Professional Documents
Culture Documents
Specifications
______________________________________________________________________________
PART 1 - GENERAL
1. Submittals:
a. Shop Drawings
b. Material List
c. Product and Equipment Schedule
d. Manufacturer's Technical Literature
e. Samples
f. Material Take-off
g. Purchase Orders
h. Operation and Maintenance Instruction
i. As-built Drawings
j. Construction Schedules
k. Progress Reports
2. Substitution.
3. Guarantees.
1.02 APPROVALS
A. All approvals shall be made by The Engineer or other persons or firms appointed by The
Employer for this purpose.
A. General
1. Within thirty (30) days of date of signing of the Contract, the Contractor shall
submit to the Engineer a list and submittal schedule of all shop drawings,
product data, technical literature and samples required by the Contract. List all
items by Specification Sections.
2. All submittals shall be in English and be clearly identified with project name
and location and manufacturer's name. All submittals shall be received and
approved by the Contractor prior to submission to the Engineer. The Contractor
shall indicate his review and approval by stamping the submittals accordingly.
3. Required Submittals:
As soon as practicable, and in ample time to avoid delay of the work, submit the
shop drawings, catalog information, and other required data to the Engineer for
review. Submit shop drawings, catalog information, etc., assembled in a neat
package and submit all together at one time. Partial submittals will not be
considered.
August 2011 Submittals, Substitutions, Schedules and Guarantees
473735480.doc-1
Mebex Consultants Rania Governmental Hospital
Specifications
______________________________________________________________________________
4. The Contractor is solely responsible for errors in the submittals, and for
accuracy of quantities and dimensions shown on submittals.
5. The Contractor shall review submittals for compliance with the Contract
Documents.
7. Date each submittal and identify with the project name and the specification
section covering the submittal. Use numbered transmittal forms for ease of
record keeping, and do not group items covered by more than one section on the
same transmittal.
8. Submittals which have not been reviewed by the Engineer, or which have been
rejected by THE ENGINEER, shall not be used for ordering, fabrication or work
at the Work Site.
9. Schedule submittals to allow adequate time for the Engineer's review and for
resubmitted if required. In the event a substitution proposed by the Contractor is
rejected, the Engineer shall require the Contractor to airfreight the originally
specified item in order to maintain the schedule.
D. After review, the Engineer shall return the shop drawings to the Contractor, who shall:
2. Provide copies of the sepia, which has been reviewed by the Engineer for:
E. The Work Site copy shall be made readily available for the Engineer 's review upon
request.
473735480.doc-2
Mebex Consultants Rania Governmental Hospital
Specifications
______________________________________________________________________________
F. Materials lists, product and equipment schedules and manufacturer's technical literature:
1.05 SAMPLES
A. Provide samples of the exact item required by the drawings and specifications.
E. The Contractor shall maintain one each approved sample at the jobsite.
A. The Contractor shall submit spare parts list in accordance with the specification.
B. Complete data in manual form. Data shall be collated, indexed and bound in durable
covers and identifying on the cover:
Include the name, address and telephone number of the manufacturer and local
distributor with the information on each component, sufficient for the
Employer's future purchasing.
C. Include only those catalogs and brochures dealing with the products and equipment used
in this project. Remove pages of a purely advertising nature, and pages dealing with
items and models not used in this project. Where more than one item or model is listed
on a page, carefully identify the exact item or model used.
473735480.doc-3
Mebex Consultants Rania Governmental Hospital
Specifications
______________________________________________________________________________
D. Operating Instructions
E. Submit 3 copies minimum to the Engineer for review and distribution. Supply additional
copies for review if record copies are desired by the Contractor and his Sub-Contractor.
A. The Contractor shall maintain one complete set of drawings at the site on which, as the
work progresses, the Contractor shall record, using red color markings, the following
information relative to work included in this Contract.
2. Changes made in the structural phases of the work above and below ground
required because of modifications or Change Orders.
3. Exact location and elevation of all underground piping and conduit and the
position of all fittings.
B. On completion of the job, the Contractor shall deliver one print of such corrected
drawings to the Engineer. The Contractor shall make such additional corrections as the
Engineer may require and shall then deliver the corrected prints to the Engineer.
C. The Contractor is cautioned that these as-built drawings are a specific requirement and
that the Contract will not be considered complete until they have been submitted in an
acceptable form.
1.09 SUBSTITUTIONS
A. Wherever catalog numbers and specific brands or trade names followed by the designated
material, product, thing or service mentioned in these specifications, they are used to
establish the standards of quality and utility required.
B. Substitutions which are equal in quality and utility to those specified will be approved,
subject to the following provisions: all substitutions must be approved by The Engineer
in writing.
For this purpose, the Contractor shall submit to The Engineer, within 30 calendar days
after the effective date of the Contract, four (4) copies of a typewritten list containing:
473735480.doc-4
Mebex Consultants Rania Governmental Hospital
Specifications
______________________________________________________________________________
Such approval shall not relieve the Contractor from complying with the requirements of
the Drawings and specifications and the Contractor shall be responsible at his own
expense for any changes resulting from his proposed substitutions which affect other
parts of this own work or the work of other Contractors.
2. List all items to be used, including specified items and proposed substitutions.
D. Alternate items installed without the Engineer 's approval shall be replaced with the
specified material at the Contractor's expense. The Contractor assumes full responsibility
that alternate items or procedures shall meet the job requirements and is responsible for
cost of redesign and of modifications to this and other parties to the work caused by
alternate items furnished under work of this Section. No more than one proposed
alternate will be considered for each item.
473735480.doc-5