.03.10)
Orissa
33 Hirakud-I U5&6, SS 2x37.5 92.37 0.25 75.00 (LE) RM&LE XII Plan
OHPC (as on
31.12.10)
34 Balimela, OHPC SS 6x60 160 - 360(LE) RM&LE XII Plan

Sub Total(B) 1372.75 1717.65 11.82 1408.75


Ongoing Schemes – Under DPR Preparation/Finalisation
Himachal Pradesh
35 Giri, HPSEB SS 2x30 48.48 - 60.00 (LE) RM&LE XII Plan
Andhra Pradesh
36 Machkund , SS 3x17 124.45 - 15.25 (U) RMU&LE XII Plan
APGENCO (St.I) +
& 3x21.25 114.75
(St.II) (LE)
Kerala
37 Sholayar, KSEB SS 3x18 54.00 0.044 54.00 (LE) RM&LE XII Plan
(as on
31.12.10)
38 Kuttiadi, KSEB SS 3x25 25.00 - 75.00 (LE) RM&LE XII Plan

Initiatives and Measures for GHG Mitigation Chapter 4: Page | 87


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Appendix 4.3
(Page 5 of 5)
S. Project, CS/ SS Installed Estimate Actual Benefits Category Year of
No Agency Capacity d Cost Expenditu (MW) Completi
(MW) on
re
(Rs. in Crs.)
Meghalaya
39 Kyrdemkulai, SS 2x30 168.00 - 60.00 (LE) RMU & LE XII Plan
MeSEB 6.00 (U)
Sub Total(C) 363.75 419.93 0.044 385.00
Ongoing Schemes – Under RLA Studies
Andhra Pradesh
40 Upper Sileru, SS 4x60 10.00 - - R&M XII Plan
APGENCO
Tamil Nadu
41 Kodayar Ph.I, SS 1x60 30.00 - 60.00 (LE) RM&LE XII Plan
TNEB
42 Kodayar SS 1x40 19.94 - 40.0(LE) RM&LE XII Plan
PH-II, TNEB
Sub Total(D) 340.00 59.94 - 100.00
Total 5248.80 3887.55 674.70 4063.45
(A+B+C+D) [212.25(U)
+
3836.20(LE)
+ 15.0
(Res.)]

Abbreviations:
R&M – Renovation & Modernisation;
RM&U – Renovation, Modernisation & Uprating,
RM&LE – Renovation, Modernisation & Life Extension
RMU&LE – Renovation, Modernisation, Uprating & Life Extension;
R&M+Res.-Renovation & Modernisation + Restoration;
RM&LE+Res.- Renovation, Modernisation & Life Extension + Restoration;
RM&U+Res. – Renovation, Modernisation & Uprating + Restoration.
MW – Mega Watt; Res – Restoration; U – Uprating; LE – Life Extension

Chapter 4: Page | 88 Initiatives and Measures for GHG Mitigation


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 5

GENERATION PLANNING

5.0 INTRODUCTION consumption peaks during the day, and


drops significantly at night and on
Economic development in the country is weekends. This demand pattern does not
being achieved by meeting the increasing very well suit plants that are built to run
demand for power by setting up on base load. Therefore, this approach of
generation capacity addition. The demand focussing mainly on adding coal-hydro-
for power is expected to grow but the nuclear base load generating capacity,
available fuel resources for generation, to while necessary, may just not be sufficient
meet this demand, are limited. Also, a during 12th Plan and beyond. Thus,
growth in generation capacity can not be additional parameters which need
viewed in isolation and has to be achieved attention and planning are reliability and
in an environment which is clean and flexibility of the power system by creating
green and sustainable in nature. peaking capacity and reserve margin in
Therefore, Low Carbon Growth Strategy is our system.
the order of the day. This has to be
planned very meticulously as its This Chapter highlights the Principles of
development may not be very easily Generation Planning adopted in the Plan
achievable. to assess the requirement of capacity
addition in the 12th and 13th Plan periods.
Till the 11th Plan period, the main focus of These principles are in consonance with
the planning process was to add large the principles of Low Carbon Strategy and
generation capacities, aiming to bridge the power system planned is able to meet
the chronic gap between supply and the additional parameters of reliability and
demand. When most parts of rural India flexibility also, in addition to capacity
did not have access to electricity, and requirement, by specifically planning for
when urban India faced power cuts peaking power and spinning reserves.
regularly, the over-riding consideration
was to ensure ‘adequacy of power” by 5.1 OPTIONS FOR POWER GENERATION IN
adding base-load capacities. During the INDIA
11th Plan, a capacity addition of about
52,000 MW is likely to be achieved against The resources for power generation in our
Mid-Term target of 62,374 MW. country are limited and since Low Carbon
Growth Strategy has to be followed, all
The situation in future may be different generation options need to be harnessed
since Urban India accounts for over half in the most optimum manner. Various
the country’s GDP, and its electricity Technology options also need to be

Generation Planning Chapter 5: Page | 89


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

explored to facilitate minimum carbon  To fulfil desired operational


emission feasible. Fuel Options for Power characteristics of the system (to
Generation are: meet varying demand) such as
Reliability and flexibility
 Conventional Sources – Hydro,  Most efficient use of resource i.e
Nuclear, Natural gas, Coal and lignite. adoption of latest technological
 Non Conventional Sources- Solar, advancements in coal based
Wind, Biomass, tidal, Geothermal, generation; Combined Cooling,
Waste to energy, Hydrogen/ fuel cells, Heating and Power (CCHP) and
etc. Distributed Generation.
Emphasis on adoption of Non
conventional sources of energy which are The above aspects have been considered
renewable in nature, along with hydro and within realms of feasibility, while drawing
nuclear resources, is one of the most up this National Electricity Plan along with
important and far reaching Initiatives the economics and the status of the
towards achieving a low carbon growth various projects.
strategy. However Non conventional
sources are generally non-despatchable in 5.2.1 Sustainable Development
nature as well as provide more costly
power and therefore, their Sustainable Development of our country
implementation is restricted beyond a is our ultimate goal which encompasses
certain extent. Power plants can be set up economic development, maintaining
based on the above conventional sources environmental quality and social equity.
of power generation. The choice of source This would also ensure that development
depends upon characteristics of each type takes place to fulfil our present needs
of plant and a judicious decision is made without compromising the needs of our
on the choice of fuel depending upon a future generations. The importance and
number of factors, major being economics relevance of power development within
of generation, fuel reserves, availability of the confines of Clean and Green Power is
fuel, dynamics of operation of the plant the most essential element. Such a
and impact on environment. These are growth depends upon the choice of an
supplemented by Non Conventional appropriate fuel / technology for power
Sources of power generation. generation. Accordingly, the Plan takes
into account the development of projects
5.2 PRINCIPLES OF GENERATION based on renewable energy sources as
PLANNING well as other measures and technologies
promoting sustainable development of
The three major aspects to be dealt with the country.
and considered in our planning process
are: The foremost Low Carbon Strategy
Initiative is the choice of resources for
 Growth of the Power Generation power generation. Projects in the Plan
Capacity to meet the demand pattern based on Conventional Sources i.e. Hydro,
in accordance with the principles of Nuclear & thermal are selected as a result
Sustainable development of Studies carried out using Capacity

Chapter 5: Page | 90 Generation Planning


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Expansion Software programmes to meet consumer in providing back up power


the demand as stipulated by the draft 18th varies from 50 paise to several Rupees per
EPS Report. Power from Renewable kWhr. The consumers would be more than
Energy Sources has also been considered willing to pay a premium for their power
while carrying out these studies. consumption in return for the assurance
of 24x7 supplies, which would obviate the
The demand adopted for planning need for them to incur the avoidable costs
purpose is the draft 18th EPS demand of owning and running back up power
projections. This demand is based on use sources. This extra price, billed as a
of energy efficient technologies being “reliability charge” by the utilities, would
used and energy conservation measures form the base for procuring “time of day”
being adopted. Therefore, the planning power from dedicated peaking plants.
strategy adopted is in accordance with
low carbon strategy growth. The higher price for power from peaking
plants must be balanced against the
5.2.2 Operational Flexibility and Reliability higher efficiency, lower impact on
environment and the flexibility made
The fuel sources and their respective possible by these plants. Also, as peaking
technologies of power generation are plants will operate for shorter duration
multiple and varied. Accordingly, each has than base-load plants, the weighted
its own characteristics of operation. The average cost of power drawn as a whole
demand of our electric system also varies will not be significantly higher.
with time of the day, season, year and the
spatial location. Therefore, matching a) Reliability of Power
generation with load at all instances of
time requires not only installation of Reliable power system operation requires
adequate capacity but is also sensitive to ongoing balancing of supply and demand
the type of generation capacity, each with in accordance with established operating
its unique characteristics of altering its criteria such as maintaining system
output and the time taken to do so. voltages and frequency within acceptable
Accordingly, this requirement of the limits. Changes in customer demand
system also needs to be considered when throughout the day and over the seasons
deciding upon the type of generation. It is, are met by controlling generation when
therefore, necessary to widen the scope needed.
of the planning process to take into
account aspects of ‘reliability’ and ‘quality’ The main characteristics of a reliable
of power, apart from the adequacy and system are as follows:
quantum of power.
 The System is controlled to stay within
With the prevalence of load acceptable limits during normal
shedding/power cuts in almost all parts of conditions.
the country, consumers are being  The System performs acceptably after
compelled to resort to back up power credible Contingencies.
from inverters and small diesel genets.
The amount spent by an average

Generation Planning Chapter 5: Page | 91


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

 The System limits the impact and scope as a result of pressure on Discoms to
of instability and cascading outages source their requirement from renewable
when they occur. energy sources (to meet RPO). Since
 The System’s Facilities are protected system stability requires matching of
from unacceptable damage by generation with the demand at all
operating them within Facility Ratings. instances of time, a certain degree of
 The System’s integrity can be restored flexibility and ability of the generators to
promptly if it is lost. respond rapidly to the changing demand
 The System has the ability to supply the must be introduced into the system
aggregate electric power and energy through appropriate generation plants.
requirements of the electricity System should be able to meet additional
consumers at all times, taking into demand arises due to unexpected
account scheduled and reasonably demand and sudden unexpected outages
expected unscheduled outages of of some units.
system components.
Peaking demand in Indian states has been
To achieve reliability in the system, met, to some extent, by purchasing
adequate Reserve capacity, spinning as power from other states through bilateral
well as non-spinning needs to be planned agreements or through the mechanism of
for in the system. Aspects related to the Unscheduled Interchange (UI) at
operation, ownership, modalities and frequency-linked prices and sometimes by
nature of reserves also need to be load shedding also. The frequency band
determined. The location of the reserve tolerated here (from 50.2 to 49.5 Hz) is far
generation capacity viz-a-viz the load above that permitted in developed
centres is also critical. countries. However in the future this
frequency band is expected to narrow
The National Electricity Policy stipulates a down and this would reduce the available
5% Reserve Margin in our system. This has margin to meet the peaking requirement
been considered while planning capacity or reserve capacity through frequency
addition requirement during the 12th and linked interchange mechanism. Hydro
13th Plans. Details of how this Reserve power plants also can be started up
Margin is to be provided are furnished quickly to meet sudden peaks, but this
later in this Chapter (under Cl. 5.4 on facility is restricted to those few states
‘Planning Approach’). that have adequate water storage, all
through the year.
b) Flexibility of operation
Peaking plants shall be environmentally-
A system that is designed for base-load friendly and must comply with emission
generation will lack the characteristics to norms, so as to be located close to load
respond dynamically or efficiently to the centres. They must be able to start up
variation in demand within a short time. (and stop) instantaneously and ramp up
Apart from variation in demand, there is quickly, and in required steps, to match
expected to be wide variability in the spike in load. Their efficiency curve
generation as well, when the installed must be high and flat at different plant
base of renewable energy plants increases loads. They must be ‘all-season’ plants and

Chapter 5: Page | 92 Generation Planning


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

use a fuel which is available throughout 5.2.3 Efficient use of resource


the year.
The fuels for power generation are scarce
As regards the Reserves in the Power and must therefore be used most
System, in developed electricity markets judiciously. From the environment point
abroad, it is customary to have several of view, it is essential that energy
layers of reserves to meet the produced per K.Cal of fuel is maximum to
contingencies. The first rapid response to the extent possible. This would minimize
a drop in frequency of say 0.1 to 0.2 Hz is the pollution caused during the process of
to bring on line a hot reserve plant (equal power production. Various measures
to the largest single unit in the grid) in 5- taken/ being taken to maximize efficient
30 seconds, through automatic use of resources i.e adoption of latest
generation control (AGC). As a second technological advancements in coal based
step, fast reserve power plants (FRPP) are generation; Combined Cooling, Heating
started in 4-15 minutes and ramped up to and Power (CCHP) and Distributed
full load, after which the AGC plant will Generation are detailed in Chapter 4
retreat to reserve mode. As a third step,
replacement reserve power plants (RRPP) 5.3 PLANNING TOOLS - DETAILS OF
come on in 45-60 minutes, after which the PLANNING MODELS
FRPP plants return to their stand-by
mode. CEA is carrying out detailed Generation
expansion studies using the following
The several layers of reserves as planned computer software models for the
in the developed countries also take care generation planning exercises:
of the flexibility of operation of the
various reserves. Therefore, hot reserve (i) Integrated System Planning (ISPLAN)
which is required to operate within (ii) Electric Generation Expansion Analysis
seconds is generally provided through System (EGEAS)
Automatic Generation Control (AGC). The
fast replacement reserve is required to be Salient features of the Planning models
from a generation source which is capable are discussed below.
of ramping up within 4-15 minutes to take
over from the AGC sources. However 5.3.1 Integrated System Planning [ISPLAN]
Replacement Reserve Capacity could be Model
from slower acting generation source to
take over from fast acting reserves. For analyzing various investment
Accordingly, each of these reserve alternatives for the system as a whole, the
capacity has to be from appropriate analytical tool should be capable of
generation source having the requisite assessing the options for both additional
ramp up and ramp down characteristics. generating capacity and transmission
These principles of planning reserve linkage expansion in an integrated fashion
capacity to provide flexibility of operation to achieve optimal solution. The major
have been adopted in our planning problems confronting planners are not
process as detailed in Clause 5.4. only those related to optimizing the
generating capacity requirement and

Generation Planning Chapter 5: Page | 93


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

reliability, but also location of the plant in not during off-peak period. As per the
relation to load centres, fuel resources, model, all the DG based stations operate
fuel transportation network and at low PLF. Some of the gas based
extension of the transmission grid. The stations also operate at low PLF. Even
power system planning is generally some of the existing load centre based
carried out over long time horizons and coal stations located at in the state of
the planning model should be capable of Haryana, Punjab, Rajasthan, Gujarat, Tamil
analyzing a large number of scenarios Nadu and even some imported coal based
within a reasonable time and with least stations located in the state of Gujarat and
effort. Maharashtra operate at low plant load
factor (PLF) on account of high delivered
The ISPLAN model has the capability to cost of fuel to these stations.
address these system planning issues as
an indicative planning tool for analyzing However, the least cost expansion plan is
the major features of an optimal not always the feasible plan. From
expansion plan for generating capacity, feasibility point of view, a number of
transmission network and fuel transport. aspects like availability of land, water etc,
The ISPLAN model works out the least obtaining various clearances for setting
cost power development plan based on up the plant, placement of orders for main
minimisation of objective function, which plant etc. need to be looked into.
comprises of Capital cost of projects
(annualised), O&M cost (Annual), Fuel 5.3.2 Electric Generation Expansion
cost, Fuel transportation cost etc. Analysis System [EGEAS]
The Electric Generation Expansion
Based on Linear Programming Analysis System (EGEAS) is a software
formulation, the model is capable of package intended for use for expansion
producing optimal expansion plans planning of an electric generation system.
effectively and quickly with respect to a In this planning model the operation of
large number of alternative input the power system is simulated
assumptions. Criteria of optimality is the probabilistically. The load on the power
minimum discounted present worth of the system is represented both in terms of
total annual system cost for the year magnitude and time variation. The model
under study including the annualized yields the reliability indices, namely the
capital cost of all new facilities Loss-Of-Load-Probability (LOLP), the
(generating plants, transmission lines etc.) expected value of Energy-Not-Served
plus the operation and maintenance cost (ENS), and the reserve margin for an
and cost of energy not served. expansion power plan by minimising the
objective function which is the present
The ISPLAN model considers operation of worth of the costs associated with
the power plants at a particular PLF operation of the existing and committed
depending upon the demand to be met generating stations viz., the annualised/
such that the cost of delivered power is levelised capital cost and operating cost
minimal. Accordingly, thermal stations of new generating stations and cost of
with costly fuel will operate at low PLF i.e. energy not served. The EGEAS model is
only during period of peak demand and capable of giving a number of expansion

Chapter 5: Page | 94 Generation Planning


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

plans along with their objective functions


and the reliability indices for each such It therefore becomes imperative to plan
plan. The optimal power plan is that plan for a more optimal mix of base-load
for which the reliability indices are capacities, peaking solutions and reserve
satisfied in accordance with certain capacities. The base load capacities will
criteria laid down by the planner, and the take care of ‘bulk-power’ requirement,
objective function is the lowest. while the others will provide the system
operator with sufficient reserve capacity
The EGEAS model, being probabilistic in and a valuable tool to take care of
nature, provides for long range seasonal spikes or time-of-day variations –
generation expansion planning as it yields expected and unexpected- in demand.
very useful quantitative measures of The dynamic response characteristics of
reliability of power supply several years such a balanced system would be far
into the future, and at the same time gives superior and would contribute to higher
an indication of the total cost of operating reliability.
the existing and committed system and
installing and operating the new system. As unscheduled intra and inter-regional
The transportation of fuel and transfers would pose challenges, the right
transmission of power are considered mix of base load and flexible solutions
explicitly in the Integrated System must preferably be determined and
Planning (ISPLAN) Model. Whereas the planned for, at the level of the state grid
overall requirement of generating itself. This will ensure the most rapid, real-
capacity is assessed using the EGEAS, the time response to local peaking needs.
siting of new generating stations that use
transportable fuel is done using ISPLAN. The Planning Approach is in the following
Under ISPLAN the broad features of the sequence:
transmission system are also obtained.
1) Preparation of All India Load Duration
5.4 PLANNING APPROACH Curve

Beyond the 11th Plan, a planning approach An All India Load Duration Curve (LDC)
whose exclusive aim is ‘adequacy of was generated from the summation of
power’ (through the addition of base-load hourly data for all states. The data was
capacities equal or close to the maximum collected for three years (2006-09) on
expected demand) would lead to sub- monthly basis from various Regional Load
optimal operation of the system for a Dispatch Centres and State Load Dispatch
majority of the time. This is due to the Centres. The hourly data was analyzed
poor turn-down capabilities inherent in and corrected for any discrepancies in
power production technologies of base terms of load shedding, frequency
load plants such as coal and nuclear fuel. correction, scheduled power cuts and any
Moreover, this pattern of under- loading data errors. The hourly loads for each
coal plants during off-peak hours down to year were normalized, summed and
50% also results in power stations averaged to unity. The peak demand was
operating at sub-optimal PLFs leading to adjusted to unity and other hourly
poor efficiency levels. demands were scaled accordingly. It was

Generation Planning Chapter 5: Page | 95


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

assured that the All India LDC meets both Duration Curve was generated based on
Peak Demand and Energy Requirement Energy Requirement and Peak Load for
monthly and annually published from time 2016-17. A typical Load Duration Curve is
to time by CEA using a mathematical illustrated in the Figure No. 5.2 below.
model. A typical Equivalent All India Load

Figure 5.2- All India Load Duration Curve (LDC)

2) Generation Expansion Studies based on inputs from Nuclear Power


Corpoation. Renewable capacity
th
The above All India LDC was fed in as an considered during 12 Plan is also as per
input to the EGEAS Software to carry out inputs from MNRE. The loading of the
generation expansion studies. Hydro, type of generation to meet the demand of
Renewable, Gas and Nuclear projects the system based on cost economics is
were accorded priority and taken as must also illustrated in Fig 5.2.
run projects on account of their inherent Reserve capacity
advantages. The programme indicated the As stipulated by NEP, 5% Spinning Reserve
requirement of coal based projects to is to be provided. This corresponds to a
meet the demand requirement out of a capacity of about 10,000 MW by 12th Plan
shelf of coal based projects under end. The requirement of this Reserve
implementation. The hydro and gas based Capacity has been incorporated in the
projects that are likely to materialise Plan by correspondingly reducing
during 12th Plan out of the shelf of projects availability of coal based plants by 5%
under various stages of implementation under normal operating conditions viz-a-
have been considered as must run for the viz normative availability from these
planning purpose. Nuclear projects have plants.
been considred for benefit during 12th Plan

Chapter 5: Page | 96 Generation Planning


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

All the above options have a very quick been considered in the studies while
response time and, therefore, adequately estimating the capacity addition
provide hot reserve, fast replacement requirement from conventional power
reserve and replacement reserve. plants. Wind and solar energy was fixed
with topmost priority as must run in the
Peaking capacity expansion exercise. The remaining
A peaking load occurs owing to several capacity addition required was then
reasons. It could be something that can be estimated to meet the demand of the
anticipated, as in morning peaks and system. Different Scenarios
evening peaks. It could happen when corresponding to likely availability of
irrigation needs have to be met and renewables were worked out.
several thousand pump sets come on
simultaneously. Urban loads can shoot up 4) Retirement of Old thermal units
in certain seasons (example, summer air-
conditioning loads in Delhi). Or the Information was compiled in respect of
peaking shortage could be due to a old thermal power plants and gradually
sudden drop in output from an infirm, and systematically all the inefficient
renewable energy source such as wind thermal units were considered for
turbines. retirement while estimating the capacity
addition requirement. During the 12th and
Plants with rapid-response characteristics 13th Plan, 4,000 MW each was retired.
that make them ideal as ‘reserve’ plants
can also be used to meet expected daily, 5) Facility for Black Start after complete
time-of-day spikes and seasonal peaks. grid collapse.
They can be an integral part of the grid
operator’s armoury to provide flexibility. As suggested above, a peaking capacity of
about 2,000 MW could be provided at
Peaking capacity also needs to come from major metropolitan cities of the country
quick response power plants. Therefore, with a view to ensure reliable power
foremost, pumped storage hydro plants supply. This facility would also be useful in
and hydro plants with storage capacity providing black startup facility in the
provide peaking power. Also, gas based/ event of a grid collapse. Combined Heat
diesel based plants i.e. OCGT and engines and Power Plants with a high efficiency of
are appropriate for peaking power. It is operation could also provide black start
also considered appropriate to have facilities immediately after grid collapse.
distributed peaking capacity at major load
centres in the country, perhaps 2000 MW 6) Time of Day (TOD) Tariff
each at the metropolitan cities to provide
quality, reliable and flexible power supply. The National Electricity Policy and the
National Tariff Policy mandates the State
3) Renewable capacity in Planning Commissions to introduce Time of the
process. day (TOD) metering in order to reduce
the demand of electricity during peak
Renewable capacity has tremendous hours. It is desirable from the system
inherent advantages and has therefore point of view to flatten the load curve for

Generation Planning Chapter 5: Page | 97


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

which it is essential to reduce peak factor causes the Plant Load Factor of the
demand and encourage generating stations to improve, thus
consumption/enhance load during off reducing the generation cost. The
peak hours. This can be done by the consumers ultimately get benefited by
following methods availing power at lower rates during off-
peak hours and also by reduction in supply
 Providing incentives to consumers for costs of the utility. The incidence of load
shifting their consumption to off- shedding is also reduced due to reduction
peak hours in the peak load
 Providing dis-incentives to consumers
for consumption during peak hours Although, TOD tariff is applicable for high
 A combination of the above two. tension consumers in many states, it is not
yet applicable at the retail level. TOD
The above methods require differential metering could be made applicable for
tariffs for different time slots of peak and those consumers where there is possibility
off-peak hours .It is well known that by of shifting the load of peak hours to off-
controlling the price of electricity, it is peak hours. To have TOD tariff imposed at
possible to motivate individual consumers the retail level, all domestic consumers
to either reduce/increase or shift their will have to be given a new meter that will
consumption from one point of time to segregate the peak and non-peak
another during the day, i.e. the consumer consumed units.
can be motivated to change his
consumption pattern during the day. 5.4 CONCLUSION

The major advantage of reducing the peak Planning for capacity addition in 12th and
demand through TOD metering, as a tool 13th Plans has been carried out in Chapter
for Demand Side Management, is that it 6 in accordance with the principles
allows the utility to reduce its outlined in this Chapter. Reliability by
generation/power purchase requirement, providing Reserve Margins and Flexibility
which reduces the overall cost of supply. by providing capacity having suitable
Another advantage, which the utility has, ramp up and ramp down response to take
is that the load factor of the system care of peaking and reserve requirements,
improves due to shifting of some peak forms an important aspect while planning
load to off peak hours and leads to capacity addition in succeeding Chapters.
flattening of load curve. Improved load

---+++---

Chapter 5: Page | 98 Generation Planning


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 6
GENERATION CAPACITY ADDITION PROGRAMME
FOR 12th & 13th PLANS

6.0 INTRODUCTION 6.1 GENERATION FROM CONVENTIONAL


SOURCES IN INDIA
In this Chapter, the Generation Capacity
addition required during the 12th Plan and 6.1.1 Hydro
tentative capacity addition required
during the 13th Plan has been assessed India’s hydroelectric resources are
based on Planning Principles and criteria estimated to be 84 GW at a 60% load
detailed in Chapter 5. factor. At an average load factor of about
30%, an installed capacity of 150 GW,
Studies have been carried out by CEA to excluding 15 GW of mini hydro-electric
assess the required capacity addition. A plants (less than 25 megawatts), may be
Shelf of projects for likely benefit during feasible. Low carbon growth Strategy
the Plan (projects which are in the would ensure clean hydropower is used to
pipeline) has been drawn up out of which its maximum potential for meeting peak
the most feasible projects are selected loads and all new projects must be
based on the Status of the Projects. designed with this objective in mind.
However the full development of India’s
Out of the Conventional Energy Sources, hydro-electric potential, while technically
Hydro and Nuclear are Clean and Green feasible, faces issues of water rights,
Sources and therefore, have been resettlement of project affected people
accorded priority by being considered as and environmental concerns –issues that
must run projects in the Studies, must be resolved.
considering the viability and status of
each project. Out of the remaining, 6.1.2 Nuclear
thermal projects are selected based on Nuclear generation is also limited due to
the preparedness of the projects. Gas availability of natural uranium in the
projects need to be set up and efforts country. Department of Atomic Energy
need to be made to ensure adequate plans to put up a total installed nuclear
availability of gas. Peaking capacity and power capacity of 20,000 MWe by the
Reserve Capacity has also been planned in year 2020 in the country. As of now, the
accordance with the Planning Principles. first stage programme based on
However, due care has also been taken to indigenous fuel is in progress and has
ensure that over capacity is not planned reached a stage of maturity. A beginning
for, since our emphasis is on an optimum has been made of the 2nd stage
solution. programme with construction of 500
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 99
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

MWe PFBR (Prototype Fast Breeder including clean coal technologies. The
Reactor). This is expected to be followed choice of fuel for power generation would
by four more 500 MWe units by the year be governed by principles of sustainable
2020. Thereafter, it will be followed by a development keeping in view energy
number of FBRs. When the capacity security aspect.
through FBRs builds up to reasonable
level, the deployment of thorium for The production and supply of gas had not
power generation through 3rd stage will been keeping pace with the growing
begin and get realized in the long term. demand of gas in the country, including
for that of power sector. The gas supply
Although nuclear energy can make only a for gas based power stations in the
modest contribution over the next 15 country is inadequate, even the
years, longer-term consideration of even a commitments of gas allocations made
modest degree of energy self-sufficiency earlier to power stations were not
suggests the need to pursue the fulfilled. The gas was sufficient to operate
development of nuclear power using these stations at about 52 % PLF only
thorium. during 2007-08. Similarly the average gas
supply during April 2008- January 2009
With the signing up of the '123 was 37.44 MMSCMD, against the
Agreement' on nuclear cooperation requirement of 66.04 MMSCMD to
between USA and India, and NSG’s waiver operate the stations at 90% PLF, which
for supply of nuclear fuel to India, it is was sufficient to operate these stations at
expected that some nuclear plants with about 51% PLF.
foreign technology from friendly
countries would be set up in the country. In the year 2009-10, Government of India
The availability of imported nuclear fuel allocated 18 MMSCMD gas from KG D6
and technology to India will help in basin out of production of 40 MMSCMD in
accelerated capacity addition from Phase I to Power Sector for existing
nuclear power plants. Commencement of power plants which helped in utilizing the
construction of reactors with imported stranded capacity of gas based power
technology during 11th/12th Plans is stations. The production at KG basin was
expected which will get commissioned in expected to go up to 80 MMSCMD.
13th Plan onwards. Development of Accordingly, EGoM allocated bulk of the
nuclear parks with Mega capacity is also additional gas from KG basin to Power
anticipated. Sector. The allocation was based on 75%
PLF to A.P. projects and 70% PLF to non
6.1.3 Gas A.P. projects. This includes 12.29
MMSCMD gas on firm basis and 12
Gas based stations are also restricted due MMSCMD on fall back basis to existing
to limited availability of gas. Therefore, power projects including projects likely to
coal based thermal generation is likely to be commissioned during 2009-10.
continue to dominate power generation in
the country and therefore requisite thrust However, in view of reduced production
is essential for the development of various from KG basin in recent past, even the
environment friendly technologies firm quantity of allocated gas is not being

th th
Chapter 6: Page | 100 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

supplied to power plants and the country 6.1.4 Coal/Lignite


is facing huge generation loss. Gas power
plants, being a semi green power, needs The coal reserves in the country are of the
to be promoted for reduction of our order of 277 billion tonnes. About 70% of
carbon foot prints and also because of the total coal produced is consumed in
many other inherent advantages of gas the Power Sector.
power plants as compared to
conventional coal power plants. However, there are impediments in the
Presently, about 13,000 MW gas based development of coal blocks due to delay
capacity in the country is under various in granting clearances and problems in
stage of construction. But non availability acquisition of land. Forest clearance is a
of gas to new power plants at present, major problem as coal blocks are in forest
have serious constraint in development of area. Captive coal blocks are generally
gas power plant in the country. So far no unexplored and are expected to take
gas allocation has been made for projects more time in development. According to
likely to be commissioned during present status of commissioning of power
remaining period of 11th Plan/early 12th projects during 11th plan and production
Plan. Few power plants are ready in all plan of CIL, the gap between demand and
aspects but commissioning is being availability of domestic coal in the
delayed due to non availability of gas. terminal year of the 11th plan is expected
to be about 53 MT necessitating import of
After start of actual supply of gas from about 35 MT of coal. Blending of imported
KG basin to power projects, a number of coal may be technically feasible to the
proposals for setting up gas based power tune of about 10-15% only. Therefore,
projects totaling to about 1,50,000 MW shortage of coal may result in stranded
including expansion as well green field coal based capacity.
projects have been received.
The geological reserves of lignite have
It is necessary to plan for about 20,000- been estimated to be about 35.6 BT.
25,000 MW gas based projects (subjected Lignite is available at limited locations
to availability of gas) to meet the capacity such as Neyveli in Tamil Nadu, Surat,
addition target and also to reduce our Akrimota in Gujarat and Barsingsar,
total CO2 emission. Two scenarios have Palana, Bithnok in Rajasthan, Over 86% of
been developed for 12th Plan in view of the resources are located in the State of
uncertainty of gas. However, it is Tamil Nadu alone, whereas the rest 14%
recommended that power projects be are distributed in other States. Since,
given higher priority as far domestic gas lignite is available at a relatively shallow
allocation is concerned in view of massive depth and is non-transferable, its use for
power shortage in the country and very power generation at pithead stations is
low emission from gas plants which will found to be attractive. The cost of mining
help us in restricting CO2 emissions from lignite has to be controlled to be
power sector. economical for power generation.

th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 101
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

6.2 NORMS ADOPTED FOR RELIABILITY electricity which has to be borne by the
CRITERIA consumer. Details of LOLP in some
countries are as follows:
The Power System is planned to meet the
forecasted demand and ensure an
expected level of reliability. Reliability is a
measure of the ability of a system to Name of country LOLP(%)
perform its designated function under the Cambodia 1.8
designed conditions. In our Studies, Loss Laos 0.27
of Load Probability (LOLP) is the criteria Thailand 0.27
adopted to reflect the capacity of the Vietnam 0.27
system to meet the peak load and Energy Hong Kong 0.006
Not Served (ENS) to reflect the Energy Bangladesh 1.0
Requirement not met in the System. LOLP Belgium 0.2
is the probability that a system will fail to USA 0.03
meet its peak load under the specified China 0.14
operating conditions. It is the proportion
of days per year or hours per year when Source: Information collected from website of
the available generating capacity is above countries.
insufficient to serve the peak demand.
This index is dimensionless and can also Up till now, in India the reliability figures
be expressed as a percentage. adopted were of LOLP – 1% and ENS- 0.15%.
This was the case when India was faced by
ENS is the expected amount of energy a huge power deficit situation. Now, the
which the system will be unable to supply power shortage is expected to ease out.
to the consumers as a fraction of the total Therefore from 12th Plan onwards more
energy requirement. This index again is Stringent Reliability norms are required to
dimensionless and can also be expressed be adopted. USA adopts an LOLP of 0.03%
as a percentage. In other words these which appears to be reasonable for a
indicate as to how many units of energy developed economy. LOLP standard
requirement in a year are not met and adopted by some South Asian countries is
correspondingly how many hours in a year 0.27 %.
the power demand is not met. Various
It is therefore proposed that an LOLP of
countries in the world have adopted their
0.2% and the Energy Not Served (ENS) of
own Reliability Criteria depending upon
0.05% shall be adopted for planning
the status of their power system and the
purposes from 12th Plan onwards.
price affordability of the consumers to
pay for the reliability of the system. It is 6.3 PLANNING NORMS (CERC NORMS)
evident that a more stringent and reliable
system would yield higher cost of The planning studies require accurate
th th
Chapter 6: Page | 102 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

performance parameters of various type MW and above have shown consistently


of generating units to assess their good performance over a long period.
availability and energy generation Higher size unit of 660 MW and above
capabilities. The peaking power which are likely to be installed in future
availability and energy generation have been placed along with 500 MW
capacity are important parameters for units for auxiliary Power consumption,
meeting the projected demand of the however for the purpose of heat rate,
country and various regions. Peak these units have been placed in a separate
availability and PLF are key performance group. Combined cycle Gas Turbines
factors required for the planning studies (CCGT) are very efficient and have lower
and other features used for planning heat rates, however, their availability and
studies are the auxiliary power PLF would depend on the availability of
consumption, heat rate, capital cost of the gas. The energy of the hydro units has
generating units, etc. Different types of been taken on the basis of the design
generating units have varied operational energy of the project.
performance and accordingly different
norms have been used for thermal (coal), 6.3.1 Peaking Availability
combined cycle, hydro and nuclear
projects. The generation planning norms The peaking availability (gross) of the
for different sizes of thermal units are various types of generating units is given
different and units of higher sizes i.e. 200 in Table 6.1

Table 6.1
PEAKING AVAILABILITY (GROSS) OF THERMAL/ NUCLEAR/ HYDRO POWER STATIONS
Figures in %
Unit Size Existing Units Future Units
Thermal (Coal) 800/660 MW - 88
500/250/210/200 MW 85 85
Below 200 MW 75 85
Below 200 MW operating below 50 -
20 % PLF at present
Gas Based OCGT all sizes 90 90
CCGT all sizes 88 88
DG Sets All sizes 75 75
Lignite Based All sizes 80 80
Nuclear All sizes 68 68
Hydro All sizes 87.5 87.5

6.3.2 Auxiliary Power Consumption: The types of generating units considered are
auxiliary consumption of the various given in Table 6.2

th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 103
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Table 6.2

I Coal Based Power stations Auxiliary Power Consumption


1. 800/ 660 MW class units 7.5%
2. 500 MW class units 7.5%
3. 250/210/200 MW class units 8.5%
4 Below 200 MW units 12.0
5 Lignite based units 12 % for <200 MW
9 % for >200 MW
II Gas Based Power Stations
1 Combined cycle 3.0%
2 Open cycle 1.0%
3 DG sets 1.0%
III Hydro Power Stations 0.7%
IV Nuclear Power Stations
160 MW BWR 10%
200/220 MW PHWR 12.5%
1000 MW LWR 7.8%
220/ 540 MW PHWR 12.5%
500 MW FBR 6.0%

6.3.3 Machine heat rate: The machine heat


rates (gross) considered for the various
thermal units are given in Table 6.3.

Table 6.3

Unit Size Gross Heat rate (Kcal/kWh)


800 MW 2300
660 MW 2300
500 MW 2425
200/210/250 MW KWU 2460
200/210/250 MW LMZ 2500
250/210/125 MW (lignite) 2750
100 MW 2750
50 MW class of units 3000
30 MW class of units 3300
Combined cycle Gas turbine 2000
Open cycle Gas turbine/DG Sets 2900

th th
Chapter 6: Page | 104 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

6.3.4 Cost and heat value of GAS/ LNG

Table 6.4
COST CALORIFIC VALUE
FUEL (RS./TH.CUM) (KCAL /CUM)
LNG 8,000 9,800
GAS (HVJ) 4,400 9,500
GAS (RELIANCE) 5,760 9,500
GAS (NER) 3,000 9,500

6.3.5 Financial Parameters


Table 6.5
S.NO ITEM UNIT VALUE
1 DEBT - % OF CAPITAL COST % 70
2 EQUITY - % OF CAPITAL COST % 30
3 WORKING CAPITAL- % OF CAPITAL COST % 6
4 INTEREST ON DEBT % 11.5
5 RETURN ON EQUITY % 15.5+TAX
6 INTEREST ON WORKING CAPITAL % 12.25
7 DISCOUNT RATE % 9.0
8 O&M CHARGES POWER PLANT % 2.5
9 O&M CHARGES – TRANSMISSION LINE % 1.5
10 DEPRECIATION - POWER PLANT % 5.28 FOR 12 YEARS

6.3.6 Plant load factor: The plant load factor based) considered for the various type of
of thermal power stations (coal and gas- plants are furnished in Table 6.6

Table 6.6
PLANT LOAD FACTORS OF THERMAL/ NUCLEAR POWER STATIONS

Units PLF (%) Remarks


Thermal
Coal Based
800/660 MW 82.5 Future Units
500/250/210/200 MW 82.5 Existing and Future Units
Below 100/110 MW 60 80% for future units
40 Units in ER and NER operating Below 20% PLF.
Lignite Based 125/ 200/250 MW 75
Gas Based
CCGT 68.5
OCGT 33
Nuclear Units
All sizes 68 Normative Capacity Factor

th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 105
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

For hydro units, the energy generation is  Seasonal Studies being carried out
as per the designed energy generation in rather than Annual Studies with a
a 90% dependable year. view to ensure demand being met
in all the seasons
6.4 GENERATION CAPACITY  Projects considered in the study
EXPANSION PLANNING DURING 12TH PLAN are as under :-

A Computer Model Study on Electric  Hydro-


Generation Expansion Analysis System
(EGEAS) programme was carried out in A shelf of hydro projects with aggregate
CEA to assess the installed capacity capacity of about 22,000 MW have been
required to meet the above demand identified which are likely to yield benefits
projections on the basis of National Load during 12th / 13th Plan. Details are furnished
Duration Curve. The Studies are based on in Appendix 6.1. Considering the status of
the following: various projects under construction and
uncertainties relating to geological
 Demand to be considered as surprises, natural calamities like floods,
forecasted by 18th EPS i.e. Peak R&R and environmental issues expected
Demand - 1,99,540 MW and Energy to be experienced during the execution of
Requirement – 1354 BU at bus bar. the hydro projects, it is proposed that a
 Spinning Reserve of 10,000 hydro capacity addition of about 9,204
MW(corresponding to 5% spinning MW is likely during 12th Plan. Details are
reserve as stipulated by National furnished in Appendix 6.1a.
Electricity Policy)
 Reliability Criteria - Loss of Load  Nuclear
Probability (LOLP) < 0.2% and
Energy Not Served (ENS) < 0.05%. A nuclear capacity of 2,800 MW has been
 Capacity addition considered considered as per the information
th
during 11 Plan is 62,374 MW (likely furnished by Nuclear Power Corporation.
capacity addition during 11th Plan as Details are furnished in Appendix 6.2.
per latest status of projects).
 Capacity retired during 12th Plan is  Thermal
about 4000 MW which includes
remaining units of coal & lignite Addition of gas based capacity is
under 100 MW (1500 MW already considered necessary to reduce CO2
retired during 11th Plan), gas plants emissions. Modern combined cycle gas
more than 30 years old (1987 & turbines (CCGTs) have high efficiency of
before) and some coal units of 110 around 55% compared to coal based plants
MW. (Gross efficiency of supercritical units is 38
 Import of hydro power of 1,200 to 40%). Gas turbines could be located
MW from neighbouring countries near the load centre with a view to
 First priority given to potential minimize the requirement of transmission
hydro projects followed by nuclear system and could be operated in a manner
and gas based projects with a view so as to maximize the output during the
to minimize CO2 emissions. peak hours and minimize during the off-
th th
Chapter 6: Page | 106 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

peak hours so as to utilize the available within the confines of the reliability
gas which is scarce, optimally. criteria.

In view of expected increase in coal Earlier Studies were conducted only to


shortage during 12th Plan, we should plan estimate the Capacity addition required to
for about 12,000-15,000 MW gas based meet the Annual Demand projections.
projects to meet the capacity addition However, it was considered that Annual
target and also to reduce our total CO2 Studies are not adequate as they would
emission. It is recommended that power not eliminate the possibility that this
projects be given higher priority as far capacity would be sufficient for the
domestic gas allocation is concerned in system to meet the reliability criteria in
view of massive power shortage in the each of the 5 seasonal blocks of months in
country and very low emission from gas a year. These five blocks of months are
plants which will help us in restricting CO2 April-June, July-September, Oct-
emissions from power sector. As the November, December-January and
availability of gas is uncertain 12,000 MW February-March. Seasonal Studies were,
gas based projects have been considered therefore, considered to be essential to
during 12th plan in the high gas scenario ensure that the seasonal demand of the
apart from 1,086 MW gas based plants for system would be met in each block when
which gas is assured from local sources considering the energy of hydro plants in
(considered in low gas scenario). Project- each of the above blocks of month.
wise details of Gas based projects Therefore studies for each 5 seasons i.e. 5
totalling to 1,086 MW & shelf of gas blocks of months in a year were carried
based projects totalling to 13,000 MW are out using EGEAS model to assess the
furnished in Appendix 6.4. capacity addition requirement.

The balance capacity is proposed to be Hydro, Gas and Nuclear based capacity is
met from coal based projects. Thus, coal is given the foremost priority due to their
expected to be main fuel for 12th Plan inherent advantages towards a Low
capacity addition too. A shelf of projects Carbon growth Strategy. Therefore,
with aggregate capacity of 1,23,135 MW capacity from these sources which is likely
coal based projects have been identified to materialise during 12th Plan has been
which are likely to yield benefits during considered as must run in the various
12th Plan. Project-wise details are Scenarios.
furnished in Appendix 6.3. The coal based Renewable capacity has also been
capacity shall be selected from the shelf considered as must run capacity.
of projects depending on the feasibility
of the various projects. Three scenarios were developed for
generating capacity addition during 12th
6.5 12TH PLAN STUDY AND RESULTS Plan. The scenarios are as follows:
Scenario 1 – Low Renewables, Low Gas
EGEAS Studies were carried out to assess
the total capacity addition requirement Scenario 2 – Low Renewables, High Gas
during the 12th Plan to meet the demand
Scenario 3 – High Renewables, High Gas
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 107
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Details of Various Scenarios and Results in


each case are as follows:

 Scenario – 1– 18th EPS Demand - Low Renewable(18,500 MW), Low gas(1086 MW)

TYPE 12thPlan Capacity


(MW)
Hydro 9,204
Thermal 67,686
Coal 66,600
Lignite 0
Gas 1,086
Nuclear 2,800
TOTAL 79,690
Wind 11,000
Solar 4,000
Other RES 3,500
TOTAL (RES) 18,500
Retirement During 4,000
12th Plan

 Scenario – 2–18th EPS Demand - Low Renewable(18,500 MW), High gas(13,086


MW)

TYPE 12thPlan Capacity


(MW)
Hydro 9,204
Thermal 67,686
Coal 54,600
Lignite 0
Gas 13,086
Nuclear 2,800
TOTAL 79,690
Wind 11,000
Solar 4,000
Other RES 3,500
TOTAL (RES) 18,500
Retirement During 4,000
12th Plan

th th
Chapter 6: Page | 108 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

 Scenario -3 - 18th EPS Demand - High Renewables (30,000 MW), High


Gas(13,086MW)
TYPE 12th Plan Capacity
(MW)
Hydro 9,204
Thermal 64,486
Coal 51,400
Lignite 0
Gas 13,086
Nuclear 2,800
TOTAL 76,490
Wind 15,000
Solar 10,000
Other RES 5,000
TOTAL (RES) 30,000
Retirement During 4,000
12th Plan

OUT OF THE ABOVE SCENARIOS, 13,086–) in High Renewables


SCENARIO-1 HAS BEEN CONSIDERED AS (30,000), High Gas
THE BASE CASE FOR PLANNING scenario(13,086MW)
CAPACITY ADDITION DURING THE 12TH
PLAN. 1200 MW import from neighboring
Details of Base Case are as follows: countries has been considered in all the
three scenarios.
12th Plan Programme

Total Capacity - 79,690 MW


(Conventional) 6.6 TENTATIVE PLANNING FOR
Hydro - 9,204 MW GENERATION CAPACITY EXPANSION
Nuclear - 2,800 MW DURING 13TH PLAN
Thermal - 67,686 MW
 Coal - 66,600 MW The studies for assessing the tentative
capacity addition requirement during the
 Gas - 1,086 MW
13th Plan was carried out based on the
following considerations:
 Indigenous capacity required to be
developed in Scenario-2 – 79,690
 Demand to be considered as
MW (Hydro-9,204 MW, Nuclear -
forecasted by 18th EPS – Peak Load-
2,800 MW, Coal -54,600 MW, Gas –
2,83,470; Energy Requirement - 1904
13,086 MW) in Low Renewables
BU
(18,500 MW) High Gas
scenario(13,086 MW).  Spinning Reserve -5% i.e. about
14,000 MW
 Indigenous capacity required to be
developed in Scenario-3 – 76,490  Reliability Criteria – Loss of load
MW (Hydro-9,204 MW, Nuclear - probabilities < 0.2 % and Energy not
2,800 MW, Coal -54,600 MW, Gas – served < 0.05 %.
th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 109
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

 Capacity addition considered during Carbon growth Strategy. Therefore this


11th Plan is 62,374 MW capacity is considered as must run in the
 12th Plan capacity of about 80,000 various Scenarios.
MW in corresponding scenario.
 Retirement of 4,000 MW which Renewable capacity has also been
includes coal units lesser than 200 considered as must run capacity.
MW (commissioned before 1982)
and gas units commissioned before Three scenarios were developed for
1992 (more than 20 years old). tentative generating capacity addition
 Import from neighbouring countries during 13th Plan. The scenarios are as
– 8,040 MW Hydro capacity follows:
Scenario 1 – Low Renewables (30,500
6.7 STUDY RESULTS FOR 13TH PLAN MW), No Gas
TENTATIVE CAPACITY EXPANSION Scenario 2 – Low Renewables (30,500
MW), High Gas (13,000 MW)
EGEAS Studies were carried out to assess Scenario 3 – High Renewables (45,000
the total capacity addition requirement MW), High Gas (13,000 MW)
during the 13th Plan to meet the demand
within the confines of the reliability Considering above must run projects, the
criteria. balance capacity is proposed to be met
from coal based projects. These Scenarios
Seasonal Studies were carried out as in are based on corresponding Scenarios
the 12th Plan. materializing in the 12th Plan. The details of
13th Plan capacity addition requirement
Hydro, Gas and Nuclear based capacity is corresponding to the three Scenarios is
given the foremost priority due to their given as under:
inherent advantages towards a Low

 Scenario-1 – Low Renewables - No Gas

TYPE 13th Plan Capacity (MW)

Hydro 12,000
Thermal 49,200
Coal 49,200
Gas 0
Nuclear 18,000
TOTAL 79,200
Wind 11,000
Solar 16,000
Other RES 3,500
Total (RES) 30,500
Retirement During 13th Plan 4,000

th th
Chapter 6: Page | 110 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

 Scenario-2 – Low Renewables - High Gas

TYPE 13th Plan Capacity (MW)

Hydro 12,000
Thermal 51,000
Coal 38,000
Gas 13,000
Nuclear 18,000
TOTAL 81,000
Wind 11,000
Solar 16,000
Other RES 3,500
Total (RES) 30,500
Retirement During 13th Plan 4,000

 Scenario-3 – High Renewables - High Gas

TYPE 13th Plan Capacity (MW)

Hydro 12,000
Thermal 47,000
Coal 34,000
Gas 13,000
Nuclear 18,000
TOTAL 77,000
Wind 20,000
Solar 20,000
Other RES 5,000
Total (RES) 45,000
Retirement During 13th Plan 4,000

OUT OF THE ABOVE SCENARIOS (Concential)


SCENARIO-1 HAS BEEN CONSIDERED AS Hydro - 12,000* MW
THE BASE CASE FOR THE 13TH PLAN. Nuclear - 18,000 MW
Thermal - 49,200 MW
The capacity addition considered during Coal - 49,200 MW
the 13th Plan is as follows: * excludes 8,040 MW imports from
hydro plants of neighbouring countries.
13th Plan Programme
 Indigenous capacity required to be
Total Capacity - 79,200 MW developed – 79,200 MW (Hydro-

th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 111
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

12,000 MW, Nuclear -18,000 MW, Coal country during the 12th Five Year Plan
-49,200 MW) assuming likely capacity addition of
about 62,374 MW during the 11th
During the 13th Plan, the capacity addition Plan, spinning reserve requirement
is from more efficient Units based on of 5% as per NEP, retirement of old
latest technologies. Thermal capacity inefficient thermal units of about
addition is from units of higher size i.e. 4,000 MW and reliability criteria of
660/800 MW in all cases with supercritical 0.2% LOLP & 0.05% ENS adopted by
technologies. These Initiatives are in CEA.
accordance with our strategies for clean
and Green Power. It is recommended that  The total capacity addition
during the 13th Plan, capacity addition requirement in the country for 12th
from coal fired power plant must be from Plan has been proposed as under:
super critical only.
Total Capacity (excluding
The required capacity addition during the renewable) - 79,690 MW
13th Plan will be of the order of about Hydro - 9,204 MW
80,000 MW. Any projects slipping from Nuclear - 2,800 MW
12th Plan capacity addition programme Thermal - 67,786 MW
MW will be added in the 13th Plan capacity  Coal - 66,600 MW
addition programme. Thus it is clear that  Gas - 1,086 MW
huge capacity addition will be required Indigenous capacity required to be
during 13th Plan for which advance developed – 79,690 MW (1,200 MW
Planning/advance action is required during imports have been assumed from
the 12th Plan itself by all concerned. neighbouring countries) .

6.9 CONCLUSION  The total capacity addition


requirement in the country for 13th
 The power demand projections Plan has been proposed as under:
considered for planning capacity
addition are as per the 18th EPS Total Capacity (excluding renewable)
Report. Details are as follows: - 79,200 MW
 End of 12th Plan are – Peak Hydro - 12,000 MW
Demand of 199,540 MW Nuclear - 18,000 MW
and Energy Requirement of Thermal - 49,200 MW
1354 BU.  Coal - 49,200 MW
 End of 13th Plan- Peak Hydro Import – 8,040 MW
Demand- 283474 MW and
Energy Requirement – 1904  Indigenous capacity required to be
BU. developed – 79,200 MW (Considering
8,040 MW imports from
 A Capacity addition of 79,690 MW neighbouring countries )
would be required to be added in the

---+++---
th th
Chapter 6: Page | 112 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Annexure 6.1

HYDRO PROJECTS IDENTIFIED FOR BENEFITS DURING 12th PLAN

Installed Benefit in
Sl.No. Name of scheme State Agency
Capacity (IC) 12th. Plan
1 Kashang - I H.P. HPPCL 65 65
2 Tidong-I H.P. Nuziveeedu Seeds Ltd 100 100
3 Kashang -IV H.P. HPPCL 48 48
4 Kashang-II & III H.P. HPPCL 130 130
5 Tangnu Romai H.P. Tangnu Romai Power 44 44
Corp.
6 Bajoli Holi H.P. GMR 180 180
7 Kutehr H.P. JSW 240 240
8 Renuka dam H.P. HPPCL 40 40
9 Sainj H.P. HPPCL 100 100
10 Shongtong Karcham H.P. HPPCL 450 450
11 Dhaula Sidh H.P. SJVNL 66 66
12 Baglihar-II J&K PDC 450 450
13 Kishan Ganga J&K NHPC 330 330
14 New Ganderbal J&K PDC 93 93
15 Kawar J&K NHPC 520 520
16 Kiru J&K NHPC 600 600
17 Singoli Bhatwari Uttarakhand L&T 99 99
18 Phata Byung Uttarakhand LANCO 76 76
19 Lata Tapovan Uttarakhand NTPC 171 171
20 Pala Maneri Uttarakhand UID 480 480
21 Tehri St-II PSS Uttarakhand THDC 1000 1000
22 Vishnugad Pipalkoti Uttarakhand THDC 444 444
23 Alaknanda (Badrinath) Uttarakhand GMR 300 300
24 Kotlibhel-St-1A Uttarakhand NHPC 195 195
25 Kotlibhel-St-1B Uttarakhand NHPC 320 320
26 Kotlibhel-St-II Uttarakhand NHPC 530 530
27 Rupsiyabagar Khasiyabara Uttarakhand NTPC 260 260
28 Hanol Tiuni Uttarakhand Sunflag 60 60
29 Naitwar Mori (Dewra Mori) Uttarakhand SJVNL 56 56
30 Arkot Tiuni Uttarakhand UID 81 81
31 Bowala Nand Prayag Uttarakhand UJVNL 300 300
32 Devsari Dam Uttarakhand SJVNL 252 252
33 Bogudiyar Sirkari Uttarakhand GVK 146 146
34 Mapang Bogudiyar Uttarakhand GVK 200 200
35 Nand Prayag Langasu Uttarakhand UJVNL 100 100
36 Tamak Lata Uttarakhand UJVNL 280 280
37 Tuini Plasu Uttarakhand UID 72 72
38 Shahpur Kandi Punjab PSEB 206 206
39 UBDC-III Punjab Bhilwara Energy Ltd. 75 75
40 Ramam St-III W. B. NTPC 120 120
41 Ramam St-I W. B. WBSEDCL 36 36
42 Ramman Ultimate(IV) W. B. WBSEDCL 28 28
43 Dummugudem A..P. APID 320 320
44 Pollavaram MPP A..P. APID 960 960

th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 113
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

45 Singareddypally A..P. APID 320 320


46 Thottiar Kerala KSEB 40 40
47 Athirapally Kerala KSEB 163 163
48 Mankulam Kerala KSEB 40 40
49 Achenkovil Kerala KSEB 30 30
50 Pambar Kerala KSEB 40 40
51 Gundia-I Karnataka KPCL 200 200
52 Gundia-II Karnataka KPCL 200 200
53 Shiva Samudram Seasonal Karnataka KPCL 345 345
HEP
54 Kundah PSS Tamil Nadu TNEB 500 500
55 Bhasmey Sikkim Gati Infrastructure 51 51
56 Jorethang Loop Sikkim DANS Energy 96 96
57 Rangit-IV Sikkim JAL Power 120 120
58 Teesta-VI Sikkim LANCO 500 500
59 Rangit-II Sikkim Sikkim Hydro 66 66
60 Ting Ting Sikkim TT Energy 99 99
61 Dikchu Sikkim Sneha Kinetic power 96 96
projects Ltd
62 Rongnichu Sikkim Madhya Bharat 96 96
Power Corporation
63 Tashiding Sikkim Shiga Energy 97 97
64 Panan Sikkim Himagiri 300 300
65 Teesta St.-IV Sikkim NHPC 520 520
66 Pare Ar. P NEEPCO 110 110
67 Demwe Lower Ar. P Athena Demwe 1750 1750
68 Dibbin Ar. P KSK Dibbin Hydro 120 120
Power Pvt. Ltd.
69 Siang Lower Ar. P Jaiprakash Associates 2700 1500
Ltd.
70 Nyamjunchhu Ar. P Bhilwara Energy Ltd 780 780
71 Tawang-I Ar. P NHPC 600 600
72 Tawang-II Ar. P NHPC 800 800
73 Londa(Talong) Ar. P GMR Energy Ltd. 225 225
74 Nafra Ar. P SEW 120 120
75 Tato-II Ar. P Reliance Enegy Ltd. 700 700
76 Dardu Ar. P KVK 60 60
77 Mago Chhu Ar. P SEW 96 96
78 Par Ar. P KVK 65 65
79 Rego Ar. P TUFF Energy 141 141
80 Dinchang Ar. P KSK 90 90
81 Nyukcha Rong Chhu Ar. P SEW 96 96
82 Loktak D/S Manipur NHPC 66 66
83 Lower Kopili Assam Assam GENCO 150 150
Total 23211 22011

th th
Chapter 6: Page | 114 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Annexure 6.1a
HYDRO PROJECTS IDENTIFIED FOR LIKELY BENEFITS DURING 12th PLAN

Sl. Capacity
Project Name State Developer Sector
No. (MW)
1 Pare Ar. Pradesh NEEPCO C 110
2 Kameng Ar. Pradesh NEEPCO C 600
3 Subansiri Lower Ar. Pradesh NHPC C 2000
4 Parbati-II H.P. NHPC C 800
5 Rampur H.P. SJVNL C 412
6 Kol Dam H.P. NTPC C 800
7 Kishan Ganga J&K NHPC C 330
8 Tuirial Mizoram NEEPCO C 60
Tapovan
9 Uttarakhand NTPC C 520
Vishnugad
10 Lower Jurala A.P. APGENCO S 240
11 Pulichintala A.P. APGENCO S 120
12 Kashang - I H.P. HPPCL S 65
13 Uhl-III H.P. BVPC S 100
14 Sawara Kuddu H.P. HPPCL S 111
15 Kashang II & III H.P. HPPCL S 130
16 Sainj H.P. HPPCL S 100
17 Baglihar-II J&K J&K State PDC S 450
18 Thottiar Kerala KSEB S 40
19 Pallivasal Kerala KSEB S 60
20 New Umtru Meghalaya MeECL S 40
N S L Tidong
21 Tidong-I H.P. P 100
Power Gen. Ltd
Himachal Sorang
22 Sorang H.P. P 100
Power Pvt. Ltd
Tangnu Romai
23 Tangnu Romai-I H.P. P 44
Power Gen.Ltd
Gati
24 Bhasmey Sikkim P 51
Infrastructure Ltd.
25 Jorethang Loop Sikkim DANS Pvt. Ltd P 96
Jal Power Corp.
26 Rangit-IV Sikkim P 120
Ltd.
Lanco Energy Pvt.
27 Teesta-VI Sikkim P 500
Ltd.
28 Teesta-III Sikkim Teesta Urja P 600
29 Singoli Bhatwari Uttarakhand L&T P 99
Lanco Energy Pvt.
30 Phata Byung Uttarakhand P 76
Ltd.
AHP Co. Ltd.
31 Srinagar Uttarakhand P 330
(GVK)
TOTAL (HYDRO) 9204

th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 115
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Annexure 6.2

NUCLEAR PROJECTS IDENTIFIED FOR LIKELY BENEFITS DURING 12th PLAN

CAPACITY
Sl.No. PLANT NAME STATE AGENCY SECTOR FUEL TYPE
(MW)

1 RAPP U 7 & 8 RAJ NPC C NUCLEAR 1400

2 KAPP U-3 & 4 GUJARAT NPC C NUCLEAR 1400

TOTAL NUCLEAR 2800

th th
Chapter 6: Page | 116 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Annexure 6.3

LIST OF SHELF OF COAL BASED PROJECTS FOR LIKELY BENEFITS DURING 12TH PLAN

(a) LIST OF THERMAL PROJECTS- ORDERS FOR MAIN PLANT PLACED WITH CLEARANCES IN
PLACE

S. Unit Capacity
Project Name State Developer Sector Status of Coal
No. No. (MW)
1 BONGAIGAON TPP 3 Assam NTPC C 250 Linkage
2 MAUDA TPP 1 Maharashtra NTPC C 500 Linkage
3 MAUDA TPP 2 Maharashtra NTPC C 500 Linkage
4 VINDHYACHAL ST-IV 11 MP NTPC C 500 Linkage
5 VINDHYACHAL ST-IV 12 MP NTPC C 500 Linkage
6 RIHAND-III 5 UP NTPC C 500 Linkage
7 RIHAND-III 6 UP NTPC C 500 Linkage
Muzaffarpur
8 1 Bihar NTPC JV C 195 Linkage
Ext.(Kanti TPP)
Muzaffarpur Ext.
9 2 Bihar NTPC JV C 195 Linkage
(Kanti TPP)
10 Barh STPP-I 1 Bihar NTPC C 660 Linkage
11 Barh STPP-I 2 Bihar NTPC C 660 Linkage
12 Barh STPP-I 3 Bihar NTPC C 660 Linkage
13 Sipat-I 3 Chhattisgarh NTPC C 660 Linkage
NTECL (NTPC/TNEB
14 Vallur 3 TN C 500 Linkage
JV)
15 Nabinagar TPP 1 Bihar NTPV JV C 250 Linkage
16 Nabinagar TPP 2 Bihar NTPV JV C 250 Linkage
17 Nabinagar TPP 3 Bihar NTPV JV C 250 Linkage
18 Nabinagar TPP 4 Bihar NTPV JV C 250 Linkage
19 Tuticorin JV 1 TN NPTL (NLC JV) C 500 Linkage
20 Tuticorin JV 2 TN NPTL (NLC JV) C 500 Linkage
21 Bokaro TPP A Exp 1 Jharkhand DVC C 500 Linkage
22 Korba West St.III 5 Chhattisgarh CSEB S 500 Linkage
23 SATPURA EXT 1 MP MPGENCO S 250 Linkage
24 SATPURA EXT 2 MP MPGENCO S 250 Linkage
Shree Singati TPP-I
25 1 MP MPGENCO S 600 Linkage
(Malwa)
Shree Singati TPP-I
26 2 MP MPGENCO S 600 Linkage
(Malwa)
27 ANPARA-D U 1 1 UP UPRVUNL S 500 Linkage
28 ANPARA-D U 2 2 UP UPRVUNL S 500 Linkage
29 Durgapur TPP U 8 8 WB DPL S 250 Linkage
30 D B STPS 2 Chhattisgarh M/S D.B. Power Ltd P 600 Linkage
Korba West Power
31 Avantha Bhandar TPP 1 Chhattisgarh P 600 Linkage
Company Ltd.
JHAJJAR THERMAL
32 2 Haryana China Light Power P 660 Linkage
POWER PROJECT
CORPORATE POWER
M/S Corporate
33 LTD, PH-I (MAITRISHI 1 Jharkhand P 270 Linkage
Power Ltd.
USHA TPP)
CORPORATE POWER
M/S Corporate
34 LTD, PH-I (MAITRISHI 2 Jharkhand P 270 Linkage
Power Ltd.
USHA TPP)
35 Amravati TPP-I 1 Maharashtra India Bulls P 270 Linkage
36 Amravati TPP-I 2 Maharashtra India Bulls P 270 Linkage
37 Amravati TPP-I 3 Maharashtra India Bulls P 270 Linkage
38 Amravati TPP-I 4 Maharashtra India Bulls P 270 Linkage
39 Amravati TPP-I 5 Maharashtra India Bulls P 270 Linkage
40 Nasik TPP-I 1 Maharashtra India Bulls P 270 Linkage
41 Nasik TPP-I 2 Maharashtra India Bulls P 270 Linkage
42 Nasik TPP-I 3 Maharashtra India Bulls P 270 Linkage

th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 117
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

S. Unit Capacity
Project Name State Developer Sector Status of Coal
No. No. (MW)
43 Nasik TPP-I 4 Maharashtra India Bulls P 270 Linkage
44 Nasik TPP-I 5 Maharashtra India Bulls P 270 Linkage
DHARIWAL
DHARIWAL
45 1 Maharashtra INFRASTRUCTURE P 300 Linkage
INFRASTRUCTURE TPP
(P) LTD
DHARIWAL
DHARIWAL
46 2 Maharashtra INFRASTRUCTURE P 300 Linkage
INFRASTRUCTURE TPP
(P) LTD
EMCO ENERGY LTD Linkage for 270
47 EMCO WARORA TPP 1 Maharashtra P 300
(GMR) MW
EMCO ENERGY LTD
48 EMCO WARORA TPP 2 Maharashtra P 300 Linkage
(GMR)
Bina Power SUPPLY
49 Bina TPP 2 MP P 250 Linkage
COMPANY LTD
Jindal India
50 DERANG TPP 1 Orissa P 600 Linkage
Thermal Power Ltd
Ind. Bharat power
51 Ind Bharat TPP 1 Orissa P 350 Linkage
(Utkal) Ltd.
Ind. Bharat power
52 Ind Bharat TPP 2 Orissa P 350 Linkage
(Utkal) Ltd.
53 TALWANDI SABO TPP 1 Punjab Vedanta P 660 Linkage
54 TALWANDI SABO TPP 2 Punjab Vedanta P 660 Linkage
55 TALWANDI SABO TPP 3 Punjab Vedanta P 660 Linkage
56 BARA TPP 1 UP Jaypee Power Ltd P 660 Linkage
57 BARA TPP 2 UP Jaypee Power Ltd P 660 Linkage
58 BARA TPP 3 UP Jaypee Power Ltd P 660 Linkage
59 ROSA TPP PH-II 3 UP RELIANCE POWER P 300 Linkage
60 ROSA TPP PH-II 4 UP RELIANCE POWER P 300 Linkage
Linkage for 660
61 Nabha ( Rajpura TPP) 1 Punjab Nabha Power Ltd. P 700
MW
Linkage for 660
62 Nabha ( Rajpura TPP) 2 Punjab Nabha Power Ltd. P 700
MW
63 Seoni TPP (Jhabua ) 1 MP Jhabua Power P 600 Linkage
64 Nasik TPP-II 1 Maharashtra India Bulls P 270 Linkage
65 Nasik TPP-II 2 Maharashtra India Bulls P 270 Linkage
66 Nasik TPP-II 3 Maharashtra India Bulls P 270 Linkage
67 Nasik TPP-II 4 Maharashtra India Bulls P 270 Linkage
68 Nasik TPP-II 5 Maharashtra India Bulls P 270 Linkage
69 Amravati TPP-II 1 Maharashtra India Bulls P 270 Linkage
70 Amravati TPP-II 2 Maharashtra India Bulls P 270 Linkage
71 Amravati TPP-II 3 Maharashtra India Bulls P 270 Linkage
72 Amravati TPP-II 4 Maharashtra India Bulls P 270 Linkage
73 Amravati TPP-II 5 Maharashtra India Bulls P 270 Linkage
74 Vizag Hinduja TPP 1 A.P HNPCL P 520 Linkage
75 Vizag Hinduja TPP 2 A.P HNPCL P 520 Linkage
Lanco Babandh
76 Lanco Babandh 1 Orissa P 600 Linkage
Power
MB Power
77 Annoppur TPP-I 1 M.P (Madhya Pradesh) P 600 Linkage
Ltd.
MB Power
78 Annoppur TPP-I 2 M.P (Madhya Pradesh) P 600 Linkage
Ltd.
M/s Vidarbha
79 Butibori TPP Ph -II 1 Maharashtra Industries Power P 300 Linkage
Ltd
K.V.K. Nilachal
80 K.V.K. Nilachal TPP 1 Orissa P 525 Linkage
Power Pvt. Ltd.
K.V.K. Nilachal
81 K.V.K. Nilachal TPP 2 Orissa P 525 Linkage
Power Pvt. Ltd.
M.s Athena
Athena Chattisgarh
82 1 Chhatisgarh Chattisgarh Power P 660 Linkage
Power Pvt. Ltd.
Pvt. Ltd.

th th
Chapter 6: Page | 118 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

S. Unit Capacity
Project Name State Developer Sector Status of Coal
No. No. (MW)
SKS Power
83 Darrampura TPP 1 Chhatisgarh P 300 Linkage
Generation Ltd.
SKS Power
84 Darrampura TPP 2 Chhatisgarh P 300 Linkage
Generation Ltd.
SKS Power
85 Darrampura TPP 3 Chhatisgarh P 300 Linkage
Generation Ltd.
SKS Power
86 Darrampura TPP 4 Chhatisgarh P 300 Linkage
Generation Ltd.
87 Lanco Vidarbha TPP 1 Maharashtra Lanco Vidarbha P 660 Linkage
88 Lanco Vidarbha TPP 2 Maharashtra Lanco Vidarbha P 660 Linkage
D.B. Power 2x660, M/s D.B. Power , Linkage for 660
89 1 MP P 660
Sidhi Sidhi MW
Maurti Clean Coal & M/s Maurti Clean
90 1 Chhattisgarh P 300 Linkage
Power TPP Coal & Power Ltd.
91 Lanco Amarkantak 3 Chhattisgarh LAP Pvt Ltd P 660 Linkage
92 Lanco Amarkantak 4 Chhattisgarh LAP Pvt Ltd P 660 Linkage
500 MW- Tapering
R.K.M. POWERGEN
93 Uchpinda TPP 1 Chhattisgarh P 360 linkage/Coal Block
PVT LTD
, 900 MW - Linkage
500 MW- Tapering
R.K.M. POWERGEN
94 Uchpinda TPP 2 Chhattisgarh P 360 linkage/Coal Block
PVT LTD
, 900 MW - Linkage
500 MW- Tapering
R.K.M. POWERGEN
95 Uchpinda TPP 3 Chhattisgarh P 360 linkage/Coal Block
PVT LTD
, 900 MW - Linkage
500 MW- Tapering
R.K.M. POWERGEN
96 Uchpinda TPP 4 Chhattisgarh P 360 linkage/Coal Block
PVT LTD
, 900 MW - Linkage
Linkage for 500
MW; Block /
97 Kamalanga TPP 1 Orissa GMR Energy P 350
tapering linkage
for 550 MW
Linkage for 500
MW; Block /
98 Kamalanga TPP 2 Orissa GMR Energy P 350
tapering linkage
for 550 MW
Linkage for 500
MW; Block /
99 Kamalanga TPP 3 Orissa GMR Energy P 350
tapering linkage
for 550 MW
Linkage for 520
100 TIRODA TPP PH-I 2 Maharashtra ADANI POWER P 660 MW & Block for
140 MW
Adhunik Power &
101 Adhunik Power TPP 1 Jharkhand Natural Resources P 270 Block
Ltd.
102 Barh STPP-II 1 Bihar NTPC C 660 Block
103 Barh STPP-II 2 Bihar NTPC C 660 Block
104 Kakatiya TPP ST -II 1 AP APGENCO S 600 Block
105 Chandrapur Ext. 8 Maharashtra MAHGENCO S 500 Block
106 Chandrapur Ext. 9 Maharashtra MAHGENCO S 500 Block
107 Koradi TPP EXT 8 Maharashtra MAHGENCO S 660 Block
108 Koradi TPP EXT 9 Maharashtra MAHGENCO S 660 Block
109 Koradi TPP EXT 10 Maharashtra MAHGENCO S 660 Block
110 Sasan UMPP 1 MP Reliance Power Ltd. P 660 Block
111 Sasan UMPP 2 MP Reliance Power Ltd. P 660 Block
112 Sasan UMPP 3 MP Reliance Power Ltd. P 660 Block
113 Sasan UMPP 4 MP Reliance Power Ltd. P 660 Block
114 Sasan UMPP 5 MP Reliance Power Ltd. P 660 Block
115 Sasan UMPP 6 MP Reliance Power Ltd. P 660 Block
Jindal India
116 DERANG TPP 2 Orissa P 600 Block
Thermal Power Ltd
Akaltara (Nariyara)
117 4 Chhattisgarh Wardha PCL (KSK) P 600 Block
TPP

th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 119
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

S. Unit Capacity
Project Name State Developer Sector Status of Coal
No. No. (MW)
Coal Block/
118 Vandana Vidyut TPP 2 Chattisgarh Vandana Vidyut P 135
Tapering Linkage
119 Tiroda TPP-II 1 Maharashtra Adani Power P 660 Block
120 Goindwal Sahib TPP 1 Punjab GVK Power P 270 Block
121 Goindwal Sahib TPP 2 Punjab GVK Power P 270 Block
D B STPS- M/S D.B. Power Coal Block/
122 1 Chhattisgarh P 600
CHHATTISGARH Ltd. Tapering Linkage
Coal Block/
123 Parli TPP Ext 8 Maharashtra MAHGENCO S 250
Tapering Linkage
Coal Block (A)/
Tapering Linkage
Akaltara (Nariyara)
124 1 Chhattisgarh Wardha PCL (KSK) P 600 (LOA for tapering
TPP
to 3x600 MW
granted by SECL)
Coal Block (A)/
Tapering Linkage
Akaltara (Nariyara)
125 2 Chhattisgarh Wardha PCL (KSK) P 600 (LOA for tapering
TPP
to 3x600 MW
granted by SECL)
Coal Block (A)/
Tapering Linkage
Akaltara (Nariyara)
126 3 Chhattisgarh Wardha PCL (KSK) P 600 (LOA for tapering
TPP
to 3x600 MW
granted by SECL)
Coal Block/
127 Marwah TPP 1 Chhattisgarh CSEB S 500 Tapering Linkage
(A)
Coal Block/
128 Marwah TPP. 2 Chhattisgarh CSEB S 500 Tapering Linkage
(A)
Coal Block/
129 Kalisindh TPS. 1 Rajasthan RRVUNL S 600 Tapering Linkage
(A)
130 Kalisindh TPS 2 Rajasthan RRVUNL S 600 Block (A)
Coal Block/
131 Chhabra TPS Ext. 3 Rajasthan RRVUNL S 250 Tapering Linkage
(A)
Coal Block/
132 Chhabra TPS Ext. 4 Rajasthan RRVUNL S 250 Tapering Linkage
(A)
Jaypee Power
133 NIGRIE TPP 1 MP P 660 Block (A)
Ventures Ltd
Jaypee Power
134 NIGRIE TPP 2 MP P 660 Block (A)
Ventures Ltd
135 Mahan TPP 1 MP Essar Power P 600 Block (A)
136 Mahan TPP 2 MP Essar Power P 600 Block (A)
137 Malibrahmani TPP Orissa Monet Power P 525 Block
Adhunik Power &
Block/Tapering
138 Adhunik TPP 2 Jharkhand Natural Resources P 270
Linkage
Ltd
Athena Chattisgarh Athena Chattisgarh
139 2 Chhatisgarh P 660 Block
Power Pvt. Ltd.2x660 Power Pvt. Ltd.
COASTAL ENERGEN Imported Coal/
140 Melamaruthur TPP 1 TN P 600
PVT LTD Linkage ( 70:30)
COASTAL ENERGEN Imported Coal/
141 Melamaruthur TPP 2 TN P 600
PVT LTD Linkage ( 70:30)
Sri Damodaram Linkage based on
142 Sanjeevaiah TPP 1 AP APGENCO S 800 70:30
(Krishnapattam TPP) Domestic:Imported
Sri Damodaram Linkage based on
143 Sanjeevaiah TPP 2 AP APGENCO S 800 70:30
(Krishnapattam TPP) Domestic:Imported

th th
Chapter 6: Page | 120 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

S. Unit Capacity
Project Name State Developer Sector Status of Coal
No. No. (MW)
Linkage based on
Thamminapatnam Meenakshi Energy
144 3 AP P 300 70:30
TPP-II Pvt. Ltd.
Domestic:Imported
Linkage based on
Thamminapatnam Meenakshi Energy
145 4 AP P 300 70:30
TPP-II Pvt. Ltd.,
Domestic:Imported
Linkage based on
East Coast Energy
146 Bhavanpadu TPP 1 AP P 660 70:30
Pvt. Ltd.
Domestic:Imported
Linkage based on
M/s. East Coast
147 Bhavanpadu TPP 2 AP P 660 70:30
Energy Pvt. Ltd.
Domestic:Imported
Linkage based on
Thermal Powertech
148 Painampuram TPP 1 AP P 660 70:30
Corporation Ltd.
Domestic:Imported
Linkage based on
Thermal Powertech
149 Painampuram TPP 2 AP P 660 70:30
Corporation Ltd.
Domestic:Imported
Linkage based on
150 Ind Barath TPP 1 TN Ind Barath Power P 660 70:30
Domestic:Imported
151 Sikka TPP Ext. 3 Gujarat GSECL S 250 Imported Coal
152 Sikka TPP Ext. 4 Gujarat GSECL S 250 Imported Coal
Madhucon projects
153 Simhapuri TPP Ph-II 1 AP Ltd (Simhapuri P 150 Imported Coal
Energy pvt. Ltd)
Madhucon projects
154 Simhapuri TPP Ph-II 2 AP Ltd (Simhapuri P 150 Imported Coal
Energy pvt. Ltd)
Linkage based on
155 MUNDRA TPP PH-III 2,3 Gujarat ADANI POWER P 1320 70:30
Domestic:Imported
The Tata Power
156 Mundra UMPP 2 Gujarat P 800 Imported Coal
Company Ltd
The Tata Power
157 Mundra UMPP 3 Gujarat P 800 Imported Coal
Company Ltd
The Tata Power
158 Mundra UMPP 4 Gujarat P 800 Imported Coal
Company Ltd
The Tata Power
159 Mundra UMPP 5 Gujarat P 800 Imported Coal
Company Ltd
TOTAL (COAL) 75650

(b) Projects having coal tied up but order for Main Plant yet to be placed

Sl. Name State Sector Capacity (MW)


No
1 Aparna Infraenergy Maharashtra P 250
2 Jinbhuvish Power Generation Maharashtra P 500
Power Ltd.-2x250
3 Central India Power Co. Ltd. Maharashtra P 660
4 NSL Power Pvt. Ltd. Tamil Nadu P 1320
5 BPL Power Projects(AP) Limited Andhra Pradesh P 600
6 PEL Power Ltd. Tirumalai TPP Tamil Nadu P 500
7 PEL Power Ltd. Tirumalai TPP Gujarat P 500
8 Gupta Energy Ltd. Maharashtra P 540
9 TPP of M/s Videocon Industries Chhattisgarh P 660
Ltd.
10 Dheeru Power Gen Pvt. Ltd. Chhattisgarh P 1050

th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 121
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Sl. Name State Sector Capacity (MW)


No
11 Haldia TPP West Bengal P 600
12 Rayalseema U-6 , APGENCO A.P S 600
13 Obra Extn U-1, UPRVUNL UP S 660
14 Tilaiya UMPP Reliance Power Jharkhand P 3960
Ltd. 6x660
15 Ib TPS Phase-II by M/s OPGC Orissa S 1320
Total 13720

(c) PROJECTS WHERE ORDER FOR MAIN PLANT PLACED BUT CERTAIN CLEARANCES
AWAITED

Capacity
S.No. Name Agency State Sector
(MW)
1 Raigarh TPP JINDAL POWER Chhattisgarh P 2400
2 Karchana TPP JP U.P. P 1980
TRN Energy Private
3 TRN Energy TPP Chhattisgarh P 600
Limited
4 Malibramani TPP U-2 Monnet Power Orissa P 525
Navabharat Power Pvt.
5 Navabharat Power Pvt. Ltd. Orissa P 1050
Ltd.
Nagarjuna Construction Nagarjuna Construction
6 A.P. P 1320
Company Ltd. Phase-I Company Ltd.
7 Krishnapatnam UMPP Unit-1-6 Reliance Power Ltd. A.P. P 3960
8 Yermarus TPP RPCL (JV of KPCL & BHEL) Karnataka S 1600
9 Edlapur TPP RPCL (JV of KPCL & BHEL) Karnataka S 800
10 Bellary Unit-3 KPCL Karnataka S 700
11 Sagardighi WBPDCL W.B. S 1000
12 Barauni TPP BSEB Bihar S 500
Raigarh TPP (600 MW+660
13 Visa Chhattisgarh P 1260
MW)
14 Lalitpur TPP Hindustan Bajaj U.P. P 1980
15 Avantha Bhandar TPP U 2 KWPCL Chhattisgarh P 600
16 Corporate Power TPP Phase-II AINL Jharkhand P 540
17 Raikheda TPP (2x685 MW) GMR P 1370
18 Pipavav TPP Pipavav Energy Pvt. Ltd. Gujarat P 600
19 Lanco Babandh TPP U-2 Lanco Babandh Orissa P 660
20 Tori TPP Essar Power Jharkhand P 1200
Akaltara ( Nariyara) TPP KSK Mahanadi Power
21 Chhattisgarh P 1200
Unit 5&6 Company Ltd
22 DB Power Sidhi U-2 DB Power M.P. P 660
Total 26505

th th
Chapter 6: Page | 122 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

(d) List of Projects proposed under Bulk Tendering

Capacity Status of
S.No. Name of Project Unit No. State Agency Sector
(MW) Coal
1 MEJA JV 1 UP NTPC JV C 660 Linkage
2 MEJA JV 2 UP NTPC JV C 660 Linkage
3 NEW NABINAGAR 1 BIHAR NTPC JV C 660 Linkage
4 NEW NABINAGAR 2 BIHAR NTPC JV C 660 Linkage
5 NEW NABINAGAR 3 BIHAR NTPC JV C 660 Linkage
6 SOLAPUR 1 MAHARASHTRA NTPC C 660 Linkage
7 SOLAPUR 2 MAHARASHTRA NTPC C 660 Linkage
8 MAUDA-II 1 MAHARASHTRA NTPC C 660 Linkage
9 MAUDA-II 2 MAHARASHTRA NTPC C 660 Linkage
10 RAGHUNATHPUR 1 JHARKHAND DVC C 660 Linkage
11 RAGHUNATHPUR 2 JHARKHAND DVC C 660 Linkage
Total 7260

(e) Thermal Projects under Planning by NHDC (Central Sector)

Capacity
S.No. Name of Project Unit No. State Agency Sector
(MW)
Reva Thermal Power NHDC
1 1&2 M.P. C 1320
Project Ltd
Total 1320

th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 123
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Annexure 6.4

LIST OF GAS BASED STATIONS FOR 12th PLAN


FOR WHICH GAS HAS BEEN TIED UP FROM LOCAL SOURCES

S.No. Name of Power Station Capacity Located in Present Status/likely


/Agency (MW) State commissioning
STATE SECTOR
1 Ramgarh CCGT 160 Rajasthan Under construction.
2013-14
2 Namrup CCGT 100 Assam Under construction.
2013-14
Sub Total (S.S.) 260
CENTRAL SECTOR
1 Tripura Gas 726 Tripura Under construction.
2012-13
2 Monarchak 100 Tripura Under construction.
2013-14
Sub Total (C.S.) 826
Total ((All India) 1086

SHELF OF GAS BASED PROJECTS UNDER CONSTRUCTION

Name of Power Capacity Located in Present Status/likely


S.No.
Station /Agency (MW) State commissioning **
STATE SECTOR
Under construction. Expected in
1 Bawana CCGT * 1000 Delhi
2012-13
Commissioned in Feb,12 (11th
2 GSEG Hazira CCGT 351 Gujarat Plan). Awaiting gas supply for
commercial operation
Block-I 351 MW by March,12 &
3 Pipavav JV CCGT 702 Gujarat
Block-II – 351MW in 2012-13
Sub Total (S.S.) 2053
Private Sector
Ready for commissioning. Awaiting
4 Vemagiri exp by GREL 768 A.P.
gas supply
Lanco Kondapalli Exp Ready for commissioning. Awaiting
5 770 A.P.
(St-III) gas supply
Kashipur CCGT Ready for commissioning. Awaiting
Uttarakha
6 (Sravanti Energy P Ltd) 450 gas supply
nd
Phase I&II
7 Samalkot Expansion 2400 A.P. Under construction. 2012-13
Under construction. Due to
uncertainty in allocation of gas, the
8 Jegrupadu Exp. (St-III)I 400 A.P. construction activity at site has
been put on hold. Sub-ordering and
manufacturing activities have also

th th
Chapter 6: Page | 124 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Name of Power Capacity Located in Present Status/likely


S.No.
Station /Agency (MW) State commissioning **
been tapered down.
Under construction. Due to
uncertainty in allocation of gas, the
construction activity at site has
9 Gautami St-II (Phase-I) 800 A.P.
been put on hold. Sub-ordering and
manufacturing activities have also
been tapered down.
CCGT by M/s Under construction. 2012-13
10 PSPL(Pandu Ranga) - 110 A.P.
Ph-I
RVK (Rajahmundry) Under construction. 2013-14
11 436 A.P.
Private Ltd.
Sugen Phase-I Unit -4 Under construction. 2012-13
12 382.5 Gujarat
M/s Torrent
Dahej SEZ (Torrent) 3 Under construction. 2013-14
13 1200 Gujarat
Modules
CCGT by M/s Beta Uttarakha Under construction. 2012-13
14 225
Infratech Private Ltd nd
CCGT by M/s Gama Uttarakha Under construction. 2012-13
15 225
Infratech Pvt Ltd nd
CCPP by M/s Guruji Uttarakha Under construction. 2013-14
16 110
Power Pvt Ltd (GPPL) nd
Latur CCPP by Hecate Maharasht Under construction. 2013-14
19 800
Power Systems P Ltd. ra
CCPP by M/s H Energy Maharasht Under construction. 2013-14
20 350
Co. Pvt. Ltd. ra
CCGT by M/s Pioneer Maharasht Under construction. 2013-14
21 400
Gas Power Ltd ra
CCGT by M/s KPR Under construction. 2013-14
22 225 AP
Chemicals Ltd.
PPN Expansion by PPN Under construction. 2013-14
Tamil
23 Power Generation Co 1080
Nadu
Ltd
Sub Total (Pvt Sector) 11131.5
TOTAL (SS+PS) 13184.5

* Total capacity of the project is 1500 MW(500 MW of Bawana project has already been commissioned)
** Commissioning subject to availability of gas

th th
Generation Capacity Addition Programme for 12 & 13 Plan Chapter 6: Page | 125
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

th th
Chapter 6: Page | 126 Generation Capacity Addition Programme for 12 & 13 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 7
OPTIMIZATION OF LAND AND WATER REQUIREMENTS FOR
THERMAL POWER PLANTS

7.0 INTRODUCTION
7.1 LAND REQUIREMENT
Large capacity addition is envisaged in the
country during the 12th Plan and beyond. Land requirement for a coal based plant
As per projections of Integrated Energy depends upon a number of factors such as
Policy, about 15,000 MW thermal capacity capacity of the plant & unit size adopted,
is to be added every year over next two quality of coal & its storage requirement,
decades. This requires installation of large type of CW system adopted, source of raw
number of coal and gas based plants. To water & its storage requirement and plant
achieve faster capacity addition targets, design aspects. For coal based plants,
large capacity plants including 4,000 MW land is basically required for main plant
size Ultra Mega power plants(UMPPs) systems/ equipment, ash dyke, pipe
using 660/800 MW supercritical units have corridors (for ash and raw water) and
been envisaged for installation at township. Plants based on imported coal
different sites mainly at pithead and require less land as compared to those
coastal locations. Availability of adequate based on indigenous coal on account of
land and water are key requirements for considerably reduced requirement for
installation of a thermal power plant. ESP, coal handling system, ash handling
system and ash dyke. Type of CW system
In the past, because of comparatively viz. open cycle or cooling tower system
slow pace of capacity addition, availability also has a significant impact on land
of adequate land was not a big constraint requirement of the plant.
and plants could be located as per other
applicable criteria viz. availability of coal Land requirement for ash dyke varies over
and water. However, since expansion of wide range depending upon quality of
power sector has been taken up in a big coal, method of ash disposal and
way, availability of land has become a utilization of fly ash. Fly ash and bottom
constraint and is posing a big challenge ash were earlier conventionally disposed
for currently planned and future plants. off to ash pond in the form of lean slurry
Land has become premium resource and requiring large pond area. However, with
its acquisition has also become difficult on increased concentration of wet slurry
account of other competing sectors and upto 25% and use of other techniques such
opposition of local population. In this as HCSD (High concentration slurry
background, optimum utilisation of land disposal) and dry fly ash disposal, the land
has gained significance so that maximum required for ash dyke has considerably
plant capacity could be installed on the reduced. MOEF’s stipulation for
available land. progressive utilization of fly ash upto 100%
Optimization of Land and Water Requirements For Thermal Power Plants Chapter 7: Page | 127
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

within a given time frame has reduced the large capacity plants with large size units
quantum of ash to be disposed off to ash are required to be installed to achieve the
dyke. Use of washed coal and blending of intended high capacity targets, CEA had
imported coal with indigenous coal has set up a committee in April, 2007 to go
also resulted in reduced land required for into the aspect of land requirement for
ash dyke. New plants based on imported thermal plants and suggest minimum land
coal would be requiring least land for ash requirement for various size plants. The
dyke. Committee submitted its report in
December 2007 and has analysed land
7.1.1 Committee for Optimisation of Land requirement aspects for various sizes &
Requirement combinations of the plants viz. indigenous
coal/imported coal, open cycle/closed
In view of large capacity addition cycle CW system. The committee has
proposed to be based on coal based recommended the land requirement as
plants, need had been felt to optimize the indicated in Table 7.1 & 2 below:
land requirement for thermal plants. As

Table 7.1
Indigenous Coal (Pithead Stations)

Sl. Description Land requirement ( acres)


N. (acre/MW)
2x500MW 3x660M 6x660M 5x800M
W W W
i) Main power plant 600 850 1250 1170
(0.6) (0.43) (0.32) (0.29)
ii) Ash dyke 500 855 1630 1200
iii) Other facilities (pipe corridors 220 245 250 250
& raw water pump house
etc.)

iv) Township 100 100 150 150

Total land requirement 1420 2050 3280 2770


(acres)

(acres/MW) (1.42) (1.04) (0.83) (0.69)

Chapter 7: Page | 128 Optimization of Land and Water Requirements for Thermal Power Plants
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Table 7.2
Imported Coal (Coastal Stations)

Sl. Description Land requirement ( acres)


N. (acre/MW)
3x660MW 6x660MW 5x800MW
Without With Without With Without With
MGR & MGR & MGR & MGR & MGR & MGR &
without with without with without with
cooling cooling cooling cooling cooling cooling
tower tower tower tower tower tower
i) Main power 400 570 630 880 570 840
plant (0.2) (0.29) (0.16) (0.22) (0.14) (0.21)
ii) Ash dyke 240 240 400 400 390 390
iii) Other facilities 100 140 110 150 110 150
(pipe corridors
& raw water
pump house
etc.)
iv) Township 100 100 150 150 150 150
Total land 840 1050 1290 1580 1220 1530
requirement
(acres)
(acres/MW) (0.42) (0.53) (0.33) (0.4) (0.3) (0.38)

The Committee has suggested that round development in the country and
further reduction in land requirement is vast growth of thermal power stations,
possible for ash dyke and the colony. The the availability of water has become
land requirement could also be reduced scarce. As drinking and irrigation uses
considerably by setting up of integrated have got priority in allocation of water
projects for fly ash utilization, compact over industrial use and power generation,
design of the plant and adopting multi the thermal power plants are facing
storey concept of the township. constraints in availability of adequate
fresh water. Judicious utilization of water
7.2 WATER OPTIMIZATION TECHNOLOGIES and recycling of plant waste water in
IN THERMAL POWER PLANTS thermal plants has become important so
as to reduce net drawal from the source
7.2.1 Introduction water body to bare minimum.

Water is one of the key inputs for thermal Large coal based capacity is required to be
power generation. Historically, thermal added during 12th Plan and beyond at the
power plants were located near water pace of about 15000 MW per year as per
bodies and adequate quantity of water the projections of Integrated Energy
was assured on sustained basis. With all Policy. This requires large number of new

Optimization of Land and Water Requirements For Thermal Power Plants Chapter 7: Page | 129
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

sites for setting up coal based power water is treated in clarification plant to
stations. Primary criteria for deciding produce clarified water which is used for
selection of sites is availability of land and clarified water applications such as
water. Much of the new capacity is cooling tower make up & service water
envisaged near pit-head due to economics etc. and as input water for DM plant &
of coal transportation and in coastal potable water system. The scheme of DM
regions. Difficulties are already being plant typically consist of pressure filters,
faced in selection of new sites due to non- cation exchanger, degasser, anion
availability of water, particularly in coal exchanger and mixed bed polisher. The
bearing states like Orissa, Jharkhand and scheme of potable water system consist
Chhatisgarh where large number of sites of filtration, chlorine dosing and any other
have been identified. Difficulties are also treatment as required to make water fit
being faced in finding coastal sites for drinking. The waste water generated
particularly on west coast. This problem is in various treatment sections (clarifier
expected to be aggravated in future when sludge, filter back wash and regeneration
more sites would be required. Thus there waste of DM plant etc.) is suitably
is a need to minimise water requirement recycled and reused with or without
in water scarce regions to enhance the treatment to the extent possible.
siting options for thermal power plants.
7.2.3 Water Requirement
7.2.2 Plant Water System
In a thermal power plant, bulk of the
The plant water system including cooling water is required for make up to the
water system depends upon source of condenser cooling water system and for
raw water. Cooling water system may be wet ash disposal. Other water
of once through type or closed cycle open requirements include power cycle make
recirculating type using cooling tower. For up, service and potable uses, coal dust
all inland plants based on fresh water suppression etc. The cooling tower blow
sources such as river, canal, lake, and down is used for disposal of ash.
reservoir, it is now mandatory to install
closed cycle cooling system employing Plant water requirement is governed by a
cooling towers. Open cycle cooling system number of factors such as quality of raw
is permitted only in coastal regions. Sea water, type of condenser cooling system,
water based cooling towers are also quality of coal, type of ash disposal
adopted at coastal sites depending upon system, waste water management
techno-economic considerations. aspects. Consumptive water requirement
for a typical 1000MW capacity plant with
The raw water input to the plant needs to different modes of ash handling system is
be treated to make it suitable for use in indicated in Table 7.3 below:
various plant applications. Typically, raw

Chapter 7: Page | 130 Optimization of Land and Water Requirements for Thermal Power Plants
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Table 7.3

Sl. Type of ash handling system COC** of Plant water


No. Fly ash Bottom ash CW system consumption (m3/h)

1 Normal mode – Dry Wet 5.0 2900*

Emergency – Wet

2 Normal mode– Dry Wet 5.0 2850

Emergency – HCSD***

* During initial period of plant operation till adequate utilization of fly ash is achieved, wet mode shall be
used for disposal of fly ash and additional requirement of water during this period shall be about 600 m3/h
over that indicated above.
** Cycle of Concentration
*** High Concentration Slurry Disposal

The requirement of plant consumptive plant waster water is also governed by


water can further be reduced by adopting stipulation of MOEF and CPCB/ SPCB in
technologies which facilitate in minimizing this regard. In some recent projects,
requirement of water. MOEF has stipulated the requirement of
zero effluent discharge from plant
7.2.4 Plant Water Optimization boundary which has a great bearing on
Technologies plant water scheme and treatment of
waste water to be adopted.
There has been continued endeavour for Technologies/measures that can be
optimization of plant water system in adopted for optimization of the water
thermal power plants on account of water required for thermal plants are described
scarcity and reducing allocation of water below:
for thermal generation. Over a period of
time in the past, plant water requirement 7.2.4.1 Cooling Water System
has been optimized by judicious utilization
of water for various applications, Cooling water system is provided to
adequate treatment for deteriorating of remove the waste heat in condenser and
quality of raw water, adoption of reduced plate heat exchangers of boiler and
margins in various consumptive uses and turbine auxiliaries. Cooling towers
use of plant waste waters in various low involve evaporation of water and require
grade applications. Further optimization blow down to limit the build up of
in plant water requirement has been dissolved salts in the circulating water.
achieved by adopting techniques aimed at Make up water is added to cooling water
reducing consumptive requirement of system to compensate for loss of water
various applications and recycling of plant due to evaporation, drift and blow down.
waste waters to maximum extent. The
requirement and scheme for utilization of
Optimization of Land and Water Requirements For Thermal Power Plants Chapter 7: Page | 131
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Dry cooling systems which do not involve atmosphere by cooling in finned tubes by
evaporation of water, thus not requiring air. Unlike wet cooling systems which
any make up water for condenser cooling operate with respect to ambient wet bulb
system can also be used for reduction of temperature and involve both sensible
plant consumptive water to a large and latent heat transfer, dry cooling
extent. systems operate with respect to ambient
dry bulb temperature and involve only
7.2.4.2 Optimisation in wet cooling system sensible cooling. Large surface area of
finned tubes is required for heat exchange
Wet cooling towers require make up in dry cooling system. The turbine back
water, the quantum of which depends pressure achievable in dry cooling system
upon cycle of concentration (COC) that is considerably higher than in wet cooling
can be maintained in the CW system. The system on account low heat transfer
COC to be adopted in the CW system coefficient and operation with respect to
primarily depends upon quality of make dry bulb temperature. Dry cooling
up water. Present practice is to use systems can be broadly classified in
clarified water as make up to the cooling following two categories :-
tower and operate the CW system at COC
of 5.0 with suitable chemical dosing so as a) Direct dry cooling systems
to optimize the plant water requirement. b) Indirect dry cooling systems.
This requires CT make up water of
typically 2 % of CW flow, and blow down In direct dry cooling system, steam
water to be effected from CW system exhaust from LP turbine is directly cooled
amounts to 0.35 % of the CW flow. in a system of finned tubes by ambient air
using mechanical draft fans. To reduce
The water for ash handling plant is tapped pressure drop in steam conveying system,
from available blow down water. In case, these units called air cooled condenser
requirement of ash handling plant is less (ACC) need to be installed close to the
than available blow down water from CW turbine hall. The finned tubes are
system, the balance blow down is led to generally arranged in the form of an ‘A’
the CMB of the plant. If water frame or delta over forced draft fans to
requirement of ash handling plant gets reduce the land area requirement.
further reduced viz. by adoption of dry
ash handling, recycling of ash pond water In an indirect dry cooling system, turbine
etc., there shall be increase in blow down exhaust steam is cooled by water in a
water to be disposed off to the CMB. The condenser which can be of surface type or
quantum of blow down water can be direct contact type and hot water is
reduced by increasing the COC of CW cooled by air in finned tube bundles
system which can be achieved by suitably utilizing natural draft tower. Because of
improving the chemical regime of water piping involved, these air cooled
circulating water. units can be located away from the main
plant. Heat exchanger elements are
7.2.4.3 Dry cooling system vertically arranged at base of the tower
Dry cooling systems refer to rejection of along its periphery with cooling taking
power cycle waste heat directly to the

Chapter 7: Page | 132 Optimization of Land and Water Requirements for Thermal Power Plants
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

place by air drawn by buoyancy of hot air system. Fly ash and bottom ash is
inside the tower shell. discharged to low lying ash pond in the
form of a lean slurry. As per requirement
Dry cooling technologies have higher of MOEF, ash pond water is to recovered
equipment cost and result in reduced and reused in ash handling system to
power output of the unit due to high conserve the water. Typically, 70% water
condenser back pressure leading to high can be recovered from the ash pond and
turbine cycle heat rate. However, these reused in ash handling plant. Thus,
technologies provide an option of locating requirement of water to be supplied to
the thermal plants in water scarce the ash handling plant from plant water
regions. There are considerable number of system gets reduced to this extent.
dry cooling installations including for large
size units (≥ 600 MW) operating in 7.2.5.2 Dry ash disposal
different parts of the world. In India, some
small size combined cycle plants, captive Wet ash disposal results in contamination
power plants and industrial units have of ground water on account of seepage
also provided with air cooled condensers. from ash pond, and areas surrounding the
pond are under threat for possible breach
In order to explore the possibility of of ash bund. Dry ash disposal overcomes
reducing the plant consumptive water these issues besides reduction in
requirement by application of dry cooling consumptive water and facilitates
system for condenser cooling in thermal utilization of fly ash in cement plants,
power plants, CEA, has set up a building material, landfill, embankments
committee with members drawn from etc. With progressive increase in
NTPC, BHEL, RRVUNL, MAHAGENCO, utilization in fly ash, the wet disposal of
CESC and TCE to examine the issue of dry ash is getting reduced. The plant water is
cooling system for condensers in thermal required only for wet disposal of bottom
power plants. The committee is expected ash which is about 20% of total ash
to suggest available options of dry cooling generation and part of fly ash which is not
systems for thermal power plants keeping disposed off in dry form.
in view various techno- economic aspects
involved. 7.2.5.3 Dry bottom ash handling

7.2.5 Ash Handling System Bottom ash is conventionally handled in


water impounded hoppers and then
Various technologies/measures that can grinded in clinker grinders for subsequent
be adopted for minimizing the disposal to ash pond alongwith fly ash in
requirement of water for ash handling the form of lean slurry. Semi- dry method
system are described below: using hydro- bins have also been used in
some of the power plants. To conserve
7.2.5.1 Recovery and reuse of ash water, bottom ash can be disposed in dry
water form also. Technologies are available for
dry extraction, cooling and conveying of
Thermal power plants have conventionally bottom ash from pulverized coal fired
been provided with wet ash disposal boilers. In India, this technology is being

Optimization of Land and Water Requirements For Thermal Power Plants Chapter 7: Page | 133
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

used in one thermal power plant with unit DM plant & condensate polishing plant
size of 300 MW. etc. An optimized plant water scheme
requires that sludge water and filter back
7.2.5.4 High concentration slurry disposal wash water are recycled to pre treatment
(HCSD) system plant and other waste waters are utilized
to maximum extent in low grade
As the name suggests, HCSD refers to applications. The unutilized waste has
disposal of fly ash from coal fired thermal high TDS on account of CT blow down and
power plant to ash disposal area in the regeneration waste. If water is to be
form of high concentration slurry. The recovered from this waste water for
process is environmental friendly and recycling in the plant, its treatment would
involves pumping of high solids require application of reverse osmosis
concentration slurry with more than 60% technology to have maximum recovery of
solids by weight employing positive water and minimum quantity of
displacement pumps as compared to lean concentrated brine reject.
slurry transportation at about 20%
concentration. The slurry forms a natural 7.3 WATER SAVING
slope on the disposal area without need
for mechanical spreading and with As can be seen from above that various
minimal release of water and generates a possibilities exist for reduction of plant
stable and dry landfill. The water water consumption which need to be
consumption of HCSD system is lower by a applied on case to case basis. For plants
factor of about 6 as compared to water with wet cooling towers, water reduction
requirement by lean slurry disposal. can typically be achieved in an optimum
However, if recovery of water from ash manner by operating the CW system at a
pond is taken into consideration, there practically possible higher COC, recycling
may not be very substantial saving in of clarifier sludge water & filter back wash
water consumption as compared to wet in pre treatment plant, reduced
disposal method. consumption in ash handling plant and
maximum utilization of waste water.
7.2.6 Minimising Effluent Discharge These measures can result in plant water
saving of about 20%. If dry cooling system
Waste waters generated in a typical is adopted in combination with dry
thermal power plant include clarifier handling of ash, plant water consumption
sludge, filter back wash, CT blow down, can be reduced by about 80- 85%.
boiler blow down, regeneration waste of

----+++----

Chapter 7: Page | 134 Optimization of Land and Water Requirements for Thermal Power Plants
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 8
LOW CARBON GROWTH STRATEGY FOR INDIAN POWER SECTOR FOR 12th &
13th FIVE YEAR PLANS

8.0 INTRODUCTION economic development of the country


and better standard of living of the
Power is one of the most essential people.
infrastructural requirements for the
overall development of the country’s Besides its importance in the growth of
economy. All the industries are heavily the country’s economy, it plays a major
dependent for their successful operation role in the life of a common man and has a
on the availability of reliable and quality direct impact on the quality of life. About
power at reasonable rates. The 56.5% of our rural households still do not
commercial and domestic power have access to electricity and therefore
requirements of the county are also the national common minimum
increasing rapidly. Therefore, making programme of our government has set a
available power on demand to all is one of target of completing electrification of all
the top most priorities of the households in coming five years.
Government. Making power available to
the consumers, be it industries, While we have to enhance availability of
enterprise, domestic consumers or energy to meet our growing demand, as a
farmers for their use, involves an overall responsible nation India has decided to
development of the entire chain from adopt a Low Carbon Growth Strategy to
power generation to its transmission and reduce the energy intensity and promote
ultimately its distribution to the point of sustainable development of the country.
consumption in the most optimum and Sustainable development is one that
efficient manner. meets the needs of the present without
compromising on the ability of the future
The demand for power has been generations to meet their own needs.
continually outstripping the growth of With a view to reduce Green House Gas
generation and therefore peak and emission, harnessing of renewable
energy shortages still prevail in the resources to the extent possible,
country either due to inadequate promotion of hydro and nuclear
generation or inadequate transmission & generation, enhancing efficiency of the
distribution facilities despite the fact that existing power plants and introduction of
generation capacity has increased many new technologies for power generation
fold since independence. The demand for for enhancing efficiency and demand side
electricity in the country has been management and conservation are being
growing at an average growth rate of pursued. Since coal will continue to
about 7 to 8% and demand-supply gap has dominate power generation in future,
widened over the years. Providing reliable Super Critical Technology has been
and inexpensive electricity is the goal for proposed to be introduced. To produce
th th
Low Carbon Growth Strategy for Indian Power Sector for 12 and 13 Five Year Plans Chapter 8: Page | 135
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

power this technology will convert coal


far more efficiently than pulverized coal 8.1 INSTALLED CAPACITY AS ON 31-12-
boiler technology with Sub-Critical steam 2011
parameters. Initiatives have also been
taken to undertake feasibility studies The total installed capacity as on 31-12-2011
towards introduction of Integrated was 1,86,655 MW comprising of 38,748
Gasification Combined Cycle (IGCC) MW hydro, 122,965 MW thermal (including
technology for power generation. gas and diesel), 4,780 MW Nuclear and
20,162 MW Renewable Energy sources.
This note details the strategy being The type-wise details of installed capacity
adopted by the Indian Power Sector to as on 31-12-2011 are given in Table 8.1 and
reduce GHG emissions in line with shown in Pie Chart 8.1 below.
government’s objectives enshrined in
NAPCC.

Table 8.1
Installed Capacity ‘MW’ as on 31.12.2011

Hydro Thermal (MW) Nuclear R.E.S *


Sector Total(MW)
(MW) ( MW) (MW)
Coal Gas Diesel Total (MNRE)
State 27338 48112.0 4327.12 602.61 53041.73 0 3225.92 83605.65
Private 2525.00 18544.38 6713.50 597.14 25855.02 0 16936.32 45316.34
Central 8885.4 37365.00 6702.23 0 44067.23 4780 0 57732.63
Total 38748.4 104021.38 17742.85 1199.75 122963.98 4780 20162.24 186654.62
* RES – Renewable Energy Sources
Chart 8.1
All India Installed Capacity (as on 31st December, 2011)

NUCLEAR, NEW
4780, 3% RENEWABLES,
20162.24, 11%

HYDRO,
38748.4, 20%

GAS, 17742.85, COAL,


DIESEL,
10% 104021.4, 55%
1199.75, 1%

th th
Chapter 8: Page | 136 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

8.2 GENERATION MIX DURING 2010-11 665 BU thermal (including gas and diesel),
26 BU nuclear and 28 BU energy from
The energy generation during 2010-11 was Renewables. The generation break-up
839 BU comprising 120 BU hydro during 2010-11 is given below:
(including 5.6 BU imports from Bhutan),

Table 8.2
Energy generation during 2010-11

Hydro ( BU) Thermal Nuclear (BU) RES* (BU) Total (BU)


(BU)
120 (14.3%) 665 (79.3%) 26 (3.0%) 28 (3.4%) 839(100%)

Chart 8.2

GENERATION DURING 2010-11(IN Billion kwh)


Nuclear, 26.3,
3%
Diesel, 3, 0%
(MNRE), 28, 3%
Gas, 97, 12%

Hydro, 120, 14%

Hydro
Coal
Gas
Diesel
Nuclear
Coal, 564.2, 68% (MNRE)

It may be seen that share of fossil fuels in 8.3 CAPACITY ADDITION DURING 11TH
installed capacity is 65%, while the share of PLAN
the same in energy generation is 80%
indicating that the fossil fuel capacity has During the 11th Plan period (2007- 2012),
been operating at a higher PLF thus Planning Commission had set a capacity
generating more. Fossil fuels based addition target of 78,700, MW comprising
generation, as such is the back bone of 15,627 MW hydro, 59693 MW thermal and
Indian Power Sector. 3380 MW nuclear projects as summarized
in Table 8.3.

th th
Low Carbon Growth Strategy for Indian Power Sector for 12 and 13 Five Year Plans Chapter 8: Page | 137
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Table 8.3

Sector Hydro Thermal Nuclear Total


Coal Gas Diesel Total
State 3482.0 19985.0 3316.4 0.0 23301.4 0.0 26783.4
Private 3491.0 9515.0 2037.0 0.0 11552.0 0.0 15043.0
Central 8654.0 23350.0 1490.0 0.0 24840.0 3380.0 36874.0
Total 15627.0 52850.0 6843.4 0.0 59693.4 3380.0 78700.4

As per the Mid Term Review, the likely commissioned during 11th Plan. The fuel-
capacity addition during the 11th plan wise break-up of likely capacity addition
period is 62,374 MW. A capacity of about during 11th Plan is summarized in Table 8.4.
44,000 MW has already been
Table 8.4

SECTOR Hydro Thermal Nuclear Total


(MW)
CENTRAL 2922 14920 3380 21222
STATE 2854 18501 0 21355
PRIVATE 2461 17336 0 19797
TOTAL 8237 50757 3380 62374
(13.2%) (81.4%) (5.4%) (100)

8.4 EMISSION FACTOR (kg/kwh of CO2) of generation as per actual during 2007-08
The weighted average emissions (tonnes and possible with latest technology are
of CO2/Mwh) fuel wise for different types indicated in Table 8.5.

Table 8.5
Weighted Average Emissions Fuel- Wise (tCO2/MWh) *

Fuel During 2007-08 With Latest Technology


Coal 1.00 0.88 (Super Critical HR 2326)
Gas 0.46 0.34 (CCGT η - 53%)
0.25 (CCHP η - 70%)
Oil 0.71 0.71
DG Sets 0.61 0.61
Bio Mass Co2 Neutral Co2 Neutral
* Values calculated on gross generation

The actual emission factor and absolute for Indian Power Sector on the basis of
CO2 emission upto 2008-09 and likely total generation is given in Chart 8.3.
scenario by the end of 11th Plan (2011-12)

th th
Chapter 8: Page | 138 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chart 8.3

It can be seen that emission factor has capacity addition by coal fired generating
been reducing over the years despite rise plants.
in CO2 emissions. It is likely to be around
0.739 kg/kwh by 2011-12 from 0.805 during 8.5 ELECTRICAL ENERGY REQUIREMENT
2002-03 (drop of about 9%) whereas total PROJECTION
emissions are likely to increase to 749 MT
during 2011-12 from the level of 429 MT The requirement of electrical energy by
during 2002-03 due to major increase in the end of 12th & 13th plan as per 18th EPS
report is shown in Chart 8.4.

Chart 8.4

18th EPS Demand Projections

2000 1904
Energy Requirement (BU)

1600
1354

1200 969
831 ER BU
800

400

0
2009-10 Actual 2011-12 11Plan 2016-17 12th 2021-22 13th
End Plan End Plan End

th th
Low Carbon Growth Strategy for Indian Power Sector for 12 and 13 Five Year Plans Chapter 8: Page | 139
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

To meet the power demand of the they have been considered as must run in
country during 12th & 13th Plan with as low the planning exercise.
increase in emissions as practicable, a Low
Carbon Growth Strategy has been (ii) Promote Renewable Energy
adopted in generation planning as including Solar Power
summarized below.
The Renewable Purchase Obligation
8.6 LOW CARBON GROWTH STRATEGY (RPO) has been notified by different
SERCs for respective states. The
Following are a few measures being Renewable Purchase Obligation (RPO) is
considered to ensure low carbon growth the obligation mandated by the State
during the 12th & 13th five year plans. Electricity Regulatory Commission (SERC)
under the Act, to purchase minimum level
(i) Promote Hydro Power of renewable energy out of the total
Development consumption in the area of a distribution
licensee. Feed in tariff for renewable
Development of hydro projects from energy has been notified by CERC and a
planning to commissioning takes a long number of State Electricity Regulatory
time and therefore advance planning of Commissions for different types of
hydro projects is necessary. CEA has renewable generation. To promote use of
prepared hydro development plan for the renewable energy, Renewable Energy
12th five year plan in Sept, 2008. All out Certificate (REC) mechanism has been
efforts were made to get timely Statutory proposed by CERC. REC is a market based
Clearances of Projects identified for 12th instrument to promote renewable energy
Plan capacity and to ensure placement of and facilitate renewable purchase
orders for main packages in 11th Plan itself obligations (RPO). REC mechanism is
so that projects could fructify during the aimed at addressing the mismatch
12th Plan. between availability of RE resources in
state and the requirement of the
Water & Water power is a state subject. A obligated entities to meet the renewable
large no. of hydro project sites have been purchase obligation (RPO).
allocated to public & private companies
for development. These projects are likely Jawahar Lal Nehru National Solar Mission
to be commissioned during 12th & 13th is a major initiative of the Government of
Plans. CEA has been monitoring the India to promote ecologically sustainable
progress of survey & investigation and growth while addressing India’s energy
preparation of Detailed Project Reports security challenge. It will also constitute a
and construction for these projects in major contribution by India to the global
close coordination with the developers. effort to meet the challenges of climate
change and tap the vast renewable
Based on the status of various hydro potential available in India from solar
projects, it has been estimated that a power. MoP and MNRE are finalizing
capacity of about 9200 MW could strategies for development of Solar
materialize during 12th Plan. In view of Projects totaling 1000 MW through
inherent advantages of hydro projects, NVVNL by 2013 which includes 200 MW

th th
Chapter 8: Page | 140 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

roof top solar by 2013 under phase-I of the


programme. Further, SERCs are to specify There is a need to develop gas based
RPOs in respect of solar energy and MoP generation capacity in the country in
is to make necessary modification in NEP/ order to meet our growing demand of
Tariff Policy. power and reduce CO2 emissions. Besides
being environmentally benign, the gas
One objective of the National Solar projects have high efficiency, low
Mission is to create an enabling policy gestation period, low capital cost and
framework for the development of 20,000 require less land and water. Gas projects
MW of solar power by 2022. are ideally suited for meeting peaking
requirements. CEA has already projected
(iii) Promoting New Gas based projects the following additional requirement for
with a mix of indigenous Gas and 12th Plan.
imported RLNG

Table 8.6
Additional gas requirement for 12th plan

Particulars Gas capacity Gas requirement at 70%


in MW PLF (mmscmd)
CCHP Capacity 2,000 8.0
Gas based capacity at the brown field sites 10,000 37.0
or at green field sites including
Peaking Gas based capacity to be located 2,000 4.0 *
near large cities
Total 25,000 90.0
* Considering operation for about 5-6 hours daily for peak load and in contingencies

The present allocation to power sector first two years of the 12th Plan is for tie up
from all domestic sources is about 79 long term contracts for RLNG for about 40
MMSCMD. Mo P&NG is probably not in MMSCMD for power sector. The current
position to indicate additional availability scenario in international market seems to
of gas from domestic sources during 12th be favourable for long term RLNG
Plan and will be in a position to indicate contracts. 40 MMSCMD for RLNG could
only after DPRs for the project be pooled with 79 MMSCMD indigenous
development are received by them. gas and supplied to the existing and new
However, they have indicated spare gas based projects on pooled price or
availability of LNG terminal capacity of allocated gas from indigenous sources
about 50MMSCMD by the end of the year and RLNG on pro-rata basis which
2011-12. effectively will result in same price of gas
for all the projects, new and old.
One option to develop new gas based
capacity which could come up during the

th th
Low Carbon Growth Strategy for Indian Power Sector for 12 and 13 Five Year Plans Chapter 8: Page | 141
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

(iv) Early notification of CEA regulation to get additional generation at low cost in
on construction of power plants short gestation period. Besides
indicating mandatory minimum generation improvement, it results in
efficiency levels improvement of environmental emissions
and improvement in availability, safety
CEA’s technical regulation for and reliability. To incentivise States, 50% of
construction of electrical plants and lines generation capability of the unit just
have been prepared and submitted to before shut down for R&M may be
MoP. These regulations indicate compensated by way of additional
mandatory minimum efficiency level of allocation from unallocated quota during
power plants and transmission the normative period of shut down. Low
equipments. interest rate financing for enhanced
efficiency based R&M has also been
(v) Retirement of Old and Inefficient initiated.
Coal based Generating units
Retirement of Old and Inefficient thermal (vii) Adoption of Clean Coal Technology
Plants and replacing them with new and
more efficient units is an effective way of As per Low Carbon Growth Strategy,
using the fuel and minimizing GHG adoption of clean coal technology which
Emissions. During the 11th Plan 1500 MW of includes addition of Super Critical units,
capacity is to be retired. This comprises of promotion of IGCC, CFBC technology is
coal and lignite units of unit size lesser being adopted for future plans. During the
than 100 MW. 12th Plan about 50% of Coal based capacity
is being planned on super critical and in
A capacity of about 4000 MW is proposed 13th Plan it has been proposed that all
to be retired during the 12th and 13th Plan coal based capacity is to be based on
each which includes the remaining units of super critical technology. In this regard
coal & lignite under 100 MW, gas plants following action has been taken/required
more than 30 years old (1987 & before) to be taken.
and some coal based units of 110 MW
capacity. Action:

(vi) Implementation of National (a) Creation of Indigenous


Enhanced Efficiency Renovation and manufacturing capacity for super
Modernization Program. critical equipment
(b) Incentivising Indigenous
CEA has already prepared a National Manufacturers to ensure transfer
Enhanced Efficiency Renovation and of Super Critical Technology
Modernisation Programme for (c) Bulk tendering for 11x660 MW
th th
implementation during 11 and 12 Plans. Super Critical units with
This covers R&M of 18965 MW capacity mandatory indigenous
during 11th Plan and 4971 MW during 12th manufacturing in progress. To
Plan. Renovation and Modernisation initiate Bulk Tendering for 800
(R&M) and Life Extension (LE) of existing MW size units shortly after
old power stations provide an opportunity finalising orders for 660 MW.

th th
Chapter 8: Page | 142 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

(d) Bulk tendering for projects based modest degree of energy self-sufficiency
on Ultra super critical technology suggests the need to pursue the
with mandatory indigenous development of nuclear power using
manufacturing by 2011-12 may be thorium. India can erect and run nuclear
taken up in consultation with plants to a capacity of 60GW by 2031-32.
indigenous manufacturers. The full development of the country’s
(e) MOEF may be advised not to hydro-electric potential and realization of
clear any Coal based projects the optimistic nuclear scenario by 2031-32
w.e.f. 01-04-2012 on Sub-critical needs to be persued.
technology. No coal linkages for
Sub-critical plants for 13th Plan With the signing up of the '123
(f) It is proposed that on Super Critical Agreement' on nuclear cooperation
Plants there should not be any between USA and India, and NSG’s waiver
custom duty and excise duty i.e. for supply of nuclear fuel to India, it is
the same exemption for excise expected that some nuclear plants with
duty and custom duty as foreign technology from friendly
applicable to Mega Power countries would be set up in the country.
Projects. The availability of imported nuclear fuel
and technology to India will help in
(viii) Nuclear Power Generation accelerated capacity addition from
nuclear power plants. Commencement of
Nuclear generation is also limited due to construction of reactors with imported
availability of natural uranium in the technology during 11th/12th Plans is
country. Department of Atomic Energy expected which will get commissioned in
plans to put up a total installed nuclear 13th Plan onwards. Development of
power capacity of 20,000 MWe by the nuclear parks with Mega capacity is also
year 2020 in the country. As of now, the anticipated. Integrated Energy Policy
first stage programme based on indicates two scenarios of nuclear
indigenous fuel is in progress and has capacity addition of about 48,000 MW in
reached a stage of maturity. A beginning low nuclear scenario and 68,000 MW in
has been made of the 2nd stage high nuclear scenario by 2031-32.
programme with construction of 500
MWe PFBR (Prototype Fast Breeder (ix) Reduction of T&D losses to be
Reactor). This is expected to be followed accorded high priority
by four more 500 MWe units by the year
2020. Thereafter it will be followed by a All India T&D Losses are very high of the
number of FBRs. When the capacity order of 29.24 %. To reduce T&D losses,
through FBRs builds up to reasonable implementation of R- APDRP to reduce
level, the deployment of thorium for technical and commercial losses are being
power generation through 3rd stage will accorded highest priority.
begin and get realized in the long term. Privatization/franchisee of distribution
should be encouraged as these measures
Although nuclear energy can make only a are expected to help in reducing AT&C
modest contribution over the next 15 Losses.
years, longer-term consideration of even a
th th
Low Carbon Growth Strategy for Indian Power Sector for 12 and 13 Five Year Plans Chapter 8: Page | 143
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

(x) Implementation of BEE Programmes exploration/production in the same area


exists in Cambay basin (Gujarat), Barmer
Bureau of Energy Efficiency (BEE) has Basin (Rajasthan) and Cauvery basin
launched various programme to promote (Tamil Nadu) wherein both CBM and Oil &
efficiency in use of electrical energy as per Natural Gas occur in the same basinal
details given below: areas. As far as technical feasibility and
horizontal/vertical separation of CBM
 Implementation of ECBC in operations and Oil & Gas operations are
states concerned it is very well established that
 DSM in municipal, agriculture both operations could be carried out
and buildings simultaneously. However, certain broad
 Enforcement of energy guidelines and procedures may have to be
intensity standards in Energy followed in this endeavor. Director
Intensive Industry and trading General Hydro Carbon under MoP&NG is
of emission reduction the nodal agency for CBM. Till date 26
certificates. blocks have been allocated.
 CFL Bachat Lamp Yojna
 Agriculture (Ag DSM) Pump 8.7 IMPROVEMENT IN EFFICIENCY OF THE
efficiency improvement THERMAL GENERATION CAPACITY
through ESCO. (COAL, LIGNITE AND GAS)
 Labeling of Appliances
 Labeling of Inverters on priority With the introduction of supercritical
technology and new gas based capacity
(xi) Utilization of Coal Bed Methane (CBM) and retirement of old units, the thermal
efficiencies at the end of the 11th, 12th &
In India, scope for simultaneous 13th Plans are expected to increase as
operations for CBM and oil and gas given in Table 8.7 & Chart 8.5 below:

Table 8.7

Thermal Capacity at Thermal Efficiency


the end of Plan (%)
th
End of 10 Plan (Actual) 84,812 33.86
End of 11th Plan(with 1500 MW 1,34,069 35.21
retirement)
End of 12th Plan 1, 97,755 35.96
( with 4000 MW retirement)
End of 13th Plan (With 4000 2,42,955 36.49
MW Retirement)

Chart 8.5
th th
Chapter 8: Page | 144 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Efficiency of the Thermal capacity at the end of


10th, 11th, 12th and 13th Plans
Thermal Efficiency
of (%)
38.0 36.49

37.0 35.96

36.0
35.21
35.0
33.86
34.0

33.0

32.0
End of 10th End of 11th End of 12th End of 13th
Plan Plan(with Plan( with Plan( with
retirement) retirement) retirement)

This increase in efficiency of thermal units Studies have been carried out for 12th &
will result in reduced emission factor 13th plan periods taking into account the
further. Further reduction is expected due existing capacity, committed capacity
to increase in generation from nuclear, during the 11th Plan that is a feasible
hydro and renewable resources under capacity of 62,374 MW and the options
various scenarios as listed below. already available for 12th Plan. Capacity
addition required has been assessed to
8.8 CAPACITY ADDITION REQUIRED meet the seasonal requirements also.
DURING 12TH & 13TH PLANS
Hydro capacity has been restricted to the
Three Scenarios have been developed for feasible capacity of 9204 MW in the three
capacity addition during 12th & 13th Plan different scenarios. Retirement of old
periods. They are Business as Usual inefficient units also has been considered
Scenarios with low gas and low renewable as given in the table of capacity addition.
Scenarios. Business as Usual Scenarios i.e. Renewable capacity has been assumed to
SC-1 is the Base Case. The capacity operate at 20% PLF.
addition required during 12th & 13th Plan
has been worked out based on the results Based on results of the studies,
of the Planning studies carried out using generation capacity addition required
EGEAS software model. during 12th & 13th Plans are summarised in
Table 8.8 & 8.9 below:

Table 8.8

th th
Low Carbon Growth Strategy for Indian Power Sector for 12 and 13 Five Year Plans Chapter 8: Page | 145
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Three Capacity Addition Scenarios-12th Plan

SC-1 SC-2 SC-3


Low Gas Low High Gas Low High Gas High
Renewables Renewables Renewables
(Base Case)
Hydro 9,204 9,204 9,204
Nuclear 2,800 2,800 2,800
Renewable(Excluding 14,500 14,500 20,000
Solar)
Solar 4,000 4,000 10,000

Retirements of Old 4,000 4,000 4,000


inefficient Units
Gas 1,086 13,086 13,086
Coal 66,600 54,600 51,400
Sub-Critical 38,700 26,700 23,500
Super Critical 27,900 27,900 27,900
12th Plan (Total) 79,690 79,690 76,490
(Conventional)

Table 8.9
Capacity Addition Scenario-13th Plan

SC-1 SC-2 SC-3


Low Gas Low High Gas Low High Gas High
Renewables Renewables Renewables
(Base Case)
Hydro 12,000 12,000 12,000
Nuclear 18,000 18,000 18,000
Renewable(Excluding 14,500 14,500 25,000
Solar)
Solar 16,000 16,000 20,000
Retirements of Old 4000 4000 4000
inefficient Units
Gas 0 13,000 13,000
Coal 49,200 38,000 34,000
Sub-Critical 10,000 0 0
Super Critical 39,200 38,000 34,000
12th Plan (Total) 79,200 81,000 77,000
(Conventional)

8.9 EMISSION PROJECTIONS UPTO THE On the basis of generation from each fuel
END OF 13th PLAN (2021-22) sources, carbon footprint i.e. Emissions
and the emission factor intensity
th th
Chapter 8: Page | 146 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

considering base year of 2004-05 have considered and the average emission
been worked out, The Electrical factor from total generation are shown in
generation growth during the plans Chart 8.6 below.

Chart 8.6
Average Emission Factor from Total Generation (Kg/kWh)

It may be seen that the average emission of 2004-05 due to various measures
factor is expected to reduce in the range mentioned above. However, the total
of 6.6 % to 20.3 % by the end of 13th Plan emission from power sector would
(2021-22) in three scenarios from the level increase as shown in Chart 8.7 below:

Chart 8.7
Total CO2 Emission (MT) from Thermal Generation

It may be seen that total absolute


emission by 2021-22 is expected to be 8.10 ANTICIPATED PERCENTAGE
about 2.3 % to 5.2 % lower in SC-2 and SC-3 REDUCTION IN EMISSION
respectively as compared to SC1 i.e. Base INTENSITY (KG CO2/ TEN ` OF GDP)
Case.
th th
Low Carbon Growth Strategy for Indian Power Sector for 12 and 13 Five Year Plans Chapter 8: Page | 147
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

FOR POWER SECTOR W.R.T. YEAR Central Statistical Organization and


2004-05 thereafter projected data at 8% CAGR has
To assess emission intensity based on been used. India’s Emission Intensity (kg
power sector emissions for year 2021-22, CO2/ ten ` of GDP) based on Power
actual GDP data upto 2007-08 has been Sector Emission is summarized in Table
taken from Economic Survey Report of 8.10.

Table 8.10
Emission Intensity based on Power Sector Emissions

YEAR GDP IN CO2 EMISSIONS(MT) CO2 IN KG/ Ten ` of GDP


RS. SC-1 SC-2 SC-3 SC-1 SC-2 SC-3
CRORE
2004-05 2388768 462 462 462 0.193 0.193 0.193
2006-07 2871118 495 495 495 0.172 0.172 0.172
2007-08 3306735 521 521 521 0.158 0.158 0.158
2011-12 4498776 749 749 749 0.166 0.166 0.166
2016-17 6610178 1030 1013 1000 0.156 0.153 0.151
2021-22 9712521 1261 1229 1191 0.130 0.127 0.123

8.11 CONCLUSION measures at the generation and


consumer end. Thrust to adoption
 An increase in thermal efficiency is of latest technologies, in particular
expected from 33.86% by end of clean coal technologies needs to
10th Plan (2006-07) to 36.49% by be vigorously pursued.
the end of 13th Plan (2021-22).
• It is feasible to achieve reduction in
 Average Emission Factor from total emission factor (CO2 per unit of
generation (including renewable) generation) from power sector by
is also expected to decrease from nearly 15 % less in 2022, compared
actual 0.737 in year 2006-07 to to 2005. The percentage reduction
0.622 by 2021-22. While estimating expected in Emission Factor (CO2
the above benefits, effect of produced per Kwh of generation)
strategies like R&M etc have not in all the three scenarios at the end
been incorporated for 13th Plan. of 11th, 12th & 13th Plans w.r.t. year
 Efforts are required to be made to 2004-05 is indicated in Table 8.11
accelerate R&M Programmes as below.
well as Energy Conservation

Table 8.11
th th
Chapter 8: Page | 148 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Scenarios End of 10th End of 11th Plan End of 12th Plan End of 13th Plan
Plan (2006-07) (2011-12) (2016-17) (2021-22)
(Actual)
Scenario-1 8.1 19.9
Scenario-2 5.1 4.9 9.4 21.8
Scenario-3 10.6 24.3

• It is feasible to achieve percentage  Facilitation of statutory


reduction in Emission Intensity (Kg clearances of hydro projects.
CO2/ ten ` of GDP) for Power
Sector w.r.t. year 2004-05 by  Transfer of Super Critical and
around 25% assuming GDP growth Ultra Super Critical Technology
of 8%. and promotion of indigenous
manufacturing capacity.
• This however depends on
satisfactory implementation of  Directives regarding minimum
efficiency of new power stations.

 Development of 31,000 MW of  Environment clearance and coal


hydro capacity (including about linkage for only Super Critical
9,000 imports from neighbouring units from 13th Plan.
countries)
 NVVNL to enable development of
 Addition of 25, 000 MW of gas 1,000 MW of grid connected solar
based capacity power.

 Addition of 60,000 MW Super  Promotion of new gas based


Critical Thermal capacity capacity through import of RLNG
with pooling of imported and
 Addition of 45,000 MW from indigenous gas for all new and
(Non Solar) renewables existing projects.

 Addition of 30,000 MW of solar  Low financing rates for efficiency


power enhancing R&M schemes.

 Retirement of 8,000 MW of  Bulk tendering of Super Critical/


inefficient thermal units Ultra Super Critical Technology
with mandatory indigenous
 Reduction of T&D losses from 30% component.
to 17%.
 Distribution franchisee model to
 Elasticity of electricity end use be promoted
decreases from 1.0 in 2005 to 0.8
in 2016-17 to 0.7 by 2021-22.  Energy intensity standards for
industry, buildings and appliances
• This would require:
th th
Low Carbon Growth Strategy for Indian Power Sector for 12 and 13 Five Year Plans Chapter 8: Page | 149
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

---+++---

th th
Chapter 8: Page | 150 Low Carbon Growth Strategy for Indian Power Sector for 12 & 13 Five Year Plans
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 9

KEY INPUTS FOR 12TH PLAN

9.0 INTRODUCTION execution of power generation works


during 12th Plan has also been made.
For successful implementation of any
Power Plan, it is essential that all key It is felt that the assessment of
inputs required for implementation of the requirement of equipment, material and
power expansion programme are made fuel as covered in this Chapter would give
available as per the schedule of sufficient input to other Ministries and to
requirement of the individual power the industry to enable them to take
projects. The timely supply of all key advance action and plan their production
inputs would ensure timely completion of targets etc. according to the requirement
the project and therefore avert of the Power Sector.
detrimental implications of cost and time
overruns in case the power project is 9.1 CAPACITY ADDITION PROGRAMME
delayed.
A capacity addition of about 79,690 MW is
This Chapter broadly deals with an required during the 12th Plan to meet the
assessment of requirement of Equipment All-India demand projections of the draft
for 12th Plan for generation capacity 18th EPS Report. A shelf of about 1,23,000
addition and key inputs required during MW of coal based capacity is under
these Plan periods, namely, Steel, Cement, various stages of construction.
aluminium for infrastructure requirement
of generating plants. An assessment of Details of capacity addition being planned
fuel, manpower and fund requirement for for the 12th Plan are given below:

Table 9.1
Type Wise Capacity Additions during 12th Plan
(Figs in MW)
th
Item 12 Plan (2012-17)
Coal based 66,660
Gas based 1,086*
Hydro 9,204
Nuclear 2,800
Total 79,690
* - Gas from local sources

th
Key Inputs for 12 Plan Chapter 9: Page | 151
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

9.2 EQUIPMENT 1. L&T-MHI


2. Toshiba-JSW
Requirement of equipment is one of the 3. Alstom-Bharat Forge
most important inputs for the setting up 4. Ansaldo-Gammon
of Power Projects. Adequate domestic 5. BGR-Hitachi
manufacturing capacities & capabilities for 6. Doosan
main plant equipment would be available 7. Thermax-Babcock
to meet the demand of the 12th Plan 8. Cethar Vessel- Riley Power
capacity addition programme as a result
of the push given by the Government for In addition, BHEL has also augmented its
indigenous manufacturing of main plant capacity from 6,000 MW per annum in 10th
equipment during the 11th Plan. To Plan to 15,000 MW per annum and is in the
ensure energy security it is vital that the process of augmenting its capacity further
manufacturers give reliable services as to 20,000 MW per annum.
well as spares during the life time
operation of the Plant; accordingly it is From the information provided by the
essential that a level playing field is manufacturers, it has emerged that
provided to manufacturers so that a following domestic capacities shall be
healthy competition ensures competitive available for steam generators and
prices and quality equipment. A number turbine generators.
of 11th Plan projects have not been able to
achieve full load operation within By 2013-14 By 2014-15
stipulated time from synchronization due SG (MW) 26,500 40,500
to non-readiness of the balance of plant. TG (MW) 30,020 35,020

7.5.1 Main Plant Equipment Balance of Plant (BoPs)


In the category of coal based power plant,
Balance of Plants such as Coal Handling
switch-over to super critical technology is
Plant, Ash Handling Plant, Water
envisaged for the new capacities coming
Treatment / DM Plant, Cooling Towers,
up in 13th Plan and beyond.
CW System, Chimney, Plant electrical and
Based on the encouragement from switchyard etc. have been identified as
Government of India for setting up critical items for timely commissioning of
domestic manufacturing facilities, a thermal power projects. BoPs have been
number of new manufacturers have come and continue to be a critical area for
forward for setting up manufacturing achieving capacity addition targets. To
facilities for Steam Generators and mitigate risk associated with BOP systems
Turbine Generators. These include: initiatives like standardisation of BOP
systems, reviewing the qualifying
requirements to ensure quality vendors
th
Chapter 9: Page | 152 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

and large vendors for faster execution of be rated based on their


projects, mandating a central performance.
organization to maintain a dynamic data • Work in hand / Bid Capacity etc.
base with regard to BOP orders and their should find place in bid documents.
liquidation. • MOP/CEA to suggest an
‘implementation mechanism’ to
It is also felt that the latest methods of enforce technical standards
civil construction with mechanised notified by CEA.
equipment and man power mobilization
• Training of Skilled/ Semi-skilled
needs to be adopted. The vendors have to
be encouraged to adopt new erection workers for Power project
technologies to reduce the erection and requirements to be taken by EPC
commissioning cycle. An institutional Contractors, Developers as well as
mechanism to develop skilled man power the Manufacturers.
for construction & execution of projects is
also to be stressed upon. 9.3 KEY MATERIALS

As per the information compiled by CEA, Steel and cement are the key materials
sufficient numbers of vendors are needed for power projects. In case of
available for major BoPs. both hydro and thermal projects, the
requirement of steel and cement are site
NUMBER OF BOP VENDORS specific and the civil engineering works
Coal handling System 15 vary from project to project depending
Ash Handling System 13 upon the features of the projects. In case
Cooling Towers 12 of thermal projects, the civil works would
DM Plants 18 be more when the first unit of the thermal
project is installed on a virgin site than for
Few suggestions regarding BOP an additional unit installed at the same
equipment for ensuring timely capacity site. However for the purpose of
addition are as follows: estimating the requirement, suitable
• Developers may execute BOPs on consumption norms have been worked
EPC basis. out based on the actual consumption of
• A web based portal needs to be steel and cement for the works
designed and managed for all completed during the past and also in
information relating to BOP respect of projects under execution. In
view of this, the assessment of steel and
vendors viz. orders at hand, their
cement required for hydro and thermal
implementation status etc. so that
projects in 12th Plan would be only
developer of projects can take an approximate.
informed decision.
• In second phase the BOP vendors
and Construction agencies could

th
Key Inputs for 12 Plan Chapter 9: Page | 153
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

9.3.1 Norms for material requirement

The Norms used for computing material


inputs for power generation projects are
as given in Table 9.2 below:

Table 9.2
Norms for Key Inputs
(Figures in Tonnes/MW)

NORMS FOR INPUT MATERIALS FOR GENERATION PROJECTS

Requirement of Thermal Hydro Remarks


Materials/MW Coal/Lignite Gas Based
Based
a) Cement 150 60 956
b) Structural steel 85 29 34
c) Reinforcement steel 45 24 93
d) Stainless steel 130.61 51.6 - Used in Bunker
e) Aluminium 0.5 0.5 0.1 Used in windows,
metal cladding walls,
control rooms

9.3.2 Material Requirement expansion plan has been worked out as


per the norms and given in Table 9.3 and
Requirement of key materials for 12th Plan 9.4 below:
and 13th Plan corresponding to generation

Table 9.3
Key Inputs for 12th Plan
(Figures in Million Tonnes)
Sl. No. Materials Thermal Capacity Hydro Total
Capacity
Coal based Gas based 9204
66,660 MW 1,086 MW MW
1. Cement 9.9 0.065 8.80 17.76
2. Structural steel 5.66 0.0097 0.31 5.92
3. Reinforcement steel 2.99 0.026 0.86 3.87
4. Stainless steel 8.70 0 8.7
5. Aluminium 0.033 0.056 0.001 0.09

th
Chapter 9: Page | 154 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Table 9.4
Key Inputs for 13th Plan
(Figures in Million Tonnes)
Sl. No. Materials Thermal Capacity Hydro Total
Capacity
Coal based No Gas 12000
49,200 based MW
MW considered
1. Cement 7.38 11.47 18.85
2. Structural steel 4.18 0.41 4.59
3. Reinforcement steel 2.21 1.12 3.33

Based on the assessment of Nuclear for planning purposes. Considering the


Power Corporation (NPCIL), requirement above, the material requirement for
of Steel, Cement and other materials for Nuclear Projects as provided by CEA is as
nuclear projects is considered at 130% of given under Table 9.5
the requirement of coal based projects

Table 9.5
Key Inputs for 13th Plan Nuclear
(Figures in Million Tonnes)
th
Material 12 Plan 13th Plan
2800 MW 18000 MW
Cement 0.55 3.51
Structural Steel 0.31 1.99
Reinforcement Steel 0.16 1.05

The main inputs for manufacturing regarding these key inputs are given in
power plant equipment are castings & the following Tables.
forgings, steel plates, structural steel,
copper, CRGO/CRNGO etc. While Steel, Castings & Forgings for Turbo-
Cement, Copper, Aluminium etc. are the Generators (TG) Sets:
key inputs needed for erection & As per the details provided by BHEL the
commissioning and transmission & average requirement of castings and
distribution networks. Some estimates forgings for a 500/660/800 MW sets is
as given below:

MT per Set
Equipment Weight of Castings Weight of Forgings
Turbine 384 235
Generator 3 130
Total 387 364

th
Key Inputs for 12 Plan Chapter 9: Page | 155
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

The requirements of Castings and per the projections given by CEA, 60%
forgings for thermal projects, based on supercritical sets have been assumed in
the above average, for the 12th and 13th 12th Plan and 100% supercritical sets
Plans works out to be as given under. As have been assumed for 13th Plan.

Lakh MT
th th
Material 12 Plan 13 Plan
67746 MW 49200 MW
Castings 0.39 0.29
Forgings 0.36 0.27
Note: As norms for nuclear projects are
not received, requirement for nuclear is As per the details provided by BHEL, the
not included. Also, requirement of average requirement of Tubes & Pipes
casting & Forgings for Hydro projects and Thick Boiler Quality Plates
are very project specific, hence not (Imported Plates) is given below. As per
included. the projections given by CEA, 60%
supercritical sets have been assumed in
Sufficient indigenous capacities for 12th Plan and 100% supercritical sets
heavy castings & forgings need to be have been assumed for 13th Plan.
created to reduce dependence on
imports.
Lakh MT
Material 12th Plan 13th Plan
67746 MW 49200 MW
Material 12th Plan 13th Plan
67746 MW 49200 MW

Tubes & Pipes 7.0 5.25


Thicker Boiler Quality Plates 0.92 0.80

Indigenous capacity availability scenario of tubes & pipes as provided by BHEL:

Lakh MT
th th
Material 12 Plan 13 Plan
Tubes & Pipes 3.8 4.2
Thicker Boiler Quality Plates - -

Considering large quantity of high alloy Copper:


tubes & pipes (like T91/P91, T92/P92
grades) required for super critical As per IEEMA, power sector
boilers and thick plates requirement, requirement of Copper would be
sufficient indigenous capacities need to approx. 12.5 lakh MT p.a. with an overall
be created in the country to avoid requirement of approx. 56 lakh MT for
dependence on the imports. entire 12th plan. This is expected to
grow at a CAGR of approx. 10% p.a.

th
Chapter 9: Page | 156 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

As per the information provided by FIMI consumption for 12th plan is given
for Copper, the capacity, production and below:

Lakh MT
Year Capacity Production Consumption
2012-13 10.0 8.0 8.8
2013-14 10.0 8.5 9.8
2014-15 15.0 13.2 11.0
2015-16 15.0 13.5 12.3
2016-17 15.0 13.7 13.3

Aluminium:

Following norms for the Aluminium requirement as projected by CEA have been
considered for working out Aluminium requirement:

Norms for Aluminium for Generating Stations:


MT per MW
Materials Thermal Hydro Remarks
Coal Gas based Nuclear
Based Based
Aluminium 0.5 0.5 130% of 0.1 Used in windows, metal
Coal Based cladding walls, control
rooms, conductors

Aluminium requirement for Generating Stations in 12th & 13th Plan:


Lakh MT
Material 12th Plan 13th Plan
Coal Gas Based Nuclear Hydro Coal Gas Nuclear Hydro
Based Based Based Based Based
66660 1086 MW 2800 MW 9204 49200 - 18000 12000
MW MW MW MW MW
Aluminium 0.333 0.005 0.018 0.009 0.246 - 0.117 0.012
Total 0.365 0.375
are being planned by a major private
Prima facie there is no likely shortage of sector manufacturer and are expected to
key materials except for CRGO, and come up in near future.
thicker steel plates. Further, there is an
inadequate indigenous manufacturing 9.4 FUEL REQUIREMENT
capacity in the country for Tubes & Pipes
especially for alloy steel tubes & Pipes Availability of fuel is essential for power
(T91/P91, T92/P92 grades), which needs to generation. In addition to tapping fuel
be augmented. Some indigenous capacity source or organizing its availability, it is
for heavy castings & forgings which are also essential to create the infrastructure
critical for power generating equipments, to facilitate fuel to reach the intended

th
Key Inputs for 12 Plan Chapter 9: Page | 157
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

destination. Therefore development of the projects also needs to be set up. With
mines/ ports and requisite transportation this objective in view, the assessment of
facilities commensurate with the fuel requirement has been carried out.
completion of the projects is very
necessary. The gestation period in the The coal requirement for thermal power
development of mines and even transport stations depends upon the scheduled
generation, quality of coal being supplied/
facilities are in some cases longer than the
to be supplied and the condition of power
gestation period for setting up of thermal station equipment. However the
power stations. It is therefore imperative normative requirement of fuel during the
for the Power Sector to make its terminal year of 12th Plan has been
prospective coal requirement, over a long estimated based on following Norms:
time horizon, known to the Ministry of
Coal, Railways and port authorities to a) 5 MT of coal per 1000 MW per year.
b) 4.8 MMSCMD gas per 1000 MW at 90
enable them to undertake co-ordinated
% PLF.
development of coal mines and transport
infrastructure with the coming up of Details of fuel requirement during
thermal power stations. Necessary terminal year of 12th Plan are summarised
infrastructure required to transport gas to below:

Table 9.6

FUEL REQUIREMENT FOR TERMINAL YEAR OF


12TH PLAN
Fuels Requirement
2016-17
Coal (Million Tonne) 842
Gas +LNG (MMSCMD) 100*
* This requirement corresponds to gas based capacity of about 20,000 MW by the end of 11th Plan and
additional requirement of for 12th Plan projects of about 1,086 MW capacities to operate at 90% PLF.

Transport around 842 MT including domestic &


Imported coal as also coal from the
Transport sector plays a vital role in the captive coal blocks. Apart from this, with
growth of Power Sector. The the increase in Unit sizes to 660 MW, 800
development of different transport MW and plus 1000 MW during 12th plan
sectors like Railways, Highways & Roads, and beyond, heavy Over Dimensional
Ports, Inland Waterways and Gas pipelines Consignments (ODC) as never before will
are key to achieve the capacity addition need to be transported from Ports (for
targets in XII five year plan. The total coal imported equipment) and Indigenous
requirement for the power utilities by end Manufacturers to Project sites. This calls
of 12th Plan (2016-17) is estimated to be for bold initiatives, policy changes as well

th
Chapter 9: Page | 158 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

as adopting basic changes in load and Western DFC (JNPT, Mumbai- Dadri, UP)
handling specifications in Roads, Railways have been sanctioned. Apart from above
and Port sectors. Railways have also planned Gauge
conversion, new railway lines,
Railways electrification of new routes and
procurement of locomotives and wagons.
The long-term strategy of Indian Railways
is to segregate the freight and passenger Broadly, Railways envisage the following
movement through construction of targets for the medium and long-term
Dedicated Freight Corridors (DFCs). At goals (XII five year plan & beyond)
present two DFC projects i.e. Eastern DFC towards creation of infrastructure and
(Dankuni, WB - Ludhiana, Punjab) and capacity build-up.

Table 9.7

Broad Category Revised XI plan Targets Vision 2020 Targets


Doubling including DFC 2500 12,000 Kms.
Gauge Conversion 6000 12,000 Kms.
New Lines 2000 25,000 kms.
Electrification 4500 14,000 kms.
Procurement of Wagons 62000 289,136
Procurement of Diesel locomotives 1019 5334
Procurement of Electric locomotives 1205 4281

To achieve, the projected high-growth to strengthen its net work speedily to


targets, Railways need massive achieve this high growth scenario. The
investments in capacity creation, tentative estimates of Investments
network expansion and up-gradation required by the year 2020 to deal with
and modernization. The existing trunk higher levels of freight traffic would
routes and other coal carrying routes be as under:
are heavily saturated. Railways needs

th
Key Inputs for 12 Plan Chapter 9: Page | 159
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Table 9.8

Description Investment (Rs)`


Bottleneck removal – 23,000 cr
Traffic facilities, freight bye-passes, logistic parks, etc.
Capacity augmentation-
New Line, 1,80,000 cr.
Doubling/Tripling/Quadrupling including DFC 1,30,000 cr.
Gauge conversion, 35,000 cr.
Electrification 12,600 cr.
Rolling stock -
Freight wagons, 86,740 cr.
Diesel locomotives, 56,007 cr.
Electric locomotives 64,873 cr.
Technological up- gradation -
Track renewal and 25 tonne axle load, 71,405 cr.
Bridges 8,000 cr.

The expansion plans detailed in the Vision movement by IWT of 3.0 million tonnes
2020 documents of Railways gives a sense per annum from Haldia to Farrakka
of confidence that to a large extent Project of NTPC is a success. At present,
Railways will be able to meet Power ten thermal power stations are
Sector requirements for 12th Plan and operational on the banks of Ganga and
beyond, provided of course that their these are located in the States of West
expansion takes place as per their vision Bengal (7) and Bihar (3). Further eleven
document. more Thermal Power Stations are
proposed in Bihar and Uttar Pradesh with
Inland Water Transport installed capacity of over 15000 MW. Their
coal requirement is estimated to be
Inland Waterways Authority (IWT) of India around 70 million metric tonnes per
has planned for the development, up- annum, which can be met through IWT.
gradation, modernization and expansion
of National Waterways / other Waterways National Highways
during 12th plan period with an estimated
investment of Rs. 10,460 Crores. Keeping The National Highways comprise of only
this in view, there is a strong possibility of around 2% of the total Road Network in
coal cargo movement through IWT India but carry more than 40% of the
becoming attractive to power companies Traffic. This makes route management of
especially if the contract of imported coal heavy Over Dimensional Consignments

th
Chapter 9: Page | 160 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

(ODCs) highly challenging and difficult.  Railway to expedite proposed


There are serious issues associated with Dedicated Freight Corridors to
ODC transportation through roads / segregate freight and passenger
highways like interpretation of Motor traffic.
Vehicle Act differently in different states,  Railways to ensure rail connectivity
inadequate strength of roads and Bridges to all ports having coal unloading
enroute to the project sites, insufficient facilities.
road width / carriage width in state  NTPC and Inland Water Ways
highways, improper design of Toll Plazas Authority of India (IWAI) would be
built on the Highways, sharp signing an agreement for
curves/bends/gradients on roads and transportation of 3 MT of imported
inadequate vertical clearance in coal to Farakka TPS. Other thermal
underpasses in North Eastern states etc. projects located on the banks of
These need to be addressed urgently Ganges in West Bengal and Bihar
including necessary fundamental changes should also explore the same.
in loading specifications of roads,
highways and bridges for which specific Roads and Highways need to be
recommendations have been given in the augmented for transportation of Over
Report. Dimensioned Consignments (ODC) for
supercritical units. The following needs to
 Railways are transporting about be considered:
60% of the total off-take of
domestic coal.  Amendment in Motor Vehicle Act
 The percentage share will remain to accommodate heavy
the same during the 12th plan. consignments above 49 MT and
 Railways to confirm their coal inclusion of hydraulic axles,
evacuation capacity from each coal trailers.
field.  Review of load classification for
 Railways to augment their capacity Roads & Bridges by IRC/ MoRTH to
to evacuate coal from three major accommodate ODCs beyond 100
coal fields namely North MT.
Karampura, Ib Valley and Mand  Single window clearance and one
Raigarh. time payment for ODC movement
 For smooth and faster evacuation  Proper design of Toll Plazas built
of coal, coal conveyors should be on highways.
used to transport coal from mine  Changes in Road design in North
to rail head with automatic loading Eastern & Hill states to minimise
in wagons. sharp curves/gradients in roads

th
Key Inputs for 12 Plan Chapter 9: Page | 161
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

and have sufficient vertical connected with gas pipelines. For


clearance in underpasses. better utilization of generation
 Proper Approach Roads to be capacities, presently running on liquid
provided for Hydro Projects. or under- utilized, it is necessary to
connect them preferably as a part of
Existing & Proposed Gas Pipelines / Grid trunk/ spur pipeline network.

Existing Gas Pipelines


 Natural gas is the fastest growing
primary energy source amongst fossil The present gas pipeline infrastructure in
fuels, projected to grow around 3-4 the county is around 12000 km with
times between 2002-2025 at current design capacity of around 283 MMSCMD.
consumption level. We have come a The existing main trunk pipelines are as
long way from the time when oil and under:
gas were first discovered in India in
1886 in Assam and subsequently when  GAIL: Owns and operates around 8000
the famous Bombay High field was km pipelines including spur lines
discovered in 1974 in the Western (mainly HVJ-GREP-DVPL including
Offshore. DVPL-GREP up gradation and DUPL-
DPPL) with design capacity around 150
 With developing gas market, timely mmscmd.
development of gas pipelines across
the country for realization of social  Reliance Gas Transportation
and economic benefits of natural gas Infrastructure Ltd. (RGTIL) : Owns and
usage has become a priority. Such operates around 1400 km long East -
trunk gas pipelines when integrated West Pipeline (EWPL) - (Kakinada-
with the existing gas pipelines shall Hyderabad-Uran-Ahmedabad) with
ultimately lead to the National Gas design capacity of 80 MMSCMD.
Grid. The indicative National Gas Grid  Other major regional players:
shall consist of the existing pipelines,
authorized / planned pipelines and  Gujurat State Petronet Ltd (GSPL)
their links to the remote and under- :Owns & operates ~ 1200 km pipelines
developed areas. with design capacity of 40 MMSCMD.

 EGOM (Empowered Group of  Assam Gas Company Ltd (AGCL) :


Ministers) have formulated Gas Owns & operates ~ 500 km pipelines
Utilization Policy for distribution and with design capacity of 8 MMSCMD.
utilization of domestic gas in the
 Authorized Gas Pipelines: Ministry of
country and have allocated priority for
Petroleum and Natural Gas in 2007
KG D6 gas allocation to existing gas
authorized following nine new trunk
based / liquid based stations,
pipelines with total length of approx.
th
Chapter 9: Page | 162 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

8700 km with design capacity of about competitive bidding through EOI route.
209 MMSCMD. PNGRB has received 06 EOIs for setting up
of additional gas pipelines. These are (as
(A) GAIL :
per PNGRB website):

- Dadri-Bawana-Nangal (600 ksm)


(i) Mallavaram (A.P.) – Vijaipur
- Chainsa-Jhajjar-Hissar (400 kms) (M.P.) – Bhilwara (Rajasthan)
- Jagdishpur-Haldia (2000 kms) (ii) Mehasana (Gujarat) to
- Dabhol-Bangalore (1400 kms) Bhatinda (Punjab) via Jaipur
- Kochi-Kanjirrkod-Bangalore (1100 kms) (Rajasthan)
(iii) Bhatinda (Punjab) to Srinagar
(B) RGTIL : (J & K)
(iv) Surat to Paradip
- Kakinada-Haldia (928 kms)
(v) Durgapur to Kolkata
- Kakinada-Chennai (577 kms)
(vi) Kakinada to Srikakulam
- Chennai-Bangalore-Mangalore (538
kms)
PORTS
- Chennai-Tuticorin (585 kms)

These pipelines are under different stages Keeping in view the estimated capacity
of development. addition of 79,690 MW, the coal quantity
to be imported by the end of 12th plan
Establishment of PNGRB: The Petroleum works out to about 218 MT including the
and Natural Gas Regulatory Board requirement for power plants that would
(PNGRB) Act 2006 provides for the be operating completely on imported
establishment of an independent coal. Based on the Maritime Agenda for
regulatory board (PNGRB) as a Ports, issued by the Ministry of Shipping,
downstream regulator to regulate the major and non major ports together are
activities of companies related to refining, targeted to handle 476.04 Million Tonnes
processing, storage, transportation, of Thermal and Coking coal combined by
distribution, marketing and sale of the end of 12th Plan. Moreover in order to
petroleum, petroleum products and augment the capacity and enhance
natural gas and City Gas productivity levels at major ports, several
Distribution(CGD). The board has been initiatives are being taken by the Ministry
established and started functioning w.e.f. of Shipping including modernisation of
June 2007. The PNGRB have formulated port infrastructure, construction of new
several regulations pertaining to gas berths/ terminals, expansion/ up-
transportation. PNGRB is authorising gradation projects for berths and
entities for laying pipeline on basis of dredging, installation of new and modern

th
Key Inputs for 12 Plan Chapter 9: Page | 163
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

equipment, mechanisation of cargo 9.5 MANPOWER REQUIREMENT


handling operations and automation
through computer aided systems. Trained manpower is an essential
However improving / augmenting rail and prerequisite for the rapid development of
road connectivity especially last mile all areas of the Power Sector. This Sector
connectivity will need special attention is poised for massive capacity addition
particularly as it involves close and the industry should take steps to
coordination and interface between increase production and project execution
Roads, Railways and Port Authorities. capacity to meet the targets of over
1,00,000 MW (including captive &
Suggestions/ Recommendations renewable) during the 12th Plan.
Manpower development including
 Adequate coal unloading training facilities shall be commensurate
arrangement at Ports to be with this large capacity addition
ensured to handle imported and requirement.
domestic coal required for power
stations (approximately 150 MT). 9.5.1 Norms for manpower requirement
 On the East Coast, coal handling
facilities to be augmented at Norms have been adopted to assess the
Paradip and Vizag Ports. This will manpower requirement for project
be necessary to evacuate coal from construction, execution and O&M of
mines in Orissa as rail routes are generation projects during the 12th Plan.
congested. Details are as follows:
 All major and important minor
ports should be mechanised by For construction of new plants
augmenting crane capacities, silos, Hydro - 10 persons per MW
conveyors & wagon tipplers. Thermal – 8 persons per MW
 Draft at various ports to be Nuclear – 8 persons per MW
increased to handle Panamax or
Capsize vessels. Project execution period
 RO-RO berths should be created Hydro - 72 months
atleast in two major ports namely Thermal - 36 months
Kandla on the west coast and Nuclear - 72 months
Paradip on the east coast for
unloading ODCs. For operation and maintenance of
 Road connectivity to ports to generation projects
handle ODCs has to be ensured. Hydro - 1.9 persons per MW
Thermal - 1.1 persons per MW
Nuclear - 1.9 persons per MW

th
Chapter 9: Page | 164 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

9.5.2 Manpower requirement during 12th distribution are required. The personnel
Plan engaged in construction area in the Power
sector during 11th Plan would be adequate
The targeted capacity addition during the to meet the requirement in construction
12th Plan is presently pegged at around during 12th Plan. The category-wise break-
80,000 MW. It has been estimated that up of the Manpower Requirement is
about 5.1 Lakh additional personnel in shown in Table 9.10
O&M of generation, Transmission &

Table 9.10

Category Construction Operation & Maintenance (Including 7.5% recoupment ) Total


Engineers 2500 45000 47500
Supervisors 3500 80000 83500
Skilled Workers 7000 80000 87000
Semi-skilled workers 7000 60000 67000
Unskilled workers 12000 80000 92000
Non-tech 8000 125000 133000
Total 40,000 4,70,000 5,10,000

The total requirement of manpower will require marginal augmentation to


during 11th & 12th five year plan is about take care of the training requirements of
16.6 lakhs personnel needed in various the additional manpower inducted during
categories from Engineers to un-skilled the 12th Plan period.
personnel.
Critical ITI trades for power industry are as
The training measures agreed upon and follows:
implemented during the 11th Plan period

Table 9.11

Trade Number of units Annual intake


Fitter 8,531 1,36,496
Electrician 8,221 1,31,536
Welder 1,068 17,088
Wireman 2,005 32,080
Turner 1,773 28,368
Mechanic 1,157 18,512
Carpenter 475 7,600
Sheet metal 285 4,560
Mason 165 2,640
Tool & die maker 38 608
Plumber 448 7,168
Total 24,166 3,86,656
Source: Director General (Employment & Training)
40,000 is the average annual requirement estimate

th
Key Inputs for 12 Plan Chapter 9: Page | 165
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

 Through case studies.


In view of the huge requirement of
trained manpower during 12th Plan and  Arranging training through local
huge training load and advancing languages as medium of instruction
technologies emerging in the Power and developing course material in
Sector, it is recommended to adopt these languages.
modern and scientific training 9.6 FUND REQUIREMENT
methodologies and create an
The requirement of funds for Generation
infrastructure accordingly including
projects has been assessed based on the
course materials and training aids. This
capacity addition of about 80,000 MW
will result in cost and time effective
during the 12th Plan. Requirement of funds
training and help in further bridging the
for transmission and distribution etc. shall
training load-infrastructure gap. Some of
be included in Volume II of the Plan
such training methodologies are
covering transmission and distribution
described below:
requirements of the country

 Through Simulators of different types


The fund requirement has been assessed
suiting to the organizational/trainee’s
based on assumption of cost per MW for
needs (i.e. through area simulator,
various generation projects based on the
compact simulator, generic simulator
costs of past projects.
or full-scope replica simulator etc.)

 Through plant specific on-plant, on- The details of assumptions for estimation
site training at power station/sub of cost of generation projects are given as
station, manufacturer’s site. Appendix 9.1.

 Through personnel computer based


Based on the above and the likely 12th Plan
self-learning package system.
Capacity addition of about 80,000 MW,
 Through video /CDs/ films. the likely fund requirement during the 12th
Plan has been assessed as 3,71,249 crs for
 Through mock up plants, models, rigs,
generation projects.
zigs line-up panels etc.

 Through correspondence courses and In addition, funds are also required during
distant learning packages. the 12th Plan for advance action for 13th
 Maintenance skill development Plan projects which has been assessed as
through ‘Hands-on’ training on actual 2,72,582 crs. Details of total fund
plants, or obsolete/ redundant requirement for capacity addition during
equipment. 12th plan are as follows:

th
Chapter 9: Page | 166 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Table 9.12
Total Fund Requirement for Capacity Addition during 12th Plan

Fund requirement in Rs.


crores
12th Plan Capacity of about 80,000 MW 3,71,249
Advance action for 13th Plan Projects 2,72,582
Total fund requirement for Generation projects during 12th 6,43,831
Plan

The total fund requirement for Generation Captive and Renewable capacity additions
Projects during the 12th Plan is 643,831 Crs. Matching funds are also required for
This fund requirement does not include transmission & Distribution sector.
funds required for R&M of power plants,

----+++----

th
Key Inputs for 12 Plan Chapter 9: Page | 167
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Appendix 9.1

Assumptions for Estimation of Cost of Projects

Assumptions for estimating cost of power projects

(Figures in Rs. crore per MW)

S.No. Type of Generation project Cost


1 Thermal generation projects 6
2 Hydro generation projects 8
3 Nuclear projects 10
4 Captive 5
5 Solar 13
6 Wind 6
7 Other RES 5

*The above costs are based on the FY 2011-12 price levels


# 10% higher costs have been assumed for projects in NE region.

Assumptions for allocation of cost towards 12th Plan

Phasing of expenditure of generation projects during the project construction period, which are
expected to be commissioned in 12th Plan is given as follows:

Particulars Year 1 Year 2 Year 3 Year 4 Year 5 Total


Thermal 15% 25% 30% 30% 0% 100%
Hydro 15% 15% 20% 25% 25% 100%
Nuclear 10% 20% 30% 25% 15% 100%

Phasing of expenditure of generation projects during the project construction period, which are
expected to be commissioned in 13th Plan is given as follows:

Particulars Year 1 Year 2 Year 3 Year 4 Year 5 Total


Thermal 20% 30% 25% 25% 0% 100%
Hydro 20% 25% 25% 15% 15% 100%
Nuclear 20% 25% 25% 15% 15% 100%

th
Chapter 9: Page | 168 Key Inputs for 12 Plan
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 10

INTEGRATED PLANNING BY THE STATES

10.0 BACKGROUND
The erstwhile State Electricity Boards
Government of India has taken a number have been unbundled into separate
of Initiatives to adopt a more pro-active, generation, transmission and distribution
market oriented approach to rid the companies. While this Initiative is
Power Sector of the problems being faced expected to be instrumental in making the
by it. These range from changing the power business economically viable, the
structure of the Power Utilities to the States have a very important role to play
operating environment and the Legislative in carrying out integrated planning of the
and Regulatory framework governing the entire electricity chain from generation to
Power Sector. Most significant changes the ultimate consumer such that all the
have been the unbundling of the vertically systems are adequate and are set up
integrated business of generation, within a matching timeframe. This
transmission & distribution and the entry Chapter outlines the planning to be
of private sector in power generation, undertaken by each state in a cohesive
transmission & distribution. These manner.
Initiatives are expected to set the stage
for a quantum jump in the capacity 10.1 CREATION OF STATE ELECTRICITY
addition programme and also making BOARD
electricity available to all including rural
households. The beginning of power supply industry in
the country was through private
The Electricity Act 2003 envisages a strong entrepreneurial initiative and as a principle
push to the structural reforms, de- the generating plants were established
licensing, thrust on rural electrification, close to load centres. The emergence of
incentives to reforming States and grid systems to connect and operate the
importantly mandatory metering with isolated generating units to improve
stronger provisions for punishment for economics and reliability of supply was
theft of electricity. The National Electricity recognized during the forties. A
Policy and the Tariff Policy further provide comprehensive legislation to restructure
guidelines for the development and the power supply industry was made with
operation of the Power Sector within the the enactment of the Electricity Supply
ambit of the Electricity Act. Act 1948. This Act provided for the

Integrated Planning by the States Chapter 10: Page | 169


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

creation of State Electricity Boards (SEB) all the Stakeholders as well as it is put up
with the responsibility of promoting on the CEA Website inviting comments of
generation and supply in an efficient and all. The Plan is finalised based on
economic manner and extension of power comments received, as considered
supply facilities in the country. The role of appropriate.
Private Sector for development of Power
at this stage was minimal with private The National Electricity Plan is prepared to
entrepreneurs only in Ahmedabad, serve as a road map towards optimum
Calcutta and Bombay being in the field. growth of the Power Sector. It is based on
an approach of integrated resource
10.2 ELECTRICITY ACT 2003 AND planning so as to optimally utilize the
NATIONAL ELECTRICITY POLICY resources including investments already
made. The Plan is evolved as a result of
Enactment of the Electricity Act, 2003 was detailed studies carried out using
aimed at addressing the problems which sophisticated generation planning
were plaguing the Power Sector in the software models available with CEA. The
past. The Act envisages development of Plan contains project-wise details of
the Power Sector in a market driven capacity addition as well as the fuel type
environment, keeping in view the interest of each project. Generation as well as
of the consumers as well as of the Transmission aspects are covered by the
suppliers of power. Generation has been Plan.
delicensed and Open access in
transmission and distribution has been 10.3 RESTRUCTURING OF THE POWER
stipulated. SECTOR

The National Electricity Policy was Creation of the State Electricity Boards
formulated to act as a functional lever to (SEBS) in the fifties was extremely
facilitate implementation of the Act beneficial for the development of the
towards providing the required thrust to Power Sector. Each State developed its
the Power Sector. integrated system from the power plants
to the transmission and the distribution
Section 3(4) of the Electricity Act 2003 network. This facilitated the reach of
mandates CEA to prepare the National electricity to a wide spatially distributed
Electricity Plan in accordance with the area of the country.
National Electricity Policy. The Plan is
expected to function as a facilitating lever However with time, the performance of
for implementation of the Electricity Act the SEBs deteriorated and they gradually
2003 in keeping with its true spirit. The became financially unviable due to
draft Plan prepared by CEA is circulated to mounting losses. This adversely affected

Chapter 10: Page | 170 Integrated Planning by the States


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

their developmental plans and the States transmission and distribution system.
started facing increasing power deficits. Short term and Long term Plans need to
This prompted the Government to be evolved for each State. Some of the
unbundled the States into separate specific reasons for this are as follows:
Generation, Transmission and Distribution
Corporations, each being a separate a) Each State has a varying Load
financial entity. Regulatory Commissions dispatch curve which has to be met by
were also set up in each State under setting up baseload as well as peaking
whose regulatory oversight the operation power plants. Even though the country is
and development of each State took expected to operate in an All India grid by
place. 2012, each State is expected to be
responsible for setting up adequate base
The main problem experienced after load as well as peaking generation
unbundling of the SEBs is that since in capacity. It is therefore necessary for each
each State generation, transmission and State to carry out short term as well as
distribution are under separate long term planning. Long term Plans
Corporations, no coordinated short term covering a period of 10 years are very
or long term planning is being done in important since some power projects
most of the States. This is expected to be specially hydro projects are long gestation
extremely detrimental to the overall ones. Also the planning process needs to
power scenario in the country. ensure that , at potential sites for storage
type of hydro projects these projects are
Earlier, the development in each State built rather than run of the river projects
was in accordance with the planning as these provide peaking power.
exercise being done by CEA. However
subsequent to the Electricity Act 2003, the b) Adequate transmission
developer of a power plant does not network needs to be set up in the same
require any clearance from CEA for setting time frame as the associated generation
up a thermal or a hydro power plant project. Also since the Act and the Policy
below a certain financial limit. Therefore provides for Open Access, sufficient
most of the States do not have a regular transmission capacity needs to be created
planning philosophy or developmental to ensure open access to all consumers as
Plans for their system. required.

10.4 NEED FOR COORDINATED PLANNING c) Distribution, even though a


IN STATES State subject, needs a coordinated
planning commensurate with the
Each State needs to have a coordinated generation and the transmission system.
planning in respect of their generation, Since the Act provides very stringently for

Integrated Planning by the States Chapter 10: Page | 171


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

reliable power, planning may be carried on a priority basis, after considering cost
out for the distribution system also. As and benefits, to facilitate creation of
per the Electricity Act, 2003 it is the prime network information and customer data
responsibility of the Distribution Company base which will help in management of
to develop their distribution network by load, improvement in quality, detection of
carrying out short term and long term theft and tampering, customer
studies to optimize the system network to information and prompt and correct
provide least cost solution, to ensure billing and collection.
voltage at various nodes within stipulated
limits as per IE Rules, Minimise energy 10.5 PROPOSAL AND RECOMMENDATION
losses in the distribution network, FOR SINGLE AGENCY IN EACH STATE FOR
Improve quality and reliability of power INTEGRATED PLANNING
supply etc. Because of multiple agencies
in one supply area, there is a need to have With a view to facilitate coordinated
one single agency to ensure integrated planning in each State covering all aspects
planning for fulfilling the above objectives of the power system, it is necessary to
This agency would coordinate with the have a Single Nodal Agency in each State
developers of generation, transmission, for this purpose. This Agency shall be
distribution and other agencies if any. This designated by each State. It may be
would facilitate development of a robust, effective for the energy department of
most economical and reliable system. the State to perform this function. CEA
shall be the consultant to this Nodal
d) Modern information Agency as it has the requisite expertise for
technology systems need to be planning and is equipped with the suitable
implemented by the distribution utilities software planning tools for this purpose.

----+++----

Chapter 10: Page | 172 Integrated Planning by the States


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 11

FUEL REQUIREMENT

11.0 INTRODUCTION

Fuel for the power project is the main timely completion of the project and
input required to be tied up before therefore avert detrimental implications
implementing the power projects. Coal is of cost and time overruns in case the
the main fuel for the Indian Power Sector power project is delayed.
and it is expected that coal will continue
to dominate the power sector in the next This Chapter broadly deals with a review
few Plans as well. An important aspect of fuel availability during the 11th Plan, an
which therefore needs to be considered is assessment of requirement of fuel for 12th
the availability of adequate coal to fuel Plan & indicative requirement for 13th Plan
the generation of power. Inadequate as well as critical issues which need to be
availability of coal will result in stranding addressed/ constraints being experienced
of generation capacity causing wastage of in the coal sector. This would give
sunken capital expenditure as well as the sufficient inputs to other Ministries and to
perpetuation of power deficit conditions the industry to enable them to take
in the country. Many existing power advance action and plan their production
plants are experiencing generation loss targets etc. according to the requirement
due to non availability of adequate coal. of the Power Sector.
Import of coal is therefore inevitable for
power generation. The timely supply of all 11.1 REQUIREMENT OF COAL
key inputs including fuel would ensure
11.1.1 Coal is the mainstay of India’s of various initiatives being taken by the
energy sector and accounts for over 50% Ministry of Power. The PLF has increased
of primary commercial energy supply. The from 57.1% in 1992-93 to 75.37% in 2010-11.
total power generation capacity ( Utility) This has increased the demand of coal per
of the country is about 1,82,689 MW MW of installed capacity. The growing
as on 31.10.2011, out of which about gap between the demand and the
1,00,098 MW (55%) is coal fired. Of the domestic supply of coal has made it
total power generated in the country, 69% imperative to augment domestic
comes from coal based thermal power production both from public sector and
stations even though they constitute only private sector and expedite the reform
55% of the total installed capacity. The process for realizing efficiency gains
Plant Load Factor (PLF) of the thermal through increased competition in the
power stations in the country has been sector during the 11th Plan.
improving steadily over the years in view

Fuel Requirement Chapter 11: Page | 173


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

11.1.2 The Government has introduced the corresponding to 42.5% for 5 years for
New Coal Distribution Policy (NCDP) that generating stations having PPA for supply
assures supplies at pre-determined prices of power for 25 years.
to some categories of consumers and
reintroduces e-auctions to encourage a 11.1.3 Coal Stocking Norms:
vibrant market for the commodity. The
Main Features of the Policy which is Coal stocking norms for power stations as
effective from 1st April 2009 are as fixed by a Committee headed by
follows: Secretary, Planning Commission depend
on the distance of the power plant from
– 100% Normative Requirement of coal the pit-head as per details given below:
would be considered for supply to
Power Utilities  Pit-head Station
– Supply of coal through commercially 15 days’ stock
enforceable Fuel Supply Agreements  Upto 500 Kms. away from Coal mine
( FSAs) at notified prices by CIL. 20 days’ stock
– 10% of annual production of CIL to be  Upto 1000 Kms. away from Coal mine
offered through e-auction for 25 days’ stock
consumers who are not able to  Beyond 1000 Kms. away from Coal
source coal through available mine 30 days’ stock
institutional mechanism.
– FSAs to indicate Annual Contracted 11.1.4 Import of coal
Quantities (ACQ) of coal to Power
Utilities by coal companies during In the past, Power Utilities were advised
entire year. Incentive and penalty to import coal to maintain the stipulations
clauses incorporated in FSAs. of Ministry of Environment and Forest
regarding use of coal of less than 34% ash
Signing of Fuel Supply Agreement (FSA) content and also to occasionally
for the Units Commissioned after 31st supplement the coal from indigenous
March, 2009: sources. The quantity of coal imported by
the power stations during the previous
For thermal power plants commissioned years is as given below:-
before 31st March, 2009, FSAs were (In Million Tonnes)
signed with a trigger value of 90% of the Year Target Actual
Annual Contracted Quantity (ACQ). 2004-05 10.0 4.5
2005-06 13.5 10.4
FSAs for thermal power plants 2006-07 20.0 9.7
commissioned after 31st March, 2009 2007-08 12.0 10.2
have not been signed , primarily due to 2008-09 20.0 16.1
CIL’s insistence for (a) keeping the 2009-10 28.7 24.6
assured supply as low as 50% of ACQ and 2010-11 35.0 30.5
(b) signing the FSA for 5 years. ACQ for 2011-12 55.0 33.7(Upto
new power plants generally being Dec, 2011)
commensurate with 85% PLF, this will
tantamount to assured supply of coal

Chapter 11: Page | 174 Fuel Requirement


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

As per the demand-supply analysis of 11.1.5 Capacity Addition Programme and


domestic coal, done above, import of non- Coal Requirement
coking coal is expected to increase by the
end of 12th Plan period is needed to meet A capacity addition target of 78,700 MW
the demand of power sector. The present has been fixed for the 11th five-year Plan
port capacity can handle around 55 MT of which has been revised to 62,374 MW
thermal coal and would need to be during Mid Term Appraisal (MTA) by
augmented to meet the rising coal import Planning Commission. All out efforts are
forecasted. Further, imported coal can be being made to realize this capacity within
used as a blend with the domestic coal to the stipulated time-period
substitute requirement of washed coal,
which is required for Power Stations to (i) Coal Supply position for the period
adhere with MoEF’s stipulation. Such a April 2011- December 2011: During the
situation would also ease the problem of period April 2011- December 2011, CIL has
handling washery rejects. However, high dispatched 223.2 MT against the target
cost of imported coal will have adverse of 347 MT for 2011-12.
impact on the power tariff.
Source wise programme and receipt for
the month of April 2011 - December 2011
vis a vis last year is given below:

April, 2010-December 2010 April 2011- December, 2011 Growth


Source ACQ/Pro- Despatch*/ % ACQ/Pro- Despatch*/ % in
rata Receipt rata Receipt Receipt
Program Program. (%)
CIL 241.2 221.3 91.7 256.8 223.2 86.8 0.77
SCCL 22.3 24.1 108.1 24.2 23.8 98.3 (-)1.24
CAPTIVE 15.8 16.8 106.3 16.28 19.3 118.6 14.9
IMPORT 34.5 20.8 60.3 41.25 33.7 81.7 62.0
TOTAL 313.8 283.0 90.2 338.5 301.1 88.9 6.4

* Despatch in case of CIL. (ii) Coal Demand and Availability


Position during the Year 2011-12:
From the above Table it may be seen For the year 2011-12, a coal based
that the growth in supplies from CIL is
capacity addition programme of around
marginally lower in comparison to the
same period previous year. 12375 MW is envisaged. The coal
requirement for the indigenous coal
based thermal units vis-a-vis coal
availability from indigenous sources and
coal requirement for plants designed on
imported coal is detailed below:

Fuel Requirement Chapter 11: Page | 175


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

SNo Description 2011-12 From the above, it may be seen that


there is a shortfall of 53 MT in the
1.1 Coal requirement for plants 455
availability of indigenous coal. In order
designed on indigenous Coal
1.2 Coal requirement for plants 20 to bridge this shortfall, power utilities
designed on imported coal have been advised to import 35 MT of
1.3 Total 475 imported coal. Apart from this, 20 MT
2. Coal Availability from of imported coal is required for power
indigenous sources stations designed to run on imported
2.1 From CIL Sources 347 coal.
2.2 From SCCL 33
(iii) 12th PLAN
2.3 From captive Mines 22
2.4 Total coal availability from 402 Considering 62,374 MW capacity
indigenous sources additions in 11th Plan, three Scenarios
3. Shortfall of indigenous coal 53
(1.1 – 2.4)
have been worked out based on 18th EPS
4.1 Coal to be imported to meet 35 Demand projections. As per the Base
the shortfall for plants case, the details of likely capacity
designed on indigenous coal addition during 12th Plan is as follows:-
4.2 Coal requirement for plants 20
designed on imported coal

Exhibit 11.1
TYPE WISE CAPACITY ADDITIONS DURING 12th PLAN
(Figs in MW)
TYPE 12thPlan Capacity
th
(With 18 EPS demand + 5% S.R.) (MW)
Hydro 9,204
Thermal 67,686
Coal 66,600
Gas 1,086
Nuclear 2,800
TOTAL 79,690
Wind 11,000
Solar 4,000
Other RES 3,500
TOTAL (RES) 18,500
Retirement During 12th Plan 4,000

Coal demand and availability during 12th accorded to maximize generation from
plan other conventional and non-conventional
sources, coal based generation is likely to
Availability of coal for the coal based be the main stay of electricity generation
thermal power stations is a matter of for 12th and 13th Plan to support the
serious concern. Although thrust is being targeted GDP growth envisaged by the

Chapter 11: Page | 176 Fuel Requirement


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Government. The coal based capacity MT coal likely to be imported by Thermal


addition programme is worked out after Power Stations designed on imported
taking into account the electricity coal. Therefore, the total quantity of coal
generation availability from other sources expected to be imported is about 218 MT.
i.e. Hydro, Nuclear, Gas, Lignite and
renewable sources. 11.1.6 Issues/Constraints in making coal
In order to meet this generation available to power stations
requirement, coal requirement (at SPCC
0.73 Kcal/ Kg) works out to around Timely availability of adequate coal is
842MT. Against the requirement of 842 extremely crucial for maximizing
MT, 54 MT coal is to be imported by generation from the power plants. In
Thermal Power Stations designed on addition to tapping fuel source or
imported coal. SCCL has confirmed a coal organizing its availability, it is also
availability of 35 MT and around 100 MT essential to create the infrastructure to
coal is expected to be available from facilitate fuel to reach the intended
captive coal blocks. Thus, 653 MT coal destination. Therefore development of
needs to be made available by CIL against mines/ ports and requisite transportation
which they have committed to supply 415 facilities commensurate with the
MT. Thus, CIL is to be impressed upon for completion of the projects is very
formulating exigency plan to enhance necessary. The gestation period in the
their production to meet the requirement development of mines and even transport
the power stations. The facilities are in some cases longer than the
availability/shortfall of indigenous coal is gestation period for setting up of thermal
detailed below: power stations. It is therefore imperative
for the Power Sector to make its
(i) Coal requirement during the year prospective coal requirement, over a long
2016-17 = 842 MT time horizon, known to the Ministry of
(ii) Coal availability from : Coal, Railways and port authorities to
enable them to undertake co-ordinated
(a) CIL = 415 MT development of coal mines and transport
(b) SCCL = 35 MT infrastructure with the coming up of
(c) Captive Blocks allocated to Power thermal power stations.
Utilities = 100 MT
(d) Coal to be imported by TPSs 11.2 COAL WASHERIES IN INDIA
designed on imported coal 54 MT
Total, coal availability = 604 MT In India, 20 percent of coal produced is
Shortfall = 238 MT washed as against a global average of 50
percent. Coking coal preparation has long
In order to bridge the above gap between been in operation in India but recently,
demand and coal availability as referred the trend has been shifted to washing of
above, Power Utilities are expected to non coking coal due to environmental and
import around 164 MT to meet shortage efficiency concerns. The long distance
in coal supply from CIL. This quantity of transportation of coal via land routes
imported coal would be in addition to 54 offer an ideal opportunity for coal

Fuel Requirement Chapter 11: Page | 177


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

washing in India because of economic international competitive bidding to


benefits. Though coal washery increases develop 22 coal Washeries in different
the overall cost of coal, but the benefits parts of India. 66 players have evinced
accrued in terms of saving in their interest to develop coal Washeries
transportation, O&M cost and efficiency for the first phase (11 coal Washeries) of
are sustained. competitive bidding. It has earmarked a
whopping Rs 5000 crores for coal
The quality of Run of Mine (ROM) coal washery development to increase the
from Indian mines is continuously capacity from 120MTPA to 250MTPA in 4
decreasing due to the geographical years of time.
pattern of coal seams in coal bed. This
very nature of coal quality from coal Strategies for improvement of domestic
seams demand coal washing, providing coal production
bullish market opportunity for national
and international players to enter the
 Use of State-of-the art technology for
lucrative washery segment of Indian coal
improvement in efficiency &
sector.
productivity in coal mines and related
The guidelines set by MOEF to use coal Policy changes:
containing ash not more than 34% for To facilitate adoption of State-of-the-
power plants situated at a distance more art International coal mining
than 1000km has changed the scenario technology, high output – high
completely. Out of the projected capacity
efficiency HEMM, new technology in
addition during the 11th plan, about 27% of
planned capacity would be located at Mine Safety, etc., further liberalization
more than 1000km. of import policies by the Indian
government is needed. In addition to
As the pressure from environment it, Coal Sector may be given
brigade is mounting, MOEF is seriously “Infrastructure Status” with ‘Tax
thinking to bring the required norms for
Holiday’ & Duty exemptions.
using 34% washed coal beyond a distance
of 500km.This will open a huge Alternatively, the concept of Mega
opportunity for private players to enter Project may be introduced in the coal
into the coal washing segment of India. sector also by according Mega Status
Currently, India has more than 100 million to Coal Mines of production level of 5
tonnes of non coking coal washing MTPA or above and providing
capacity. benefits of tax / duty concessions.
CIL has been in the fore front in
developing coal Washeries but due to  R&R Policy for Coal Mining Industry:
man power constraints coupled with cost Resettlement and rehabilitation policy
of the operation, it has decided to needs to be evolved to protect the
outsource this operation to private livelihood of project-affected people.
players in BOM (Build, Operate and To bring in clarity and uniformity –
Maintain) basis. It has planned for
Nationwide, a uniform R&R policy

Chapter 11: Page | 178 Fuel Requirement


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

needs to be formulated which should development of that land so that


be adopted by all coal producing cultivation can again be done. The
companies in India. With increased use Agency/Organization, engaged in coal
of state-of-the-art technology and mining in a particular block, will
sophistication, more automation & remain responsible for development &
computer control in coal mining return of the land.
operation, less manpower deployment
will be required in the new mines and  Expeditious clearances for
thus there will be less job development of Coal Mining Projects:
opportunities. So, while formulating Govt. support in terms of simplified
National R&R policies for coal mining, procedures and single-window
this aspect may also be looked into approach for granting of various
and suitable alternatives, beneficial for clearances and permissions, including
upliftment of livelihood of the environmental clearance, faster
displaced persons, may be agreed investment decisions, closer
upon. Moreover, in order to avoid coordination between the Centre and
erosion of land compensation amount the State Govt. agencies etc. would be
by the land oustees in a short span, a needed for speedier execution of coal
suitable mechanism like Interest- mining projects.
carrying deposits of land
compensation amount – part or full in
a suitable fund created by the mine  Captive Coal Mining
owner, issuance of Bonds, etc., may be Coal production, modernization and
explored. efficiency improvement would depend
on the level of competition in the
Unlike other industries, coal mining industry. Mobilization of the requisite
industry does not require investment in coal mining also
establishment of permanent fixtures reinforces the need to induct more
over the entire acquired land, hence players from both the public and
the some of the land, after mining, can private sectors. The introduction of
be used for cultivation with proper new players in the coal sector would
development like earth-filling & be beneficial to the sector as a whole
putting in of fertilizers, etc. R&R Policy and is considered essential. It would
for Coal Mining may look into another also be essential to gradually increase
dimension like taking of agricultural the production through captive mining
land from local people on term-lease & of 40 to 50 % of the total production of
returning of land to the extent the country. Reputed International
possible in an area where mining Coal Mining Companies may be
operation is completed after proper encouraged to come to India for
Fuel Requirement Chapter 11: Page | 179
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

development & operation of coal reporting must be done in a


mines which will facilitate introduction transparent manner and in electronic
of latest mining technology & mine form.
safety measures
 To ensure adequate exploration of
 State Governments must become coal mines and reliability of estimates
partners in development of coal of extractable reserves
i. There is a need to incentivise It is needed to speed up our efforts to
states from mining operation. accelerate the pace of regional
ii. Before the allocation of blocks, surveys and drilling to complete the
concerned Sate Govt. may be comprehensive coal resource
consulted with and made party assessment exercise. Therefore, there
to it, as mining of coal in their is a need to enrol more specialist
States would directly and agencies to conduct exploration of
indirectly benefit that blocks and prepare GRs, so that
particular state. production from blocks can start in a
iii. In mineral rich states, a timely manner.
separate cell may be made
operational for land acquisition  Commercial coal mining by private
process, processing of sector
proposal related to The need to provide adequate
environment and forest investments in coal mines, conserve
clearance (Single window coal reserves ensure mine safety and
approach through MOU), etc. environmental protection and to
iv. Coal-bearing states, in addition assure decent living standard for the
to Royalty, may be incentivised coal labour was the basic reason for
for their co-operation in start nationalization of coal mines during
of mining in a time-bound 1971 and 1973.
manner. In this regard, Coal Mines
(Nationalisation) Amendment Bill,
 Special Task Force for monitoring the 2000 is a step towards promoting
progress of project implementation liberalisation in the coal sector. It will
A special Task Force may be in place also address the need for augmenting
for periodic review & monitoring of coal production in the country
the progress of coal mining projects. It through wider participation of private
will prevent any slippage, help in coal mining companies. The proposed
clearances / approvals and ensure amendment bill is pending for long
timely commencement of production time to be expedited
of coal. Such monitoring & status

Chapter 11: Page | 180 Fuel Requirement


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Coal price pooling: expenditure on freight and avoidable


overloading of Indian Railways network
The concept of pooling of price of and creating other logistic problem.
domestic and imported coal is Transporting coal from such a long
necessitated due to the fact that the distance also increases transit loss
production of domestic coal is not thereby reflecting in the bottom line of
increasing commensurate with the generating utilities. Since the fuel price is
requirement of coal for power stations generally pass through in the tariff, higher
which are existing and are being planned, freight charges will certainly increase the
based on domestic coal. Most of the new tariff resulting in higher cost of electricity
Power Utilities would be required to to the consumers. The situation thus
import coal to bridge the gap between needs to be rationalized to the extent
their requirement and availability of feasible.
domestic coal.
A solution to this problem could be the
Coal for thermal power plants is allocation of coal to Power Utilities from
predominantly being imported from the nearby coal source to the extent
countries like Australia and Indonesia possible to minimize transportation cost.
which has a high Calorific Value ranging Power Utilities located in coastal areas
from 6000-6500 Kcal/ Kg with low ash may be asked to use larger chunk of
content. Major ports for import are imported coal being nearest to the port
Mundra, Vizag, Gangavaram, Ennore, subject to design limitations. Most of the
Tuticorin, Pipavav etc. Transportation coal mines of Coal India Ltd. are located in
cost from these ports to power plant site Central India giving almost an equal
which are not in the coastal region or not distance of coal transportation from coal
in the state where these ports are located mine to a majority of Power Stations.
may be as high as Rs. 1500 per tonne. Therefore, the Power Utilities which are at
a larger distance from ports may be
Coal for the Power Utilities in the country allocated coal from the mines of Coal
is being transported by Indian Railways India only and be asked to use imported
and most of their routes are already coal only in the case of shortfall to avoid
facing congestion due to heavy unnecessary double movement of coal
movement of traffic. There is cross rakes.
movement of coal from port to Power
Utilities located in Central India and from It is accepted fact that the cost of
domestic coal mines to Power Utilities imported coal is higher than domestic coal
located in coastal or adjoining areas. This even after accounting for its higher GCV,
is causing duplicate movement of coal at present rate it is almost two and half
rakes and causing unnecessary times costlier than domestic coal on heat
Fuel Requirement Chapter 11: Page | 181
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

value basis. This could be a deterrent to facilities at power stations to the extent
the Power Utilities at coastal areas which possible.
would be asked to use a higher chunk of
imported coal as it will increase their cost Pooled price is to be evaluated based on
of generation. the heat value(Rs/Kcal) of the coal. CIL
shall be responsible for importing coal
A case, therefore, exists for importing and levying the pooled price on the
coal to bridge the gap between various power utilities. This is reasonable
requirement and availability of domestic in view of the fact that the New Coal
coal and the cost of the same to be Distribution Policy stipulates that CIL is
equitably borne by all the power utilities. responsible for meeting 100% of the
It may however be mentioned that the normative requirement of coal of the
concept of pooling cost is to be applicable power utilities, and import of coal may be
to power stations designed for domestic resorted to the extent required.
coal only. Imported coal based stations
and stations linked to dedicated coal Demand side management of Coal
blocks are not to be considered in this
pooling mechanism. All the new units planned in12th plan
(excluding which are already under
Following categories of power plants may construction) thrust to be given for super
be accorded higher preference for critical technology, which will result in
utilizing imported coal (subject to 15% saving of about 5-8 % of fuel requirement
blending with imported coal for existing and correspondingly less emission. As,
stations and upto 30% blending for new coal is increasingly becoming a scarce
stations) under the pooling of price resource, India’s long term fuel security
concept:- depends on its efficient utilization. In
 Coastal power stations order to optimally utilize coal, efficient
 Stations where availability of coal consumption (heat rate and auxiliary
indigenous coal is a major consumption) norms be used for
constraint. according linkage (FSA).
 Stations situated at long distances
from pithead e-Auction of coal
 Stations which have to comply
with MOEF stipulations on ash As per NCDP, around 10% of total
content. domestic coal production is allowed for e-
Auction by CIL. It is to be ensured that
The above are to be prioritized before offering 10% quantity, FSA/MOU
considering the existing coal handling commitments are met with. The issue of
rail connectivity to such mines from

Chapter 11: Page | 182 Fuel Requirement


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

where coal for e-auction is sourced should to coal conservation thereby maximising
be taken up immediately. percentage of coal recovery from
geological blocks.
Coal Regulator
The Regulator must standardise norms of
A need is being felt for long to institute an operation, establish benchmarks and
independent regulatory body to regulate ensure that coal companies raise their
the upstream allotment and exploitation level of competence to be at par with
of available coal blocks to yield coal, coal international standards.
bed methane, coal-to-liquid and for in-situ
coal gasification. The proposed The proposed Coal Regulator should also
Regulatory Body, as an interim measure, be entrusted with following aspects of
may approve coal price revisions, ensure coal mining:
supply of coal to the power sector under  Coal Resources Management
commercially driven long-term FSAs,  Safety, Health, and Employment in
facilitate the development of coal mines
formulae/indices for resetting coal prices  Prices, Taxes, Royalty, Value Added
under long-term fuel supply agreements, Tax, Property Tax, and Salary of
monitor the functioning of the proposed Workers
e-auctions, ensure that the price discovery  Environment Management
through e-auctions is free of distortions,  Policy-Legal, Public Relations,
regulate trading margins, develop a Statistics, and Dispute Resolution
mechanism for adequate quantities of  Recommendation to CIL for issuance
coal imports under long-term contracts to of LoAs
bridge the gap between supply and  Approval of mine plans including mine
demand thereby assuring that the e- closure plans
auctions and consequent price discovery  Optimization of current linkages to
does not take place in a supply minimize Rail/Road transportation
constrained market and, finally, create the  Oversight role on captive coal block
environment for a competitive coal auctions
market to operate.
 Dispute resolution - primary forum for
:
Once a competitive market is developed,
 dispute resolution among entities;
the role of Regulator in determining the
 entities aggrieved due to decisions
prices would be to ensure a free and
given by MOC/MOEF relating to mine
transparent market for coal. The
closure, etc.
Regulator must ensure that mines are
planned, designed and developed in a
scientific manner giving due importance
Fuel Requirement Chapter 11: Page | 183
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

11.3 LIGNITE thermal power stations subject to cost-


economics, particularly in the states of
Lignite reserves in the country have been Tamil Nadu, Rajasthan and Gujarat having
estimated at around 40.9 Billion tonnes, the limitations of transportation of coal to
most of which is found in the state of these regions. State-wise distribution of
Tamil Nadu. About 82 % of the Lignite Lignite resources, Lignite Demand &
reserves are located in the State of Tamil Production Plan by M/s. Neyveli Lignite
Nadu & Pondicherry. At present only a Corporation Ltd. (NLC) and Lignite
small percentage of the total reserves of Demand & Production Plan by State
lignite have been exploited. Considerable Electricity Board are shown in Table- 7.6
scope remains for the exploitation of the to 7.8
lignite reserves and use of lignite in
Table–7.6
State-wise Lignite Reserves

State Total[MT]

Tamil Nadu 33309.53

Rajasthan 4835.29

Gujarat 2722.05

Jammu & Kashmir 27.55

Others (Kerala, West Bengal) 11.44

Total 40905.86

Table -7.7

Lignite Demand & Production Plan by M/s. Neyveli Lignite Corporation Ltd. (NLC)

Item 2012- 2013- 2014- 2015- 2016- 12th


13 14 15 16 17 plan

Demand(MT) 25.60 26.12 25.91 25.37 27.26 130.27

Production 26.01 26.01 26.01 26.01 27.29 131.33


(MT)

Demand- 0.41 -0.11 0.10 0.64 0.02 1.05


Production
Gap (MT)

Chapter 11: Page | 184 Fuel Requirement


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Brief year-wise anticipated demand & companies (other than NLC) during
production plan of Lignite by other 12th five year plan period are shown
State Electricity Boards and private below (TABLE 7.8).

Table 7.8
Lignite Demand & Production Plan by State Electricity Board

Item 2012-13 2013-14 2014-15 2015-16 2016-17 12th plan

Rajasthan Rajya Vidyut Utpadan Nigam Limited

Demand(MT) 8.4 8.4 10.5 10.7 10.7 48.7

Production (MT) 5.4 6.1 10.6 13.1 13.1 48.3

Demand-Production Gap (MT) -3 -2.3 0.1 2.4 2.4 -0.4

Gujarat Industries Power Company Ltd.

Demand (MT) 3.6 3.6 3.6 8.1 8.1 27.0

Production (MT) 3.6 4.2 5 8.4 8.4 29.6

Demand-Production Gap (MT) 0 0.6 1.4 0.3 0.3 1.4

 Immediate steps needed to augment lignite production considering large reserves of


lignite in the country. The technology issues for efficient utilization of lignite
resources need to be addressed.

11.4 NATURAL GAS: of Natural Gas has sharply increased in the


last two decades at the global level.
(i) With only one carbon and four
hydrogen atoms per molecule, Natural In India, the natural gas sector has gained
Gas has the lowest carbon to hydrogen importance particularly over the last
ratio, hence it burns completely, making it decade and being termed as the Fuel of
the cleanest of fossil fuels. Natural gas the 21st Century. The demand of Natural
satisfies most of the requirements for fuel Gas in power sector has ramped up in the
in a modern day industrial society; being last decade but the supply is not keeping
efficient, non-polluting and relatively pace with demand.
economical. The periodic uncertainties
and volatility in both the price and supply
of oil have also helped Natural Gas
emerge as a preferred fuel in the energy
basket across the countries. The demand

Fuel Requirement Chapter 11: Page | 185


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

(ii)Supply of Gas to Gas based power demand of gas in the country, including for
plants: that of power sector. Supply of gas to gas
based power plants during last few years
The production and supply of gas had not had been as under:
been keeping pace with the growing

Table 7.9

Sl. Years Capacity at the Gas Required* Aver. Gas Shortfall


No. end of year (MMSCMD) Supplied (MMSCMD)
(MW) (MMSCMD)
(1) (2) (3) (4) (5) (6)=(4)-(5)

1 2000-01 9028.70 44.54 24.40 20.14

2 2001-02 9432.90 46.31 24.33 21.98

3 2002-03 9949.00 48.26 25.12 23.14

4 2003-04 10,154.90 49.25 25.62 23.63

5 2004-05 10,224.90 49.73 30.70 19.03

6 2005-06 10,919.62 53.38 35.37 18.01

7 2006-07 12,444.42 61.18 35.10 26.08

8 2007-08 13,408.92 65.67 38.14 27.53

9 2008-09 13,599.62 66.61 37.45 29.16

10 2009-10 15,769.27 78.09 55.45 22.64

11 2010-11 16,639.77 81.42 59.31 22.11

12 2011-12 16,676.27 81.44 57.67 23.77


[Apr.-Oct.
2011)
to depletion of these fields. In view of low
The production of gas from KG basin (D-6) availability of domestic gas, existing
has started from April 2009. So far, EGoM power plants in the country are getting
has allocated gas to the existing power lesser supply of gas resulting in sub-
plants based on anticipated production of optimal utilization of these power plants.
about 90 MMSCMD from KG-D6 basin.
Presently, the production from KG-D6 has The average gas supply during 2011-12
come down to about 40 MMSCMD against [April to October 2011) was 57.67
the firm production of about 60 MMSCMD MMSCMD against the requirement of
last year. The gas production from other 81.44 MMSCMD (as on 31.10.2011) to
old fields is also reducing day by day due operate the stations at 90% PLF, which

Chapter 11: Page | 186 Fuel Requirement


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

was sufficient to operate these stations at generation was augmented by use of such
about 63.73% PLF. fuels. On account of the prevailing high
costs of liquid fuels resulting in high cost
(iii). Generation loss due to gas shortage of generation, the actual generation using
these fuels was, however, dependent
There was a shortage in availability of gas. upon the requirement/acceptance by the
This resulted in loss of generation of beneficiaries. Loss of generation due to
power. In case of gas based power shortage in availability of gas as reported
stations having provision for the use of to CEA and based on possible operation of
alternate fuels, such as naphtha, HSD, power plants at 90% PLF were as under:

Table 7.10

Generation Loss during the year (BUs)

S. Year As reported to CEA by Gas Based on possible operation


No. Based Power Stations of gas power plants at 90%
PLF
1 2004-05 7.03 23.71

2 2005-06 7.69 23.88

3 2006-07 8.06 26.33

4 2007-08 9.34 31.17

5 2008-09 11.99 33.71

6 2009-10 3.24 25.02

7 2010-11 6.39 28.27

8 2011-12 2.90 19.44


(Apr.-Oct.
2011)

(iv) Steps taken by the Government to ● MOP&NG is taking necessary steps to


overcome the gas shortage augment production of natural gas
from the gas fields/wells.
Government of India has adopted a multi-
● MOP&NG is taking necessary steps to
pronged strategy to augment gas supplies
increase availability of gas from
and bridge the gap between supply and
domestic sources by awarding gas
demand for the domestic market. These
blocks for Exploration & Production
include:-
(E&P) activities in various sedimentary

Fuel Requirement Chapter 11: Page | 187


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

basins of the country under the New Prices” under the Chairmanship of
Exploration Licensing Policy (NELP). Saumitra Chaudhary. The committee
● MOP&NG is encouraging import of gas has submitted its report in August,
in the form of Liquefied Natural Gas 2011. The committee has emphasized
(LNG) and also making efforts for for increasing share of RLNG in the
import of gas through international Power Sector.
pipelines projects.
● In order to explore and produce new (v) Gas Requirement for power sector
th
sources of natural gas from coal for 12 Five Year Plan
bearing areas, government has
formulated a Coal Bed Methane (CBM) A capacity addition of about 80,000 MW
Policy providing attractive fiscal and may be required in power sector to meet
contractual framework for exploration the growing demand of power during the
and production of CBM in the country. 12th Five Year Plan. Due to uncertainty in
● Government is encouraging Under availability of domestic gas, a gas based
Ground Coal Gasification (UGCG) and capacity of only 1086 MW has been
coal liquification and investment by considered for the 12th Plan i.e. only those
private entrepreneurs in development projects in case of which gas is assured
of these frontier technologies. The from local sources. However, there is an
notification specifying coal gasification urgent need to plan for additional gas
and liquefaction as end-uses has been based capacity to the tune of 25,000 MW
published in the Gazette of India on depending on the availability of gas. Bulk
12th July, 2007. of this capacity could be developed in
● Implementation of Natural Gas next 3 years at the brown field sites or
Hydrate Programme (NGHP) for green field sites where land is already
evaluation of hydrate resources and available. This additional GT capacity will
their possible commercial exploitation. help in meeting particularly the shortfall
● Efforts are also being made to which is expected due to delay in
persuade Government to accord commissioning of the ongoing thermal
priority to Power Sector while and hydro projects.
finalizing Gas Utilization Policy of the
Government for all future domestic By the end of the year 2012-13, a
gases. substantial coal based capacity is going to
● While allocation was made for RIL gas be operationalised. The base load
from KG basin (D-6), the power sector requirement by the country will be met
has been given priority. from nuclear, pit head coal based
● Planning Commission had constituted generation and partly by non pit-head
an Inter-Ministerial Committee on coal based generation and gas based
Policy for Pooling of Natural Gas generation. The intermediate and peak

Chapter 11: Page | 188 Fuel Requirement


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

load is required to be met by hydro, non- may have to plan our gas based
pit head coal based generation and gas generation at an average PLF of around
based generation. The wind, solar and 70 - 75%.
small hydro will be “must run” generation
and will have to be accommodated by The additional gas requirement for 12th
backing down thermal generation. Thus, plan is worked out as under :
by the end of year 2012-13/2013-14 , we

Table 7.11
th
12 Plan Gas Requirement

Particulars Gas capacity Gas requirement at 70% PLF


in MW (mmscmd)
CCHP Capacity 2,000 8.0
Gas based capacity at the brown field 21,000 78.0
sites or at green field sites
Peaking Gas based capacity to be located 2,000 4.0 *
near large cities
Total 25,000 90.0
* Considering operation for about 5-6 hours daily for peak load and in contingencies

Pooling of domestic gas with imported purchase of fixed percentage of power


RLNG can be one solution to reduce the may be made mandatory by the
shortage of gas. Based on capacity of Regulatory Commissions, so as to make
exiting/proposed LNG terminals in the the gas based power having higher tariff
country, it is felt that additional 40-50 despatchable.
MMSCMD gas can be made available for
power sector by 2012-13, which can (vi) Total Gas Requirement by Terminal
support about 10,000-12,000 MW Year of 12th Plan (2016-17)
additional gas based power plants in the
country. LNG being costlier fuel, can be It is expected that total gas based
pooled with domestic gas and the installed capacity in the country by the
common pooled pricing of Natural Gas end of 11th Plan would be about 20,000
may be implemented as a policy directive MW. Based on normative requirement of
and this will give the much needed 4.8 MMSCMD gas per 1000 MW at 90 %
impetus to the growth of Gas based PLF, gas requirement for these projects
generation in the country though it may works out to 96 MMSCMD.
increase the cost of generation. Due to
inherent advantages of gas based
generation being green power, the

Fuel Requirement Chapter 11: Page | 189


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Details of fuel requirement during below:


terminal year of 12th Plan are summarised

Table 7.12

GAS REQUIREMENT FOR TERMINAL YEAR OF


12TH PLAN (2016-17) *
Gas requirement by 11th Plan 98.4 MMSCMD
end
Requirement for 12th Plan 90 MMSCMD
Projects
Total Gas requirement by 12th 188.4 MMSCMD
Plan end
* This requirement corresponds to 20,500 MW gas based installed capacity likely by 11th Plan end and
90 MMSCMD gas required to promote 25,000 MW new capacity during 12th Plan.

11.5 NUCLEAR DEVELOPMENT The India’s nuclear power strategy has


depended on a three stage development
The Government has introduced the New programme consisting of conventional
Coal Distribution Policy (NCDP) that nuclear reactors in the first phase, fast
assures supplies at pre-determined prices breeder reactors in the second phase and
to some categories of consumers and thorium based reactors in the third phase.
Expansion of capacity in atomic energy Successful transition to the third phase
has been limited in the past due to the will enable us to explore India’s vast
lack of availability of domestic uranium or thorium resources to become much more
the non-availability of supply of energy independent beyond 2050. If we
international supply of uranium fuel depend on domestic uranium resources,
because of the restrictions imposed by the first phase plants cannot exceed
the Nuclear Suppliers Group. These 10,000 MWe from PHWR. A cap of 10,000
restrictions have now been lifted and we MWe would have limited the scale and
can expect a much faster expansion in our pace of fast breeder reactor programme
nuclear generation capacity. DAE and therefore, the production of
envisages to add 2800 MW in the 12th plutonium which determines the rate at
Plan based on domestic manufacturing which thorium based nuclear plants can
capability and additional 18,000 MW be mobilized. With the lifting of NSG
during 13th Plan. Despite availability of restrictions, import of uranium would
imported uranium, we must give priority enhance the capacity base of our first
to domestic development of uranium stage programme. Government has taken
mines. This would enable faster steps to import nuclear fuel from NSG
development of the sector. members and reactors from the nuclear
equipment suppliers to enhance the

Chapter 11: Page | 190 Fuel Requirement


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

capacity base in the country. 300 tonnes approval for five coastal sites to set up
of Uranium concentrates has already been nuclear power parks of 6000 to 10000
imported from France. Steps are on to get MWe capacity based on LWRS with
long term supply of 2,000 tonnes of cooperation from Russian Federation,
Uranium pellets from Russian federation USA and France. A total LWRs capacity of
in a phased manner. 40,000 MWe is possible to be added
progressively by 2032 depending up on
The Fast Breeder Reactor programme is the actual start of work on these reactors.
set to be launched with the prototype 500 The spent fuel of LWRs is planned to be
MWe Fast Breeder reactor plant being reprocessed and deployed in safeguarded
built at Kalpakkam, which is likely to be FBRs and additional PHWRs. This would
commissioned by March 2012. This is first further enhance the FBR capacity in the
of its kind project in India and is being long term and thus increase the role that
implemented by the BHAVINI, a public nuclear energy can play in long term
sector company set up to build this energy security. without the need for any
project and all future fast breeder reactor further import of nuclear fuel. This would
projects. Successful commissioning of this significantly increase the role that nuclear
project would go a long way in achieving energy can play in our long term energy
the three stage development of India’s security.
nuclear power programme for the future.
The 3rd phase of the 3-phase nuclear
DAE envisages start of work on eight units energy program, has several complex
of indigenous 700 MWe PHWRS in the 11th technological issues to be tackled before
Plan for commissioning during 13th Plan. our ability to use Thorium. A clear analysis
Four units have been already approved and assessment of the need of additional
and work has commenced. These are Manpower, R&D investment and new
slated for commissioning in 2016/2017. facilities are called for including the
Work is also planned to be started on elements to be covered in the remaining
LWRs based on international cooperation. 11th plan period. Schedules are of serious
The Government has accorded in principle concern on this front.

---+++---

Fuel Requirement Chapter 11: Page | 191


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Chapter 11: Page | 192 Fuel Requirement


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 12

ENERGY CONSERVATION AND DEMAND-SIDE MANAGEMENT

12.0 BACKGROUND by about 20-25%. Yet there are places


where energy efficiency opportunities
continue to exist largely because of a
The gap between electricity supply and
range of market failures, information,
demand in terms of both capacity (i.e.
risks and split incentives. This has led the
MW) and energy (i.e. MWh) has been
Government of India through the Energy
steadily growing in India. Improving the
Conservation Act and the Bureau of
efficiency with which energy is used to
Energy Efficiency to launch several
provide economic services meets the dual
programs.
objectives of promoting sustainable
development and of making the economy The Energy Conservation Act (2001) is the
competitive. Energy Efficiency & most important multi-sectoral legislation
Conservation has also assumed enhanced in India and is intended to promote
importance with a view to conserve efficient use of energy in India. The Act
depleting energy resources and Energy specifies energy consumption standards
Efficiency is being increasingly recognized for equipment and appliances, establishes
as the most cost-effective option in the and prescribes energy consumption
short to medium term to meet the energy norms and standards for designated
requirements of increased economic consumers, prescribes energy
growth and while minimizing the impact conservation building code for efficient
of global climate change. Efficiency use of energy in commercial buildings, and
options can reduce the need for establishes a compliance mechanism for
expensive new electricity generation energy consumption norms and
capacity and, since much of the standards. Large scale energy savings can
generation is coal-based, reduce the be realized through strengthening of the
greenhouse gas (GHG) emissions from existing policies, schemes as well as
energy production and use. expanding and reaching out to new areas
in the 12th Five Year Plan.
Over the past one decade energy
efficiency in India has been increasing at a The primary energy consumption of India
good trot, and energy intensity declined is 421 million tonnes of oil equivalent

Energy Conservation and Demand-Side Management Chapter 12: Page | 193


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

economy through various regulatory and


promotional instruments.

Some of these initiatives are:

a) Regulatory Commissions allowing


utilities to factor EE/ DSM expenditure
into the tariff
b) Creation of an EE/ DSM cell in
utilities.
c) Introduction of Time of Day tariffs
(mtoe) (2008; International Energy
for large industrial and commercial
Agency 2009) which is about 3.5% of the
consumers to flatten the load curve.
world primary energy consumption in the
d) Enforcement of mandatory
year 2008. The per capita energy
purchase of electricity at fixed prices from
consumption is only 0.53 kilogram of oil
cogenerators (at declared avoided costs
equivalent (kgOE) whereas the world
of the utility) by the grid to encourage
average is 1.82 kgOE (2008; International
cogeneration.
Energy Agency 2009). India lacks
e) Adoption of efficient pumping
sufficient domestic energy resources and
systems and shifting of pumping load to
imports much of its growing energy
off-peak hours.
requirements. According to the
f) Energy audits to be done
International Energy Agency (IEA),
periodically and be made mandatory for
coal/peat account for nearly 40 percent of
public buildings, large establishments
India’s total energy consumption,
(connected load >1 MW or equivalent
followed by nearly 27 percent for
energy use >1MVA) and energy intensive
combustible renewables and waste. Oil
industries.
accounts for nearly 24 percent of total
energy consumption, natural gas 6
12 .1 ENERGY CONSERVATION POTENTIAL
percent, hydroelectric power almost 2
percent, nuclear nearly 1 percent, and
As per the BEE/NPC report 2009 the
other renewables less than 0.5 percent.
electrical energy conservation and
About 30 percent of India’s total energy
potential in India has been identified as
needs are met through imports.
below. It is estimated that total 15%-20%
Bureau of Energy Efficiency (BEE), a energy savings potentials have been
statutory body under Ministry of Power is identified across the various sectors
responsible for spearheading the through demand side management and
improvement of energy efficiency in the energy efficiency in India. The
Government of India has initiated a
Chapter 12: Page | 194 Energy Conservation and Demand-Side Management
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

comprehensive program to significantly market to function and unlock the


enhance availability of energy at an estimated potential of around 20%, the
affordable price to meet the growing enactment of the Energy Conservation
needs of the economy. While capacity Act, 2001, setting up of Bureau of Energy
addition has been given a major focus, Efficiency (BEE) and the National Mission
energy efficiency along with renewable for Enhanced Energy Efficiency, are steps
energy, nuclear energy is the thrust areas in this direction. Following table shows
to ensure sustainable development. The the saving potential in India from energy
aim of the energy efficiency policy is to conservation and demand side
create appropriate conditions for a robust management.

Table 12.1
Electrical Energy Consumption and Conservation
Potential in India (in BU)

S.No. Sector Consumption Saving % Savings


Potenial
1.
Agriculture 92.33 27.79 30.09
Pumping
2. Commercial 9.92 1.98 19.95
Buildings
/Establishments
with connected
load>500 KW
3. Municipalities 12.45 2.88 23.13
4. Domestic 120.92 24.16 19.98
5. Industry (including 265.38 18.57 6.99
SMEs)
Total 501.00 75.36 15.04
Source: BEE/NPC Study 2009

12.2 ENERGY CONSERVATION (EC) ACT Act – 2001 and established Bureau of
Energy Efficiency.
Recognizing the fact that efficient use of
energy and its conservation is the least- The Act provides for institutionalizing and
cost option to mitigate the gap between strengthening delivery mechanism for
demand and supply, Government of India energy efficiency services in the country
has enacted the Energy Conservation (EC) and provides the much-needed
coordination between the various entities.

Energy Conservation and Demand-Side Management Chapter 12: Page | 195


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

The Bureau would be responsible for 12.3.1 Energy Conservation Building


implementation of policy programmes Code (ECBC): To set the minimum
and co-ordination of implementation of energy performance standards for new
energy conservation activities. commercial buildings, having connected
load of 100 kW and above, as well as to
The mission of BEE is to develop policy promote energy efficiency in the existing
and strategies with a thrust on self- buildings through retrofitting, Energy
regulation and market principles, within Conservation Building Code (ECBC) was
the overall framework of the EC Act with launched on 27th May 2007. This code is
the primary objective of reducing energy intended for new commercial buildings
intensity of the Indian economy. having a connected load of more than 500
kW and has initially been launched on
12.3 PROGRAMME AND MEASURES voluntary basis. Rajasthan and Orissa have
UNDER THE PROVISIONS OF EC ACT 2001 notified ECBC and three other states (,
In order to enhance energy conservation Kerala and Uttrakhand) are in the process
and energy efficiency, various schemes of notification.
have been initiated by BEE. They are:
1. Energy Conservation Building Code The ECBC User Guide has been prepared
2. Bachat Lamp Yojana to guide and assist the building designers,
3. Strengthening of State Designated architects and all others involved in
Agencies the building construction industry to
4. Standards and Labelling program implement ECBC in real situation and
5. Municipal Demand Side comply with the requirements of ECBC.
Management (MuDSM) The draft report on “Low Carbon
6. Agriculture Demand Side Strategies for Inclusive Growth” indicates
Management (AgDSM) that by mandating ECBC for new
7. Energy Efficiency in Small and commercial complexes and energy audits
Medium Enterprises (SMEs) and in existing buildings, 75 % of new
Designated Consumers commercial buildings constructed during
8. Professional certification and the 12th Plan would be compliant to the
accreditation ECBC. Similarly, 20% of existing buildings
9. Manuals and codes would reduce their present energy
10. Energy efficiency policy research consumption by 20% through energy
program audits & retrofits. Consequently, the
11. Delivery Mechanisms for energy estimated savings in energy use in new
Services, and and existing buildings over the Business
12. School education/awareness etc. As Usual (BAU) scenario is likely to be 5.07
BU.

Chapter 12: Page | 196 Energy Conservation and Demand-Side Management


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Energy audit studies in buildings have for such buildings. Buildings with a
shown large potential for energy savings connected load of 100 KW and above are
in government and commercial office being considered under the BEE Star
buildings. BEE is promoting the rating scheme. It will be subsequently
implementation of energy efficiency extended to other building types and
measures in existing buildings through different climatic zones.
Energy Service Companies (ESCOs) which
provide an innovative business model 12.3.2 Bachat Lamp Yojana: The
through which the energy-savings residential sector accounts for 25.87
potential in existing buildings can be percent of the electricity demand in the
captured and the risks faced by building country. The lighting load comprises of
owners can also be addressed. BEE has 28% of this electricity demand in the
facilitated implementation of energy residential sector and contributes almost
efficiency improvement in some large fully to the peak load as well. To promote
government buildings in New Delhi, the penetration of energy saving CFLs in
notably Rashtrapati Bhavan, PMO, etc. the residential sector, BEE has developed
The implementation of these measures the “Bachat Lamp Yojana” (BLY) Scheme.
have indicated a reduction in electricity Under the BLY scheme, a maximum of 4
bills by about 30% and simple payback on nos. long-life, quality CFL would be
investments by Energy Service Companies distributed by the CFL supplier to the grid-
(ESCOs), who invested in these measures, connected residential households in
of 1-2 years. exchange of equivalent no. of
incandescent lamp (ICL) and Rs. 15 per
In order to further accelerate the energy CFL. Approximately 700,000 CFLs can be
efficiency activities in the commercial distributed within a single project. The
building sector, BEE developed a Star savings in electricity that would mitigate
labelling programme (Voluntary) for day GHG emissions will be leveraged in the
use office buildings, BPOs and Shopping international market by the CFL supplier
complexes have been developed, which is under the Clean Development Mechanism
based on the actual performance of a (CDM) of the Kyoto Protocol.
building in terms of its specific energy
usage in kwh/sqm/year, and 123 buildings Three types of ICL lamp wattages
have been awarded energy star ratings commonly in use viz. 40 W, 60 W and 100
label. The programme rates office W are likely for replacement under the
buildings on a 1-5 Star scale, with a 5 Star BLY scheme. This Bachat lamp Yojana
labeled building being the most efficient. Scheme is registered as Programme of
The Star rating Programme provides Activities (PoA) with the CDM executive
public recognition to energy efficient board to reduce the transaction cost
buildings and creates a ‘demand side’ pull associated with CDM. The project brings

Energy Conservation and Demand-Side Management Chapter 12: Page | 197


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

together the three key players, namely validation, and CDM Project Activities
BEE, the Electricity Distribution (CPA).
Companies (DISCOMs) and investors to Bachat Lamp Yojana has been registered
supply the households with CFLs. To with UNFCCC. The projected electricity
bridge the cost differential between the saving at the end of 12th Plan is i.e. 2016-17
market price of the CFLs and the price at about 4.4 BU with the financial budget
which they are distributed to households, requirement of Rs. 6 crore.
the Clean Development Mechanism
(CDM) is harnessed. The CFL supplier 12.3.3 Strengthening of State Designated
(Investor) would cover the project cost Agencies (SDAs): State Designated
through the sale of greenhouse gas (GHG) Agencies (SDAs) are statutory bodies set
emission reductions achieved in their up by states to implement energy
respective project areas. conservation measures at state level.
BEE, the Coordinating and Managing State designated agencies (SDAs) in
Entity (CME) will have to keep a different states need to play a very
functionary to handle the various important role in terms of carrying
documentation and protocols required by forward various energy efficiency
the UNFCCC (United Nations framework initiatives at the state level. The main
Convention for Climate Change) and the emphasis of the scheme is to build
PoA. Further to facilitate the capacity of the SDAs to enable them to
implementation of BLY projects and CFL discharge regulatory, facilitative and
distribution, this functionary will have to enforcement functions under the EC Act
continuously engage with the State 2001. The thrust of the SDA program
Electricity Distribution Companies and CFL during the 12th Plan will be on
suppliers. The database management of strengthening the 32 SDAs which would
the BLY projects and Capacity building of enable them to implement various
State Electricity Distribution Companies programs and activities initiated by BEE or
and CFL suppliers along with BEE SDAs themselves.
functionary will be the key focus areas in
12th Plan. In the 11th Plan, BEE supported State
In 12th Five Year Plan, activities proposed designated agencies (SDAs) in preparation
to be undertaken are: strengthen the on- of action plan, building institutional
going BLY scheme by continued capacity of SDAs, to perform their
engagement with the state electricity regulatory, developmental and
distribution companies and streamlining promotional functions in their respective
and sustaining operations-mainly states, by way of technical assistance,
database management, data security, BLY guidance and funding etc. Each SDA has
system audit, PoA updation & re- been supported to develop a five year
Energy Conservation Action Plan,

Chapter 12: Page | 198 Energy Conservation and Demand-Side Management


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

customized to local needs aiming at and


delivery of the EC act mandates. The total funds requirement for the above
The proposed activities for the 12th Plan proposed activities is Rs. 140 crore.
include sector specific interventions in
areas like municipality (drinking water and The State Energy Conservation Funds
sewage treatment), agriculture sector (SECF) as mandated under the Energy
(pumping), street lighting, commercial Conservation Act, 2001, have already been
buildings, government buildings and constituted in 22 states and funds have
waste heat recovery in SMEs including been released to 21 states during the 11th
demonstration projects. Following Plan to operationalize the SECF for various
initiatives of SDA are proposed to be energy efficiency initiatives. The state
supported that would help in governments of Andhra Pradesh,
strengthening the capacities of SDAs and Rajasthan, Chhattisgarh, Karnataka,
undertaking of various projects and Haryana, Gujarat and Mizoram have also
programmes to promote energy efficiency contributed a matching grant to the SECF.
in their respective states: In the 12th Plan, it is proposed to set up
 Support for implementing state-wise the SECF in all the states and
sector specific energy saving plan by  Pursue with SDAs for constitution of
the SDAs SECF in the states and matching
 Continued engagement of SDAs with contribution by the state
energy efficiency professionals like governments to the SECF.
energy auditors, energy managers and  Coordinate with SDAs to implement
ESCOs various energy conservation
 Implement various EE demonstration activities and utilization of fund
projects in the states to showcase the under SECF.
effectiveness of the most advanced Contribution of Rs. 70 crore to state
energy efficient technology and energy conservation fund is proposed
pursue state governments to replicate under the 12th Plan.
the project in other parts of the state. Total fund required for strengthening of
 LED village campaign in the villages SDAs and SECF is Rs. 210 crore.
and pursue state governments to
replicate the project in other parts of 12.3.4 Equipments & Appliances
the state. (a) Standards and Labeling Program: The
 Publicity /awareness on EE in the National Energy labeling program was
states launched on May 18, 2006. Key objective
 Workshops/ training programmes for of this scheme is to provide the consumer
all the stakeholders an informed choice about the energy
 Capacity building programmes for the saving and thereby cost saving potential
SDAs of the relevant marketed

Energy Conservation and Demand-Side Management Chapter 12: Page | 199


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

equipments/appliances. During the 11th  Undertaking of check testing, label


Plan, under this scheme, a large number verification, market impact
of appliances were covered initially under assessment for appliances/
the voluntary labeling categories, out of equipments covered under S&L
which four appliances/equipment namely scheme and
AC, Frost Free Refrigerator, TFLs and  Up-gradation of energy performance
Distribution Transformers have been standards for equipment/ appliances
notified for mandatory labeling program. covered during 11th Plan.
The S&L Program was quite successful
(b) S&L for Transport Sector
during the 11th Plan period and has
contributed to the savings in avoided There are total 13.3 million passenger cars
capacity addition of 4,898 MW upto 31st (2010 – 11) in India which consume about 9
March 2011. It is anticipated that by the mtoe. The average annual sales of new
end of the 11th plan, total savings in passenger cars in the country are about 1.1
avoided capacity addition would be 7,315 million. Under the labeling scheme, the
MW. following activities are proposed

The 11th Plan has already envisaged  Introduction of fuel economy norms
completion of 21 appliances under S&L effective from 1st year of 12th Plan,
programme and the 12th Plan also  Technical study for 2 & 3 wheelers
envisage similar numbers. However, data and commercial vehicles (Truck &
on some of the appliances/equipments Buses) to finalise S&L programme
such as chillers, pumps, data centres, The targeted energy saving by the end of
furnaces, boilers, desert coolers, laptop the 12th Five Year Plan is 4.3 mtoe.
chargers, deep freezers etc. is not
Based on the above proposed schemes,
available and is planned to be collected
fund requirement of Rs. 183 crores have
through baseline survey.
been envisaged for the Standard &
The proposed activities in 12th Five Year Labeling programme for the 12th Plan.
Plan under S&L for equipments and Based on the above investment, the likely
appliances include: saving from the S&L scheme in the year
 Inclusion of at least 5 selected new 2016-17 is estimated to be 10.4 BU of
equipment and appliances (selection electrical energy and 4.3 mtoe of thermal
is to be made from the list provided energy. The proposed savings are based
in the table given below). Standby on the baseline data of 2006-07 on which
power loss reduction in few of the basis the energy savings have been
electrical appliances will also be assessed.
focussed in the 12th Plan.
 Awareness creation among all the
stakeholders,
Chapter 12: Page | 200 Energy Conservation and Demand-Side Management
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

(c) Super Efficient Equipment Program average purchase and that of the most
(SEEP) efficient technology available
internationally.
SEEP is a part of Market Transformation
for Energy Efficiency (MTEE) initiative, Super efficient appliances (SEA) may
one of the four initiatives of the National consume 30 to 50 percentages less energy
Mission on Enhanced Energy Efficiency than the five star rated equipments of
(NMEEE). The primary objective of MTEE BEE. SEAs will have their high first cost
is to accelerate the shift to energy which can be decreased by large scale
efficient appliances through innovative production facilities, but due to
measures to make the products more uncertainty of market demand,
affordable. NMEEE seeks to achieve manufacturers feel reluctant to make the
annual savings of 19,598 MW of power initial investment to change production
and 23 million tonnes of fuel and lines for super efficient appliances. This
greenhouse gas emissions reduction of barrier needs to be removed by innovative
98.55 million tonnes. The mission is one of policy interventions.
the eight mission under the Prime BEE has already announced the SEEP for
Minister's National Action Plan on Climate ceiling fans, and has initiated a dialogue
Change (NAPCC). BEE is the mission with manufacturers on setting the
implementing agency for NMEEE. technical specification, monitoring
This programme proposes to deal directly process etc. SEEP would also be extended
with the manufacturers of select key to LED Tube lights & LED bulbs. Financial
appliances. Usually, only a handful of incentives of Rs 244 crore per year would
manufacturers account for 70 to 90% of be required (depending on the market
the market share of these appliances. situation and technical preparation).
SEEP would compensate the The ceiling fan market will undergo a
manufacturers for a major part of the significant transformation because of the
incremental cost of producing Super SEEP intervention. It is expected that
Efficient Appliances (SEAs), and 26.86 million SEA ceiling fans will be sold
encourage them to not just produce but in 12th Plan which will provide savings of
also sell SEAs at an affordable price to 2.2 billion units in the year 2016-17 of 12th
common consumers. The need for five year Plan.
incentive is expected to reduce very fast
Estimated market of Tube Fluorescent
as volumes pick up.
Lamp (TFL) in terms of lighting points
In this manner, the programme would shall be about 270 million in 2016-17. With
help to introduce appliances that are far an incentive pattern under SEEP, it is
more efficient than the ones currently assumed that about 33.96 million lighting
available in India thus, narrowing the points would get converted from
massive gap between the efficiency of the conventional lighting to LEDs lighting

Energy Conservation and Demand-Side Management Chapter 12: Page | 201


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

points giving a saving of around 10 -12 the ULBs. The situation analysis was
Watt per lighting point. The savings the carried out in the Municipal sector in 2007
year 2016-17 of 12th five year Plan from covering 23 States/UTs. The finding across
sales of 33.96 million LED TL would be all the 171 cities spread in 23 states points
around 0.91 billion units. out that only 9 cities have exclusive
Further, currently both in the S&L and energy cell. Other Municipal’s region
SEEP programme, no intervention in the neither had energy cells nor having any
bulb market was envisaged, although, BLY medium for collection of data for
scheme considers the replacement of improvement of energy efficiency. Bureau
inefficient incandescent lamps (bulb) by of Energy Efficiency has initiated a
CFL. The new emergent technology under programme to cover 175 municipalities in
SEEP through LEDs bulb (replacement of the country by conducting energy audits
60 W incandescent bulbs with 8-12 Watt and preparation of Detailed Project
LED bulb) would give large savings about Reports(DPRs) and implementation
70-80%. The saving in the year 2016-17 of through ESCO mode.
12th five year Plan from sales of 33.96 Energy Efficiency in ULBs
million LED bulbs would be around 3.42
 As low as only 38 cities out of 171 have
billion units.
separate allocation in their budget for
12.3.5 Municipal Demand Side any energy efficiency initiative.
Management (MuDSM)- The global trend Notably out of total budget allocation
towards increased urbanization requires of Rs. 12,123 crore across these 171
municipal bodies to provide services such cities, only Rs 128.5 crore (1.06%) was
as streetlights, solid waste management, allocated exclusively for energy
sewage treatment & disposal, etc. All efficiency initiatives in the year 2006-
these activities consume significant 07. This subsequently went down to
amount of electricity, usually in an 0.88% in 2007-08 with the allocation of
inefficient manner. The cost of energy Rs 161.8 crores out of total budget
sometimes constitutes more than 50% of provision of Rs 18,430 crore. Based on
the municipality’s budget and the data collected in the situation
implementing efficiency measures could analysis survey, the energy saving
reduce it by at least 25%. The basic potential for 12th Plan has been
objective of the Municipal Demand Side estimated as 257 million units (MU) in
Management (MuDSM) programme is to the urban local bodies.
improve the overall energy efficiency of Energy Efficiency in Water pumping
the Urban Local Bodies (ULBs) which
could lead to substantial savings in the  During the course of initial Investment
electricity consumption, thereby Grade Audits (IGAs) of ULBs, it was
resulting in cost reduction/savings for found that over a period of time, many

Chapter 12: Page | 202 Energy Conservation and Demand-Side Management


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

of the water pumping bodies (Jal accounts for about 27% of electricity
Nigam/ Jal Sansthan/ Water consumption in the country, which is
Department) have separated out from increasing due to rural electrification
the scope of ULBs and therefore, a efforts of the Government. The electricity
separate situation analysis of these is largely used in agricultural pump sets
bodies was carried out. The which generally have very poor efficiency.
representative water bodies, Since agricultural tariffs are usually the
encompassing total of 3520.65 lakh of lowest and also highly subsidized, there is
population in 1896 Sq.km spread no incentive to the agricultural consumer
across 105 cities, were covered during to improve efficiency of the pump set.
this sample based survey for situation However, utilities are not able to recover
analysis covering 19 states. economic price on every unit of energy
In this study, the overall estimated sold to these categories of consumers and
electricity consumption in the pumping therefore need to aggressively target
was 1040 MU with an estimated electricity these consumers for DSM measures. Ag
saving potential of 208 MU. DSM promises immense opportunity in
reducing the overall power consumption,
Based on the above survey, funding
improving efficiencies of ground water
requirement of Rs. 45 crores is assessed
extraction and reducing the subsidy
for the MuDSM Scheme as this scheme
burden of the states without sacrificing
would create an institutional mechanism
the service obligation to this sector. To
for implementation of the MuDSM in the
tap the energy saving potential in the
country. The above budget is meant for
agriculture sector, which is estimated to
undertaking investment grade energy
be 20.75% (2007-08) of the total energy
audits in both ULBs and Jal-Nigams. It is
consumption, the activities planned to be
envisaged that implementation of the
undertaken in the 12th Plan would focus
proposed IGAs can be achieved through
on development of innovative financial
funding under JNNURM and linking the
mechanisms like Venture Capital Fund
same through development fund of
(VCF) and Partial Risk Guarantee Fund
MoUD to realize the savings. Any
(PRGF) for the large-scale implementation
implementation programme under BEE
of AgDSM projects on Public Private
scheme is to be considered for separately
Partnership (PPP) mode, in the states for
funded.
which DPRs have been prepared in the
The projected electricity saving at the end 11th Five Year Plan. The major impacts of
of 12th Plan i.e. 2016-17 is about 0.47 BU the Ag DSM scheme during the 11th Five
with the financial budget requirement of Year Plan includes 97 MU of annual
Rs. 45 crore. energy saving potential assessed across
12.3.6 Agriculture Demand Side eight different states covering about
Management (AgDSM)- : Agriculture 20,885 pump sets.

Energy Conservation and Demand-Side Management Chapter 12: Page | 203


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Based on the results achieved during the transformation of agriculture pump sets,
11th Plan, the targeted reduction in major manufacturer of agriculture pumps
electricity consumption at the end of 12th in the organized SME sector would
Plan is 0.7 billion units (BU) which would transform into manufacturing of energy
be about 0.57% of the electricity efficient star labelled pumps through the
consumption in the agriculture pumping various initiatives of BEE
system. The following instruments are schemes/programmes.
proposed to meet the proposed target: Wider involvement of stakeholders like
 Financing mechanism for promoting DISCOMs, state regulatory commissions,
investments in Ag DSM projects State Designated Agencies, State
(Target – 0.25 million pump sets, 0.7 Governments, pump manufacturers,
BU of energy savings, Total Budgetary energy saving companies, farmers/
Provision: Rs. 352 crore). consumers etc. is one of the key initiatives
 Placement of partial risk guarantee under the scheme.
fund for risk mitigation of The projected electricity saving at the end of
Manufacturer/Implementer/ESCOs/FIs 12th Plan i.e. 2016-17 is about 0.7 BU with the
. financial budget requirement of Rs. 393 crore.

 Placement of capital subsidy


fund/venture capital fund for 12.3.7 Energy Efficiency in Small and
providing incentive to Medium Enterprises (SMEs) and
Manufacturer/Implementer/ESCOs. Designated Consumers: The MSME sector
 Monitoring and verification protocol is an important constituent of the Indian
under the AgDSM scheme (Total economy, contributing significantly in
Budgetary Provision: 25 crore) GDP, manufacturing output and export.
Similarly this sector also plays a significant
 Monitoring and verification protocol
role in energy consumption which is about
under the AgDSM scheme (Total
25% of the total energy consumption by
Budgetary Provision: 25 crore)
industrial sector. To stimulate energy
 Integrated water and energy efficiency measures in 25 high energy
conservation scheme – 100 Joint consuming small and medium enterprises
Demo projects implementation(Total BEE in consultation with Designated State
Budgetary Provision: Rs. 10 crore) Agencies has initiated diagnostic studies
 Technical assistance & capacity in 25 SME clusters in the country and
development of all stakeholders developed cluster specific energy
(Total Budgetary provision – Rs. 6 efficiency manuals/ booklets and other
crores) documents to enhance energy
At the end of the 12th Five Year Plan, it is conservation in SMEs. The EC Act
forecasted that through market identifies 9 energy intensive sectors

Chapter 12: Page | 204 Energy Conservation and Demand-Side Management


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

(Thermal Power, Iron & Steel, Aluminium, implementation of DPRs on energy


Cement, Fertilizer, Chlor Alkali, Pulp & efficient technologies and development
Paper, Textile and Railways sectors) as of Local /technologies Service Providers
designated consumers. Under which the for SMEs, capacity building of
designated consumers have to comply stakeholders including bankers /FIs and
with the energy efficiency norms once strategic approach for dissemination of
they are notified and the proposed results. The strategy will be to move from
targeted savings through this scheme is cluster based approach to sector based
500 MW. approach to enable large degree
In the 12th Five Year Plan, BEE would implementation in the sectors selected
target the SME sector for reduction in under the 11th Five Year Plan.
energy consumption by 5.75% of the The projected saving in the year 2016-7 of
energy used in the energy intensive 12th Five Year Plan is 1.75 mtoe in which
manufacturing SMEs which is equivalent 1.59 mtoe is thermal energy and rest is
to 1.75 mtoe. The targeted goal is equivalent to the 1.83 BU of electricity
proposed to be achieved by introducing with the financial budget requirement of
innovative business models and financial Rs. 55 crore. In addition to this, Rs. 400
instruments (like Venture Capital crore is also proposed for setting-up of
Fund/Revolving Fund, Partial Risk Revolving fund and partial risk guarantee
Guarantee Fund). The proposed fund.
schemes/activities to be undertaken in The total funds requirement for SMEs
12th Plan are as mentioned below: under the 12th plan is Rs. 455 Crore.
 Sector specific approach for energy
efficiency and technology 12.3.8 Promotional Activities to Enhance
upgradation through facilitation of Awareness Support Energy Conservation
implementation of DPRs Act

 Energy mapping of the targeted SME


The EC Act, 2001 requires the Government
Sector on all India basis
and BEE to take steps to enhance
 Undertaking of Innovative Financial
awareness about energy efficiency and
Schemes for adoption of EE energy conservation amongst
Technologies in the SMEs
stakeholders. In pursuance, the following
 Technical assistance and capacity activities are being implemented:
building
 SMEs Product Labelling Promotion  National Awareness Campaign
Scheme The objective of the general awareness as
The approach would be based on the well as the Standards and Labelling
replication of results and findings from Programme Campaign of BEE and MOP is
the 11th Plan. This would include to create awareness amongst public on

Energy Conservation and Demand-Side Management Chapter 12: Page | 205


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

the efficacy and virtues of adopting a plan for Cinema and internet has also
habit for energy conservation. been proposed.
Many activities to promote awareness on
The General Awareness Campaign would energy conservation amongst the
create awareness to motivate people to targeted sectors and general public and
save power by rational use of electricity. also for school children were undertaken
This campaign will serve as the umbrella during 11th Plan which include National
campaign for the energy conservation Energy Conservation Award for industries,
initiatives and lay emphasis on the subject buildings and railways and Painting
as the need of the hour. A Multi media Competition on energy conservation for
outreach strategy has been prepared to school children.
achieve maximum reach to the targeted
audience. The combination of Media  National Energy Conservation
taken in the plan viz. Print, TV, Satellite, Awards
Radio, Cinema, Internet would give 96%
reach. The National Energy Conservation Award
Scheme of Ministry of Power covers about
The multimedia campaign is being carried 34 sectors of industry, thermal power
out in a phased manner: TV, Print and stations, office buildings, hotels and
Radio plan has already been rolled out. hospitals, zonal railways, state designated
Channel selection in TV/Satellite is based agencies, municipalities and
on TAM ratings to achieve 65%+ reach at manufacturers of BEE Star labelled
5+ OTS. For print, popular and top English, appliances. In the last 11 years of Award
Hindi and regional language newspapers Scheme of the period 1999-2009, the
along with vernacular magazines have participating units have collectively saved
been taken up. The stations for radio Rs 11261 Crores and the investment made
campaign have also been selected in such on energy efficiency projects was
a way so as to attain the maximum reach. recovered back in 17.6 months. In energy
All the channels, stations and newspapers terms, 12113 Million kWh of electrical
have been selected as per the DAVP power, 24 lakhs kilolitre of oil, 67 lakhs
policy. Alongside, monitoring and metric tonne of coal and 21.2 billion cubic
performance evaluation would be metre of gas was saved, through the
stepped up to ensure that the scheme energy conservation measures of the
attains its designated targets. participating units. The progressive
industrial units and other establishments
The allocation of resources over the have already realized the cost
various media platforms is such that TV effectiveness of energy conservation
and satellite constitutes the highest measures and honouring their efforts on
allocation followed by print and radio. The National Energy Conservation Day, gives a
Chapter 12: Page | 206 Energy Conservation and Demand-Side Management
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

message to thousands of other industrial for students in the standards 4th, 5th &
units and establishments who may have 6th at the School, State and at National
not yet fully utilized their cost effective level, Essay writing competition for
potential through energy conservation. It students in the standards 6th to 8th at the
is hoped that National Energy School and State level, Debate
Conservation Award Scheme would help competition for students in the standards
in motivating the other energy consumers 9th to 12th at the District and State level
in joining and promoting of a nation wise has been included as one of the activities
energy conservation movement. of the campaign, which would not only
make aware the children about the need
of conserving energy but at the same time
It is proposed to strengthen all ongoing
would educate and involve their parents
activities during the 12th Plan and
as well in the above cause. The identified
introduce the following specific activities:
activity is one of the measures, which can
 Creation of data base and its analysis help in creating awareness in the
EC Award participating units domestic sector. In 2009, around 40,814
 Compilation and dissemination of schools and 911,553 students participated
best-practices in industry and building in the Painting competition. In the year
sector 2010, about 15.63 lakh students
 Continuation of EC Awards and participated in the competition in
paintings competition on energy comparison to 3.43 lakh in the year 2005.
conservation
12.3.9 Results achieved / expected
 Awareness creation on energy
The Ministry has set up a targeted
conservation through print, electronic
reduction of 5% energy consumption by
and other media for general public
the end of XI Five year Plan. The energy
The projected saving in the year 2016-17 of conservation potential as assessed is
12th Plan is about 3.42 BU of electrical energy
20,000 MW and the target planned for the
and 5 mtoe of thermal fuel saving with the
XI Plan is 10,000 MW.
financial budget requirement of Rs. 100 crore.

The major achievements are as follows:


 National Painting Competition  7756 Certified Energy Managers out
of which 5390 are Certified Energy
Children are an important target group as Auditors.
well as stakeholders in increasing  8 National Certification Examination
awareness; therefore the Ministry of for Energy Managers and Energy
Power and BEE took up this innovative Auditors successfully conducted.
scheme to target children. The Ministry of  4 Guidebooks prepared to assist
Power has launched Painting competition energy professionals.

Energy Conservation and Demand-Side Management Chapter 12: Page | 207


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

 Four interactive Websites in place. 12.4 SUPPLY-SIDE MANAGEMENT


 32 State Governments and Union
Territories have notified State 12.4.1 The thermal units in the country
Designated Agencies for have a unit capacity of up to 600MW. A
implementing EC Act within the large number of supercritical units of sizes
state. 660/800 MW are under construction.
 Energy Conservation Building Codes Initially supercritical units were designed
(ECBC) prepared. with parameters of 247kg/cm2, 537/50C.
 Standards & Labeling scheme has Now higher parameters of 247kg/cm2,
resulted in electricity saving of 565/5930C are being envisaged. With the
2106.16 MU, equivalent to avoided higher steam parameters being envisaged
capacity generation of 599.44 MW for supercritical units, the efficiency of
during 2008-2009. these supercritical units would be about
 As per details collected from SDAs to 5% higher than the efficiency of present
review energy savings based on 500 MW units. This would lead to
activities carried out, the verified corresponding saving in coal consumption
savings amounted to 2755.48 MU, and reduction in GHG emissions. In 12th
equivalent to 660.43 MW avoided Plan, supercritical units are likely to
generation during the year 2008- constitute a majority of coal based
2009. capacity addition.. During 13th Plan,
 The estimated energy savings based thermal capacity addition will be from
on individual savings achieved by all supercritical units only. A very large
the participating units in the National number of small size units of 100 MW or
Energy Conservation Award less capacity are in operation. The average
Programme 2009, has been verified PLF of most of these units is very low,
at 1633.25 MU, equivalent to 239 even less than 50%. These units are of
MW. non-reheat type having very low design
 The achievements in respect of efficiency. Such units are planned to be
energy saved relating to the retired in a phased manner over a period
programmes/ schemes of the BEE of next ten years.
during 2007-08, 2008-09 is 2128 MW.
Out of the target of 2600 MW fixed 12.4.2 Thermal power stations in the
for 2009-10, BEE has achieved 1348 country are operating with high auxiliary
MW upto 30th Sept., 2009. It is power consumption and secondary fuel
expected that the ambitious target oil consumption. These factors, coupled
2600 MW for 2009-10 will also be with poor operation and maintenance
achieved as is the case for last 2 practices, result in poor efficiency of the
years. stations. Mapping studies carried out by
CEA on thermal power stations have
Chapter 12: Page | 208 Energy Conservation and Demand-Side Management
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

revealed that the power stations are Reduction of the non-technical losses
losing heavily due to poor condenser could be achieved with better
vacuum, non-availability of HP heaters, management at a little extra cost.
excessive consumption of DM water, air Schemes have been drawn up to reduce
ingress into the boiler, high flue gas technical losses by installation of
temperature and a number of other additional capacitors, appropriate size of
reasons. Most of the power stations were the transformers, installation of
incurring huge financial losses due to sub- amorphous core transformers,
optimal operation resulting in increased augmentation and strengthening of
coal & oil consumption. transmission and distribution lines and
reduction of the length of low voltage
12.4.3 Benefits have accrued in terms of lines. Based on the guidelines issued for
higher generation, improvement in heat reduction of transmission and distribution
rate, and reduction in specific fuel oil and losses and energy audit in power system,
coal consumption at a number of TPSs Utilities have been encouraged to reduce
where the recommendations given by CEA the T&D losses by implementing the
in the mapping reports have been schemes in regard to computerised
implemented. Monitoring of system load management through
implementation of the recommendations segregation of load to agriculture and
is being carried out regularly. CEA has also introduction of Time of Use (TOU)
prepared “Guidelines for establishment of differential tariffs etc. T.O.U. Tariffs
Energy Audit Cells at TPS” to encourage should be such designed in the form of
thermal power stations to conduct energy incentive of lower rate that it should
audits on their own. Energy Conservation encourage use of more energy during off-
Act 2001 makes it mandatory to get peak hours and higher rate should be
energy audit of power stations done fixed to discourage the use of energy
through Accredited Energy Auditors. during peak-hours. Regional staggering of
Energy Audit and implementation of load should be aimed to stagger the load
recommendations to improve operational and minimizing the load of the system
efficiency may form part of regular during peak hours. These efforts have to
activity and necessary financial be vigorously followed up along with
arrangements may be made accordingly. steps to curb pilferage and theft of
electricity. The High Voltage Distribution
12.4.4 Transmission and Distribution system (HVDS) has greater potential to
(T&D) losses in the Indian system are reduce T&D losses and should be
amongst the highest in the world. encouraged.
Presently the all-India T&D losses are
around 27%, out of which substantial 12.4.5 The Indian power system is around
portion is non-technical losses and theft. hundred years old. With latest technology

Energy Conservation and Demand-Side Management Chapter 12: Page | 209


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

developments, there is ample scope for energy consumption level in the


improvement in the system of generation beginning of the 11th Five Year Plan.
and supply of electricity to the ultimate The outcomes of these schemes are quite
consumers in the most effective and encouraging; various activities under
efficient way within acceptable different schemes of BEE and MoP have
environmental level. Some of the latest resulted in savings in avoided power
technologies are Circulating/ Pressurized capacity of 7,415 MW (verified; till Dec
Fluidized Bed Combustion (CFBC & PFBC), 2010) and 250 MW (unverified for 4th
coal washing/ benefaction, computer- Quarter of year 2010 – 11) and 3409 MW
aided up gradation of sub-stations, avoided power capacity savings is
supercritical pulverized fuel units and projected during the last year of the 11th
Integrated Gasification Combined Cycle Five Year Plan (2011-12).
(IGCC) plants.

12.5 ACHIEVEMENT UNDER THE 11th Plan 12.6 UTILITY BASED DEMAND SIDE
MANAGEMENT IN THE 12TH PLAN
Bureau of Energy Efficiency (BEE) and
Ministry of Power (MoP) had introduced a Demand-Side Management (DSM) is the
number of schemes during 11th Five Year selection, planning, and implementation
Plan for promotion of energy efficiency in of measures intended to have an influence
India. The schemes of BEE include on the demand or customer-side of the
Standards and Labeling (S&L), Energy electric meter. DSM program can reduce
Conservation Building Code (ECBC) & energy costs for utilities, and in the long
Energy Efficiency in Existing Buildings, term, it can limit the requirement for
Bachat Lamp Yojana (BLY), SDA further generation capacity augmentation
strengthening, Energy Efficiency in Small and strengthening of transmission and
and Medium Enterprises (SMEs), distribution system. BEE would provide
Agriculture & Municipal Demand Side the technical assistance for establishment
Management (DSM) and Contribution to of DSM cells in the DISCOMs and capacity
State Energy Conservation Fund (SECF). building of personnel of DSM cells for
enabling them to undertake the following
The schemes of the Ministry of Power strategies and schemes of DSM in 12th Five
(MoP) include Energy Conservation Year plan:
Awareness, Energy Conservation Awards
& Painting Competition on Energy (I) LOAD SURVEY
Conservation for school students and The questionnaire based surveys are the
National Mission for Enhanced Energy most commonly adopted tools to study
Efficiency (NMEEE). In the 11th Five Year the consumption pattern of the
Plan (2007–12), it was proposed to achieve consumers by a utility. “Standard load
the energy saving of 5% of the anticipated survey techniques” need to be developed

Chapter 12: Page | 210 Energy Conservation and Demand-Side Management


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

which may be adopted by the DISCOMs. above to convey to the customer


Also it is envisaged that DISCOMs to about the prevailing demand, supply,
develop utility/city level load profiles prices on real time basis and the
which may be uploaded on DISCOMs and incentives and options for him, which
BEE’s DSM website (http://www.bee- are used by the customer to manage
dsm.in) on a periodical basis which can be the demand.
utilized for DSM plans and for further (III) DEMONSTRATION STUDIES
analysis.
Direct installation programs that provide
(II) LOAD STRATEGIES complete services to design, finance, and
Load strategies are to be adopted by install a package of efficiency measures.
electricity utilities to modify customer (IV) ADVANCED METERING
load profiles and thereby reduce their
peak demands. Following Load Advanced Meter has the capability of
management strategies may be online communication, accurate
demonstrated by DISCOMs/Utilities: measurements, local intelligence, load
connect-disconnect facility and consumer
* Demand Response
friendly display unit. Adoption of this
Demand Response is an effort to create technology will help distribution
additional capacity during the peak hours, companies in implementing Demand Side
by involving voluntary load curtailment by Management specially Demand Response
consumers during peak hours or when Activities.
requested by the distribution companies.
(V) DSM FINANCING
The load curtailment can be achieved
through implementing load reduction by The strategic value of DSM measures and
Energy Efficiency or by load shifting energy efficiency lies in their ability to
measures. improve the financial cash flow of Indian
utilities.
* Load Management Programmes
 Dynamic/Real Time Pricing: Based on Moreover, DSM and Demand Response
real time system of supply & demand (DR) Activity are utilized to curtail the
peak electricity demand. In other words, it
 Time-of-Use Rates: Customers are
helps to negate spending on generation,
offered different rates for electricity
transmission and distribution
usage at different times of the day.
infrastructure by curtailing the peak. Thus,
 Automated/Smart Metering: it can be said that funds are freed up
Implementing Dynamic/ Real Time which would otherwise be utilized to
Pricing or Time-of-use rate structure meet the peak demand. At the National
and billing accordingly. level, the load growth should be reviewed
 Web-based/Communication System: with and without DSM and the fund freed
This is a tool used along with the up because of lower peak growth should

Energy Conservation and Demand-Side Management Chapter 12: Page | 211


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

be used for DSM/DR activity. In other the demand side (equivalent to 60.17 BU
words, the DSM/DR should have a target at Bus bar) and an additional energy
(say 0.5% to 1%) of peak demand reduction saving equivalent of 21.3 mtoe in the
and the net saving in infrastructure due to industrial sector (including Thermal Power
that should be used for DSM/DR activity. Stations (TPS) and Small and Medium
Enterprises), Transport Sector and Energy
The total funds required for providing
Conservation (EC) award scheme. The
technical assistance for capacity building
share of target energy saving (Electrical &
of DSM cells established by DISCOMs under
Thermal) for various proposed schemes
12th Five Year Plan is Rs. 300 crore.
under 12th Plan is given below:
12.7 ENERGY CONSERVATION STRATEGY
IN THE 12TH PLAN 12.8 THE NATIONAL ACTION PLAN ON
th
The strategies adopted during the 11 Five CLIMATE CHANGE (NAPCC)
Year Plan have started showing
encouraging outcomes. It is necessary to The National Action Plan on Climate
carry forward the existing schemes as well Change(NAPCC) released by the Prime
as further strengthen the activities to Minister on 30th June, 2008, recognizes
accelerate the process of implementation the need to maintain a high growth rate
of energy efficiency measures to achieve for increasing living standards of the vast
majority of people and reducing their

the desired energy savings. vulnerability to the impacts of climate


change. The National Action Plan outlines
Further, large scale energy savings can be
Eight National Missions, representing
realized through strengthening of the
multi-pronged, long-term and integrated
schemes in industrial, commercial,
strategies for achieving key goals in the
residential and agriculture sectors as well
context of climate change. The National
as expanding and reaching out to new
Mission of Enhanced Energy Efficiency is
areas. Projected electrical energy saving
considered as one of the key missions to
potential at the end of 12th Five Year Plan
achieve the objectives of the NPACC. The
i.e during the year 2016-17 is 44.85 BU on

Chapter 12: Page | 212 Energy Conservation and Demand-Side Management


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Ministry of Power (MOP) and Bureau of measures to promote India’s


Energy Efficiency (BEE) were tasked to development objectives and also result in
prepare the implementation plan for the co-benefits useful in dealing with adverse
National Mission on Enhanced Energy impacts of climate change. Cost-effective
Efficiency (NMEEE). The mission over the energy efficiency and energy conservation
next four years is likely to achieve avoided measures are particularly important in this
capacity of over 19,000 MW. connection. The basic tenet of the mission
is to ensure sustainable growth through
The National Mission for Enhanced Energy an appropriate mix of 4 Es: Energy,
Efficiency (NMEEE) seeks to identify Efficiency, Equity, and Environment.

The NMEEE spelt out the following four new initiatives to enhance energy efficiency,
(in addition to the programmes on energy efficiency being pursued by MOP and BEE
in the 11th Plan):

i) Unique market based mechanism for energy intensive industries through


Perform Achieve and Trade (PAT);

ii) Accelerating the shift to energy efficient appliances in designated sectors


through innovative measures to make the products more affordable. (Market
Transformation for Energy Efficiency (MTEE);

iii) Creation of mechanisms that would help finance demand side management
programmes in all sectors by capturing future energy savings. (Energy
Efficiency Financing Platform (EEFP);

iv) Developing fiscal instruments to promote energy efficiency namely Framework


for Energy Efficient Economic Development (FEEED);

1. Perform Achieve and Trade (PAT) carried out by accredited verification


Under the PAT mechanism, the specific agency or accredited energy auditor’s
energy consumption (SEC) reduction .The Energy Saving Certificates (ESCerts)
targets for the 714 energy-intensive units will be issued to those who exceed their
in 9 sectors namely, aluminium, cement, target SEC reduction. The trading of the
iron and steel, chlor-alkali, thermal power ESCerts earned can be carried out on
plants, fertilizer, pulp and paper, textiles special trading platforms in the two
and railways, which are designated power exchanges. The accounting and
consumers under Energy Conservation depository protocols are in the process of
Act and notified by MoP, are to be evolution. A transparent conversion factor
achieved. The verification process of the will be adopted based upon some
Specific Energy Consumption (SEC) will be verifiable parameters eg. Mtoe. A joint
Energy Conservation and Demand-Side Management Chapter 12: Page | 213
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

group of the agencies administering the household consumption of (BAU) 190


PAT mechanism and the REC mechanism billion KWh. BEE has proposed
could agree to the linkage mechanism Implementation of Regulated Multi State
between the RECs and the ESCerts once Demand Side Management Programme
both the mechanisms are operational. (RMSDP) – with the key objective of
During the 12th Plan period, efforts creating an appropriate policy and
will be made to initiate deepening and regulatory framework to incentivise
broadening of the adoption of PAT manufacturers to produce and sell Super
mechanism by large industry consumers. Efficient Equipments (SEE). The proposed
This would be done with industry and utility and manufacturer based program
stakeholder consultation. has been supported by CERC as well.

2. Market Transformation for Energy 3. Energy Efficiency Financing


Efficiency (MTEE) Platform (EEFP)
Under the MTEE, international funds EEFP framework would ensure availability
would be leveraged for promoting energy of finance at reasonable rates for
efficiency and a National Energy-Efficiency implementation of energy-efficiency
CDM Road Map would be implemented. projects and expansion of EEFP with
The Programme of Activities (PoA) to PFC/REC/IDBI, HSBC etc. Under the
leverage CDM for agriculture and framework bankable projects and
municipal sectors would be developed by markets, programme of activities for
March, 2010. One of the proposed enabling CDM would be prepared. Two
schemes under the MTEE is Regulated financial institutions have already joined
Multi State Demand Side Management the EEFP and PTC India Ltd., commenced
Programme (RMSDP). For the household financing of ESCO-based projects at
energy consumption, few appliances like Rashtrapati Bhavan, ESIC hospitals, AIIMS
for lighting (incandescent bulbs and tube etc. and SIDBI has initiated exercise for
lights), fans, refrigerators, ACs and TVs – financing projects in SMEs. A
contribute to 80% of the household Memorandum of Understanding has been
consumption in 2008, a trend that is likely signed between Bureau of Energy
to continue till 2013-14. Four of these Efficiency & The Hongkong and Shangai
appliance i.e. Fans, ACs, TV, and Banking Corporation Limited (HSBC Bank).
Refrigerator, are also the fastest growing On similar lines, MoU has been signed
appliances in the period indicated. between BEE and Small Industries
Interventions to enhance their efficiencies Development Bank of India (SIDBI) for
significantly from the Business As Usual financing energy efficiency activities in
(BAU) could result in energy savings to small and medium enterprises.
the tune of about 48 billion KWh in 2013
which is almost 25% of expected
Chapter 12: Page | 214 Energy Conservation and Demand-Side Management
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

4. Framework for Energy-Efficient efficiency through public procurement,


Economic Development (FEEED) policy guidance to CPSUs to take up
Under the FEEED framework, lenders energy-efficiency projects. Further,
would be provided the comfort by support and assistance to Electricity
provision of Risk guarantee for Regulatory Commissions for stimulating
performance contract, Venture Capital utility driven DSM, tax / duty exemptions
Fund for Energy Efficiency etc. Central for promotion of Energy Efficiency under
public-sector undertakings (CPSUs) will be the FEED framework.
given incentives for taking up energy

12.9 OTHER POTENTIAL AREAS

Other potential areas that BEE has initiated and which offer significant energy efficiency
potential:
Trigeneration
The HVAC market size in India in the year 2007 was about 13 million kW; 14 % of that was for
the domestic sector. The ratio of window to split ACs in 2004-05 was 3:1 and now the figure is
1:1. HVAC market in India is mainly characterized by the air-conditioning market.

There is a market for hot water generators (i.e. geysers) in the Northern and Central part of the
country. About 1.6 million of such heaters are sold annually in India. Assuming average power
consumption of 1.5 kW/ heater, total installed capacity would be about 2400 MW.

It has been estimated that about 3000 MW gas based power system is already installed in India,
out of that about 1000 MW are recently added in Indian building sector and out of the 1000
MW installed 522 MW are for cogeneration/tri-generation projects.

The tri-generation and cogeneration market is expected to grow very rapidly in future. Present
market size has been estimated at 13 x 106 kW (3.7 X 106 TR) out of which about 2.3 x 106 kW
(0.65 x 106 TR) represents chilled water based central system, which is likely to be the
immediate target market for cogeneration/tri-generation system.

Energy Conservation and Demand-Side Management Chapter 12: Page | 215


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Target Market : Segments with Gas Existing &


Proposed (Bubble Size in MW)

10.5
Hotel
731
9.5 A irport
1,698
Market Attractiveness

Hospital
8.5
270

7.5
Retail
754

6.5

Off ice
5.5 2,590

4.5
7.0 7.5 8.0 8.5 9.0 9.5 10.0 10.5
Financial Attr active ne s s

Of f ice Retail Hotel Hospital A irport

Chapter 12: Page | 216 Energy Conservation and Demand-Side Management


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Waste-to Heat Recovery

India has nearly 13 million of micro, small & medium enterprises which constitute more
than 80% of the total number of industrial enterprises in the country. Small industries
have a 45% share of the total manufacturing output and they contribute nearly 40% of
total exports in the economy. They are one of the biggest employers providing
employment to about 41 million people and according to recent estimates, constitutes
about 8-9% of the country’s GDP. The SME sector is one area which demonstrates high
overall potential for reductions in energy intensity ranging from 20 – 25% as per study
conducted by the BEE. SMEs, especially those for whom energy costs represent a large
portion of total production costs, can reap especially high benefits from improving
efficiency of energy conversion and reduction of energy losses, yet numerous barriers
and market failures have prevented widespread adoption of these measures.

Rising energy costs can lead to higher production and distribution costs for business,
eroding long term competitiveness and profitability. SMEs are particularly vulnerable due
to limited resources and tight operating margins. Cutting energy waste can be quick way
for them to reduce costs, but they often lack the knowledge, financing and dedicated
personnel needed to identify efficiency opportunities and implement improvements.
Potential savings can be unlocked through simple measures, one of which can be the
waste heat recovery in some of the clusters. Also, demonstration in few units will have
high replicability potential as these units are located in clusters.

In order to have an effective implementation mechanism within the timelines indicated in


National Mission on Enhanced Energy Efficiency (NMEEE), the Ministry recommended
augmentation of energy efficiency institutional structure, both at the policy/ regulatory
level by strengthening BEE and creation of an implementation corporate entity as a Joint
Venture. As a result, Energy Efficiency Services Limited (EESL) is a joint venture company
promoted by 4 Central Public Sector Undertakings (CPSUs), namely National Thermal

12.10 HUMAN RESOURCE DEVELOPMENT conservation campaign as a mass


PROGRAMMES movement and seeking wide support. In
the 11th Plan, BEE will continue with their
There is a vast potential for energy campaigns. In addition, Central
savings through human intervention. BEE government will partially fund the SDAs
and SDAs have a major responsibility for for their respective campaigns in the
stimulating a major change in the energy States.
efficiency ethos and practices (energy
modesty) by directing the national energy

Energy Conservation and Demand-Side Management Chapter 12: Page | 217


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

The following initiatives will be taken in (vi) Training to drivers in road transport
the area of HRD: on fuel efficient driving
(i) Capacity building: a) Officials of BEE (vii) Nationwide campaigns: a) through
& SDAs abroad/ in India; b) Code media; b) awareness programs for
officials from SDAs, urban & general public & institutions in state
municipal bodies for promoting & capitals and other locations; c)
enforcement of energy conservation painting competition for school
building codes; c) Orientation children; d) Eco clubs activities for
programs every year for senior youth clubs
officials from Central & State Govt. (viii) Introduction of the modules on
departments to review the energy efficiency/ DSM in the
achievements, impediments and curricula of a) schools b) technical
strategies to step up the tempo of institutes engineering colleges c)
energy conservation. other degree/ postgraduate courses
(ii) Capacity building for new breed of including MBA programs.
professionals: a) energy 12.11 OTHER TECHNOLOGIES/AREAS FOR
managers/auditors being developed ENERGY CONSERVATION
under the EC Act from 2003 by BEE
Award for manufacturer offering the most
through National Certification energy efficient appliance models
Examination by offering Refresher
Appliances manufacturing companies may
training modules for lifelong training
have started producing energy efficient,
for Energy Auditors & Managers; b) star rated models. However, they also
Tutorial /help-line support for produce a wide range of models that are
prospective candidates in the cheaper and popular but energy
national examination for energy inefficient. An award will incentivize the
managers/auditors. manufacturing companies to offer more
energy efficient models and will act as
(iii) Demonstration centres in 2 industrial
recognition of their commitment to
estates to showcase and convince
energy efficiency.
the entrepreneurs & plant
The Ministry of Power already has the
engineers/technicians for industrial
National Energy Conservation Award
energy efficiency products (NECA) scheme to recognize the
/technologies innovation and achievements in energy
(iv) Orientation workshops on energy conservation & efficiency by the industry,
efficiency for top management, and the above proposed award can be a
middle level executives and shop part of the scheme.
floor operating personnel ENERGY EFFICIENCY RESEARCH CENTERS
(v) Farmers training by display of Setting up of 10 energy efficiency research
energy efficient pump-sets & other centres for selected energy consuming
relevant products sectors may be considered in
Chapter 12: Page | 218 Energy Conservation and Demand-Side Management
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

collaboration with the Department of are not presently/ adequately covered


Science & Technology (DST). Based on a under the existing BEE schemes. These
model appropriate for India, BEE may include the defence establishments like
invite offers from academic institutions, ordinance factories (purely on a voluntary
manufacturing associations & ESCOs and basis), Public Sector Units (PSUs)
offer funding for initial set up, partial township and large engineering/
running and maintenance cost for the first manufacturing industries.
5 year period. Lighting Centre of Excellence
The financial budget requirement for this Creating a demonstration centre on
activity is Rs. 200 crore in 12th Five Year lighting technologies (Lighting Centre of
Plan. Excellence) to showcase energy efficient
Other Strategies and Initiatives lighting technologies, may be considered
in the 12th Plan.
Other strategies
12.12 CONCLUSION AND
Encourage planners and regulators
related to energy and technology up RECOMMENDATIONS
gradation sector to adopt integrated The target of energy saving which may be
resource planning in the entire value chain achieved in the terminal year 2016-17 of
of activities, right from extraction or 12th Five year Plan as a consequence of
procurement, and conversion to final end Demand Side Management (DSM), Energy
use. Efficiency and Energy Conservation
New areas/initiatives schemes as proposed in the plan is
expected to be 44.85 BU (at consumer
side) which is equivalent to 60.17 BU at
Railways the Bus bar side. The equivalent avoided
The Indian Railways in past has peaking capacity is estimated to be 12,350
undertaken many initiatives to conserve MW at the end of the 12th five year plan. In
energy. However, still many opportunities addition to the electricity saving, total
may exist for improving the energy thermal energy saving equivalent to 21.30
efficiency in the railway sector as a whole. million tonne of oil equivalent (mtoe) in
Given the energy saving potential that the Industries & SME, Transport sector
may exist in this sector, it is proposed to and Energy Conservation (EC) award is
initiate studies and various schemes in also expected to be achieved in the
coordination with the Ministry of terminal year of 12th Plan.
Railways. The details of target of energy saving
Additional sectors during 12th Plan as well as corresponding
fund requirement for various programmes
A few additional sectors are proposed initiated by BEE are summarized in
under the 12th Plan, where possibilities to following table.
reduce energy consumption exist, which

Energy Conservation and Demand-Side Management Chapter 12: Page | 219


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Energy Saving Targets for 12th Plan


Total Fund Total Fund
Targeted Targeted
Sr requirement in requirement in
Sectors Schemes Electricity Thermal Fuel
No schemes (Rs. In sector (Rs. In
Saving, BU Saving, mtoe
Crore) Crore)
DSM Programme
1 Utility Based DSM 300 300 - -
for Utilities
Industries 3767 11.96 10.41
2 Industries 4222
SMEs 455 1.83 1.59
Bachat Lamp
3 Residential Sector 6 6 4.40 -
Yojana
Standards &
Equipment & Labeling 183 10.40 4.30
4 1653
Appliances (S & L)
SEEP 1470 6.60 -
Agricultural
5 Agriculture Sector Demand Side 393 393 0.70 -
Management
ECBC & Energy
6 Commercial Sector Efficiency in 65 65 5.07 -
Existing Buildings
Municipal Demand
7 Municipal Sector 45 45 0.47 -
Side Management
State Designated
8 SDA Strengthening 140 210 - -
Agencies
State Energy
70 - -
Conservation Fund
National Awards,
National Awards,
9 Painting & 100 100 3.42 5.00
Painting & Awareness
Awareness
Innovative Energy Efficiency
10 200 200 - -
Technologies/Areas Research Centre
11 HRD HRD 288 288 - -
Total 7482 44.85 21.30
Total electricity saving at demand side, BU 44.85
Total electricity saving at Bus bars, BU 60.17
Following recommendations/new thrust of the SDA program during the
initiatives are suggested for 12th Plan. 12th Plan will be on strengthening the
32 SDAs which would enable them to
 Continuation of on-going
implement various programs and
Schemes/Programs by Bureau of
activities initiated by BEE or SDAs
Energy Efficiency and Ministry of
themselves.
Power
 In the 12th Plan, it is proposed to set
 State designated agencies (SDAs) in
up State Energy Conservation Fund
different states need to play a very
(SECF) in all the States and pursue
important role in terms of carrying
with SDAs for constitution of SECF in
forward various energy efficiency
the states to implement various
initiatives at the state level. The
energy conservation activities and

Chapter 12: Page | 220 Energy Conservation and Demand-Side Management


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

utilization of fund under SECF.  Undertaking of check testing, label


Matching contribution may be made verification, market impact
by the state governments to the assessment for appliances/
SECF. equipments covered under S&L
The proposed activities in 12th Five Year scheme and
Plan under Standard & Labelling  Up-gradation of energy performance
Programme (S&L) for equipments and standards for equipment/ appliances
appliances include: covered during 11th Plan.
 Inclusion of at least 5 selected new Under the labelling scheme, the following
equipment and appliances. Standby activities are proposed
power loss reduction in few of the  Introduction of fuel economy norms
electrical appliances will also be effective from 1st year of 12th Plan,
focussed in the 12th Plan.
 Awareness creation among all the  Technical study for 2 & 3 wheelers and
stakeholders, commercial vehicles (Truck & Buses)
to finalise S&L programme

---+++---

Energy Conservation and Demand-Side Management Chapter 12: Page | 221


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Chapter 12: Page | 222 Energy Conservation and Demand-Side Management


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 13

REQUIREMENT OF PEAKING POWER AND RESERVE MARGIN

13.0 BACKGROUND times, the largest amount of electricity is


needed (peak load), but a “base load” of
The National Electricity Policy, 2005 aims electricity is needed year-round. Because
at achieving the following objectives. electricity cannot be stored easily, utilities
must anticipate demand, even on the
 Access to Electricity – available for all hottest summer day or coolest winter day,
households.
and supply enough electricity to meet the
 Availability of Power – demand to be
demand. Consumption depends
fully met by 2012. Energy and peaking
shortages to be overcome and predominantly on the time of day and on
spinning reserve to be available. the season. Utilities meet this demand
 Supply of reliable and quality power of with in-state power plants and by
specified standards in an efficient purchasing electricity from power plants
manner and at reasonable rates. in other states. The balancing of supply
 Financial turnaround and commercial
and demand is required in order to
viability of electricity sector.
 Protection of consumers’ interests. maintain a reliable electric system without
a power interruption to the consumer.
While, a lot of work has been done and is Energy use, as opposed to demand, is the
under progress for achieving the total amount of measured electricity that
objectives as envisaged in the Policy, but consumers use over time. Demand or
out of the above, objectives like Demand energy use can be divided into “base
to be fully met, Energy & Peaking
load,” “intermediate load,” and “peak
shortages to be overcome and building
spinning reserves have yet to be load”. This helps to determine the type
achieved. It is expected that although in and quantity of power plants needed to
next 5 yrs or so our country may become produce the electricity at the right times.
base load power surplus but peak power Different types of plants using different
deficits will still prevail. In this scenario fuels or combination of fuels are needed
any measures for improving the base load
to fulfil one or more of these three types
power situation shall not lead to the
of demand.
desired and targeted benefits to the
economy.
Base load plants provide a base level of
Consumers’ demand for electricity electricity to the system and are typically
changes daily and seasonally. During peak large generating units. Base load plants

Requirement of Peaking Power & Reserve Margin Chapter 13: Page | 223
operate almost continuously system stability requires matching of
(approximately 70 to 80 percent of the generation with the demand at all
time), except when down for scheduled instances of time, a certain degree of
maintenance, repairs, or unplanned flexibility and ability of the generators to
outages. They take a long time to ramp respond rapidly to the changing
back up to full capacity and have limited demand/availability for RE sources must
ability to vary their output of electricity. In be introduced into the system through
contrast, plants that satisfy peak demand appropriate generation plants.
(peaking plants) are highly responsive to
changes in electrical demand. They can be 13.1 RESERVE MARGIN (RM)
turned off and on relatively quickly.
However, they typically operate less than A reserve margin is the electric generating
20 percent of the time. Peaking plants are capacity the utilities maintain beyond
most often either reservoir based Hydro demand to handle unpredicted needs and
projects or Pumped storage systems or shut downs, both planned & forced. It is
natural gas combustion turbines. The cost the generation capacity above the annual
and flexibility of intermediate load plants peak requirement. Normal practice
fall in between those of base and peak requires utilities to maintain at least a 15
load plants. These plants are designed percent reserve margin in their electric
more specifically for cyclic operation, or generation planning.
they can be older coal plants that have Reserve Margin (RM) = (Installed Capacity
become too expensive to run as base load – Peak Load) / Peak Load
plants. They normally operate during
times of elevated load demand, between At present our system has about 28%
30 and 60 percent of the time. Compared reserve margin. In spite of having a
to peaking plants, they are generally more significant reserve margin the system has
efficient or utilize a cheaper fuel source a high loss of load probability. This is due
and, therefore, cost less to operate. to the following factors:
A system that is designed for base-load
generation will lack the characteristics to i) The outages both forced and due
respond dynamically or efficiently to the to maintenance are high.
variation in demand within a short time. ii) The share of Renewables which is
Apart from variation in demand, there is about 10% does not generate
expected to be wide variability in during peak hours and are of highly
generation as well, when the installed non-dispatchable in nature.
base of renewable energy plants increases iii) The share of Hydro projects is
as a result of pressure on Discoms to about 23% and the energy of the
source their requirement from renewable hydro projects is relatively low.
energy sources (to meet RPO). Since

Chapter 13: Page | 224 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

loss in supply. It occurs because


13.2 OPERATING RESERVES immediately following a loss of supply;
the generators slow down due to the
Operation of Power System has to be increased load. To combat this
made to meet the load forecast. slowing, many generators have a
Secondly, utilities make forecast for a governor. By helping the generators to
planned load or schedule to deliver equal speed up, these governors provide a
amount of power. However, the actual small boost to both the output
availability of power or the actual load frequency and the power of each
may be different from what was forecast, generator. However, because the
due to a number of reasons like extreme frequency-response reserve is often
weather conditions or unscheduled small and not at the discretion of the
outages to generation units. Thus system operator it is not considered
generation and distribution have to be part of the operating reserve. The
managed by what are known as frequency deployment of the primary control
control reserves. The system has to have reserves is from 0 to 30 seconds. The
certain surplus spinning capacity to primary frequency control systems are
immediately meet the change in forecast activated if the frequency deviation is
demand. more than the dead band of the
controller. Half of the primary control
System reserves can be classified into reserves should be in operation in 15
i) Primary Control Reserves or seconds, and all reserves should be in
Frequency Control Reserves full power in 30 seconds.
ii) Secondary Reserves or
Spinning and Non-spinning  The non-spinning or supplemental
Reserves reserve is the extra generating
iii) Tertiary Reserves or
capacity that is not currently
Replacement Reserves
connected to the system but can be
 The spinning reserve is the extra brought online after a short delay. In
generating capacity that is available by isolated power systems, this typically
increasing the power output of equates to the power available from
fast-start generators. However in
generators that are already connected
interconnected power systems, this
to the power system. For most
generators, this increase in power may include the power available on
output is achieved by increasing the short notice by importing power from
torque applied to the turbine's rotor. other systems or retracting power
that is currently being exported to
The frequency-response reserve (also
other systems. The secondary reserves
known as regulating reserve) is
provided as an automatic reaction to a should be activated within 30 seconds

Requirement of Peaking Power & Reserve Margin Chapter 13: Page | 225
and they should be in full output typically initiated when the frequency
within 15 minutes. The activation is drops below the given limits. The
done automatically. The secondary manual actions are initiated by starting
control reserves should release the the reserve power plants (non-
primary reserves for the next spinning reserves), or by increasing
disturbance in the system. the load of the operating plants
 Tertiary Reserve/Replacement (spinning reserves). Tertiary control is
Reserve: Tertiary control actions based mainly on manual actions
should free the secondary control initiated by the operator.
reserves in 15 minutes from the start
of the disturbance. Part of the actions The time periods over which all three
will be taken automatically and some kinds of reserve power operate is
manually. Automatic actions are illustrated in the diagram given below.

13.3 REQUIREMENT OF RESERVE PLANTS meet the distribution in the system. The
reserves should be activated within a
The Optimal power system should have period of 30 seconds and should give full
about 15-20 % reserve plants, about 20- output within the next 15 minutes, with a
30% peaking plants, 10-20 % Intermediate view to release the primary control
plants, and about 50-60% Base load reserves. In addition the system should
plants. In Indian power system also, the have tertiary reserves also which can
standard frequency control reserves are take over from the scanty reserves
also need to be created. These are within fifteen minutes of the disturbance
reserves which are primarily reserved to and release these scanty reserves. These
Chapter 13: Page | 226 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

are generally non spinning reserves to a drop in frequency of say 0.1 to 0.2
which can be brought into service at Hz is to bring on line a hot reserve plant
very short notice. As such it is important (equal to the largest single unit in the
to discuss as to what should be the grid) in 5-30 seconds, through automatic
quantum of each of these resources. generation control (AGC). As a second
step, fast reserve power plants (FRPP)
13.4 PRACTICES IN DEVELOPED are started in 4-15 minutes and ramped
COUNTRIES up to full load, after which the AGC plant
will retreat to reserve mode. As a third
As regards the Reserves in the Power
step, replacement reserve power plants
System, in developed electricity markets
(RRPP) come on in 45-60 minutes, after
abroad, it is customary to have several
which the FRPP plants return to their
layers of reserves to meet the
stand-by mode. These reserves are as
contingencies. The first rapid response
illustrated in Figure 13.1 below:

Figure 13.1

To restore first To restore


To come on line if response second response
frequency drops by plants to plants to standby
0.1 or 0.2 Hz normal

The several layers of reserves as planned fast replacement reserve is required to be


in the developed countries also take care from a generation source which is capable
of the flexibility of operation of the of ramping up within 4-15 minutes to take
various reserves. Therefore hot reserve over from the AGC sources. However
which is required to operate within Replacement Reserve Capacity could be
seconds is generally provided through from slower acting generation source to
Automatic Generation Control (AGC). The take over from fast acting reserves.
Requirement of Peaking Power & Reserve Margin Chapter 13: Page | 227
Accordingly, each of these reserve within 30 seconds and can be in full
capacity has to be from appropriate output within 15 minutes.
generation source having the requisite 3. The tertiary reserves can be some
ramp up and ramp down characteristics. old oil or coal fired stations which
can be activated manually and free
The rule that the grid operator generally the secondary reserves for fresh
uses is that they must always have an disturbances.
ability to replace the loss of the largest
generating unit. It can of course be Indian System
replaced from multiple sources, including The load duration curve of the country
imports. Because of the hydraulic and reveals that the duration of peak demands
import abilities, they don’t need to keep being shorter, it may not be economically
fossil units running very much just for viable to depend on purely base load
spinning reserve (but they do warm them stations to meet such peak demands. It
up in advance of forecasted demand). makes more sense to set up some power
Nuclear can not be used for spinning plants for operating only during peak
reserve. It is either on or it is off. The period. However, such plants would
same is true of co-generation or combined require a different tariff structure to
heat and power installations. recover their costs. Differential tariff
structure for peak and off peak periods
Our suggestions on Reserves for the existing generating plants as well
1. About 10,000 MW of the capacity as for the new peaking power plants can
which will be operating at lower to a large extent address this problem.
PLFs would ramp up to meet the The non-pit head power plants and
sudden peak in demand and these coastal plants based on imported coal
will be our primary control with higher variable charges may have to
reserves alter the load during the day depending
2. The supplemental reserves or on the load demand. During the off-peak
secondary reserves can be the hours also, such coal based plants may
hydro stations with storage, continue to operate, though at reduced
pumped storage plants or Gas load.
engines which can be activated

Chapter 13: Page | 228 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

The following figures show respectively the all India load duration curve (as met) for 2008-
09 and projected for 2016-17:

ALL INDIA PROJECTED LDC 2016 -17

Requirement of Peaking Power & Reserve Margin Chapter 13: Page | 229
13.5 REQUIREMENT OF PEAKING frequency-linked prices and sometimes by
POWER load shedding also. The frequency band
tolerated here (from 50.5 to 49 Hz) is far
Power supply position in the country above that permitted in developed
indicates continued energy and peaking countries. However in the future this
shortages. While the energy shortage frequency band is expected to narrow
makes it imperative to set up base load down to 49.9 to 50.1 Hz and this would
stations, the peak shortage underscores reduce the available margin to meet the
the need for separate dispensation to peaking requirement or reserve capacity
meet demands during peak periods. through frequency linked interchange
Peaking demand in Indian states has been mechanism. Hydro power plants also can
met, to an extent, by purchasing power be started up quickly to meet sudden
from other states through bilateral peaks, but this facility is restricted to
agreements or through the mechanism of those few states that have adequate
Unscheduled Interchange (UI) at water storage, all through the year.
response during peak hours could be
Peaking power can ideally be provided by provided by the gas engine based
pondage / reservoir based hydro plants. generation because of their excellent
However, hydro capacity alone may not peaking support capability.
be able to meet the peaking demand. Fast
Given the continuing peaking shortages meet mainly the peaking and intermediate
on all India level and the region specific or load demand.
State specific shortages there is a need for The trends both in terms of volume and
peaking power plants. At the same time, price of electricity in the short-term
given the fact that energy shortages also market further reiterate the need for
persist we would continue to need setting up of adequate generation
investment in the base load / intermediate capacity in general and peaking power
load stations. The major capacity addition plants in particular to enable the
is expected in hydro, coal and renewable. distribution companies to make long-term
Hydro capacity addition though small is planning for meeting their requirements
also mainly in run of the river type or with for power for base-load as well as peak-
small pondage. No peaking stations are load.
under execution except 1000MW pumped
storage scheme at Tehri, order for which 13.6 OPTION FOR PEAKING POWER
is yet to be placed. Thus there is an urgent GENERATION
need to plan for peaking capacity. It
would also be desirable to operate the The optimum base load capacity is the one
combined cycle gas based capacity to which can supply energy under the Load
Duration Curve (LDC) running at nearly full

Chapter 13: Page | 230 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

load both technically as well as turbine station, and gas based


commercially (with reference to its cost of reciprocating engines.
operation and efficiency). On the merit
order the demand is first met from Peaking plants shall be environmentally-
nuclear or renewable energy sources or friendly and must comply with emission
run of the river hydro stations and hydro norms, so as to be located close to load
plants with storage which have to release centres. They must be able to start up
water to meet irrigation requirements (and stop) instantaneously and ramp up
which are must run, followed by quickly, and in required steps, to match
generation from pit head coal based the spike in load. Their efficiency curve
station, followed by load centre and must be high and flat at different plant
coastal coal based stations, and combined loads. They must be ‘all-season’ plants and
cycle gas based station. Balance demand use a fuel which is available throughout
could be supplemented further by the year. A comparison of various types of
peaking power plants, namely, storage peaking alternatives and their economics
type hydro generating station including in term of objective function being
pumped storage schemes, open cycle gas minimum are as given in Table 13.1 below:

Table 13.1

Type Capital Effici- Fixed Variable Obj.fn Rs.Cr. % Change


cost ency O&M O&M
Cr/MW % Rs/kW Rs/MWh 2017 Ext. 2017 Ext.
period period
Gas Engines 3.5 41.9 842 442 49991.3 357145.2 - -
Gas (Duel 4.0 42.6 870 442 50228.4 358514.8 0.47 0.38
Fuel)
Diesel HFO 3.0 41.8 1270 663 50232.9 359198.1 0.48 0.57
OCGT 3.0 37.8 876 731 50241.9 359270.5 0.50 0.60
From the above gas engines appear to be the cheapest option.

Peak load management can be very alone plants supplying peak demand.
useful in the short term. It can be With the National grid in place the role
developed further with remote of distributed plants is to meet the peak
measuring and a new load based tariff load and reserve loads. Distributed
system or time of the day metering & power can be a major source to meet
tariff. However, as there is a significant the peak demand in the future. In peak
demand during peaking specially in cities load service the most profitable
and big towns separate peaking plants investments are the gas & Diesel engine
are to be setup. These are to be plants and Aero derivative gas turbine
distributed generating plants or stand plants. The most common applications
Requirement of Peaking Power & Reserve Margin Chapter 13: Page | 231
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

of the internal combustion engines are in that even CCGT can work on load shift
standby and reserve capacities. They are basis as peaking stations.
distributed in hospitals, super markets,
airports, nuclear power plants and The hydro generating stations, other
industrial facilities to ensure safety in than run of the river type, can be
case of blackout or in a sudden spurt of operated, as and when required. In
demand. these stations water can be stored
during off-peak hours so as to generate
Typical diesel engines can be more power during peak hours. As such
synchronized in one minute, and can these hydro generating stations are
deliver full output within 3 minutes. Gas normally used as peaking power
Engines can be synchronized in 2 stations. The pumped storage hydro
minutes and can deliver full output generating station is also a good option
within 8 minutes. An Aero derivative gas for meeting peak demand.
turbine can be synchronized within five
minutes & can deliver full output in ten Similarly we may also have to plan some
minutes. These options may be GTs / Reciprocating Gas Engines to meet
considered to meet the peak demand the peaking requirements. These plants
and the tariff may be as per CERC will be expected to be operated for
guidelines for peaking tariff. about 6-8 hours a day. It is
recommended that part of such plants
13.7 ISSUES IN PEAKING PLANTS may be constructed near the metro
cities in the vicinity of existing or
Peaking plants are generally gas turbines proposed gas grid. Besides meeting the
that burn natural gas or Pumped storage peaking demand these plants could also
systems. A few plants burn petroleum- be operated during the system
derived liquids, such as diesel oil and jet contingencies such as low voltage,
fuel, but they are usually more expensive transmission constraints, etc., thus
than natural gas, so their use is limited. adding to reliability of power supply of
However, many peaking plants are able the metro city.
to use petroleum as a backup fuel. The
thermodynamic efficiency of open cycle Operation of CCGTs in peaking mode as
gas turbine power plants ranges suggested above and OCGT for peaking
between 30 to 42% for a new plant. may result in higher heat rate and O&M
Reciprocating gas engines are also good costs (on account of higher repair and
options for the peaking plants near the maintenance cost) for which the power
load centres and can provide higher plant will have to be compensated.
efficiency of about 44%. It is now stated

Chapter 13: Page | 232 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Most of the combined cycle plants have power would be costlier as compared to
modules with 2 GTs and 1 steam turbine. off peak power. To determine the peak
It is proposed to close down 1 GT in each and off peak tariff a Task Force under
module after the evening peak hours the chairmanship of Shri Rakesh Nath,
and restart at the commencement of the then Chairperson, CEA was constituted
morning peak hours. Thus, during night by CERC and the task force has already
hours such plants may operate at about submitted the report. The notification
50% capacity. Some modern combined for separate tariff for peak and off peak
cycle gas based plants have single shaft power would help in flattening of Load
configuration with 1 GT and 1 ST. Such Duration Curve and ultimately it would
unit may have to be closed down result in lesser capacity addition to meet
completely during night hours after the same power demand in the country.
evening peak hours or may have to be
operated at partial load during off-peak 13.9 Policy Initiatives for peaking
night hours. power plants

Allocation of gas to the CCGT plants Provision in Act


connected to gas grid from domestic
Inception of peaking power plants
sources corresponds to operation of
would require initial Policy support to
these plants at a PLF of 70 to 75%. Cyclic
start off with. There are following
operation of CCGTs in the manner
regulatory enablers that provide for the
indicated above will be optimal use of
provision of the same. Relevant
available gas. Presently, GAIL does not
stipulations under Electricity Act 2003
allow wide variation in withdrawal of gas
are
by power plants. However, with
increase in pipeline capacity such
i. Section 61 (b),(c)&(e) of the
variations may be possible in near future. Electricity Act, 2003: States that the
Matter will have to be taken with GAIL in Appropriate Commission, in
this regard. specifying terms and conditions for
determination of tariff, shall be
13.8 PEAKING TARIFF guided by :
a) Commercial principles
b) Encouraging efficiency,
Operation of CCGTs in peaking mode as
economical use of resources,
suggested above and OCGT for peaking good performance and
may result in higher heat rate and O&M optimum investments
costs (on account of higher repair and c) Rewarding efficiency in
maintenance cost) for which the power performance
plant will have to be compensated.
Therefore, it is obvious that peaking ii. Section 62(3) of the Electricity Act,
2003: The Act contemplates certain
Requirement of Peaking Power & Reserve Margin Chapter 13: Page | 233
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

specific factors which may form the cycling requirement at different times of
basis to justify differential tariffs, the day and also complement infirm
including nature of renewable energy plants. This
a) Total consumption of
will result into huge economical benefit
electricity during any specified
period; in terms of operational & capital
b) Time at which supply is expenses.
required;
c) Nature of supply; and Gas based power plants are amongst the
d) Purpose for which supply is best available options for meeting the
required. peaking power needs. Also as Natural
gas is a scarce resource it needs optimal
In the above, efficiency and rewarding
utilization. For gas based peaking power
efficiency performance needs special
generation, cost of generation would be
mention during formulation of peaking
on higher side if domestic fuel is not
power policy. As consistent with the
allocated. Hence, for gas based peaking
nature of Peaking, technology used for
power plant, there could be separate
meeting such needs should have certain
allocation of Domestic Natural Gas.
specific characteristics which are listed
as under:
Specific quantity of domestic gas may be
 Fast start up & shut down times
allocated for peaking plant for assuring
 Fast ramp up rate
reasonable cost to DISCOMs. Initially
 Wide load range
introduction of about 2000 MW (in
 Black start capability
various sizes ranging from 100 –150 MW)
 Un restricted up/down times
dedicated peaking power capacities is
 Fuel flexibility envisaged which would need about 2
 Low emissions MMSCMD of natural gas (@ 25% PLF).
In the bidding process for selecting Such Plants should be located in vicinity
dedicated peaking power plants, a of major cities/ industrial load centres of
critical evaluation needs to be done on the State for deriving the optimum
above parameters. benefits.

Plants specifically dedicated for peaking, Legislative and policy support required
shall be a part of planned capacity
addition and like the renewables, a 1. In line with National Electricity Policy,
target figure of 10% of installed capacity notification of Peaking Power Policy
by 2020 may be incorporated for peaking needs to done which provides
power plants. This will optimise the necessary directives to mandate the
generation mix, where “Base Load State distribution companies to
Plants” can run on high PLF & the provide universal access to power
“Peaking Power Plants” can meet the (by every section of society – rural,
Chapter 13: Page | 234 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

urban, agricultural) and unrestricted only 4 to 6 hours of power supply


availability of power to all. daily, while the cities suffer
restriction of various duration
2. It is necessary to mandate the from season to season.
Regulators to implement “load (ii) Also if existing plants are allowed
shedding free system” by allowing to supply peaking power as well,
differential tariff in different times of it may lead to a situation where a
day or for different users in a phased generation company defaults in
manner to recover the cost of power. its base-load supply
commitments to a distribution
3. Power purchase from dedicated company to cater to peaking
peaking power plants should be requirements in some other parts
based on an auction system (like of the country to unduly make
Case 2 bidding ) with plant profit.
characteristics defined in the bid
document as: This will also ensure additionality of
 6 hours/day operation split into capacity suited for the peaking plants at
multiple starts and stops much lower capital cost and higher
 Capability to start and reach full load efficiency. It is important to ensure that
within 10 minutes and stop within 2 distinction is made between “peaking
minutes plants’ and ‘base load plants’ as use of
same plant for both the purpose, will
CERC could be assigned the task of only result in profiteering by a section of
preparing model bidding document. In base load operators by diversion of
the above context, two directives could capacity in peak time.
be issued :-
1. In the formative years, say 5 years
(i) Existing Power Plants designed from date of issuing the Peaking
for base loads shall not normally Power policy, the State and Central
participate in auction as Peaking Electricity Regulators may approve
power plants. This emerges from procurement of power by DISCOMs
the very fact that if the existing from “new plants” set up as
plants had excess capacities to “Peaking Power Plants” either in
offer under ‘Peaking’, then there public or private sector when the
would not have been any plant capital cost is established by
necessity to shed or restrict the the plant owner based on
power supply to the extent it competitive bidding and the gas
prevails today in India. Most of price to be pass through. CERC with
the rural areas in our country get assistance of CEA may be mandated
to define a model tariff formula
Requirement of Peaking Power & Reserve Margin Chapter 13: Page | 235
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

based on suitable normative of fixed charges), as may be decided in


parameters. the REB.

Suitable policy measure coupled with 13.10 ISSUES IN INDIA


effective implementation plan will help
Indian electricity sector to come out of India being in a deficit situation so far
the problems of load-shedding & take really does not have any reserve plants
the country forward on the path of 24x7 to meet the sudden demand spikes. But
uninterrupted power supplies and thus while planning for the future with 5%
becoming a powerful enabler to the spinning reserve and the fact that India
economic growth & stability. However, is becoming a competitive market
there is a need to ensure that such reserve plants need to be identified/
measures lead to the new capacity – designated.
“Peaking Power plants” in the system.
13.11 OPTIONS AVAILABLE /
Duration of peak and off-peak hours SUGGESTED
For daily recovery of peak hour capacity
charges, the peak hours in a day may be In India one option to have reserve
considered as 6 hours in case of thermal margin could be construction of reserve
generating stations and 3 hours in case plants with proper regulatory support.
of hydro generating stations to be The other option that could be operation
declared by the National Load of plants below declared capacity, so
Dispatched Centre from time to time. that in case of sudden demand
additional power could be generated. In
Basis for differentiation of peak and off- planning exercise to carry out study for
peak tariff additional capacity requirement in future
The prices should be differentiated for plans, the availability factor is reduced to
peak and off-peak supply and the tariff meet the requirement of 5% reserve
should include variable cost of margin in the system.
generation at actual levels and
reasonable compensation for capacity
charges.
13.12 RECOMMENDATION
It would be necessary that a distinction
should be made between drawl of It is recommended to plan for at least
power in the peak and off-peak time. 2000 MW gas based peaking power
Over-drawls in peak time should be over plants during 12th Plan, 400 MW each in
a stiffer surcharge compared to over five major metro cities of India with
drawls in off-peak time – (say 10% to 50% proper regulatory support. The

Chapter 13: Page | 236 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

experience gained from operation of It is also recommended that a Task


these peaking plants would pave the Force under CERC to deliberate upon the
way for creation of additional peaking various aspects associated with setting
plants in other major cities and higher up of peaking plants and creation of
capacity in future plans. adequate system reserve may be set up
at the earliest.

---+++---

Requirement of Peaking Power & Reserve Margin Chapter 13: Page | 237
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

Chapter 13: Page | 238 Requirement of Peaking Power & Reserve Margin
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

Chapter 14

CONCLUSIONS AND RECOMMENDATIONS


The National Electricity Plan includes a capacity of 18,500 MW/30,000 MW
review of the 11th Plan, detailed planning during 12th Plan has been considered for
for the 12th Plan and Perspective 13th Plan planning studies to work out balance
projections. Planning Studies have been thermal capacity additions required. A
carried out, considering Demand as nuclear capacity of 2,800 MW has been
projected by the draft 18th EPS Report. proposed as per the information
Based on results of studies following furnished by NPCIL. Gas based capacity
recommendations emerge. of 1086 MW/ 13,086 MW has been
considered.
(1) 12TH PLAN CAPACITY ADDITION
REQUIREMENT (iii) The total capacity addition
requirement in the country for 12th Plan
(i)-A Capacity addition of about 80,000 under Base Case Scenario has been
MW would be required to be added in proposed as under:
the country during the 12th Five Year Plan
assuming likely capacity addition of Total Capacity (excluding
about 62,374 MW during the 11th Plan, renewable) - 79,690 MW
spinning reserve requirement of 5% as Hydro - 9,204 MW
per NEP, retirement of old inefficient Nuclear - 2,800 MW
thermal units of about 4,000 MW and Thermal - 67,686
revised reliability criteria of CEA. Three MW
scenarios have been worked out  Coal - 66,600 MW
corresponding to low renewables/Low  Gas - 1,086 MW
Gas (BASE CASE), Low Renewables/High  Renewable – 18500
Gas and High Renewables High Gas. MW
Indigenous capacity required to be
(ii) High priority has been accorded developed – 79,690 MW (1,200 MW
towards development of renewables, imports have been assumed from
hydro, nuclear and gas based projects in neighbouring countries).
order to minimize CO2 emissions. Hydro
capacity addition of 9,204 MW has been (2) 13TH PLAN CAPACITY ADDITION
considered during 12th Plan based on REQUIREMENT
progress of actual construction at
project site and taking into account A capacity of 79,200 MW would be
uncertainty in development of hydro required to be added in the country
projects relating to geological surprises, during 13th Plan considering capacity
natural calamities, R&R and addition of about 80,000 MW during 12th
environmental issues. Renewable Plan. Three Scenarios have been worked

Conclusions & Recommendations Chapter 14: Page | 239


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

out corresponding to Low commissioning agencies to meet


Renewables/No Gas (BASE CASE), Low the rapidly growing
Renewables/High Gas and High requirement.
Renewables/High Gas.  Logistics for movement of heavy
machinery like roads and bridges
The total capacity addition requirement must be improved.
in the country for 13th Plan under Base  Making the key inputs available
Case has been proposed as under: like Cement, Steel, etc. These
need to be tied up well in
Total Capacity - 79,200 MW advance.
(excluding renewable)  Human resource development
Hydro - 12,000 MW commensurate with the
Nuclear - 18,000 MW requirement of the various skilled
Thermal - 49,200 MW and unskilled manpower is
 Coal - 49,200 MW essential.
 Gas - 0 MW
 Renewable 30,500 MW (4) POLICY INITIATIVES
Hydro Import – 8,040 MW
In order to realise the massive
 Indigenous capacity required to be capacity addition requirement during the
developed – 79,200 MW 12th and 13th Plans within the ambit of a
(Considering 8,040 MW imports Low Carbon Growth Strategy, a number
from neighbouring countries ) of Policy Initiatives and Measures need
to be taken. They are as summarised
(3) MAJOR ISSUES below:

With a view to expedite new capacity (i) Central Electricity Authority (CEA)
addition, following issues may be has been carrying out Integrated
addressed expeditiously: Power Planning for the country
as a whole. The States are
 Availability of land and water. responsible for State specific
 Environment and forest clearance planning for generation,
at State level to expedite E& F transmission and distribution
clearance to the project with a view to optimally utilize
 To incentivise new BOP resources and to meet their
manufacturers and the existing demand. Earlier, State Electricity
manufacturers to increase their Boards which were integrated
capacity and/or diversify, in order entities were doing integrated
to meet the complete demand of power planning for the States.
the new power generating After unbundling of power sector
capacity. This would also be in the States and formation of
instrumental in introducing generation, transmission and
competition and reducing prices. distribution companies, there is
 To incentivise setting up of more no single organization
number of erection and responsible for integrated

Chapter 14: Page | 240 Conclusions & Recommendations


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

planning and coordination with adopted is LOLP of 0.2% and ENS


CEA. of 0.05%. It is felt that as more
and more generation capacity is
It is proposed that integrated added, the planning norms
planning of generation, should be made more and more
transmission and distribution stringent to improve the
systems within each State may be reliability of generation.
done by a single agency. To
facilitate this each State may
appoint a suitable Nodal Agency (5) ISSUES RELATED TO COAL
for this purpose which shall AVAILABILITY
coordinate with the generation
and distribution utilities in the (i) Coal Requirement by the End
States. of 12th Plan.

(ii) National Electricity Policy Coal requirement during the year 2016-17
stipulates that a spinning = 842 MT
reserves of 5% needs to be
provided in the system. However, Coal availability from :
this implies a large capacity to
provide spinning reserve which (a) CIL = 415 MT
would otherwise be idle in the (b) SCCL = 35 MT
system. Since this implies setting (c) Captive Blocks allocated to Power
up of power projects involving Utilities = 100 MT
huge sum of money , which are (d) Coal to be imported by TPSs
required to operate only under designed on imported coal 54 MT
emergency condition, it is Total, coal availability = 604 MT
suggested that the amount of Shortfall = 238 MT
spinning reserves may be
reduced to Largest unit size + In order to bridge the above gap
fraction of peak load (1 % may be between demand and coal availability as
considered). For the 12th Plan, this referred above, Power Utilities are
corresponds to about 3000 MW. expected to import around 159 MT to
A discussion on what should be meet shortage in coal supply from CIL.
the optimum Spinning Reserve is This quantity of imported coal would be
required. in addition to 54 MT coal likely to be
imported by Thermal Power Stations
(iii) Earlier the generation planning designed on imported coal. Therefore,
exercise was carried out the total quantity of coal expected to be
corresponding to reliability imported is about 213 MT.
criteria of 1% LOLP and 0.15% ENS.
While planning for 12th & 13th Plan
capacity addition the reliability (ii) Limited availability of coal for running
criteria has been made more of power stations is a matter of grave
stringent and the criteria

Conclusions & Recommendations Chapter 14: Page | 241


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

concern. Following initiatives therefore • Deficiency in mining agencies


need to be taken:- and equipment to be
overcome
a. Use of domestic coal in a • Upgradation of coal mining
judicious and most appropriate facilities, desired quality of
manner. Due to shortage of coal etc.
domestic coal, import of coal may • Adequate crushing facilities at
also be tied up. A Policy decision mine head.
may have to be taken to allocate • Expedite setting up of rapid
coal only to super critical power loading system/ Silos at coal mine
plants in future. head.
• Construction of Dedicated Freight
b. Other Initiatives which Corridors to be expedited.
needs to be taken to ensure • Allocation of coal mines on tariff
availability of coal to power based bidding like Case II tariff
plants are as follows: based biding for power projects.
• Compress time taken for
• Acquisitions of fuel assets abroad development of coal blocks
by power developers, coal • Coal mining may be allocated to
companies and other industries private parties on cost/time basis.
and tieing up of import of coal on • Setting up of coal washeries for
a long term basis. reducing burden on railways and
• Development of specialized to improve efficiency of power
ports/jetties well-equipped with stations.
adequate coal handling • Development of Coal Blocks.
infrastructure.
• Priority to Power Sector in (6) ISSUES RELATED TO GAS AVAILABILITY
berthing at ports. AND NEED FOR PROMOTION OF GAS
• Development of adequate port, BASED GENERATION IN THE COUNTRY
railways and roads infrastructure
for transportation of coal to (i)So far gas available from KG basin has
power projects. been allocated to existing projects only
• Additional availability of Railway and Power Sector has been given 2nd
Rakes and augmentation of priority in gas allocation next to Fertilizer
tracks / sections commensurate Sector. It is recommended that power
with increasing requirement for projects be given highest priority as far
transportation of coal from pit as domestic gas allocation is concerned
head to power plant. in view of power shortage in the country
• Availability of wagons in and very low emission from gas plants
conformity with the unloading which will help us in restricting CO2
facilities available at TPSs. emissions from power sector. In view of
• Expeditious implementation of expected coal shortage during 12th Plan,
express freight corridor. it would be desirable to plan for about
25,000 MW gas based projects in next
few years to meet the capacity addition

Chapter 14: Page | 242 Conclusions & Recommendations


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

target and also to reduce our total CO2 requirements far more reliably compared to
emission. other available options.

(ii) Total Gas Requirement by Terminal Shorter construction periods


Year of 12th Plan (2016-17) Gas-based power plants can be constructed
in a much shorter time-frame of 18-24
It is expected that total gas based months relative to longer construction
installed capacity in the country by the timelines involved in coal and hydel projects.
end of 11th Plan would be about 20,000
MW corresponding to gas requirement
Lesser strain on resources – land and water:
of 98.4 MMSCMD at 90 % PLF. Details of
Gas based plants require lesser land and
fuel requirement during terminal year of
water as compared to coal based plants or
12th Plan are summarised below:
hydro capacities, where there is a possibility
of large-scale people displacement.
Gas requirement by 11th Plan end: 98.4
MMSCMD
Additional Gas Requirement for 25,000 Considerable environmental benefits
MW capacity during 12th Plan : 90 relative to coal-based power:
MMSCMD (at 70/PLF) Gas-based power is considerably cleaner
Total Gas requirement by 12th Plan end: when compared to coal-based power. CO2
188.4 MMSCMD emissions from a modern combined cycle
gas turbine (CCGT)/ combined cycle gas
(iii) Need for Promotion of Gas Based engines (CCGE) are only 0.35 kg/kwh in
Generation in the Country contrast with 0.83 kg/kwh from a 660 MW
super critical unit.
There is urgent need for promotion of gas
based generation in the country due to Diversification of fuel supply /energy
inherent advantage of these power plants, security risks:
as given below: Availability of domestic natural gas, though
anticipated to increase substantially post
Load profile in the country and the role of commencement of production from KG-D6
gas based power in addressing the gas finds, has declined in the recent months.
requirements reliably: However, a calibrated approach in gas-based
CERC has encouraged setting up of peaking capacity addition combined with the
capacities by prescribing peaking tariffs for adoption of appropriate policies in the
different category of plants including natural gas sector, still makes sense to
pumped storage schemes. Hydel projects diversify fuel supply risks resulting from
have taken much longer gestation period for excessive dependence on coal. Even if part
development and construction and as a of gas requirement is to be imported as LNG,
result hydro power share in the country’s it provides diversification of source
generation capacity mix has continuously countries from where energy is imported,
slipped. It is in this context that gas-based thereby providing diversification of energy
generation can play an important role in security risks.
meeting peak/intermediate load

Conclusions & Recommendations Chapter 14: Page | 243


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

(iv) Policy changes to be adopted to suitably amended to alter current level


encourage gas based capacity (relatively low) of minimum off-take
addition guarantees to suitably higher levels. It
 Policy initiatives required to also needs to be ensured that gas-
incentivize gas based plants based plants do not face dispatch risks
including Combined Heating & during their intended hours of
Cooling plants having high
operation (peak/ intermediate load).
efficiency.
 Capital cost and heat rate under
 Mandatory purchase of gas based
power by DISCOMs and priority for competitive bidding scope: Bidding
gas allocation to CCHP plants. would therefore be primarily on
 Constitution of task force under competitively discovering capacity
CERC to address issues related to charges and conversion (net heat
setting up of Peaking and Reserve rate) efficiencies.
Plants.  Gas based peaking power if
 Standard Bidding Documents
integrated into the total electricity
(SBDs)– need to be adapted for gas-
generation system can lead to carbon
based power.
reduction efficiencies even higher
 Duration of PPA: Duration of PPA is
than renewables like wind or solar
kept at 25 years, it needs to be
power. Hence it is suggested to
brought down to 15-18 years, keeping
extend the fiscal benefits to gas based
in mind economic life of gas-based
peaking power projects at par with
power plants. Further, normally gas is
the renewable energy projects or
allocated for 5 Year period, as such
Ultra Mega Projects. Specifically, zero
signing of PPA need to be facilitated
customs duties & taxes and interest
for 5 year period, to be reviewed from
rate subsidy.
time to time in line with extension of
 Technical requirements for
gas allocation period upto the
intermittent or peaking application:
economic life cycle of 15-18 year of the
Bid invitation should specify these
plant.
requirements as the very nature of
 Fuel risks pass-through: Current
application would influence the choice
domestic and international market
of fuel and technology. These are –
environment for natural gas suggests
 Capable of number of stop / starts in a
that there are far too many
day in other words to operate on Load
uncertainties with regard to
Follow Principle
availability and/or price of natural gas.
 No effect on maintenance due to
Developers are not ideally placed to
multiple stop / starts
take those risks. Therefore fuel
 5 to 10 minutes time from start up to
availability and price risks need to be
full load
borne by the procurers.
 5 to 10 minutes shut down time from
 Take-or-Pay risk pass-through: Gas
full load to zero
supply contracts are characterized by
 Black start capability
high level of Take-or-Pay obligations
 No effect on efficiency due to part
on fuel buyer. PPA needs to be
load operation of the plant

Chapter 14: Page | 244 Conclusions & Recommendations


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

 High availability - >94% (8) DEVELOPMENT OF RENEWABLE


ENERGY SOURCES
(7) GREEN HOUSE GAS MITIGATION
Renewable Energy has been
STRATEGY
appropriately given the central place
in India’s National Action Plan on
Green House Gas mitigation strategy
Climate Change. During the 12th Plan
needs to be adopted in order to meet
a renewable capacity of about 18,000
the emission standards. Some of the
MW is likely to be added with
major Initiatives proposed in view of
substantially higher target of about
Coal being the main stay of the
30,000 MW during 13th Plan.
Generation capacity addition in the next
few plan periods are:
(9) ENERGY CONSERVATION AND
DEMAND-SIDE MEASURES
• Increase of unit size with higher
steam parameters.
Energy Conservation and demand-
• Technology Development – Adoption
of higher unit size & Clean Coal side measures will remain cost
technologies effective tools to bridge the gap
 Supercritical Technology – 2 between demand and supply of
percent point efficiency gain power. Three pronged approach of
possible Energy Efficiency, Conservation of
 Ultra Supercritical Technology –
Energy and Demand Side
additional efficiency 0.75% over
800 MW supercritical Management assumes central role in
 Integrated Gasification achieving the mission of Government
Technology – higher efficiency of of India - "Power for all" by 2012.
40-45% Towards this end, the power sector
• R & M and Life Extension of old has to play a central role in enabling
power stations – Benefits of CDM to this transformation. There is a need
be extended to overcome fund
to shift from supply domination and
constraints
• Energy Efficiency improvement capacity expansion towards
• Retirement of old inefficient units improvement in operational
• Coal quality Improvement efficiency of the existing power
generating stations, reduction in
Other measures include Transmission and distribution losses
• Reduction in T & D losses – All India and most importantly improving the
T&D losses- 28.65% in 2006-07. Aim to end use efficiency. Energy efficiency,
bring down to 15% conservation of energy and demand
• Efficiency in use of energy side management needs to be
• Setting up of pithead stations for tapped vigorously.
reduction in transportation of coal

Conclusions & Recommendations Chapter 14: Page | 245


National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

(10) NEED FOR PEAKING POWER PLANTS creation of additional peaking plants
in other major cities and higher
(i) It is recommended to plan for at capacity in future plans.
least 2000 MW gas based peaking
power plants during 12th Plan, 400 (ii) It is also recommended that a Task
MW each in five major metro cities Force under CERC to deliberate
of India with proper regulatory upon the various aspects associated
support. The experience gained with setting up of peaking plants
from operation of these peaking and creation of adequate system
plants would pave the way for reserve may be set up at the earliest.

----+++----

Chapter 14: Page | 246 Conclusions & Recommendations


Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

ACRONYMS
ACRONYMS EXPANSION
AC Alternating Current
AG&SP Accelerated Generation & Supply Programme
AHWR Advanced Heavy Water Reactor
AIIMS All India Institute of Medical Sciences
AMD Atomic Minerals Directorate
APM Administered Price Mechanism
AREP Accelerated Rural Electrification Programme
BARC Bhabha Atomic Research Centre
Bcum, Billion cubic metre
BCM,Bm3
BEE Bureau of Energy Efficiency
BFP Boiler Feed Pump
BHEL Bharat Heavy Electricals Ltd.
BSES Bombay Suburban Electric Supply
BU Billion units or Billion kWh
C&I Control & Instrumentation
CAD & CAM Computer-Aided Design & Computer-Aided Management
CAGR Compounded Annual Growth Rate
CBIP Central Board of Irrigation & Power
CBM Coal Bed Methane
CCEA Cabinet Committee on Economic Affairs
CCGT Combined Cycle Gas Turbine
CD Compact Disc
CDAC Centre for Development of Advanced Computing
CDM Clean Development Mechanism
CEA Central Electricity Authority
CFBC Circulating Fluidized Bed Combustion
CFL Compact Fluorescent Lamp
CFRI Central Fuel Research Institute
CIL Coal India Ltd.
CLA Central Loan Assistance
CPP Captive Power Producer
CPRI Central Power Research Institute
CPSU Central Public Sector Undertaking
Acronyms Page | 247
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

ACRONYMS EXPANSION
Crs Crores
CS Central Sector
CSIR Council for Scientific and Industrial Research
CSMRS Central Soil & Materials Research Station
CWC Central Water Commission
DAE Department of Atomic Energy
DC Direct Current
DDG Decentralised Distributed Generation
DGH Director General Hydro Carbon
DG Set Diesel Generating Set
DISCOM Distribution Company
DMLF Data Management & Load Forecasting
DOPT Department of Personnel & Training
DPR Detailed Project Report
DSM Demand - Side Management
DST Department of Science & Technology
DSTATCOM Distribution Static Compensation
DVC Damodar Valley Corporation
DVR Dynamic Voltage Restorer
EA 2003 Electricity Act 2003
ECIL Electronic Corporation of India Ltd.
EGEAS Electric Generation Expansion Analysis System
ENS Energy Not Served
EPS Electric Power Survey
ERDA Electric Research & Development Association
ESCO Energy Service Company
ESP Electro Static Precipitator
EPC Engineering Procurement Contract
FAUP Fly Ash Utilisation Programme
FBC Fluidised Bed Combustion
FO Forced Outage
FOR Forum of Regulators
GCV Gross Calorific Value
GDP Gross Domestic Product
GHG Green House Gas
GIS Gas Insulated Switchgear
GPS Geographic Positioning System
Page | 248 Acronyms
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

ACRONYMS EXPANSION
GR General Review
GSPC Gujarat State Petroleum Corporation
GT Gas Turbine
GWe Gega Watt (Electrical)
HBJ Hazira-Bijapur-Jagdishpur ( pipeline)
HFO Heavy Fuel Oil
HEP Hydro Electric Project
HPS Heavy Petroleum Stock
HRD Human Resource Development
HSD High Speed Diesel
HT High Tension
HVDS High Voltage Distribution System
ID Induced Draft
IEP Integrated Energy Policy
IGCAR Indira Gandhi Centre for Atomic Research
IGCC Integrated Gasification Combined Cycle
IISC Indian Institute of Science
IIT Indian Institute of Technology
IPP Independent Power Producer
IS Indian Standard
ISCC Integrated Solar Combined Cycle
ISO International Standard Organisation
ISPLAN Integrated System Planning
IT Information Technology
kCal kilo Calorie
kg kilogram
KKNPP Kudankulam Nuclear Power Project
kW kilo Watt
kWh kilo Watt hour
LEP Life Extension Programme
LF Load Factor
LNG Liquefied Natural Gas
LOA Letter of Award
LOLP Loss of Load Probability
LP Linear Programming
LRVI Loss Reduction & Voltage Improvement
LSHS Low Sulphur Heavy Stock
Acronyms Page | 249
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

ACRONYMS EXPANSION
LT Low Tension
LWR Light Water Reactor
MAPS Madras Atomic Power Station
MCFC Mother Carbonate Fuel Cell
Mcm Million cubic metre
MHD Magneto Hydro Dynamics
MMSCMD Million Metric Standard Cubic Metre per Day
MNRE Ministry of New & Renewable Energy
MNP Minimum Need Programme
MoEF Ministry of Environment & Forest
MoP Ministry of Power
MT Million Tonne
MToe Million Tonnes Oil equivalent
MU Million Units
MW Mega Watt
MWe Mega Watt electric
NAPS Narora Atomic Power Station
NCPS National Capital Power Station
NDT Non-Destructive Test
NEP National Electricity Policy
NFC Nuclear Fuel Complex
NHPC National Hydroelectric Power Corporation
NMDC National Mineral Development Corporation
NML National Metallurgical Laboratory
NOX Oxides of Nitrogen
NPC National Productivity Council
NPCIL Nuclear Power Corporation of India Ltd.
NPTI National Power Training Institute
NTC Nuclear Training Centre
NTPC National Thermal Power Corporation
OCGT Open Cycle Gas Turbine
OGIP Original Gas In Place
O&M Operation & Maintenance
PAFC Phosphoric Acid Fuel Cell
PC Pulverized Coal
PFBC Pressurised Fluidized Bed Combustion
PFC Power Finance Corporation
Page | 250 Acronyms
Central Electricity Authority National Electricity Plan U/S 3 (4) of Electricity Act 2003

ACRONYMS EXPANSION
PFR Preliminary Feasibility Report
PGCIL Power Grid Corporation of India Limited
pH Hydrogen Ion Concentration
PIE Partnership In Excellence
PIB Public Investment Board
PHWR Pressurised Heavy Water Reactor
PLF Plant Load Factor
PMGY Pradhan Mantri Gramodaya Yojna
PMI Power Management Institute
PMO Prime Minister’s Office
PPM Parts Per Million
PS Private Sector
PSC Production Sharing Contract
PSP Power Supply Position
PSS Pumped Storage Schemes
PSU Public Sector Undertaking.
R&D Research & Development
R&M Renovation & Modernisation
RAPP Rajasthan Atomic Power Project
RAPS Rajasthan Atomic Power Station
REB Regional Electricity Board
REC Rural Electrification Corporation
REDB Rural Electricity Distribution Backbone
RHE Rural Household Electrification
RLA Residual Life Assesment
RM Reserve Margin
SAARC South Asian Association for Regional Corporation
SEB State Electricity Board
SERC State Electricity Regulatory Commission
SOG Sanctioned & Ongoing
SOX Oxides of Sulphur
SPIC Southern Petro India Chemicals Ltd.
SPM Suspended Particulate Matter
SS State Sector
SSB Solid State Breakers
SSTS Solid State Transfer Switches
STPP Super Thermal Power Plant
Acronyms Page | 251
National Electricity Plan U/S 3 (4) of Electricity Act 2003 Central Electricity Authority

ACRONYMS EXPANSION
STPS Super Thermal Power Station
STUs State Transmission Utilities
T&D Transmission & Distribution
TAPP Tarapur Atomic Power Project
TAPS Tarapur Atomic Power Station
TIFAC Technology Information Forecasting & Assessment Council
TOU Time of Use
TPS Thermal Power Station
UCIL Uranium Corporation of India Ltd.
UMPP Ultra Mega Power Project
UN United Nations
UNDP United Nations Development Programme
UT Union Territory
VEI Village Electrification Infrastructure
WBPDCL West Bengal Power Development Corporation Limited

Page | 252 Acronyms

You might also like