Professional Documents
Culture Documents
György Kovács
To cite this article: György Kovács (2020): Combination of Lean value-oriented conception
and facility layout design for even more significant efficiency improvement and cost reduction,
International Journal of Production Research, DOI: 10.1080/00207543.2020.1712490
Combination of Lean value-oriented conception and facility layout design for even more
significant efficiency improvement and cost reduction
György Kovács ∗
Global market competition and fluctuating customers’ demands require manufacturing enterprises to focus on cost reduction
and efficiency improvement to increase competitiveness and sustainability. The purpose of the research was the elaboration
of the methodology and procedure of a new combined efficiency improvement method which basically applies Lean methods
and also uses the facility layout design (FLD) method simultaneously, integrating the different advantages of these methods,
which is even more efficient that applying each of the methods individually. The main significant added-value of the study
is the elaboration of a new combined method, which results in even more significant improvement of efficiency and several
KPIs, furthermore, cost reduction, which is confirmed by a real case study for the improvement of a manufacturing plant.
In the case study, the application of 13 Lean methods and the FLD method (which aims at the minimisation of material
workflow, travel distance of materials, material handling cost and space used for assembly) led to the improvement of
10 quantitative and 5 qualitative indicators: productivity; cycle-time; number of workstations and operators; WIP (work-
in-process) inventories; space used for assembly; material workflow; travel distance of materials; material handling cost;
labour cost; component supply; products’ quality; transparency; standardisation; workplace ergonomics.
Keywords: lean process improvement; facility layout design; newly elaborated combined improvement method; cost
reduction; real case study
1. Introduction
Globalisation, market competition, more individual and rapidly changing customers’ demands have resulted in changes in
the production system. In production the resources (raw materials, machines, humans, energy, etc.) are limited; the human
population and consumption are increasing; furthermore, environmental damage is also a global problem. So, current prac-
tices in the use of resources are not sustainable. Therefore, enterprises have to produce cost-effective, energy-efficient and
material-efficient final products, which can be achieved by maximised utilisation of resources. Innovative, environmentally
friendly technologies and efficiency improvement methods are required in order to establish profitability and sustainability
(Dolgui, Guschinsky, and Levin 2009; Kovács 2017; Yu, Cadeaux, and Song 2017; Kot 2018).
The significance of the research topic is that the companies have to focus on productivity and cost reduction; therefore,
the application of efficiency improvement methods is essential and important for companies in order to maintain and increase
their competitiveness and provide sustainable production.
The most often used efficiency improvement methods are the Lean philosophy and the Facility Layout Design (FLD).
The essence of the Lean methods is to focus on the elimination of waste or non-value-added activities to create value-adding
processes, and to realise only value-adding activities in the production system (Alemu, Torgeir, and Petri 2014). Therefore,
in the literature Lean process improvement is called value-oriented or value stream-oriented process improvement (Dennis
2015; Shingo 2017; Erlach 2013). FLD is another most often applied efficiency improvement method which aims at the
optimal arrangement of facilities (departments, workstations, machines, equipment, etc.) on the manufacturing site and the
optimal material flow between these facilities (Heragu 2016; Naik and Kallurkar 2016).
The combined efficiency improvement method applies the elements of the Lean and FLD methods simultaneously, inte-
grating the different advantages of these methods; therefore, it is even more efficient than applying each of the methods
individually. Based on the synthesis of the recent literature it can be concluded, that a uniform and standard methodology or
a procedure for the combined method is not available either in practice or in literature. Therefore, each researcher and indus-
trial expert elaborates and applies their own methodology and procedure differently, combining the elements and advantages
of the Lean and the FLD methods, so the procedures of the combined methods are also different. (The methodology and
*Email: loginno@freemail.hu
© 2020 Informa UK Limited, trading as Taylor & Francis Group
2 G. Kovács
procedure of the combined method mainly depend on the characteristics of the given industrial projects.) Consequently, the
methodologies and procedures relating to the combined methods of each author are unique and can contribute to the recent
state of the research field if they differ from other published methods and procedures and further at the same time lead to
significant process improvement.
The purpose of the research was the elaboration of a new combined efficiency improvement method which basically
apply the Lean value-oriented improvement methods, but use also the FLD method simultaneously in order to result in even
more significant efficiency improvement, cost reduction and improvement of several KPIs. The other aim of the research
was the introduction of a real case study to confirm that the elaborated new combined method can be applied effectively in
practice for the optimal formation of a manufacturing system.
The newly elaborated combined efficiency improvement method results in the utilisation of the different advantages
of the Lean and FLD methods, which is more advantageous compared to the individual application of the two methods
and even more significant efficiency improvement can be achieved. There is no need to execute the Lean and the FLD effi-
ciency improvement procedures separately; instead, we only have to consider, combine and apply the different advantageous
elements of the two methods in the same improvement procedure simultaneously.
There are several significant advantageous differences between the two methods that can be utilised by the application
of the combined method (Section 3.1). Among these differences, the two most important are that:
(1) FLD provides the possibility of the optimal arrangement of the workstations on a manufacturing site; in addition,
the number of workstations can even be reduced by the application of Lean methods.
(2) By the application of the newly elaborated combined method, the total travel distance of materials and the total
material workflow can also be minimised due to the usage of the FLD method, which results in the minimisation of
the material handling cost and minimisation of the space used for assembly. Therefore, these four KPIs can also be
improved by the combined process improvement method.
In the study – besides introducing the methodology, procedure and the practical steps of the newly elaborated method – a real
case study is also described, which confirms that significant improvement in efficiency and cost reduction can be achieved
by the application of the new combined method in a manufacturing plant. The case study shows how the production process
of a real manufacturing system was improved by the application of 13 Lean methods; furthermore – due to applying the
FLD method – the total material workflow, the travel distance of materials, the material handling cost and the space used
for assembly could also be reduced.
The original and the newly improved manufacturing processes and layouts were compared and evaluated in the study.
The results and the significant changes in the process improvement can be seen visually in Figures 4–5, and numerically in
Table 3.
From the case study, it can be concluded, that – due to the new combined method – 10 quantitative indicators (pro-
ductivity; cycle-time; number of workstations and operators; WIP inventory; space used for assembly; material workflow;
travel distance of materials; material handling cost and labour cost of operators) and 5 qualitative indicators (reliability
of continuous component supply of the production lines; processes’ and final products’ quality; processes’ transparency;
process standardisation; workplace ergonomics) were improved.
The main significant added value and novelty of the study is that I elaborated the detailed methodology and the procedure
of a new combined efficiency improvement method, and at the same time the efficiency of the elaborated combined method
is confirmed by a real industrial project. This elaborated combined method – due to the utilisation of the different advantages
of the Lean and FLD methods – results in even more significant efficiency improvement, cost reduction and improvement
of more KPIs in practice during the process improvement.
It can be concluded that – due to the utilisation of the different advantages of the Lean and FLD methods – even more
significant efficiency improvement can be achieved by the application of the newly elaborated combined method during the
improvement of manufacturing processes.
2018; Oliveira, Sousa, and Campos 2019; Braglia et al. 2019; Tortorella et al. 2019) and FLD methods (Pourvaziri and
Pierreval 2017; Anjos and Vieira 2017; Hosseini-Nasab et al. 2018) individually.
Several recent articles put great emphasis on the relations of different efficiency improvement methods and production
philosophies. So, few studies discuss the relation of Industry 4.0 conception and Lean production philosophy, i.e. Kamble
et al. analysed the effects of Industry 4.0 technologies on Lean manufacturing practices (Kamble, Gunasekaran, and Dhone
2019). There are also available some publications in topic of possibility of simultaneous application of Lean and Simulation
efficiency improvement methods (Uriarte, Amos, and Moris 2020).
There are some studies in which the elements and advantages of Lean and FLD methods are partially discussed, mainly
in relation with Lean philosophy (Bai, Satir, and Sarkis 2019; Shang and Sui 2014; Orr and Orr 2014; Chiarini, Found, and
Rich 2016). Furthermore, it can be found also few articles which discuss basically the FLD method, but partially mention
the cellular design method – as a Lean tool – and its advantages (Tubaileh and Siam 2017; Chen and Tiong 2019). But
in these publications, only the importance of the formation of the adequate layout is emphasised, and the general layout
configurations are described as single-row layout (linear, U-shaped, semicircular, serpentine); double row layout; multi-row
layout; cluster layout and loop layout. But in these articles, the procedure and methodology of the combined method are not
included.
Consequently, it can be concluded that there is a gap in the literature in the field of combined efficiency improvement
methods which integrate the elements and advantages of Lean and FLD methods simultaneously. In the existing literature,
there are no articles which focus on a combined method and discuss it in any depth. Therefore, there is a lack of studies
on the complex methodology and procedure of the combined methods as well as a lack of real case studies for process
improvement through the combined method.
Although Lean and FLD methods are often used in practice during the process improvement of industrial projects,
generally complex, theoretical and scientific methodologies and procedures are not elaborated based on the results of these
industrial projects, so no articles have been published in the topic of the combined method. The aims of industrial experts
are to achieve even more effective results during a real industrial improvement projects, but at the same time is not aim to
separate theoretically and methodologically the Lean and FLD methods. The opinion of some industrial experts is that in
practice the Lean and FLD methods are so closely related, that they are not really treated separately (Chiarini, Found, and
Rich 2016). On the contrary, a detailed and complex elaboration of the methodology and procedure of the combined method
is required in terms of science.
It can be summarised, that there are not enough recent publications available in the field of the combined efficiency
improvement method; therefore, a more detailed literature review cannot be presented in this topic.
Furthermore, it can be concluded, that a uniform and standard methodology or a procedure for the combined method
is not available either in practice or in literature. Therefore, each researcher and industrial expert elaborates and applies
their own methodology and procedure differently, combining the elements and advantages of the Lean and the FLD
methods.
Based on the above-mentioned facts – in my opinion – the main added-value of my study is that in my article I describe
the detailed methodology and procedure of the combined method that I elaborated, and at the same time a practical appli-
cation of this newly elaborated method is also introduced in the framework of a real industrial project, which confirms the
efficiency of the elaborated combined method.
The newly elaborated combined method applies the elements of both the Lean and FLD methods; therefore, the
methodology and procedure of these methods are introduced according to the relevant literature in the next sub-sections.
Recently this conception is used in many sectors, e.g. automotive, electronical and white goods, administration,
hospitals, education, etc. (Tubaileh and Siam 2017; Yildirim, Oflaç, and Yurt 2018; Pearce, Pons, and Neitzert 2018).
At first the objective function of the FLD has to be defined, which can be the minimisation of the total material workflow or
the minimisation of the material handling costs.
Material workflow (EMWF ) is a widely used objective function for the description of the amount of workflow that should
be minimised. Material workflow can be calculated:
n
n
EMWF = qij lij (1)
i=1 j=1
where qij is the material flow between the workstations (UL – unit load which can be a box, pallet, etc.); lij is the distance
between the workstations on the shop floor (m); n is the number of workstations on the shop floor.
Matrix of material flow:
1 ... j ... n
1 ⎡ ⎤
..
. ⎢ ⎥
Q= ⎢ ⎥
i ⎢ qij ⎥
⎢ ⎥
.. ⎣ ⎦
.
n
Matrix of distances:
1 ... j ... n
1 ⎡ ⎤
..
. ⎢ ⎥
L= ⎢ ⎥
i ⎢ lij ⎥
⎢ ⎥
.. ⎣ ⎦
.
n
• lij : the distance between the individual workstations on the shop floor (m).
6 G. Kovács
3. Newly elaborated combined efficiency improvement method – combination of Lean and facility layout design
methods
The main significant added value of the research is that I elaborated a new combined method, which – due to the utilisation of
the different advantages of the Lean and FLD methods – results in even more significant efficiency improvement, operational
cost reduction and improvement of more KPIs can be achieved.
3.2. General procedure and main practical steps of the combined efficiency improvement method
The main practical steps of the general procedure of the new combined method are the following:
(1) Determining the objectives of the improvement project, identifying the general problems with the management.
First, the most important design aims (KPIs) have to be defined: those that should be measured at the beginning of the
project and those which have to be improved by the end of the improvement project.
(2) Choosing the focus area – the most important product, product family, process or customer to be examined.
Pareto analysis has to be applied by the following possible criteria: final products’ volume; final products’ sales value; costs;
strategical customer; etc.
Based on the results of the Pareto analysis one final product or one process has to be chosen for in-depth analysis.
(3) Mapping the current state of the pilot improvement process – drawing the Current State Map (CSM).
CSM helps to represent where wastes occur in the process and to visualise the information flow and material flow, to
make the wastes visible, shows the relation between information flow and product flow, and defines the Lean improvement
actions.
International Journal of Production Research 7
3.3. Main contributions of the newly elaborated combined method to the industrial application
The newly elaborated combined efficiency improvement method results in the utilisation of the different elements and
advantages of the Lean and FLD methods, which is more advantageous and provides even more significant efficiency
improvement in industrial projects compared to the individual application of the two methods. The combined method results
in even more significant operational cost reduction and improvement of more KPIs, that applying each of the Lean and FLD
methods individually. We only have to combine and apply the different advantageous elements of the two methods in the
same improvement procedure simultaneously.
The newly elaborated combined method utilises the several significant advantageous differences of the Lean and FLD
methods, which provides the main contributions of the application of the combined method to the industrial application.
These main contributions are the following:
(1) The aims of both methods are taken into consideration in the new combined method: on the one hand to focus on
the elimination of waste or non-value-added activities, on the other hand, to achieve the optimal arrangement of
facilities and optimal material flow on the shop floor.
8 G. Kovács
(2) FLD provides the possibility of defining the optimal arrangement of the workstations on a manufacturing site; in
addition, the number of workstations can even be also reduced by the application of Lean methods (Takt-Time
Analysis and Line Balancing methods).
(3) By the application of the combined method – due to the usage of the FLD method – the total travel distance of
materials and total material workflow can also be minimised, leading to the minimisation of the material handling
cost and minimisation of the space used for assembly. Therefore, these four KPIs can also be improved by the
combined method.
(4) In the elaborated combined method – due to the application of the Lean methods – not only the quantitative indi-
cators, but at the same time the qualitative indicators (e.g. quality of the processes and final products, workplace
ergonomics, etc.) can also be improved.
(5) In the new combined method by the application of Lean methods (e.g. Cellular design, Supermarket, Kanban
methods, etc.) the huge number of possible layout alternatives can also be reduced.
• The layout of the manufacturing plant has to be adjusted from time to time to fit changing production plans
and processes (e.g. the company has to produce a new type or higher volume of final products, etc.).
• Modernisation of the manufacturing activity: new technologies have to be implemented, which require new
facilities (e.g. machines, workstations, etc.).
• Productivity and competitiveness of the company have to be increased (e.g. higher utilisation of machines,
humans, etc.).
• Sustainability requirements have to be fulfilled (e.g. application of environmentally friendly and sustainable
technologies, etc.).
• The aim of the process improvement is not only to achieve the optimal arrangement of facilities, but at the
same time also to reduce the number of workstations.
• Free space has to be provided on the shop floor for new value-adding activities (establishment of new
processes, e.g. packaging, etc.).
• In those manufacturing plants, where most of the workstations can be arbitrarily moveable on the shop floor,
because the cost and time of the rearrangement of the machines located in fixed position are very high.
• In those manufacturing process improvement projects which require the application of the combined
method, because the individual application of the Lean or FLD method is not effective enough. The com-
bined method integrates the different advantages of these two methods, which results even more significant
efficiency improvement, cost reduction and improvement of more KPIs, that applying each of the methods
individually (e.g. the number of the workstations cannot be reduced by the individual application of the
FLD method.)
The application of the combined method leads to significant positive results, i.e. improvement of several KPIs. On the
one hand – due to the FLD method – the reduction of the total travel distance of materials, reduction of the total material
workflow and reduction of the material handling cost can be achieved. On the other hand – due to the Lean methods –
the following KPIs can be improved: e.g. lead time, productivity, number of workstations and operators, labour cost, WIP
inventory and several quality indicators (e.g. products’ quality, ergonomic workplace), etc.
The application of the combined method is not more expensive compared to the individual application of the Lean or
FLD method (e.g. one of the most expensive activity is the rearrangement of workstations located in a fixed position, but
this activity is often used also in the FLD process improvement).
Of course a more complex process improvement requires higher investment cost. Based on the benefit-loss analysis
the total cost of the full implementation of the project and the payback period of the investment can be defined. Based
on this information the management makes the final decision relating to the detailed elaborated plan of the full process
improvement, which includes the budget, steps and scheduling of the process improvement project.
International Journal of Production Research 9
4. Discussion – process improvement of a manufacturing plant by the application of the newly elaborated
combined method, case study
In this section, the process improvement of a manufacturing plant is introduced by the application of the new combined
efficiency improvement method. The procedure of the process improvement was achieved by the main steps of Section 3.2.
During the complex process improvement 13 Lean methods were applied, which are the following: Value Stream Mapping;
Takt-Time Analysis; Line Balancing; Cellular design; 5S; Workplace ergonomics; Pull; JIT; Kanban; Supermarket; One-
piece flow; Visual management; Standardisation. Furthermore, the FLD method was also used, which resulted the reduction
of the total material workflow, the travel distance of materials, the material handling cost and the space used for assembly
(Section 4.2.).
The goal was to achieve significant results in the process improvement by the simultaneous application of more and
more Lean tools and FLD method. After it the original and the newly improved manufacturing processes and layouts were
compared and evaluated. The results of the process improvement can be seen visually in Figures 4 and 5, numerically in
Table 3.
TA min
Ttakt = (2)
Q unit
where TA is the total available working time in a shift (min); Q is the average number of final products that customers require
per shift (unit).
The total available working time is the total real manufacturing time (8 h/shift) including break times (0.5 h/shift). The
available working time in a shift is 450 min/shift.
In our case study, the customer’s demand is 80 units/shift of final products. Based on Equation (2) the calculated takt-time
is 5.62 min/unit.
• The takt-time and the cycle times (Table 1) of the individual workstations have to be compared (Figure 3).
Cycle times of the individual workstations have to be below the takt-time, otherwise the expected number of final
products required by the customers is not fulfilled. If the cycle time is longer than the takt-time, there will be a bottleneck
in a manufacturing process. The processes that take less time than the takt-time are also problematic, because they result in
unutilised resources (machine, human, etc.).
Figure 3 shows that the activity at workstation 9 is a critical bottleneck because if it takes much longer than takt-time, it
interrupts the continuous value stream and leads to a higher amount of WIP. Shorter cycle times of workstations 3, 4, 7, 8
and 10 result in unutilised resources which can also be improved.
TT
NOp,Ws = (3)
Ttakt
where TT is the sum of the cycle times of all of the individual workstations, means the total time consumption to produce
one final product (min).
In our case study, the total time consumption is 60.7 min, so the ideal theoretical number of the operators and worksta-
tions is 10.8 pieces based on Equation (3). Unfortunately, in practice, the relocation of the workloads is not possible in case
of all of workstations or operations. In the investigated manufacturing process, only the reorganisation of the workloads of
workstations 2–4 and workstations 7–10 was possible.
In the original manufacturing process, the workstation 9 was the bottleneck (bold value in Table 2).
After balancing workstation 4 was eliminated by reallocating its task to workstations 2 and 3. Workstation 7 was also
eliminated by reallocating its task to workstations 8, the subprocesses of workstation 8 was allocated to workstation 9.
Subprocesses of workstation 9 was reallocated to workstation 10. Due to the reconfiguration of the cycle time of workstation
9 also was reduced, so this earlier bottleneck was eliminated. The results of the Line balance can be seen in Table 2 and in
Figure 4.
It can be concluded that the total workload of the total manufacturing process was achieved in the original state by
14 workstations and 14 operators, while after Line balancing (after reallocating the workloads) it could be carried out by
12 workstations and 12 operators. The balanced process provides higher utilisation of both the workstations and human
resources.
Table 2. Comparison of the original cycle times and the newly balanced cycle times.
Workstations 1 2 3 4 5 6 7 8 9 10 11 12 13 14 1–14
Original cycle times (before) (min) 4.6 3.9 3.4 3.5 5.1 4.7 3.2 3.4 6.1 3.4 5.2 4.1 5.1 5.0 60.7
Newly balanced cycle times (after) (min) 4.6 5.4 5.4 0 5.1 4.7 0 5.4 5.4 5.3 5.2 4.1 5.1 5.0 60.7
Figure 4. Comparison of the original cycle times and the newly balanced cycle times.
12 G. Kovács
4.2.5. Pull method, just in time method, Kanban method and supermarket method
In the case study the Pull Method, the Just In Time Method, the Kanban Method and the Supermarket Method were also
implemented simultaneously. Since these methods have logical, thematic and causal relations, they are discussed in this
sub-section together.
Pull based production starts only after receiving a specific customer’s demands. Therefore, Pull philosophy produces
only the necessary amount of final products according to real customers’ demands. The company produces exactly what
the customers want, in the form and at the exact time they want it, free of defects. The Lean philosophy is based on Pull
production philosophy; this is the reason why the Pull method is also an important Lean tool.
JIT is a production and inventory strategy. Applying JIT leads to improvement in the return on investment of the
company by reducing WIP inventory and lead times and improving efficiency. The JIT manufacturing system supports
the operation of the Pull principle; each manufacturing process produces only what the next process in the sequence is
calling for (pull). In our case study, the JIT principle was established by the implementation of the Kanban system.
The Kanban method is a special visualised form of the JIT conception. The manufacturing process is driven by signals
which are the Kanban cards, that inform the production processes about the demands of the next process. The cards indi-
cate the standard quantity of production, maintain the Pull production principle, and visualise the workflow. The aim of
the Kanban technique is to establish a Pull type production and inventory strategy and to eliminate labour and inventory
wastes through the production process and to thus achieve better performance. In our project the Kanban technique was
implemented, the component supply of the production lines was scheduled and achieved by a milk-run train in the plant.
The milk-run stops were removed and located according to the newly improved value-stream-oriented layout (Figure 5).
The application of Supermarkets reduces component shortages at the production line, reduces inventory of components
in the plant, and means faster delivery of the components to the production line. In the supermarket the frequently used
materials (those that turn faster than the average materials) are stored close to the production line. When the components
are removed from the supermarket, a signal (like a Kanban card) is taken by the material handler to retrieve the missing
components. In our improvement project, two supermarkets were located on the shop floor close to the supplying process
(Figure 5).
Since the number of possible alternative layouts is huge, the number of possible alternatives had to be reduced tak-
ing into consideration (1) design aims, (2) design constraints and limitations, (3) management’s demands, (4) practical
applicability and (5) designer experience. Finally, the ideal layout (best solution) had to be selected based on the objective
function.
where qij is the material flow between the workstations (UL – unit load which can be a box, pallet, etc.); lij is the distance
between the workstations on the shop floor (m); n is the number of workstations on the shop floor.
In case of the original layout the quantity of the material flow and the distances between workstations are the following:
⎡ ⎤
0 5 0 0 1 5 0 0 0 0 0 0 0 0
⎢0 0 5 0 0 0 0 0 0 0 0 0 0 0⎥
⎢ ⎥
⎢0 0 0 5 0 0 0 0 0 0 0 0 0 0⎥
⎢ ⎥
⎢0 0 0 0 5 0 0 0 0 0 0 0 0 0⎥
⎢ ⎥
⎢0 0 0 0 0 6 0 0 0 0 0 0 0 0⎥
⎢ ⎥
⎢0 0 0 0 0 0 0 0 0 0 0 11 0 0⎥
⎢ ⎥
⎢0 0 0 0 0 0 0 4 0 0 0 0 0 0⎥
QOrig = ⎢⎢ ⎥ [UL]
⎢0 0 0 0 0 0 0 0 4 0 0 0 0 0⎥⎥
⎢0 0 0 0 0 0 0 0 0 4 0 0 0 0⎥
⎢ ⎥
⎢0 0 0 0 0 0 0 0 0 0 4 0 0 0⎥
⎢ ⎥
⎢0 0 0 0 0 0 0 0 0 0 0 4 0 0⎥
⎢ ⎥
⎢0 0 0 0 0 0 0 0 0 0 0 0 15 0 ⎥
⎢ ⎥
⎣0 0 0 0 0 0 0 0 0 0 0 0 0 15⎦
0 0 0 0 0 0 0 0 0 0 0 0 0 0
⎡ ⎤
0 3.5 6 9.5 7 4 18 14.5 13 11.5 5.5 9 12.5 15
⎢ 3.5 0 2.5 6 6.5 7.5 14.5 11 9.5 8 9 12.5 16 18.5⎥
⎢ ⎥
⎢ 6 2.5 0 3.5 9 10 12 8.5 8 9.5 11.5 15 18.5 21 ⎥
⎢ ⎥
⎢ 9.5 6 3.5 0 5.5 9.5 8.5 5 4.5 6 8 11.5 15 17.5⎥
⎢ ⎥
⎢ 7 6.5 9 5.5 0 7 11 7.5 6 4.5 3.5 8 11.5 12 ⎥
⎢ ⎥
⎢ 4 7.5 10 9.5 7 0 18 14.5 13 11.5 3.5 5 8.5 11 ⎥
⎢ ⎥
⎢ 18 14.5 12 8.5 11 18 0 3.5 5 6.5 14.5 19 22.5 20 ⎥
LOrig =⎢
⎢14.5 11
⎥ [m]
⎢ 8.5 5 7.5 14.5 3.5 0 1.5 3 11 15.5 19 16.5⎥⎥
⎢ 13 9.5 8 4.5 6 13 5 1.5 0 1.5 9.5 14 17.5 15 ⎥
⎢ ⎥
⎢11.5 8 9.5 6 4.5 11.5 6.5 3 1.5 0 8 12.5 16 13.5⎥
⎢ ⎥
⎢ 5.5 9 11.5 8 3.5 3.5 14.5 11 9.5 8 0 4.5 8 9.5 ⎥
⎢ ⎥
⎢ 9 12.5 15 11.5 8 5 19 15.5 14 12.5 4.5 0 3.5 6 ⎥
⎢ ⎥
⎣12.5 16 18.5 15 11.5 8.5 22.5 19 17.5 16 8 3.5 0 2.5 ⎦
15 18.5 21 17.5 12 11 20 16.5 15 13.5 9.5 6 2.5 0
After the process improvement the quantity of the material flow and the distances between workstations are the following:
⎡ ⎤
0 5 0 1 5 0 0 0 0 0 0 0
⎢0 0 5 0 0 0 0 0 0 0 0 0 ⎥
⎢ ⎥
⎢0 0 0 5 0 0 0 0 0 0 0 0 ⎥
⎢ ⎥
⎢0 0 0 0 6 0 0 0 0 0 0 0 ⎥
⎢ ⎥
⎢0 0 0 0 0 0 0 0 0 11 0 0 ⎥
⎢ ⎥
⎢0 0 0 0 0 0 4 0 0 0 0 0 ⎥
QNew = ⎢ ⎢ ⎥ [UL]
⎥
⎢0 0 0 0 0 0 0 4 0 0 0 0 ⎥
⎢0 0 0 0 0 0 0 0 4 0 0 0 ⎥
⎢ ⎥
⎢0 0 0 0 0 0 0 0 0 4 0 0 ⎥
⎢ ⎥
⎢0 0 0 0 0 0 0 0 0 0 15 0 ⎥
⎢ ⎥
⎣0 0 0 0 0 0 0 0 0 0 0 15⎦
0 0 0 0 0 0 0 0 0 0 0 0
16 G. Kovács
⎡ ⎤
0 3.5 7.5 7 4 13.5 12 10.5 7.5 10.5 10 13
⎢ 3.5 0 4 6.5 7.5 10 8.5 7 10 14 13.5 10.5⎥
⎢ ⎥
⎢ 7.5 4 0 6.5 7.5 6 5.5 7 10 14 13.5 10.5⎥
⎢ ⎥
⎢ 7 6.5 6.5 0 7 6.5 5 3.5 3.5 7.5 7 6 ⎥
⎢ ⎥
⎢ 4 7.5 7.5 7 0 13.5 12 10.5 7.5 6.5 10 13 ⎥
⎢ ⎥
⎢13.5 10 6 6.5 13.5 0 1.5 3 6 10 9.5 6.5 ⎥
LNew =⎢
⎢ 12
⎥ [m]
⎢ 8.5 5.5 5 12 1.5 0 1.5 4.5 8.5 8 5 ⎥⎥
⎢10.5 7 7 3.5 10.5 3 1.5 0 3 7 6.5 3.5 ⎥
⎢ ⎥
⎢ 7.5 10 10 3.5 7.5 6 4.5 3 0 4 3.5 5.5 ⎥
⎢ ⎥
⎢10.5 14 14 7.5 6.5 10 8.5 7 4 0 3.5 6.5 ⎥
⎢ ⎥
⎣ 10 13.5 13.5 7 10 9.5 8 6.5 3.5 3.5 0 3 ⎦
13 10.5 10.5 6 13 6.5 5 3.5 5.5 6.5 3 0
The material workflow can be calculated by Equation (1).
Total material workflow in case of the original layout is:
where EMWF is the material workflow; cmh is the specific material handling cost (Euro/UL. m).
The material handling cost after the Lean process improvement was reduced significantly.
• Labour cost of operators
Labour cost is proportional to the number of operators. The reduction of number of operators resulted the saving of
labour cost. The labour cost can be calculated by
CL = NOp · cL (5)
where NOp is the number of operators (person); cL is the specific labour cost (Euro/person).
Workstations 1, 5 and 6 of the original layout are located in a fixed position, but all of the other workstations were arbitrarily
moveable on the shop floor.
The rearrangement of the fixed positioned workstations would have been very costly and would have required a long
time and too much downtime; therefore – at my and management’s suggestions – these 3 workstations were not moved. But
after balancing, workstation 4 was eliminated by reallocating its task to workstations 2 and 3. Consequently, the number of
workstations and operators was reduced by 1.
(2) Second phase: Workstations 7–11. on original layout (Figure 2). Workstations 6–9. on the new ideal layout after
process improvement (Figure 5).
Workstation 7 was also eliminated by reallocating its task to workstation 8. Consequently, the number of workstations and
operators was further reduced by 1.
The subprocesses of workstation 8 were allocated to workstation 9. The subprocesses of workstation 9 were reallocated
to workstation 10. Due to the reconfiguration the cycle time of workstation 9 was reduced, so workstation 9 – which was
earlier a bottleneck – was eliminated.
(3) Third phase: Workstations 12–14. on original layout (Figure 2). Workstations 10–12. on the new ideal layout after
process improvement (Figure 5).
The conception of the redesign in my and management’s opinions – was that phase 2 (workstations 6–9 on the new layout)
and phase 3 (workstations 10–12 on the new layout) had to be handled as one logical technological process, due to the
characteristics of the manufacturing activity. It was the main reason that only one U cell was formed instead of two U cells.
Therefore, the linear layout configuration (workstations 7–14 on the original layout) was organised into one U-shaped cell
(workstations 6–12 on the newly improved layout).
Further reduction of the number of workstations and operators was not possible in the case of workstations 6–12, because
the subprocesses of the assembling activities cannot be allocated to other workstations due to technological reasons, and
also because of the results of Takt-time analysis, since the calculated takt-time (Equation (2)) is 5.62 min/unit (Section
4.2.2). Based on Equation (3) the number of workstations and operators cannot be reduced on workstations 6–12 on the new
improved layout, because 8 operators are needed in the U cell. (Consequently, in the case of the implementation of two U
cells the number of workers could not be reduced, either.)
Two shifts were running at the company, so there was no downtime, because the three-phase rearrangement was carried
out on workdays outside working hours and at weekends.
The total cost of the full implementation – including the costs of the rearrangement and the implementation of the 13
Lean tools – was declared as a business secret by the company. The total time of the full implementation – including times
of the rearrangement and the implementation of the 13 Lean tools – was 11 weeks.
The results of the comparison of the original and the improved balanced layout can be seen in Table 3. One of the most
important results was that after the reorganisation of the layout 56 m2 of free floor space was gained in the manufacturing
plant. This area was used for further value-added activities (establishment of new workstations). Another important result
of the process improvement was that the total workload of the total manufacturing process, which was achieved in the
original state by 14 workstations and 14 operators, required only 12 workstations and 12 operators after Line balancing
(after reallocating the workloads). The freed-up workers were employed at the new workstations established in the new free
area.
5.2. Results of comparison of the original and the improved balanced layout
The original layout and the newly improved balanced layout were compared based on 15 indicators including 10 quantitative
and 5 qualitative indicators (in first column of Table 3). The results of the process improvement are that all of the 15
indicators were significantly improved.
1. Longest cycle time (Reduction by 11.47%)
The activity at workstation 9 was a critical bottleneck in the original production process, because its cycle time (6.1 min)
took much longer than takt-time (5.62 min). After Line balancing the longest cycle time became 5.4 min, which defines the
throughput of the whole manufacturing process (Table 2; Figure 4).
2. Productivity improvement (Increase by 13.7%)
Before Line balancing workstation 9 was the bottleneck; its cycle time was 6.1 min. In the new improved process, the longest
cycle time became 5.4 min. Therefore, before Line balancing the productivity of the production line was 73 (units/shift),
while after it the productivity became 83 (units/shift).
18 G. Kovács
(1) The aims of both methods are taken into consideration in the new combined method: on the one hand to focus on
the elimination of waste or non-value-added activities, on the other hand to achieve the optimal arrangement of
facilities and optimal material flow on the shop floor.
(2) FLD provides the possibility of defining the optimal arrangement of the workstations on a manufacturing site; in
addition, the number of workstations can even be also reduced by the application of Lean methods (Takt-time
analysis and Line Balancing methods).
(3) By the application of the combined method – due to the usage of the FLD method – the total travel distance of
materials and total material workflow can also be minimised, leading to the minimisation of the material handling
cost and minimisation of the space used for assembly. Therefore, these four KPIs can also be improved by the
combined method.
(4) In the elaborated combined method – due to the application of the Lean methods – not only the quantitative indi-
cators, but at the same time the qualitative indicators (e.g. quality of the processes and final products, workplace
ergonomics, etc.) can also be improved.
(5) In the new combined method by the application of Lean methods (e.g. Cellular design, Supermarket, Kanban, etc.)
the huge number of possible layout alternatives can also be reduced.
This study not only discusses the methodology, procedure and practical steps of the elaborated combined method, but
also introduces a real case study to confirm that the new combined method can be applied effectively in practice for an
increase in productivity and a reduction in costs in manufacturing processes.
In the case study a process improvement of a manufacturing plant was carried out in order to show how significant
efficiency improvement and cost saving can be achieved by application of 13 Lean methods and – due to the usage of
FLD method – the total material workflow, the travel distance of materials, the material handling cost and the space used
for assembly also could be reduced. From the case study it can be concluded, that – by the application of the new com-
bined method – significant improvement of efficiency and cost reduction can be achieved and all of the 15 indicators were
improved (Table 3).
The main significant added value and novelty of the study is that I elaborated the methodology and the procedure of a
new combined efficiency improvement method, and at the same time the efficiency of the elaborated combined method is
confirmed by a real industrial project. This elaborated combined method – due to the utilisation of the different advantageous
elements of the Lean and FLD methods – results in even more significant efficiency improvement, operational cost reduction
and the improvement of more KPIs.
In the last 7 months, the results of the process improvement were continuously monitored. The targeted aims were
successfully fulfilled, and company’s management is totally satisfied with the results of the R&D project.
The aims of my future research are the following: The fifth principle of the Lean philosophy is ‘Perfection – Continuous
improvement’. It means that there is no perfect process, every process can be improved. In this spirit, manufacturing pro-
cesses can also be improved in the future by the application of the same or further Lean methods. Furthermore, due to the
higher utilisation of the different advantages of the Lean and FLD methods even more significant efficiency improvement
can be achieved.
In this article, the original and the newly improved layouts were compared based on the most important KPIs (including
also material handling and labour costs), and the process improvement was confirmed. In my future publications – in addition
to the numerical comparison of the selected KPIs – I will make an in-depth cost/benefit analysis during the selection of the
ideal layout alternative.
Disclosure statement
No potential conflict of interest was reported by the author.
20 G. Kovács
References
Alemu, M. B., W. Torgeir, and H. Petri. 2014. “Approaching Lean Product Development Using System Dynamics: Investigating Front-
Load Effects.” Advanced Manufacturing 2: 130–140.
Anjos, M. F., and M. V. C. Vieira. 2017. “Mathematical Optimization Approaches for Facility Layout Problems: The State-of-the-art and
Future Research Directions.” European Journal of Operational Research 261: 1–16.
Bai, C., A. Satir, and J. Sarkis. 2019. “Investing in Lean Manufacturing Practices: an Environmental and Operational Perspective.”
International Journal of Production Research 57 (4): 1037–1051.
Beemsterboer, B., M. Land, and R. Teunter. 2017. “Flexible lot Sizing in Hybrid Make-to-Order/Make-to-Stock Production Planning.”
European Journal of Operational Research 260: 1014–1023.
Braglia, M., M. Frosolini, and M. Gallo. 2017. “SMED Enhanced with 5-Whys Analysis to Improve set-up Reduction Programs: The
SWAN Approach.” International Journal of Advanced Manufacturing Technology 90: 1845–1855.
Braglia, M., M. Frosolini, M. Gallo, and L. Marrazzini. 2019. “Lean Manufacturing Tool in Engineer-to-Order Environment: Project Cost
Deployment.” International Journal of Production Research 57 (6): 1825–1839.
Chay, T. F., Y. C. Xu, A. Tiwari, and F. Chay. 2015. “Towards Lean Transformation: The Analysis of Lean Implementation Frameworks.”
Journal of Manufacturing Technology Management 26 (7): 1031–1052.
Chen, C., and L. K. Tiong. 2019. “Using Queuing Theory and Simulated Annealing to Design the Facility Layout in an AGV-Based
Modular Manufacturing System.” International Journal of Production Research 57 (17): 5538–5555.
Chiarini, A. 2013. Lean Organization: From the Tools of the Toyota Production System, to Lean Office, Perspectives in Business Culture
3. Springer-Verlag.
Chiarini, A., P. Found, and N. Rich, eds. 2016. Understanding the Lean Enterprise - Strategies, Methodologies, and Principles for a More
Responsive Organization. New York: Springer.
Dennis, P. 2015. Lean Production Simplified. New York: CRC Press.
Dolgui, A., N. Guschinsky, and G. Levin. 2009. “A Design of DSS for Mass Production Machining Systems.” Bulletin of the Polish
Academy of Sciences: Technical Sciences 57 (3): 265–271.
Erlach, K. 2013. Value Stream Design: The Way Towards a Lean Factory. Berlin: Springer-Verlag.
García-Alcaraz, J. L., and A. A. Maldonado-Macías. 2016. Just-In-Time Elements and Benefits. Springer.
Heragu, S. S. 2016. Facilities Design. CRC Press.
Hosseini-Nasab, H., S. Fereidouni, S. M. T. F. Ghomi, and M. B. Fakhrzad. 2018. “Classification of Facility Layout Problems: A Review
Study.” International Journal of Advanced Manufacturing Technology 94: 957–977.
Huawei, C., L. Guoping, T. Haining, W. Aimin, and N. Ruxin. 2016. “Layout Adjustment of Cellular Production Line Based on Material
Logistic Analysis.” The International Journal of Advanced Manufacturing Technology 87: 1409–1420.
Kamble, S., A. Gunasekaran, and N. C. Dhone. 2019. “Industry 4.0 and Lean Manufacturing Practices for Sustain-
able Organisational Performance in Indian Manufacturing Companies.” International Journal of Production Research,
doi:10.1080/00207543.2019.1630772.
Keller, B., and U. Buscher. 2015. “Single row Layout Models.” European Journal of Operational Research 245: 629–644.
Kot, S. 2018. “Sustainable Supply Chain Management in Small and Medium Enterprises.” Sustainability 1143: 1–19.
Kovács, Gy. 2017. Changes in Production Philosophies – Efficiency Improvement of Production and Logistics Processes. Hungary:
University Press: University of Miskolc.
Naik, B. S., and S. Kallurkar. 2016. “A Literature Review on Efficient Plant Layout Design.” International Journal of Industrial
Engineering Research and Development 7 (2): 43–51.
Nallusamy, S., and V. Saravanan. 2016. “Enhancement of Overall Output in a Small Scale Industry Through VSM, Line Balancing and
Work Standardization.” International Journal of Engineering Research in Africa 26: 176–183.
Ojaghi, Y., A. Khademi, N. M. Yusof, N. G. Renani, and S. A. Helmi. 2015. “Production Layout Optimization for Small and Medium
Scale Food Industry.” Procedia CIRP 26: 247–251.
Oliveira, R. I., S. O. Sousa, and F. C. Campos. 2019. “Lean Manufacturing Implementation: Bibliometric Analysis 2007–2018.” The
International Journal of Advanced Manufacturing Technology 101 (1–4): 979–988.
Orr, L. M., and D. J. Orr. 2014. Eliminating Waste in Business, Run Lean, Boost Profitability. USA: Apress.
Pearce, A., D. Pons, and T. Neitzert. 2018. “Implementing Lean: Outcomes From SME Case Studies.” Operations Research Perspectives
5: 94–104.
Peetu, P., J. Koshy, and C. A. Biju. 2013. “Conversion of Regular Assembly Line Into Cellular Manufacturing Layout.” International
Journal of Engineering and Innovative Technology 7: 1–9.
Pourvaziri, H., and H. Pierreval. 2017. “Dynamic Facility Layout Problem Based on Open Queuing Network Theory.” European Journal
of Operational Research 259: 538–553.
Riyad, H., R. Kamruzzaman, and T. Subrata. 2014. “Increasing Productivity Through Facility Layout Improvement Using Systematic
Layout Planning Pattern Theory.” Global Journal of Researches in Engineering 14 (7): 1–7.
Shang, G., and P. L. Sui. 2014. Lean Construction Management - The Toyota Way. Singapore: Springer.
Shingo, S. 2017. Fundamental Principles of Lean Manufacturing. Bellingham: Productivity Press.
Sigma Savvy. 2019. Accessed January 7. http://www.sigmasavvy.com/5-lean-principles-everything-you-need-to-know/.
Tortorella, G. L., D. Fettermann, P. A. C. Miguel, and R. Sawhney. 2019. “Learning Organisation and Lean Production: an Empirical
Research on Their Relationship.” International Journal of Production Research, doi:10.1080/00207543.2019.1633028.
International Journal of Production Research 21
Tortorella, G. L., L. G. L. Vergara, and E. P. Ferreira. 2017. “Lean Manufacturing Implementation: an Assessment Method with Regards
to Sociotechnical and Ergonomics Practices Adoption.” International Journal of Advanced Manufacturing Technology 89 (9-12):
3407–3418.
Tubaileh, A., and J. Siam. 2017. “Single and Multi-Row Layout Design for Flexible Manufacturing Systems.” International Journal of
Computer Integrated Manufacturing 30 (12): 1316–1330.
Uriarte, A. G., H. C. N. Amos, and M. U. Moris. 2020. “Bringing Together Lean and Simulation: a Comprehensive Review.” International
Journal of Production Research 58 (1): 87–117.
Vitayasak, S., and P. Pongcharoen. 2015. “Re-layout and Robust Machine Layout Design Under Stochastic Demand.” Applied Mechanics
and Materials 789-790: 1252–1257.
Yadav, O. P., B. P. Nepal, M. M. Rahaman, and V. Lal. 2017. “Lean Implementation and Organizational Transformation: A Literature
Review.” EMJ – Engineering Management Journal 29 (1): 2–16.
Yildirim, C., B. S. Oflaç, and O. Yurt. 2018. “The Doer Effect of Failure and Recovery in Multi-Agent Cases: Service Supply Chain
Perspective.” Journal of Service Theory and Practice 28 (3): 274–297.
Yu, K., J. Cadeaux, and H. Song. 2017. “Flexibility and Quality in Logistics and Relationships.” Industrial Marketing Management 62:
211–225.
Zhou, B. 2016. “Lean Principles, Practices, and Impacts: a Study on Small and Medium-Sized Enterprises (SMEs).” Annals of Operations
Research 241: 457–474.